JPH01235705A - Dryer for asphalt plant - Google Patents

Dryer for asphalt plant

Info

Publication number
JPH01235705A
JPH01235705A JP6272188A JP6272188A JPH01235705A JP H01235705 A JPH01235705 A JP H01235705A JP 6272188 A JP6272188 A JP 6272188A JP 6272188 A JP6272188 A JP 6272188A JP H01235705 A JPH01235705 A JP H01235705A
Authority
JP
Japan
Prior art keywords
drum
hopper
aggregate
hot
waste material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6272188A
Other languages
Japanese (ja)
Other versions
JPH0515843B2 (en
Inventor
Katsuhiko Nishio
西尾 勝彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nikko KK
Original Assignee
Nikko KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nikko KK filed Critical Nikko KK
Priority to JP6272188A priority Critical patent/JPH01235705A/en
Publication of JPH01235705A publication Critical patent/JPH01235705A/en
Publication of JPH0515843B2 publication Critical patent/JPH0515843B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)

Abstract

PURPOSE:To contemplate simplification of a device structure and saving of an installation space, by heating fresh aggregates and spent aggregates together in only one drying drum. CONSTITUTION:A drum 3 is provided at one end with a hot hopper 6 having a burner 7 for heating aggregates, and at the other end with a cold hopper 10 having a flue gas duct 11. Two rows of through-holes 15 and 16 are formed on the drum 3 circumferentially along and in the vicinity of a lateral center thereof, and surrounded and closed with cover members 18, respectively. A feed inlet 19 for fresh aggregates is provided on the cover member 18 disposed on the hot hopper side, while an outlet 8 for the fresh aggregates is formed on the lower part of the hot hopper 6. On the other hand, spent material is fed through an inlet 25 of the cold hopper 10 into the drum and discharged through an outlet 30 formed on the lower part of the cover member on the cold hopper side. Moreover, in a dryer apparatus 1 for an asphalt plant, an inner tube member 9 is disposed within the drum 3 to branch the hot air supplied from the hot hopper.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は通路舗装材であるアスファルト合材を製造する
アスファルトプラントの骨材加熱装置であるドライヤに
関し、特に新規骨材及び廃材の両材料も加熱することが
できるドライヤに関するものである。
Detailed Description of the Invention [Industrial Field of Application] The present invention relates to a dryer that is an aggregate heating device for an asphalt plant that produces asphalt mixture that is a path paving material, and particularly relates to a dryer that is an aggregate heating device for an asphalt plant that produces asphalt mixture that is a path paving material. The present invention relates to a dryer that can be heated.

[従来技術] 道路工事等によって掘り起こされたアスファルト舗装廃
材(以下「廃材」という)は加熱再生されてアスファル
ト合材として再利用されるようになってきており、この
廃材を加熱する装置は、−殺菌にはアスファルトプラン
トの新規骨材加熱装置であるドライヤとほぼ同構造のも
のが採用されている。そして、上記廃材加熱用のドライ
ヤはアスファルトプラントのドライヤと併設されること
が多い。
[Prior art] Asphalt pavement waste materials (hereinafter referred to as "waste materials") dug up during road construction, etc. are being heated and regenerated and reused as asphalt mixture, and devices for heating this waste material are - For sterilization, a device with almost the same structure as a dryer, a new aggregate heating device for asphalt plants, is used. The dryer for heating waste materials is often installed alongside the dryer of an asphalt plant.

[発明が解決しようとする課題] しかしながら、新規骨材加熱用ドライヤと廃材加熱用ド
ライヤを同一工場の敷地内に併設すると装置の構成及び
配置が繁雑となり、敷地面積を有効、に利用することが
できない。
[Problem to be solved by the invention] However, if a dryer for heating new aggregates and a dryer for heating waste materials are installed together on the same factory premises, the configuration and arrangement of the equipment will become complicated, making it difficult to use the site area effectively. Can not.

