JPH0470424A - Lift-down underground structure construction method - Google Patents
Lift-down underground structure construction methodInfo
- Publication number
- JPH0470424A JPH0470424A JP2182220A JP18222090A JPH0470424A JP H0470424 A JPH0470424 A JP H0470424A JP 2182220 A JP2182220 A JP 2182220A JP 18222090 A JP18222090 A JP 18222090A JP H0470424 A JPH0470424 A JP H0470424A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- underground
- basement
- lift
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 25
- 238000009434 installation Methods 0.000 claims description 10
- 238000009412 basement excavation Methods 0.000 description 13
- 238000000034 method Methods 0.000 description 11
- 239000004567 concrete Substances 0.000 description 7
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000011150 reinforced concrete Substances 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 239000002184 metal Substances 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000007599 discharging Methods 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 239000004035 construction material Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009408 flooring Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は建物の地下階を構築する為に開発されたリフ
トダウン地下躯体工法に関するものである。[Detailed Description of the Invention] [Industrial Field of Application] This invention relates to a lift-down underground framework construction method developed for constructing underground floors of buildings.
都心部に建つたいていの建物には、1乃至2階程度の地
下室が設けられているが、近年の地価高騰に伴い、限ら
れた建築面積に於いて可能な限り床面積を広く確保する
為、地下部分をもっと有効に利用したいとの要請が高い
。Most buildings built in the city center have a basement of about 1 or 2 floors, but due to the recent rise in land prices, in order to secure as much floor space as possible within the limited building area, There is a strong demand for more effective use of underground areas.
この為、もはや地下2階程度では充分な地下利用は図れ
ず、最近では5階程度の地下室も建設されるようになっ
てきている。For this reason, it is no longer possible to achieve sufficient underground utilization with only two floors underground, and recently, basements with about five floors are being constructed.
しかし、地下工事は地盤面下の工事である為、工期の長
期化が免れないだけでなく、地上階の工事に較べて工事
費が嵩み、しかも安全性についても充分配慮する必要が
ある。However, since underground construction is carried out below the ground surface, it not only inevitably takes a long time, but also costs more than ground floor construction, and it is also necessary to give due consideration to safety.
この発明はこのような事情に鑑みて提案されたもので、
前記3つの課題の解決を可能にしたリフトダウン地下躯
体工法を提供することを目的とするものである。This invention was proposed in view of these circumstances.
The object of the present invention is to provide a lift-down underground structure construction method that makes it possible to solve the above three problems.
前記目的を達成する為に、この発明にかかるリフトダウ
ン地下躯体工法は構築しようとする地下階の外周に地中
連続壁を構築し、続いて当該地中連続壁の内側に地下階
の柱を構築し、続いて地上に於いて地下階の各階の床ス
ラブを構築し、続いて前記地中連続壁によって囲まれた
地盤面以下の部分を掘削しつつ前記床スラブをリフトダ
ウンし、且つ各階の床スラブ設置位置に前記地中連続壁
及び柱に固定して設置する。In order to achieve the above object, the lift-down underground framework construction method according to the present invention constructs an underground continuous wall around the outer periphery of the underground floor to be constructed, and then installs columns for the underground floor inside the underground continuous wall. Then, the floor slabs for each basement floor are constructed above ground, and the floor slabs are lifted down while excavating the area below the ground level surrounded by the underground continuous wall, and each floor The floor slab is installed at the location where the floor slab is installed, fixed to the underground continuous wall and columns.
また、構築しようとする地下階の外周に地中連続壁を構
築し、続いて地上に於いて地下階の全階にわたる躯体を
構築し、続いて前記地中連続壁によって囲まれた地盤面
以下の部分を、いわゆる水中掘削しつつ前記地下階全階
の躯体をリフトダウンしてもよい。In addition, a continuous underground wall is constructed around the outer periphery of the basement floor to be constructed, and then a framework covering all floors of the basement floor is constructed above ground, and then the ground level below the ground level surrounded by the continuous underground wall is constructed. The entire basement floor structure may be lifted down while the section is excavated underwater.
以下、この発明にかかるリフトダウン躯体工法を図示す
る一実施例に基づいて順を追って説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a lift-down frame construction method according to the present invention will be explained in order based on an embodiment illustrating the method.
