JPH0138927B2 - - Google Patents
Info
- Publication number
- JPH0138927B2 JPH0138927B2 JP57068766A JP6876682A JPH0138927B2 JP H0138927 B2 JPH0138927 B2 JP H0138927B2 JP 57068766 A JP57068766 A JP 57068766A JP 6876682 A JP6876682 A JP 6876682A JP H0138927 B2 JPH0138927 B2 JP H0138927B2
- Authority
- JP
- Japan
- Prior art keywords
- hole
- concrete
- soft member
- blocking means
- joint box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
本発明は地中壁の接続方法に関し、さらに詳し
くはコンクリートを段階的に場所打ちして構築さ
れる地中壁を接続して地中連続壁とする場合に、
隣接する地中壁間に特殊な止水施工をする地中壁
の接続方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for connecting underground walls, and more specifically, when connecting underground walls constructed by pouring concrete in a step-by-step manner to form a continuous underground wall.
This article relates to a method for connecting underground walls that performs special water-stopping construction between adjacent underground walls.
前記したタイプの地中連続壁を構築する場合、
第1の孔を掘削した後、該孔の端部に遮断手段、
例えばインターロツキングパイプを建込み、前記
第1の孔に地中壁となるべきコンクリートを打設
する。その後このコンクリートの硬化後、インタ
ーロツキングパイプを引き抜き、前記端部側で前
記第1の孔を延長すべく第2の孔を掘削して、同
様の操作を繰り返す。 When constructing a diaphragm wall of the type described above,
After drilling the first hole, a blocking means is provided at the end of the hole;
For example, an interlocking pipe is built, and concrete that is to become an underground wall is placed in the first hole. Thereafter, after the concrete has hardened, the interlocking pipe is pulled out, a second hole is drilled to extend the first hole on the end side, and the same operation is repeated.
ところが、前記のように掘削された孔には地山
の崩壊を防止するために泥水からなる安定液が充
満されるので、第1の孔に打設されたコンクリー
トの第2の孔側の端面に泥膜が付着する。しか
も、第2の孔へのコンクリートの打設時に前記端
面近傍にスライムが溜つたり、コンクリート打設
管から噴出されてこの周囲に山状となつたコンク
リートが低部へ流動するなだれ込みが起こつて端
面近傍にコンクリートのない空隙部が発生したり
して、前記端面を含む地中壁の接続部に弱体箇所
が生じ、止水性が不良になるという避けられない
欠陥がある。 However, since the hole drilled as described above is filled with a stabilizing liquid consisting of muddy water to prevent the collapse of the ground, the end surface of the concrete poured in the first hole on the second hole side A mud film adheres to the surface. Moreover, when pouring concrete into the second hole, slime may accumulate near the end face, or avalanche may occur in which the concrete that has spewed out from the concrete pouring pipe and formed a mountain around it flows to a lower part. As a result, voids without concrete may be created near the end faces, resulting in weak spots in the connecting parts of the underground walls including the end faces, resulting in unavoidable defects in water-stopping properties.
従つて、本発明の目的は、先行して構築された
地中壁と後行して構築される地中壁との接続部に
前記のような不都合が生じても、コンクリート打
設後の止水施工により止水性を格段に向上できる
地中壁の接続方法を提供することにある。 Therefore, it is an object of the present invention to prevent the above-mentioned problems from occurring at the connection between the previously constructed underground wall and the subsequently constructed underground wall, without stopping the concrete from being placed. The object of the present invention is to provide a method for connecting underground walls that can significantly improve water-stopping performance through water construction.
本発明は、コンクリートを段階的に場所打ちし
て構築される地中壁を接続する方法であつて、第
1の孔の端部に、外周面に凹状の保持部を有しか
つ該保持部に軟質部材が保持した遮断手段を、前
記軟質部材が前記第1の孔の幅方向の孔壁面間に
位置するように建込むこと、前記第1の孔にコン
クリートを打設すること、該コンクリートの硬化
後前記軟質部材を残留させて前記遮断手段を前記
第1の孔から引き抜くこと、前記第1の孔の前記
端部側で前記第1の孔を延長すべく掘削された第
2の孔にコンクリートを打設すること、該コンク
リートの硬化後前記軟質部材を囲む前記コンクリ
ートの前記軟質部材との境界面をビツトの案内面
として前記軟質部材からその周囲のコンクリート
にわたる孔を穿つこと、該孔にモルタルを充填す
ることを含む。 The present invention is a method for connecting an underground wall constructed by pouring concrete in a step-by-step manner, and includes a holding portion having a concave shape on the outer peripheral surface at the end of a first hole; erecting a blocking means held by a soft member such that the soft member is positioned between the hole wall surfaces in the width direction of the first hole; pouring concrete into the first hole; pulling out the blocking means from the first hole with the soft member remaining after hardening; a second hole being drilled at the end side of the first hole to extend the first hole; pouring concrete into the concrete, after the concrete has hardened, drilling a hole from the soft member to the surrounding concrete using the boundary surface of the concrete surrounding the soft member with the soft member as a guide surface for a bit; including filling with mortar.