そこで、本発明は上記の点に鑑み、新規骨材と廃材の両
材料を単一のドラムで加熱することができるドライヤを
提案することを目的とするものである。
Therefore, in view of the above points, the present invention aims to propose a dryer that can heat both new aggregate and waste materials with a single drum.

[課題を解決するための手段] 本発明は上記課題を解決するために、一端部に骨材加熱
用バーナを有したホットホッパを、他端部に排気煙道を
有したコールドホッパを配設し、回転自在に傾斜枢支し
たドラムのほぼ中央部付近のドラム周壁に沿って適宜間
隔で透孔を二列穿設し、該透孔を外周部からカバー体で
それぞれ包囲し、骨材加熱用バーナ側に位置するカバー
体の上部に新規骨材投入部を、ホットホッパ下部に新規
骨材排出部を配設するとともに、コールドホッパに新規
骨材をも供給できる廃材供給部を、コールドホッパ側に
位置するカバー体下部に排出ゲートを有する廃材排出口
を配設する一方、前記ドラムのバーナ寄りの前半部に熱
風を分流通過させる筒状体を挿入配設したことを特徴と
するアスファルトプラントのドライヤを提供するもので
ある。
[Means for Solving the Problems] In order to solve the above problems, the present invention provides a hot hopper having an aggregate heating burner at one end and a cold hopper having an exhaust flue at the other end. Then, two rows of through holes are bored at appropriate intervals along the circumferential wall of the drum, which is rotatably supported in an inclined manner, at an appropriate interval. A new aggregate input section is installed at the top of the cover body located on the burner side, and a new aggregate discharge section is installed at the bottom of the hot hopper. An asphalt plant characterized in that a waste material discharge port having a discharge gate is disposed in the lower part of the cover body located on the side, and a cylindrical body for passing hot air in a divided manner is inserted in the front half of the drum near the burner. dryer.

[作 用] 本発明によれば、新規骨材と廃材を同時に加熱する場合
は、ドラム中央部付近のコールドホッパ側に位置するカ
バー体下部の排出ゲートを開動作させておき、ドラムの
一端部に配設した骨材加熱用バーナより発生させた高温
の熱風をドラム内に送り込み、他端部のコールドホッパ
に配設された排気煙道へ導出する一方、ドラム中央部付
近のホットホッパ側のカバー体上部の新規骨材供給部か
ら新規骨材をドラム内に供給し、ドラムのバーナ寄りの
前半部内を転勤流下する間に熱風と熱交換させて所望の
温度まで加熱し、ホットホッパ下部の新規骨材排出口よ
り排出する。またコールドホ・ンパ側から廃材をドラム
内に供給し、ドラムの後半部内を転勤流下する間に、ド
ラム前半部に挿入配設された筒状体内を通過してくる熱
風と、筒状体の外側を通過し新規骨材と熱交換して温度
低下した熱風とを混合して廃材を必要以上に加熱しない
温度に調整した熱風によって所望の温度まで加熱し、ド
ラム中央部付近に穿設した透孔を通してカバー体下部の
廃材排出口より排出する。
[Function] According to the present invention, when new aggregate and waste material are heated simultaneously, the discharge gate at the lower part of the cover body located on the cold hopper side near the center of the drum is opened, and one end of the drum is heated. High-temperature hot air generated by the aggregate heating burner installed at the drum is sent into the drum and led out to the exhaust flue installed at the cold hopper at the other end, while the hot air at the hot hopper side near the center of the drum is New aggregate is supplied into the drum from the new aggregate supply section on the upper part of the cover body, and while flowing down the front half of the drum near the burner, it is heated to the desired temperature by exchanging heat with hot air, and is heated to the desired temperature at the bottom of the hot hopper. Discharge from the new aggregate discharge port. In addition, while the waste material is supplied into the drum from the cold press machine side and transferred down the rear half of the drum, the hot air passing through the cylindrical body inserted into the front half of the drum and the outside of the cylindrical body The waste material is heated to the desired temperature by the heated air, which has been adjusted to a temperature that does not heat the waste material more than necessary, by mixing it with hot air that has lowered its temperature by exchanging heat with the new aggregate. through the waste material outlet at the bottom of the cover body.

