[go: up one dir, main page]

JPH05202563A - Joint construction of panel structure and joining metal fixture - Google Patents

Joint construction of panel structure and joining metal fixture

Info

Publication number
JPH05202563A
JPH05202563A JP3716292A JP3716292A JPH05202563A JP H05202563 A JPH05202563 A JP H05202563A JP 3716292 A JP3716292 A JP 3716292A JP 3716292 A JP3716292 A JP 3716292A JP H05202563 A JPH05202563 A JP H05202563A
Authority
JP
Japan
Prior art keywords
panel
floor
unit room
bolt
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3716292A
Other languages
Japanese (ja)
Other versions
JP2612658B2 (en
Inventor
Toshihiko Okutsu
俊彦 奥津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP4037162A priority Critical patent/JP2612658B2/en
Publication of JPH05202563A publication Critical patent/JPH05202563A/en
Application granted granted Critical
Publication of JP2612658B2 publication Critical patent/JP2612658B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

PURPOSE:To and quickly joint a panel structure by fixing bolts protruded from anchor bolts or wall panels through a metal block fixed on a floor panel from the outside of the panel structure when a panel structure like a foundation or a unit room is installed. CONSTITUTION:A jointing metal fixture 10 is fixed through fitting holes 20 at both right and left sides 12 in the recession 44 formed at the endface of a floor panel 38 of a unit room 32. The bolt 48 protruded from the wall panel 40 side is inserted into the upper jointing hole 22 of the jointing metal fixture 10 and fastened. And the bolt protruded from a foundation 30 or other unit room to be jointed is inserted into the lower jointing hole 23 of the jointing metal fixture 10 and fastened. In this way, jointing work, of panel structures can be carried out.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、工業化住宅におけるパ
ネル構造体の連結構造およびこの連結構造に好適に使用
されるパネル構造体用連結金物に関し、特にユニットル
ームと基礎或はユニットルーム同士を連結するに適した
パネル構造体の連結構造および連結金物に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a panel structure connecting structure in an industrialized house and a panel structure connecting metal piece suitable for use in this connecting structure, and more particularly to connecting a unit room with a foundation or unit rooms. The present invention relates to a panel structure connecting structure and a connecting metal article suitable for the above.

【0002】[0002]

【従来の技術】近年、建築物等においては、工業化が進
められている。
2. Description of the Related Art In recent years, industrialization has progressed in buildings and the like.

【0003】特に工期の短縮、現場施工の容易性などか
ら、例えばユニット工法が取り入れられている。このユ
ニット工法においては、予め工場で組み立て生産した箱
状のユニットルームを現場に搬送して、現場で複数のユ
ニットルームを組み付けることによって、住宅などを建
築するようにしている。
[0003] In particular, for example, a unit construction method has been adopted in order to shorten the construction period and to facilitate on-site construction. In this unit construction method, a box-shaped unit room preassembled and produced in a factory is transported to the site, and a plurality of unit rooms are assembled at the site to build a house or the like.

【0004】そして、従来ではこのようなユニットルー
ムを基礎上に固定する場合、或はユニットルーム同士を
積み重ねて上下に連結固定する場合、基礎上に取り付け
たアンカボルト或は階下のユニットルームの壁パネルに
取り付けたボルトをユニットルームの床パネルに貫通さ
せ、ユニットルームの室内側からこれらアンカボルト或
はボルトにナットを取付け、これを締付けて連結固定す
るようにしていた。
[0004] Conventionally, when fixing such unit rooms on a foundation, or stacking unit rooms and connecting and fixing them vertically, an anchor bolt mounted on the foundation or a wall of a unit room downstairs. The bolts attached to the panel are pierced through the floor panel of the unit room, nuts are attached to these anchor bolts or bolts from the indoor side of the unit room, and the nuts are tightened for connection and fixing.

【0005】[0005]

【発明が解決しようとする課題】前記従来例において
は、基礎に配設したアンカボルト或は階下のユニットル
ームの壁パネルより突出させたボルトを、直接取り付け
ようとするユニットルームの床パネルに貫通させ、室内
側からナットを締付け固定するようにしていたため、取
り付けようとするユニットルームを基礎上又はユニット
ルーム上に載置して位置決めし、アンカボルト又は階下
のユニットルームの壁パネルより突出させたボルトを床
パネルに形成した貫通孔を挿通させた後、作業者がユニ
ットルーム内に入り込んでナットの締付け作業を行なわ
なければならず、ユニットルームの載置位置決め作業
と、ナットの締付け作業とを別々の段階で行なわなけれ
ばならないため、作業に手間がかかり、それだけ作業時
間も延びることとなるという問題があった。
In the above-mentioned conventional example, an anchor bolt arranged on a foundation or a bolt protruding from a wall panel of a unit room downstairs penetrates a floor panel of a unit room to be directly attached. Since the nut was tightened and fixed from the indoor side, the unit room to be mounted was placed and positioned on the foundation or on the unit room and projected from the anchor bolt or the wall panel of the unit room below. After inserting the bolts through the through holes formed in the floor panel, the worker must enter the unit room and perform the nut tightening work.The mounting and positioning work of the unit room and the nut tightening work must be performed. Since it has to be performed in different stages, the work is troublesome and the work time is extended accordingly. There has been a problem to say.

