JPH04104288U - Automatic welding machine for ready-made piles - Google Patents
Automatic welding machine for ready-made pilesInfo
- Publication number
- JPH04104288U JPH04104288U JP1285091U JP1285091U JPH04104288U JP H04104288 U JPH04104288 U JP H04104288U JP 1285091 U JP1285091 U JP 1285091U JP 1285091 U JP1285091 U JP 1285091U JP H04104288 U JPH04104288 U JP H04104288U
- Authority
- JP
- Japan
- Prior art keywords
- welding
- torch
- cart
- pile
- attached
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
(57)【要約】
【目的】 溶接時間の短縮を図り、施工能率の向上及び
コストダウンを図る
【構成】 杭1の外周上に固定したガイドレール4に駆
動台車5を走行自在に取付け、この駆動台車5の走行方
向の前後に連結金具11,12を介して溶接台車6を連
結し、各溶接台車6に1又は複数の溶接用トーチ39を
取付けたことを特徴としている。
(57) [Summary] [Purpose] To reduce welding time, improve construction efficiency, and reduce costs. [Structure] A driving trolley 5 is movably attached to a guide rail 4 fixed on the outer periphery of a pile 1. The welding carts 6 are connected to the front and rear of the driving cart 5 through connecting fittings 11 and 12 in the running direction, and one or more welding torches 39 are attached to each welding cart 6.
Description
【0001】0001
この考案は、上下に接合する既製杭を自動的に溶接する自動溶接機、特に駆動 台車に連結した溶接台車に取付けた溶接トーチを、継手部の周囲を旋回させなが ら溶接する自動溶接機に関するものである。 This invention is an automatic welding machine that automatically welds prefabricated piles that are joined above and below. The welding torch attached to the welding cart connected to the cart is rotated around the joint. This invention relates to an automatic welding machine for welding.
【0002】0002
杭の溶接方法として従来、半自動又は全自動溶接機により多層溶接することが 一般的であるが、杭の多層溶接においては上下の杭相互の継手部を突合せること によりその周囲できた溶接開先の周囲に、杭の周囲を旋回走行する走行架台に取 付けた一本のアーク溶接トーチを旋回させながら一層目の溶着金属の盛り上げを 全周に渡って行い、その後において再び一本のアーク溶接トーチを開先周囲に旋 回させながら、一層目の溶着金属上に重ねて二層目の溶着金属の盛り上げを全周 に渡って行なうという多段階操作により溶接しているのが現状である。 Conventionally, the method of welding piles is multi-layer welding using a semi-automatic or fully automatic welding machine. Generally speaking, in multi-layer welding of piles, the joints of the upper and lower piles are butted against each other. Around the weld groove created by Build up the first layer of weld metal by rotating the attached arc welding torch. Weld around the entire circumference, then rotate the single arc welding torch around the groove again. While rotating, overlap the first layer of weld metal and apply the second layer of weld metal all the way around. Currently, welding is a multi-step process that involves several steps.
【0003】 しかしながら、このような多段階溶接では、一回の多層溶接にアーク溶接トー チを二回以上旋回させ、しかも一層目の溶接後その表面にできる溶接スラグを除 去し、更に溶接トーチの位置を調節した上で二層目を溶接するという作業を伴う ため、溶接作業が煩雑で時間がかかり、作業効率が悪いという問題があった。0003 However, in such multi-step welding, arc welding torque is required for one multi-layer welding. The welding slag that forms on the surface of the first layer after welding is removed. This involves removing the welding material, adjusting the position of the welding torch, and then welding the second layer. Therefore, there was a problem that welding work was complicated and time-consuming, and work efficiency was poor.
