[go: up one dir, main page]

JPH02311250A - Production planning formation device - Google Patents

Production planning formation device

Info

Publication number
JPH02311250A
JPH02311250A JP1133314A JP13331489A JPH02311250A JP H02311250 A JPH02311250 A JP H02311250A JP 1133314 A JP1133314 A JP 1133314A JP 13331489 A JP13331489 A JP 13331489A JP H02311250 A JPH02311250 A JP H02311250A
Authority
JP
Japan
Prior art keywords
production
plan
constraint
production plan
constraints
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1133314A
Other languages
Japanese (ja)
Other versions
JP2956972B2 (en
Inventor
Kazuyuki Mori
一之 森
Makoto Tsukiyama
誠 築山
Toyoo Fukuda
福田 豊生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP13331489A priority Critical patent/JP2956972B2/en
Publication of JPH02311250A publication Critical patent/JPH02311250A/en
Application granted granted Critical
Publication of JP2956972B2 publication Critical patent/JP2956972B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Feedback Control In General (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To form a production plan at a high speed by providing a means setting a constraint on production for each process, a means comparing constraints, a means deleting or appending a process plan, and a means correcting the constraint. CONSTITUTION:By a production planning instruction device 1, a constraint on production is instructed and constructed on a constraint expression device 4, and based on the constraint, searching is executed by a production planning searching device 2. When the production plan expressed by a production planning expression device 3 and that indicated by the device 1 competes with each other, priority between processes is compared by a production planning comparison device 5. When the priority of the product on the device 3 is lower, the production plan is deleted by a production planning deleting device 6, recorded on the device 4, and the production plan instructed by the device 1 is appended to the production plan on the device 3 by a production planning appending device 7. When the priority is higher, the constraint on the production instructed by the device 1 is corrected by a constraint automatic accumulation device 8 or by the device 1, and a production plan is kept on being formed by the device 2 until the constraint instructed by the device 1 is satisfied.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は非同期並列な生産システムの生産計画の作成
を支援する生産計画作成装置に関し、特に生産計画作成
中あるいは作成後の計画の変更と追加ができ、しがち生
産計画の高速化ができるものに関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a production planning device that supports the creation of a production plan for an asynchronous parallel production system, and particularly to a production planning device that supports the creation of a production plan during or after creation of a production plan. It relates to things that can speed up production planning.

〔従来の技術〕[Conventional technology]

一般に、生産計画作成装置は計画の作成、変更。 In general, production planning devices are used to create and change plans.

追加において製品の計画を変更する場合、変更する製品
のすべての工程の計画を変更する必要があり、計画の作
成、変更、追加に多くの時間を要していた。
When changing a product plan during addition, it is necessary to change all process plans for the changed product, and it takes a lot of time to create, change, and add plans.

一参考文献一 築山、森、福田、“生産スケジューリングの一手法゛、
計測自動制御学会第1回離散事象システム研究会講演論
文集33/38,198B、9〔発明が解決しようとす
る課題〕 従来の装置は以上のように構成されており、生産計画の
作成、変更、追加に多くの時間が必要であった。
1 References 1 Tsukiyama, Mori, Fukuda, “A method of production scheduling,”
Proceedings of the 1st Discrete Event System Study Group, Society of Instrument and Control Engineers, 33/38, 198B, 9 [Problem to be solved by the invention] Conventional equipment is configured as described above, and it is difficult to create and change production plans. , which required a lot of additional time.

この発明は上記のような従来のものの問題点を解消する
ためになされたもので、生産計画の作成。
This invention was made in order to solve the problems of the conventional ones as mentioned above.

変更、追加を種々の制約条件を満足させながら生産計画
を高速に自動で作成することができる生産計画作成装置
を得ることを目的とする。
It is an object of the present invention to provide a production plan creation device that can automatically create a production plan at high speed while making changes and additions while satisfying various constraint conditions.

〔課題を解決するための手段〕[Means to solve the problem]

この発明に係る生産計画作成装置は、生産における制約
を各製品の各工程に設定する手段と、工程間の制約を比
較する手段と、既存の計画から任意の製品の任意の工程
の処理計画を削除する手段と、既存の計画に任意の製品
の任意の工程の処理計画を追加する手段と、任意の製品
の任意の工程の制約を修正する手段とを設けたものであ
る。
The production planning device according to the present invention includes means for setting production constraints in each process of each product, means for comparing constraints between processes, and a process plan for any process of any product from an existing plan. This system includes means for deleting, means for adding a processing plan for any process of any product to an existing plan, and means for modifying constraints for any process for any product.