なお、新規骨材のみを加熱する場合は、ドラムの中央部
付近のカバー体下部の排出ゲートを閉動作させて廃材排
出口より骨材が外部に流出するのを阻止しながらドラム
の一端部の骨材加熱用バーナによりドラム内に高温の熱
風を送り込む一方、コールドホッパ側から新規骨材を供
給し、ドラムの中央部付近に穿設した透孔から落下する
一部の骨材をカバー体下部に溜めながらドラム内を転勤
流下させる間に所望の温度まで加熱し、ホットホッパ下
部の新規骨材排出口より加熱した骨材を排出するのであ
る。
In addition, when heating only new aggregate, close the discharge gate at the bottom of the cover near the center of the drum to prevent aggregate from flowing out from the waste material discharge port, while heating one end of the drum. While the aggregate heating burner sends high-temperature hot air into the drum, new aggregate is supplied from the cold hopper side, and some of the aggregate that falls through the hole drilled near the center of the drum is transferred to the lower part of the cover body. The heated aggregate is heated to a desired temperature while being stored in the drum and flowing down the drum, and the heated aggregate is discharged from the new aggregate discharge port at the bottom of the hot hopper.

[実施例] 以下本発明の実施例を図面に基づいて説明する。[Example] Embodiments of the present invention will be described below based on the drawings.

■は新規骨材及び廃材を加熱するドライヤであって、内
部に多数の掻き上げ羽根2を周設した円筒状のドラム3
を機台4上の支持ローラ5によって回転自在に傾斜枢支
し、駆動装置(図示せず)により所定の速度で回転させ
ている。6はドラムの一端部に配設したホットホッパで
、該ホットホッパ6にはドラム3内に熱風を送り込む骨
材加熱用バーナ7が配設され、またホットホッパ6下部
には加熱された新規骨材を排出する新規骨材排出口8が
形成されている。ドラム3のバーナ7寄りの前半部内に
はバーナ7で発生する熱風を分流し、熱風の一部を高温
度に維持したままドラム3の後半部に通過させる適宜口
径の筒状体9が挿入配設されている。
■ is a dryer that heats new aggregate and waste materials, and is a cylindrical drum 3 with a large number of scraping blades 2 installed around it.
is tilted and rotatably supported by support rollers 5 on a machine stand 4, and is rotated at a predetermined speed by a drive device (not shown). Reference numeral 6 denotes a hot hopper disposed at one end of the drum, and the hot hopper 6 is equipped with an aggregate heating burner 7 that sends hot air into the drum 3, and the lower part of the hot hopper 6 is equipped with heated new bone. A new aggregate discharge port 8 for discharging aggregate material is formed. A cylindrical body 9 of an appropriate diameter is inserted into the front half of the drum 3 near the burner 7 to separate the hot air generated by the burner 7 and allow a part of the hot air to pass through the rear half of the drum 3 while maintaining a high temperature. It is set up.

ドラム3の他端部にはコールドホッパ10が配設され、
該コールドホッパ10にはドラム3内を通過した排ガス
を導出する排気煙道11が連結されており、該排気煙道
11の下流には飛散するダスト捕促用の集塵機12、及
びガス吸引用の排風機13が配設されている。
A cold hopper 10 is arranged at the other end of the drum 3,
An exhaust flue 11 is connected to the cold hopper 10 for discharging the exhaust gas that has passed through the drum 3, and downstream of the exhaust flue 11 there is a dust collector 12 for catching scattered dust, and a dust collector 12 for collecting the scattered dust. An exhaust fan 13 is provided.