【0004】 そのため、本出願人らは先に、杭周囲に設けたガイドレールに駆動台車とこれ に連結した1台のトーチ台車を走行自在に設置し、このトーチ台車にその走行方 向に所定間隔で複数のアーク溶接トーチを取付け、この溶接トーチをトーチ台車 と共に杭継手部の開先周囲に旋回させ、その旋回方向前方に位置するアーク溶接 トーチにより溶接した溶接スラグが硬化する前に、その上に重ねて後続のアーク 溶接トーチにより次層の溶着金属を盛り上げることにより、アーク溶接トーチを 一回旋回させるだけで多層溶接を完了させ、しかもスラグの除去や溶接トーチの 位置の調節を要することなく極めて単純に杭の溶接を行い得るようにした溶接装 置を開発し、既に特願平1−324619号として特許出願した。0004 For this reason, the applicants first installed a drive carriage on the guide rail installed around the pile. A torch trolley connected to the Install multiple arc welding torches at predetermined intervals in the direction of the The arc welding is rotated around the groove of the pile joint, and the arc welding is located in front of the groove in the direction of rotation. Before the welding slag welded by the torch hardens, it is layered on top of the welding slag for the subsequent arc. The arc welding torch is used to raise the next layer of weld metal with the welding torch. Multi-layer welding can be completed with just one rotation, and slag removal and welding torch A welding device that allows pile welding to be performed extremely simply without the need for position adjustment. The company has developed a new system and has already filed a patent application as Japanese Patent Application No. 1-324619.
【0005】 そして、この多層溶接装置においては溶接能率を向上するものであるが、駆動 台車に連結した溶接台車が1台であるため、2本の溶接トーチで全周を溶接する ためには杭周囲を一回旋回しなければならないものであった。[0005] Although this multi-layer welding device improves welding efficiency, the drive Since there is only one welding cart connected to the cart, two welding torches are used to weld the entire circumference. In order to do so, one had to circle around the pile once.
【0006】[0006]
この考案は、上記従来技術において、杭外周上を複数回旋回しなければ所定の 肉盛溶接ができないため、杭径が大きくなる程溶接時間が長くなり施工能率が低 下するという問題点を解決することにある。 This invention differs from the conventional technology described above in that it is necessary to turn the pile multiple times on the outer circumference of the pile. Since overlay welding is not possible, the larger the pile diameter, the longer welding time and lower construction efficiency. The aim is to solve the problem of lowering
【0007】[0007]
この考案は前記従来の問題点を解決するために、杭1の外周上に固定した円環 状のガイドレール4に駆動台車5を走行自在に取付け、この駆動台車5の走行方 向の前後に連結金具11,12を介して溶接用トーチ台車6を連結した既製杭用 自動溶接機を提案するものである。 In order to solve the above-mentioned conventional problems, this invention is based on a circular ring fixed on the outer periphery of the pile 1. A driving cart 5 is attached to a guide rail 4 having a shape such that it can run freely, and the way in which this driving cart 5 runs is For ready-made piles with welding torch carts 6 connected via connecting fittings 11 and 12 at the front and rear of the direction. We propose an automatic welding machine.
【0008】[0008]
駆動台車5が杭1の外周上に固着されたガイドレール4上を駆動するとき、そ の前後に連結された溶接台車6が連動して走行移動し、これに取付けた溶接トー チ39,39’が杭継手部の開先周囲に旋回して溶接作業が行われる。 When the driving cart 5 drives on the guide rail 4 fixed on the outer periphery of the pile 1, A welding trolley 6 connected to the front and rear of the The welding work is performed by turning the grooves 39 and 39' around the groove of the pile joint.
【0009】 このときの1台の溶接台車6の溶接範囲、すなわち駆動台車5の移動距離は全 溶接範囲対して、取付けられた溶接台車6の個数分の1の距離となる。[0009] At this time, the welding range of one welding cart 6, that is, the moving distance of the driving cart 5 is the entire The distance is 1/the number of welding carts 6 attached to the welding range.
【0010】 例えば、溶接台車6が図1のように杭周の二等分点に二台配置されている場合 には、駆動台車5がレール4上を半回転すると全周が溶接され、1台の溶接台車 6に一本の溶接トーチ39を取付けた場合には、半周で1層、一周で二層の溶接 が行われ、多層溶接が完了する。0010 For example, when two welding carts 6 are placed at the bisecting points of the pile circumference as shown in Figure 1, When the driving cart 5 rotates half a turn on the rail 4, the entire circumference is welded, and one welding cart is formed. When one welding torch 39 is attached to 6, one layer welds in half the circumference and two layers welds in one circumference. is carried out, and multilayer welding is completed.