■(地中連続壁の施工)
地中連続壁1は建物の規模等によって異なるが、現場打
ち鉄筋コンクリート若しくはPCコンクリート板等によ
って、構築しよとする建物の地下階の外周に構築する(
第1図及び第2図参照)。■(Construction of an underground continuous wall) The underground continuous wall 1 is constructed around the outer periphery of the basement floor of the building to be constructed using cast-in-place reinforced concrete or PC concrete boards, etc., although it differs depending on the scale of the building etc.
(See Figures 1 and 2).
また、地中連続壁1は地盤面より最下階の基礎部分まで
連続して構築する。Further, the underground continuous wall 1 is constructed continuously from the ground level to the foundation of the lowest floor.
■(柱の施工)
柱2は地中連続壁1によって囲まれた敷地内の当初より
定められた位置に、地下階の全階にわたって構築し、必
要により地中連続壁1の直ぐ内側にもこれに添え付けて
構築する(第1図及び第2図参照)。■(Column construction) Pillars 2 will be constructed at the predetermined location within the site surrounded by the underground continuous wall 1, spanning all floors of the underground floor, and if necessary, installed directly inside the underground continuous wall 1. It is constructed in addition to this (see Figures 1 and 2).
また、柱2は建物の規模等によっても異なるが、鉄筋コ
ンクリート、鉄骨、鉄骨鉄筋コンクリート若しくは鉄骨
コンクリート等によって構築するものとし、その断面形
状も図示するような十字形断面形の他に矩形断面や円形
断面形に構築するものとする(第1図及び第3図参照)
。Column 2 is constructed of reinforced concrete, steel frame, steel reinforced concrete, steel frame concrete, etc., depending on the scale of the building, etc., and its cross-sectional shape may be rectangular or circular in addition to the cruciform cross-sectional shape shown in the figure. (See Figures 1 and 3)
.
■(床スラブの施工)
床スラブは地中連続壁1内の地盤面上に於いて、地下階
の階数に応じて各階の床スラブ3.4,5.6を個々に
構築する。(Construction of floor slabs) Floor slabs 3.4 and 5.6 for each floor are individually constructed on the ground surface within the underground continuous wall 1 according to the number of basement floors.
床スラブ3,4,5,6.は建物の規模等によっても異
なるが、PCコンクリート板若しくは現場打ちコンクリ
ート等によって構築する。Floor slabs 3, 4, 5, 6. Although it varies depending on the scale of the building, etc., it is constructed using PC concrete boards or cast-in-place concrete.
また、床面積が相当大きいときは、適当な位置に鉄骨梁
やPC梁若しくは鉄筋コンクリド梁等の梁7を設ける(
第5図及び第9図参照)。In addition, if the floor area is quite large, install beams 7 such as steel beams, PC beams, or reinforced concrete beams at appropriate positions (
(See Figures 5 and 9).
■(地盤の掘削)
掘削は従来一般に広く行われている掘削工法によって行
うものとし、床スラブ3.4,5.6直下の地盤を全体
に平均して徐々に掘り進めるものとする(第2図参照)
、。■ (Excavation of the ground) Excavation shall be carried out using the conventionally widely used excavation method, and the ground immediately below floor slabs 3.4 and 5.6 shall be dug gradually over the entire area (2nd (see figure)
,.
なお、床スラブ3,4,5.6には、地盤掘削の際に機
材を搬入したり、掘削土を排出する為の出入り口8を数
箇所設けておくものとする(第1図参照)。Note that the floor slabs 3, 4, 5.6 are provided with several entrances and exits 8 for carrying in equipment during ground excavation and for discharging excavated soil (see Figure 1).
■(床スラブのリフトダウン)
床スラブ3,4,5.6のリフトダウンは地盤の掘削に
並行して行うものとする(第2図参照)。■(Lift-down of floor slabs) Lift-down of floor slabs 3, 4, 5.6 shall be carried out in parallel with the excavation of the ground (see Figure 2).
作業には複数台のジヤツキ9と複数本のロッド10を使
用する(第6図及び第7図参照)。A plurality of jacks 9 and a plurality of rods 10 are used for the work (see FIGS. 6 and 7).
