JPH05112949A - Execution method of foundation - Google Patents
Execution method of foundationInfo
- Publication number
- JPH05112949A JPH05112949A JP27528591A JP27528591A JPH05112949A JP H05112949 A JPH05112949 A JP H05112949A JP 27528591 A JP27528591 A JP 27528591A JP 27528591 A JP27528591 A JP 27528591A JP H05112949 A JPH05112949 A JP H05112949A
- Authority
- JP
- Japan
- Prior art keywords
- liner
- concrete
- cutting
- section
- scrap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は捨型枠を使用した布基
礎または地中梁および柱脚基礎の施工方法に関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a cloth foundation or an underground beam and a column base using a scrap frame.
【0002】[0002]
【発明が解決しようとする課題】従来の一般的な布基礎
の施工法は、地盤を根切りした後、鉄筋を現場で組み、
その両側に型枠をセパレーター等の型枠緊結金具を使用
して組立ており、コンクリートの打設後、コンクリート
の硬化を待って脱型しており、現場での作業量が根切り
量とともに相当必要である。The conventional general method of constructing a cloth foundation is to cut the ground and then assemble the reinforcing bars on-site.
Formwork is assembled on both sides using formwork binding metal fittings such as separators, and after pouring concrete, it is demolded waiting for the concrete to harden. Is.
【0003】この発明は前記従来工法を省力化すべく開
発したものである。The present invention was developed to save labor in the conventional method.
【0004】[0004]
【課題を解決するための手段】この発明は、地盤に所定
深さの根切りをなし、根切り底にライナーを設置し、ラ
イナーを定規として捨型枠を樹立して捨型枠の外側を埋
戻し、次いで捨型枠間に先組した鉄筋を落し込み、次い
で捨型枠間にコンクリートを打設する基礎の施工方法お
よび地盤に所定深さの根切りをなし、根切り底にライナ
ーを設置し、先組した柱脚部鉄筋を基礎上に設置すると
ともにライナーを定規として先組した地中鉄筋を設置
し、前記柱脚部鉄筋および地中梁鉄筋の周囲に捨型枠を
樹立し、捨型枠の外側を埋戻し、次いで捨型枠間にコン
クリートを打設することを特徴とする基礎の施工法であ
る。According to the present invention, a root is cut to a predetermined depth in the ground, a liner is installed at the root cutting bottom, a liner is used as a ruler to establish a scrap frame, and the outside of the scrap frame is set. Backfill, then drop the pre-assembled rebar between the scrap frames, then place concrete between the scrap frames.Construction method of the foundation and root cutting to a predetermined depth in the ground, and liner on the root cutting bottom. Installed and installed the pre-assembled column base rebar on the foundation and installed the pre-assembled underground rebar using the liner as a ruler, and established a scrap frame around the column base rebar and the underground beam rebar. It is a foundation construction method characterized by backfilling the outside of the scrap frame and then placing concrete between the scrap frames.
【0005】[0005]
【実施例】1番目の発明は次の工程よりなる。先ず、地
盤Aに所定深さ、すなわち布基礎の根入れ深さに相当す
る深さの根切りBをなし、その根切り底に敷砂を布設、
または捨コンクリートを打設し、その上にライナー1を
設置する。このライナー1はL形断面の両側受レール2
が連結材3で連結され、この連結材3の上部は鉄筋受部
4があり立上り辺5と受レール2とで溝形をなし、長さ
方向に所定間隔に配置されている。この受レール2には
内面にリブ付きのプレキャストコンクリート板等からな
る捨型枠6の下端を嵌めて樹立し、直ちに捨型枠6の外
側根切り部分に土砂を埋戻す。The first invention comprises the following steps. First, a root cutting B having a predetermined depth, that is, a depth corresponding to the rooting depth of the cloth foundation, is formed on the ground A, and laying sand is laid on the root cutting bottom,
Alternatively, waste concrete is poured and the liner 1 is installed on it. This liner 1 is a double-sided rail 2 with an L-shaped cross section.
Are connected by a connecting member 3, and an upper portion of the connecting member 3 has a reinforcing bar receiving portion 4, and a rising edge 5 and a receiving rail 2 form a groove shape and are arranged at predetermined intervals in the length direction. The bottom of a scrap frame 6 made of a precast concrete plate or the like with ribs is fitted to the inside of the receiving rail 2 to establish it, and the earth and sand are immediately buried in the outer root cutting portion of the scrap frame 6.
【0006】次いで先組した梁部鉄筋すなわち主筋とス
タラップ筋を組立てた地中梁鉄筋篭Cを捨型枠6間に落
し込み、その位置は根切り底のライナー1の鉄筋受部4
によって固定される。なお、地中梁鉄筋篭の落し込みに
際しては捨型枠6の上部の止め金具12は一時的に外し
ておく。Next, the pre-assembled beam reinforcing bar, that is, the underground beam reinforcing bar cage C, in which the main reinforcing bar and the stirrup bar are assembled, is dropped into the scrap frame 6, and the position thereof is the reinforcing bar receiving portion 4 of the liner 1 at the root cutting bottom.