本発明の別の特徴では、第1の孔の端部に遮断
手段を建込むこと、該遮断手段に沿わせて第1の
ジヨイントボツクスを建込むこと、外周面に凹状
の保持部を有しかつ該保持部に軟質部材を保持し
た第2のジヨイントボツクスを、前記軟質部材が
前記第1の孔の幅方向の孔壁面側に位置するよう
に前記第1のジヨイントボツクスに沿わせて建込
むこと、前記第1の孔にコンクリートを打設する
こと、該コンクリートの硬化後前記遮断手段を前
記第1の孔から引き抜くこと、前記遮断手段の引
き抜き後またはこれに先立つて前記軟質部材を残
留させて前記第2のジヨイントボツクスを前記第
1の孔から引き抜くこと、前記第2のジヨイント
ボツクスの引き抜きによつて生じた空間内に前記
軟質部材を覆いしかも前記第1のジヨイントボツ
クスと前記コンクリートとに接触するスペサーボ
ツクスを建込むこと、前記第1の孔の前記端部側
で該第1の孔を延長すべく掘削された第2の孔か
ら、前記スペサーボツクスおよび第1のジヨイン
トボツクスを引き抜いた後、該第2の孔にコンク
リートを打設すること、該コンクリートの硬化後
前記軟質部材を囲むコンクリートの前記軟質部材
との境界面をビツトの案内面として軟質部材から
周囲のコンクリートにわたる孔を穿つこと、該孔
にモルタルを充填することを含む。 Another feature of the present invention is that a blocking means is built into the end of the first hole, a first joint box is built along the blocking means, and a concave holding portion is provided on the outer peripheral surface. and placing a second joint box holding a soft member in the holding portion along the first joint box such that the soft member is located on the hole wall side in the width direction of the first hole. pouring concrete into the first hole; pulling out the blocking means from the first hole after the concrete has hardened; pulling out the second joint box from the first hole while leaving the soft member in the space created by pulling out the second joint box; erecting a spacer box in contact with the box and the concrete; from a second hole drilled on the end side of the first hole to extend the first hole; After pulling out the joint box, concrete is poured into the second hole, and after the concrete has hardened, the interface between the concrete surrounding the soft member and the soft member is used as a guide surface for the bit to be removed from the soft member. It involves drilling a hole through the surrounding concrete and filling the hole with mortar.
本発明の更に別の特徴では、第1の孔の端部に
遮断手段を建込むこと、貫通孔を有するコンクリ
ートブロツクを前記遮断手段に沿わせて建込むこ
と、前記第1の孔にコンクリートを打設するこ
と、該コンクリートの硬化後前記遮断手段を前記
第1の孔から引き抜くこと、前記第1の孔の前記
端部側で該第1の孔を延長すべく掘削された第2
の孔にコンクリートを打設すること、該コンクリ
ートの硬化後前記コンクリートブロツクの貫通孔
の内周面をビツトの案内面として該コンクリート
ブロツクから前記第1および第2の孔に打設され
た前記コンクリートにわたる孔を穿つこと、該孔
にモルタルを充填することを含む。 Still other features of the invention include building a blocking means at the end of the first hole, building a concrete block having a through hole along the blocking means, and placing concrete in the first hole. pouring, and pulling the blocking means out of the first hole after the concrete has hardened; and drilling a second hole at the end of the first hole to extend the first hole.
After the concrete has hardened, the concrete is poured into the first and second holes from the concrete block using the inner peripheral surface of the through hole of the concrete block as a guide surface for the bit. and filling the hole with mortar.
以下に、図面を参照して本発明の実施例につい
て説明する。 Embodiments of the present invention will be described below with reference to the drawings.
本発明の接続方法は、先行してコンクリートが
打設される第1の孔10の端部に後述する遮断手
段を建込む。これに先だつて第1の孔10を掘削
する(第1図)。第1の孔10の掘削はクラムシ
エル型バケツトのような掘削具で行うことが作業
能率上好ましい。そのためには、先行ボーリング
孔12を鉛直精度のよいリバース機で穿孔し、半
円筒状の地山面14をバケツトのガイドとする。
また、土質が硬質であつたり、岩盤である場合な
ど、複数の中抜ボーリング孔16をし、あらかじ
め土質を緩めて、バケツト掘削を容易にする。こ
の中抜ボーリングは軟岩(圧縮強度500Kg/cm2未
満)ではロツクオーガー、硬岩(圧縮強度500
Kg/cm2以上)ではリバース機で行う。バケツトで
掘削した部分には地山の崩壊を防止するための泥
水からなる安定液を充満させる。第1の孔の掘削
後、孔の底ざらい、スライム処理をする。 In the connection method of the present invention, a blocking means, which will be described later, is installed at the end of the first hole 10 in which concrete is placed in advance. Prior to this, a first hole 10 is excavated (FIG. 1). In terms of work efficiency, it is preferable to excavate the first hole 10 using a digging tool such as a clamshell type bucket. To do this, the preliminary boring hole 12 is bored with a reversing machine with good vertical accuracy, and the semi-cylindrical ground surface 14 is used as a guide for the bucket.
In addition, when the soil is hard or rocky, a plurality of hollow boring holes 16 are made to loosen the soil in advance to facilitate bucket excavation. This hollow boring is used for soft rock (compressive strength less than 500Kg/ cm2 ) with a rock auger, hard rock (compressive strength 500Kg/cm2 or less).
Kg/cm 2 or more), use a reverse machine. The area excavated with a bucket is filled with a stabilizing solution consisting of muddy water to prevent the ground from collapsing. After drilling the first hole, the bottom of the hole is roughened and slime is treated.
第1の孔10の端部、図示の例では先行ボーリ
ング孔12の位置に遮断手段であるインターロツ
キングパイプ18を後述する態様で建込む(第2
図)。遮断手段は第1の孔10内に打設されるコ
ンクリートの流動を阻止するものであればよく、
図示の例のようなインターロツキングパイプの
外、横断面が方形のインターロツキングボツクス
など適宜に用い得る。 At the end of the first hole 10, in the illustrated example, at the position of the preceding boring hole 12, an interlocking pipe 18, which is a blocking means, is built in the manner described later (second
figure). The blocking means may be of any type as long as it prevents the flow of concrete poured into the first hole 10.
In addition to the interlocking pipe shown in the illustrated example, an interlocking box having a rectangular cross section may be used as appropriate.
インターロツキングパイプ18の外周面19に
凹状の保持部20がその軸線に沿つて全長にわた
つて設けられている。インターロツキングパイプ
18の建込みに先立つて、この保持部20に発泡
スチロール製の軟質部材22を保持する。保持は
軟質部材22を保持部20に押し込んで変形さ
せ、保持部20により挾持する外、微量の接着剤
を保持部20の軸線方向に断続状に塗布すると
か、粘着テープで断続状に貼り付けるとか、細い
弱いワイヤでくくるなどにより行う。どのような
保持形態であれ、後述するように、軟質部材22
のインターロツキングパイプの外周面19から突
出した部分24を第1の孔10に打設されるコン
クリートで囲んだ場合、コンクリート硬化後のコ
ンクリートによる保持力の方が保持部20による
保持力よりも勝り、軟質部材22をコンクリート
に残留させてインターロツキングパイプ18を引
き抜くことができるように保持する。軟質部材2
2は硬化したコンクリートよりも軟質の材料で形
成する。例えば前記発泡スチロールの外、木材、
ゴムなどである。 A concave holding portion 20 is provided on the outer circumferential surface 19 of the interlocking pipe 18 along the entire length thereof. Prior to installing the interlocking pipe 18, a soft member 22 made of expanded polystyrene is held in this holding part 20. For holding, the soft member 22 is pushed into the holding part 20 to deform it, and in addition to being held by the holding part 20, a small amount of adhesive is applied intermittently in the axial direction of the holding part 20, or it is pasted intermittently with adhesive tape. Or by tying it with thin, weak wire. Regardless of the holding form, as will be described later, the soft member 22
When the part 24 protruding from the outer peripheral surface 19 of the interlocking pipe is surrounded by concrete poured into the first hole 10, the holding force of the concrete after concrete hardening is greater than the holding force of the holding part 20. Instead, the soft member 22 is retained in the concrete so that the interlocking pipe 18 can be pulled out. Soft member 2
2 is made of a material softer than hardened concrete. For example, in addition to the Styrofoam, wood,
Rubber, etc.
保持部20の横断面は図示の例では、円弧状で
あり、軟質部材22の横断面は円形である。イン
ターロツキングパイプ18の外周面19から突出
している軟質部材22の部分24の横断面積は保
持部20によつて保持された部分25の横断面積
よりも大である。この結果、後述するように、第
1の孔10にコンクリートを打設し、このコンク
リートの硬化後、軟質部材22をコンクリート中
に残留させてインターロツキングパイプ18を引
き抜いたとき、第2の孔へ向けて突出する軟質部
材22の部分25は少なくなり、第2の孔を掘削
する際に軟質部材22を損傷する可能性が少なく
なつて好ましい。軟質部材22の横断面は円形以
外の方形、楕円形などであつてもよく、この場
合、保持部20の横断面は軟質部材の断面形状に
適合し、軟質部材の軸線に沿う一部分を保持でき
る形状である。 In the illustrated example, the cross section of the holding portion 20 is arcuate, and the cross section of the soft member 22 is circular. The cross-sectional area of the portion 24 of the soft member 22 protruding from the outer peripheral surface 19 of the interlocking pipe 18 is larger than the cross-sectional area of the portion 25 held by the holding portion 20. As a result, as will be described later, when concrete is poured into the first hole 10 and after the concrete hardens, the soft member 22 remains in the concrete and the interlocking pipe 18 is pulled out. The portion 25 of the soft member 22 that protrudes toward the hole is reduced, which is preferable because there is less possibility of damaging the soft member 22 when drilling the second hole. The cross section of the soft member 22 may be rectangular, elliptical, etc. other than circular, and in this case, the cross section of the holding part 20 matches the cross-sectional shape of the soft member and can hold a portion of the soft member along the axis. It is the shape.
軟質部材22を保持したインターロツキングパ
イプ18を、インターロツキングパイプの外周面
19から突出した軟質部材22の部分24が第1
の孔10の幅方向の孔壁面26,27間に位置し
しかも軟質部材22が鉛直となるように孔10の
端部に建込む(第2図)。 The interlocking pipe 18 holding the soft member 22 is held in place so that the portion 24 of the soft member 22 protruding from the outer peripheral surface 19 of the interlocking pipe is the first
The soft member 22 is placed between the hole wall surfaces 26 and 27 in the width direction of the hole 10, and is built at the end of the hole 10 so that the soft member 22 is vertical (FIG. 2).
インターロツキングパイプ18を建込んだ後、
第1の孔10に鉄筋篭28を入れ、コンクリート
打設管であるトレミー管30を設置する(第3
図)。このトレミー管30を使用して第1の孔1
0内に沈澱している微粒物をエアーリフトにより
スライム処理した後、トレミー管30により安定
液中にコンクリートを打設する。このコンクリー
トの硬化後、軟質部材22をコンクリートに残留
させてインターロツキングパイプ18を引き抜
く。コンクリートの硬化後とは、インターロツキ
ングパイプ18を引き抜いても、コンクリートが
流動せずに打設された形状に自己保持され、しか
もインターロツキングパイプ18を引き抜き易い
時期であつて、例えばコンクリート打設後数時間
経過した時である。前記コンクリートは硬化して
地中壁32となる。 After installing interlocking pipe 18,
A reinforcing bar basket 28 is inserted into the first hole 10, and a tremie pipe 30, which is a concrete pouring pipe, is installed (the third
figure). Using this tremie tube 30, the first hole 1
After the fine particles precipitated in the concrete are slimed by an air lift, concrete is poured into the stabilizing liquid using a tremie pipe 30. After the concrete hardens, the interlocking pipe 18 is pulled out with the soft member 22 remaining in the concrete. After the concrete has hardened is the period when the concrete does not flow even if the interlocking pipe 18 is pulled out and is self-retained in the cast shape, and the interlocking pipe 18 is easy to pull out. This was several hours after the installation. The concrete hardens and becomes an underground wall 32.
次いで、第1の孔10の前記端部側で第1の孔
を延長すべく第2の孔34の第1の孔10と同じ
手順で掘削し(第4図)、底ざらい、スライム処
理した後、鉄筋篭28を第2の孔34に入れ、ト
レミー管30を設置する(第5図)。このトレミ
ー管30により微粒物のスライム処理をした後、
第2の孔34(インターロツキングパイプ18を
引き抜いた後の第1の孔の部分を含む)にコンク
リートを打設する。このコンクリートは硬化して
地中壁36となる。 Next, in order to extend the first hole on the end side of the first hole 10, the second hole 34 was excavated in the same procedure as the first hole 10 (FIG. 4), and the bottom was roughened and treated with slime. After that, the reinforcing bar cage 28 is inserted into the second hole 34, and the tremie tube 30 is installed (FIG. 5). After sliming fine particles with this tremie tube 30,
Concrete is poured into the second hole 34 (including the first hole after the interlocking pipe 18 has been pulled out). This concrete hardens and becomes an underground wall 36.
第2の孔34へのコンクリートの打設後、先行
して打設されたコンクリートによつて構築された
地中壁32と後行して打設されたコンクリートに
よつて構築された地中壁36との接続部38が収
縮した後、軟質部材22を囲むコンクリートの軟
質部材との境界面40をビツトの案内面として軟
質部材22から周囲のコンクリートにわたつて穿
孔する。 After pouring concrete into the second hole 34, an underground wall 32 constructed from the concrete placed first and an underground wall constructed from the concrete placed subsequently. After the connecting portion 38 with the soft member 36 has shrunk, a hole is drilled from the soft member 22 to the surrounding concrete using the interface 40 of the concrete surrounding the soft member with the soft member as a guide surface for the bit.
穿孔は第7図に示す拡孔ビツト42を用いて行
うことが好ましい。拡孔ビツト42は、軟質部材
22の外径よりもわずかに小さいか実質的に等し
い外径を有するコアチユーブ44の先端部にコア
チユーブと同径の先端ビツト46を、後端部にウ
イングビツト48をそれぞれ備えたもので、先端
ビツト46により軟質部材22を穿孔する。ウイ
ングビツト48は後端に向けて末広状に形成さ
れ、例えば円周方向に90゜の間隔をへだてて溶接
によりコアチユーブ44に取り付けられている。
拡孔ビツト42はボーリング機に取り付けられ、
回転される。 Preferably, the holes are made using a hole expanding bit 42 shown in FIG. The hole expanding bit 42 has a tip bit 46 having the same diameter as the core tube at the distal end of the core tube 44, which has an outer diameter slightly smaller than or substantially equal to the outer diameter of the soft member 22, and a wing bit 48 at the rear end. The soft member 22 is pierced by a tip bit 46, respectively. The wing bits 48 are formed in a shape that widens toward the rear end, and are attached to the core tube 44 by welding, for example, at intervals of 90° in the circumferential direction.
The hole expanding bit 42 is attached to the boring machine,
be rotated.
先端ビツト46が軟質部材22を穿孔して軟質
部材中へ進入すると、コアチユーブ44の外周面
が軟質部材22を囲む地中壁のコンクリートの境
界面40によつて案内されることとなり、拡孔ビ
ツト42は軟質部材22の伸びる方向へ次第に進
入する。そしてウイングビツト48がコンクリー
トの境界面40に達すると、コンクリートの境界
面40の周りのコンクリートが削り取られて拡孔
され、軟質部材から周囲のコンクリートにわたる
孔41が穿たれる(第6図)。この拡孔により、
接続部38のうち拡孔された部分に付着した泥膜
が弱体簡所を削り取る。 When the tip bit 46 perforates the soft member 22 and enters the soft member, the outer peripheral surface of the core tube 44 is guided by the concrete boundary surface 40 of the underground wall surrounding the soft member 22, and the hole expansion bit 42 gradually enters in the direction in which the soft member 22 extends. When the wing bit 48 reaches the concrete boundary surface 40, the concrete around the concrete boundary surface 40 is scraped away and expanded, and a hole 41 extending from the soft member to the surrounding concrete is bored (FIG. 6). With this hole expansion,
The mud film adhering to the expanded portion of the connecting portion 38 scrapes off weak spots.
穿孔後、孔41の透水テスト(ルジオンテス
ト)を実施し、該孔41の透水度により、割目の
状態や弱体箇所の有無を確認する。透水テストに
代えてボアホールテレビによる視認も可能であ
る。透水テストの後、必要に応じてグラウチング
処理し、割目や弱体箇所を補強して止水性を高め
る。もつとも、前記のように形成した孔41は先
行して打設されたコンクリートと後行して打設さ
れたコンクリートとの接続部38に位置するので
必ず、接続部38そのものの割目が存在する。そ
こでまず外管を孔あきのストレーナ管とした2重
管を孔41に挿入した後、外管と内管との間にモ
ルタルとベントナイトの混合物であるゲインを注
入して接続部38の割目を固化して割目からの漏
水を防止した後、所定箇所にパツカーグラウチン
グ処理する。 After drilling, the hole 41 is subjected to a water permeability test (Lugeon test), and the state of the cracks and the presence or absence of weak points are confirmed based on the water permeability of the hole 41. Visual confirmation using borehole television is also possible instead of a water permeability test. After the water permeability test, grouting is performed as necessary to strengthen cracks and weak areas to improve water-stopping properties. However, since the hole 41 formed as described above is located at the connecting part 38 between the concrete placed previously and the concrete placed subsequently, there is always a gap in the connecting part 38 itself. . Therefore, first, a double pipe with a perforated strainer pipe as the outer pipe is inserted into the hole 41, and then gain, which is a mixture of mortar and bentonite, is injected between the outer pipe and the inner pipe to widen the crack at the connection part 38. After solidifying to prevent water from leaking through the cracks, patch grouting is performed at designated locations.
前記グラウチングの後、孔41に膨張モルタル
又は無収縮モルタル42を充填する(第6図)。
以下同じ操作をして隣接する地中壁を接続し、地
中連続壁が構築される。 After the grouting, the holes 41 are filled with expanding mortar or non-shrinking mortar 42 (FIG. 6).
The same operation is then performed to connect adjacent underground walls, and a continuous underground wall is constructed.
第8図ないし第12図は別の接続方法である。
前記方法と同じ要素には同じ符号を使用して説明
する。 8 to 12 show another connection method.
The same elements as in the previous method will be described using the same reference numerals.
前記と同じ手順で掘削された第1の孔10の端
部にインターロツキングパイプ18を建込む。こ
の場合のインターロツキングパイプ18には何ら
特別の加工は施されていない。このインターロツ
キングパイプ18に沿わせて第1のジヨイントボ
ツクス44を、さらに第1のジヨイントボツクス
44に沿わせて後述する態様で第2のジヨイント
ボツクス46を建込む(第8図)。図示の例では、
第1のジヨイントボツクス44のインターロツキ
ングパイプ18に対面する側面は、インターロツ
キングパイプ18の外周面に適合する内方に凹と
なつた凹状面45に形成されている。このように
すると、インターロツキングパイプ18を引き抜
いた後、クラムシエル型バケツトにより第2の孔
を掘削する際に、凹状面45をバケツトの案内面
とすることができるので好ましい。 An interlocking pipe 18 is installed at the end of the first hole 10 drilled in the same manner as described above. The interlocking pipe 18 in this case is not subjected to any special processing. A first joint box 44 is installed along this interlocking pipe 18, and a second joint box 46 is installed along the first joint box 44 in a manner described later (FIG. 8). . In the illustrated example,
The side surface of the first joint box 44 facing the interlocking pipe 18 is formed into a concave surface 45 that is concave inward to fit the outer peripheral surface of the interlocking pipe 18. This is preferred because the concave surface 45 can be used as a guide surface for the bucket when the second hole is excavated by the clamshell bucket after the interlocking pipe 18 is pulled out.
第2のジヨイントボツクス46の外周面47に
凹状の保持部48が設けられ、この保持部48に
軟質部材22を保持する。保持部48は軟質部材
の横断面を実質的に2分する位置で軟質部材22
の軸線に沿う部分25を保持しており、外周面4
7から突出した軟質部材の部分24が第1の孔1
0の幅方向の孔壁面26,27間に位置するよう
に、第2のジヨイントボツクス46を第1の孔1
0に建込む。図示の例では、第2のジヨイントボ
ツクス46の幅方向の側面49と孔壁面26,2
7との間にそれぞれエアーバツグ50が介装され
ている。このエアーバツグに圧縮空気を封入して
孔壁面と密着させ、第1の孔10に打設されたコ
ンクリートが第1のジヨイントボツクス44の方
へ回り込むのを防止する。エアーバツクに代えて
エアーホースとすることもできる。 A concave holding portion 48 is provided on the outer peripheral surface 47 of the second joint box 46, and the soft member 22 is held in this holding portion 48. The holding portion 48 holds the soft member 22 at a position that substantially bisects the cross section of the soft member.
It holds a portion 25 along the axis of the outer peripheral surface 4.
The portion 24 of the soft member protruding from the first hole 1
The second joint box 46 is inserted into the first hole 1 so that it is located between the hole wall surfaces 26 and 27 in the width direction of the hole 1.
Set it to 0. In the illustrated example, the widthwise side surface 49 of the second joint box 46 and the hole wall surfaces 26, 2
An air bag 50 is interposed between each of them and 7. This air bag is filled with compressed air and brought into close contact with the hole wall surface to prevent the concrete poured in the first hole 10 from going around toward the first joint box 44. An air hose can be used instead of an air bag.
第1の孔10に鉄筋篭28を入れ、トレミー管
30を設置した後、スライム処理し、コンクリー
トを打設する(第9図)。コンクリート硬化後、
インターロツキングパイプ18を引き抜き、その
後、軟質部材22をコンクリートに残留させて第
2のジヨイントボツクス46を引き抜く(第10
図)。インターロツキングパイプ18の引き抜き
に先立つて第2のジヨイントボツクス46を引き
抜くこともできる。しかし、引き抜きの容易さの
点では、インターロツキングパイプ18を先に引
き抜く方がよい。第2のジヨイントボツクス46
の引き抜きはエアーバツグ50の圧縮空気を排除
して行う。 After inserting the reinforcing bar cage 28 into the first hole 10 and installing the tremie pipe 30, slime treatment is performed and concrete is poured (FIG. 9). After concrete hardens,
The interlocking pipe 18 is pulled out, and then the second joint box 46 is pulled out with the soft member 22 remaining in the concrete (10th joint box 46).
figure). It is also possible to withdraw the second joint box 46 prior to withdrawing the interlocking pipe 18. However, in terms of ease of pulling out, it is better to pull out the interlocking pipe 18 first. Second joint box 46
The extraction is performed by removing the compressed air from the air bag 50.
第2のジヨイントボツクス46の引き抜きによ
つて生じた空間52内にスペーサボツクス54を
建込む(第11図)。スペーサボツクス54は凹
所55を備えており、この凹所55により軟質部
材22の、コンクリートから空間52へ突出して
いる部分25を覆い、保護する。スペーサボツク
ス54はコンクリート32の側面と第1のジヨイ
ントボツクス44の側面とにそれぞれ当接され、
第2の孔34の掘削時に第1のジヨイントボツク
ス44に加わる反力を受け止める。 A spacer box 54 is built into the space 52 created by pulling out the second joint box 46 (FIG. 11). The spacer box 54 is provided with a recess 55 which covers and protects the portion 25 of the soft member 22 which projects from the concrete into the space 52. The spacer box 54 is in contact with the side surface of the concrete 32 and the side surface of the first joint box 44, respectively,
The reaction force applied to the first joint box 44 during excavation of the second hole 34 is received.
前記と同じ手順により第2の孔34を掘削した
後、第1のジヨイントボツクス44およびスペー
サボツクス54を引き抜き、前記と同じ手順によ
りコンクリートを打設する(第12図)。その後、
地中壁32,36の接続部38において、前記と
同じく軟質部材22から周囲のコンクリートにわ
たる孔を穿ち、透水テスト、グラウチング処理し
た後、膨張モルタル又は無収縮モルタル42を孔
に充填する。 After the second hole 34 is excavated in the same manner as described above, the first joint box 44 and spacer box 54 are pulled out, and concrete is poured in the same manner as described above (FIG. 12). after that,
At the connecting portion 38 of the underground walls 32, 36, a hole is drilled from the soft member 22 to the surrounding concrete in the same manner as described above, and after a water permeability test and grouting treatment, the hole is filled with expanding mortar or non-shrinking mortar 42.
第13図ないし第16図はさらに別の接続方法
である。 FIGS. 13 to 16 show still another connection method.
前記と同じ手順によつて掘削した第1の孔10
の端部にインターロツキングパイプ18を建込
み、このインターロツキングパイプ18に沿わせ
てプレキヤストのコンクリートブロツク58を建
込む(第13図)。 First hole 10 drilled by the same procedure as above
An interlocking pipe 18 is erected at the end of the interlocking pipe 18, and a precast concrete block 58 is erected along this interlocking pipe 18 (FIG. 13).
コンクリートブロツク58は中央に貫通孔60
を備えており、第1の孔10の孔壁面26,27
間にわたる幅を有する。コンクリートブロツク5
8のインターロツキングパイプ18に対面する側
面は、このインターロツキングパイプ18に適合
する、内方に向けて凹状となつた凹状面59に形
成されている。この凹状面59は第2の孔掘削時
に、クラムシエル型バケツトの案内面となる。図
示の例では、凹状面59は貫通孔60に対して対
称状に設けられている。このようにすると、コン
クリートブロツク58を建込むとき、設置方向を
任意にできるので、作業性が良い。コンクリート
ブロツク58の最小厚み部分の厚みWは、その後
に穿孔する孔の口径より50mmあるいはそれ以上小
さくなるように設定することが好ましい。このよ
うにすると、後の穿孔が容易である。 The concrete block 58 has a through hole 60 in the center.
The hole wall surfaces 26, 27 of the first hole 10
It has a width between concrete block 5
The side surface facing the interlocking pipe 18 of No. 8 is formed into a concave surface 59 that is concave toward the inside and fits the interlocking pipe 18. This concave surface 59 serves as a guide surface for the clamshell bucket during the second hole drilling. In the illustrated example, the concave surface 59 is provided symmetrically with respect to the through hole 60. In this way, when erecting the concrete block 58, the installation direction can be set arbitrarily, so that work efficiency is improved. It is preferable that the thickness W of the minimum thickness portion of the concrete block 58 is set to be 50 mm or more smaller than the diameter of the hole to be drilled thereafter. In this way, later drilling becomes easier.
コンクリートブロツク58は貫通孔58の軸線
が鉛直となるように建込まれる。地中壁の深さが
大きい場合には、コンクリートブロツク58は鉛
直方向に複数個が積層される。この場合の、コン
クリートブロツク58相互間の接続部は、例えば
シールド工法におけるセグメント方式のオス・メ
スのチヤツクピンと同様のチヤンクピンによつて
接続できるように形成する。 The concrete block 58 is built so that the axis of the through hole 58 is vertical. When the depth of the underground wall is large, a plurality of concrete blocks 58 are stacked vertically. In this case, the connecting portions between the concrete blocks 58 are formed so that they can be connected, for example, by chain pins similar to segment type male and female chuck pins in the shield construction method.
コンクリートブロツク58を建込んだ後、第1
の孔10に鉄筋篭28を入れてコンクリートを打
設し、このコンクリート硬化後に、インターロツ
キングパイプ18を引き抜く(第14図)。その
後第2の孔34を掘削し、鉄筋篭28を入れてコ
ンクリートを打設する。コンクリートの収縮後、
コンクリートブロツク58の貫通孔60の内周面
61をビツトの案内面として、コンクリートブロ
ツク58から地中壁32,36のコンクリートに
わたる孔62を穿ち、透水テスト、グラウチング
処理した後、孔62に膨張モルタル又は無収縮モ
ルタル42を充填する。この例は特に深度が大き
い場合に好適である。 After constructing concrete block 58, the first
A reinforcing bar cage 28 is inserted into the hole 10, concrete is poured, and after the concrete hardens, the interlocking pipe 18 is pulled out (FIG. 14). After that, a second hole 34 is excavated, a reinforcing bar cage 28 is inserted, and concrete is poured. After concrete shrinks,
Using the inner peripheral surface 61 of the through hole 60 of the concrete block 58 as a guide surface for the bit, a hole 62 is drilled from the concrete block 58 to the concrete of the underground walls 32 and 36, and after a water permeability test and grouting treatment, the hole 62 is filled with expanded mortar. Or fill with non-shrinkage mortar 42. This example is particularly suitable when the depth is large.
本発明の接続方法によつて奏される作用効果は
次の通り要約される。 The effects achieved by the connection method of the present invention are summarized as follows.
(イ) 打設したコンクリート中に埋め込まれた軟質
部材を囲むコンクリートの軟質部材との境界面
又は前もつて貫通孔が設けられたコンクリート
ブロツクの該貫通孔の内周面をビツトの案内面
としてビツトを進入させ、先行して構築された
地中壁と後行して構築された地中壁とのコンク
リートにわたる穿孔をするので、ビツトの案内
が確実であり、穿孔そのものも極めて容易にで
きる上に、穿孔によつて安定液の泥膜、スライ
ム集積部、モルタル分が不足して骨材が露出し
たいわゆるジヤンカ等の弱体箇所を削り取るこ
とができる。(b) The boundary surface of the concrete surrounding the soft member embedded in the poured concrete with the soft member, or the inner circumferential surface of the through hole of a concrete block previously provided with the through hole, is used as the guide surface for the bit. Since the bit is advanced and the hole is drilled across the concrete between the underground wall constructed beforehand and the underground wall constructed afterward, the guidance of the bit is reliable, and the drilling itself is extremely easy. In addition, by drilling, it is possible to scrape off weak areas such as the mud film of the stabilizing liquid, slime accumulation areas, and so-called junks where aggregate is exposed due to lack of mortar.
(ロ) 孔の透水テストの結果得られた透水度又はボ
アホールテレビによる視認から割目の状態や弱
体箇所を調査、確認できる。(b) The condition of cracks and weak points can be investigated and confirmed based on the water permeability obtained as a result of the water permeability test of the hole or visual confirmation using borehole television.
(ハ) 透水テスト又はボアホールテレビの視認の結
果に基づいて、割目や弱体箇所をグラウチング
処理した後、あるいはグラウチング処理せず
に、膨張モルタル又は無収縮モルタルを充填す
ることにより、接続部に完全に近い止水性をも
たせ、また弱体箇所の補強が可能である。(c) Based on the results of water permeability tests or borehole TV visual inspection, the joints can be completely sealed by grouting cracks and weak points or by filling with expanding mortar or non-shrinking mortar without grouting. It has water-tightness close to that of the original, and can also strengthen weak areas.
(ニ) 隣接する地中壁の接続部には特別の仕切り鋼
材、H型鋼のような埋込物を設けることを要し
ないので、安価に構築でき、経済性の点で優れ
ている。(d) Since it is not necessary to install special partition steel materials or embedded objects such as H-beam steel at the joints between adjacent underground walls, it can be constructed at low cost and is excellent in terms of economy.
前記作用効果よりして、本発明はダムの遮水
壁、地下永久構造物、大深度地下構造物などの地
中連続壁を構築する場合に、段階的に構築される
地中壁を接続するとき特に適する。 Based on the above-mentioned effects, the present invention connects underground walls that are constructed in stages when constructing underground continuous walls such as impermeable walls of dams, underground permanent structures, deep underground structures, etc. Particularly suitable when
第1図ないし第6図は第一番目の発明の手順を
示す断面図、第7図は拡孔ビツトの正面図、第8
図ないし第12図は第二番目の発明の手順を示す
断面図、第13図ないし第16図は第三番目の発
明の手順を示す断面図である。
10:第1の孔、18:インターロツキングパ
イプ(遮断部材)、20:保持部、22:軟質部
材、26,27:孔壁面、28:鉄筋篭、30:
トレミー管、32,36:地中壁、38:接続
部、40:コンクリート壁面、42:モルタル、
44:第1のジヨイントボツクス、46:第2の
ジヨイントボツクス、57:エアーバツク、5
2:空間、54:スペーサブロツク、58:プレ
キヤストコンクリートブロツク、60:貫通孔。
Figures 1 to 6 are sectional views showing the procedure of the first invention, Figure 7 is a front view of the hole expanding bit, and Figure 8 is a front view of the hole expanding bit.
12 to 12 are sectional views showing the procedure of the second invention, and FIGS. 13 to 16 are sectional views showing the procedure of the third invention. 10: First hole, 18: Interlocking pipe (blocking member), 20: Holding part, 22: Soft member, 26, 27: Hole wall surface, 28: Rebar cage, 30:
Tremy pipe, 32, 36: underground wall, 38: connection, 40: concrete wall, 42: mortar,
44: First joint box, 46: Second joint box, 57: Air bag, 5
2: Space, 54: Spacer block, 58: Precast concrete block, 60: Through hole.
Claims (1)
れる地中壁を接続する方法であつて、第1の孔の
端部に、外周面に凹状の保持部を有しかつ該保持
部に軟質部材を保持した遮断手段を、前記軟質部
材が前記第1の孔の幅方向の孔壁面間に位置する
ように建込むこと、前記第1の孔にコンクリート
を打設すること、該コンクリートの硬化後前記軟
質部材を残留させて前記遮断手段を前記第1の孔
から引き抜くこと、前記第1の孔の前記端部側で
前記第1の孔を延長すべく掘削された第2の孔に
コンクリートを打設すること、該コンクリートの
硬化後前記軟質部材を囲む前記コンクリートの前
記軟質部材との境界面をビツトの案内面として前
記軟質部材からその周囲のコンクリートにわたる
孔を穿つこと、該孔にモルタルを充填することを
含む、地中壁の接続方法。 2 前記保持部は前記遮断手段の全長にわたつて
設けられており、前記軟質部材は前記遮断手段と
ほぼ等しい長さを有する、特許請求の範囲第1項
に記載の接続方法。 3 前記遮断手段に保持された前記軟質部材は該
遮断手段の外周面から突出する部分を有し、該部
分の横断面積は前記保持部に保持された部分の横
断面積より大である、特許請求の範囲第1又は2
項に記載の接続方法。 4 コンクリートを段階的に場所打ちして構築さ
れる地中壁を接続する方法であつて、第1の孔の
端部に遮断手段を建込むこと、該遮断手段に沿わ
せて第1のジヨイントボツクスを建込むこと、外
周面に凹状の保持部を有しかつ該保持部に軟質部
材を保持した第2のジヨイントボツクスを、前記
軟質部材が前記第1の孔の幅方向の孔壁面間に位
置するように前記第1のジヨイントボツクスに沿
わせて建込むこと、前記第1の孔にコンクリート
を打設すること、該コンクリートの硬化後前記遮
断手段を前記第1の孔から引き抜くこと、前記遮
断手段の引き抜き後またはこれに先立つて前記軟
質部材を残留させて前記第2のジヨイントボツク
スを前記第1の孔から引き抜くこと、前記第2の
ジヨイントボツクスの引き抜きによつて生じた空
間内に前記軟質部材を覆いしかも前記第1のジヨ
イントボツクスと前記コンクリートに接触するス
ペーサボツクスを建込むこと、前記第1の孔の前
記端部側で該第1の孔を延長すべく掘削された第
2の孔から前記スペーサボツクスおよび第1のジ
ヨイントボツクスを引き抜いた後該第2の孔にコ
ンクリートを打設すること、該コンクリートの硬
化後前記軟質部材を囲むコンクリートの前記軟質
部材との境界面をビツトの案内面として軟質部材
から周囲のコンクリートにわたる孔を穿つこと、
該孔にモルタルを充填することを含む、地中壁の
接続方法。 5 前記第2のジヨイントボツクスと前記孔壁面
との間にシール用のエアバツグを配置する、特許
請求の範囲第4項に記載の接続方法。 6 コンクリートを段階的に場所打ちして構築さ
れる地中壁を接続する方法であつて、第1の孔の
端部に遮断手段を建込むこと、貫通孔を有するコ
ンクリートブロツクを前記遮断手段に沿わせて建
込むこと、前記第1の孔にコンクリートを打設す
ること、該コンクリートの硬化後前記遮断手段を
前記第1の孔から引き抜くこと、前記第1の孔の
前記端部側で該第1の孔を延長すべく掘削された
第2の孔にコンクリートを打設すること、該コン
クリートの硬化後前記コンクリートブロツクの貫
通孔の内周面をビツトの案内面として該コンクリ
ートブロツクから前記第1および第2の孔に打設
された前記コンクリートにわたる孔を穿つこと、
該孔にモルタルを充填することを含む、地中壁の
接続方法。[Claims] 1. A method for connecting underground walls constructed by pouring concrete in stages in a step-by-step manner, the first hole having a concave holding portion on its outer peripheral surface at the end thereof; erecting a blocking means holding a soft member in the holding portion such that the soft member is located between the hole wall surfaces in the width direction of the first hole; and pouring concrete into the first hole. , pulling out the blocking means from the first hole with the soft member remaining after the concrete hardens, and a first hole excavated to extend the first hole at the end side of the first hole pouring concrete into the hole No. 2, and after the concrete hardens, drilling a hole extending from the soft member to the surrounding concrete using the boundary surface of the concrete surrounding the soft member with the soft member as a guide surface for the bit; , a method for connecting an underground wall, comprising filling the hole with mortar. 2. The connection method according to claim 1, wherein the holding portion is provided over the entire length of the blocking means, and the soft member has a length approximately equal to that of the blocking means. 3. The soft member held by the blocking means has a portion protruding from the outer peripheral surface of the blocking means, and the cross-sectional area of the portion is larger than the cross-sectional area of the portion held by the holding portion. Range 1 or 2
Connection method described in section. 4. A method for connecting underground walls constructed by pouring concrete in stages in stages, in which a blocking means is built at the end of the first hole, and a first joint is installed along the blocking means. A second joint box having a concave holding portion on its outer circumferential surface and holding a soft member in the holding portion is installed so that the soft member is attached to the hole wall surface in the width direction of the first hole. placing concrete along the first joint box so as to be located in between; placing concrete in the first hole; and pulling out the blocking means from the first hole after the concrete hardens. The second joint box may be pulled out from the first hole with the soft member remaining after or prior to the withdrawal of the blocking means, or the second joint box may be pulled out. erecting a spacer box that covers the soft member and contacts the first joint box and the concrete in the space formed by the flexible member; and extending the first hole at the end side of the first hole. pouring concrete into the second hole after pulling out the spacer box and the first joint box from the excavated second hole; and after the concrete hardens, the soft member of concrete surrounding the soft member; Drilling a hole from the soft member to the surrounding concrete using the interface with the bit as a guide surface for the bit,
A method for connecting an underground wall, the method comprising filling the hole with mortar. 5. The connection method according to claim 4, wherein a sealing air bag is disposed between the second joint box and the hole wall surface. 6. A method for connecting underground walls constructed by pouring concrete in stages in places, which includes constructing a blocking means at the end of the first hole, and placing a concrete block with a through hole in the blocking means. placing concrete in the first hole; pulling out the blocking means from the first hole after the concrete has hardened; and placing concrete on the end side of the first hole. pouring concrete into a second hole drilled to extend the first hole; after the concrete hardens, the concrete block is moved from the concrete block to the second hole using the inner peripheral surface of the through hole of the concrete block as a guide surface for a bit; drilling a hole across the concrete cast in the first and second holes;
A method for connecting an underground wall, the method comprising filling the hole with mortar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57068766A JPS58185822A (en) | 1982-04-26 | 1982-04-26 | Connection of underground wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57068766A JPS58185822A (en) | 1982-04-26 | 1982-04-26 | Connection of underground wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS58185822A JPS58185822A (en) | 1983-10-29 |
JPH0138927B2 true JPH0138927B2 (en) | 1989-08-17 |
Family
ID=13383178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP57068766A Granted JPS58185822A (en) | 1982-04-26 | 1982-04-26 | Connection of underground wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58185822A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4971707A (en) * | 1972-11-13 | 1974-07-11 | ||
JPS5526334A (en) * | 1978-08-11 | 1980-02-25 | Mitsui Constr Co Ltd | Constructing method of underground continuous wall |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5426502B1 (en) * | 1971-03-03 | 1979-09-04 |
-
1982
- 1982-04-26 JP JP57068766A patent/JPS58185822A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4971707A (en) * | 1972-11-13 | 1974-07-11 | ||
JPS5526334A (en) * | 1978-08-11 | 1980-02-25 | Mitsui Constr Co Ltd | Constructing method of underground continuous wall |
Also Published As
Publication number | Publication date |
---|---|
JPS58185822A (en) | 1983-10-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4451553B2 (en) | Buoyancy prevention structure and construction method thereof | |
GB2264739A (en) | Diaphragm wall with liquid tight joints | |
US4367057A (en) | Method of forming a foundation with liquid tight joints | |
EP0580926A1 (en) | Sealing joint in diaphragms formed by concrete panels cast in situ and a process for building said diaphragms | |
JP2005120622A (en) | Construction method of underground structure | |
JP2533853B2 (en) | Pile construction method | |
JPH0138927B2 (en) | ||
US4430027A (en) | Method of forming a foundation with liquid tight joints | |
JPH0613770B2 (en) | Method of constructing mountain retaining wall with parent pile | |
JP3355282B2 (en) | Construction method of perforated sheet pile and continuous underground wall having permeation section using this sheet pile | |
JP4086400B2 (en) | Propulsion shaft, its construction method and propulsion method | |
JPH1162469A (en) | Structure of earth retaining wall in shield shaft and method of starting and reaching shield machine | |
JP3311961B2 (en) | Continuous wall permeation method using water permeation pipe | |
JPS6358975B2 (en) | ||
JP2001329779A (en) | Construction method for reinforcing natural ground | |
JP2001152444A (en) | Column wall construction method | |
JP3509066B2 (en) | Pipe burial method | |
IE57077B1 (en) | A method of and apparatus for grouting | |
JPS60199123A (en) | Water-proofing work for concrete wall | |
JPS6361479B2 (en) | ||
JPS584021A (en) | Underground wall construction work | |
JPH0133610B2 (en) | ||
EP0736665A2 (en) | Construction of holes and tunnels having support walls | |
JPS6019369B2 (en) | How to build a diaphragm wall | |
JPS6360172B2 (en) |