JPH0525927A - Assembling and disassembling of prefabricated scaffolding - Google Patents
Assembling and disassembling of prefabricated scaffoldingInfo
- Publication number
- JPH0525927A JPH0525927A JP18238191A JP18238191A JPH0525927A JP H0525927 A JPH0525927 A JP H0525927A JP 18238191 A JP18238191 A JP 18238191A JP 18238191 A JP18238191 A JP 18238191A JP H0525927 A JPH0525927 A JP H0525927A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- floor
- building
- ground
- assembling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004744 fabric Substances 0.000 claims description 12
- 238000000034 method Methods 0.000 claims description 9
- 239000002184 metal Substances 0.000 description 10
- 230000008878 coupling Effects 0.000 description 7
- 238000010168 coupling process Methods 0.000 description 7
- 238000005859 coupling reaction Methods 0.000 description 7
- 239000000463 material Substances 0.000 description 6
- 238000010276 construction Methods 0.000 description 5
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、建築物の作業足場と
なる枠組足場を組立てる工法及び解体工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method and a dismantling construction method for assembling a frame scaffold which is a working scaffold for a building.
【0002】[0002]
【従来の技術】建築物の作業足場として構築される枠組
足場は、並列する複数に建枠をブレースと布枠又は歩み
板で結合して階床を組み立て、この階床を複数段積み重
ねることにより所定の高さに構築するものである。2. Description of the Related Art A frame scaffold constructed as a work scaffold for a building is constructed by connecting a plurality of building frames in parallel with a brace and a cloth frame or a step board to assemble a floor, and stacking the floors in plural stages. It is constructed at a predetermined height.
【0003】従来、上記のような枠組足場を組立てるに
は、先ず地上において最下位の階床を組み立て、次に各
資材を階床上に持上げて上階の階床を組立て、これを上
方に順次繰返しながら所望の高さに組立てるものであ
る。Conventionally, in order to assemble the above-mentioned frame scaffolding, first, the lowest floor on the ground is assembled, then each material is lifted onto the floor to assemble the upper floor, and this is sequentially arranged upward. It is repeatedly assembled to a desired height.
【0004】また、構築後の枠組足場を解体するには、
最上位の階床から順に解体を行ない、各資材を地上へ降
すことによって行なうものである。In addition, in order to dismantle the frame scaffold after construction,
This is done by dismantling the highest floor in order and dropping each material to the ground.
【0005】[0005]
【発明が解決しようとする課題】ところで、上記した従
来の組立方法は、組立てが上方に進むに従って各資材を
持上げなければならず、しかも組立が高所作業となるた
め、作業能率が極めて悪く、手間と時間がかかると共
に、危険をともなうという問題がある。By the way, in the above-mentioned conventional assembling method, each material has to be lifted as the assembling progresses upward, and the assembling requires high work, resulting in extremely poor work efficiency. There is a problem that it takes time and labor and is dangerous.
【0006】また、従来の解体方法は、上部階床から解
体して行くため、各資材をクレーンで地下に降さなけれ
ばならず、解体が高所作業となるため、作業化に手間と
時間がかかり危険をともなうという問題がある。Further, in the conventional dismantling method, since the dismantling is performed from the upper floor, it is necessary to drop each material to the basement with a crane, and dismantling requires work at a high place. There is a problem that it is overloaded and dangerous.
【0007】そこで、この発明は、安全に能率よく枠組
足場を構築することができる組立工法と、枠組足場を安
全に能率よく解体できる解体工法を提供することを課題
としている。[0007] Therefore, an object of the present invention is to provide an assembly method capable of safely and efficiently constructing a frame scaffold and a dismantling method capable of safely and efficiently disassembling the frame scaffold.
【0008】[0008]
【課題を解決するための手段】上記のような課題を解決
するため、第1の発明は、並列する複数の建枠をブレー
スと布枠又は歩み板で順次結合して枠組足場の階床を組
み立て、増床時にこれをクレーンで吊り上げ保持した状
態で各建枠の下に建枠を継ぎ足して下位の階床を組み立
て、これを繰り返して階床を増やして行く方法を採用し
たものである。In order to solve the above problems, a first aspect of the present invention relates to a floor of a frame scaffold by sequentially connecting a plurality of parallel construction frames with a brace and a cloth frame or a step board. When assembling and expanding the floor, it is lifted by a crane and held to add a building frame under each building frame to assemble a lower floor, and this is repeated to increase the floors.
