JPH04323445A - Structure of joint part of concrete filling steel pipe column and flat slab - Google Patents
Structure of joint part of concrete filling steel pipe column and flat slabInfo
- Publication number
- JPH04323445A JPH04323445A JP11676191A JP11676191A JPH04323445A JP H04323445 A JPH04323445 A JP H04323445A JP 11676191 A JP11676191 A JP 11676191A JP 11676191 A JP11676191 A JP 11676191A JP H04323445 A JPH04323445 A JP H04323445A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- column
- flat slab
- concrete
- floor side
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 81
- 239000010959 steel Substances 0.000 title claims abstract description 81
- 238000009415 formwork Methods 0.000 claims abstract description 5
- 230000003014 reinforcing effect Effects 0.000 claims description 12
- 238000000465 moulding Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 5
- 230000005540 biological transmission Effects 0.000 abstract description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 3
- 230000002349 favourable effect Effects 0.000 abstract 1
- 238000009434 installation Methods 0.000 abstract 1
- 239000003351 stiffener Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
【0001】0001
【産業上の利用分野】本発明は、コンクリート充填鋼管
柱を階毎に分断使用した建造物におけるフラットスラブ
と、各コンクリート充填鋼管柱との接合部の構造に関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the structure of a joint between a flat slab and each concrete-filled steel pipe column in a building in which concrete-filled steel pipe columns are divided into floors.
【0002】0002
【従来の技術】コンクリート充填鋼管柱を上下階にわた
る通し柱の形で使用した建造物は既に知られている。BACKGROUND OF THE INVENTION Buildings are already known in which concrete-filled steel pipe columns are used in the form of columns extending over upper and lower floors.
【0003】このコンクリート充填鋼管柱の耐力強度は
、鋼管に対するコンクリートの充填性状に大きく影響さ
れるのであるが、コンクリート充填鋼管柱では、コンク
リート被覆形鋼管柱とは異なり、コンクリートの充填状
況を全長さわたって目視確認することが困難であり、通
し柱として長尺の鋼管を使用する時には、この困難性が
一層増大するため、コンクリート充填鋼管柱の耐力強度
の信頼性を高めるのは容易でない。The yield strength of this concrete-filled steel pipe column is greatly influenced by the filling properties of the concrete in the steel pipe, but unlike concrete-coated steel pipe columns, the concrete filling condition cannot be checked over the entire length of the concrete-filled steel pipe column. It is difficult to visually check the concrete-filled steel pipe columns, and this difficulty increases even more when long steel pipes are used as the through-pillars. Therefore, it is not easy to increase the reliability of the bearing strength of concrete-filled steel pipe columns.
【0004】また、この種建造物の柱梁接合部では、コ
ンクリート充填鋼管柱と鉄骨梁フランジ間の応力伝達の
ために、鋼管の途中の外側壁にスチフナリングを溶接し
ているが、このスチフナリングを所定位置に的確に取付
けるには、相応の熟練技能と手間労力を必要とする。[0004] Furthermore, in the column-beam joints of this type of building, a stiffener ring is welded to the outside wall of the steel pipe in the middle of the steel pipe in order to transmit stress between the concrete-filled steel pipe column and the steel beam flange. Accurately attaching the ring to a predetermined position requires considerable skill and effort.
【0005】[0005]
【発明が解決しようとする課題】従って本発明の目的は
、鋼管に対するコンクリートの充填性が良いため、コン
クリート充填鋼管柱の耐力強度の信頼性を容易に高めら
れると共に、コンクリート充填鋼管柱とスラブ間の応力
伝達手段として前記スチフナリングのように取付け施工
が面倒な部材を特に使用しないため、施工が簡略化され
る、コンクリート充填鋼管柱とフラットスラブの接合部
の構造を提供することである。SUMMARY OF THE INVENTION Therefore, an object of the present invention is to easily increase the reliability of the bearing strength of a concrete-filled steel pipe column, and to improve the reliability of the bearing strength of a concrete-filled steel pipe column because the concrete fills the steel pipe well. To provide a structure of a joint between a concrete-filled steel pipe column and a flat slab, which simplifies construction because members such as the stiffener ring, which are difficult to install, are not used as stress transmission means.
【0006】[0006]
【課題を解決するための手段】以下、添付図面中の参照
符号を用いて説明すると、本発明の構造では、上下端外
周の水平なコネクタフランジ2,3に垂直孔4,5を相
対応して設けた鋼管1を柱構成用鋼管として用い、下階
側の柱構成用鋼管1の上位コネクタフランジ2の上面側
に、フラットスラブ用鉄筋組立体8を配置し、上位コネ
クタフランジ2の垂直孔4よりアンカーボルト9を該鉄
筋組立体8に挿通し、鉄筋組立体8を埋め込むようにフ
ラットスラブ成形用型枠10と該鋼管1内にコンクリー
ト11を打設して、上階側のフラットスラブ12と下階
側のコンクリート充填鋼管柱6を造る。[Means for Solving the Problems] In the structure of the present invention, vertical holes 4 and 5 are made to correspond to horizontal connector flanges 2 and 3 on the outer periphery of the upper and lower ends. Using the steel pipe 1 provided as a column-forming steel pipe, a flat slab reinforcing bar assembly 8 is placed on the upper surface side of the upper connector flange 2 of the column-forming steel pipe 1 on the lower floor, and the vertical hole of the upper connector flange 2 is 4, insert the anchor bolts 9 into the reinforcing bar assembly 8, and pour concrete 11 into the flat slab molding form 10 and the steel pipe 1 so as to embed the reinforcing bar assembly 8, and form the flat slab on the upper floor side. 12 and concrete-filled steel pipe columns 6 on the lower floor side.
【0007】該上階側のフラットスラブ12より突出し
たアンカーボルト9の上端部を、上階側の柱構成用鋼管
1の下位コネクタフランジ3の垂直孔5に挿通して、該
上階側の鋼管1を上階側のフラットスラブ12に建て上
げ、アンカーボルト9に螺合したナット13で締付け固
着する。The upper end of the anchor bolt 9 protruding from the flat slab 12 on the upper floor side is inserted into the vertical hole 5 of the lower connector flange 3 of the steel pipe 1 for forming the column on the upper floor side. A steel pipe 1 is erected on a flat slab 12 on the upper floor side and fixed by tightening with a nut 13 screwed onto an anchor bolt 9.
【0008】[0008]
【作用】下階側の柱構成用鋼管1と上階側の柱構成用鋼
管1に対するコンクリート11の打設は、同時には行わ
れず、下階側の柱構成用鋼管1への打設が先行される。[Operation] Concrete 11 is not poured into the column-forming steel pipe 1 on the lower floor side and the column-forming steel pipe 1 on the upper floor side at the same time, but the concrete 11 is poured onto the column-forming steel pipe 1 on the lower floor side first. be done.
【0009】下階側の柱構成用鋼管1へのコンクリート
11の打設は、上位コネクタフランジ2の垂直孔4から
鉄筋組立体8に挿入したアンカーボルト9を、上端部が
鉄筋組立体8の上面側に突出した位置に保持しながら、
フラットスラブ形成用型枠10への打設と一緒になされ
る。コンクリート11は鉄筋組立体8の透き間を通って
柱構成用鋼管1に充填される。Concrete 11 is poured onto the steel pipes 1 for forming columns on the lower floor by inserting anchor bolts 9 into the reinforcing bar assembly 8 through the vertical holes 4 of the upper connector flange 2 so that the upper end of the anchor bolts are inserted into the reinforcing bar assembly 8. While holding it in a position protruding from the top side,
This is done together with pouring into the formwork 10 for forming a flat slab. Concrete 11 passes through the gaps in reinforcing bar assembly 8 and is filled into column-forming steel pipes 1.
【0010】上階側の柱構成用鋼管1は、下階側のコン
クリート充填鋼管柱6と上階側のフラットスラブ12の
充填コンクリート11が十分に硬化した段階で、下階側
のコンクリート充填鋼管柱6の延長線上に当たるフラッ
トスラブ12の上面部分に建て上げられ、下階側のコン
クリート充填鋼管柱6と上階側の柱構成用鋼管1は、上
下コネクタフランジ2,3の垂直孔4,5を通るアンカ
ーボルト9とナット13によって、上階側のフラットス
ラブ12を介して剛に接合される。The steel pipes 1 for forming columns on the upper floor side are replaced with concrete-filled steel pipes on the lower floor side when the concrete-filled steel pipe columns 6 on the lower floor side and the filling concrete 11 of the flat slab 12 on the upper floor side are sufficiently hardened. It is built on the upper surface of the flat slab 12 which is an extension of the column 6, and the concrete-filled steel pipe column 6 on the lower floor and the column-forming steel pipe 1 on the upper floor are connected to the vertical holes 4 and 5 of the upper and lower connector flanges 2 and 3. It is rigidly joined via the flat slab 12 on the upper floor side by anchor bolts 9 and nuts 13 that pass through.
