[go: up one dir, main page]

JPH04106293A - Underground connection method of shield tunnel - Google Patents

Underground connection method of shield tunnel

Info

Publication number
JPH04106293A
JPH04106293A JP22135990A JP22135990A JPH04106293A JP H04106293 A JPH04106293 A JP H04106293A JP 22135990 A JP22135990 A JP 22135990A JP 22135990 A JP22135990 A JP 22135990A JP H04106293 A JPH04106293 A JP H04106293A
Authority
JP
Japan
Prior art keywords
shield
shield machine
freezing
later
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22135990A
Other languages
Japanese (ja)
Other versions
JPH06102957B2 (en
Inventor
Taro Kasuya
太郎 粕谷
Tetsuji Kato
加藤 哲治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seiken Co Ltd
Tekken Corp
Original Assignee
Seiken Co Ltd
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seiken Co Ltd, Tekken Corp filed Critical Seiken Co Ltd
Priority to JP22135990A priority Critical patent/JPH06102957B2/en
Publication of JPH04106293A publication Critical patent/JPH04106293A/en
Publication of JPH06102957B2 publication Critical patent/JPH06102957B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To reduce a construction period by inserting a flexible freezing pipe from the inside of a first shield machine into an excavated hole in a bedrock to construct a freezing earth wall, making penetration of a second shield machine into the freezing earth wall, and executing a primary lining after making cut-off in the rear. CONSTITUTION:When a bedrock is in a good stabilized state, double packer for an excavated hole pipe and a freezing pipe is provided to a shield steel plate of a first shield machine 1. After that, for example, boring is made by means of a small caliber muddy water driving pipe method, the driving pipe is drawn out while making the substitution of muddy water, and flexible freezing pipes 4 are buried to construct a tulip-like freezing earth wall F. Then, after penetration of a second shield machine 1a into the freezing earth wall F, segment freezing plates 7 are assembled to a segment of the shield machine 1a to refreeze Fa. In addition, after cutters of the shield machines 1 and 1a or bulk chambers b are dismantled, a primary lining is executed with a steel segment.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は2台のシール1く機を対向させて地中を掘進さ
せながらシールドトンネルを形成し接合する際の接合方
法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a joining method for forming and joining a shield tunnel while digging underground with two sealers facing each other.

〔従来の技術〕[Conventional technology]

近時、地下開発が盛んに行なわれており、地下トンネル
の構築が増加している。この地下トンネルの構築は主と
してシールド機によって行なわれるため、シールド機の
開発も多岐に亘り、掘削断面が変化するシールド機や多
面シールド機等によるトンネル工事も増加している。
Recently, underground development has been actively carried out, and the construction of underground tunnels is increasing. Since the construction of underground tunnels is mainly carried out using shield machines, a wide variety of shield machines have been developed, and tunnel construction using shield machines with variable excavation cross sections, multifaceted shield machines, etc. is also increasing.

而して、前記トンネルの構築に際しては、2台のシール
ド機を互いに対向させて発進させ、掘進させながらシー
ルドトンネルを形成して行き、最終的に双方が形成した
シールドトンネルを地中接合するのであるが、そのため
の工法として、凍結地中接合工法がある。この工法は安
全且つ確実で、よくシールドトンネルを接合することが
出来るが、通常で4〜5ケ月もの長い工期を要するとい
う欠点がある。
Therefore, when constructing the tunnel, two shield machines are launched facing each other, form a shield tunnel while digging, and finally the shield tunnels formed by both machines are connected underground. However, one method for this purpose is the frozen underground bonding method. This construction method is safe and reliable, and can connect shield tunnels well, but it has the disadvantage that it usually requires a long construction period of 4 to 5 months.

即ち、従来の凍結地中接合方法は、2台のシールド機を
互いに対向させて発進させ、掘進させながらシールドト
ンネルを形成して行き、同機が同時に接合地点に到着す
る場合は、第10図に示すように、シールド機51.5
+、aからそれぞれ円錐形状に凍結管52を埋設して算
盤珠状の凍土壁53を造成した後、シールド機51..
51aのカッター〇、バルク室す等を解体、撤去し、−
法覆工を施工し、てシールドトンネルを接合する方法が
採られているが、この方法では、−殻内に凍結管理設等
の準備、仮設工に2力月、凍結期間に1〜1.5力月、
解体。
In other words, in the conventional frozen underground joining method, two shield machines are launched facing each other and form a shield tunnel while digging.If the machines arrive at the joining point at the same time, As shown, shield machine 51.5
After embedding frozen pipes 52 in a conical shape from + and a to create an abacus-shaped frozen soil wall 53, a shield machine 51. ..
Dismantle and remove the cutter 〇, bulk chamber, etc. of 51a, and -
The method used is to construct a lining and then join the shield tunnel, but this method requires - Preparation of freeze control facilities etc. inside the shell, 2 months for temporary construction, and 1 to 1 month during the freezing period. 5 Rikizuki,
Dismantling.

覆工に1〜1.5力月を要し、合計すれば4〜5力月の
長い工事期間を必要としていた。
It took 1 to 1.5 months to lay the lining, and the total construction period was 4 to 5 months.

そこで、この工期を少しでも短縮するために。Therefore, in order to shorten this construction period as much as possible.