Fixed by. In addition, when the underground beam rebar cage is dropped, the stopper 12 on the upper portion of the scrap frame 6 is temporarily removed.
【0007】次いで、捨型枠6間にコンクリート7を打
設して基礎を完成する。Then, concrete 7 is placed between the scrap frames 6 to complete the foundation.
【0008】なお柱脚部においては杭基礎の上にフーチ
ングコンクリート8を打設し、前記ライナー1の端部は
このフーチングコンクリート8にホールインアンカー9
によって固定され、またこのフーチングコンクリート8
上には先組した柱脚部鉄筋Dを設置する。At the column base, footing concrete 8 is placed on the pile foundation, and the end of the liner 1 is attached to the footing concrete 8 by a hole-in anchor 9.
Fixed by also this footing concrete 8
The column base rebar D assembled in advance is installed above.
【0009】2番目の発明はライナー1の設置までは同
様であるが、次いで先組した柱脚部鉄筋Dをフーチング
コンクリート8上に穿設したアンカーボルト10を覆う
ように設置し、かつライナー1を定規として先組した地
中梁鉄筋篭Cを設置し、地中梁鉄筋篭Cと柱脚部鉄筋D
とはグラウトカップラー11を用いて接続され、次いで
その周囲に捨型枠6を樹立し、の上部を止め金具12で
連結し、その捨型枠6の外側を埋戻し、次いで捨型枠間
にコンクリートを打設する。The second aspect of the invention is the same until the liner 1 is installed. Then, the previously assembled column base rebar D is installed so as to cover the anchor bolt 10 drilled on the footing concrete 8, and the liner 1 is installed. Underground girder rebar cage C is installed with the ruler as a ruler, and underground girder rebar cage C and column base rebar D
And are connected using a grout coupler 11, then a scrap frame 6 is established around the grout coupler 11, the upper part of is connected with a stopper 12, the outside of the scrap frame 6 is backfilled, and then between the scrap frames. Place concrete.
【0010】[0010]
【発明の効果】この発明は以上の構成からなり、捨型枠
が土留矢板を兼ねることになり、根切り後捨型枠を上か
ら落し込んで直ちに埋め戻すものであり、鉄筋を根切り
溝で組立てず、先組して落し込むので根切り幅も鉄筋篭
の接続作業空間を除いて最小限とすることができ根切り
量も少なく、鉄筋の先組と相俟って現場作業の省力化が
著しい。EFFECTS OF THE INVENTION The present invention is constructed as described above, and the scrap frame also serves as the earth retaining sheet pile, and after the root cutting, the scrap frame is dropped from the top and immediately backfilled. Since it is not assembled at first and it is dropped in the first assembly, the root cutting width can be minimized except for the connecting work space of the rebar basket, and the amount of root cutting is also small, and in combination with the front assembly of the reinforcing bar, labor saving on site work The conversion is remarkable.
【図1】第1の発明の実施過程の断面図で(a) は捨型枠
の落し込み状態の断面図である。FIG. 1A is a cross-sectional view of the process of carrying out the first invention, wherein FIG.
【図2】ライナー設置状態の斜視図である。FIG. 2 is a perspective view of a liner installed state.
【図3】鉄筋落し込み状態の拡大断面図である。FIG. 3 is an enlarged cross-sectional view of a state where a reinforcing bar is dropped.
【図4】第1の発明の実施例の施工過程の斜視図であ
る。FIG. 4 is a perspective view of the construction process of the embodiment of the first invention.
【図5】第1の発明の実施例の施工過程の斜視図であ
る。FIG. 5 is a perspective view of the construction process of the embodiment of the first invention.
【図6】第1の発明の実施例の施工過程の斜視図であ
る。FIG. 6 is a perspective view of the construction process of the embodiment of the first invention.
【図7】第1の発明の実施例の施工過程の斜視図であ
る。FIG. 7 is a perspective view of the construction process of the embodiment of the first invention.
【図8】第1の発明の実施例の施工過程の斜視図であ
る。FIG. 8 is a perspective view of the construction process of the embodiment of the first invention.
【図9】第2の発明の実施例の施工過程の斜視図であ
る。FIG. 9 is a perspective view of the construction process of the embodiment of the second invention.
【図10】第2の発明の実施例の施工過程の斜視図であ
る。FIG. 10 is a perspective view of the construction process of the embodiment of the second invention.
【図11】第2の発明の実施例の施工過程の斜視図であ
る。FIG. 11 is a perspective view of the construction process of the embodiment of the second invention.
【図12】第2の発明の実施例の施工過程の斜視図であ
る。FIG. 12 is a perspective view of the construction process of the embodiment of the second invention.