ドラム3のほぼ中央部付近の内周壁には適宜高さの堰1
4が周設され、該堰14を挟んだドラム3の周壁に沿っ
て適宜間隔で二列の透孔15.16が穿設されており、
該透孔15.16のそれぞれを外周部よりドラム3と切
り離して固定されたカバー体17.18で包囲しである
。19はカバー体17の上部に配設した新規骨材投入用
シュートであって、その先端部はカバー体17を貫通し
てドラム3に穿設した透孔15に臨ませて新規骨材を透
孔15よりドラム3内に投入するようにしてあり、透孔
15には新規骨材がドラム3内にスムーズに投入される
ように案内シュート20が取付けである。21a〜21
dは各種粒径側に新規骨材を貯蔵する骨材ホッパであり
、該骨材ホッパから切り出しフィーダ22a〜22dに
より所定量切り出した新規骨材をコンベヤ23、コンベ
ヤ24を介して新規骨材投入用シュート19に供給する
ようにしている。25a〜25bは各種粒径側に廃材を
貯蔵する廃材ホッパであり、該廃材ホッパ25a〜25
bから切り出しフィーダ26a、26bにより所定量切
り出した廃材をコンベヤ27、コンベヤ28を介してド
ラム3内に供給するようにしである。
A weir 1 of an appropriate height is installed on the inner wall near the center of the drum 3.
4 are provided around the drum 3, and two rows of through holes 15 and 16 are bored at appropriate intervals along the peripheral wall of the drum 3 sandwiching the weir 14,
Each of the through holes 15 and 16 is surrounded by a cover body 17 and 18 that is fixed and separated from the drum 3 from the outer periphery. Reference numeral 19 denotes a chute for introducing new aggregate arranged at the upper part of the cover body 17, and its tip passes through the cover body 17 and faces the through hole 15 drilled in the drum 3, so that the new aggregate is introduced through the chute. The new aggregate is fed into the drum 3 through the hole 15, and a guide chute 20 is attached to the through hole 15 so that the new aggregate can be fed smoothly into the drum 3. 21a-21
d is an aggregate hopper that stores new aggregate on the side of various particle sizes, and feeders 22a to 22d cut out a predetermined amount of new aggregate from the aggregate hopper and input the new aggregate via conveyors 23 and 24. The liquid is supplied to a chute 19 for use. 25a to 25b are waste material hoppers that store waste materials on the side of various particle sizes, and the waste material hoppers 25a to 25
A predetermined amount of waste material is cut out from the feeders 26a and 26b from the waste material 26a and 26b, and is fed into the drum 3 via a conveyor 27 and a conveyor 28.

また、骨材ホッパ21a〜21dに貯蔵する新規骨材の
みを加熱する場合には、ドラム3内に供給する骨材供給
量が多くなるので効率良く加熱するためにコールドホッ
パlO側から供給できるようにコンベヤ22とコンベヤ
27どの間に点線で示すように別のコンベヤ(図示せず
)を介在させている。ドラム3の中央部付近のカバー体
18下部にはドラム3内に供給され所望温度に加熱され
た廃材を外部に排出する排出ゲート29を有する廃材排
出口30が形成されている。
In addition, when only new aggregates stored in the aggregate hoppers 21a to 21d are heated, the amount of aggregate supplied into the drum 3 increases, so in order to heat efficiently, it is necessary to supply the aggregate from the cold hopper lO side. Another conveyor (not shown) is interposed between the conveyor 22 and the conveyor 27 as shown by a dotted line. A waste material discharge port 30 having a discharge gate 29 for discharging waste material supplied into the drum 3 and heated to a desired temperature to the outside is formed in the lower part of the cover body 18 near the center of the drum 3.