2台のシールド機の接合地点への到着時期をずらして、
第11図に示すように、先着したシールド機51から円
錐形状に直管状の凍結管52を埋設し、円錐形状の凍土
壁53aを造成して、後着シールド機を待つ方法も採ら
れているが、この方法では凍結管が直管であるため1円
錐形状の凍土壁53aと後着のシールド機51aとの隙
間が大きくなるので、後着のシールド機51aから補助
凍結管52aを埋設して前記隙間に凍土53bを造成す
るか又は時間を掛けて前記凍結管52により前記隙間を
凍結しなければならず、結局は工期の短縮もシールド機
51の先着による効果も充分活用出来なくて、前者の方
法に比べ、1力月程度工期を短縮できるに過ぎないので
ある。
By staggering the arrival times of the two shield machines at the joining point,
As shown in FIG. 11, a method is also adopted in which a straight conical freezing tube 52 is buried from the shield machine 51 that arrived first, and a conical frozen wall 53a is created to wait for the shield machine that arrives later. However, in this method, since the freezing pipe is a straight pipe, the gap between the conical frozen soil wall 53a and the subsequent shielding machine 51a becomes large, so an auxiliary freezing pipe 52a is buried from the succeeding shielding machine 51a. It is necessary to create frozen soil 53b in the gap or to freeze the gap with the freezing tube 52 over time, and in the end, the shortening of the construction period and the effect of the first arrival of the shielding machine 51 cannot be fully utilized, and the former Compared to the above method, the construction period can only be reduced by about one month.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上記のような従来技術の欠点を補うために、a 凍結管
理設等の工程を短縮できるように、そのための機材をシ
ールド機に着装する b シールド機の面盤に工夫を凝らして、シールド機と
シールド機の接合区間を極力狭め、凍土壁の厚みを減少
させる などの対策が考えられている。これらの対策は一見合理
的に見えるが、実際にはシールド機の構造を複雑にする
結果、故障や事故発生のおそれが多く、また、シールド
工法の主目的である掘進を犠牲にせざるを得ないことも
あり、充分満足すべき成果は得られない。
In order to compensate for the shortcomings of the conventional technology as described above, a. Attach equipment to the shield machine so as to shorten the process of freezing control equipment, etc. b. Innovate the face plate of the shield machine to make it compatible with the shield machine. Countermeasures are being considered, such as narrowing the joint section of the shield machine as much as possible and reducing the thickness of the frozen soil wall. Although these measures seem reasonable at first glance, in reality they complicate the structure of the shield machine, increasing the risk of breakdowns and accidents, and they also force the sacrifice of excavation, which is the main purpose of the shield method. As a result, satisfactory results may not be obtained.

従って、本発明が解決しようとする課題は、シールド機
の構造を変化させることなく、しかも工期を短縮できる
と共にあらゆる種類のシールド機の形状や機能に対応し
て、シールドトンネルを接合できる凍結地中接合方法を
提供することである。
Therefore, the problem to be solved by the present invention is to provide a method for connecting shield tunnels in frozen underground that can shorten the construction period without changing the structure of the shield machine, and can accommodate the shapes and functions of all types of shield machines. An object of the present invention is to provide a joining method.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は上記の課題を解決することを目的としてなされ
たもので、その第一発明の構成は、2台のシールド機を
対向させ地中を掘進させてシールドトンネルを形成し接
合するシールドトンネルの接合方法において、接合すべ
き地点におけるシールド機の到着時期をずらし、先着し
たシールド機の内部から操向性ボーリングにより円弧状
又は曲線状に地山を削孔して、該掘削孔に可撓性の凍結
管を挿入し、後着シールド機の到着時期に合わせて横向
きチューリップ状の凍土壁を造成しておき、該凍土壁内
に後着シールド機を貫入させた後、後着シールド機の後
方にセグメント凍結板を組立てるか又は貼付凍結管を設
置するなどして後部止水を行なってから、シールド機の
カッター、バルク室等を解体し、スチールセグメント等
によjJ−法覆工を施してシールドトンネルを接合する
ことを特徴とするものであり、また、第二発明の構成は
、2台のシールド機を対向させ地中を掘進させてシール
ドトンネルを形成し接合するシールドトンネルの接合方
法において、接合すべき地点におけるシールド機の到着
時期をずらし、先着したシールド機の直後のセグメント
に、水平凍結管理設用の削孔室を拡巾構築できる機構を
内装させ、後着シールド機が前記所定の地点に到達する
までの期間中に拡巾した削孔室から水平凍結管を、後着
するシールド機のテール部分まで埋設して、該シールド
機の口径よりやや大きい円筒形状の凍土壁を造成し、後
着シールド機が前記凍土壁内に到着した後、該後着シー
ルド機の後方にセグメント凍結板を組立るか又は凍着用
設備を設置するなどして後部止水を行なってから、シー
ルド機のカンタ−バルク室等を解体し、スチールセグメ
ント等により一次覆工を施工して、シールドトンネルを
接合することを特徴とするものである。
The present invention has been made with the aim of solving the above problems, and the first aspect of the invention is a shield tunnel in which two shield machines face each other, dig underground to form a shield tunnel, and join together. In the joining method, the arrival time of the shield machine at the point to be joined is staggered, and a hole is drilled into the ground in an arcuate or curved shape using steerable boring from inside the shield machine that arrived first, and a flexible A freezing pipe is inserted to create a horizontal tulip-shaped frozen soil wall in time for the arrival of the later-arriving shield machine, and after penetrating the later-arriving shield machine into the frozen soil wall, After assembling segment freezing plates or installing affixed freezing pipes to stop the water at the rear, dismantle the shield machine's cutter, bulk chamber, etc., and apply JJ-method lining with steel segments, etc. The second invention is characterized in that a shield tunnel is joined, and the configuration of the second invention is a method for joining a shield tunnel, in which two shield machines face each other and dig underground to form and join a shield tunnel. , the timing of the arrival of the shield machine at the point to be welded is staggered, and a mechanism that can expand the width of a drilling chamber for horizontal freezing control equipment is installed in the segment immediately after the shield machine that arrived first, so that the later-arriving shield machine During the period up to reaching the point, a horizontal freezing pipe is buried from the widened hole drilling chamber up to the tail of the shield machine that will be installed later, creating a cylindrical frozen wall that is slightly larger than the diameter of the shield machine. After the later-arriving shield machine arrives within the frozen soil wall, water is stopped at the rear by assembling a segment freezing plate or installing freezing equipment behind the later-arriving shield machine, and then the shield is removed. This method is characterized by dismantling the canter bulk chamber of the machine, constructing a primary lining using steel segments, etc., and joining the shield tunnel.

