JPH04189905A - Cut-and-cover method for road - Google Patents
Cut-and-cover method for roadInfo
- Publication number
- JPH04189905A JPH04189905A JP31802190A JP31802190A JPH04189905A JP H04189905 A JPH04189905 A JP H04189905A JP 31802190 A JP31802190 A JP 31802190A JP 31802190 A JP31802190 A JP 31802190A JP H04189905 A JPH04189905 A JP H04189905A
- Authority
- JP
- Japan
- Prior art keywords
- road
- work
- construction
- road surface
- elevated road
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 11
- 238000010276 construction Methods 0.000 claims abstract description 32
- 238000009412 basement excavation Methods 0.000 claims description 17
- 238000009434 installation Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 6
- 238000011835 investigation Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000000470 constituent Substances 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 230000008719 thickening Effects 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は地下鉄駅部の開削工事等に適用される道路の開
削工法に関する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a road cut-and-cut method applied to cut-and-cover work in subway stations, etc.
(従来の技術) 従来の開削工法においては、まず埋設物調査。(Conventional technology) In the conventional trenchless construction method, the first step is to investigate buried objects.
埋設物移設、支持杭打設、支持桁敷設から覆工板を敷設
して、その後1次掘削、支保工、2次掘削と行っていく
。Relocation of buried objects, driving of support piles, laying of support girders, and laying of lining plates will be followed by primary excavation, shoring, and secondary excavation.
(発明が解決しようとするIII)
上述した従来の開削工法では1次掘削以陳は覆工板下で
工事が行われるため上部の道路と通行する交通を阻害す
ることはないが、1次掘削までの埋設物調査、埋設物移
設、支持杭打設、支持桁敷設から覆工板敷設、1次掘削
までの工事においては道路面を専有して行う必要があり
、交通止め、通行規制等の交通阻害となるため、交通量
の多い道路においては交通量の減少する夜間のみの工事
となり、このとき日中は交通の用に供する必要があるた
め、掘削、埋戻しの作業をくり返し行う必要が生してい
る。すなわち手戻り作業が多く、従って工期が長(なる
とともにコストもかかるという問題があった。(III to be solved by the invention) In the conventional cut-and-cover construction method described above, the work after the first excavation is carried out under the lining board, so it does not obstruct the road and traffic passing above. It is necessary to occupy the road surface exclusively for the construction work, from investigation of buried objects, relocation of buried objects, driving of support piles, laying of support girders, laying of lining plates, and primary excavation, and traffic closures, traffic regulations, etc. As this will obstruct traffic, construction work will only be carried out at night when traffic volume is reduced on roads with heavy traffic, and since it will be necessary to use it for traffic during the day, excavation and backfilling work will need to be carried out repeatedly. alive. In other words, there was a problem that there was a lot of rework, which resulted in a long construction period (as well as increased costs).
また既存の立体道路式路面補修車等を用いた仮設立体道
路を用いる方法も考えられるが、地下を掘削していくに
つれ、立体道路の支持部が弱くなるという問題がある。Another possible method is to use a temporary structure road using an existing grade-level road surface repair vehicle, but there is a problem that the support part of the grade-level road becomes weaker as the underground is excavated.
さらに1次掘削以陵の覆工板下の工事においても上空に
広い空間が必要な工事の際には覆工板をはずし開口を作
って、また敷設するのには舗装のすりつけ等手間がかか
るという問題があった。Furthermore, in the case of construction work under the lining board after the first excavation, when a large space is required above the lining board, the lining board must be removed to make an opening, and laying the lining board again requires time and effort such as sanding the pavement. There was a problem.
(課題を解決するための手段)
本発明は前記課題に対処するものとして、高架支持部と
立体道路路面板等より構成され、工事区間上に作業スペ
ースを確保すべく道路進行方向に跨ぐ仮設立体道路を設
置し、この立体道路下のスペースにて、埋設物調査、埋
設物移設、1次掘削等の工事を行うと同時に分割された
支持杭を打設しながら深さ方向に連結していき、所定の
深度に達したところで立体道路の支持部を移設支持杭と
連結し、掘削が進行した際にも十分支持可能な橋脚部を
形成し、土留杭の打設も支持杭と同様に行なう。(Means for Solving the Problems) The present invention addresses the above-mentioned problems by providing a temporary construction structure that is composed of an elevated support section, a multi-level road surface board, etc., and that straddles the road in the direction of travel in order to secure a work space on a construction section. A road will be constructed, and in the space under this multi-level road, construction work such as buried object investigation, buried object relocation, and primary excavation will be carried out. At the same time, divided support piles will be driven and connected in the depth direction. When a predetermined depth has been reached, the supporting parts of the multi-level road are connected to the relocated supporting piles to form bridge piers that can provide sufficient support even as the excavation progresses, and the earth retaining piles are driven in the same way as the supporting piles. .