【0011】この上階側の柱構成用鋼管1の上位コネク
タフランジ2の上面側には、更に上階側のフラットスラ
ブ用鉄筋組立体8が配置され、該上位コネクタフランジ
2の垂直孔4から鉄筋組立体8にアンカーボルト9が挿
入される。以下、前記各工程を順次繰り返すことによっ
て、目的とする階数の建造物が構築される。A reinforcing bar assembly 8 for the flat slab on the upper floor side is further arranged on the upper surface side of the upper connector flange 2 of the steel pipe 1 for forming columns on the upper floor side. Anchor bolts 9 are inserted into reinforcing bar assembly 8 . Thereafter, by sequentially repeating each of the above steps, a building having the desired number of floors is constructed.
【0012】0012
【実施例】図示の実施例では、柱構成用鋼管1として円
形鋼管が使用され、上位コネクタフランジ2と下位コネ
クタフランジ3はいずれも円形リング板で構成され、鋼
管本体の端面に溶接されている。各コネクタフランジ2
,3には45度間隔で8個の垂直孔4,5を設けてある
。なお、柱構成用鋼管1としては角形鋼管を使用するこ
ともでき、上下の各コネクタフランジ2,3の平面形状
も鋼管本体に対応して変更することができる。[Embodiment] In the illustrated embodiment, a circular steel pipe is used as the column forming steel pipe 1, and both the upper connector flange 2 and the lower connector flange 3 are composed of circular ring plates, and are welded to the end face of the steel pipe body. . Each connector flange 2
, 3 are provided with eight vertical holes 4, 5 at 45 degree intervals. Note that a square steel pipe can also be used as the column-forming steel pipe 1, and the planar shape of each of the upper and lower connector flanges 2, 3 can also be changed in accordance with the steel pipe body.
【0013】[0013]
【発明の効果】以上のように本発明では、柱構成用鋼管
1は下階側と上階側とで完全に分断して使用されており
、柱構成用鋼管1の長さは、建造物の1階分の高さとほ
ぼ同じ程度のものであるから、上下階にわたる通し柱と
して使用されている従来のコンクリート充填鋼管柱と比
較して、柱構成用鋼管1に対するコンクリート11の打
設は、充填性状が良好になされることに成り、下階側の
コンクリート充填鋼管柱6と上階側のコンクリート充填
鋼管柱7のいずれにおいても、耐力強度の信頼性を確実
に高めることが出来る。Effects of the Invention As described above, in the present invention, the column-forming steel pipe 1 is used completely divided between the lower floor side and the upper floor side, and the length of the column-forming steel pipe 1 is determined by the length of the column-forming steel pipe 1. Since the height is approximately the same as that of one floor, compared to the conventional concrete-filled steel pipe column used as a through-column extending over the upper and lower floors, the concrete 11 placed on the column-forming steel pipe 1 is This results in good properties, and the reliability of the yield strength can be reliably increased in both the concrete-filled steel pipe columns 6 on the lower floor side and the concrete-filled steel pipe columns 7 on the upper floor side.
【0014】また、下階側のコンクリート充填鋼管柱6
と上階側のコンクリート充填鋼管柱7は、上階側のフラ
ットスラブ12を上下の各コネクタフランジ2,3の間
に挟んで、アンカーボルト9とナット13で堅固に締付
け固着されているから、コンクリート充填鋼管柱6,7
とフラットスラブ12との間の応力伝達が良好になされ
る。[0014] Also, the concrete-filled steel pipe column 6 on the lower floor side
The concrete-filled steel pipe column 7 on the upper floor side is firmly fixed with the anchor bolt 9 and nut 13 with the flat slab 12 on the upper floor sandwiched between the upper and lower connector flanges 2 and 3. Concrete-filled steel pipe columns 6, 7
Good stress transmission is achieved between the flat slab 12 and the flat slab 12.