ジャ・7キ9は地上1階の床部分に地中連続壁1及び柱
2を支持部として縦横に架設された受は梁11の上にこ
れと略直角に受は台12をのせ、当該受は台12の両側
に設置する(第6図及び第7図参照)。Ja-7ki 9 is constructed vertically and horizontally on the floor of the first floor above ground using underground continuous walls 1 and pillars 2 as supporting parts, and a platform 12 is placed on top of the beam 11 at approximately right angles thereto. The receivers are installed on both sides of the stand 12 (see Figures 6 and 7).
また、ロッド10.10は左右ジヤツキ99にそれぞれ
連結し、当該ロッド10.10の下端部にブラケット1
3を水平に取り付ける。Further, the rod 10.10 is connected to the left and right jacks 99, respectively, and a bracket 1 is attached to the lower end of the rod 10.10.
Install 3 horizontally.
そして、ブラケット13の上に床スラブ3,4゜5.6
を重ねて載せ吊り下げる。Then, on top of the bracket 13, the floor slab 3,4°5.6
Lay them on top of each other and hang them.
なお、ジヤツキ9及びロッド10の数及び設置場所は、
床スラブ3,4.5.6の大きさ及び重量に基づいて適
当に決めるものとする。In addition, the number and installation location of jacks 9 and rods 10 are as follows:
It shall be determined appropriately based on the size and weight of the floor slabs 3, 4, 5, 6.
このような構成に於いて、ジヤツキ9,9を操作して床
スラブ3,4,5.6を地下−階の床スラブ設置位置ま
で徐々にリフトダウンし、地下−階の床すらぶ設置位置
に達したら、−時停止する。In such a configuration, by operating the jacks 9, 9, the floor slabs 3, 4, 5.6 are gradually lifted down to the installation position of the floor slab between basement and floor, and the installation position where even the floor between basement and floor is installed. When it reaches -, stop.
そして、地下−階の床スラブ3を地中連続壁1及び柱2
の側面部に一体的に接合する。Then, the floor slab 3 of the basement floor is connected to the underground continuous wall 1 and the pillars 2.
It is integrally joined to the side part of.
床スラブ3の接合が完了したら、再び掘削を開始すると
共に床スラブ3を除く他の床スラブ4,5.6を地下二
階の床スラブ設置位置まで徐々にリフトダウンする(第
2図参照)。When the joining of the floor slabs 3 is completed, excavation is started again and the other floor slabs 4, 5, 6 except the floor slab 3 are gradually lifted down to the floor slab installation position on the second basement floor (see Fig. 2).
地下二階の床スラブ設置位置に達したら、−時停止し、
今度は床スラブ4を地中連続壁1及び柱2の側部に一体
的に接合する。When you reach the floor slab installation position on the second basement floor, stop at -
Next, the floor slab 4 is integrally joined to the sides of the underground continuous wall 1 and the columns 2.
以下、同様にして床スラブ5及び6を掘削と並行して徐
々にリフトダウンし、地下三階及び四階の床スラブ設置
位置ににそれぞれ接合する。Thereafter, in the same manner, the floor slabs 5 and 6 are gradually lifted down in parallel with the excavation and joined to the floor slab installation positions on the third and fourth basement floors, respectively.
各階の床スラブ3,4,5.6と地中連続壁lとの接合
は、第3図及び第4図に図示する方法によって行う。The floor slabs 3, 4, 5.6 of each floor and the underground continuous walls 1 are joined by the method shown in FIGS. 3 and 4.
その詳細を説明すると地中連続壁1の内側に鉄筋コンク
リート若しくは鉄骨鉄筋コンクリート等からなる受は梁
14を地中連続壁1の周方向に水平連続して構築し、一
方法スラブ3.4.5.6の周縁部には凹凸状のコツタ
ー15を形成する。To explain the details, a support beam 14 made of reinforced concrete or steel reinforced concrete is constructed horizontally and continuously in the circumferential direction of the underground continuous wall 1, and one method slab 3.4.5. A concave and convex shaped cotter 15 is formed on the peripheral edge of 6.
