JPH0532582U - Frame scaffolding building frame - Google Patents

Frame scaffolding building frame

Info

Publication number
JPH0532582U
JPH0532582U JP7848891U JP7848891U JPH0532582U JP H0532582 U JPH0532582 U JP H0532582U JP 7848891 U JP7848891 U JP 7848891U JP 7848891 U JP7848891 U JP 7848891U JP H0532582 U JPH0532582 U JP H0532582U
Authority
JP
Japan
Prior art keywords
frame
building
scaffolding
outer pipe
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7848891U
Other languages
Japanese (ja)
Inventor
和則 岡田
Original Assignee
株式会社竹中工務店
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社竹中工務店 filed Critical 株式会社竹中工務店
Priority to JP7848891U priority Critical patent/JPH0532582U/en
Publication of JPH0532582U publication Critical patent/JPH0532582U/en
Pending legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

(57)【要約】 (修正有) 【目的】 本考案は、枠組足場を形成する建枠に関し、
現場の状況に応じて枠組足場を所望の高さに組み立てら
れるように、高さ調節を可能にした建枠を提供すること
を目的とする。 【構成】 横方向に所定間隔を置いて多数配置し、それ
らの上又は間に足場板を架け渡し、且つ側部の各支柱1
1間に筋かいを連結して枠組足場を形成する建枠9に於
て、上記支柱11を、外管13と、当該外管13の内径
よりも小径で外管13内から伸縮自在な内管15とで構
成すると共に、内管15を外管13に固定する固定手段
を備えたものである。
(57) [Summary] (Modified) [Purpose] The present invention relates to a building frame forming a frame scaffold,
It is an object of the present invention to provide a building frame whose height can be adjusted so that the frame scaffold can be assembled at a desired height according to the situation of the site. [Structure] A large number of laterally-arranged columns are arranged, a scaffolding board is bridged over or between them, and each side pillar 1 is provided.
In the building frame 9 which connects the braces between 1 to form the frame scaffold, the pillar 11 is an outer tube 13 and an inner tube which is smaller in diameter than the inner diameter of the outer tube 13 and is expandable from the outer tube 13. The tube 15 and the tube 15 are provided with a fixing means for fixing the inner tube 15 to the outer tube 13.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、枠組足場を形成する建枠に係り、詳しくは、足場を所望の高さに組 み立てることができるように高さ調節を可能にした伸縮自在な建枠に関する。 The present invention relates to a building frame forming a framed scaffold, and more particularly, to a retractable building frame whose height can be adjusted so that the scaffolding can be assembled at a desired height.

【0002】[0002]

【従来の技術】[Prior Art]

従来、建築物の補修や塗装等の作業は、建築物の外周や室内に設けた枠組足場 を利用して行われている。 Conventionally, work such as repair and painting of buildings has been carried out using frame scaffolds provided on the outer periphery of the building or inside the building.

【0003】 枠組足場は、図4の如く予め工場に於て足場用鋼管を一定の枠の単位に加工し た建枠1を、図5に示すように横方向に所定間隔を置いて多数配置し、対向配置 された建枠1の上や建枠1間に、作業員が作業するための足場板3が略水平に架 け渡されている。そして、対向配置された建枠1の側部同士に、足場を剛構造と する筋かい5がX字状に連結された構造となっている。As for the frame scaffolding, as shown in FIG. 4, a large number of building frames 1 in which steel pipes for scaffolding are processed in advance in a factory into fixed frame units are arranged at predetermined intervals in the lateral direction as shown in FIG. However, a scaffolding plate 3 for workers to work on is substantially horizontally bridged between the building frames 1 arranged opposite to each other and between the building frames 1. Then, the braces 5 having a rigid structure for the scaffold are connected in an X-shape to the side portions of the building frames 1 arranged so as to face each other.

【0004】 又、図示しないが、建築物の高い場所の作業を行う場合には、建枠の上部に更 に建枠を継ぎ足して、枠組足場を上方まで延設している。 而して、以上のように構成された枠組足場7では、足場板3を利用して種々の 作業を容易に行うことができることとなる。Further, although not shown, in the case of performing work in a high place of a building, a building frame is further added to the upper part of the building frame to extend the frame scaffolding upward. Thus, in the frame scaffolding 7 configured as described above, various works can be easily performed by using the scaffolding plate 3.