即ち、第一発明の接合工法は、2台のシールド機のシー
ルドトンネルを接合すべき地点への到着時期をずらし、
先着のシールド機内から凍結工法を用いてその先端側に
、後着のシールド機が進入できるように、チューリップ
状の凍土壁を造成しておき、後着のシールド機を前記凍
土壁内に貫入させ、該後着シールド機内から不足する凍
土を造成するために、セグメント凍結板を組立るか、ま
たは貼付凍結管を設備して、後部を凍着、止水し、あと
は常法によって、スチールセグメント等による一次覆工
を施工することにより、シールドトンネルの接合工事期
間を短縮しようというものであり、一方、第二発明の接
合方法は、第一発明と同様に、2台のシールド機の到着
時期をずらし、先着のシールド機直後のセグメントに水
平凍結管を埋設するための削孔室を拡巾構築し、該削孔
室から前方へ向は水平凍結管を埋設して円筒形状の凍土
壁を造成しておき、該凍土壁内に後着シールド機を貫入
させた後、第一発明と同様にしてシールドトンネルを接
合することにより、シールドトンネルの接合期間を短縮
しようというものである。
That is, the joining method of the first invention staggers the timing of the arrival of the shield tunnels of the two shield machines at the point where they are to be joined.
A tulip-shaped frozen wall is created from inside the first-arriving shield machine using a freezing method on the tip side so that the second-arriving shield machine can enter, and the second-arriving shield machine penetrates into the frozen soil wall. In order to create the insufficient frozen soil from inside the later-attached shield machine, assemble a segment freezing plate or install a pasted freezing pipe to freeze the rear part and stop water, and then install the steel segment using the usual method. On the other hand, the joining method of the second invention is similar to the first invention, and the joining method of the second invention is based on the timing of the arrival of the two shield machines. A hole drilling chamber for burying a horizontal freezing pipe was constructed in the segment immediately after the first-arriving shield machine, and a cylindrical frozen wall was constructed by burying the horizontal freezing pipe from the drilling room forward. The purpose is to shorten the joining period of the shield tunnel by constructing the frozen soil wall, penetrating the later-attached shield machine into the frozen soil wall, and joining the shield tunnel in the same manner as in the first invention.

〔実施例〕〔Example〕

次に本発明接合方法の実施例を図により工程順に説明す
る。
Next, an embodiment of the bonding method of the present invention will be explained step by step with reference to the drawings.

第1図及び第2図は、凍結管を埋設する状態を示す図で
、第1図は地山の安定状態が良好な場合の説明図、第2
図は地山の安定状態が悪い場合の説明図、第3図はチュ
ーリップ状の凍土を造成した状態の断面図、第4図は後
着シールド機が到着し、その後方を凍結した状態の断面
図、第5図はシールド機の内部を解体し、−法覆工を施
工して接合した状態を示す断面図、第6図は第二発明に
より先着シールド機の前方に円筒形状の凍土壁を造成し
て後着シールド機を貫入し、その後方を到着した状態の
断面図、第7図は削孔室の拡巾前の横断面図、第8図は
同じく縦断面図、第9図は平面図である。
Figures 1 and 2 are diagrams showing the state in which frozen pipes are buried; Figure 1 is an explanatory diagram when the ground is in a stable state;
The figure is an explanatory diagram when the stability of the ground is poor, Figure 3 is a cross-sectional view of the state where tulip-shaped frozen soil has been created, and Figure 4 is a cross-section of the state where the late-arriving shield machine has arrived and the area behind it is frozen. Figure 5 is a cross-sectional view showing the state in which the inside of the shield machine has been disassembled and the lining has been installed and joined, and Figure 6 is a cylindrical frozen wall in front of the first-come-first-served shield machine according to the second invention. A cross-sectional view of the hole after it has been drilled and penetrated by a later-arriving shield machine, Figure 7 is a cross-sectional view of the drilling chamber before it is widened, Figure 8 is a longitudinal cross-sectional view of the hole, and Figure 9 is a vertical cross-sectional view of the same. FIG.

第一発明 ■ 着シールド  からの凍  の埋 、凍a 先着し
たシールド機内から、造成される凍土がチューリップ状
になるように曲線ボーリングを行なう。この曲線ボーリ
ングは、操向性ボーリング例えば小口径泥水推進管工法
等の工法を利用して削孔し、地山の安定状態が良い場合
は、孔壁保持のため泥水置換しながら推進管を抜取り、
掘削孔にそれより一回り小さい可撓性のある凍結管を挿
入し、また、地山の安定状態が悪い場合は、泥水推進管
のバルクヘッド装置を残置したまま、推進管内にそれよ
り一回り小さい可撓性のある凍結管を挿入して、空隙に
泥水等の充填剤を封入する。
First Invention■ Filling of frozen soil from the arriving shield, freezing a Curve boring is performed from inside the shield machine that arrived first so that the frozen soil to be created is shaped like a tulip. In this curved boring, the hole is drilled using a method such as steerable boring, such as the small-diameter muddy water propulsion pipe construction method, and if the ground is in a stable condition, the propulsion pipe is extracted while displacing muddy water to maintain the hole wall. ,
Insert a flexible cryotube one size smaller into the excavation hole, and if the ground is not stable, insert the bulkhead device of the muddy water propulsion tube into the propulsion tube one size larger. A small flexible cryotube is inserted to fill the void with a filler such as muddy water.