そして、各階の床スラブ3,4,5.6の周縁部を受は
梁14の上に載せ、且つ地中連続壁1−&床スラブ3,
4,5.6との間にコンクリート16を充填することに
より一体化する。Then, the peripheral edges of the floor slabs 3, 4, 5.6 of each floor are placed on the support beams 14, and the underground continuous wall 1-&floor slab 3,
4, 5.6 are integrated by filling concrete 16 between them.
また、各階の床スラブ3,4,5.6と柱2との接合は
、第3図及び第4図に図示するような方法によって接合
する。Further, the floor slabs 3, 4, 5.6 of each floor and the columns 2 are joined by the method shown in FIGS. 3 and 4.
その詳細を説明すると、各柱2の側部にブラケット17
を突設し、一方各階の床スラブ3゜4.5.6の端部に
接合金具18を突設する。To explain the details, a bracket 17 is attached to the side of each pillar 2.
A joint fitting 18 is protruded from the end of the floor slab 3°4.5.6 on each floor.
そして、各階の床スラブ3,4,5.6をブラケット1
7の上に載せ、且つ接合金具18をブラケット17に溶
接着しくはボルト止め等して一体的に接合する。Then, attach the floor slabs 3, 4, 5.6 of each floor to the bracket 1.
7, and the joining fitting 18 is integrally joined to the bracket 17 by welding or bolting.
他の方法としては、ブラケッ1−17を省略し、床スラ
ブの端部にシアポル1−19を突設し、当該シアボルト
19を梁7に固定ナツト20で固定してもよい(第8図
参照)。As another method, the bracket 1-17 may be omitted, the shear bolt 1-19 may be provided protruding from the end of the floor slab, and the shear bolt 19 may be fixed to the beam 7 with the fixing nut 20 (see Fig. 8). ).
床スラブに梁7が設けである場合には、第5図及び第9
図に図示するような方法によって接合するものとし、梁
7を地中連続壁1及び柱2の側面部に接合する。If the floor slab is provided with beams 7, please refer to Figures 5 and 9.
The beams 7 are joined to the side surfaces of the underground continuous walls 1 and columns 2 by the method shown in the figure.
その詳細を説明すると、図は柱2及び梁7共に鉄骨材か
らなる場合の接合方法を示したものであるが、柱2の側
面部に接合金具21をボルト止めして突設し、当該接合
金具21に梁7の端部をボルト止めすることにより接合
する。To explain the details, the figure shows a joining method when both the column 2 and the beam 7 are made of steel frame materials. The ends of the beams 7 are connected to the metal fittings 21 by bolting them.
第10図乃至第15図は他の施工方法を示すもので、以
下その施工方法を順を追って説明する。FIGS. 10 to 15 show another construction method, which will be explained step by step below.
■ まず、先の施工方法と全く同様に地中連続壁1を構
築する(第1O図参照)。■ First, construct the underground continuous wall 1 in exactly the same manner as the previous construction method (see Figure 1O).
■ 続いて、地中連続壁Iで囲まれた地盤面上に於いて
、地下階全階の躯体を構築する。■ Next, the framework for all basement floors will be constructed on the ground surface surrounded by underground walls I.
図中、番号2は柱、番号3,4.5は各階の床スラブ、
番号22は外壁、そして番号23は基礎である。In the diagram, number 2 is the pillar, number 3, 4.5 is the floor slab of each floor,
Number 22 is the outer wall, and number 23 is the foundation.
■ 続いて、今構築した地下階全階の躯体直下の地盤面
以下の部分を全体にわたって排水することなしに、いわ
ゆる水中掘削により徐々に掘削する。■Next, we will gradually excavate all of the basement floors just constructed below the ground level directly under the frame using what is called underwater excavation, without draining the entire area.
地盤の掘削は主にジェット噴流水によって行うもめとし
、掘削土の排土は浚渫によって行うものとする。Excavation of the ground will be carried out mainly by jet water, and excavated soil will be removed by dredging.
また、常時地盤面まで水をはって地中連続壁1が掘削側
へ傾斜しないように注意する(第14図参照)。Also, be careful not to incline the diaphragm wall 1 toward the excavation side by constantly pouring water up to the ground level (see Figure 14).
この掘削作業と並行して地下階全階をリフトダウンする
。In parallel with this excavation work, all basement floors will be lifted down.
地下階のリフトダウンには、先の施工方法と同様に複数
台のジヤツキ9と複数本のロッド10を使用する。To lift down the basement floor, a plurality of jacks 9 and a plurality of rods 10 are used as in the previous construction method.
ジヤツキ9は地中連続壁1の上端部に設置された受は台
12の上に設置し、ロッド10はジヤツキ9に連結する
。The jack 9 is installed at the upper end of the underground continuous wall 1 on a stand 12, and the rod 10 is connected to the jack 9.
また、地下階の下端部にブラケット13を水平に突設し
、このブラケットI3にロッド10の下端部を連結して
地下階全体を吊るす。Further, a bracket 13 is horizontally protruded from the lower end of the basement floor, and the lower end of the rod 10 is connected to this bracket I3 to suspend the entire basement floor.
なお、ジヤツキ9及びロッド10の数及び設置場所は、
床スラブ3,4,5.6の大きさ及び重量等に基づいて
適当に決めるものとする(第14図参照)。In addition, the number and installation location of jacks 9 and rods 10 are as follows:
It shall be determined appropriately based on the size and weight of the floor slabs 3, 4, 5, 6 (see Fig. 14).
このような構成に於いて、ジヤツキ9.9を操作して地
下部分を徐々にリフトダウンし、地盤面下に完全に沈め
る。In such a configuration, the underground portion is gradually lifted down by operating the jack 9.9 until it is completely submerged below the ground surface.
地下階の設置が完了したら地下階の周辺部及び基礎スラ
ブの下側にコンクリート等のグラウト材を充填すること
より地下階を地盤中に完全に固定する。Once the basement floor installation is complete, the basement floor is completely fixed into the ground by filling the surrounding area of the basement floor and the underside of the foundation slab with grouting material such as concrete.
沈設後の地下階の碇着(位置決めも含む)の調整方法と
しては、地中連続壁を反力としてワイヤーによって行う
か、エアバックによる浮力によって行うか、或いは碇着
部をコラムジェット等によってテーブル状に整地する方
法が考えられる。The method of adjusting the anchorage (including positioning) on the basement floor after the underground floor is submerged is to use a wire using the underground continuous wall as a reaction force, to use the buoyancy of an air bag, or to adjust the anchorage to a table using a column jet, etc. One possible method is to level the ground in a shape.
そして、前記グラウト材が充分な強度を発現したら排水
する。Then, when the grout material has developed sufficient strength, it is drained.
なお、基礎スラブ23には先の施工方法と同様に地盤掘
削の際に機材を搬入したり掘削土を排出する為の出入り
口8を、数箇所設けておくものとする。Note that, similar to the previous construction method, the foundation slab 23 is provided with several entrances and exits 8 for carrying in equipment and discharging excavated soil during ground excavation.
また、地下階の外周には地下部分が水平状態でスムーズ
に降下できるようにガイドローラ24を設けておくもの
とする。Further, guide rollers 24 are provided around the outer periphery of the basement floor so that the underground portion can descend smoothly in a horizontal state.
■ 地下部分の各階の床スラブ若しくは床スラブ及びそ
の梁を全て地上に於いて構築する為、品質、安全生及び
作業能率の大幅な向上が図れる。■ Since the floor slabs or floor slabs and their beams for each floor of the underground section are all constructed above ground, quality, safety and work efficiency can be significantly improved.
■ 各階の床スラブは施工途中においては、切り梁、腹
起こし等の山止め材として兼用される為、従来必要であ
った切り梁、腹起こし等の山止め材及びこれらの組み立
てが一切不要になり仮設資材費の低減化及び工期の短縮
化が可能である。■ During construction, the floor slabs on each floor are also used as pile-stopping materials for cut beams, raised-backs, etc., so there is no need for the conventionally required pile-stopping materials such as beam-cut beams, raised-backs, etc., and their assembly. Therefore, it is possible to reduce the cost of temporary construction materials and shorten the construction period.