【0005】[0005]

【考案が解決しようとする課題】[Problems to be solved by the device]

然し乍ら、図4の如き従来の建枠1は高さが調節できないため、現場の状況に 応じた高さに枠組足場を組み立てることができない欠点が指摘されていた。 However, since the height of the conventional building frame 1 as shown in FIG. 4 cannot be adjusted, it has been pointed out that the frame scaffolding cannot be assembled at a height according to the situation of the site.

【0006】 又、従来、高さの異なる建枠が数種類製造されているが、これら数種の建枠を 予め現場に搬入しておくにはそれらの保管場所を確保しなければならず、而も、 これらの建枠が時として作業の邪魔になってしまう欠点もあった。Further, conventionally, several types of building frames having different heights are manufactured, but in order to bring these several types of building frames to the site in advance, it is necessary to secure a storage place for them. However, there was a drawback that these building frames sometimes hinder the work.

【0007】 そして、状況に応じてこれらの建枠を適宜選択し、それらの保管場所から枠組 足場の設置場所に建枠を移動する作業も非常に手間の掛かるものであった。 本考案は斯かる実情に鑑み案出されたもので、現場の状況に応じて枠組足場を 所望の高さに組み立てられるように、高さ調節を可能にした枠組足場の建枠を提 供することを目的とする。[0007] The work of appropriately selecting these building frames according to the situation and moving the building frames from their storage location to the installation location of the framework scaffolding is also very troublesome. The present invention has been devised in view of such circumstances, and provides a construction frame of a frame scaffold capable of adjusting the height so that the frame scaffold can be assembled at a desired height according to the situation of the site. With the goal.

【0008】[0008]

【課題を解決するための手段】[Means for Solving the Problems]

斯かる目的を達成するため、本考案は、横方向に所定間隔を置いて多数配置し 、それらの上又は間に足場板を架け渡し、且つ側部の各支柱間に筋かいを連結し て枠組足場を形成する建枠に於て、上記支柱を、外管と、当該外管の内径よりも 小径で外管内から伸縮自在な内管とで構成すると共に、内管を外管に固定する固 定手段を備えたものである。 In order to achieve such an object, the present invention provides a large number of laterally spaced scaffolds, bridges scaffolding boards on or between them, and connects braces between each side pillar. In a building frame that forms a frame scaffold, the pillar is composed of an outer pipe and an inner pipe that has a diameter smaller than the inner diameter of the outer pipe and is expandable and contractable from inside the outer pipe, and the inner pipe is fixed to the outer pipe. It is equipped with a fixing means.

【0009】[0009]

【作用】[Action]

本考案によれば、各支柱の内管を夫々の外管から伸縮させてこれを各外管に固 定すれば、現場の状況に応じて建枠の高さ調節がなされることとなる。 According to the present invention, the height of the building frame can be adjusted according to the situation of the site by expanding and contracting the inner pipe of each strut from the respective outer pipe and fixing it to each outer pipe.

【0010】[0010]

【実施例】【Example】

以下、本考案の実施例を図面に基づき詳細に説明する。 図1に於て、9は足場用鋼管で製造された本考案の一実施例に係る建枠で、当 該建枠9の2本の支柱11は、夫々、外管13と、外管13の内径よりも小径な 内管15とで構成されており、内管15の下端は外管13内に挿入されている。 Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. In FIG. 1, reference numeral 9 denotes a building frame according to an embodiment of the present invention, which is manufactured from a steel pipe for scaffolding. Two columns 11 of the building frame 9 include an outer pipe 13 and an outer pipe 13, respectively. The inner tube 15 has a diameter smaller than the inner diameter of the inner tube 15, and the lower end of the inner tube 15 is inserted into the outer tube 13.

【0011】 又、両支柱11の内管15の上端には足場板載置管17が架け渡されており、 図2に示すように各内管15を外管13内から上下方向へ伸縮させることによっ て、足場板載置管17の高さが変えられるようになっている。Further, a scaffolding plate mounting pipe 17 is laid over the upper ends of the inner pipes 15 of both columns 11, and each inner pipe 15 is expanded and contracted in the vertical direction from the inside of the outer pipe 13 as shown in FIG. As a result, the height of the scaffolding plate mounting tube 17 can be changed.