【0009】同じく第2の発明は、並列する複数の建枠
をブレースと布枠又は歩み板で順次結合して階床を組
み、これを複数段積み重ねて構築した枠組足場の解体に
際し、枠組足場をクレーンで吊り上げ保持した状態で下
位の階床から順に解体する方法を採用したものである。Similarly, a second aspect of the invention is to dispose a frame scaffold constructed by stacking a plurality of stages in parallel by connecting a plurality of parallel construction frames with a brace and a cloth frame or a step board and stacking the floors. It is a method of dismantling the lower floors in order with the cranes being lifted and held by a crane.
【0010】[0010]
第1の発明
地上において、並列配置した建枠をブレースと布枠又は
歩み板で順次結合して階床を組み立て、階床を上方に増
やすには、地上の階床をクレーンで吊り上げて保持し、
各建枠の下端に建枠の上端を接続して継ぎ足すと共に、
隣接する建枠をブレースと布枠又は歩み板で結合して階
床を組立て、全体を地上に下せば一階床分が増えた枠組
足場となる。1st Invention On the ground, assembling the floors by sequentially connecting the building frames arranged in parallel with the brace and the cloth frame or the step board, and in order to increase the floors upward, the floors on the ground are lifted and held by a crane. ,
While connecting the upper end of the building frame to the lower end of each building frame and adding it,
If the floors are assembled by connecting adjacent building frames with braces and cloth frames or walking boards, and the whole floor is put on the ground, it becomes a frame scaffolding with an increase of one floor.
【0011】このように、クレーンによる枠組足場の吊
り上げと、建枠下端に対する建枠の継ぎ足しによる階床
の組立てにより、階床の増加を枠組足場の下から行な
え、これによって組立作業が地上において行なえること
になり、資材の持上げや高所作業の必要をなくし、作業
の能率と安全性を向上させる。As described above, the floors can be increased from below the frame scaffolds by lifting the frame scaffolds by the crane and assembling the floors by adding the building frames to the lower ends of the building frames, whereby the assembling work can be performed on the ground. This eliminates the need to lift materials and work in high places, improving work efficiency and safety.
【0012】第2の発明
地上に構築した枠組足場の解体に際し、枠組足場全体を
クレーンで吊り上げて地上から浮かし、最下位階床を解
体する。Second invention When dismantling the frame scaffold constructed on the ground, the entire frame scaffold is lifted by a crane and floated from the ground to dismantle the lowest floor.
【0013】この後、枠組足場全体を階床の高さ分だけ
下し、下位階床を解体し、これを繰返して行なうことに
より、解体作業が地上において行なえ、高所作業をなく
して安全性と能率を向上させる。After that, the entire frame scaffolding is lowered by the height of the floor, the lower floors are dismantled, and this is repeated, so that dismantling work can be performed on the ground and safety is avoided by eliminating work at high places. And improve efficiency.
【0014】[0014]
【実施例】以下、この発明の実施例を添付図面に基づい
て説明する。Embodiments of the present invention will be described below with reference to the accompanying drawings.
【0015】図1と図2のように、枠組足場1は、一対
の縦柱2、2の上部を横桟3で結合した門型や鳥居型に
形成されたパイプ製の建枠4と、対向状に並列する建枠
4の縦柱2を互に連結するブレース5と、対向する建枠
4の横桟3間に架設する布枠6又は歩み板と、上下の建
枠4を互に連結するジョイント7とを用いて組立てられ
ることになる。As shown in FIGS. 1 and 2, the frame scaffold 1 comprises a pipe-shaped building frame 4 formed in a gate type or a torii type in which the upper portions of a pair of vertical columns 2 and 2 are connected by a horizontal crosspiece 3, The brace 5 connecting the vertical columns 2 of the building frames 4 arranged in parallel to each other, the cloth frame 6 or the walking board laid between the horizontal rails 3 of the facing building frame 4, and the upper and lower building frames 4 to each other. It will be assembled using the connecting joint 7.
【0016】上記建枠4を対向状に起立させ、これをブ
レース5と布枠6又は歩み板で結合することによって階
床Aが形成され、建枠4の数を選ぶことにより、平面的
に必要な長さの階床Aを得ることができる。A floor A is formed by erecting the building frames 4 so as to face each other and connecting them with the braces 5 and the cloth frames 6 or step plates. The floor A of the required length can be obtained.
【0017】上記建枠4には図3のように、両縦柱2、
2の上端にジョイント7が固定され、このジョイント7
の上半部を上位建枠の下端に挿入して結合することによ
り、上下の建枠4を互に接続することができるようにな
っている。As shown in FIG. 3, both the vertical columns 2,
A joint 7 is fixed to the upper end of 2, and the joint 7
The upper and lower building frames 4 can be connected to each other by inserting the upper half part of the upper building frame into the lower end of the upper building frame and connecting them.
【0018】ジョイント7は図4に示すように、縦柱2
が外嵌する接続パイプ8の中間部外周面に縦柱2の端部
を受ける突条9を周設すると共に、接続パイプ8の内部
にロックユニット10を収納して形成され、接続パイプ
8は縦柱2の上端に下半部を嵌合し、その下端を径方向
に貫通するピン11によって縦柱2に固定されている。The joint 7 is, as shown in FIG.
Is formed by accommodating the lock unit 10 inside the connection pipe 8 while surrounding the projection 9 for receiving the end of the vertical column 2 on the outer peripheral surface of the intermediate portion of the connection pipe 8 to which the connection pipe 8 is fitted. The lower half part is fitted to the upper end of the vertical column 2, and the lower end is fixed to the vertical column 2 by a pin 11 penetrating in the radial direction.
【0019】上記ロックユニット10は、上下に長い帯
板状に形成した本体12と、この本体12の表面側で上
端に突設した結合金属ピン13と、本体12の表面側で
中間部の位置に突設した操作ボタン14と、本体12の
背面側に取付けたばね15とで構成され、接続パイプ8
には、突条9の部分に操作ボタン14の嵌合孔16と、
上部外周面に金属結合ピン13の貫通孔17とが設けら
れている。The lock unit 10 has a main body 12 formed in the shape of a vertically long strip, a coupling metal pin 13 protruding from the upper surface of the main body 12 at the upper end, and an intermediate position on the front surface of the main body 12. It is composed of an operation button 14 projecting on the rear side and a spring 15 attached to the back side of the main body 12,
Includes a fitting hole 16 for the operation button 14 in the protrusion 9.
A through hole 17 for the metal connecting pin 13 is provided on the outer peripheral surface of the upper portion.
【0020】また、縦柱2の下端側には、接続パイプ8
の上半部に外嵌挿したとき、貫通孔17と対応する位置
に金属結合ピン13が嵌合する結合孔18が設けられて
いる。On the lower end side of the vertical column 2, a connecting pipe 8 is provided.
A coupling hole 18 into which the metal coupling pin 13 fits is provided at a position corresponding to the through hole 17 when the metal coupling pin 13 is externally fitted and inserted.
【0021】前記ロックユニット10は接続パイプ8内
へ組込むことによって、ばね10で本体12が常時押圧
され、操作ボタン14が嵌合孔16から突条9の外面に
突出し、金属結合ピン13が貫通孔17から外部に突出
していると共に、操作ボタン14を押込むと、この操作
ボタン14の上面に設けた段部14aが嵌合孔16の上
部内端面に係合し、結合ピン13が貫通孔17から接続
パイプ8の内部に没入した状態が保持され、接続パイプ
8の上半部と上位縦柱2の抜き差しが支障なく行なえる
ようになっている。When the lock unit 10 is assembled in the connecting pipe 8, the main body 12 is constantly pressed by the spring 10, the operation button 14 projects from the fitting hole 16 to the outer surface of the ridge 9, and the metal connecting pin 13 penetrates. When the operation button 14 is pushed in while protruding to the outside from the hole 17, the stepped portion 14a provided on the upper surface of the operation button 14 engages with the upper inner end surface of the fitting hole 16, and the coupling pin 13 is inserted into the through hole. The state of being immersed in the inside of the connection pipe 8 from 17 is maintained, and the upper half of the connection pipe 8 and the upper vertical column 2 can be inserted and removed without any trouble.
【0022】また、接続パイプ8と上位縦柱2の結合
は、操作ボタン14を押し下げて段部14aの係止を解
けばよく、金属結合ピン13は縦柱2の結合孔18に嵌
合することになる。To connect the connection pipe 8 and the upper vertical column 2, the operation button 14 may be pushed down to unlock the stepped portion 14a, and the metal connecting pin 13 fits into the connecting hole 18 of the vertical column 2. It will be.