【0011】 また一台の溶接台車6に左右に複数のアーク溶接トーチを取付けた場合には、 その旋回方向前方に位置するアーク溶接トーチ39により一層目の溶着金属が盛 り上げられ、この一層目の溶着金属が硬化する前に、その上に重ねて後続のアー ク溶接トーチ39’により次層の溶着金属が盛り上げられ、溶接台車6を半周旋 回させるだけで多層溶接を完了させることができ、溶接台車6の数を増すほど旋 回範囲を少なくして短時間に溶接を完了することになる。[0011] In addition, when multiple arc welding torches are attached to the left and right sides of one welding cart 6, The first layer of weld metal is deposited by the arc welding torch 39 located in front of the rotating direction. This first layer of weld metal is then layered on top of it before it hardens. The next layer of weld metal is raised by the welding torch 39', and the welding cart 6 is rotated semicircularly. Multi-layer welding can be completed simply by turning the welding carts 6, and as the number of welding carts 6 increases, the turning Welding can be completed in a short time by reducing the number of times.
【0012】0012
以下この発明を図面に示す実施例について説明すると、下杭1’の上端継手部 上に下端継手部を重ねた上杭1の周囲にはレール固定脚2が固定ネジ3により取 付けられ、このレール固定脚2の外周に取付けた円環状のガイドレール4に、図 1に示すように駆動台車5及びその走行方向の前後に連結した溶接台車6がそれ ぞれ旋回走行自在に複数台取付けられている。 Hereinafter, an embodiment of the present invention shown in the drawings will be described. A rail fixing leg 2 is attached with a fixing screw 3 around the upper pile 1 on which the lower end joint is placed. The annular guide rail 4 attached to the outer periphery of the rail fixing leg 2 is As shown in FIG. 1, the driving truck 5 and the welding truck 6 connected to the front and rear in the running direction are Multiple units are installed so that each can rotate freely.
【0013】 駆動台車5は図2及び図3に示すように、その背面に取付けた上下の車輪7を ガイドレール4の上下に係合させ、ガイドレール4の表面に取付けたラックレー ル8に噛み合う中間の駆動ピニオン車輪9を変速モーターで回転駆動することに より、上杭1の周囲を旋回走行するように構成されている。[0013] As shown in FIGS. 2 and 3, the drive truck 5 has upper and lower wheels 7 attached to its back. A rack rack that is engaged with the top and bottom of the guide rail 4 and attached to the surface of the guide rail 4. The intermediate driving pinion wheel 9 that meshes with the wheel 8 is rotationally driven by a variable speed motor. Therefore, it is configured to rotate around the upper pile 1.
【0014】 各溶接台車6は図4〜図6に示すように、その背面に取付けた上下の車輪10 をガイドレール4の上下に係合させて走行し、それらの端部と駆動台車5の前後 端との間に連結した円弧状の連結具11,12により駆動台車5に連結して牽引 走行されるようになっている。[0014] Each welding cart 6 has upper and lower wheels 10 attached to its back as shown in FIGS. 4 to 6. are engaged with the upper and lower parts of the guide rail 4, and their ends and the front and rear of the drive carriage 5 are connected to each other. It is connected to the drive cart 5 by arc-shaped connectors 11 and 12 connected between the ends and is towed. It is designed to be driven.
【0015】 なお、図示の実施例では2台連結した溶接台車6を杭周の2等分点に配置した が、例えば3台連結して3等分点に配置するなど、必要に応じて複数台で各種の 等分配置が可能である。[0015] In addition, in the illustrated example, two connected welding carts 6 are arranged at bisecting points of the circumference of the pile. However, if necessary, multiple units can be used to perform various tasks, such as connecting three units and placing them at three equal points. Equal distribution is possible.
【0016】 溶接台車6の表面には、昇降ロッド13を摺動自在に包持した複数(図では3 個)の溝型のガイドホルダー14が左右に間隔を置いて取付けられ、各ガイドホ ルダー14には昇降ロッド13の側面に形成したラック15に噛み合うピニオン ギヤ16が回転自在に支承されており、このピニオンギヤ16の支軸17を回転 摘まみ18にて回転することにより、各昇降ロッド13の上下位置を昇降調節し 、それぞれ所要位置においてクランプネジ19により締付け固定できるように構 成されている。[0016] On the surface of the welding cart 6, there are a plurality of lifting rods 13 (three in the figure) that slidably support the lifting rods 13. ) groove-shaped guide holders 14 are installed at intervals on the left and right, and each guide holder is The lever 14 has a pinion that engages with a rack 15 formed on the side of the lifting rod 13. A gear 16 is rotatably supported, and a support shaft 17 of this pinion gear 16 is rotated. By rotating the knob 18, the vertical position of each lifting rod 13 can be adjusted up and down. , each is structured so that it can be tightened and fixed at the required position with a clamp screw 19. has been completed.
【0017】 各昇降ロッド13の下端には、溶接台車6の前方に水平に突出したガイドロッ ド20が設けられ、このガイドロッド20にこれを包持するように溝型の移動ホ ルダー21が進退自在に取付けられ、この移動ホルダー21にはガイドロッド2 0の上面に形成したラック22に噛み合うピニオンギヤ23が回転自在に支承さ れており、このピニオンギヤ23の支軸24を回転摘まみ25にて回転すること により、各移動ホルダー21の前後位置を進退調節し、それぞれ所要位置におい てクランプネジ26により締付け固定できるように構成されている。[0017] A guide rod protruding horizontally in front of the welding cart 6 is provided at the lower end of each lifting rod 13. A groove-shaped moving holder is provided to surround the guide rod 20. A guide rod 21 is attached to the movable holder 21 so as to move forward and backward. A pinion gear 23 that meshes with a rack 22 formed on the top surface of 0 is rotatably supported. The spindle 24 of this pinion gear 23 can be rotated with a rotation knob 25. adjust the forward and backward position of each movable holder 21, and place each movable holder 21 at the desired position. It is configured such that it can be tightened and fixed using a clamp screw 26.
【0018】 各移動ホルダー21には水平のブラケット27が突設され、その底面にトーチ 狭着基板28又は28’が縦の枢軸29により水平旋回自在に取付けられており 、各トーチ狭着基板28,28’には枢軸29を曲率中心とする円弧スリット3 0が設けられ、トーチ狭着基板28の下方から円弧スリット30を通してブラケ ット27の通孔に挿通されたクランプボルト31の突出上端にナット32をねじ 込み、各トーチ狭着基板28,28’を所要旋回位置において固定できるように なっている。[0018] A horizontal bracket 27 is protruded from each movable holder 21, and a torch is attached to the bottom of the bracket 27. A sandwiching board 28 or 28' is mounted so as to be horizontally pivotable by a vertical pivot 29. , each torch clamping board 28, 28' has a circular arc slit 3 with the pivot axis 29 as the center of curvature. 0 is provided, and the bracket is inserted through the arcuate slit 30 from below the torch-clamping board 28. Screw the nut 32 onto the protruding upper end of the clamp bolt 31 inserted into the through hole of the nut 27. so that each torch clamping board 28, 28' can be fixed at a required rotation position. It has become.
【0019】 溶接台車6の走行方向の前端側及び後端側に位置するガイドロッド20におけ るトーチ狭着基板28の下方には、V型状のトーチ狭着板33がその左右のフラ ンジ状端部において締結ボルト34により取付けられている。[0019] In the guide rods 20 located at the front end side and the rear end side of the welding cart 6 in the traveling direction, Below the torch clamping board 28, a V-shaped torch clamping plate 33 is attached to the left and right flaps. It is attached by a fastening bolt 34 at the hinged end.
【0020】 溶接台車6の走行方向の中間に位置するガイドロッド20におけるトーチ狭着 基板28’は、本来上記トーチ狭着基板28と構成上同じでよいが、本実施例に おいては設計上上記トーチ狭着基板28,28間の間隔を狭くしたために、これ らに重なることを避ける必要上、その下方に垂直部35を設け、これに水平に相 対してトーチ狭着板36がその左右のフランジ状端部において締結ボルト37に より取付けられている。[0020] Torch jamming in the guide rod 20 located in the middle of the welding cart 6 in the running direction The substrate 28' may originally have the same structure as the torch-clamping substrate 28, but in this embodiment, In this case, the space between the torch-clamping boards 28, 28 was narrowed due to the design. In order to avoid overlapping the other parts, a vertical part 35 is provided below the vertical part 35, and a horizontal part 35 is provided below it. On the other hand, the torch clamping plate 36 is attached to the fastening bolt 37 at its left and right flange-shaped ends. More installed.
【0021】 溶接台車6の旋回方向の前端側に位置するトーチ狭着基板28とトーチ狭着板 33との間には、予熱用ガストーチ38がその本体部において狭着固定され、同 中間に位置するトーチ狭着基板28’の垂直部35とトーチ狭着板36との間、 および後端側に位置するトーチ狭着基板28とトーチ狭着板33との間には、半 自動又は全自動アーク溶接トーチ39の把手部並びに同様のアーク溶接トーチ3 9’の本体部が、それぞれトーチ先端を杭周側に向けて狭着固定されている。[0021] A torch clamping board 28 and a torch clamping plate located on the front end side of the welding cart 6 in the rotating direction 33, a preheating gas torch 38 is narrowly fixed in its main body, and the same Between the vertical portion 35 of the torch-clamping board 28' located in the middle and the torch-clamping plate 36, There is a half space between the torch sandwiching board 28 and the torch sandwiching plate 33 located on the rear end side. Handle of automatic or fully automatic arc welding torch 39 and similar arc welding torch 3 The main body parts of 9' are narrowly fixed with the torch tips facing toward the circumferential side of the pile.
【0022】 溶接台車5の旋回方向の後端に設けたブラケット40には、先端部に取付けた スラグ除去用ブラシ41を回転駆動する本体部42が取付けられている。[0022] A bracket 40 provided at the rear end of the welding cart 5 in the rotating direction has a bracket attached to the tip. A main body portion 42 is attached to rotate the slag removal brush 41.
【0023】 以上のように構成された全自動溶接機を用いて上杭1とその上に載置した下杭 1’相互の溶接を行う際には、上杭1の周囲に固定ベース2を取付け、この固定 ベース2のガイドレール4に駆動台車5及び溶接台車6を取付け、両者を連結具 11により連結する。[0023] Using the fully automatic welding machine configured as above, upper pile 1 and lower pile placed on top of it 1' When performing mutual welding, attach the fixing base 2 around the upper pile 1, and Attach the drive cart 5 and welding cart 6 to the guide rail 4 of the base 2, and connect them with a connecting device. Connected by 11.
【0024】 次に、溶接台車6の回転摘まみ18にて各昇降ロッド13の上下位置を昇降調 節し、予熱用ガストーチ38及びアーク溶接トーチ39,39’の各トーチ先端 の上下位置を、上杭1と下杭1’相互の端板間の溶接開先43に合せて調節し、 次いで回転摘まみ25にて各移動ホルダー21を進退調節すると共に、トーチ狭 着板28,28’を旋回調節しながら、予熱用ガストーチ38及びアーク溶接ト ーチ39,39’の各トーチ先端を溶接開先43に適正近接位置及び角度に調節 設定する。[0024] Next, use the rotary knob 18 of the welding cart 6 to adjust the vertical position of each lifting rod 13. Each torch tip of the gas torch 38 for knotting and preheating and the arc welding torches 39, 39' Adjust the vertical position of the weld groove 43 between the end plates of the upper pile 1 and the lower pile 1', Next, use the rotary knob 25 to adjust each movable holder 21 forward or backward, and to narrow the torch. While adjusting the rotation of the mounting plates 28, 28', the preheating gas torch 38 and the arc welding torch are turned on. Adjust the tip of each torch of torches 39 and 39' to the appropriate close position and angle to the welding groove 43. Set.
【0025】 特に、溶接台車6の旋回方向前方に位置する一層目用のアーク溶接トーチ39 を、後方に位置する二層目用のアーク溶接トーチ39’よりも先端位置が溶接開 先43に対して深い位置になるように設定する。[0025] In particular, the arc welding torch 39 for the first layer located at the front of the welding cart 6 in the direction of rotation. The tip of the arc welding torch 39' for the second layer located at the rear is open for welding. The position is set to be deep relative to the tip 43.
【0026】 また、スラグ除去用ブラシ41は、適宜その本体部42の取付位置を調節して 溶接開先43上に合せる。[0026] In addition, the slag removal brush 41 can be adjusted by adjusting the mounting position of the main body 42 as appropriate. Align it on the welding groove 43.
【0027】 このようにして溶接準備作業が完了した後、駆動台車5の走行速度を調節した 上で起動スイッチを入れ、各溶接台車6を牽引しながら旋回走行を開始すると同 時に、これに連動して溶接電源も入り、予熱用ガストーチ38が先行して溶接開 先43を加熱乾燥し、これに続いてアーク溶接トーチ39,39’は溶接開先4 3の周囲を併行して旋回しながら溶接を開始すると共に、多層溶接した溶接部の 表面をスラグ除去用ブラシ41が回転しながら摺接してスラグを自動的に除去す る。[0027] After the welding preparation work was completed in this way, the traveling speed of the drive cart 5 was adjusted. At the top, turn on the start switch and start turning while towing each welding cart 6. At times, the welding power is also turned on in conjunction with this, and the preheating gas torch 38 starts welding in advance. The tip 43 is heated and dried, and then the arc welding torches 39, 39' are applied to the welding groove 4. Start welding while circling in parallel around 3, and weld the welded part of the multi-layer weld. The slag removal brush 41 rotates and slides on the surface to automatically remove slag. Ru.
【0028】 このとき、先行するアーク溶接トーチ39が第一層目の溶着金属の盛り付けを 行ない,この溶着金属が硬化しない前に後続のアーク溶接トーチ39’が第二層 目の溶着金属の盛り付けを行なうことが肝要で、そのようタイミングに各アーク 溶接トーチ39,39’間の間隔及び旋回走行速度を適正に調節する。[0028] At this time, the preceding arc welding torch 39 deposits the first layer of weld metal. The subsequent arc welding torch 39' is applied to the second layer before this weld metal has hardened. It is important to place the weld metal on each arc at such a timing. The distance between the welding torches 39, 39' and the turning speed are adjusted appropriately.
【0029】 駆動台車5が駆動することにより、溶接台車6,6が牽引されて連動し、駆動 台車が1/2周移動したときに溶接作業が完了する。[0029] When the driving cart 5 is driven, the welding carts 6, 6 are pulled and interlocked, and the driving The welding work is completed when the cart has moved 1/2 round.
【0030】 このようにして溶接開先43の周囲を各アーク溶接トーチ39,39’が半周 旋回した後起動スイッチを切ると、同時に溶接電源も自動的に切れ、1パスで多 層溶接が完了する。[0030] In this way, each arc welding torch 39, 39' makes a half-circle around the welding groove 43. When you turn off the start switch after turning, the welding power is automatically turned off at the same time, and multiple passes can be made in one pass. Layer welding is completed.
【0031】 なお、以上の実施例ではアーク溶接トーチ39,39’を二本併設した例を示 したが、トーチを二本以上として二層以上の多層溶接も可能であり、また溶接ト ーチが1本でもよく、この場合には各溶接台車6を1回転することにより2層溶 接を行うことができる。[0031] In addition, the above embodiment shows an example in which two arc welding torches 39 and 39' are installed together. However, it is also possible to weld two or more layers using two or more torches, and welding In this case, two layers of welding can be achieved by rotating each welding cart 6 once. be able to communicate with others.
【0032】[0032]
以上の通りこの考案によれば、杭外周上に駆動台車に連動する溶接台車を複数 台配置したので、1台当たりの溶接範囲が少なくて済み、大径杭の場合などにお いて溶接効率を大幅に向上して、溶接時間の短縮が可能となる。 As described above, according to this invention, multiple welded carts linked to the drive cart are installed on the outer periphery of the pile. Because the units are arranged, the welding range per unit is small, which is useful for large-diameter piles, etc. This greatly improves welding efficiency and reduces welding time.
【0033】 また、アーク溶接トーチやその取付調節部材をなどの溶接機材は、駆動台車と は分離してこれに連結した溶接台車に設置されているため、溶接機材の取付スペ ースの制約がなく設計に自由性があり、製造上も容易であると共に、予熱用ガス トーチ、スラグ除去用ブラシ或いは防風カバーなどの付帯機材を取付けることが でき、しかも駆動台車と溶接台車の溶接部を別体にして軽量コンパクトに構成で きるため、装置の持ち運びや取付け取外しなどの取扱いが極めて容易となる。[0033] In addition, welding equipment such as arc welding torches and their mounting adjustment parts are attached to drive carts. is installed on a welding cart that is separated and connected to it, so there is no installation space for welding equipment. There is no restriction on the base, there is freedom in design, and manufacturing is easy. Ancillary equipment such as a torch, slag removal brush or windproof cover can be attached. Moreover, the welding parts of the driving cart and welding cart are separated, making it lightweight and compact. This makes it extremely easy to carry, install and remove the device.
【図1】この考案の溶接装置の設置状態を示す平面図。FIG. 1 is a plan view showing the installed state of the welding device of this invention.
【図2】この考案に係る駆動台車の正面図。FIG. 2 is a front view of the drive truck according to the invention.
【図3】この考案に係る駆動台車の設置状態を示す縦断
側面図。FIG. 3 is a longitudinal sectional side view showing the installed state of the drive truck according to the invention.
【図4】この考案に係る溶接台車の正面図。FIG. 4 is a front view of the welding cart according to the invention.
【図5】この考案に係る溶接台車の平面図。FIG. 5 is a plan view of the welding cart according to the invention.
【図6】この考案に係る溶接台車の設置状態を示す縦断
側面図。FIG. 6 is a longitudinal sectional side view showing the installed state of the welding cart according to the invention.
【図7】この考案に係る溶接台車の斜視図。FIG. 7 is a perspective view of the welding cart according to the invention.
1 上杭 1’ 下杭 2 レール固定脚 3 固定ネジ 4 ガイドレール 5 駆動台車 6 溶接台車 7 車輪 8 ラックレール 9 駆動ピニオン車輪 10 車輪 11 連結具 12 連結具 13 昇降ロッド 14 ガイドホルダー 15 ラック 16 ピニオンギヤ 17 支軸 18 回転摘まみ 19 クランプネジ 20 ガイドロッド 21 移動ホルダー 22 ラック 23 ピニオンギヤ 24 支軸 25 回転摘まみ 26 クランプネジ 27 ブラケット 28 トーチ狭着基板 28’ トーチ狭着基板 29 枢軸 30 円弧スリット 31 クランプボルト 32 ナット 33 トーチ狭着板 34 締結ボルト 35 垂直部 36 トーチ狭着板 37 締結ボルト 38 予熱用ガストーチ 39 アーク溶接トーチ 39’ アーク溶接トーチ 40 ブラケット 41 スラグ除去用ブラシ 42 本体部 43 溶接開先 1 Upper stake 1’ Lower stake 2 Rail fixed legs 3 Fixing screw 4 Guide rail 5 Drive truck 6 Welding trolley 7 Wheels 8 Rack rail 9 Drive pinion wheel 10 wheels 11 Connector 12 Connector 13 Lifting rod 14 Guide holder 15 racks 16 Pinion gear 17 Spindle 18 Rotary knob 19 Clamp screw 20 Guide rod 21 Moving holder 22 rack 23 Pinion gear 24 Spindle 25 Rotary knob 26 Clamp screw 27 Bracket 28 Torch clamp board 28’ Torch clamp board 29 Axis 30 Arc slit 31 Clamp bolt 32 Nut 33 Torch narrowing plate 34 Fastening bolt 35 Vertical part 36 Torch fitting plate 37 Fastening bolt 38 Preheating gas torch 39 Arc welding torch 39’ arc welding torch 40 bracket 41 Slag removal brush 42 Main body 43 Welding groove
Claims (2)
ルに駆動台車を走行自在に取付け、この駆動台車の走行
方向の前後に連結金具を介して溶接台車を連結したこと
を特徴とする既製杭用自動溶接機。[Claim 1] A ready-made product characterized in that a driving truck is movably attached to an annular guide rail fixed on the outer periphery of a pile, and a welded truck is connected to the front and rear of the driving truck via connecting fittings in the running direction. Automatic welding machine for piles.
てなることを特徴とする既製杭用自動溶接機。2. An automatic welding machine for ready-made piles, characterized in that a plurality of welding torches are attached to a welding cart.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1285091U JPH04104288U (en) | 1991-02-15 | 1991-02-15 | Automatic welding machine for ready-made piles |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1285091U JPH04104288U (en) | 1991-02-15 | 1991-02-15 | Automatic welding machine for ready-made piles |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04104288U true JPH04104288U (en) | 1992-09-08 |
Family
ID=31747067
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1285091U Pending JPH04104288U (en) | 1991-02-15 | 1991-02-15 | Automatic welding machine for ready-made piles |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04104288U (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS59139948A (en) * | 1983-01-28 | 1984-08-11 | 株式会社 サタケ | Hull feed amount control apparatus in vibration sorting hulling machine |
JPS60261671A (en) * | 1984-06-05 | 1985-12-24 | サイペム・エス・ペー・アー | Track device |
-
1991
- 1991-02-15 JP JP1285091U patent/JPH04104288U/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS59139948A (en) * | 1983-01-28 | 1984-08-11 | 株式会社 サタケ | Hull feed amount control apparatus in vibration sorting hulling machine |
JPS60261671A (en) * | 1984-06-05 | 1985-12-24 | サイペム・エス・ペー・アー | Track device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4811891A (en) | Method of assembling vehicle body of two-wheeled vehicle and assembling apparatus therefor | |
JP2908472B2 (en) | Automatic welding machine for welding fittings to pipes | |
CN108296615A (en) | New energy automobile motor stator connecting line bonding machine | |
JP2001321944A (en) | Curved pipe welding equipment | |
KR200391479Y1 (en) | Auto welding device for pipe | |
CN109834423B (en) | H-shaped steel welding clamping fixture | |
JP3083082B2 (en) | Method and apparatus for manufacturing beam-piercing type steel column | |
JP3083083B2 (en) | Method of manufacturing a steel column of through beam type and manufacturing apparatus used in the method | |
CN112719540A (en) | Welding device and welding method | |
JPH04104288U (en) | Automatic welding machine for ready-made piles | |
CN207026847U (en) | The welding workstation of special-purpose vehicle back end beam | |
JPH03184672A (en) | Automatic multilayer welding equipment for pile joint part | |
SU627941A1 (en) | Device for assembling and rotating articles during welding | |
JP3224364B2 (en) | Steel material processing method, steel material rotation support device, and steel material processing device | |
JP3958472B2 (en) | Curved multipoint spot welding method and welding apparatus | |
JPS6310222Y2 (en) | ||
US3483353A (en) | Welding apparatus | |
JP2001129686A (en) | Circular rail device for welding trolley | |
JPS6310223Y2 (en) | ||
JPH08206880A (en) | Plate material holder | |
CN207873451U (en) | A kind of two-way Multi-angular rotary welding tooling rolling bed | |
JPH08281483A (en) | Device for welding pile and pile | |
CN109396710A (en) | Welding workstation of special-purpose vehicle rear end roof beam | |
CN219852985U (en) | Welding fixture for motorcycle exhaust pipe | |
CN222740656U (en) | A flange welding 90 degree flip positioner |