【0006】また、ユニットルームの室内側からボルト
・ナットの締付け作業を行うためには、壁パネル内側に
締付け作業用の開口部を形成する必要がある。そして、
この開口部を覆いかくすとともにクロスなどの内装仕上
げ材を取付ける作業は、ボルト・ナットの締付け作業が
終了した後に行なわなければならず、現場での内装仕上
げ作業が必要であった。このような現場での内装仕上げ
作業がパネル工法あるいはユニット工法の工業化を図る
うえで障害のひとつとなっていた。
In order to tighten the bolts and nuts from the inside of the unit room, it is necessary to form an opening for tightening work inside the wall panel. And
The work of covering the opening and mounting the interior finishing material such as a cloth must be performed after the tightening work of the bolts and nuts is completed, and the interior finishing work on site is required. Such interior finishing work at the site was one of the obstacles to the industrialization of the panel construction method or the unit construction method.

【0007】本発明は、前記問題点に鑑みてなされたも
のであって、その目的は、基礎や階下のユニットルーム
の設置時に、ユニットルームまたは壁パネルなどのパネ
ル構造体の外側から、アンカボルトや壁パネルより突出
させたボルトを締付け固定することにより、簡単にかつ
短時間で連結可能とするパネル構造体の連結構造および
この連結に好適に使用される連結金具を提供することに
ある。
The present invention has been made in view of the above problems, and an object thereof is to install an anchor bolt from the outside of a panel structure such as a unit room or a wall panel when installing a foundation or a unit room downstairs. Another object of the present invention is to provide a panel structure connecting structure that can be connected easily and in a short time by tightening and fixing bolts protruding from the wall panel and a connecting fitting that is preferably used for this connection.

【0008】[0008]

【課題を解決するための手段】前記目的を達成するため
に、請求項1のパネル構造体の連結構造は、基礎または
壁パネルと床パネルとの連結構造において、床パネルの
外側端面側に複数の連結金物を固定し、この連結金物を
介して前記基礎と前記床パネル、または前記床パネルと
前記壁パネルとを連結し、連結操作を壁パネルの外方よ
り行なうことを特徴とする。
In order to achieve the above object, the connecting structure of the panel structure according to claim 1 is a plurality of connecting structures of a foundation or wall panel and a floor panel on the outer end face side of the floor panel. The connection hardware is fixed, and the foundation and the floor panel or the floor panel and the wall panel are connected via the connection hardware, and the connection operation is performed from the outside of the wall panel.

【0009】また、請求項2に記載のパネル構造体用連
結金物は、床パネル外側端面に固定するための取付孔を
有する側部と、上下方向に貫通形成したボルト挿入用の
連結孔を有する上部および下部と、少なくとも前面を開
放して形成したボルト締付け操作部と、を含むことを特
徴としている。
Further, the panel structure connecting metal article according to a second aspect has a side portion having a mounting hole for fixing to an outer end surface of the floor panel and a connecting hole for vertically inserting a bolt. It is characterized by including an upper portion and a lower portion, and a bolt tightening operation portion formed by opening at least the front surface.

【0010】[0010]

【作用】前記連結金物をその側部に形成した取付孔を介
して、床パネルなどの取付け部材にネジ等によって取り
付ける。
The connecting hardware is attached to a mounting member such as a floor panel with a screw or the like through a mounting hole formed in a side portion thereof.

【0011】次に、上下部に貫通形成したボルト挿入用
の連結孔に、アンカボルトや壁パネルから突出させたボ
ルトを挿入する。
Next, anchor bolts or bolts protruding from the wall panel are inserted into the bolt insertion connecting holes formed in the upper and lower portions.

【0012】そして、少くとも前面を開口して形成した
ボルト締付け操作部より、前記アンカボルト或はボルト
にナットを螺合させて締付け固定すれば簡単に連結がで
きる。しかも、連結金物は、予め工場出荷段階に置いて
取付け部材に取り付けておくことができるので、現場で
の施工固定が省略され、それだけ施工時間も短縮化でき
るものである。
The bolt can be easily connected by screwing a nut to the anchor bolt or the bolt by the bolt tightening operation portion formed by opening the front surface at least. Moreover, since the connecting hardware can be placed in advance at the factory shipment stage and attached to the attachment member, the work fixing at the site is omitted, and the work time can be shortened accordingly.

【0013】また、この連結金物を用いてパネル工法に
用いられる各パネルやユニットルームなどのパネル構造
体を連結する場合には、ユニットルームの場合を例にと
って説明すると、予め工場出荷段階において、ユニット
ルームの床パネルの外側端面の所定位置に、複数の連結
金物をその側部の取付孔を介してを固定する。
Further, in case of connecting the panel structure such as each panel or unit room used in the panel construction method by using the connecting hardware, the case of the unit room will be explained as an example. A plurality of connecting metal parts are fixed to predetermined positions on the outer end surface of the floor panel of the room through the mounting holes on the side parts thereof.

【0014】次に、このユニットルームの壁パネルから
突出させたボルトを連結金物の上部連結孔に挿通させて
締付け、この状態で建築現場に搬送する。
Next, the bolts protruding from the wall panel of the unit room are inserted into the upper connecting holes of the connecting metal article and tightened, and the bolts are conveyed to the construction site in this state.

【0015】次に、基礎又は連結する他のユニットルー
ムの壁パネルから突出させたボルトを連結金物の下部連
結孔に位置合せをして挿通させ、ユニットルームの外側
からボルト締付け操作部内にナットを挿入してボルトに
螺合させ締付ければ、ユニットルームの位置合わせと同
時に連結固定もなし得、施工時間も短縮化し得ることと
なるものである。
Next, a bolt protruding from the wall panel of the foundation or another unit room to be connected is inserted into the lower connecting hole of the connecting metal fitting in alignment, and a nut is inserted into the bolt tightening operation portion from the outside of the unit room. If it is inserted, screwed into the bolt and tightened, the unit room can be aligned and connected and fixed at the same time, and the construction time can be shortened.

【0016】また、上述のように壁パネルの外側からパ
ネル相互間の連結を行なうことができるため、壁パネル
の内壁面に予め工場でクロス等の内装仕上げを行なうこ
とができ、仕上げ工事の大幅な効率化を図ることができ
る。
Further, as described above, since the panels can be connected to each other from the outside of the wall panel, the inner wall surface of the wall panel can be preliminarily subjected to interior finishing such as cloth at the factory. Efficiency can be improved.

【0017】[0017]

【実施例】以下、本発明の好適な実施例について図面を
参照しながら詳細に説明する。
Preferred embodiments of the present invention will be described in detail below with reference to the drawings.

【0018】図1〜図6は本発明の一実施例を示す図で
ある。
1 to 6 are views showing an embodiment of the present invention.

【0019】本実施例の連結金物10は、図1に示すよ
うに、前面を開口して形成した箱状のもので、左右両側
部12と、上下部14、16と、これら左右両側部1
2、上下部14、16を連結する奥壁部18とを有して
いる。
As shown in FIG. 1, the connecting hardware 10 of the present embodiment is a box-shaped member having an open front surface, and has left and right side portions 12, upper and lower portions 14 and 16, and these left and right side portions 1.
2. It has an inner wall portion 18 that connects the upper and lower portions 14 and 16.

【0020】左右両側部12には、それぞれ予め工場等
において床パネル等の取付け対象物に取付けておくため
の2つのネジ止め用の取付孔20が形成されている。
On both the left and right sides 12, two mounting holes 20 for screwing are formed in advance so as to be mounted on a mounting object such as a floor panel in a factory.

【0021】上下部14、16には、壁パネルなどの上
下の連結対象物より突出させたボルトを挿入させるため
の連結孔22、23が貫通形成されている。
Connection holes 22 and 23 are formed through the upper and lower portions 14 and 16 for inserting bolts protruding from the upper and lower connection objects such as wall panels.

【0022】また、左右両側部12、上部14、下部1
6及び奥壁部18に囲まれる部分は前面を開口にした空
間として形成され、前記上下部14、16の連結孔2
2、23を貫通したボルトに対して前面側よりナットを
装着し締付けるためのボルト締付け操作部24として形
成されるようになっている。
The left and right side portions 12, the upper portion 14, the lower portion 1
A portion surrounded by 6 and the back wall portion 18 is formed as a space having an opening on the front surface, and the connecting hole 2 of the upper and lower portions 14 and 16 is formed.
It is formed as a bolt tightening operation portion 24 for mounting and tightening a nut from the front side with respect to the bolt penetrating 2 and 23.

【0023】次に、前記連結金物10を用いたユニット
ルームの連結構造について図2〜図6を参照して説明す
る。
Next, a unit room connecting structure using the connecting hardware 10 will be described with reference to FIGS.

【0024】この実施例では、図2に示すように、基礎
30上に1階のユニットルーム32を設置し、その1階
のユニットルーム32の上に2階のユニットルーム34
を設置するもので、前記基礎30と1階のユニットルー
ム32及び1階のユニットルーム32と2階のユニット
ルーム34との連結に前記連結金物10を複数ヵ所にお
いて用いるようにしている。
In this embodiment, as shown in FIG. 2, a unit room 32 on the first floor is installed on a foundation 30, and a unit room 34 on the second floor is placed on the unit room 32 on the first floor.
In order to connect the foundation 30 and the unit room 32 on the first floor and the unit room 32 on the first floor and the unit room 34 on the second floor, the connecting hardware 10 is used at a plurality of places.

【0025】基礎30は予め現場において施工され、そ
の上面の適宜位置より複数のアンカボルト36が突出し
た状態となっている。
The foundation 30 is preliminarily constructed in the field and a plurality of anchor bolts 36 are projected from appropriate positions on the upper surface thereof.

【0026】1階のユニットルーム32は、基礎30上
に設置可能な床パネル38上に壁パネル40を立設固定
し、これら壁パネル40にて形成される壁部の上開口部
分には天井材43を取付け、さらに、壁パネル40の内
壁に仕上げ材としてのクロス40aを取付け、予め工場
で箱状に組み付けられた状態で建築現場に搬送されるよ
うになっている。
In the unit room 32 on the first floor, a wall panel 40 is erected and fixed on a floor panel 38 that can be installed on the foundation 30, and a ceiling is formed in the upper opening portion of the wall portion formed by these wall panels 40. The material 43 is attached, and further, a cloth 40a as a finishing material is attached to the inner wall of the wall panel 40, and the cloth 40a is preliminarily assembled in a box shape at the factory and is transported to the construction site.

【0027】図3および図4に示すように、床パネル3
8の外周側端に位置する芯材42は、壁パネル40のほ
ぼ半分の厚さに設定され、さらにその側端面には基礎3
0より突出したアンカボルト36と対応する位置に、連
結金物10を取り付ける凹部44を形成し、その凹部4
4内に、開口を外側に向けた状態でかつ左右両側の取付
孔20を介して連結金物10をネジ止めするようにして
いる。
As shown in FIGS. 3 and 4, the floor panel 3
The core member 42 located at the outer peripheral side end of 8 is set to have a thickness almost half that of the wall panel 40, and the side end face has a base 3
At a position corresponding to the anchor bolt 36 protruding from 0, a concave portion 44 for mounting the connecting hardware 10 is formed, and the concave portion 4 is formed.
The connecting hardware 10 is screwed into the inside of the housing 4 with the opening facing outward and through the mounting holes 20 on both the left and right sides.

【0028】また、壁パネル40の下辺に位置する芯材
46には上方からボルト48が挿通され、予め工場にお
いて、このボルト48を前記床パネル38に取り付けた
連結金物10の上部側の連結孔22に挿通させ、ナット
50にて締付け連結するようにしている。
Further, a bolt 48 is inserted from above into the core member 46 located on the lower side of the wall panel 40, and the bolt 48 is attached to the floor panel 38 in advance in a factory. It is made to pass through 22 and is connected by tightening with a nut 50.

【0029】さらに、図5に示すように、壁パネル40
の上辺部にある芯材52には、下方側から上方に向けて
連結用のボルト54を突出させ、かつ脱落防止用のリン
グ56を装着している。尚、このボルト54は、予め工
場において装着されるものである。
Further, as shown in FIG. 5, the wall panel 40
On the core member 52 at the upper side, a connecting bolt 54 is projected from the lower side to the upper side, and a ring 56 for preventing the falling is attached. The bolt 54 is attached in advance at the factory.

【0030】2階のユニットルーム34は、前記1階の
ユニットルーム32と同様に1階のユニットルーム32
の壁パネル40上に載置される床パネル58と、この床
パネル58上に立設される壁パネル40と、この壁パネ
ル40の上開口部分に取り付けられた天井材60と、壁
パネル40の内壁に取付けたクロス40aとを有し、予
め工場において箱状に形成されている。
The unit room 34 on the second floor is the same as the unit room 32 on the first floor, and the unit room 32 on the first floor is the same.
Floor panel 58 placed on the wall panel 40, the wall panel 40 standing on the floor panel 58, the ceiling material 60 attached to the upper opening portion of the wall panel 40, and the wall panel 40. And a cloth 40a attached to the inner wall of the box, and is formed in a box shape in advance in a factory.