【0023】次に、枠組足場の組立工法を説明する。Next, a method for assembling the frame scaffold will be described.
【0024】先ず、地上において対向させた建枠4をブ
レース5と布枠6又は歩み板で結合し、これを平面的に
必要な長さだけ繰返すことによって枠組足場の階床Aを
組立てる。First, the building frame 4 of the frame scaffolding is assembled by connecting the building frames 4 opposed to each other on the ground with the brace 5 and the cloth frame 6 or the step board, and repeating this planarly for the required length.
【0025】階床Aを上に増やすには、図1と図2に示
すように、クレーンのフック21に吊り下げた吊り金具
22と各建枠4の上部をロープやワイヤ23で接続し、
仮設足場全体を建枠4の高さ寸法よりも少し高い量だけ
吊り下げて保持する。In order to increase the floor A upward, as shown in FIGS. 1 and 2, the hanging metal fittings 22 hung on the hooks 21 of the crane and the upper parts of the respective building frames 4 are connected by ropes or wires 23,
The entire temporary scaffold is suspended and held by an amount slightly higher than the height of the building frame 4.
【0026】この状態で各建枠4の下端に地上から建枠
4を継ぎ足す。この継ぎ足しは、縦柱2の上端に取付け
たジョイント7におけるロックユニット10の操作ボタ
ン14を押込んで係止し、金属結合ピン13を没入させ
ておき、持上げた建枠4のジョイント7を上位建枠4に
おける縦柱2の下端に差し込み、この差し込み状態で操
作ボタン14を操作して係止を解き、金属結合ピン13
を貫通孔17と結合孔18にわたって嵌合させれば、ジ
ョイント7を介して上下の建枠4が連結され、図1によ
うに下位の建枠4は吊り下げられた状態になる。In this state, the building frames 4 are added to the lower end of each building frame 4 from the ground. In this extension, the operation button 14 of the lock unit 10 in the joint 7 attached to the upper end of the vertical column 2 is pushed and locked, the metal coupling pin 13 is immersed, and the joint 7 of the lifted building frame 4 is constructed in a higher order. Insert into the lower end of the vertical column 2 in the frame 4, and operate the operation button 14 in this inserted state to release the lock,
Is fitted over the through hole 17 and the coupling hole 18, the upper and lower building frames 4 are connected via the joint 7, and the lower building frame 4 is suspended as shown in FIG.
【0027】このようにして、吊り上げた各建枠4の下
端に建枠4を連結すると共に、隣接する建枠相互をブレ
ース5と布枠6又は歩み板で結合すれば階床Aが組上が
り、この後全体を下降させて接地させれば、階床Aが一
段増えた枠組足場となる。In this way, the floor A is assembled by connecting the building frames 4 to the lower ends of the hoisted building frames 4 and connecting the adjacent building frames with the brace 5 and the cloth frame 6 or the step board. After that, if the whole is lowered and brought into contact with the ground, the floor A becomes a frame scaffolding with a further increase.
【0028】上記のように、階床Aを上方に順次増やす
には、クレーンでの吊り上げと、下方からの継ぎ足しを
順次繰り返して行なえればよく、作業は地上にてすべて
実施できる。As described above, in order to sequentially increase the floor A upward, it is sufficient to carry out lifting by a crane and replenishment from below in sequence, and all the work can be performed on the ground.
【0029】なお、枠組足場はクレーンでの吊り上げに
より、ジョイント7の部分に引張り荷重がかかることに
なるが、ジョイント7は図4に示したように、接続パイ
プ8と下位建枠の上端がピン11によって、また、接続
パイプ8と上位建枠の下端とは金属結合ピン13によっ
て結合されているため、接続部分の耐引張り強度が強
く、クレーンでの吊り上げが支障なく行なえる。In the frame scaffolding, a tensile load is applied to the joint 7 portion by hoisting it with a crane. However, as shown in FIG. 4, the joint pipe 8 and the upper end of the lower building frame are pinned. Since the connection pipe 8 and the lower end of the upper building frame are connected by the metal connecting pin 11, the connection portion has a high tensile strength and the crane can be lifted without any trouble.
