JPH0156310B2 - - Google Patents
Info
- Publication number
- JPH0156310B2 JPH0156310B2 JP54077710A JP7771079A JPH0156310B2 JP H0156310 B2 JPH0156310 B2 JP H0156310B2 JP 54077710 A JP54077710 A JP 54077710A JP 7771079 A JP7771079 A JP 7771079A JP H0156310 B2 JPH0156310 B2 JP H0156310B2
- Authority
- JP
- Japan
- Prior art keywords
- vertical duct
- vertical
- duct unit
- duct
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Duct Arrangements (AREA)
Description
【発明の詳細な説明】
本発明は、高層ビルの空調用竪ダクトを施工性
よく施設するダクト工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a duct construction method for constructing vertical air conditioning ducts for high-rise buildings with good construction efficiency.
従来、建物内に空調用竪ダクトを配設する場合
には、通常は建物が建上つたあとダクト配設用の
シヤフト内に各フロアーの天井高さよりも低いダ
クトを持ち込んでこれを接続する工法が採られて
いた。そのため、他の建築仕上工程との調整が必
要で繁雑化するとともに、工数も多数必要とし、
また継目が多くなることから漏気の問題も生じて
いた。特に、中高層および超高層ビルの工事の場
合はこのような問題が顕在化するし、全空気方式
の「VAV空調」を行なう場合にはダクト量がき
わめて多くなるので、かかる従来方式をそのまま
踏襲して実施するには問題が多々ある。 Conventionally, when installing vertical air conditioning ducts in a building, the method was to connect ducts that were lower than the ceiling height of each floor and were brought into the duct installation shaft after the building was erected. was taken. Therefore, coordination with other building finishing processes is necessary, which makes it complicated, and requires a large number of man-hours.
Additionally, the large number of seams caused problems with air leakage. In particular, such problems become apparent when constructing medium-to-high-rise buildings and skyscrapers, and the amount of ductwork required is extremely large when performing all-air type "VAV air conditioning," so it is difficult to continue with the conventional method. There are many problems in implementing this.
本発明は、高層建物の空調用竪ダクトを極めて
施工性よく施設するダクト工法を提供するもの
で、複数層階分の長さを有し且つ各フロアーへの
横引きダクト用取付口を設けたスパイラルダクト
からなる送気用竪ダクトユニツトを、上層階への
鉄骨建方進行と同時性をもつて、タワークレーン
によつて垂直に揚重し、既設の下層階竪ダクトユ
ニツトの上端とこの揚重した竪ダクトユニツトの
下端とを先細り部を上にしたレジユーサーを介し
て接続する竪ダクト施工法であつて、揚重した上
層階竪ダクトユニツトの上部を建方部材に仮受け
した状態で、前記レジユーサーの下端または上端
とダクトとの重ね合わせ量を上下方向に移動させ
ることによつて、揚重した上層階竪ダクトユニツ
トを所定の固定位置に位置決めすることを特徴と
するものである。 The present invention provides a duct construction method for constructing vertical air-conditioning ducts in high-rise buildings with extremely high construction efficiency. The air supply vertical duct unit, which consists of a spiral duct, is lifted vertically by a tower crane at the same time as the steel frame is being erected to the upper floor, and the upper end of the existing lower floor vertical duct unit and this lifted This is a vertical duct construction method in which the lower end of the vertical duct unit is connected to the lower end of the vertical duct unit via a reducer with the tapered part facing upward, and the upper part of the vertical duct unit on the upper floor is temporarily supported on the construction material. The invention is characterized in that the lifted upper floor vertical duct unit is positioned at a predetermined fixed position by moving the overlapping amount of the lower end or upper end of the reducer and the duct in the vertical direction.
図面に示した実施例に従つて具体的に説明する
と、第1図は、4層階分の長さを有する竪ダクト
ユニツト1を、タワークレーン2によつて、n−
1節に揚重している状態を示している。すなわ
ち、n−2節は外壁3等も完成した節であり、n
−1節の鉄骨建方の進行と同時性をもつて、この
n−1節のコンクリート打ちが終了し数日間の養
生期間を経たあとn節の鉄骨組立前に、n−1節
の竪ダクトユニツト1を、n−2節の既設の竪ダ
クト1aに接続する状態を示している。第2図
は、この竪ダクトユニツト1を既設の竪ダクトユ
ニツト1aに接続するさいの拡大図であり、n−
2節の最上階フロアー4iを固定階として固定金
具5によつて垂直に固定された既設竪ダクト1a
に対して、n−1節の最上階フロアー4mを固定
階として吊り金具6によつて仮止めされた竪ダク
トユニツト1が、レデユーサー7を介して、接続
される直前の状態を示している。第3図は、この
第2図の状態にあるレデユーサー7の部分の拡大
図であり、このレデユーサー7が既設竪ダクト1
aの上端にビス9によつて仮止めされた状態を示
している。 To explain specifically according to the embodiment shown in the drawings, FIG.
Section 1 shows the state of lifting. In other words, node n-2 is the node where the outer wall 3 etc. have also been completed, and
At the same time as the erection of the steel frame for section -1, after concrete pouring for section n-1 was completed and a curing period of several days had passed, the vertical duct of section n-1 was constructed before the steel frame for section n was erected. A state in which the unit 1 is connected to the existing vertical duct 1a at node n-2 is shown. FIG. 2 is an enlarged view of the vertical duct unit 1 connected to the existing vertical duct unit 1a, and is an enlarged view of the vertical duct unit 1a.
Existing vertical duct 1a fixed vertically with fixing fittings 5 with the top floor 4i of section 2 as a fixed floor
On the other hand, the vertical duct unit 1 is shown in a state immediately before being connected via the reducer 7, with the vertical duct unit 1 temporarily fixed by the hanging fittings 6 with the top floor 4m of the n-1 node as the fixed floor. FIG. 3 is an enlarged view of the reducer 7 in the state shown in FIG.
It shows a state in which it is temporarily fixed to the upper end of a with screws 9.
竪ダクトユニツト1の下端と既設竪ダクト1a
の上端との接続は、各ダクトとも第2図に示す如
く固定階フロアー4iと4mによつて固定した状
態で、既設竪ダクト1aに仮止めしたレデユーサ
ー7を上方に移動させることによつて行なう。す
なわち、第3図の如き状態から、ビス9を外し、
レデユーサー持上げ金具10によつて、レデユー
サー7を上方に持ち上げ、このレデユーサー7の
上縁部11を、第4図に示した如く、竪ダクトユ
ニツト1の下部開口に差し込み、ビス12によつ
てこの竪ダクトユニツト1に固定すると共に、こ
のレデユーサー7の下縁部13もその分スライド
させて再びビス9によつて既設竪ダクトユニツト
1aの上端に固定する。なお、第5図および第6
図に示した如く、竪ダクトユニツト1の下部にレ
デユーサー7を取り付けておき、レデユーサー7
の上縁部11をスライドさせ、既設竪ダクト1a
の下端とレデユーサー7の下縁部13とをビス9
によつて固定することもできる。 Lower end of vertical duct unit 1 and existing vertical duct 1a
The connection with the upper end is performed by moving the reducer 7 temporarily fixed to the existing vertical duct 1a upward, with each duct fixed by the fixed floors 4i and 4m as shown in Fig. 2. . That is, from the state shown in Fig. 3, remove screw 9,
Lift the reducer 7 upward with the reducer lifting fitting 10, insert the upper edge 11 of the reducer 7 into the lower opening of the vertical duct unit 1 as shown in FIG. At the same time as it is fixed to the duct unit 1, the lower edge 13 of this reducer 7 is also slid by that amount and fixed again to the upper end of the existing vertical duct unit 1a with screws 9. In addition, Figures 5 and 6
As shown in the figure, the reducer 7 is attached to the lower part of the vertical duct unit 1.
Slide the upper edge 11 of the existing vertical duct 1a
Connect the lower end and the lower edge 13 of the reducer 7 with the screw 9.
It can also be fixed by
本工法で使用する竪ダクトユニツトは、工場生
産されたスパイラルダクトの使用を可能とする。
すなわち、亜鉛メツキ鋼板をらせん状に巻いて円
筒を形成するスパイラルダクトを好適に使用する
ことができ、現場施工の従来法に比して作業性、
製作コスト、正確性、耐久性等において多大の利
点を享受することができる。そしてこのスパイラ
ルダクトユニツトには、工場生産時に各フロアー
への横引きダクト用の取付口14(第2図)を予
め所定位置に設けておくと、一層作業能率が向上
する。なお、各竪ダクトユニツトは、高層階にゆ
くに従い短径となつており、各々の揚重にさいし
ては、次揚重ダクトユニツトの径に係合するレデ
ユーサーをその上端に取付けさらに養生フタを被
着して揚重するのが実作業上便宜である。 The vertical duct unit used in this construction method allows the use of factory-produced spiral ducts.
In other words, a spiral duct in which a galvanized steel plate is spirally wound to form a cylinder can be suitably used, and it is easier to work with than the conventional method of on-site construction.
Many advantages can be enjoyed in terms of manufacturing cost, accuracy, durability, etc. If the spiral duct unit is provided with attachment ports 14 (FIG. 2) for horizontal ducts to each floor at predetermined positions during factory production, the work efficiency will be further improved. The diameter of each vertical duct unit becomes shorter as it goes to the higher floors, and for each lift, a reducer that engages with the diameter of the next lifted duct unit is attached to its upper end, and a curing lid is attached. It is convenient for actual work to cover the material and lift it.
このようにして、本発明工法によるときは、空
調用ダクト施工は建方完了後に行なうという従来
の常識的な考え方を払拭して、鉄骨建方の進行と
同時性をもつて簡便にダクトを揚重しかつ正確安
全に施設でき、その工数の単縮が大巾に達成され
ると共に、継目の減少から漏気も大巾に減少する
ことができる。 In this way, when using the construction method of the present invention, the conventional common sense idea that air conditioning duct construction should be carried out after erection is completed, and the duct can be easily lifted at the same time as steel frame erection progresses. The construction can be carried out accurately and safely, and the number of man-hours required can be greatly reduced, and air leakage can also be greatly reduced due to the reduction in joints.
第1図は本発明工法のダクト揚重状態を示す説
明図、第2図はダクト仮置き状態を示す図、第3
図は第2図のレデユーサー部の拡大図、第4図は
レデユーサー部の接続した状態を示す第3図同様
の拡大図、第5図および第6図は別の態様を示す
第3図および第4図同様の拡大図である。
1……竪ダクトユニツト、2……タワークレー
ン、4……固定階、5……固定金物、7……レデ
ユーサー。
Figure 1 is an explanatory diagram showing the duct lifting state using the method of the present invention, Figure 2 is a diagram showing the duct being temporarily placed, and Figure 3 is a diagram showing the duct being temporarily placed.
The figure is an enlarged view of the reducer part in Figure 2, Figure 4 is an enlarged view similar to Figure 3 showing the connected state of the reducer part, and Figures 5 and 6 are Figures 3 and 6 showing different aspects. This is an enlarged view similar to Figure 4. 1...Vertical duct unit, 2...Tower crane, 4...Fixed floor, 5...Fixed hardware, 7...Reducer.
Claims (1)
たり、複数層階分の長さを有し且つ各フロアーへ
の横引きダクト用取付口を設けたスパイラルダク
トからなる送気用竪ダクトユニツトを、上層階へ
の鉄骨建方進行と同時性をもつて、タワークレー
ンによつて垂直に揚重し、既設の下層階竪ダクト
ユニツトの上端とこの揚重した竪ダクトユニツト
の下端とを先細り部を上にしたレジユーサーを介
して接続する竪ダクト施工法であつて、揚重した
上層階竪ダクトユニツトの上部を建方部材に仮受
けした状態で、前記レジユーサーの下端または上
端とダクトとの重ね合わせ量を上下方向に移動さ
せることによつて、揚重した上層階竪ダクトユニ
ツトを所定の固定位置に位置決めすることを特徴
とする高層建物の空調用竪ダクト施工法。1. When installing a vertical air conditioning duct in a high-rise building, an air supply vertical duct unit consisting of a spiral duct with a length for multiple floors and with installation ports for horizontal ducts on each floor is installed. Simultaneously with the progress of the steel frame erection on the upper floors, a tower crane was used to lift the steel frame vertically and connect the upper end of the existing lower floor vertical duct unit with the lower end of this lifted vertical duct unit to form a tapered section. This is a vertical duct construction method in which the upper part of the lifted upper floor vertical duct unit is temporarily supported on the construction material, and the lower end or upper end of the said registerer is overlapped with the duct. A method for constructing vertical air conditioning ducts for high-rise buildings, characterized by positioning a lifted upper floor vertical duct unit at a predetermined fixed position by moving the vertical duct unit vertically.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7771079A JPS563372A (en) | 1979-06-20 | 1979-06-20 | Uniting method of verticul duct for air conditioning of high building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7771079A JPS563372A (en) | 1979-06-20 | 1979-06-20 | Uniting method of verticul duct for air conditioning of high building |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS563372A JPS563372A (en) | 1981-01-14 |
JPH0156310B2 true JPH0156310B2 (en) | 1989-11-29 |
Family
ID=13641440
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7771079A Granted JPS563372A (en) | 1979-06-20 | 1979-06-20 | Uniting method of verticul duct for air conditioning of high building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS563372A (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0250042A (en) * | 1988-08-09 | 1990-02-20 | Taiyo Kk | Air conditioning piping for building |
JP5679761B2 (en) * | 2010-10-19 | 2015-03-04 | 積水化学工業株式会社 | Piping support fixing structure |
JP6698336B2 (en) * | 2015-12-23 | 2020-05-27 | 積水化学工業株式会社 | Piping structure |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS49130162A (en) * | 1973-04-12 | 1974-12-13 | ||
JPS5156557A (en) * | 1974-11-11 | 1976-05-18 | Kajima Corp | KUCHOPAIPUTORITSUKE SOCHI |
-
1979
- 1979-06-20 JP JP7771079A patent/JPS563372A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS49130162A (en) * | 1973-04-12 | 1974-12-13 | ||
JPS5156557A (en) * | 1974-11-11 | 1976-05-18 | Kajima Corp | KUCHOPAIPUTORITSUKE SOCHI |
Also Published As
Publication number | Publication date |
---|---|
JPS563372A (en) | 1981-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4717517A (en) | Concurrent method of building construction and formwork structure therefore | |
JP6842881B2 (en) | Duct construction method | |
KR20250036109A (en) | Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing | |
JPH0156310B2 (en) | ||
US20030042394A1 (en) | Method and apparatus for making concrete buildings | |
AU2020264333B2 (en) | A Construction System and Method of Use Thereof | |
US4567709A (en) | Method and apparatus for erecting a building | |
EP0065793B1 (en) | Reinforcement structure for reinforced-concrete buildings | |
EP0790364A1 (en) | Reinforced or prestressed semi-precast concrete structure for building | |
JPH11200651A (en) | Clean room building and executing method therefor | |
CN111206676B (en) | An integral prefabricated balcony module suitable for beam-through steel frame | |
JPS6326215B2 (en) | ||
JPS61162679A (en) | Construction of nuclear reactor plant | |
JPH05306572A (en) | Construction method for building | |
CN114263268A (en) | Assembled light heat-insulation quick-installation integrated house and installation method | |
JPS6355572B2 (en) | ||
JPH026904B2 (en) | ||
SU973758A1 (en) | Method of erecting a monolithic building in slide form | |
JPS6131258B2 (en) | ||
AU2023228697A1 (en) | A construction system and method of use thereof | |
JP2733507B2 (en) | Industrialization of racks for piping and wiring | |
JP2566058B2 (en) | Wall construction method | |
JP2001107565A (en) | Building construction method | |
SU1684445A1 (en) | Method for building houses | |
JPS63312464A (en) | Execution of duct space under veranda |