【0012】 そして、両内管15と足場板載置管17との間には、足場板載置管17を補強 する略L字状の補強枠19が取り付けられ、又、各外管11の内側にも略L字状 の補強枠21が取り付けられている。A substantially L-shaped reinforcing frame 19 that reinforces the scaffolding plate mounting pipe 17 is attached between both inner pipes 15 and the scaffolding plate mounting pipe 17, and each outer pipe 11 has A substantially L-shaped reinforcing frame 21 is also attached to the inside.

【0013】 又、図3に示すように、上記外管13の上部周壁には、一対のピン挿通孔23 が対向して設けられており、当該ピン挿通孔23に固定支持ピン25が挿入され るようになっている。又、固定支持ピン25の軸部25aには割りピン27が挿 入される割りピン挿通孔29が設けられており、当該割りピン挿通孔29に割り ピン27を挿入することによって、ピン挿通孔23に挿入した固定支持ピン25 の脱落が防止されている。Further, as shown in FIG. 3, a pair of pin insertion holes 23 are provided in the upper peripheral wall of the outer tube 13 so as to face each other, and the fixed support pins 25 are inserted into the pin insertion holes 23. It has become so. Further, the shaft portion 25a of the fixed support pin 25 is provided with a split pin insertion hole 29 into which the split pin 27 is inserted, and by inserting the split pin 27 into the split pin insertion hole 29, the pin insertion hole is formed. The fixed support pin 25 inserted in the 23 is prevented from falling off.

【0014】 一方、上記内管15の周壁にも、固定支持ピン25が挿入可能な複数対のピン 挿通孔31が上下方向に所定間隔を開けて対向して設けられており、図3に示す ように、ピン挿通孔23,31に固定支持ピン25を挿入して、内管15が外管 13に固定されるようになっている。On the other hand, a plurality of pairs of pin insertion holes 31 into which the fixed support pins 25 can be inserted are also provided in the peripheral wall of the inner tube 15 so as to face each other at a predetermined interval in the vertical direction, as shown in FIG. As described above, the inner pipe 15 is fixed to the outer pipe 13 by inserting the fixed support pin 25 into the pin insertion holes 23 and 31.

【0015】 本実施例に係る建枠9はこのように構成されているから、現場で作業を行うに 当たり、各建枠9の支柱11の各内管15を夫々の外管13から伸縮した後、内 管15の所定のピン挿通孔31と外管13のピン挿通孔23を一致させ、内,外 管13,15を固定支持ピン25で固定して建枠9を一定の高さに設定しておけ ばよい。Since the building frame 9 according to the present embodiment is configured in this way, when performing work on site, the inner pipes 15 of the columns 11 of each building frame 9 are expanded and contracted from the respective outer pipes 13. After that, the predetermined pin insertion hole 31 of the inner pipe 15 and the pin insertion hole 23 of the outer pipe 13 are aligned with each other, and the inner and outer pipes 13 and 15 are fixed by the fixed support pins 25 to keep the building frame 9 at a constant height. Just set it.

【0016】 そして、従来と同様、斯かる建枠9を横方向に所定間隔を置いて多数配置し、 対向配置された建枠9の上やその間に、作業員が作業するための足場板を略水平 に架け渡し、又、各建枠9の支柱11同士に、筋かいをX字状に連結すれば、一 定の高さの枠組足場が形成されることとなる。As in the conventional case, a large number of such building frames 9 are laterally arranged at a predetermined interval, and scaffolding boards for workers to work are provided on or between the facing building frames 9. If the braces are connected in an X-shape between the columns 11 of each building frame 9, the frame scaffolds of a certain height will be formed.