【0031】また、必要に応じ、工場において、壁パネ
ル40の外壁に外壁材を取付けておくこともできる。こ
のように、壁パネルの内外壁に仕上げ材を取付けておく
ことにより、現場での複雑で手間のかかる内外装作業を
行なう必要がなくなり、施行効率を高めることができ
る。
If necessary, an outer wall material may be attached to the outer wall of the wall panel 40 at the factory. As described above, by attaching the finishing material to the inner and outer walls of the wall panel, it is not necessary to perform a complicated and laborious interior and exterior work at the site, and the working efficiency can be improved.

【0032】なお、この2階のユニットルーム34の壁
パネル40上部には、図示せぬ屋根パネルが取り付けら
れるようになっている。
A roof panel (not shown) is attached to the upper portion of the wall panel 40 of the unit room 34 on the second floor.

【0033】又、床パネル58の外枠を構成する芯材6
2は、壁パネル40のほぼ半分の厚さに設定され、その
芯材62の前記ボルト54対応位置下部側には、凹部6
4が形成され、この凹部64内に、外側を開口させた状
態で、左右両側部12の取付孔20を介して連結金物1
0をネジ等にて固定するようにしている。
Further, the core material 6 which constitutes the outer frame of the floor panel 58.
2 is set to be approximately half the thickness of the wall panel 40, and a recess 6 is formed on the lower side of the core member 62 corresponding to the bolt 54.
4 is formed, and in the recess 64, with the outer side open, through the mounting holes 20 of the left and right side portions 12
0 is fixed with a screw or the like.

【0034】この連結金具10は、1階のユニットルー
ム32と同様に壁パネル40下辺側の芯材46を貫通さ
せたボルト48及びナット50を介し、予め工場におい
て上部14の連結孔22を介し連結金物10と連結一体
化されるようになっている。
Similar to the unit room 32 on the first floor, this connecting fitting 10 is provided with a bolt 48 and a nut 50 which penetrate the core material 46 on the lower side of the wall panel 40, and in advance through a connecting hole 22 of the upper part 14 in a factory. It is adapted to be connected and integrated with the connecting hardware 10.

【0035】なお、ボルト48、54にはそれぞれ締付
け時の空転を防止するための座金66が取り付けられて
いる。
A washer 66 is attached to each of the bolts 48 and 54 to prevent idling during tightening.

【0036】なお、床パネル38、58外周の露出部分
には胴差しあるいは幕板68、70が取付けられるよう
になっている。
A barrel insert or curtain plates 68, 70 are attached to the exposed portions of the outer peripheries of the floor panels 38, 58.

【0037】そして、これら1階のユニットルーム32
及び2階のユニットルーム34を施工現場に搬送し、施
工現場において連結固定するもので、その連結は次の様
にして行なう。
The unit room 32 on the first floor
And the unit room 34 on the second floor is transported to the construction site and connected and fixed at the construction site. The connection is performed as follows.

【0038】先ず、1階のユニットルーム32をクレー
ン等にて吊り下げ基礎30上迄移動させる。
First, the unit room 32 on the first floor is suspended by a crane or the like and moved to above the foundation 30.

【0039】次いで、図4に示すように、基礎30より
突出させたアンカボルト36と、1階のユニットルーム
32の床パネル38の取り付けた連結金物10の下部1
6側の連結孔23との位置合せを行ないつつ、1階のユ
ニットルーム32を基礎30上に載置する。この状態
で、連結金物10の連結孔23にアンカボルト36が挿
通した状態となっており、しかも連結金物10の外側が
開口してアンカボルト36の先端部が外側から見得る状
態となっているため、連結金物10のボルト締め付け操
作部24より、アンカボルト36にナットを装着して締
め付ければ1階のユニットルーム32の連結固定が外部
から容易になし得ることとなるものである。
Next, as shown in FIG. 4, the anchor bolt 36 protruding from the foundation 30 and the lower portion 1 of the connecting metal fitting 10 to which the floor panel 38 of the unit room 32 on the first floor is attached.
The unit room 32 on the first floor is placed on the foundation 30 while being aligned with the connecting hole 23 on the sixth side. In this state, the anchor bolt 36 is inserted into the connecting hole 23 of the connecting metal piece 10, and the outer side of the connecting metal piece 10 is open so that the tip of the anchor bolt 36 can be seen from the outside. Therefore, if the nut is attached to the anchor bolt 36 and tightened from the bolt tightening operation portion 24 of the connecting hardware 10, the unit room 32 on the first floor can be connected and fixed easily from the outside.

【0040】次に、2階のユニットルーム34をクレー
ン等にて吊り上げ、1階のユニットルーム32上まで移
動させる。
Next, the unit room 34 on the second floor is lifted by a crane or the like and moved to above the unit room 32 on the first floor.