【0030】また、枠組足場の吊り上げ時において、ジ
ョイント7にかかる引張り荷重をなくすには、図2に一
点鎖線で示すように、吊り金具22に取付けたロープ2
3又はワイヤの枠組足場への接続を最下位建枠の位置に
なるよう選べばよい。In order to eliminate the tensile load applied to the joint 7 when the frame scaffold is hoisted, the rope 2 attached to the hoisting metal fitting 22 as shown by the chain line in FIG.
3 or wire connections to the frame scaffold may be chosen to be at the lowest building position.
【0031】上記のように組立てた枠組足場の解体は、
組立て時と同様、枠組足場全体をクレーンで吊り上げた
状態で、最下位の階床から順に分解して行けばよい。The disassembly of the frame scaffold assembled as described above is
As with assembly, the entire frame scaffolding can be lifted by a crane and disassembled in order from the lowest floor.
【0032】即ち、枠組足場全体を地上から浮くように
クレーンで吊り上げ、最下位の階床を解体すると、枠組
足場を階床の高さ分だけ下して下位の階床を解体し、こ
れを順次繰返すことにより、地上での作業によって解体
が行なえる。That is, when the entire frame scaffold is lifted by a crane so as to float above the ground and the lowest floor is dismantled, the frame scaffold is lowered by the height of the floor to dismantle the lower floor, and By repeating it in sequence, dismantling can be performed by work on the ground.
【0033】なお、解体時におけるロープ又はワイヤの
枠組足場に対する接続は、上部階床の建枠に設定してお
けばよい。The connection of the rope or wire to the frame scaffold at the time of disassembly may be set in the building frame of the upper floor.
【0034】[0034]
【効果】以上のように、この発明によると、枠組足場の
組立て及び解体がすべて地上において行なえ、組立時及
び解体時の高所作業が一切不要になるので、足場組立て
及び解体の安全性を大幅に向上させることができる。[Effect] As described above, according to the present invention, the assembly and dismantling of the frame scaffolding can be performed on the ground altogether, and no work at a high place is required at the time of assembling and dismantling, so that the safety of scaffolding assembly and dismantling is greatly improved. Can be improved.
【0035】また、枠組足場を構成する各資材を組立て
及び解体の進行と共に上げ下しするというような作業が
不要となり、しかも組立作業及び解体作業が地上で行な
えるので、作業能率が向上し、省力化を図ることができ
る。Further, the work of raising and lowering each material constituting the frame scaffolding as the assembly and dismantling progress is unnecessary, and since the assembling work and the dismantling work can be performed on the ground, the work efficiency is improved, Labor saving can be achieved.
【図1】この発明の組立工法を示す組立途中の正面図FIG. 1 is a front view during assembly showing the assembly method of the present invention.
【図2】同上の側面図FIG. 2 is a side view of the above.
【図3】上下建枠の接続部分を示す拡大縦断面図FIG. 3 is an enlarged vertical cross-sectional view showing a connecting portion of upper and lower building frames.
【図4】同上におけるジョイント部分の拡大縦断面図FIG. 4 is an enlarged vertical sectional view of a joint portion of the above.
1 枠組足場 2 縦柱 4 建枠 5 ブレース 6 布枠 7 ジョイント 8 接続パイプ A 階床 1 framework scaffolding 2 vertical columns 4 building frames 5 braces 6 cloth frame 7 joint 8 connection pipes A floor
Claims (2)
は歩み板で順次結合して枠組足場の階床を組み立て、増
床時にこれをクレーンで吊り上げ保持した状態で各建枠
の下に建枠を継ぎ足して下位の階床を組み立て、これを
繰り返して階床を増やして行くことを特徴とする枠組足
場の組立工法。1. A floor of a frame scaffolding is assembled by sequentially connecting a plurality of parallel building frames with a brace and a cloth frame or a step board, and when the floors of the framed scaffolding are suspended and held by a crane, they are placed under each building frame. A method for assembling a frame scaffold, which is characterized by adding building frames to assemble lower floors, and repeating this to increase floors.