【符号の説明】 A…地盤、B…根切り、C…地中梁鉄筋篭、D…柱脚部
鉄筋 1…ライナー、2…受レール、3…連結材、4…鉄筋受
部、5…立上り部、6…捨型枠、7…コンクリート、8
…フーチングコンクリート、9…ホールインアンカー、
10…アンカーボルト、11…カップラー、12…止め
金具。[Explanation of Codes] A ... Ground, B ... Root Cutting, C ... Underground Beam Reinforcement Basket, D ... Column Base Reinforcing Bar 1 ... Liner, 2 ... Receiving Rail, 3 ... Connecting Material, 4 ... Reinforcing Bar Receiving Section, 5 ... Rise, 6 ... Waste form, 7 ... Concrete, 8
… Footing concrete, 9… Hole-in anchor,
10 ... Anchor bolt, 11 ... Coupler, 12 ... Stopper.
Claims (2)
底にライナーを設置し、ライナーを定規として捨型枠を
樹立して、捨型枠の外側を埋戻し、次いで捨型枠間に先
組した鉄筋を落し込みによって設置し、次いで捨型枠間
にコンクリートを打設することを特徴とする基礎の施工
方法。1. A root is cut to a predetermined depth in the ground, a liner is installed on the root cutting bottom, a liner is used as a ruler to establish a scrap frame, the outside of the scrap frame is backfilled, and then the scrap frame. A method of constructing a foundation, characterized by placing rebars assembled in the interim by dropping and then placing concrete between the scrap frames.
底にライナーを設置し、先組した柱脚鉄筋を基礎上に設
置するとともにライナーを定規として先組した地中梁鉄
筋を設置し、柱脚部鉄筋および地中梁鉄筋の周囲に捨型
枠を樹立し、捨型枠の外側を埋戻し、次いで捨型枠間に
コンクリートを打設することを特徴とする基礎の施工
法。2. The ground is cut to a predetermined depth, a liner is installed at the root cutting bottom, the pre-assembled column base rebar is installed on the foundation, and the pre-assembled underground beam rebar is used as a ruler. Installation, construction of a scrap frame around the column base rebar and underground beam rebar, backfilling the outside of the scrap frame, then placing concrete between the scrap frames Law.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27528591A JPH05112949A (en) | 1991-10-23 | 1991-10-23 | Execution method of foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27528591A JPH05112949A (en) | 1991-10-23 | 1991-10-23 | Execution method of foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05112949A true JPH05112949A (en) | 1993-05-07 |
Family
ID=17553297
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP27528591A Withdrawn JPH05112949A (en) | 1991-10-23 | 1991-10-23 | Execution method of foundation |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05112949A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06330530A (en) * | 1993-05-21 | 1994-11-29 | Mitsui Home Co Ltd | Construction method of housing strip footing |
JP2012077575A (en) * | 2010-10-06 | 2012-04-19 | Kumagai Gumi Co Ltd | Construction method for revetment |
-
1991
- 1991-10-23 JP JP27528591A patent/JPH05112949A/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06330530A (en) * | 1993-05-21 | 1994-11-29 | Mitsui Home Co Ltd | Construction method of housing strip footing |
JP2012077575A (en) * | 2010-10-06 | 2012-04-19 | Kumagai Gumi Co Ltd | Construction method for revetment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0151626B1 (en) | Procedure for making foundations for a structure, and intermediate piece for use in the procedure | |
JPH05112949A (en) | Execution method of foundation | |
JPH0684690B2 (en) | Building basement extension method | |
JPH0657768A (en) | Retaining wall structure and its construction method | |
JPH10299003A (en) | Foundation method using precast concrete members | |
KR101809554B1 (en) | Structure using key-block and sheetfile | |
JPH05112948A (en) | Permanent form and foundation execution method using it | |
JPS59192145A (en) | Fixing of iron pillar | |
JPH0711630A (en) | Precast prestressed concrete plate wall combined underground continuous wall method | |
JPS6350491B2 (en) | ||
JPH07103583B2 (en) | Construction method for large span underground structure | |
JPH0467533B2 (en) | ||
JP2877881B2 (en) | How to build a reinforced concrete basement | |
JPH04111813A (en) | Retaining wall structure and its construction | |
JP3108112B2 (en) | Foundation structure | |
KR0165582B1 (en) | Construction of the precast concrete wall | |
JP2506978Y2 (en) | Synthetic retaining wall | |
JPH02248527A (en) | Constructing foundation structure | |
JP3002026B2 (en) | Structure of residential continuous foundation | |
JPH06193084A (en) | Construction method for undeground structure | |
JP2643760B2 (en) | How to build foundation beams | |
JPS62111028A (en) | Construction of underground structure | |
JPS6138028A (en) | Construction of foundation | |
JPH0374725B2 (en) | ||
JPH0748848A (en) | Construction method of underground skeleton by reverse construction method |