【0041】次いで、図6に示すように、1階のユニッ
トルーム32の壁パネル40上辺部より突出させたボル
ト54と、2階のユニットルーム34の床パネル58に
取り付けた連結金物10の下部16側の連結孔23との
位置合せを行ないながら、2階のユニットルーム34を
1階のユニットルーム32の壁パネル40上に載置す
る。
Next, as shown in FIG. 6, the bolt 54 protruding from the upper side of the wall panel 40 of the unit room 32 on the first floor and the lower portion of the connecting metal fitting 10 attached to the floor panel 58 of the unit room 34 on the second floor. The unit room 34 on the second floor is placed on the wall panel 40 of the unit room 32 on the first floor while aligning with the connecting hole 23 on the 16th side.

【0042】そして、この状態で、連結金物10の連結
孔23に1階のユニットルーム32のボルト54が挿通
し、かつ連結金物10の開口が外側に向いているので、
そのボルト締め付け操作部24よりナットをボルト54
に装着し、締め付ければ1階のユニットルーム32と2
階のユニットルーム34との連結固定が容易になし得る
ものである。
In this state, the bolt 54 of the unit room 32 on the first floor is inserted into the connecting hole 23 of the connecting metal article 10 and the opening of the connecting metal article 10 is directed outward.
From the bolt tightening operation section 24, attach the nut to the bolt 54
Installed on and tightened, unit rooms 32 and 2 on the first floor
It can be easily connected and fixed to the unit room 34 on the floor.

【0043】このように、基礎30と1階のユニットル
ーム32及び1階のユニットルーム32と2階のユニッ
トルーム34との連結固定を連結金物10を用いてそれ
ぞれ外側から容易に行なうことができ、かつ施工時間の
短縮化にもつながるものである。
As described above, the foundation 30 and the unit room 32 on the first floor, and the unit room 32 on the first floor and the unit room 34 on the second floor can be easily connected and fixed from the outside using the connecting hardware 10. It also leads to a reduction in construction time.

【0044】前記実施例においては、基礎30と1階の
ユニットルーム32及び1階のユニットルーム32と2
階のユニットルーム34の連結固定について説明した
が、この例に限られるものではなく、例えば2階以上の
ユニットルームの連結にも適応し得るものである。ま
た、前記実施例においては、ユニットルームとユニット
ルームとの連結構造について説明したが、この例に限ら
れるものではなく、例えば、床パネルと壁パネル単体と
を連結する構造にも適応することができる。
In the above embodiment, the foundation 30 and the unit room 32 on the first floor and the unit rooms 32 and 2 on the first floor
Although the connection and fixation of the unit rooms 34 on the first floor have been described, the present invention is not limited to this example, and can be applied to the connection of the unit rooms on the second floor or higher, for example. Further, in the above embodiment, the connection structure between the unit room and the unit room has been described, but the present invention is not limited to this example, and may be applied to a structure for connecting a floor panel and a wall panel alone, for example. it can.

【0045】[0045]

【発明の効果】以上説明したように、本発明は、側部に
形成した取付孔にて連結金物を床パネルなどの取付け部
材に取り付け、上下部に貫通形成したボルト挿入用の連
結穴にアンカボルトや壁パネルから突出させたボルトを
挿入し、前面を開口して形成したボルト締付け操作部よ
り前記アンカボルト或はボルトにナットを螺合させて締
付け固定すれば、簡単に連結ができ、しかも連結金物
は、予め工場出荷段階に置いて取付け部材に取り付けて
おくことができるので、現場での施工固定が省略され、
それだけ施工時間も短縮化できるという効果がある。
As described above, according to the present invention, the connecting metal piece is attached to the attaching member such as the floor panel through the attaching hole formed in the side portion, and the anchor is formed in the connecting hole for inserting the bolt formed through the upper and lower portions. If you insert a bolt or a bolt protruding from the wall panel and screw the anchor bolt or bolt with the nut from the bolt tightening operation part that is formed by opening the front surface, you can easily connect, and Since the connecting hardware can be placed at the factory shipment stage in advance and attached to the attachment member, construction fixing at the site is omitted,
The construction time can be shortened accordingly.