また高架支持部と路面板部との取付は取りはすしと、回
転ピンを用いる等の簡易な方法にしておくことで、上空
に広い空間の必要な際に、−時的な交通規制は伴うが簡
易的にスピーデイ−に空間を確保し、かつ復旧すること
ができるようにした。In addition, by using simple methods such as using sushi and rotating pins to attach the elevated support part and the road surface plate part, it is possible to install the elevated support part and the road surface plate part in a simple manner, such as by using a rotating pin. This makes it possible for people to easily and quickly secure space and recover.
(作 用)
そして本発明は上記の手段により工事区間をまず初期段
階に仮設立体道路で跨ぐことにより埋設物調査、埋設物
移設等の作業が交通阻害することなく連続的に行える。(Function) According to the present invention, by using the above-mentioned means to straddle the construction section with a temporary road at the initial stage, work such as buried object investigation and buried object relocation can be carried out continuously without interfering with traffic.
また比較的高さのない空間ではあるが、掘削前に分割し
た支持杭を順次深さ方向に連結しながら所定の深さまで
打設し、そこに立体道路の支持部を固定することで掘削
をしていっで′も大丈夫な支持部が得られる。Furthermore, although the space is relatively low in height, the support piles that have been divided are successively connected in the depth direction before excavation, and are driven to a specified depth, and the support parts of the overpass are fixed there. At the same time, you can obtain a support part that is suitable for ′′.
さらに時に応して簡易的かつスムーズに道路面上に開口
部を設けられる。Furthermore, openings can be simply and smoothly provided on the road surface as the occasion demands.
(実施例)
本発明の一実施例としての組立式立体道路の構成概要及
び組立方法を第1図乃至第7図に示す。(Example) An outline of the configuration and assembly method of a prefabricated multi-level road as an example of the present invention is shown in FIGS. 1 to 7.
第1図乃至第4図において1は組立式仮設立体道路、2
は(地下工事)作業空間、3は立体道路路面板、4は支
持脚、5は移動用ローラー、6は連結金具、7は荷重分
散前(設置用ガイドレール兼用)、8は搬送用トレーラ
−19は搬送組立用ロボット台車を示す。In Figures 1 to 4, 1 is a prefabricated temporary structure road, 2
(underground construction) work space, 3 is a multi-level road surface board, 4 is a support leg, 5 is a moving roller, 6 is a connecting fitting, 7 is before load distribution (also serves as a guide rail for installation), 8 is a transport trailer. Reference numeral 19 indicates a robot carriage for transportation and assembly.
本発明における組立式仮設立体道路1は、道路上または
地下工事等における工事区間上方を道路進行方向に跨ぎ
、作業空間2を確保する様、立体道路路面板3と支持脚
4等より構成される。なお、支持脚4には移動用ローラ
ー5が取りつけられていてもよい。第2図乃至第3図に
設置手順を示す。The prefabricated temporary structure road 1 of the present invention is constructed of a multi-dimensional road surface plate 3, support legs 4, etc., so as to straddle the road in the direction of road travel over a construction section for on-road or underground construction, etc., and to secure a work space 2. . Note that moving rollers 5 may be attached to the support legs 4. The installation procedure is shown in FIGS. 2 and 3.
立体道路の構成単位体である立体道路路面板3は、何セ
ットかを段積みし搬送用トレーラ−8で工事区域まで搬
送する。工事区域にはそれまでにユニツクトラック等(
図示していない)で荷重分散前(兼設置用ガイドレール
)7を搬入、布設しておく、ここで搬送トレーラ−8に
縦に数段績まれている立体道路路面板3を搬送組立用ロ
ボット台車9により降ろし、回転させ支持脚を立てて順
次ガイドレール7上に設置し、移動用ローラー5を用い
て送り、すでに設置済の立体道路路面板3とX給金具6
をもって接合固定しながら組立式立体道路を形成してい
く。このとき支持′脚にとりつく移動用ローラーの接地
面積を太き(とる等すれば設置用ガイドレール兼荷重分
散沓7の設置を省くことができる。第5図乃至第14図
に搬送組立用ロボット台車9による立体道路路面板3の
設置要領を更に詳述する。Sets of three-dimensional road road surface boards 3, which are the constituent units of a three-dimensional road, are stacked and transported to a construction area by a transport trailer 8. Unit trucks, etc. (
Before the load is distributed (not shown), the guide rail 7 (also used as a guide rail for installation) is carried in and installed.The robot for transporting and assembling the three-dimensional road surface board 3 that is rolled vertically in several stages on the transport trailer 8. It is unloaded using a trolley 9, rotated, the support legs are erected, and sequentially installed on the guide rail 7, and transported using the moving rollers 5, and the already installed three-dimensional road road surface board 3 and the X feeder 6
A prefabricated three-dimensional road will be formed by joining and fixing the parts. At this time, if the ground contact area of the moving roller attached to the support leg is made thicker, the installation of the installation guide rail and load distribution shoe 7 can be omitted. The procedure for installing the three-dimensional road surface board 3 using the trolley 9 will be described in further detail.