【0017】 又、現場の状況に応じて、上記枠組足場よりも例えば高い枠組足場が必要とな る場合には、枠組足場を形成するに当たり、図2の如く建枠9の支柱11の各内 管15を夫々の外管13から伸長させ、そして、図3に示すように、選択した内 管15のピン挿通孔31と外管13のピン挿通孔23とを一致させてこれらに固 定支持ピン25を挿入した後、割りピン27を割りピン挿通孔29に挿入して内 管15を外管13に固定すれば、建枠9の高さ調節が完了する。In addition, depending on the situation of the site, when a frame scaffolding higher than the above frame scaffolding is required, for example, when forming the frame scaffolding, each of the columns 11 of the building frame 9 as shown in FIG. The pipes 15 are extended from the respective outer pipes 13, and as shown in FIG. 3, the pin insertion holes 31 of the selected inner pipes 15 and the pin insertion holes 23 of the outer pipe 13 are aligned and fixedly supported. After inserting the pin 25, the split pin 27 is inserted into the split pin insertion hole 29 to fix the inner pipe 15 to the outer pipe 13, whereby the height adjustment of the building frame 9 is completed.

【0018】 而して、斯様に高さ調節がなされた建枠9を用いて枠組足場を作れば、より高 い枠組足場が形成されることとなる。 このように、本実施例は、建枠9の両支柱11を、外管13と、当該外管13 内から伸縮自在な内管15とで構成すると共に、外管13と内管15とを固定支 持ピン25で固定するようにしたものであるから、現場の状況に応じて建枠9の 高さ調節が可能である。If a frame scaffold is made using the building frame 9 whose height is adjusted in this way, a higher frame scaffold will be formed. As described above, in this embodiment, both columns 11 of the building frame 9 are configured by the outer pipe 13 and the inner pipe 15 that is expandable and contractable from within the outer pipe 13, and the outer pipe 13 and the inner pipe 15 are connected to each other. Since it is fixed by the fixed support pin 25, the height of the building frame 9 can be adjusted according to the situation at the site.

【0019】 従って、本実施例によれば、複数種類の建枠を用いずに枠組足場を所望の高さ に組み立てることができると共に、従来の如く高さの異なる数種類の建枠を現場 に用意しておく必要がなくなり、又、状況に応じて他の高さの建枠をその保管場 所から枠組足場の設置場所に移動する作業等も不要となる等、現場に於ける作業 性が向上できる利点を有する。Therefore, according to this embodiment, the frame scaffolding can be assembled at a desired height without using a plurality of types of building frames, and several types of building frames having different heights can be prepared on the site as in the past. There is no need to keep it in place, and there is no need to move the building frames of other heights from their storage location to the installation location of the frame scaffolding depending on the situation, improving workability on site. It has the advantage that it can.

【0020】 尚、上記実施例では、固定支持ピン25を用いて外管13と内管15を固定し たが、固定手段は上記実施例に限定されるものではなく、その他の手段を用いて もよいことは勿論である。In the above embodiment, the outer pipe 13 and the inner pipe 15 are fixed by using the fixed support pins 25, but the fixing means is not limited to the above embodiment, and other means may be used. Of course, it is also good.

【0021】[0021]

【考案の効果】[Effect of the device]

以上述べたように、本考案に係る建枠によれば、現場の状況に応じてその高さ 調節が可能であるから、複数種類の建枠を用いずに枠組足場を所望の高さに組み 立てることができると共に、従来の如く高さの異なる数種類の建枠を現場に用意 しておく必要がなくなり、又、状況に応じて他の高さの建枠をその保管場所から 枠組足場の設置場所に移動する作業等も不要となる等、現場に於ける作業性が向 上できる利点を有する。 As described above, according to the construction frame of the present invention, the height can be adjusted according to the situation of the site, so that the frame scaffold can be assembled at a desired height without using a plurality of types of construction frames. In addition to being able to stand, it is no longer necessary to prepare several types of building frames with different heights at the site as before, and depending on the situation, building frames of other heights can be installed from the storage location to the frame scaffolding. It also has the advantage of improving workability on site, such as eliminating the need for work to move to a location.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の一実施例に係る建枠の正面図である。FIG. 1 is a front view of a building frame according to an embodiment of the present invention.

【図2】図1に示す建枠の高さ調節の方法を示す正面図
である。
FIG. 2 is a front view showing a method for adjusting the height of the building frame shown in FIG.

【図3】外管と内管の固定手段の拡大断面図である。FIG. 3 is an enlarged cross-sectional view of fixing means for an outer pipe and an inner pipe.

【図4】従来の建枠の正面図である。FIG. 4 is a front view of a conventional building frame.

【図5】図4に示す建枠を用いた従来の枠組足場の斜視
図である。
5 is a perspective view of a conventional framed scaffolding using the building frame shown in FIG.

【符号の説明】[Explanation of symbols]

9 建枠 11 支柱 13 外管 15 内管 17 足場板載置管 23,31 ピン挿通孔 25 固定支持ピン 27 割りピン 9 Building frame 11 Struts 13 Outer pipe 15 Inner pipe 17 Scaffolding plate mounting pipe 23, 31 Pin insertion hole 25 Fixed support pin 27 Split pin

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 横方向に所定間隔を置いて多数配置し、
それらの上又は間に足場板を架け渡し、且つ側部の各支
柱間に筋かいを連結して枠組足場を形成する建枠に於
て、上記支柱を、外管と、当該外管の内径よりも小径で
外管内から伸縮自在な内管とで構成すると共に、内管を
外管に固定する固定手段を備えたことを特徴とする枠組
足場の建枠。
1. A large number are arranged at predetermined intervals in the lateral direction,
In a building frame in which a scaffolding board is bridged over or between them, and braces are connected between each side pillar to form a frame scaffold, the above pillar is used as an outer pipe and an inner diameter of the outer pipe. A construction frame for a scaffolding frame, comprising a fixing means for fixing the inner pipe to the outer pipe, the inner frame having a diameter smaller than that of the inner pipe and capable of expanding and contracting from the outer pipe.
JP7848891U 1991-09-27 1991-09-27 Frame scaffolding building frame Pending JPH0532582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7848891U JPH0532582U (en) 1991-09-27 1991-09-27 Frame scaffolding building frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7848891U JPH0532582U (en) 1991-09-27 1991-09-27 Frame scaffolding building frame

Publications (1)

Publication Number Publication Date
JPH0532582U true JPH0532582U (en) 1993-04-27

Family

ID=13663367

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7848891U Pending JPH0532582U (en) 1991-09-27 1991-09-27 Frame scaffolding building frame

Country Status (1)

Country Link
JP (1) JPH0532582U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100385817B1 (en) * 1999-12-29 2003-06-02 한전기공주식회사 Lifting adjuster

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6125445B2 (en) * 1983-01-10 1986-06-16 Kazansukii Abiatsuionii Inst Imeni An Teyuhoreba

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6125445B2 (en) * 1983-01-10 1986-06-16 Kazansukii Abiatsuionii Inst Imeni An Teyuhoreba

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100385817B1 (en) * 1999-12-29 2003-06-02 한전기공주식회사 Lifting adjuster

Similar Documents

Publication Publication Date Title
JPH10280669A (en) Scaffolding unit
JPH0532582U (en) Frame scaffolding building frame
CN108149911B (en) Modular scaffold and erection method thereof
JPH0754480A (en) Prefabricated scaffolding and assembling and disassembling method thereof
JP2022089706A (en) Building interior stairs advance construction method
JP2020007738A (en) Strut support tool
JP4136960B2 (en) Multi-layer scaffold installation method and frame fastener
JPH0874412A (en) Building scaffold and construction method thereof
JPH0270861A (en) Mounting and overhaulting method of work scaffold in step-up technique
JP2001288883A (en) Precedent handrail for prefabricated scaffolding
JPS6349460Y2 (en)
RU23899U1 (en) BUILDING FORESTS AND AREA FOR FASTENING DIAGONAL AND HORIZONTAL LINKS OF BEARING FRAMES OF BUILDING FORESTS
CN217461426U (en) Universal force clip springboard
JP3303218B2 (en) Reconstruction method
JP7390733B2 (en) Construction method and hollow parts for scaffolding truss beams
JPS6348752Y2 (en)
JP2542029Y2 (en) Assembling type work scaffold
JPH06248794A (en) Large-sized assembled-type moving scaffold
JPH0616600U (en) Temporary scaffolding for construction
JPH0447300Y2 (en)
JP2024053180A (en) Construction methods for wooden buildings
JPH0623651Y2 (en) Sash assembly device for curtain wall
JP4627597B2 (en) Working scaffold installed in the circulating water elbow piping
JPS6126533Y2 (en)
JPH04228772A (en) Method of building movable suspended scaffold for working at ceiling of large space structure