■ 地下工事の初期の段階から地上階の工事も並行して
行うことができる為、全体工事の工期の短縮化も図れる
。■ Since ground floor construction can be carried out in parallel from the initial stage of underground construction, the overall construction period can be shortened.
■ さらに、床付は面に予め地盤改良を施し、止水する
ことにより地下掘削時の水処理が極めて容易となり、作
業能率及び安全生の向上が図れる。■Furthermore, by pre-improving the ground on the surface of the flooring and stopping water, water treatment during underground excavation becomes extremely easy, improving work efficiency and safety.
第1図〜第9図は請求項第1項記載の発明の一実施例を
示すもので、第1図は建物の地下階部分の平面図、第2
図はその施工途中の縦断面図、第3図は地下階部分の一
部拡大平面図、第4図及び第5図はその縦断面図、第6
図は施工途中の地下階部分の平面図、第7図はその一部
拡大側面図、第8図及び第9図は床スラブと柱との接合
部の平面図、第10図〜第15図は請求項第2項記載の
発明の一実施例を示すもので、第10図〜第13図はそ
の施工方法を示す工程図、第14図は地下階躯体の一部
縦断面図、第15図はその平面図である。
l・・・地中連続壁、2・・・柱、
3.4,5.6・・・床スラブ、7・・・梁、8・・・
出入り口、9・・・ジヤツキ、lO・・・口、ド、11
・・・受は梁、12・・・受は台、13・・・ブラケ、
7ト、I4・・・受は梁、15・・・コック
16・・・コンクリート、I7・・・ブラケット、18
・・・接合金具、19・・・シアボルト、20・・・固
定ナンド、21・・・接合金具、22・・・外壁、23
・・・基礎、24・・・ガイドローラ。
(′r′)ぐ
第
図
第14
図
n
第
図
第
図
第15
図
第
]]
図1 to 9 show an embodiment of the invention as claimed in claim 1, in which FIG. 1 is a plan view of the basement floor of a building;
The figure is a vertical cross-sectional view during construction, Figure 3 is a partially enlarged plan view of the basement floor, Figures 4 and 5 are vertical cross-sectional views, and Figure 6 is a vertical cross-sectional view of the construction.
The figure is a plan view of the basement floor part under construction, Figure 7 is a partially enlarged side view, Figures 8 and 9 are plan views of the joint between the floor slab and columns, and Figures 10 to 15. 10 to 13 are process diagrams showing the construction method, FIG. 14 is a vertical cross-sectional view of a part of the basement floor structure, and FIG. The figure is a plan view thereof. l... Underground continuous wall, 2... Column, 3.4, 5.6... Floor slab, 7... Beam, 8...
Entrance/exit, 9...jazz, lO...mouth, de, 11
...The receiver is a beam, 12...The receiver is a stand, 13...The bracket,
7, I4...The support is a beam, 15...Cock 16...Concrete, I7...Bracket, 18
...Joining metal fitting, 19... Shear bolt, 20... Fixed nand, 21... Joining metal fitting, 22... Outer wall, 23
...Basic, 24...Guide roller. ('r') Figure 14 Figure n Figure Figure 15 Figure]] Figure
Claims (2)
築し、続いて当該地中連続壁の内側に地下階の柱を構築
し、続いて地上に於いて地下階の各階の床スラブを構築
し、続いて前記地中連続壁によって囲まれた地盤面以下
の部分を掘削しつつ前記床スラブをリフトダウンし、且
つ各階の床スラブ設置位置に前記地中連続壁及び柱に固
定して設置することを特徴とするリフトダウン地下躯体
工法。(1) Construct an underground continuous wall around the outer periphery of the underground floor to be constructed, then construct columns for the underground floor inside the underground continuous wall, and then construct the floors of each basement floor above ground. Construct a slab, then lift down the floor slab while excavating the area below the ground surface surrounded by the underground continuous wall, and fix it to the underground continuous wall and columns at the floor slab installation position of each floor. A lift-down underground structure construction method characterized by installation.
