[go: up one dir, main page]

JP7628830B2 - Construction method for column-beam joint structure - Google Patents

Construction method for column-beam joint structure Download PDF

Info

Publication number
JP7628830B2
JP7628830B2 JP2021015680A JP2021015680A JP7628830B2 JP 7628830 B2 JP7628830 B2 JP 7628830B2 JP 2021015680 A JP2021015680 A JP 2021015680A JP 2021015680 A JP2021015680 A JP 2021015680A JP 7628830 B2 JP7628830 B2 JP 7628830B2
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
column
pipe
lower steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021015680A
Other languages
Japanese (ja)
Other versions
JP2022118883A (en
Inventor
隆之 佐川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2021015680A priority Critical patent/JP7628830B2/en
Publication of JP2022118883A publication Critical patent/JP2022118883A/en
Application granted granted Critical
Publication of JP7628830B2 publication Critical patent/JP7628830B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

本発明は、柱梁接合構造の施工方法に関するものである。 The present invention relates to a method for constructing a beam-column joint structure.

従来から、鋼管の内部に接合鉄筋(主筋)及びコンクリートが充填されたコンクリート充填鋼管柱と、コンクリート充填鋼管柱の上下に配置された鉄骨造の梁との接合構造が知られている。 A joint structure between a concrete-filled steel pipe column, in which the inside of the steel pipe is filled with connecting rebars (main bars) and concrete, and a steel-framed beam arranged above and below the concrete-filled steel pipe column has been known.

下記の特許文献1では、コンクリート充填鋼管柱の内部に、補強鉄筋体が配置されたものが提案されている。補強鉄筋体は、鉛直方向に延び周方向に沿って間隔を有して配置された複数の鉛直補強筋と、複数の鉛直補強筋を束ねるように鉛直方向に間隔を有して複数配置された平面視円形をなすせん断補強筋(円形補強鉄筋)と、を有している。火災時に鋼管が高温になり、鋼管による拘束効果が激減した場合も、補強鉄筋体によって、柱のせん断伝達性能及びび軸力伝達性能を確保することができる。 The following Patent Document 1 proposes a concrete-filled steel pipe column with a reinforcing steel body arranged inside. The reinforcing steel body has multiple vertical reinforcing bars that extend vertically and are arranged at intervals along the circumferential direction, and multiple shear reinforcing bars (circular reinforcing bars) that are circular in plan view and arranged at intervals in the vertical direction to bundle the multiple vertical reinforcing bars. Even if the steel pipe becomes hot during a fire and the restraining effect of the steel pipe is greatly reduced, the reinforcing steel body can ensure the shear transmission performance and axial force transmission performance of the column.

特開2018-131770号公報JP 2018-131770 A

しかしながら、柱梁接合部(仕口部)の上側から下側の柱の鋼管内及びふさぎ板内にコンクリートを打設する際に、仕口部に鉄骨梁及び接合鉄筋が存在するため、コンクリート打設作業の効率が著しく低下し、時間がかかるという問題点がある。また,下側の柱の鋼管内及びふさぎ板内を同時に打設するため、特にふさぎ板内のコンクリート充填作業の作業難易度が高くなることが多い。仕口部の上側からコンクリートを打設する際には、接合鉄筋は結束線等による簡易な固定のみであるため、打設作業時に接合鉄筋が所定の位置からずれてしまった場合は、接合鉄筋を所定の位置に戻す後作業が発生し、作業手間がかかっている。 However, when pouring concrete from the top of a beam-column joint (joint) into the steel pipe of the lower column and into the plug plate, the presence of the steel beam and the connecting rebar at the joint poses the problem of significantly reducing the efficiency of the concrete pouring work and taking time. In addition, because concrete is poured into the steel pipe of the lower column and into the plug plate at the same time, the work of filling the plug plate in particular is often difficult. When pouring concrete from the top of the joint, the connecting rebar is only simply fixed with binding wires, etc., so if the connecting rebar shifts from its designated position during pouring, post-concrete work is required to return it to its designated position, which is time-consuming.

また、柱高さが大きい場合は、コンクリートホースなどを使用する必要があるが、通常サイズの打設作業用ホースは仕口部の直交する梁のフランジどうしの隙間等を通らないことが多く、打設作業用ホースの直径を小さくする必要が生じる。そのため、コンクリートの打設作業の効率が著しく低下するか、あるいはコンクリートの打設自体が困難になるという問題点がある。 In addition, when the pillars are tall, it is necessary to use concrete hoses, but a normal-sized concrete pouring hose often cannot fit through the gaps between the flanges of the beams that cross at right angles at the joint, making it necessary to reduce the diameter of the concrete pouring hose. This can result in a significant decrease in the efficiency of concrete pouring, or even make pouring concrete itself difficult.

また、下側の柱の鋼管内にコンクリートを打設する際には、仕口部の上面から打設作業を行う必要があるため、上側の柱鋼管建方作業は下側のコンクリート打設作業後に行うこととなり、工程選択の自由度が低くなるという問題点がある。 In addition, when pouring concrete into the steel pipe of the lower column, pouring work must be done from the top of the joint, so the upper column steel pipe erection work must be done after the lower concrete pouring work, which creates the problem of reduced freedom in process selection.

そこで、本発明は、上記事情に鑑みてなされたものであり、コンクリートの打設作業を容易に行うことができる柱梁接合構造の施工方法を提供する。 Therefore, the present invention has been made in consideration of the above circumstances, and provides a construction method for a column-beam joint structure that allows concrete pouring work to be easily performed.

上記目的を達成するために、本発明は以下の手段を採用している。
すなわち、本発明に係る柱梁接合構造の施工方法は、コンクリート充填鋼管造の柱と鉄骨造の梁との柱梁接合構造の施工方法であって、下側鋼管を鉛直方向に延びるように設置する下側鋼管設置工程と、鉛直方向に延びる複数の接合鉄筋と、該複数の接合鉄筋の鉛直方向の中間の外側を囲繞するように配置されたふさぎ鋼管と、該ふさぎ鋼管の内部に充填された接合コンクリート部と、前記ふさぎ鋼管に接合された接合梁と、を有する接合部材を、前記ふさぎ鋼管を前記下側鋼管の上側に同軸に配置する接合部材設置工程と、前記ふさぎ鋼管の上側に同軸に上側鋼管を設置する上側鋼管設置工程と、前記下側鋼管の上部に該下側鋼管の板厚を貫通するように形成された打設孔からコンクリートを打設する下側鋼管コンクリート打設工程と、を備える。
In order to achieve the above object, the present invention employs the following means.
In other words, the construction method of the column-beam joint structure of the present invention is a construction method of a column-beam joint structure between a column of concrete-filled steel pipe construction and a beam of steel frame construction, and includes the following steps: a lower steel pipe installation step of installing a lower steel pipe so as to extend in the vertical direction; a connecting member installation step of arranging a connecting member having a plurality of connecting rebars extending in the vertical direction, a plugging steel pipe arranged to surround the outside of the vertical middle of the plurality of connecting rebars, a connecting concrete portion filled inside the plugging steel pipe, and a connecting beam connected to the plugging steel pipe, coaxially installing the plugging steel pipe above the lower steel pipe; an upper steel pipe installation step of installing an upper steel pipe coaxially above the plugging steel pipe; and a lower steel pipe concrete pouring step of pouring concrete from a pouring hole formed in the upper part of the lower steel pipe so as to penetrate the plate thickness of the lower steel pipe.

このように構成された柱梁接合構造の施工方法では、接合部材設置工程で、ふさぎ鋼管の内部に接合コンクリート部が充填された接合部材を下側鋼管の上側に設置する。下側鋼管コンクリート打設工程では、下側鋼管の内部にコンクリートを打設し、ふさぎ鋼管の内部には既にコンクリートが充填されているため充填する必要がない。よって、コンクリートの打設作業を容易に行うことができる。 In the construction method for a beam-column joint structure configured in this way, in the joint member installation process, a joint member with a joint concrete portion filled inside the plugging steel pipe is installed above the lower steel pipe. In the lower steel pipe concrete pouring process, concrete is poured inside the lower steel pipe, and there is no need to fill the plugging steel pipe because it is already filled with concrete. This makes it easy to pour the concrete.

また、本発明に係る柱梁接合構造の施工方法は、筒状に形成された打設管の一端部を前記打設孔に接続し、前記打設管の他端部が上方を向くように設置する打設管設置工程を備えていてもよい。 The method for constructing a beam-column joint structure according to the present invention may also include a casting pipe installation step in which one end of a cylindrical casting pipe is connected to the casting hole and the other end of the casting pipe is installed so as to face upward.

このように構成された柱梁接合構造の施工方法では、下側鋼管の上部に形成された打設孔に打設管を接続して、打設管の上方を向く他端部から下側鋼管の内部にコンクリートを打設する。よって、下側鋼管の上方からコンクリートを打設することができるため、コンクリートの打設の作業性が良い。 In the construction method for a beam-column joint structure configured in this way, a pouring pipe is connected to a pouring hole formed in the upper part of the lower steel pipe, and concrete is poured into the lower steel pipe from the other end of the pouring pipe facing upward. This allows concrete to be poured from above the lower steel pipe, making pouring concrete easy.

また、本発明に係る柱梁接合構造の施工方法は、前記下側鋼管の上部に該下側鋼管の板厚を貫通するように形成された作業孔にバイブレータを挿入して、前記下側鋼管に打設されたコンクリートに振動を与えて締固めるコンクリート締固め工程を備えていてもよい。 The construction method for a beam-column joint structure according to the present invention may also include a concrete compaction process in which a vibrator is inserted into a working hole formed in the upper part of the lower steel pipe so as to penetrate the plate thickness of the lower steel pipe, and the concrete poured in the lower steel pipe is vibrated to compact it.

このように構成された柱梁接合構造の施工方法では、下側鋼管に打設されたコンクリートに振動を与えて締固めるバイブレータを、下側鋼管の上部に形成された作業孔から挿入する。よって、コンクリートを打設する打設孔とは別に、バイブレータを挿入する作業孔があるため、コンクリートの締め固めの作業性が良い。 In the construction method for a beam-column joint structure configured in this way, a vibrator that vibrates and compacts the concrete poured into the lower steel pipe is inserted through a work hole formed in the upper part of the lower steel pipe. Therefore, since there is a work hole for inserting the vibrator in addition to the pouring hole for pouring the concrete, the workability of compacting the concrete is good.

また、本発明に係る柱梁接合構造の施工方法は、筒状に形成された作業管の一端部を前記作業孔に接続し、前記作業管の他端部が上方を向くように設置する作業管設置工程を備えていてもよい。 The method for constructing a beam-column joint structure according to the present invention may also include a work pipe installation process in which one end of a cylindrically formed work pipe is connected to the work hole and the other end of the work pipe is installed so as to face upward.

このように構成された柱梁接合構造の施工方法では、下側鋼管の上部に形成された作業孔に作業管を接続して、作業管の上方を向く他端部からバイブレータを挿入することができるため、コンクリートの締め固めの作業性が更に良い。 In this construction method for a beam-column joint structure, a work pipe can be connected to a work hole formed in the upper part of the lower steel pipe, and a vibrator can be inserted from the other end of the work pipe facing upward, making it easier to compact the concrete.

また、本発明に係る柱梁接合構造の施工方法は、前記作業管の他端部から前記下側鋼管に打設されたコンクリートを確認するコンクリート確認工程を備えていてもよい。 The construction method for a beam-column joint structure according to the present invention may also include a concrete checking process for checking the concrete poured into the lower steel pipe from the other end of the work pipe.

このように構成された柱梁接合構造の施工方法では、コンクリートの締め固めで使用する作業管を使用して、下側鋼管に打設されたコンクリートを確認することができるため、コンクリートを確認するための確認孔を別に設ける必要がない。 In this construction method for a beam-column joint structure, the working pipe used for compacting the concrete can be used to check the concrete poured into the lower steel pipe, eliminating the need to drill a separate inspection hole for checking the concrete.

本発明に係る柱梁接合構造の施工方法によれば、コンクリートの打設作業を容易に行うことができる。 According to the construction method for a column-beam joint structure of the present invention, concrete pouring work can be easily carried out.

本発明の一実施形態に係る柱梁接合構造を示す鉛直断面図である。1 is a vertical cross-sectional view showing a column-beam joint structure according to one embodiment of the present invention. 図1のA-A線断面図である。2 is a cross-sectional view taken along line AA in FIG. 1. 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、接合部材組立工程を示す。1 is a diagram showing a construction method for a beam-column joint structure according to one embodiment of the present invention, illustrating the joint member assembly process. 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、接合部材組立工程を示し、図3の後工程を示す。4 is a diagram showing a construction method for a column-beam joint structure according to one embodiment of the present invention, showing a joint member assembly process, which is a process subsequent to that shown in FIG. 3 . 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、下側鋼管設置工程及び接合部材設置工程を示す。1 is a diagram showing a construction method for a column-beam joint structure according to one embodiment of the present invention, illustrating a lower steel pipe installation process and a joint member installation process. FIG. 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、上側鋼管設置工程を示す。1 is a diagram showing a construction method for a column-beam joint structure according to one embodiment of the present invention, illustrating the upper steel pipe installation process. 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、打設管設置工程、作業管設置工程、下側鋼管コンクリート打設工程及びコンクリート締固め工程を示す。This is a diagram showing a construction method for a column-beam joint structure according to one embodiment of the present invention, and shows the pouring pipe installation process, the working pipe installation process, the lower steel pipe concrete pouring process, and the concrete compaction process. 本発明の一実施形態に係る柱梁接合構造の施工方法を示す図であり、コンクリート確認工程を示す。1 is a diagram showing a construction method for a column-beam joint structure according to one embodiment of the present invention, illustrating a concrete inspection process.

本発明の一実施形態に係る柱梁接合構造の施工方法について、図面を用いて説明する。
まず、柱梁接合構造の構成について説明する。
図1は、本発明の一実施形態に係る柱梁接合構造を示す鉛直断面図である。図1に示すように、本実施形態の柱梁接合構造100では、コンクリート充填鋼管造(CFT造)の柱1と鉄骨造(S造)の梁2との接合構造である。本実施形態の柱梁接合構造100は、柱部材1Aと、梁部材2Aと、柱梁接合部材(接合部材)3と、を有している。
A construction method for a beam-column joint structure according to one embodiment of the present invention will be described with reference to the drawings.
First, the configuration of the column-beam joint structure will be described.
Fig. 1 is a vertical cross-sectional view showing a column-beam joint structure according to an embodiment of the present invention. As shown in Fig. 1, the column-beam joint structure 100 of this embodiment is a joint structure between a column 1 of a concrete-filled steel pipe construction (CFT construction) and a beam 2 of a steel frame construction (S construction). The column-beam joint structure 100 of this embodiment has a column member 1A, a beam member 2A, and a column-beam joint member (joint member) 3.

柱部材1Aは、柱梁接合部材3の上側及び下側に配置されている。柱部材1Aは、鋼管11と、柱コンクリート部12と、を有している。鋼管11は、円筒状に形成されている。鋼管11の軸線は、鉛直方向を向いている。柱コンクリート部12は、鋼管11の内部に充填されている。下側の柱部材1Aの鋼管11を下側鋼管11aと称する。上側の柱部材1Aの鋼管11を上側鋼管11bと称する。 The column members 1A are arranged above and below the column-beam joint member 3. The column members 1A have a steel pipe 11 and a column concrete section 12. The steel pipe 11 is formed in a cylindrical shape. The axis of the steel pipe 11 faces vertically. The column concrete section 12 is filled inside the steel pipe 11. The steel pipe 11 of the lower column member 1A is referred to as the lower steel pipe 11a. The steel pipe 11 of the upper column member 1A is referred to as the upper steel pipe 11b.

下側鋼管11aの上部には、下側鋼管11aの板厚を貫通するように打設孔51が形成されている。打設孔51には、筒状に形成された打設管52の一端部52aが接続されている。打設孔51と打設管52とは、連通している。打設管52は、下側鋼管11aの外側且つ上方に延びている。打設管52の他端部52bは、上方を向くように配置されている。打設管52の内部にも、柱コンクリート部12が充填されている。柱コンクリート部12は、打設管52の他端部52bよりもわずかに低い位置まで充填されている。 A casting hole 51 is formed in the upper part of the lower steel pipe 11a so as to penetrate the plate thickness of the lower steel pipe 11a. One end 52a of a cylindrical casting pipe 52 is connected to the casting hole 51. The casting hole 51 and the casting pipe 52 are connected. The casting pipe 52 extends outside and upward of the lower steel pipe 11a. The other end 52b of the casting pipe 52 is arranged to face upward. The inside of the casting pipe 52 is also filled with the column concrete section 12. The column concrete section 12 is filled to a position slightly lower than the other end 52b of the casting pipe 52.

下側鋼管11aの上部には、下側鋼管11aの板厚を貫通するように作業孔56が形成されている。作業孔56には、筒状に形成された作業管57の一端部57aが接続されている。作業孔56と作業管57とは、連通している。作業管57は、下側鋼管11aの外側且つ上方に延びている。作業管57の他端部57bは、上方を向くように配置されている。作業管57の内部にも、柱コンクリート部12が充填されている。柱コンクリート部12は、作業管57の他端部57bよりもわずかに低い位置まで充填されている。 A work hole 56 is formed in the upper part of the lower steel pipe 11a so as to penetrate the plate thickness of the lower steel pipe 11a. One end 57a of a cylindrically formed work pipe 57 is connected to the work hole 56. The work hole 56 and the work pipe 57 are connected to each other. The work pipe 57 extends outside and upward from the lower steel pipe 11a. The other end 57b of the work pipe 57 is arranged to face upward. The inside of the work pipe 57 is also filled with the column concrete section 12. The column concrete section 12 is filled to a position slightly lower than the other end 57b of the work pipe 57.

梁部材2Aは、柱梁接合部材3の後述する接合梁34の長さ方向の端部に接続されている。梁部材2Aは、平面視十字状に配置されている。梁部材2Aは、H形鋼で構成されている。梁部材2Aは、一対のフランジ21と、ウェブ22と、を有している。一対のフランジ21は、鉛直方向に離間して配置されている。ウェブ22は、一対のフランジ21どうしを連結している。 The beam member 2A is connected to the longitudinal end of the joining beam 34 (described later) of the beam-column joining member 3. The beam member 2A is arranged in a cross shape in a plan view. The beam member 2A is made of H-shaped steel. The beam member 2A has a pair of flanges 21 and a web 22. The pair of flanges 21 are arranged spaced apart in the vertical direction. The web 22 connects the pair of flanges 21 to each other.

柱梁接合部材3は、ふさぎ鋼管31と、接合鉄筋32と、接合コンクリート部33と、接合梁34と、を備えている。 The column-beam joint member 3 comprises a sealing steel pipe 31, a joint reinforcing bar 32, a joint concrete section 33, and a joint beam 34.

ふさぎ鋼管31は、後述する直交配置された接合梁34の接合ウェブ34bどうしの間に配置される4枚の鋼管板材31aを有している。ふさぎ鋼管31は、4枚の鋼管板材31aによって、略円筒状に形成されている。ふさぎ鋼管31の軸線は、鉛直方向を向いている。ふさぎ鋼管31は、上下の柱部材1Aの鋼管11の間に配置されている。ふさぎ鋼管31の径は、鋼管11の径と略同一である。ふさぎ鋼管31は、鋼管11と同軸上に配置されている。 The plugging steel pipe 31 has four steel pipe plate materials 31a arranged between the joint webs 34b of the orthogonally arranged joint beams 34 described below. The plugging steel pipe 31 is formed into a substantially cylindrical shape by the four steel pipe plate materials 31a. The axis of the plugging steel pipe 31 is oriented vertically. The plugging steel pipe 31 is arranged between the steel pipes 11 of the upper and lower column members 1A. The diameter of the plugging steel pipe 31 is substantially the same as the diameter of the steel pipe 11. The plugging steel pipe 31 is arranged coaxially with the steel pipe 11.

接合鉄筋32は、鉛直方向に延びている。図2は、図1のA-A線断面図である。図2に示すように、ふさぎ鋼管31の内側に、複数の接合鉄筋32が配置されている。複数の接合鉄筋32は、周方向に間隔を有して配置されている。接合鉄筋32は、後述する接合梁34と干渉しない位置に配置されている。 The connecting rebars 32 extend vertically. Figure 2 is a cross-sectional view of line A-A in Figure 1. As shown in Figure 2, multiple connecting rebars 32 are arranged inside the sealing steel pipe 31. The multiple connecting rebars 32 are arranged with intervals in the circumferential direction. The connecting rebars 32 are arranged in positions that do not interfere with the connecting beams 34 described below.

図1に示すように、接合鉄筋32のうちふさぎ鋼管31よりも上方に突出する部分を、上側突出鉄筋32aと称する。上側突出鉄筋32aは、上側鋼管11bの内部に配置されている。上側突出鉄筋32aは、上側鋼管11bの内部に充填された柱コンクリート部12に定着している。 As shown in FIG. 1, the portion of the connecting rebar 32 that protrudes above the filling steel pipe 31 is called the upper protruding rebar 32a. The upper protruding rebar 32a is disposed inside the upper steel pipe 11b. The upper protruding rebar 32a is fixed to the column concrete portion 12 filled inside the upper steel pipe 11b.

接合鉄筋32のうちふさぎ鋼管31の内部に配置される部分を、中間鉄筋32bと称する。ふさぎ鋼管31は、接合鉄筋32の鉛直方向の中間である中間鉄筋32bの外側を囲繞するように配置されている。中間鉄筋32bは、後述する接合コンクリート部33に定着している。 The portion of the connecting rebar 32 that is placed inside the plugging steel pipe 31 is called the intermediate rebar 32b. The plugging steel pipe 31 is placed so as to surround the outside of the intermediate rebar 32b, which is the vertical center of the connecting rebar 32. The intermediate rebar 32b is fixed to the connecting concrete portion 33, which will be described later.

接合鉄筋32のうちふさぎ鋼管31よりも下方に突出する部分を、下側突出鉄筋32cと称する。下側突出鉄筋32cは、下側鋼管11aの内部に配置されている。下側突出鉄筋32cは、下側鋼管11aの内部に充填された柱コンクリート部12に定着している。 The portion of the connecting rebar 32 that protrudes downward from the filling steel pipe 31 is called the lower protruding rebar 32c. The lower protruding rebar 32c is disposed inside the lower steel pipe 11a. The lower protruding rebar 32c is fixed to the column concrete portion 12 filled inside the lower steel pipe 11a.

接合コンクリート部33は、ふさぎ鋼管31の内部に充填されている。4本の接合梁34が、平面視十字状に直交配置されている。接合梁34は、H形鋼で構成されている。接合梁34は、一対の接合フランジ34aと、接合ウェブ34bと、を有している。一対の接合フランジ34aは、鉛直方向に離間して配置されている。接合ウェブ34bは、一対の接合フランジ34aどうしを連結している。接合ウェブ34bは、ふさぎ鋼管31に接合されている。 The joint concrete section 33 is filled inside the sealing steel pipe 31. Four joint beams 34 are arranged perpendicular to each other in a cross shape when viewed from above. The joint beams 34 are made of H-shaped steel. The joint beams 34 have a pair of joint flanges 34a and a joint web 34b. The pair of joint flanges 34a are arranged spaced apart in the vertical direction. The joint web 34b connects the pair of joint flanges 34a to each other. The joint web 34b is joined to the sealing steel pipe 31.

接合フランジ34aの長さ方向の端部には、梁2のフランジ21が接合されている。接合ウェブ34bの長さ方向の端部には、梁2のウェブ22が接合されている。 The flange 21 of the beam 2 is joined to the end of the joint flange 34a in the longitudinal direction. The web 22 of the beam 2 is joined to the end of the joint web 34b in the longitudinal direction.

上側の柱1は、上側鋼管11bと、上側突出鉄筋32aと、柱コンクリート部12と、を備えている。下側の柱1は、下側鋼管11aと、下側突出鉄筋32cと、柱コンクリート部12と、を備えている。梁2は、梁部材2Aと、接合梁34と、を備えている。上下の柱1と梁2とは、ふさぎ鋼管31、中間鉄筋32b及び接合コンクリート部33によって接合されている。 The upper column 1 has an upper steel pipe 11b, an upper protruding rebar 32a, and a column concrete section 12. The lower column 1 has a lower steel pipe 11a, a lower protruding rebar 32c, and a column concrete section 12. The beam 2 has a beam member 2A and a joint beam 34. The upper and lower columns 1 and beams 2 are joined by a filling steel pipe 31, an intermediate rebar 32b, and a joint concrete section 33.

次に、柱梁接合構造の施工方法について説明する。
接合部材組立工程を行う。
図3に示すように、作業面g上に仮設下側鉄骨41を立設させる。仮設下側鉄骨41は、後工程で配置する柱梁接合部材3の接合梁34が配置される4箇所の下方に配置しておくことが好ましい。4本の接合梁34を直交配置する。直交配置された接合梁34の間を鋼管板材31aで接合して、ふさぎ鋼管31を形成する。
Next, a construction method for the column-beam joint structure will be described.
The joining member assembly process is carried out.
As shown in Fig. 3, a temporary lower steel frame 41 is erected on a work surface g. The temporary lower steel frame 41 is preferably arranged below four locations where the connection beams 34 of the column-beam connection members 3 to be arranged in a later process will be arranged. The four connection beams 34 are arranged orthogonally. The orthogonally arranged connection beams 34 are joined with steel pipe plate materials 31a to form the sealing steel pipes 31.

図4に示すように、接合梁34上に仮設上側鉄骨42を設置する。例えば、仮設上側鉄骨42を、仮設下側鉄骨41の鉛直上方に配置する。作業面g上であって複数の仮設下側鉄骨41で囲まれた内部に、下側鉄筋支持台43を設置する。複数の仮設上側鉄骨42上に架設するように、上側鉄筋支持台44を設置する。ふさぎ鋼管31の内部に接合鉄筋32を複数配置する。例えば、接合鉄筋32の上端部及び下端部を上側鉄筋支持台44及び下側鉄筋支持台43に上下方向に貫通するように形成された支持孔に挿入して、接合鉄筋32の位置決めをする。ふさぎ鋼管31の下部に型枠(不図示)を設置して、ふさぎ鋼管31の内部にコンクリートを打設して、接合コンクリート部33を形成する。これによって、柱梁接合部材3が完成する。なお、予め製造工場等で接合部材組立工程を行って柱梁接合部材3を製造して建設現場に搬入してもよいし、建設現場で接合部材組立工程を行って柱梁接合部材3を製造してもよい。 As shown in FIG. 4, a temporary upper steel frame 42 is installed on the connecting beam 34. For example, the temporary upper steel frame 42 is placed vertically above the temporary lower steel frame 41. A lower rebar support base 43 is installed on the work surface g inside the interior surrounded by the multiple temporary lower steel frames 41. An upper rebar support base 44 is installed so as to be erected on the multiple temporary upper steel frames 42. A plurality of connecting rebars 32 are placed inside the sealing steel pipe 31. For example, the upper and lower ends of the connecting rebars 32 are inserted into support holes formed so as to penetrate the upper rebar support base 44 and the lower rebar support base 43 in the vertical direction to position the connecting rebars 32. A formwork (not shown) is installed at the bottom of the sealing steel pipe 31, and concrete is poured inside the sealing steel pipe 31 to form the connecting concrete portion 33. This completes the column-beam connecting member 3. The joint member assembly process may be carried out in advance at a manufacturing factory or the like to manufacture the column-beam joint member 3 and then transported to the construction site, or the joint member assembly process may be carried out at the construction site to manufacture the column-beam joint member 3.

下側鋼管設置工程を行う。
図5に示すように、設置面h上に、下側鋼管11aが鉛直方向に延びるように、つまり下側鋼管11aの軸線が鉛直方向を向くように下側鋼管11aを設置する。
The lower steel pipe installation process is carried out.
As shown in FIG. 5, the lower steel pipe 11a is placed on the placement surface h so that the lower steel pipe 11a extends in the vertical direction, that is, so that the axis of the lower steel pipe 11a faces the vertical direction.

接合部材設置工程を行う。
柱梁接合部材3のふさぎ鋼管31が下側鋼管11aの上側で下側鋼管11aと同軸になるように、柱梁接合部材3を設置する。下側突出鉄筋32cは、下側鋼管11aの内部に配置される。
A joining member installation process is carried out.
The column-beam connection member 3 is installed so that the plugging steel pipe 31 of the column-beam connection member 3 is coaxial with the lower steel pipe 11a above the lower steel pipe 11a. The lower protruding rebar 32c is disposed inside the lower steel pipe 11a.

上側鋼管設置工程を行う。
図6に示すように、上側鋼管11bを、ふさぎ鋼管31の上側でふさぎ鋼管31と同軸になるように設置する。上側突出鉄筋32aは、上側鋼管11bの内部に配置される。なお、上側鋼管設置工程は、後述する打設管設置工程、作業管設置工程、下側鋼管コンクリート打設工程、コンクリート締固め工程及びコンクリート確認工程の一部と並行して行ってもよい。
The upper steel pipe installation process is carried out.
As shown in Fig. 6, the upper steel pipe 11b is installed above the blocking steel pipe 31 so as to be coaxial with the blocking steel pipe 31. The upper protruding rebar 32a is disposed inside the upper steel pipe 11b. The upper steel pipe installation process may be performed in parallel with a part of the pouring pipe installation process, the working pipe installation process, the lower steel pipe concrete pouring process, the concrete compaction process, and the concrete inspection process, which will be described later.

打設管設置工程を行う。
図7に示すように、下側鋼管11aの上部に下側鋼管11aの板厚を貫通するように打設孔51を形成する。打設孔51に筒状に形成された打設管52の一端部52aを接続し、打設孔51と打設管52とを連通させる。打設管52の他端部52bは、上方を向くように配置する。なお、打設孔51は、下側鋼管11aの上端部に設けてもよいし、下側鋼管11aの上端部よりも下方の位置に設けてもよい。
The pouring pipe installation process is carried out.
As shown in Fig. 7, a casting hole 51 is formed in the upper part of the lower steel pipe 11a so as to penetrate the plate thickness of the lower steel pipe 11a. One end 52a of a casting pipe 52 formed in a cylindrical shape is connected to the casting hole 51, and the casting hole 51 and the casting pipe 52 are connected. The other end 52b of the casting pipe 52 is arranged so as to face upward. The casting hole 51 may be provided at the upper end of the lower steel pipe 11a, or may be provided at a position lower than the upper end of the lower steel pipe 11a.

作業管設置工程を行う。
下側鋼管11aの上部に下側鋼管11aの板厚を貫通するように作業孔56を形成する。作業孔56に筒状に形成された作業管57の一端部57aを接続し、作業孔56と作業管57とを連通させる。作業管57の他端部57bは、上方を向くように配置する。なお、作業孔56は、下側鋼管11aの上端部に設けてもよいし、下側鋼管11aの上端部よりも下方の位置に設けてもよい。作業孔56は、打設孔51よりも高い位置に形成されていることが好ましい。
The working pipe installation process is carried out.
A work hole 56 is formed in the upper part of the lower steel pipe 11a so as to penetrate the plate thickness of the lower steel pipe 11a. One end 57a of a cylindrically formed work pipe 57 is connected to the work hole 56 to communicate the work hole 56 and the work pipe 57. The other end 57b of the work pipe 57 is arranged to face upward. The work hole 56 may be provided at the upper end of the lower steel pipe 11a, or may be provided at a position lower than the upper end of the lower steel pipe 11a. The work hole 56 is preferably formed at a position higher than the casting hole 51.

下側鋼管コンクリート打設工程を行う。
打設用ホース53を打設管52の他端部52bから挿入して打設孔51を通して、下側鋼管11aの内部に配置する。打設用ホース53にコンクリート54を流し込み、下側鋼管11aの内部にコンクリート54を打設する。このコンクリート54は、下側鋼管11aの内部に柱コンクリート部12となる。
The process of pouring concrete into the lower steel pipe is carried out.
The casting hose 53 is inserted from the other end 52b of the casting pipe 52 through the casting hole 51 and placed inside the lower steel pipe 11a. Concrete 54 is poured into the casting hose 53, and the concrete 54 is cast inside the lower steel pipe 11a. This concrete 54 becomes the column concrete portion 12 inside the lower steel pipe 11a.

コンクリート締固め工程を行う。
バイブレータ58を作業管57の他端部57bから挿入して作業孔56を通して、下側鋼管11aの内部に配置する。下側鋼管11aに打設されたコンクリート54(柱コンクリート部12)に振動を与えて締固める。
The concrete compaction process is carried out.
The vibrator 58 is inserted from the other end 57b of the work pipe 57 through the work hole 56 and placed inside the lower steel pipe 11a. The concrete 54 (column concrete portion 12) poured in the lower steel pipe 11a is vibrated and compacted.

コンクリート確認工程を行う。
図8に示すように、下側鋼管11aの内部に打設されたコンクリート54(柱コンクリート部12)が状態や量等を、作業管57の他端部57bから確認する。コンクリート54(柱コンクリート部12)が下側鋼管11aの上端部まで打設されていることが好ましい。
Carry out concrete inspection process.
As shown in Fig. 8, the condition, amount, etc. of the concrete 54 (column concrete portion 12) poured inside the lower steel pipe 11a is checked from the other end 57b of the work pipe 57. It is preferable that the concrete 54 (column concrete portion 12) is poured up to the upper end of the lower steel pipe 11a.

このように構成された柱梁接合構造の施工方法では、接合部材設置工程で、ふさぎ鋼管31の内部に接合コンクリート部33が充填された柱梁接合部材3を下側鋼管11aの上側に設置する。下側鋼管コンクリート打設工程では、下側鋼管11aの内部にコンクリート54(柱コンクリート部12)を打設し、ふさぎ鋼管31の内部には既にコンクリート(接合コンクリート部33)が充填されているため充填する必要がない。よって、コンクリートの打設作業を容易に行うことができる。 In the construction method for a column-beam joint structure configured in this manner, in the joint member installation process, the column-beam joint member 3, in which the joint concrete portion 33 is filled inside the plugging steel pipe 31, is installed above the lower steel pipe 11a. In the lower steel pipe concrete pouring process, concrete 54 (column concrete portion 12) is poured inside the lower steel pipe 11a, and there is no need to fill the plugging steel pipe 31 because it is already filled with concrete (joint concrete portion 33). This makes it easy to pour the concrete.

また、下側鋼管11aの上部に形成された打設孔51に打設管52を接続して、打設管52の上方を向く他端部52bから下側鋼管11aの内部にコンクリート54(柱コンクリート部12)を打設する。よって、下側鋼管11aの上方からコンクリートを打設することができるため、コンクリートの打設の作業性が良い。 In addition, a casting pipe 52 is connected to a casting hole 51 formed in the upper part of the lower steel pipe 11a, and concrete 54 (column concrete part 12) is cast into the inside of the lower steel pipe 11a from the other end 52b facing upward of the casting pipe 52. Therefore, concrete can be cast from above the lower steel pipe 11a, making concrete casting easy to do.

また、下側鋼管11aに打設されたコンクリート54(柱コンクリート部12)に振動を与えて締固めるバイブレータ58を、下側鋼管11aの上部に形成された作業孔56から挿入する。よって、コンクリート54(柱コンクリート部12)を打設する打設孔51とは別に、バイブレータ58を挿入する作業孔56があるため、コンクリートの締め固めの作業性が良い。 In addition, a vibrator 58 that vibrates and compacts the concrete 54 (pillar concrete section 12) poured into the lower steel pipe 11a is inserted through a work hole 56 formed in the upper part of the lower steel pipe 11a. Therefore, since there is a work hole 56 for inserting the vibrator 58 in addition to the pouring hole 51 for pouring the concrete 54 (pillar concrete section 12), the workability of compacting the concrete is good.

また、下側鋼管11aの上部に形成された作業孔56に作業管57を接続して、作業管57の上方を向く他端部57bからバイブレータ58を挿入することができるため、コンクリートの締め固めの作業性が更に良い。 In addition, a work pipe 57 can be connected to a work hole 56 formed in the upper part of the lower steel pipe 11a, and a vibrator 58 can be inserted from the other end 57b of the work pipe 57 facing upward, making the work of compacting the concrete even easier.

また、コンクリートの締め固めで使用する作業管57を使用して、下側鋼管11aに打設されたコンクリート54(柱コンクリート部12)を確認することができるため、コンクリート54(柱コンクリート部12)を確認するための確認孔を別に設ける必要がない。 In addition, the working tube 57 used for compacting the concrete can be used to check the concrete 54 (pillar concrete section 12) poured into the lower steel pipe 11a, so there is no need to provide a separate inspection hole for checking the concrete 54 (pillar concrete section 12).

また、接合部材組立工程では、接合鉄筋32の上端部を上側鉄筋支持台44で支持し、接合鉄筋32の下端部を下側鉄筋支持台43で支持する。よって、接合鉄筋32の配置位置の精度を高めることができる。これによって、下側鋼管コンクリート打設工程時に、接合鉄筋32を所定の位置に戻す必要なく作業手間を減らすことができる。 In addition, in the joint member assembly process, the upper end of the joint rebar 32 is supported by the upper rebar support base 44, and the lower end of the joint rebar 32 is supported by the lower rebar support base 43. This improves the accuracy of the positioning of the joint rebar 32. This reduces the amount of work required during the lower steel pipe concrete pouring process, as there is no need to return the joint rebar 32 to its designated position.

また、下側鋼管コンクリート打設工程前に上側鋼管設置工程を行うことができるため、工程選択の自由度を高めることができる。 In addition, the upper steel pipe installation process can be carried out before the lower steel pipe concrete pouring process, allowing for greater freedom in process selection.

なお、上述した実施の形態において示した組立手順、あるいは各構成部材の諸形状や組み合わせ等は一例であって、本発明の主旨から逸脱しない範囲において設計要求等に基づき種々変更可能である。 The assembly procedures and the shapes and combinations of the components shown in the above-mentioned embodiments are merely examples, and may be modified in various ways based on design requirements, etc., without departing from the spirit of the present invention.

例えば、上記に示す実施形態では、下側鋼管11aの打設孔51に打設管52が接続され、打設管52からコンクリートを充填しているが、本発明はこれに限られない。打設管52が無くて打設孔51からコンクリートを充填してもよい。 For example, in the embodiment shown above, a pouring pipe 52 is connected to the pouring hole 51 of the lower steel pipe 11a, and concrete is poured from the pouring pipe 52, but the present invention is not limited to this. Concrete may be poured from the pouring hole 51 without the pouring pipe 52.

また、上記に示す実施形態では、下側鋼管11aの作業孔56に作業管57が接続され、作業管57からバイブレータ58を挿入しているが、本発明はこれに限られない。作業管57が無くて作業孔56からバイブレータ58を挿入してもよいし、打設孔51や打設管52等からバイブレータ58を挿入してもよい。 In the embodiment shown above, the work pipe 57 is connected to the work hole 56 of the lower steel pipe 11a, and the vibrator 58 is inserted from the work pipe 57, but the present invention is not limited to this. The vibrator 58 may be inserted from the work hole 56 without the work pipe 57, or the vibrator 58 may be inserted from the casting hole 51, casting pipe 52, etc.

1…柱
1A…柱部材
2…梁
2A…梁部材
11…鋼管
11a…下側鋼管
11b…上側鋼管
12…柱コンクリート部
31…ふさぎ鋼管
32…接合鉄筋
33…接合コンクリート部
34…接合梁
51…打設孔
52…打設管
52a…一端部
52b…他端部
56…作業孔
57…作業管
57a…一端部
57b…他端部
58…バイブレータ
100…柱梁接合構造
DESCRIPTION OF SYMBOLS 1...Column 1A...Column member 2...Beam 2A...Beam member 11...Steel pipe 11a...Lower steel pipe 11b...Upper steel pipe 12...Column concrete section 31...Covering steel pipe 32...Connecting reinforcing bar 33...Connecting concrete section 34...Connecting beam 51...Pouring hole 52...Pouring pipe 52a...One end 52b...Other end 56...Work hole 57...Work pipe 57a...One end 57b...Other end 58...Vibrator 100...Column-beam joint structure

Claims (5)

コンクリート充填鋼管造の柱と鉄骨造の梁との柱梁接合構造の施工方法であって、
下側鋼管を鉛直方向に延びるように設置する下側鋼管設置工程と、
鉛直方向に延びる複数の接合鉄筋と、該複数の接合鉄筋の鉛直方向の中間の外側を囲繞するように配置されたふさぎ鋼管と、該ふさぎ鋼管の内部に充填された接合コンクリート部と、前記ふさぎ鋼管に接合された接合梁と、を有する接合部材を、前記ふさぎ鋼管を前記下側鋼管の上側に同軸に配置する接合部材設置工程と、
前記ふさぎ鋼管の上側に同軸に上側鋼管を設置する上側鋼管設置工程と、
前記下側鋼管の上部に該下側鋼管の板厚を貫通するように形成された打設孔からコンクリートを打設する下側鋼管コンクリート打設工程と、を備える柱梁接合構造の施工方法。
A method for constructing a column-beam joint structure between a concrete-filled steel pipe column and a steel beam, comprising:
a lower steel pipe installation process for installing the lower steel pipe so as to extend in a vertical direction;
a connecting member installation process in which a connecting member having a plurality of connecting rebars extending in the vertical direction, a plugging steel pipe arranged to surround the outside of the vertical middle of the plurality of connecting rebars, a connecting concrete portion filled inside the plugging steel pipe, and a connecting beam connected to the plugging steel pipe is coaxially arranged above the lower steel pipe;
an upper steel pipe installation process in which an upper steel pipe is coaxially installed on the upper side of the plugging steel pipe;
A lower steel pipe concrete pouring process for pouring concrete through a pouring hole formed in the upper part of the lower steel pipe so as to penetrate the plate thickness of the lower steel pipe.
筒状に形成された打設管の一端部を前記打設孔に接続し、前記打設管の他端部が上方を向くように設置する打設管設置工程を備える請求項1に記載の柱梁接合構造の施工方法。 The method for constructing a beam-column joint structure according to claim 1, further comprising a step of installing a casting pipe in which one end of a cylindrical casting pipe is connected to the casting hole and the other end of the casting pipe is installed so as to face upward. 前記下側鋼管の上部に該下側鋼管の板厚を貫通するように形成された作業孔にバイブレータを挿入して、前記下側鋼管に打設されたコンクリートに振動を与えて締固めるコンクリート締固め工程を備える請求項1または2に記載の柱梁接合構造の施工方法。 The method for constructing a beam-column joint structure according to claim 1 or 2 includes a concrete compaction process in which a vibrator is inserted into a working hole formed in the upper part of the lower steel pipe so as to penetrate the plate thickness of the lower steel pipe, and the concrete poured in the lower steel pipe is vibrated and compacted. 筒状に形成された作業管の一端部を前記作業孔に接続し、前記作業管の他端部が上方を向くように設置する作業管設置工程を備える請求項3に記載の柱梁接合構造の施工方法。 The method for constructing a beam-column joint structure according to claim 3, further comprising a work tube installation step of connecting one end of a cylindrically formed work tube to the work hole and installing the other end of the work tube so that it faces upward. 前記作業管の他端部から前記下側鋼管に打設されたコンクリートを確認するコンクリート確認工程を備える請求項4に記載の柱梁接合構造の施工方法。 The method for constructing a beam-column joint structure according to claim 4, further comprising a concrete checking process for checking the concrete poured into the lower steel pipe from the other end of the work pipe.
JP2021015680A 2021-02-03 2021-02-03 Construction method for column-beam joint structure Active JP7628830B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021015680A JP7628830B2 (en) 2021-02-03 2021-02-03 Construction method for column-beam joint structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021015680A JP7628830B2 (en) 2021-02-03 2021-02-03 Construction method for column-beam joint structure

Publications (2)

Publication Number Publication Date
JP2022118883A JP2022118883A (en) 2022-08-16
JP7628830B2 true JP7628830B2 (en) 2025-02-12

Family

ID=82845140

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021015680A Active JP7628830B2 (en) 2021-02-03 2021-02-03 Construction method for column-beam joint structure

Country Status (1)

Country Link
JP (1) JP7628830B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004108091A (en) 2002-09-20 2004-04-08 Shimizu Corp Composite structure building and construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004108091A (en) 2002-09-20 2004-04-08 Shimizu Corp Composite structure building and construction method

Also Published As

Publication number Publication date
JP2022118883A (en) 2022-08-16

Similar Documents

Publication Publication Date Title
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
JP6792329B2 (en) Construction method of column beam frame using precast concrete columns
JP6855296B2 (en) Building foundation structure and its construction method
JP6628588B2 (en) Construction method of structures, structures
JP2010261270A (en) Construction method of composite structure and composite structure building
JP7628830B2 (en) Construction method for column-beam joint structure
JP6574336B2 (en) Steel-framed reinforced concrete columns and buildings using the same
JP7200048B2 (en) pile foundation structure
KR101636471B1 (en) Reinforced concrete column structure
JP2021113438A (en) Joint hardware, and method for connecting joint precast member and column member
KR101485563B1 (en) The horizontal structural frame
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JPH07292773A (en) Construction method of frame with steel tube concrete columns
JP3222856B2 (en) Construction method of column / beam joint
JP7532735B2 (en) Connection structure
JP7230317B2 (en) Column construction method
KR101657628B1 (en) Top-down method for building undergroud structure using steel pipe
JP2020204207A (en) Precast column-beam structure and its manufacturing method
JP7610953B2 (en) Beam and slab joint structure
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
KR20010095899A (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP5327615B2 (en) Joint structure of column and flat slab
JP7158997B2 (en) Joining structure and joining method of precast concrete members
JPH0762740A (en) Joining method of precast steel reinforced concrete column beam
JP2022178700A (en) Seismic isolation device installation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231221

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240808

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240910

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20241025

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20250121

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20250130

R150 Certificate of patent or registration of utility model

Ref document number: 7628830

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150