【0046】また、この連結金物を用いてユニットルー
ムなどのパネル構造体を連結する場合には、予め工場出
荷段階において、床パネル側端面に連結金物の開口を外
側に向けた状態で、側部の取付孔を介して連結金物を床
パネルに固定し、壁パネル側から突出させたボルトを連
結金物の上部連結孔に挿通させて締付け、この状態で建
築現場に搬送し、基礎又は連結する他の壁パネルから突
出させたボルトを連結金物の下部連結孔に位置合せをし
て挿通させ、壁パネルの外側からボルト締付け操作部内
にナットを挿入してボルトに螺合させ締付ければ、ユニ
ットルームの位置合わせと同時に連結固定もなし得、施
工時間も短縮化し得ることとなるという効果がある。
When the panel structure such as a unit room is connected by using the connecting metal piece, the side portion is preliminarily shipped at the factory shipment stage with the opening of the connecting metal piece facing outward on the end face on the floor panel side. Fix the connecting metal object to the floor panel through the mounting hole of, insert the bolt protruding from the wall panel side into the upper connecting hole of the connecting metal object and tighten it, transport it to the construction site in this state, and connect it to the foundation or other Align the bolts protruding from the wall panel of the wall panel with the lower connection holes of the connecting hardware, insert the nuts from the outside of the wall panel into the bolt tightening operation part, and screw them into the bolts to tighten the unit room. There is an effect that the connection and the fixing can be performed at the same time as the position alignment, and the construction time can be shortened.

【0047】このように壁パネルあるいはユニットルー
ムを構成する壁パネルの外側から、基礎と床パネルある
いは床パネルと壁パネルとの連結操作を行なうことがで
きるため、上述のように現場での施工が簡略化できるだ
けでなく、壁パネルの内壁のクロスや外壁材などの仕上
げ材の取り付けを工場で行なうことができ、工業化住宅
の工業化を更に高度に達成することができる。
As described above, since the operation of connecting the foundation and the floor panel or the floor panel and the wall panel can be performed from the outside of the wall panel or the wall panel constituting the unit room, the construction on site can be performed as described above. Not only can it be simplified, but finishing materials such as the cloth on the inner wall of the wall panel and the outer wall material can be attached at the factory, and industrialization of the industrialized house can be achieved to a higher degree.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例に係る連結金物を示す斜視図
である。
FIG. 1 is a perspective view showing a connecting hardware according to an embodiment of the present invention.

【図2】本発明の一実施例に係るユニットルームの連結
構造を示す斜視図である。
FIG. 2 is a perspective view showing a unit room connection structure according to an embodiment of the present invention.

【図3】基礎と1階のユニットルームの連結状態を示す
分解斜視図である。
FIG. 3 is an exploded perspective view showing a connection state of a foundation and a unit room on the first floor.

【図4】図3の縦断面図である。4 is a vertical cross-sectional view of FIG.

【図5】1階のユニットルームと2階のユニットルーム
の連結構造を示す斜視図である。
FIG. 5 is a perspective view showing a connecting structure of a unit room on the first floor and a unit room on the second floor.

【図6】図5の縦断面である。6 is a vertical cross section of FIG.

【符号の説明】 10 連結金物 12 左右両側部 14 上部 16 下部 20 取付孔 22、23 連結孔 24 ボルト締付け操作部 30 基礎 32 1階のユニットルーム 34 2階のユニットルーム 36 アンカボルト 38、58 床パネル 40 壁パネル 44、64 凹部 48、54 ボルト 50、66 ナット[Explanation of Codes] 10 Connecting Hardware 12 Left and Right Sides 14 Upper 16 Lower 20 Mounting Hole 22, 23 Connecting Hole 24 Bolt Tightening Operation Section 30 Foundation 32 1st Floor Unit Room 34 2nd Floor Unit Room 36 Anchor Bolt 38, 58 Floor Panel 40 Wall panel 44, 64 Recessed portion 48, 54 Bolt 50, 66 Nut

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 基礎または壁パネルと床パネルとの連結
構造において、 前記床パネルの外側端面側に複数の連結金物を固定し、
この連結金物を介して前記基礎と前記床パネル、または
前記床パネルと前記壁パネルとを連結し、連結操作を壁
パネルの外方より行なうことを特徴とするパネル構造体
の連結構造。
1. In a connection structure of a foundation or wall panel and a floor panel, a plurality of connection metal parts are fixed to an outer end surface side of the floor panel,
A connecting structure for a panel structure, characterized in that the foundation and the floor panel or the floor panel and the wall panel are connected via the connecting hardware, and the connecting operation is performed from the outside of the wall panel.
【請求項2】 床パネル外側端面に固定するための取付
孔を有する側部と、 上下方向に貫通形成したボルト挿入用の連結孔を有する
上部および下部と、 少なくとも前面を開放して形成したボルト締付け操作部
と、 を含むことを特徴とするパネル構造体用連結金物。
2. A side portion having a mounting hole for fixing to an outer end surface of the floor panel, an upper portion and a lower portion having connection holes for inserting a bolt which are vertically formed so as to penetrate, and a bolt formed by opening at least a front surface. A fastening structure for a panel structure, comprising:
【請求項3】 請求項1において、前記床パネル外側端
面に、請求項1に記載の連結金物をその側部の取付孔を
介して複数個固定し、 前記床パネルの上位に位置する壁パネル側から突出させ
たボルトを前記連結金物の上部連結孔に挿通させて固定
すると共に、 基礎または前記床パネルの下位に位置する壁パネル側か
ら突出させたボルトを連結金物の下部連結孔に挿通させ
て固定することを特徴とするパネル構造体の連結構造。
3. The wall panel according to claim 1, wherein a plurality of the connecting hardware according to claim 1 is fixed to an outer end surface of the floor panel through mounting holes on a side portion of the floor panel, and the wall panel is positioned above the floor panel. The bolt protruding from the side is inserted and fixed in the upper connecting hole of the connecting metal object, and the bolt protruding from the side of the wall panel located below the foundation or the floor panel is inserted into the lower connecting hole of the connecting metal object. A structure for connecting panel structures, which is characterized in that the panel structure is fixed.
【請求項4】 請求項1または3において、前記壁パネ
ルは、少くともその内壁にクロスなどの内装仕上げ材が
取付けられていることを特徴とするパネル構造体の連結
構造。
4. The connection structure for a panel structure according to claim 1, wherein the wall panel has an interior finishing material such as a cloth attached to at least an inner wall thereof.
JP4037162A 1992-01-27 1992-01-27 Panel structure connection structure Expired - Lifetime JP2612658B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4037162A JP2612658B2 (en) 1992-01-27 1992-01-27 Panel structure connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4037162A JP2612658B2 (en) 1992-01-27 1992-01-27 Panel structure connection structure

Publications (2)

Publication Number Publication Date
JPH05202563A true JPH05202563A (en) 1993-08-10
JP2612658B2 JP2612658B2 (en) 1997-05-21

Family

ID=12489905

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4037162A Expired - Lifetime JP2612658B2 (en) 1992-01-27 1992-01-27 Panel structure connection structure

Country Status (1)

Country Link
JP (1) JP2612658B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10299104A (en) * 1997-04-24 1998-11-10 Sekisui Chem Co Ltd Installing structure of building, building unit, unit building and floor metallic material
KR101278983B1 (en) * 2012-02-16 2013-07-15 주식회사 포스코에이앤씨건축사사무소 Modular unit and modular construction using the same
WO2024224161A1 (en) 2023-04-28 2024-10-31 Universidade De Coimbra Connection system for modular construction of multi-storey buildings

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6183788A (en) * 1984-09-27 1986-04-28 ミサワホ−ム株式会社 Clamp structure of upstair and downstair opening unit

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6183788A (en) * 1984-09-27 1986-04-28 ミサワホ−ム株式会社 Clamp structure of upstair and downstair opening unit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10299104A (en) * 1997-04-24 1998-11-10 Sekisui Chem Co Ltd Installing structure of building, building unit, unit building and floor metallic material
KR101278983B1 (en) * 2012-02-16 2013-07-15 주식회사 포스코에이앤씨건축사사무소 Modular unit and modular construction using the same
WO2024224161A1 (en) 2023-04-28 2024-10-31 Universidade De Coimbra Connection system for modular construction of multi-storey buildings

Also Published As

Publication number Publication date
JP2612658B2 (en) 1997-05-21

Similar Documents

Publication Publication Date Title
JPH05202563A (en) Joint construction of panel structure and joining metal fixture
JPH0744642Y2 (en) Unit room connection structure
JPS6124497B2 (en)
JP2850990B2 (en) Wall panel joint structure
JPH0744641Y2 (en) Unit room connection structure
JP2001059298A (en) Exterior wall panel mounting structure
JP2601641Y2 (en) Floor panel structure
JP2602573Y2 (en) Connecting structure of overhang floor unit
JP3105133B2 (en) Inlet wall structure
JPH08165725A (en) Wall panel assembly construction and wall panel
JPH042267Y2 (en)
JPH03202535A (en) Fitting metal of wall panel
JP2000273964A (en) Joint fittings and unit building
JPS5841281Y2 (en) Balcony wall mounting device
JPH0285445A (en) Fixture and method for assembling framework wall panel of wood structure
JP2587615Y2 (en) House panel
JP2004019354A (en) Mounting structure of wall panel
JPH0552364A (en) Air conditioning apparatus for unit residence
JPH09125525A (en) Building unit
JPH03191156A (en) Structure of assembling wall and roof
JPH06146539A (en) Mounting structure of corner panel
JPH0742281A (en) Structure for attachment of bay window
JPH0742230A (en) Mounting structure of bay window floor panel
JPH06336768A (en) Joining structure for building unit
JPH01158143A (en) Fixture for lateral lined wall of alc panel

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970114