【0015】コネクタフランジ2,3は柱構成用鋼管1
の上下端に固着されるものであるから、鋼管の途中の外
壁に溶接される従来のスチフナリングとは異なり、応力
伝達用手段の構成部材の取付け施工が容易になされる。[0015] The connector flanges 2 and 3 are the steel pipes 1 for forming the column.
Since the stiffener rings are fixed to the upper and lower ends of the steel pipe, unlike conventional stiffener rings that are welded to the outer wall in the middle of the steel pipe, the structural members of the stress transmitting means can be easily installed.
【0016】上階側のフラットスラブ12を造るときに
は、下側階の柱構成用鋼管6が下側階のフラットスラブ
12に締付け固着されているから、その柱構成用鋼管6
を上階側のフラットスラブ形成用型枠10の支保工の一
部に有効利用することによって、支保工の箇所と手間を
省くことができ、施工コストを節減することができる。When constructing the flat slab 12 on the upper floor, the steel pipes 6 for forming columns on the lower floor are tightened and fixed to the flat slab 12 on the lower floor.
By effectively utilizing this as part of the shoring of the formwork 10 for forming a flat slab on the upper floor side, the location and labor of shoring can be saved, and construction costs can be reduced.
【0017】柱構成用鋼管1の前記長さ寸法の短縮化に
加えて、柱構成用鋼管1,1の内部に鉄筋が一切配設さ
れていないことによって、コンクリート11の充填性が
一層改善されているため、鋼管壁によるコンクリートの
拘束効果とあいまって、耐力強度に悪影響を及ぼすこと
なく、柱構成用鋼管1の口径を縮減することができ、こ
れは建造物の平面計画上の自由度を増大させることにな
る。[0017] In addition to the shortening of the length dimension of the column-constituting steel pipes 1, the filling properties of the concrete 11 are further improved because no reinforcing bars are provided inside the column-constituting steel pipes 1, 1. Coupled with the restraint effect of the concrete by the steel pipe wall, the diameter of the column-forming steel pipe 1 can be reduced without adversely affecting the load-bearing strength. It will increase it.
【図1】本発明の一実施例に係るコンクリート充填鋼管
柱とフラットスラブの接合部を示す立面図である。FIG. 1 is an elevational view showing a joint between a concrete-filled steel pipe column and a flat slab according to an embodiment of the present invention.
【図2】第2図は第1図のA−A線断面図である。FIG. 2 is a sectional view taken along the line AA in FIG. 1;
1 柱構成用鋼管 2 コネクタフランジ 3 コネクタフランジ 4 垂直孔 5 垂直孔 6 コンクリート充填鋼管柱 7 コンクリート充填鋼管柱 8 フラットスラブ用鉄筋組立体 9 アンカーボルト 10 フラットスラブ成形用型枠 11 コンクリート 12 フラットスラブ 13 ナット 1 Steel pipe for column construction 2 Connector flange 3 Connector flange 4 Vertical hole 5 Vertical hole 6 Concrete filled steel pipe column 7 Concrete filled steel pipe column 8 Rebar assembly for flat slab 9 Anchor bolt 10 Flat slab molding formwork 11 Concrete 12 Flat slab 13 Nut
Claims (1)
2,3に垂直孔4,5を相対応して設けた鋼管1を柱構
成用鋼管として用い、下階側の柱構成用鋼管1の上位コ
ネクタフランジ2の上面側に、フラットスラブ用鉄筋組
立体8を配置し、上位コネクタフランジ2の垂直孔4よ
りアンカーボルト9を該鉄筋組立体8に挿通し、鉄筋組
立体8を埋め込むようにフラットスラブ成形用型枠10
と該鋼管1内にコンクリート11を打設して、上階側の
フラットスラブ12と下階側のコンクリート充填鋼管柱
6を造り、該上階側のフラットスラブ12より突出した
アンカーボルト9の上端部を、上階側の柱構成用鋼管1
の下位コネクタフランジ3の垂直孔5に挿通して、該上
階側の鋼管1を上階側のフラットスラブ12に建て上げ
、アンカーボルト9に螺合したナット13で締付け固着
して成るコンクリート充填鋼管柱とフラットスラブの接
合部の構造。Claim 1: A steel pipe 1 in which horizontal connector flanges 2 and 3 on the outer periphery of the upper and lower ends are provided with vertical holes 4 and 5 in correspondence with each other is used as a steel pipe for forming a column, and a steel pipe 1 for forming a column on the lower floor side is A flat slab reinforcing bar assembly 8 is placed on the top side of the connector flange 2, and the anchor bolts 9 are inserted into the reinforcing bar assembly 8 through the vertical holes 4 of the upper connector flange 2, and the flat slab is inserted so that the reinforcing bar assembly 8 is embedded. Formwork 10 for slab molding
Concrete 11 is poured into the steel pipe 1 to create a flat slab 12 on the upper floor side and a concrete-filled steel pipe column 6 on the lower floor side, and the upper end of the anchor bolt 9 protrudes from the flat slab 12 on the upper floor side. The steel pipe 1 for the column structure on the upper floor side