は歩み板で順次結合して階床を組み、これを複数段積み
重ねて構築した枠組足場の解体に際し、枠組足場をクレ
ーンで吊り上げ保持した状態で下位の階床から順に解体
することを特徴とする枠組足場の解体工法。2. When disassembling a frame scaffold constructed by stacking a plurality of stages in which a plurality of parallel building frames are connected in sequence with a brace and a cloth frame or a step board and the floors are stacked, the frame scaffold is lifted and held by a crane. The method of dismantling the frame scaffold, which is characterized by disassembling the lower floors in that order.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18238191A JPH0525927A (en) | 1991-07-23 | 1991-07-23 | Assembling and disassembling of prefabricated scaffolding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18238191A JPH0525927A (en) | 1991-07-23 | 1991-07-23 | Assembling and disassembling of prefabricated scaffolding |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0525927A true JPH0525927A (en) | 1993-02-02 |
Family
ID=16117321
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18238191A Pending JPH0525927A (en) | 1991-07-23 | 1991-07-23 | Assembling and disassembling of prefabricated scaffolding |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0525927A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0882087A (en) * | 1994-09-13 | 1996-03-26 | Kajima Corp | Assembling method and dismantling method of frame scaffold |
KR20010105570A (en) * | 2000-05-16 | 2001-11-29 | 박재영 | Jig for pulling up a strut and a strut lift-up construction method using the same |
JP2010222884A (en) * | 2009-03-24 | 2010-10-07 | Sano Kasetsu Kogyo:Kk | Assembling and demolition method for scaffold |
FR3005083A1 (en) * | 2013-04-30 | 2014-10-31 | Godon Sas | FRAME FOR TURNING ROTOR COMPRISING ELASTIC LATCHING MEANS AND METHOD OF MOUNTING THE SAME |
-
1991
- 1991-07-23 JP JP18238191A patent/JPH0525927A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0882087A (en) * | 1994-09-13 | 1996-03-26 | Kajima Corp | Assembling method and dismantling method of frame scaffold |
KR20010105570A (en) * | 2000-05-16 | 2001-11-29 | 박재영 | Jig for pulling up a strut and a strut lift-up construction method using the same |
JP2010222884A (en) * | 2009-03-24 | 2010-10-07 | Sano Kasetsu Kogyo:Kk | Assembling and demolition method for scaffold |
FR3005083A1 (en) * | 2013-04-30 | 2014-10-31 | Godon Sas | FRAME FOR TURNING ROTOR COMPRISING ELASTIC LATCHING MEANS AND METHOD OF MOUNTING THE SAME |
WO2014177462A1 (en) * | 2013-04-30 | 2014-11-06 | Godon Sas | Frame for a shoring tower, comprising resilient locking means, and method for assembling said frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3302749A (en) | Derrick scaffold structure | |
CN107761961A (en) | A kind of electronic climbing frame monolithic construction method of high-rise building | |
JPH0525927A (en) | Assembling and disassembling of prefabricated scaffolding | |
CN212246007U (en) | Be used for tower crane bracket welded portable platform | |
CN216516907U (en) | High-altitude convenient cantilever frame | |
CN212405472U (en) | Cross node connection structure of assembled frame structure | |
CN215291319U (en) | Multi-point elevator shaft construction lifting platform | |
CN212406038U (en) | Lower hanging construction platform module of high-altitude large-cantilever steel roof truss | |
JP2000120367A (en) | External fastening liner plate and method for using it | |
WO2023173676A1 (en) | Space truss support platform, system and method for super-deep slurry wall | |
CN210438301U (en) | Light slat lifting device for building partition wall | |
CN113445723A (en) | Construction platform for mounting overhanging structure curtain wall and mounting method | |
JPS6168971A (en) | Assembling and disassembling of frame scaffold | |
JP4011722B2 (en) | Hanging stairs | |
KR100948447B1 (en) | Truss top plate dismantling device and method | |
CN218714945U (en) | Assembled building combination is from promoting protection frame | |
JP2003034939A (en) | Underground reverse construction method | |
CN217299872U (en) | Shaft hydraulic comprehensive distribution platform | |
CN215107235U (en) | High-altitude cantilever structure formwork support platform | |
JP2817208B2 (en) | Construction method of rack steel frame | |
CN114439248B (en) | Steel column installation method | |
JP2532116B2 (en) | Lifting scaffolding | |
CN214302864U (en) | A combined steel platform for shaft operation | |
CN217326481U (en) | I-steel subassembly fast combination construction structures | |
JPH03125755A (en) | Constructing method for cylindrical multistoried structure |