〔作用〕[Effect]

この発明においては、上述のように構成することにより
、計画の削除と追加を行う場合に必要な計画だけを削除
、追加することで生産計画を高速に作成することが可能
となる。
In the present invention, by configuring as described above, it is possible to create a production plan at high speed by deleting and adding only necessary plans when deleting and adding plans.

〔実施例〕〔Example〕

以下、この発明の実施例を図について説明する。 Embodiments of the present invention will be described below with reference to the drawings.

第1図は本発明の一実施例による生産計画作成装置の全
体構成図である。
FIG. 1 is an overall configuration diagram of a production planning device according to an embodiment of the present invention.

本実施例による生産計画作成装置は、生産計画の制約(
例えば納期、加工開始時刻、加工条件。
The production planning device according to this embodiment has constraints on production planning (
For example, delivery date, processing start time, processing conditions.

生産における目標など)を指示する装置1と、生産計画
における装置の遊休時間を探索する装W2と、生産計画
を表現し記憶する装置3と、装置1で指示した生産にお
ける制約を表現する装置4と、各製品の各工程間の優先
順位を比較する装置5と、既存の生産計画から任意の製
品の生産計画を削除する装置6と、既存の生産計画に任
意の製品の生産計画を追加する装置7と、任意の製品の
任意の工程の制約を自動的に修正する装W8とを備えた
ものである。
a device 1 for instructing (targets in production, etc.); a device W2 for searching idle time of devices in a production plan; a device 3 for expressing and storing the production plan; and a device 4 for expressing constraints in production instructed by the device 1. , a device 5 for comparing priorities between each process of each product, a device 6 for deleting a production plan for any product from an existing production plan, and a device 6 for adding a production plan for any product to an existing production plan. The device 7 includes a device 7 and a device W8 that automatically corrects constraints in any process of any product.

生産計画指示装置1により生産における制約を指示して
制約表現装置4上に構築し、生産計画表現装置3に表現
されている生産計画上に生産計画を追加できるかどうか
を、上記制約に基づいて生産計画探索装置2によって探
索する。もし生産計画表現装置3に表現されている生産
計画と、生産計画指示装置1によって指示した生産計画
との間に競合が生じた場合には、各製品の工程間の優先
順位の比較を生産計画比較装置5によって行う。
The production plan instruction device 1 instructs constraints in production, constructs them on the constraint expression device 4, and determines whether the production plan can be added to the production plan expressed in the production plan expression device 3 based on the constraints. Search is performed using the production plan search device 2. If a conflict occurs between the production plan expressed in the production plan expression device 3 and the production plan instructed by the production plan instruction device 1, the production plan is compared with the priorities among the processes of each product. This is done by the comparator 5.

そして、生産計画表現装置上の製品の方が優先順位が低
いときには、生産計画表現装置3上の製品の生産計画を
生産計画削除装置6によって削除し、削除した生産計画
を制約表現装置4に記録し、生産計画作成装置工によっ
て指示した生産計画を、生産計画追加装置7によって生
産計画表現装置3上の生産計画に追加する。しかるに、
もし生産計画表現装置3上の製品の生産計画の方が優先
順位が高いときは、装置Iで指示した生産の制約を制約
自動集積装置8によって、あるいは生産計画指示袋W1
によって修正し、再度生産計画探索装置2によって生産
計画指示装置1で指示した生産の制約を満たすまで生産
計画を作成するようにする。
Then, when the product on the production plan expression device has a lower priority, the production plan of the product on the production plan expression device 3 is deleted by the production plan deletion device 6, and the deleted production plan is recorded in the constraint expression device 4. Then, the production plan instructed by the production plan creation device engineer is added to the production plan on the production plan expression device 3 by the production plan addition device 7. However,
If the production plan for the product on the production plan expression device 3 has a higher priority, the production constraints specified by the device I are applied by the automatic constraint accumulation device 8 or the production plan instruction bag W1.
Then, the production plan searching device 2 again creates a production plan until the production constraints specified by the production plan instructing device 1 are satisfied.

また、第2図は本実施例装置の動作を示すフローチャー
ト図である。
Moreover, FIG. 2 is a flowchart diagram showing the operation of the apparatus of this embodiment.