The steel pipe 1 on the upper floor side is inserted into the vertical hole 5 of the lower connector flange 3 of the upper floor side, and the steel pipe 1 on the upper floor side is erected on the flat slab 12 on the upper floor side, and the concrete filling is made by tightening and fixing it with nuts 13 screwed into anchor bolts 9. Structure of joint between steel pipe column and flat slab.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11676191A JPH04323445A (en) | 1991-04-19 | 1991-04-19 | Structure of joint part of concrete filling steel pipe column and flat slab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11676191A JPH04323445A (en) | 1991-04-19 | 1991-04-19 | Structure of joint part of concrete filling steel pipe column and flat slab |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04323445A true JPH04323445A (en) | 1992-11-12 |
Family
ID=14695087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11676191A Withdrawn JPH04323445A (en) | 1991-04-19 | 1991-04-19 | Structure of joint part of concrete filling steel pipe column and flat slab |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04323445A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105839777A (en) * | 2016-03-31 | 2016-08-10 | 初明进 | Line-shaped steel-concrete composite structure member |
CN105971163A (en) * | 2016-06-02 | 2016-09-28 | 初明进 | Combined structural member of T-shaped steel member and concrete |
-
1991
- 1991-04-19 JP JP11676191A patent/JPH04323445A/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105839777A (en) * | 2016-03-31 | 2016-08-10 | 初明进 | Line-shaped steel-concrete composite structure member |
CN105971163A (en) * | 2016-06-02 | 2016-09-28 | 初明进 | Combined structural member of T-shaped steel member and concrete |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108571070B (en) | Prefabricated steel tube concrete ring beam connecting structure and construction method | |
JP5023219B2 (en) | Precast temporary structure and construction method thereof | |
JP2004108034A (en) | Foundation structure, construction method and steel-pipe-mounted precast concrete pile for steel-framed building | |
KR102453791B1 (en) | PC double pannel using plate | |
JP2899463B2 (en) | Material | |
JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
JP2883898B2 (en) | PC pillar and PC pillar construction method | |
JPH04323445A (en) | Structure of joint part of concrete filling steel pipe column and flat slab | |
KR101254983B1 (en) | Joint structure of concrete filled tube and beam | |
JPH0436951B2 (en) | ||
KR101701495B1 (en) | Top-down construction method using steel tube column with horizontal and vertical reinforcement | |
CN107338862A (en) | Concrete-filled steel tubular frame structure non-dismantling formwork fills wall and steel pipe anchor connector | |
JP7532735B2 (en) | Connection structure | |
KR20210026900A (en) | Joining method of precast concrete pillar and girderin concrete structure | |
JP2504195B2 (en) | Construction method of the frame | |
KR20140111798A (en) | Footing for column and construction method thereof | |
JP7537982B2 (en) | Pile head seismic isolation structure and construction method thereof | |
KR101657628B1 (en) | Top-down method for building undergroud structure using steel pipe | |
KR102474648B1 (en) | Precast concrete Rahmen structure with bolt box joint | |
KR102554408B1 (en) | Connection Structure Between Steel-Concrete Hybrid Columns Using Vetical Member | |
JPS583884Y2 (en) | Side block for manhole | |
JPH0115764Y2 (en) | ||
JP2578671B2 (en) | Column and beam construction method | |
KR100402660B1 (en) | Precast concrete column for multi-stories | |
JP2677189B2 (en) | Steel beam for joining reinforced concrete columns |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Application deemed to be withdrawn because no request for examination was validly filed |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 19980711 |