搬送組立用ロボット台車9は、第5図に示すように走行
及び旋回用の車輪10.昇陳用ジヤツキ11゜その上に
小型ジヤツキ14.支持脚折り込み装置15等を具備し
た薄型ドーリ−台車12を備える。搬送用トレーラ−8
に段積みされた立体道路路面板3のうち、上から2段目
のものの路面上に搬送組立用ロボット台車9の送出入部
13を連接しく第6図)。As shown in FIG. 5, the transport and assembly robot cart 9 has wheels 10 for traveling and turning. Display jack 11゜ On top of that, small jack 14. A thin dolly truck 12 equipped with a support leg folding device 15 and the like is provided. Transport trailer-8
Among the three-dimensional road road surfaces 3 stacked in stages, the delivery/input section 13 of the transport and assembly robot cart 9 is connected to the road surface of the second stage from the top (Fig. 6).
この上を通して最上段の立体道路路面板3の下面部に薄
型ドーリ−台車12を挿入(第7図)、立体道路路面板
3をジヤツキアップしく第8図)、ドーリ−台車によっ
て搬送組立用ロボット台車9の上面まで路面板3を送出
する(第9図)。その後送出入部13を収納して(第1
1図)1台車を回転させ路面板を横向きにするとともに
(第12図)、薄型ドーリ−台車の支持脚折り込み装置
15により路面板の支持脚部のロックをはずし支持脚を
立たせ再びロックを行った状態(第14図)で布設され
た設置用ガイドレール兼荷重分散沓上に上架する。Insert the thin dolly trolley 12 into the lower surface of the uppermost three-dimensional road surface plate 3 through this (Fig. 7), and jack up the three-dimensional road road surface plate 3 (Fig. 8). The road surface plate 3 is sent out to the upper surface of the road surface plate 9 (FIG. 9). After that, the sending/unloading section 13 is stored (the first
Figure 1) 1 Rotate the trolley to turn the road plate sideways (Figure 12), and use the support leg folding device 15 of the thin dolly-cart to unlock the support legs of the road plate, raise the support legs, and lock them again. In this state (Fig. 14), it is placed on top of the installation guide rail and load distribution shoes that have been installed.
その後は前述した通りである。もちろん搬送組立用ロボ
ット台車9にターンテーブル部を組み込めば、走行及び
旋回用車輪10を用いずに路面板13を90″回転させ
ることは可能になる。After that, the process is as described above. Of course, if a turntable section is incorporated into the transport and assembly robot cart 9, it becomes possible to rotate the road surface plate 13 by 90'' without using the wheels 10 for traveling and turning.
立体道路を撤去する場合はこれらと逆の手順で行う。When removing an overpass, follow these steps in reverse.
立体道路路面板については上述のタイプの他に第15図
乃至第17図に示すような支持脚部を分割別置きとして
もよく、またこの支持脚部は、第17図乙こ示すごとく
トラス型の支持部とすることもできる。また搬送トレー
ラ−からの荷おろし組立については搬送組立用ロボット
台車を使用する他にもちろん第15図に示すようなりレ
ーン等の揚重機やフォークリフト22等を使用すること
も可能である。In addition to the above-mentioned types, for multi-level road road slabs, support legs may be separated and placed separately as shown in Figures 15 to 17, and these support legs may be of a truss type as shown in Figure 17. It can also be used as a support part. Further, for unloading and assembling the load from the transport trailer, in addition to using the robot cart for transport and assembly, it is of course possible to use a lifting machine such as a lane or a forklift 22 as shown in FIG. 15.
次に地下鉄駅部の掘削工事を例に上記仮設立体道路を用
いた工法について実施例を示す。Next, an example of a construction method using the above-mentioned temporary construction road will be shown, taking excavation work at a subway station as an example.
第18図乃至第29図に仮設立体道路を利用した工事の
工法の各工程を示す。第18図に示すように仮設立体道
路1の設置・撤去の短期間をのぞき、第19図に示すよ
うに埋設物23の位置調査及び第20図に示すように埋
設物23の移動・埋戻しは仮設立体道路1の下部空間で
行えるため工事は昼夜間を問わず実施可能となるととも
に、埋戻し等による手戻りもなくなる。Figures 18 to 29 show each step of the construction method using the temporary construction road. As shown in Fig. 18, except for the short period of installation and removal of the temporary structure road 1, as shown in Fig. 19, the location of buried objects 23 is investigated, and as shown in Fig. 20, the buried objects 23 are moved and backfilled. Since the construction work can be carried out in the space under the temporary structure road 1, the construction work can be carried out day or night, and there is no need for rework due to backfilling or the like.
掘削の進展につれである時期に立体道路支持部の移設(
新設)、支持スパンが長くなるときは、桁の増厚という
追加工事(第22図乃至第24図)は生じるが、それを
あわせ考えてもたいへんな合理化となる。As the excavation progresses, at some point the overpass support section will be relocated (
(new construction), and when the support span becomes longer, additional work such as thickening the girders (Figures 22 to 24) will be required, but considering this together, it will be a great rationalization.
さて土留杭26.覆工支持杭25の打設にあっては従来
工法のごとき大型の杭打ちマシンは使用できない。第2
1図及び第23図に示すように本工法においては作業空
間に入ることのできる小型の杭打ちマシン32にて杭を
打ち込み、上部に追加抗を連結しては打ちだすという打
ちつぎを行い所定の深さの杭の打設を行う。このときの
追加杭とのジヨイント部の実施例を第30図に示す。即
ち追加抗25aは接合板25b及びガイド板25cによ
り連結される。Now, earth retaining pile 26. When driving the lining support piles 25, it is not possible to use a large pile driving machine as in the conventional construction method. Second
As shown in Figures 1 and 23, in this construction method, piles are driven by a small pile driving machine 32 that can enter the work space, and additional piles are connected to the top and driven out. Piles will be driven to a depth of . An example of the joint portion with the additional pile at this time is shown in FIG. That is, the additional resistor 25a is connected by the connecting plate 25b and the guide plate 25c.
掘削が進んでくると仮設道路の支持部を覆工支持杭25
上に移す必要が生じる。また支持スパン長によっては仮
設道路路面板の増厚や補強が必要になってくる。路面板
の補強等は部材を搬入し既存の重機で行う。支持部の新
設・移設・撤去については第31図乃至第32図に示す
ように行う。すなわち搬入された支持yn29を脚取付
台車31によって所定位置に挿入し、覆工支持杭25と
連結後、支持脚中央部のバックル30をしめることで支
持脚をのばし仮設道路の荷重を支える。As the excavation progresses, the support section of the temporary road will be installed with lining support piles 25.
You will need to move it up. Also, depending on the length of the support span, it may be necessary to increase the thickness or reinforce the temporary road surface plate. Reinforcement of the road surface board will be carried out using existing heavy machinery. New installation, relocation, and removal of the support section are performed as shown in FIGS. 31 and 32. That is, the carried support yn 29 is inserted into a predetermined position by the leg mounting cart 31, and after being connected to the lining support pile 25, the buckle 30 at the center of the support leg is tightened to extend the support leg and support the load of the temporary road.
第27図乙こ示すような躯体構築の工程等においては、
仮設道路上からの責機材の投入が必要になるときがある
。第33図はこのようなときのために立体道路路面板の
ところどころにもうけられたハツチ33であり、路肩方
向にピン結合されており、必要に応して一時的な車線規
制のもとに本ハツチを開閉シリンダー35等で開口すれ
ば、立体道路路面板上からの資機材の搬出入が短時間の
うちに可能となる。In the process of building the frame as shown in Figure 27,
There are times when it is necessary to introduce equipment from above the temporary road. Figure 33 shows hatches 33 that have been made here and there on the road surface plate for such cases, and are connected with pins in the direction of the road shoulder. If the hatch is opened using the opening/closing cylinder 35 or the like, materials and equipment can be carried in and out from the multi-level road surface board in a short time.