即ち、第1図は地山の安定状態が良い場合を示すもので
、シールド機1のシールド鋼板2に削孔管用と凍結管用
の二重パッカー3を取付けて、まず、操向性ボーリング
例えば小口径泥水推進管工法を利用して削孔し、孔壁保
持のため泥水置換しながら推進管を抜取り、可撓性の凍
結管4を埋設して凍結工法により、第3図に示すように
、チューリップ状の凍土壁Fを造成する。また、第2図
は地山の安定状態が悪い場合を示すもので、上記におけ
る推進管と同し推進管5を用いて削孔し、そのバルクヘ
ット装@5aを残置したままパッカー3に泥水等の封入
蓋3aを施すと共に凍結管4を埋設し、推進管5と凍結
管4との間の空隙に泥水等の充填材6を封入し、凍結管
4に冷媒を通して、第3図に示すようなチューリップ状
の凍土壁Fを造成するのである。
That is, FIG. 1 shows a case where the ground is in a good stable state. First, a double packer 3 for drilling pipes and for freezing pipes is attached to the shield steel plate 2 of the shielding machine 1, and first, a maneuverable boring, for example, a small A hole is drilled using the muddy water propulsion pipe method, the propulsion pipe is extracted while replacing muddy water to maintain the hole wall, a flexible freezing pipe 4 is buried, and the freezing method is used to create a hole, as shown in Figure 3. Create a tulip-shaped frozen wall F. In addition, Figure 2 shows a case where the stability of the ground is poor. A hole is drilled using the propulsion tube 5, which is the same as the propulsion tube described above, and muddy water etc. are poured into the packer 3 while leaving the bulkhead device @5a. At the same time, a freezing tube 4 is buried, a filling material 6 such as mud water is filled in the gap between the propulsion tube 5 and the freezing tube 4, and a refrigerant is passed through the freezing tube 4, as shown in FIG. This will create a tulip-shaped frozen wall F.

b 而して、チューリップ状の凍土壁Fの造成期間は従
来の凍土壁の造成と同し程度の日数(仮設に2力月と凍
結に1力月)を要するが、これを後着シールド機1aが
到着する3ケ月前から実施すると、工程上はこの3ケ月
が工事全体の工程とは無関係となり、それ以降の作業が
必要工程となる。
b.The construction period for the tulip-shaped frozen wall F is about the same number of days as for the construction of a conventional frozen wall (2 months for temporary construction and 1 month for freezing), but this can be done by using a later-installed shield machine. If the work is carried out three months before the arrival of 1a, these three months will be irrelevant to the overall construction process, and the work after that will become a necessary process.

■  シールド機の到着と後着側の凍結後着シールド機
1aが、第4図に示すように、チューリップ状凍土壁F
内に到着したら、後着シールド機1aのセグメントにセ
グメント凍結板7を組立てた後、冷却用の設備と配管工
事を行なうだけで、サグメ凍結−凍結扱7の凍着が可能
となるから、従来方法のように後着シールド機laから
凍結管を埋設する作業は必要がなく、後着シール(・機
18到着に伴う前記凍土壁Fの解凍幅だけ再凍結Faさ
せて、後着シールド機1aのシールドセグメント凍結板
7と凍着させれば5M体工事に着手できる。このセグメ
ント凍結板7の仮設工と再凍結期間を含めても0.5力
月(2週間程度)の期間で充分である。
■ The arrival of the shield machine and the frozen later-arriving shield machine 1a, as shown in Figure 4,
After arriving at the destination, after assembling the segment freezing plate 7 to the segment of the later-attached shield machine 1a, the freezing of the Sagme freezing-freezing treatment 7 can be performed simply by assembling the segment freezing plate 7 on the segment of the later-attached shield machine 1a and performing the cooling equipment and piping work. Unlike the method, there is no need to bury the frozen pipe from the later-arriving shield machine la, and the later-arriving shield machine 1a is refrozen by the thawing width of the frozen soil wall F upon arrival of the later-arriving shield machine 1a. By freezing the shield segments with the freezing plate 7, construction of the 5M structure can begin.Even including the temporary construction of the segment freezing plate 7 and the refreezing period, a period of 0.5 months (about 2 weeks) is sufficient. be.

■解体、覆エ シールド機の解体と覆工は従来と同し、即ち、カッター
a、バルク室すを解体し、スチールセグメント8により
一次覆工を施して両シールl−トンネルを接合するので
ある。
(1) Disassembly and lining The dismantling and lining of the shield machine are the same as in the past, namely, the cutter a and the bulk chamber are dismantled, a primary lining is applied with steel segments 8, and both seals l-tunnels are joined.

以上の工程を総合すると、実施工程期間は、後着シール
ド機内の仮設、再凍結0.5ケ月と解体。
Putting the above processes together, the implementation process will take 0.5 months for temporary construction, refreezing, and dismantling in the later-arriving shield machine.

覆工の1〜1.5力月だけとなり、凍結地中接合が1.
5〜2力月程度の期間で完了することになり、全体の工
程に及ぼす工期は実質上、従来方法の172〜1/3に
短縮することが出来るのである。
Only 1 to 1.5 months of lining work and 1.5 months of frozen underground joints.
The process can be completed in about 5 to 2 months, and the time required for the entire process can be substantially reduced to 172 to 1/3 of the conventional method.

第2発明 この第二発明は地盤の状態その他の事情によりチューリ
ップ状の凍土壁を造成するのに不適当な場合に適したも
ので、先着シールド機1直後のセグメント10にシール
用パツキンpを介して水密且つ移動可能に削孔室11を
内装し、該削孔室11を拡巾部材12により水密に拡巾
してシールド機1の外側に突出させ、拡巾された削孔室
】1から水平凍結管13をシールド機1の外側前方に埋
設して、後着シールド機1aの口径よりやや大きめの内
径を有する円筒形状の凍土壁F′を造成しておき、後着
シールド機1aをこの凍土壁F′に貫入させ、該後着シ
ールド機1aの後方にセグメント凍結板14を組立て凍
着させて止水な行なってから、両シールド機のカッター
a、バルク室す等を解体し、スチールセグメント8等に
より一次覆工を施してシールドトンネルを接合するので
あるが、通常、削孔室の拡巾。
Second invention This second invention is suitable for cases where it is inappropriate to create a tulip-shaped frozen wall due to ground conditions or other circumstances. A hole drilling chamber 11 is installed in a watertight and movable manner, and the hole drilling chamber 11 is watertightly widened by a widening member 12 to protrude to the outside of the shielding machine 1. A horizontal frozen pipe 13 is buried outside and in front of the shield machine 1 to create a cylindrical frozen wall F' having an inner diameter slightly larger than the diameter of the later shield machine 1a. After penetrating the frozen soil wall F' and assembling the segment freezing plate 14 behind the later-attached shield machine 1a and freezing it to stop water, the cutter a, bulk chamber, etc. of both shield machines are dismantled, and the steel The shield tunnel is joined by applying a primary lining using segments 8, etc., but usually the width of the drilling chamber is expanded.

水平凍結管の埋設及び凍結と後着シールド機の到着と後
着側の凍結は次のようにして行なう。
The burying and freezing of the horizontal freezing pipe, the arrival of the later-arriving shield machine, and the freezing of the later-arriving side are carried out as follows.

■塑」jし久鉱辿− 前記セグメント10に内装した削孔室11には画盤21
を定着し、この画盤2Iの外側にカッターフェイス22
、内側に該カンタ−フェイス22を駆動するモータMを
、それぞれ2個ずつ装着しておき、シールド機上が所定
の位置の1〜2m手前に着いたら、前記セグメント10
を通常のセグメントと同様にして組み立てる。
■Plastics” J Shi Hisaoi- The drilling chamber 11 installed in the segment 10 has a drawing board 21.
Fix the cutter face 22 on the outside of this drawing board 2I.
, two motors M for driving the canter face 22 are installed inside each, and when the top of the shield machine reaches 1 to 2 meters before the predetermined position, the segment 10
Assemble the segments in the same way as normal segments.

而して、シールド機1が所定の位置に到達し停止したら
、モータMを駆動してカンタ−フェイス22を回転させ
ながら同時に画盤21に設けである泥水供給口23から
泥水を送り込み、同じく削泥取扱み口24から土砂を排
出する。
When the shielding machine 1 reaches a predetermined position and stops, the motor M is driven to rotate the canterface 22 while simultaneously feeding muddy water from the muddy water supply port 23 provided on the drawing board 21, and also cutting. The earth and sand are discharged from the mud handling port 24.

一方、内装用セグメントの内側に反力受け25を仮設し
、削孔室11の内側にその拡巾部材12を溶接等により
水密に接続して、反力受けに取付けたジヤツキ26によ
り押し上げて削孔室11を拡巾して行き、削孔室】1が
その先端が所定の位置に達するまで拡巾されたら、次の
削孔室を同様にして拡巾し、シールドトンネルの全周に
亘り拡巾されてシールドトンネルの外側に突出した削孔
室11を形成する。
On the other hand, a reaction force receiver 25 is temporarily installed inside the interior segment, and the widening member 12 is watertightly connected to the inside of the drilling chamber 11 by welding or the like, and the jack 26 attached to the reaction force receiver is used to push it up and cut the hole. The width of the hole chamber 11 is expanded until the tip of the hole hole chamber 1 reaches a predetermined position, and then the next hole chamber is expanded in the same way to cover the entire circumference of the shield tunnel. A drilling chamber 11 is formed which is widened and protrudes to the outside of the shield tunnel.

(牙水玉遠栽1夏工笠、遠藝 上記のようにして削孔室11を拡巾したら、次に該削孔
室11から水平凍結管13を埋設して行くのであるが、
削孔室11はその長さが短いので、水平凍結管13は短
尺の鋼管ピースを接続して構成しなければならないため
、削孔用と凍結用とに分けて、削孔用鋼管は3.5〜4
B、長さ20〜30cmのねし込み管を使用し、その中
に2〜2.5Bの凍結用鋼管を溶接等により接続、挿入
して凍結管13とするのである。尚、凍結管13を削孔
用と凍結用の二重管構造にしたのは、冷却溶媒の漏洩に
より凍土が侵食されるのを防止するためである。また、
この凍結管13の埋設は拡巾部材12内に削孔用パッカ
ー27を設置して行なうものとする。
(Fang Water Ball Encai 1 Summer Technology Kasa, Engei After widening the drilling chamber 11 as described above, the horizontal freezing pipe 13 is then buried from the drilling chamber 11.
Since the length of the drilling chamber 11 is short, the horizontal freezing pipe 13 must be constructed by connecting short steel pipe pieces. 5-4
B. A threaded pipe with a length of 20 to 30 cm is used, and a 2 to 2.5 B freezing steel pipe is connected and inserted into the pipe by welding or the like to form the freezing pipe 13. The reason why the freezing pipe 13 has a double pipe structure for drilling and freezing is to prevent the frozen soil from being eroded by leakage of the cooling solvent. Also,
The freezing tube 13 is buried by installing a hole drilling packer 27 inside the width expanding member 12.

上記により埋設された凍結管13に冷却溶媒を循環させ
てその周辺の地盤を凍結して行くと、円筒形状の凍土壁
F′が造成される。
When the cooling solvent is circulated through the buried freezing pipe 13 as described above and the ground around it is frozen, a cylindrical frozen wall F' is created.

而して、■の削孔室の拡巾に約1カ月を要し、また、凍
結管の埋設と凍結に従来の凍土壁の造成と同し程度の日
数を要するが、準備下と仮設工を平行作業で実施するよ
うにし、これらの作業を後着シールド機が到着する3力
月前から実施すれば、工程上はこの3力月が工事全体の
工程とは無関係になり、それ以降の作業が必要工程とな
る。
Therefore, it takes about one month to expand the width of the drilling room in (■), and it takes about the same number of days to bury and freeze the frozen pipe as it does to create a conventional frozen soil wall, but it takes a lot of time during preparation and temporary construction. If these tasks are carried out in parallel, and if these tasks are carried out three months before the arrival of the later-arriving shield machine, these three months will be unrelated to the overall construction process, and subsequent work will be The work becomes a necessary process.

■後着シールド機の到着後の後着側の凍結上記の凍土壁
F′内に後着シールド機1aを進入させ、該シールド機
18が所定位置まで進入したら、その後方にセグメント
凍結板14を組み立て、冷却装置(図示せず)を設置し
て、前記凍土壁F″とセグメント凍結板14を凍着させ
る。
■ Freezing of the rear-arriving side after the arrival of the later-arriving shield machine The later-arriving shield machine 1a enters the above-mentioned frozen soil wall F', and when the shield machine 18 enters the predetermined position, the segment freezing plate 14 is placed behind it. Assemble and install a cooling device (not shown) to freeze the frozen soil wall F'' and the segment freezing plate 14.

その他は第一発明と同様である。The rest is the same as the first invention.

■解体、覆工 第一発明におけるそれと同様である。■Demolition, lining This is similar to that in the first invention.

以上の工程を総合すると、接合工程に要する工期は、削
孔室11の拡巾に要する工期及び凍土の造成は凍結地中
接合に含まれないので、後着シールド機内の仮設、再凍
結0.5力月と、解体、覆工の1〜1.5力月だけとな
り、凍結地中接合が1.5〜2力月程度の期間で終了す
ることになり、従来方法に比べて大幅に工期を短縮でき
る。
Taking all the above steps into account, the construction period required for the joining process is 0.2%, since the construction period required for expanding the width of the drilling chamber 11 and the creation of frozen soil are not included in the frozen underground joining process. It will take only 5 months and 1 to 1.5 months for demolition and lining, and the frozen underground bonding will be completed in about 1.5 to 2 months, significantly reducing the construction time compared to conventional methods. can be shortened.

〔発明の効果〕〔Effect of the invention〕

本発明は上述の通りであって、2台対向させ発進、掘進
させてシールドトンネルを形成すべきシールド機のシー
ルドトンネルを接合すべき地点への到着時期をずらし、
先着のシールド機の先端側に後着のシールド機が貫入出
来る横向きチューリップ状の凍土壁又は後着シールド機
の口径よりやや大きい内径を有する円筒形状の凍土壁を
造成して、該凍土壁内に後着のシールド機を貫入させ。
The present invention is as described above, and involves staggering the timing of arrival of two shield machines that are to be started and excavated in opposition to each other to form a shield tunnel at a point where the shield tunnels are to be joined.
A horizontal tulip-shaped frozen wall that allows the subsequent shield machine to penetrate, or a cylindrical frozen wall with an inner diameter slightly larger than the diameter of the later-arrived shield machine, is created on the tip side of the first-arriving shield machine, and inside the frozen soil wall. Infiltrate the shield machine that arrived later.

後着のシールド機の後方にセグメント凍結板を組立るか
又は貼付凍結管を設備して、後部の凍着止水を行なうの
みで、後は常法により両シールド機のカッターやバルク
室を解体して、−法覆工を施工すれば、シールドトンネ
ルを接合できるから、その接合のための工事期間は従来
方法に比し、著しく短縮でき、これに伴って工事費の大
幅な節減を図ることが出来る。
All you need to do is assemble a segment freezing plate or install a pasted freezing pipe at the rear of the later shield machine to stop freezing water at the rear, and then dismantle the cutters and bulk chambers of both shield machines using the usual method. Then, by constructing the method lining, the shield tunnel can be joined, so the construction period for the joining can be significantly shortened compared to the conventional method, and the construction cost can be significantly reduced accordingly. I can do it.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は、凍結管を埋設する状態を示す図で
、第1図は地山の安定状態が良好な場合の説明図、第2
図は地山の安定状態が悪い場合の説明図、第3図はチュ
ーリップ状の凍土を造成した状態の断面図、第4図は後
着シールド機が到着し、その後方を凍結した状態の断面
図、第5図はシールド機の内部を解体し、−法覆工を施
工して接合した状態を示す断面図、第6図は第二発明に
より先着シールド機の前方に円筒形状の凍土壁を造成し
て後着シールド機を貫入し、その後方を到着した状態の
断面図、第7図は削孔室の拡巾前の横断面図、第8図は
同じく縦断面図、第9図は平面図、第10図及び第11
図は従来方法の説明図である。 1・・・先着のシールド機、1a・・・後着のシールド
機、2・・・シールド鋼板、3・・・パッカー、4・・
・可撓性凍結管、5・・推進管、6・・・充填剤、7・
・・セグメント凍結板、F・・チューリップ状凍土壁、
Fa・・・再凍結、10・・セグメント、11・・削孔
室、12・・・拡巾部材、13凍結管。 14・・・セグメント凍結板、 21・画盤、 カッタ フェイス、 M・・モータ
Figures 1 and 2 are diagrams showing the state in which frozen pipes are buried; Figure 1 is an explanatory diagram when the ground is in a stable state;
The figure is an explanatory diagram when the stability of the ground is poor, Figure 3 is a cross-sectional view of the state where tulip-shaped frozen soil has been created, and Figure 4 is a cross-section of the state where the late-arriving shield machine has arrived and the area behind it is frozen. Figure 5 is a cross-sectional view showing the state in which the inside of the shield machine has been disassembled and the lining has been installed and joined, and Figure 6 is a cylindrical frozen wall in front of the first-come-first-served shield machine according to the second invention. A cross-sectional view of the hole after it has been drilled and penetrated by a later-arriving shield machine, Figure 7 is a cross-sectional view of the drilling chamber before it is widened, Figure 8 is a longitudinal cross-sectional view of the hole, and Figure 9 is a vertical cross-sectional view of the same. Plan view, Figures 10 and 11
The figure is an explanatory diagram of a conventional method. 1... First-arriving shield machine, 1a... Later-arriving shield machine, 2... Shield steel plate, 3... Packer, 4...
・Flexible freezing tube, 5. Propulsion tube, 6. Filler, 7.
・・Segment frozen plate, F・・Tulip-shaped frozen soil wall,
Fa: Refreeze, 10: Segment, 11: Drilling chamber, 12: Width expansion member, 13: Freezing tube. 14...Segment freezing plate, 21.Panel, cutter face, M...Motor

Claims (1)

【特許請求の範囲】 1 2台のシールド機を対向させ地中を掘進させてシー
ルドトンネルを形成し接合するシールドトンネルの接合
方法において、接合すべき地点におけるシールド機の到
着時期をずらし、先着したシールド機の内部から操向性
ボーリングにより円弧状又は曲線状に地山を削孔して、
該掘削孔に可撓性の凍結管を挿入し、後着シールド機の
到着時期に合わせて横向きチューリップ状の凍土壁を造
成しておき、該凍土壁内に後着シールド機を貫入させた
後、後着シールド機の後方にセグメント凍結板を組立て
るか又は貼付凍結管を設置するなどして後部止水を行な
ってから、シールド機のカッター,バルク室等を解体し
、スチールセグメント等により一次覆工を施してシール
ドトンネルを接合することを特徴とするシールドトンネ
ルの地中接合方法。 2 2台のシールド機を対向させ地中を掘進させてシー
ルドトンネルを形成し接合するシールドトンネルの接合
方法において、接合すべき地点におけるシールド機の到
着時期をずらし、先着したシールド機の直後のセグメン
トに、水平凍結管理設用の削孔室を拡巾構築できる機構
を内装させ、後着シールド機が前記所定の地点に到達す
るまでの期間中に拡巾した削孔室から水平凍結管を、後
着するシールド機のテール部分まで埋設して、該シール
ド機の口径よりやや大きい円筒形状の凍土壁を造成し、
後着シールド機が前記凍土壁内に到着した後、該後着シ
ールド機の後方にセグメント凍結板を組立るか又は凍着
用設備を設置するなどして後部止水を行なってから、シ
ールド機のカッター,バルク室等を解体し、スチールセ
グメント等により一次覆工を施工して、シールドトンネ
ルを接合することを特徴とするシールドトンネルの接合
方法。
[Claims] 1. In a shield tunnel joining method in which two shield machines face each other and dig underground to form and join a shield tunnel, the timing of the arrival of the shield machines at the point to be joined is staggered, and the shield tunnel is first arrived at. Drilling holes in the ground in an arc or curve shape using steerable boring from inside the shield machine,
A flexible freezing pipe is inserted into the excavation hole, a horizontal tulip-shaped frozen wall is created in time for the arrival of the later-arriving shield machine, and after the later-arriving shield machine is penetrated into the frozen soil wall. After assembling a segment freezing plate or installing a pasted freezing pipe at the rear of the shield machine, the water is stopped at the rear of the shield machine, and then the cutter, bulk chamber, etc. of the shield machine are dismantled, and the primary covering is made with steel segments, etc. An underground joining method for shield tunnels, which is characterized by joining shield tunnels by performing construction. 2. In the method of joining shield tunnels, in which two shield machines face each other and dig underground to form and join a shield tunnel, the timing of the arrival of the shield machines at the point to be joined is staggered, and the segment immediately after the first shield machine arrives. A mechanism that can expand the width of the drilling chamber for horizontal freezing management equipment is installed, and the horizontal freezing pipe is inserted from the expanded drilling chamber during the period until the later-arriving shield machine reaches the predetermined point. Bury up to the tail of the shield machine that will arrive later, and create a cylindrical frozen wall that is slightly larger than the diameter of the shield machine.
After the later-arriving shield machine arrives within the frozen soil wall, water is stopped at the rear by assembling a segment freezing plate or installing freezing equipment behind the latter-applying shield machine, and then the shield machine is operated. A method for joining a shield tunnel, which comprises dismantling cutters, bulk chambers, etc., constructing a primary lining using steel segments, etc., and joining the shield tunnel.
JP22135990A 1990-08-24 1990-08-24 Underground joining method of shield tunnel Expired - Lifetime JPH06102957B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22135990A JPH06102957B2 (en) 1990-08-24 1990-08-24 Underground joining method of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22135990A JPH06102957B2 (en) 1990-08-24 1990-08-24 Underground joining method of shield tunnel

Publications (2)

Publication Number Publication Date
JPH04106293A true JPH04106293A (en) 1992-04-08
JPH06102957B2 JPH06102957B2 (en) 1994-12-14

Family

ID=16765560

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22135990A Expired - Lifetime JPH06102957B2 (en) 1990-08-24 1990-08-24 Underground joining method of shield tunnel

Country Status (1)

Country Link
JP (1) JPH06102957B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264717A (en) * 2004-02-19 2005-09-29 Kajima Corp How to freeze the ground
CN104695964A (en) * 2013-12-04 2015-06-10 宏润建设集团股份有限公司 Subway shield tunnel freeze entering method
JP2017150174A (en) * 2016-02-23 2017-08-31 清水建設株式会社 Freezing method
CN108843336A (en) * 2018-07-02 2018-11-20 中国铁建重工集团有限公司 Development machine, development machine cutterhead and cutter replacing method
CN109403987A (en) * 2018-12-11 2019-03-01 南京林业大学 Shield end horizontal frozen combines reception device and construction method with short steel case
JP2019131964A (en) * 2018-01-29 2019-08-08 鹿島建設株式会社 Flow suppressing method
CN112127942A (en) * 2020-08-24 2020-12-25 中铁第四勘察设计院集团有限公司 Connection structure of evacuation platform in shield zone at interconnection channel
CN112302669A (en) * 2020-12-01 2021-02-02 长江勘测规划设计研究有限责任公司 A kind of auxiliary construction method and structure for subway shield tunnel arrival under complex environmental conditions
JP2022524893A (en) * 2019-03-22 2022-05-10 ハイパートンネル アイピー リミティッド Methods and systems for constructing underground tunnels
CN115288700A (en) * 2022-01-11 2022-11-04 浙江理工大学 Shield tunneling machine fault freezing method front-dismantling method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264717A (en) * 2004-02-19 2005-09-29 Kajima Corp How to freeze the ground
CN104695964A (en) * 2013-12-04 2015-06-10 宏润建设集团股份有限公司 Subway shield tunnel freeze entering method
JP2017150174A (en) * 2016-02-23 2017-08-31 清水建設株式会社 Freezing method
JP2019131964A (en) * 2018-01-29 2019-08-08 鹿島建設株式会社 Flow suppressing method
CN108843336A (en) * 2018-07-02 2018-11-20 中国铁建重工集团有限公司 Development machine, development machine cutterhead and cutter replacing method
CN108843336B (en) * 2018-07-02 2024-02-02 中国铁建重工集团股份有限公司 Heading machine, heading machine cutterhead and cutter changing method
CN109403987A (en) * 2018-12-11 2019-03-01 南京林业大学 Shield end horizontal frozen combines reception device and construction method with short steel case
CN109403987B (en) * 2018-12-11 2023-10-20 南京林业大学 Shield end horizontal freezing and short steel box combined receiving device and construction method
US11591908B2 (en) 2019-03-22 2023-02-28 Hypertunnel Ip Limited Method and system of constructing an underground tunnel
JP2022524893A (en) * 2019-03-22 2022-05-10 ハイパートンネル アイピー リミティッド Methods and systems for constructing underground tunnels
CN112127942A (en) * 2020-08-24 2020-12-25 中铁第四勘察设计院集团有限公司 Connection structure of evacuation platform in shield zone at interconnection channel
CN112302669A (en) * 2020-12-01 2021-02-02 长江勘测规划设计研究有限责任公司 A kind of auxiliary construction method and structure for subway shield tunnel arrival under complex environmental conditions
CN115288700A (en) * 2022-01-11 2022-11-04 浙江理工大学 Shield tunneling machine fault freezing method front-dismantling method

Also Published As

Publication number Publication date
JPH06102957B2 (en) 1994-12-14

Similar Documents

Publication Publication Date Title
JP4958035B2 (en) Shield roof construction method
CN109869159B (en) A kind of shield construction method of communication channel
JP4793655B2 (en) Tunnel construction method
JP2007217911A (en) Cavity construction method and tunnel construction method
JP4771170B2 (en) Construction method of underground cavity
AU2015317071A1 (en) Method and installation for mechanised digging of a cross-passage between two traffic tunnels or between two vertical shafts
JPH04106293A (en) Underground connection method of shield tunnel
JP4471521B2 (en) Shield construction method, large section tunnel and its construction method, and shield machine
JP3860143B2 (en) Excavator for pipe roof and pipe roof construction method using them
JP2942874B2 (en) How to join tunnels
JP3851590B2 (en) Preceding ground mountain consolidation method using self-drilling bolt and FRP bolt
JP2663106B2 (en) Construction method of outer wall of propulsion pipe and large cavity
JP3710991B2 (en) Ground reinforcement method
JP2849605B2 (en) Large section tunnel and its construction method
JP2551506B2 (en) Construction method of arch shell in tunnel precedent
JPH0462299A (en) Larger section tunnel and construction method thereof
JPS62258096A (en) Method of underground joining construction of shield-tunnel
JP7162501B2 (en) Outer shell shield construction method using shield starting base and circumferential tunnel
JP3515046B2 (en) Ground reinforcement method
JP7026562B2 (en) Tunnel construction method
JPS62258095A (en) Method of underground joining construction of shield-tunnel
JPH07116907B2 (en) Shield tunnel joining method
JPH0423994Y2 (en)
JPH04106292A (en) Widening method of shield tunnel
JPS62258094A (en) Method of underground joining construction of shield-tunnel

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081214

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081214

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091214

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091214

Year of fee payment: 15

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101214

Year of fee payment: 16

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101214

Year of fee payment: 16