築し、続いて地上に於いて地下階の全階にわたる躯体を
構築し、続いて前記地中連続壁によって囲まれた地盤面
以下の部分を、水中掘削しつつ前記地下階の全階をリフ
トダウンすることを特徴とするリフトダウン地下躯体工
法。(2) Construct a continuous underground wall around the outer periphery of the underground floor to be constructed, then construct a frame that spans all floors of the underground floor above ground, and then build the ground surface surrounded by the continuous underground wall. A lift-down underground structure construction method characterized by lifting down all floors of the basement floor while excavating the following parts underwater.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2182220A JP2536249B2 (en) | 1990-07-10 | 1990-07-10 | Lift-down underground structure construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2182220A JP2536249B2 (en) | 1990-07-10 | 1990-07-10 | Lift-down underground structure construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0470424A true JPH0470424A (en) | 1992-03-05 |
JP2536249B2 JP2536249B2 (en) | 1996-09-18 |
Family
ID=16114447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2182220A Expired - Lifetime JP2536249B2 (en) | 1990-07-10 | 1990-07-10 | Lift-down underground structure construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2536249B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6981824B2 (en) * | 2003-01-21 | 2006-01-03 | David Zingerman | Sling-traverse device for massive object lifting system |
JP2022528743A (en) * | 2019-04-04 | 2022-06-15 | 延煦 ▲問▼ | Wall subsidence construction method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101044443B1 (en) | 2009-03-05 | 2011-06-27 | 이예리 | Slab hoisting device for reverse construction of underground structure |
KR101044441B1 (en) | 2009-03-05 | 2011-06-27 | 이예리 | Reverse construction method of underground structure |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS59114336A (en) * | 1982-12-22 | 1984-07-02 | Taisei Corp | How to build underground structures |
JPS6272822A (en) * | 1985-09-24 | 1987-04-03 | Kajima Corp | Construction method for underground structures |
JPH01322045A (en) * | 1988-06-24 | 1989-12-27 | Shimizu Corp | How to build a basement |
-
1990
- 1990-07-10 JP JP2182220A patent/JP2536249B2/en not_active Expired - Lifetime
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS59114336A (en) * | 1982-12-22 | 1984-07-02 | Taisei Corp | How to build underground structures |
JPS6272822A (en) * | 1985-09-24 | 1987-04-03 | Kajima Corp | Construction method for underground structures |
JPH01322045A (en) * | 1988-06-24 | 1989-12-27 | Shimizu Corp | How to build a basement |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6981824B2 (en) * | 2003-01-21 | 2006-01-03 | David Zingerman | Sling-traverse device for massive object lifting system |
JP2022528743A (en) * | 2019-04-04 | 2022-06-15 | 延煦 ▲問▼ | Wall subsidence construction method |
Also Published As
Publication number | Publication date |
---|---|
JP2536249B2 (en) | 1996-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2000054409A (en) | Work execution method of top-down construction stanchion in underground excavated space peripheral part | |
JPH102126A (en) | Seismic isolated building | |
JP5977412B2 (en) | Basement of new building using existing building | |
JPH0470424A (en) | Lift-down underground structure construction method | |
JP4550534B2 (en) | Building basic structure | |
KR100967496B1 (en) | Device for constructing an underground structure | |
JP3641227B2 (en) | Construction method of underground structure | |
JPH0684690B2 (en) | Building basement extension method | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
RU190322U1 (en) | Device for the construction of multi-storey underground structures | |
JP5506057B2 (en) | Building construction method | |
KR100593203B1 (en) | Construction method of underground structure using deck support frame for side pressure support formation and deck support frame for side pressure support formation | |
JP2000297476A (en) | How to build a dome structure | |
KR100679986B1 (en) | Installation structure of suspension type support girders for flat plate deck installation and reverse casting method using the same | |
JP2016098531A (en) | Temporary support method | |
JP2894217B2 (en) | Building structural frame | |
JPH10237886A (en) | Method for constructing underground tank | |
KR200369485Y1 (en) | a deck supportframe | |
JPH0657769A (en) | Underground structure and its construction method | |
JP2761528B2 (en) | How to build structures | |
JP2508931B2 (en) | Lift slab method | |
JP2025007140A (en) | Deck retaining structure and method | |
RU2052052C1 (en) | Method for installing floors in many-storied blocks of flats by lifting | |
JPH0874278A (en) | Construction method for large underground space | |
JP2022111553A (en) | Architectural structure |