(発明の効果)
このように本発明によるときは工事区間の道路に、道路
との間に作業空間を存して道路を跨ぐ仮設立体道路を設
置し、該仮設立体道路の下面で掘削工事を行うようにし
たものであるから交通阻害をすることなしに連続して工
事が可能となり手戻りをへらし工程を短縮して工事費用
を削減できると共に地下鉄駅部の開削工事等にともなっ
て都市の交通機能を低下させることもなくなる等の効果
を有する。(Effects of the Invention) As described above, according to the present invention, a temporary structure road is installed on the road in the construction section, straddling the road with a work space between it and the road, and excavation work is carried out on the underside of the temporary structure road. This allows construction to be carried out continuously without disrupting traffic, reducing rework, shortening the process, and reducing construction costs. It has the effect of eliminating the possibility of deterioration of function.
図面は本発明の一実施例を示すもので第1図は組立式立
体道路の概念図、第2図乃至第14図は組立式立体道路
設置手順の概念図、第15図乃至第17図は組立式立体
道路設置の他の手順の概念図、第18図乃至第29図は
開削工事手順の概念図、第30図乃至第32図は組立式
立体道路の追加設置手順の概念図、第33図は開削工事
の追加手順の概念図である。The drawings show one embodiment of the present invention. Figure 1 is a conceptual diagram of a prefabricated multi-level road, Figures 2 to 14 are conceptual diagrams of the installation procedure of a prefabricated multi-level road, and Figures 15 to 17 are conceptual diagrams of a prefabricated multi-level road. Figures 18 to 29 are conceptual diagrams of the excavation construction procedure; Figures 30 to 32 are conceptual diagrams of additional installation procedures for the assembly type grade-level road; Figure 33; The figure is a conceptual diagram of the additional steps for excavation work.
Claims (1)
を跨ぐ仮設立体道路を設置し、該仮設立体道路の下面で
掘削工事を行うようにしたことを特徴とする道路の開削
工法。A road excavation method characterized by installing a temporary road that straddles the road with a work space between it and the road in the construction section, and carrying out excavation work on the underside of the temporary road. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31802190A JPH04189905A (en) | 1990-11-26 | 1990-11-26 | Cut-and-cover method for road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31802190A JPH04189905A (en) | 1990-11-26 | 1990-11-26 | Cut-and-cover method for road |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04189905A true JPH04189905A (en) | 1992-07-08 |
Family
ID=18094613
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP31802190A Pending JPH04189905A (en) | 1990-11-26 | 1990-11-26 | Cut-and-cover method for road |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04189905A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012526213A (en) * | 2009-05-06 | 2012-10-25 | エ.ア.デシャンプ.エ.フィス | Improved temporary bridge |
-
1990
- 1990-11-26 JP JP31802190A patent/JPH04189905A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012526213A (en) * | 2009-05-06 | 2012-10-25 | エ.ア.デシャンプ.エ.フィス | Improved temporary bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7193172B2 (en) | Floor slab erection machine | |
US20140041135A1 (en) | Pipeline crossing bridge | |
US5809702A (en) | Surface layer ground establishment block, surface layer ground using the same and method for utilizing the same | |
JPH04189905A (en) | Cut-and-cover method for road | |
JPH11158814A (en) | Construction method of gate type pier of viaduct beam | |
JPH03241200A (en) | Method and device for setting precast board for tunnel | |
US20180283041A1 (en) | Border Wall | |
JP4004423B2 (en) | Road three-dimensional intersection construction method and pier connection structure | |
JPH10280900A (en) | Temporary sleepers for shield tunnel construction | |
JP2008303537A (en) | Transporting precast floor slabs | |
JP2001115555A (en) | Shed parts, shed structure and method of building shed structure | |
JP2023154910A (en) | Girder transporting carriage and girder replacing method using the same | |
JP2003239366A (en) | Concrete block conveyor | |
CN205061417U (en) | Soil lifting system for construction of deep foundation pit of building in narrow area | |
JP3711280B2 (en) | Mobile all-weather work building | |
JP3940587B2 (en) | Construction method of divided bridge type traffic route | |
JP7188861B2 (en) | Installation method of track for truck running | |
JPH09296407A (en) | Lining board | |
JP6944900B2 (en) | Construction method of linear structure | |
US5575594A (en) | Modular rail car unloading pit and method of using the same | |
JP7624910B2 (en) | How to set up shoring | |
JPH06288189A (en) | Laying method for portal culvert | |
JP3920292B2 (en) | Land improvement method for landfill using mobile all-weather work building | |
JP4711235B2 (en) | Concrete block carrying device and carrying method | |
JPH0434172Y2 (en) |