次に上記実施例の動作を第1図ないし第2図を参照しな
がら説明する。
Next, the operation of the above embodiment will be explained with reference to FIGS. 1 and 2.

システムを起動すると、まず、生産計画指示袋W1によ
り生産計画における制約を指示する処理1を行い、続い
て追加する製品の工程の処理に関する制約を設定する処
理2を行う。そして、処理2で設定した制約と生産計画
表現装置3上の計画との制約の競合(矛盾)を調べる処
理3を行う。
When the system is started, first, a process 1 is performed to instruct constraints in the production plan using the production plan instruction bag W1, and then a process 2 is performed to set constraints regarding the process of the product to be added. Then, a process 3 is performed to check for conflicts (contradictions) between the constraints set in process 2 and the plan on the production plan expression device 3.

ここで、競合が生じない場合には処理2で設定した制約
に基づく工程処理の計画を追加する処理7を生産計画追
加装置7によって行うが、もし制約に競合が生じた場合
には、装置1で設定した工程の制約と装置3で設定され
ている生産計画の工程の制約との優先順位(制約の強さ
)を比較する処理4を行い、装R3で設定されている工
程の制約の優先順位の方が高い時は装置lにより手動に
て、あるいは制約自動修正装置8により自動的に工程の
制約を修正し、工程の制約の再設定の処理2を行う。装
置3で設定されている工程の制約の優先順位の方が低い
場合は、その工程を削除する処理5を生産計画削除装置
6によって行い、削除した工程を制約表現装置4に記録
する処理6を行い、制約表現袋W4で設定されている制
約に基づ(工程処理の計画を追加する処理7を生産計画
追加装置7によって行う。そして、装置4で設定された
制約に基づく工程処理が全て計画されたか否かを調べる
処理8を行い、計画されていなければ次に設定する工程
を処理2へ移すが、一方、計画されていれば処理5で削
除された工程が全て計画されたか否かを調べる処理10
を行い、計画されていない工程があれば、削除した工程
を設定する処理11を行って処理を処理2へ移すが、全
てが計画されていればそこでこの一連の処理を終了する
Here, if there is no conflict, the production plan addition device 7 performs process 7 of adding a process plan based on the constraints set in process 2, but if a conflict occurs in the constraints, the device 1 Process 4 is performed to compare the priorities (strength of constraints) between the process constraints set in Equipment R3 and the process constraints of the production plan set in Equipment R3, and the process constraints set in Equipment R3 are prioritized. When the ranking is higher, the process constraints are corrected manually by the device 1 or automatically by the automatic constraint correction device 8, and process 2 of resetting the process constraints is performed. If the priority of the process constraints set in the device 3 is lower, the production plan deletion device 6 performs a process 5 for deleting that process, and a process 6 for recording the deleted process in the constraint expression device 4. Then, based on the constraints set in the constraint expression bag W4, the production plan addition device 7 performs processing 7 for adding a process plan.Then, all the process processes based on the constraints set in the device 4 are planned. Process 8 is performed to check whether the processes deleted in Process 5 have been planned. Process to check 10
If there is a process that has not been planned, a process 11 for setting the deleted process is performed and the process moves to process 2, but if all have been planned, this series of processes ends there.

このように、本実施例によれば、製品の工程を優先順位
の高いものから計画していくので無駄な計画の削除を行
う可能性が少なくなる。即ち、本装置により既存の装置
と比較して高速な生産計画を行える。また、この装置に
よって作成された計画は生産の条件を重要なものから満
たしているので準最適な計画となっている。
In this way, according to the present embodiment, product processes are planned in order of priority, so the possibility of unnecessary deletion of plans is reduced. In other words, this device allows for faster production planning compared to existing devices. Furthermore, the plan created by this device satisfies the important production conditions, making it a semi-optimal plan.

〔発明の効果〕〔Effect of the invention〕

以上のように、この発明に係る生産計画作成装置によれ
ば、生産の制約を満足した上で製品の工程の優先順位の
高いものから計画していくようにしたので、生産計画の
作成が高速に行えるという効果がある。
As described above, according to the production planning device according to the present invention, the production plan can be created quickly because the product process is planned in the order of priority after satisfying the production constraints. This has the effect of allowing you to do this.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例による生産計画作成装置のブ
ロック構成を示す図、第2図は第1図の装置の動作を示
すフローチャート図である。 図において、1は生産計画指示装置、2は生産計画探索
装置、3は生産計画表現装置、4は制約表現装置、5は
生産計画比較装置、6は生産計画削除装置、7は生産計
画追加装置、8は制約自動修正装置である。
FIG. 1 is a diagram showing a block configuration of a production planning device according to an embodiment of the present invention, and FIG. 2 is a flowchart showing the operation of the device in FIG. 1. In the figure, 1 is a production plan instruction device, 2 is a production plan search device, 3 is a production plan expression device, 4 is a constraint expression device, 5 is a production plan comparison device, 6 is a production plan deletion device, and 7 is a production plan addition device. , 8 is a constraint automatic correction device.