しかして、新規骨材と廃材を同時に加熱する場合は、ド
ラム中央部付近のコールドホッパ1o側に位置するカバ
ー体18下部の排出ゲート29を開動作し、骨材加熱用
バーナ7によりドラム3内に熱風を送り込む一方、各種
粒径側に新規骨材を貯蔵する骨材ホッパ21a〜21d
から切り出しフィーダ22a〜22dによって所定量切
り出した新規骨材をコンベヤ23.24を介してドラム
3の中央部付近の新規骨材投入用シュート19に供給し
、ドラム3の前半部内を転勤流下させる間に新規骨材を
所望温度まで加熱し、ホットホッパ6下部の新規骨材排
出口8より排出する。また、各種粒径側に廃材を貯蔵す
る廃材ホッパ25a、25bから切り出しフィーダ26
a、26bによって所定量の廃材を切り出し、コンベヤ
27.28を介してコールドホッパ側10よりドラム3
内に供給する。そして、ドラム3の前半部に挿入配設さ
れた筒状体9内を高温度を維持して通過してくる熱風と
、筒状体9の外側で新規骨材との接触によって熱交換し
て温度低下した熱風とを混合し、廃材を必要以上に加熱
しない温度に調整した熱風によってドラム3の後半部内
を転勤流下する廃材を所望の温度にまで加熱し、ドラム
3の周壁に沿って穿設した透孔16を通してカバー体1
8下部の廃材排出口30より排出させるのである。この
時、ドラム3の中央部付近の内周壁に周設した堰14は
、進行してきた廃材を透孔16に確実に落下させるのに
有効に作用する。
When heating new aggregate and waste material at the same time, the discharge gate 29 at the bottom of the cover body 18 located on the cold hopper 1o side near the center of the drum is opened, and the burner 7 for heating the aggregate is heated inside the drum 3. Aggregate hoppers 21a to 21d store new aggregate on the side of various particle sizes while sending hot air into the
A predetermined amount of new aggregate cut out from the feeders 22a to 22d is supplied to the new aggregate input chute 19 near the center of the drum 3 via the conveyor 23, 24, and is transferred and flowed down inside the front half of the drum 3. The new aggregate is heated to a desired temperature and discharged from the new aggregate outlet 8 at the bottom of the hot hopper 6. In addition, a feeder 26 is provided for cutting out waste materials from waste material hoppers 25a and 25b that store waste materials on the side of various particle sizes.
A and 26b cut out a predetermined amount of waste material, and convey it to the drum 3 from the cold hopper side 10 via conveyors 27 and 28.
supply within. Heat is exchanged between the hot air that maintains a high temperature and passes through the cylindrical body 9 inserted into the front half of the drum 3 and the new aggregate on the outside of the cylindrical body 9. The waste material flowing down the rear half of the drum 3 is heated to a desired temperature by mixing with hot air whose temperature has been lowered and adjusted to a temperature that does not overheat the waste material more than necessary, and the waste material is then drilled along the peripheral wall of the drum 3. cover body 1 through the through hole 16
The waste material is discharged from the waste material discharge port 30 at the bottom of 8. At this time, the weir 14 provided around the inner circumferential wall near the center of the drum 3 effectively acts to ensure that the advancing waste material falls into the through hole 16.

新規骨材のみを加熱する場合は、ドラム3の中央部付近
の廃材排出口30の排出ゲート29を閉動作し、骨材加
熱用バーナ7によりドラム3内に熱風を送り込む一方、
各種粒径側に骨材を貯蔵する骨材ホッパ21a〜21d
から切り出しフィーダ22a〜22dによって所定量切
り出した新規骨材をコンベヤ23からコンベヤ28に点
線で示すように別のコンベヤ(図示せず)で供給先を切
り替え、コールドホッパlO側に供給する。供給された
新規骨材はドラム3の後半部内を加熱されながら転勤流
下し、ドラム3の中央部付近に達するとドラム3の周壁
に穿設された透孔16からその一部がカバー体18に落
下し、カバー体18下部及び廃材排出口29に溜ること
となるが、その大部分はドラム3の内周壁に周設した堰
14tt乗り越えてドラム3の前半部へと進行して行く
、この時、骨材の一部はドラム3の中央部付近の周壁に
穿設された透孔15よりドラム3外に落下し、カバー体
17の下部に溜ることとなるが案内シュート20に掻き
上げられてドラム3内に戻される。
When only new aggregate is heated, the discharge gate 29 of the waste material discharge port 30 near the center of the drum 3 is closed, and hot air is sent into the drum 3 by the aggregate heating burner 7.
Aggregate hoppers 21a to 21d that store aggregate on the side of various particle sizes
A predetermined amount of new aggregate is cut out by the cutting feeders 22a to 22d from the conveyor 23 to the conveyor 28 as shown by the dotted line, and the supply destination is switched by another conveyor (not shown) and fed to the cold hopper IO side. The supplied new aggregate flows down while being heated in the rear half of the drum 3, and when it reaches the vicinity of the center of the drum 3, a part of it flows into the cover body 18 through a through hole 16 bored in the peripheral wall of the drum 3. It falls and accumulates in the lower part of the cover body 18 and the waste material discharge port 29, but most of it passes over the weir 14tt provided around the inner circumferential wall of the drum 3 and advances to the front half of the drum 3. A part of the aggregate falls to the outside of the drum 3 through the through hole 15 bored in the peripheral wall near the center of the drum 3 and accumulates at the bottom of the cover body 17, but is scraped up by the guide chute 20. It is returned into the drum 3.

そして、骨材はバーナ7に向ってドラム3内を転勤流下
する間に所望温度まで加熱され、ホットホッパ6下部の
新規骨材排出口8より排出されるのである。
The aggregate is heated to a desired temperature while flowing down the drum 3 toward the burner 7, and is discharged from the new aggregate discharge port 8 at the bottom of the hot hopper 6.

[発明の効果J 以上のように本発明ドライヤにあっては、単一のドラム
でもって新規骨材及び廃材の両材料を同時に加熱するこ
とも、またそれぞれ材料を単独に加熱することもでき、
しかも、装置をコンパクトにできるので装置の構成及び
配置が簡素となり省スペース化が計れるものである。
[Effect of the Invention J As described above, in the dryer of the present invention, both new aggregate and waste materials can be heated simultaneously with a single drum, or each material can be heated individually.
In addition, since the device can be made compact, the configuration and arrangement of the device can be simplified and space can be saved.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明ドライヤの一実施例の一部切欠概略正面
図、第2図は第1図のA−A線切断拡大断面図である。 1・・・ドライヤ 2・・・掻き上げ羽根 3・・・ド
ラム6・・・ホットホッパ 7・・・骨材加熱用バーナ
 8・・・新規骨材排出口 9・・・筒状体 10・・
・コールドホッパ 11・・・排気煙道15.16・・
・透孔 17.18・・・カバー体 19・・・新規骨
材投入用シュート21a〜21d・・・骨材ホッパ 2
5a〜25b・・・廃材ホッパ 29・・・排出ゲート
30・・・廃材排出口
FIG. 1 is a partially cutaway schematic front view of an embodiment of the dryer of the present invention, and FIG. 2 is an enlarged sectional view taken along the line A--A in FIG. 1... Dryer 2... Scraping blade 3... Drum 6... Hot hopper 7... Burner for heating aggregates 8... New aggregate discharge port 9... Cylindrical body 10.・
・Cold hopper 11...Exhaust flue 15.16...
・Through hole 17.18... Cover body 19... Chute for introducing new aggregate 21a to 21d... Aggregate hopper 2
5a-25b...Waste material hopper 29...Discharge gate 30...Waste material discharge port

Claims (1)

【特許請求の範囲】[Claims] 一端部に骨材加熱用バーナを有したホットホッパを、他
端部に排気煙道を有したコールドホッパを配設し、回転
自在に傾斜枢支したドラムのほぼ中央部付近のドラム周
壁に沿って適宜間隔で透孔を二列穿設し、該透孔を外周
部からカバー体でそれぞれ包囲し、骨材加熱用バーナ側
に位置するカバー体の上部に新規骨材投入部を、ホット
ホッパ下部に新規骨材排出口を配設するとともに、コー
ルドホッパに新規骨材をも供給できる廃材供給部を、コ
ールドホッパ側に位置するカバー体下部に排出ゲートを
有する廃材排出口を配設する一方、前記ドラムのバーナ
寄りの前半部に熱風を分流通過させる筒状体を挿入配設
したことを特徴とするアスファルトプラントのドライヤ
A hot hopper with a burner for heating aggregates at one end and a cold hopper with an exhaust flue at the other end are installed along the peripheral wall of the drum near the center of the drum, which is rotatably supported at an angle. Two rows of through holes are drilled at appropriate intervals, each of the through holes is surrounded by a cover body from the outer periphery, and a new aggregate input part is placed in the upper part of the cover body located on the aggregate heating burner side, and the hot hopper is inserted into the hot hopper. A new aggregate discharge port is provided at the bottom, and a waste material supply section that can also supply new aggregate to the cold hopper is provided, while a waste material discharge port with a discharge gate is provided at the bottom of the cover body located on the cold hopper side. A dryer for an asphalt plant, characterized in that a cylindrical body is inserted into the front half of the drum near the burner to allow hot air to pass through in a divided manner.
JP6272188A 1988-03-15 1988-03-15 Dryer for asphalt plant Granted JPH01235705A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6272188A JPH01235705A (en) 1988-03-15 1988-03-15 Dryer for asphalt plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6272188A JPH01235705A (en) 1988-03-15 1988-03-15 Dryer for asphalt plant

Publications (2)

Publication Number Publication Date
JPH01235705A true JPH01235705A (en) 1989-09-20
JPH0515843B2 JPH0515843B2 (en) 1993-03-02

Family

ID=13208498

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6272188A Granted JPH01235705A (en) 1988-03-15 1988-03-15 Dryer for asphalt plant

Country Status (1)

Country Link
JP (1) JPH01235705A (en)

Also Published As

Publication number Publication date
JPH0515843B2 (en) 1993-03-02

Similar Documents

Publication Publication Date Title
US5193935A (en) Soil decontamination apparatus and methods of decontaminating soil
US4371375A (en) Apparatus and process for drying sawdust
US4797002A (en) Apparatus for mixing asphalt compositions
WO2001088272A1 (en) Aggregate dryer for asphalt plant
JPH01315502A (en) Dryer for asphalt plant
JPH01235705A (en) Dryer for asphalt plant
JP2007105605A (en) Carbonization apparatus and the method
JP2005156085A (en) Livestock dung drying incineration equipment
US4412814A (en) Apparatus and method for operating a brick kiln
JPH01235704A (en) Dryer for asphalt plant
JPH0254006A (en) Dryer for asphalt plant
BR112019011596B1 (en) FACTORY FOR THE PRODUCTION AND DISTRIBUTION OF BITUMINOUS CONGLOMERATES
JP2003080226A (en) Cleaning method for contaminated soil and asphalt plant
JPH0512323Y2 (en)
US5238399A (en) Material treating apparatus
JPH03235803A (en) Asphalt plant dryer
JPH0415775Y2 (en)
JP4243516B2 (en) Asphalt plant capable of purifying contaminated soil
JP2611933B2 (en) Garbage disposal equipment including agricultural and marine wastes and method of operating this garbage disposal equipment including agricultural and marine wastes
JPH0355606Y2 (en)
JPH072652Y2 (en) Dryer for recycling asphalt pavement waste
JPH0355605Y2 (en)
JPS63138005A (en) Asphalt plant
JPH0526082Y2 (en)
JPH03100206A (en) Asphalt compound manufacturing method and device therefor