Claims (1)

【特許請求の範囲】[Claims] (1)生産における制約を各製品の各工程に設定する手
段と、 工程間の制約を比較する手段と、 既存の計画から任意の製品の任意の工程の処理計画を削
除する手段と、 既存の計画に任意の製品の任意の工程の処理計画を追加
する手段と、 任意の製品の任意の工程の制約を修正する手段とを備え
たことを特徴とする生産計画作成装置。
(1) A means for setting constraints in production for each process of each product, a means for comparing constraints between processes, a means for deleting a processing plan for any process for any product from an existing plan, and A production planning device comprising: means for adding a processing plan for any process of any product to a plan; and means for modifying constraints of any process for any product.
JP13331489A 1989-05-26 1989-05-26 Production plan creation device Expired - Fee Related JP2956972B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13331489A JP2956972B2 (en) 1989-05-26 1989-05-26 Production plan creation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13331489A JP2956972B2 (en) 1989-05-26 1989-05-26 Production plan creation device

Publications (2)

Publication Number Publication Date
JPH02311250A true JPH02311250A (en) 1990-12-26
JP2956972B2 JP2956972B2 (en) 1999-10-04

Family

ID=15101786

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13331489A Expired - Fee Related JP2956972B2 (en) 1989-05-26 1989-05-26 Production plan creation device

Country Status (1)

Country Link
JP (1) JP2956972B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07287730A (en) * 1994-04-19 1995-10-31 Hitachi Ltd Work assignment support device
US5479343A (en) * 1990-11-28 1995-12-26 Hitachi, Ltd. Production planning system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6464761A (en) * 1987-09-03 1989-03-10 Fujitsu Ltd Work allotting device
JPS6476360A (en) * 1987-09-18 1989-03-22 Hitachi Ltd Work scheduling system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6464761A (en) * 1987-09-03 1989-03-10 Fujitsu Ltd Work allotting device
JPS6476360A (en) * 1987-09-18 1989-03-22 Hitachi Ltd Work scheduling system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5479343A (en) * 1990-11-28 1995-12-26 Hitachi, Ltd. Production planning system
JPH07287730A (en) * 1994-04-19 1995-10-31 Hitachi Ltd Work assignment support device

Also Published As

Publication number Publication date
JP2956972B2 (en) 1999-10-04

Similar Documents

Publication Publication Date Title
JPH1153202A (en) Parallel transaction processing system
KR100311187B1 (en) Dynamic Information Processing System and Method
JPH02311250A (en) Production planning formation device
JPS59214964A (en) Conversational scheduling system
CN113222441B (en) Comprehensive flexible scheduling method considering double-equipment cooperative procedure
US20210232998A1 (en) Schedule creation device, schedule creation method, and program
KR100298212B1 (en) A Real-time task scheduling method solving the priority reversal
KR0185742B1 (en) Order management device
JP2000293215A (en) Method for commanding work program of numerical controller
JP2013196541A (en) Production management method and production management device
JPH07210394A (en) Program management method for distributed system
JPH04101233A (en) Task controlling method by two-hierarchy queue structure
JP2002175353A (en) Operation plan planning method and operation plan planning device using the method
JPH08264405A (en) Process flow generator
JPH036535B2 (en)
JPH1058287A (en) Production schedule planning method and device, and determining method and device for processing device
JP4848341B2 (en) Scheduling device
JP2953223B2 (en) Scheduling planning equipment
CN117933642A (en) Intelligent production scheduling system, method, equipment and medium
JPH01119804A (en) Scan time fixing system for programmable controller
JPH0221329A (en) Report output system
JPH05197570A (en) Dynamic scheduling device for job
JPH0577144A (en) Work indicating device
JPH10232755A (en) Window control system
JPH02127732A (en) Job control system

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070723

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080723

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees