[go: up one dir, main page]

JP6723032B2 - High altitude construction method using overhead crane - Google Patents

High altitude construction method using overhead crane Download PDF

Info

Publication number
JP6723032B2
JP6723032B2 JP2016045382A JP2016045382A JP6723032B2 JP 6723032 B2 JP6723032 B2 JP 6723032B2 JP 2016045382 A JP2016045382 A JP 2016045382A JP 2016045382 A JP2016045382 A JP 2016045382A JP 6723032 B2 JP6723032 B2 JP 6723032B2
Authority
JP
Japan
Prior art keywords
work stage
duct
construction
work
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016045382A
Other languages
Japanese (ja)
Other versions
JP2017160659A (en
Inventor
恒 佐々木
恒 佐々木
靖志 川又
靖志 川又
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takasago Thermal Engineering Co Ltd
Original Assignee
Takasago Thermal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takasago Thermal Engineering Co Ltd filed Critical Takasago Thermal Engineering Co Ltd
Priority to JP2016045382A priority Critical patent/JP6723032B2/en
Publication of JP2017160659A publication Critical patent/JP2017160659A/en
Application granted granted Critical
Publication of JP6723032B2 publication Critical patent/JP6723032B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Control And Safety Of Cranes (AREA)

Description

本発明は、建屋の高所にダクトや配管などの長尺の部材を施工する方法に関する。 The present invention relates to a method for constructing a long member such as a duct or a pipe in a high place of a building.

例えば改修工事での高所作業は、キャットウォークなど保守のための歩廊やトラスなどを利用できる場合には、それらに足場板を渡すなどして施工することが考えられる。しかし、施工範囲が歩廊やトラスらから離ていたり、点検以外の作業が予定されていない構造である場合もある。また、既設の施設では地上で作業が行われていたり、機器や什器が設置されていたりして、高所作業が運用できないことがある。工事のために当該作業等の休止や既設置物品の一時的移設は施設の運用者としては避けたいところである。 For example, for work in high places during renovation work, if a corridor or truss for maintenance such as a catwalk can be used, it is conceivable to carry out a scaffolding board for them. However, there are cases where the construction area is far from the corridor or truss, or the structure is such that no work other than inspection is scheduled. Further, in existing facilities, work may be performed on the ground, or equipment and fixtures may be installed, so work at heights may not be possible. The operator of the facility would like to avoid the suspension of such work and the temporary relocation of existing items for construction.

ここで、特許文献1には、トラスに足場板を敷き、ダクトなどの取付工事をすることが示されている。また、特許文献2には、アスベスト等の除去作業を行う作業床をクレーン上に設置することが示されている。また、特許文献3には、天井のスレート張りを行うための足場を、トラス上を移動する移動台車に設けることが示されている。さらに、特許文献4には、天井クレーンの走行レールを利用して、天井空間を仕上げる足場を移動させることが示されている。 Here, Patent Document 1 discloses that a scaffolding plate is laid on a truss and installation work such as a duct is performed. Patent Document 2 discloses that a work floor for removing asbestos and the like is installed on a crane. Further, Patent Document 3 discloses that a scaffold for performing slate tensioning of a ceiling is provided on a moving carriage that moves on a truss. Further, Patent Document 4 discloses that a traveling rail of an overhead crane is used to move a scaffold for finishing an overhead space.

特開平11−36578号公報JP-A-11-36578 特開2009−235882号公報JP, 2009-235882, A 実公平3−27052号公報Japanese Utility Model Publication No. 3-27052 特開2003−321932号公報JP, 2003-321932, A

しかしながら、特許文献1の技術は、作業板をトラス上に敷く前に鳶工など作業者の墜落防止用のネットを張り渡し、作業板を敷く前後で工具部材の落下防止用のシートを張る必要がある。発明者の知見では、床面積3300m程度の大空間にこの工法を適用しようとすると、それらの準備作業に2、3か月要し、それからようやく本工事に移ることになる。また天井トラス鋼材の起立部が干渉することで、作業性に難がある。また、トラスより下の高さ位置に取り付け等の施工をする場合には適用が困難である。ダクトや配管は長手方向に連設されるものであり立上り立下りがあり得、またドレン配管のように勾配をとることが必要なものもある。また、特許文献2〜4の技術は、いずれも作業位置が一直線上でしか移動できず、天井全体を二次元的に移動して作業することが困難である。 However, in the technique of Patent Document 1, it is necessary to stretch a net for prevention of a worker's fall, such as a girder, before laying the work plate on the truss, and to put a sheet for preventing the tool member from falling before and after laying the work plate. There is. According to the inventor's knowledge, if this construction method is applied to a large space with a floor area of about 3300 m 2 , it takes a few months for the preparatory work, and finally the main construction is started. Further, since the standing portions of the ceiling truss steel material interfere with each other, workability is difficult. In addition, it is difficult to apply when installing at a height below the truss. Ducts and pipes are connected in the longitudinal direction and may rise and fall, and some pipes, such as drain pipes, require a slope. Further, in any of the techniques of Patent Documents 2 to 4, the work position can be moved only on a straight line, and it is difficult to work by moving the entire ceiling two-dimensionally.

したがって、本発明は、落下防止用のシートなどの準備作業を省略でき、既設の建物など地上に障害物のある施設でも、ダクトや配管といった長尺物を建屋の高所全体に施工できる高所施工方法を提供することを目的とする。 Therefore, according to the present invention, it is possible to omit preparation work such as a sheet for fall prevention, and to install a long object such as a duct or a pipe in the whole height of a building even in a facility with an obstacle on the ground such as an existing building. The purpose is to provide a construction method.

上記課題を解決する本発明によれば、建屋の両側の壁に設けられた一対の軌道と、該一対の軌道に跨るように配置され該軌道上を移動可能に設けられたクレーンガータと、前記クレーンガータに設けられた柵と、前記クレーンガータに設置されたレール上を走行自在に設けられフックが吊り下げられた台車と、を有する天井クレーンを利用して、建屋の高所に長尺の部材を施工する方法であって、前記台車の上方に縦桟と横桟とを有してなる柵を取り付け、該柵に作業者の足場となる足場板を設置して作業ステージを取り付け、前記作業ステージの範囲内において部材の一部分を施工する工程と、前記作業ステージを移動させる工程を順次繰り返すことにより、建屋の高所に長尺の部材を施工することを特徴とする、天井クレーンを用いた高所施工方法が提供される。
According to the present invention for solving the above problems, a pair of tracks provided on both side walls of a building, a crane garter provided so as to be movable over the pair of tracks arranged above the pair of tracks, and a fence provided on the crane garter, using an overhead crane having a trolley the installed Re travel freely provided et the upper rails off click is suspended on the crane garter, the altitude of the building A method of constructing a long member, wherein a fence having vertical rails and horizontal rails is attached above the trolley, and a scaffolding board serving as a footing for workers is installed on the rail to set a work stage. Mounting, a step of constructing a part of the member within the range of the work stage, and a step of moving the work stage are sequentially repeated to construct a long member at a high place of the building, the ceiling. An aerial construction method using a crane is provided.

かかる本発明の高所施工方法にあっては、互いに同一方向に延びる長尺の部材が複数系統あり、各系統ごとに、前記作業ステージを長尺の部材の長手方向に往復移動させ、前記作業ステージの往路移動の際に施工を行い、前記作業ステージの復路移動の際に施工の確認を行うようにしても良い。また、互いに同一方向に延びる長尺の部材が複数系統あり、前記作業ステージを長尺の部材と交差する方向に往復移動させ、前記作業ステージの往路移動の際に施工を行い、前記作業ステージの復路移動の際に施工の確認を行うことを繰り返すことにより、複数系統の長尺の部材を同時進行で施工するようにしても良い。 In the aerial work method of the present invention, there are a plurality of long members extending in the same direction, and the work stage is reciprocally moved in the longitudinal direction of the long member for each system to perform the work. The construction may be performed when the stage moves forward, and the construction may be confirmed when the work stage moves backward. Further, there are a plurality of long members extending in the same direction, reciprocating the working stage in a direction intersecting with the long member, performing work when the working stage moves forward, By repeating the confirmation of the construction at the time of the return movement, it is possible to construct the long members of a plurality of systems simultaneously.

なお、前記作業ステージの移動は、クレーンガータ上の作業者がリモコンスイッチを操作して行うことができる。また、前記作業ステージは、前記台車に設けられた手摺に取り付けられていても良い。また、長尺の部材は、前記クレーンガータに直行する方向に複数系統設けられるものであり、前記作業ステージの範囲内において前記長尺の部材の一部を施工した後に、前記作業ステージを移動させて次の一部を施工するようにされても良い。
The work stage can be moved by an operator on the crane garter operating a remote control switch. Further, the work stage may be attached to a handrail provided on the carriage. Further, the long member is provided in a plurality of systems in a direction orthogonal to the crane garter, and after operating a part of the long member within the range of the work stage, the work stage is moved. Then, the following part may be constructed .

本発明によれば、台車に取り付けられた作業ステージの範囲内において部材の一部分を施工する工程と、作業ステージを移動させる工程を順次繰り返すことにより、建屋の高所全体にダクトや配管などの長尺の部材を施工することができる。また、施工を作業ステージの範囲内において行うため、作業ステージの直上が工事作業空間となるので、落下防止用のシートなどの準備作業を省略でき、既設の建物など地上に障害物のある施設でも、ダクトや配管といった長尺物を建屋の高所全体に施工できるようになる。 According to the present invention, by sequentially repeating the step of constructing a part of the member within the range of the work stage attached to the truck and the step of moving the work stage, it is possible to extend the length of ducts, pipes, etc., over the entire height of the building. Scale members can be constructed. In addition, since the work is performed within the range of the work stage, the work space immediately above the work stage becomes the work space, so preparatory work such as sheets for fall prevention can be omitted, even in facilities with obstacles on the ground such as existing buildings. , It becomes possible to construct long objects such as ducts and pipes all over the high places of the building.

本発明の実施の形態に係る高所施工方法を実施する建屋の正面図である。It is a front view of the building which implements the high-place construction method which concerns on embodiment of this invention. 建屋の高所に施工される長尺の部材の一例である枝ダクトと天井クレーンの位置関係を示す平面図である。It is a top view which shows the positional relationship of the branch duct which is an example of the elongate member constructed in the high place of a building, and an overhead crane. 台車に取り付けられた作業ステージの説明図である。It is explanatory drawing of the work stage attached to the trolley|bogie. 作業ステージの移動手順の一つの態様の説明図である。It is explanatory drawing of one aspect of the moving procedure of a work stage. 作業ステージの移動手順のもう一つの態様の説明図である。It is explanatory drawing of another aspect of the moving procedure of a work stage.

以下、本発明の実施の形態の一例を図面を参照にして説明する。なお、本明細書および図面において、実質的に同一の機能構成を有する要素においては、同一の符号を付することにより重複説明を省略する。 Hereinafter, an example of an embodiment of the present invention will be described with reference to the drawings. In the present specification and the drawings, elements having substantially the same functional configuration are designated by the same reference numerals, and duplicate description will be omitted.

図1に示すように、建屋1の天井には、屋根10を支える天井トラス11が構築されている。建屋1の内部上方には、天井トラス11のすぐ下を水平方向に移動する天井クレーン2が装備されている。 As shown in FIG. 1, on the ceiling of the building 1, a ceiling truss 11 that supports the roof 10 is constructed. An overhead crane 2 that horizontally moves below the ceiling truss 11 is installed above the inside of the building 1.

建屋1の両側の壁15には、軌道(ランウェイ)16が取り付けられており、天井クレーン2のクレーンガータ17の左右に装着された車輪18が、この軌道16の上に載せられている。天井クレーン2のクレーンガータ17は、車輪18の回転によって軌道16の上を走行し、図1における紙面垂直方向(図2における紙面上下方向)に水平移動する。 Tracks (runways) 16 are attached to the walls 15 on both sides of the building 1, and wheels 18 mounted on the left and right sides of a crane garter 17 of the overhead crane 2 are mounted on the tracks 16. The crane garter 17 of the overhead crane 2 travels on the track 16 by the rotation of the wheels 18, and horizontally moves in the direction perpendicular to the paper surface of FIG. 1 (vertical direction in the paper surface of FIG. 2).

クレーンガータ17の上面は柵20によって囲まれており、クレーンガータ17の上面は作業者が歩行することができる。クレーンガータ17の上面には、図2に示すように、クレーンガータ17の長手方向に延びるレール21が設置されている。クレーンガータ17の長手方向とは、図1、2における紙面左右方向であり、レール21は、クレーンガータ17の上面における長手方向全長に設置されている。 The upper surface of the crane gutter 17 is surrounded by the fence 20, and an operator can walk on the upper surface of the crane gutter 17. As shown in FIG. 2, a rail 21 extending in the longitudinal direction of the crane gutter 17 is installed on the upper surface of the crane gutter 17. The longitudinal direction of the crane gutter 17 is the left-right direction of the paper surface in FIGS. 1 and 2, and the rail 21 is installed on the upper surface of the crane gutter 17 along the entire length in the longitudinal direction.

クレーンガータ17の上面には、レール21上を走行する台車(クラブトロリ)22が搭載されている。図3に示すように、台車22は、基台部23の上に巻き上げユニット部24を取り付け、さらに巻き上げユニット部24の上に手摺25を取り付けた構成である。基台部23の下部には車輪30が装着してあり、この車輪30でレール21上を走行することにより、台車22は、クレーンガータ17の上面における長手方向全長を移動自在である。 A carriage (club trolley) 22 traveling on a rail 21 is mounted on the upper surface of the crane gutter 17. As shown in FIG. 3, the cart 22 has a configuration in which a winding unit unit 24 is mounted on a base unit 23, and a handrail 25 is further mounted on the winding unit unit 24. Wheels 30 are attached to the lower portion of the base portion 23, and by traveling on the rails 21 with the wheels 30, the truck 22 is movable along the entire length in the longitudinal direction on the upper surface of the crane garter 17.

巻き上げユニット部24にはモータ31が内蔵されており、このモータ31の稼働でワイヤ32を巻き上げるによって、台車22に吊り下げられたフック33が昇降される。モータ31の稼働(フック33の昇降)は、リモコンスイッチ34によって操作される。なお、クレーンガータ17の上面における台車22の走行も、リモコンスイッチ34によって操作される。 A motor 31 is built in the hoisting unit 24, and the wire 32 is hoisted by the operation of the motor 31 to raise and lower the hook 33 suspended on the carriage 22. The operation of the motor 31 (the raising and lowering of the hook 33) is operated by the remote control switch 34. The traveling of the carriage 22 on the upper surface of the crane gutter 17 is also operated by the remote control switch 34.

台車22の上には作業者aが乗ることが可能な作業ステージ40が取り付けられている。作業ステージ40は、足場板41の周囲を柵42で囲んだ構成である。この実施の形態では、台車22の上部に設けられた手摺25に接して作業ステージ40が取り付けられ、作業ステージ40の上端は手摺25の高さを超えている。 A work stage 40 on which a worker a can ride is mounted on the carriage 22. The work stage 40 has a structure in which a scaffold plate 41 is surrounded by a fence 42. In this embodiment, the work stage 40 is attached in contact with the handrail 25 provided on the upper portion of the carriage 22, and the upper end of the work stage 40 exceeds the height of the handrail 25.

作業ステージ40の柵42の縦桟42aと横桟42bとして例えば単管パイプを用い、台車22の上部に設けられた手摺25に、柵42の縦桟42a(単管パイプ)を取り付けることにより、台車22の上に作業ステージ40が固定されている。この場合、作業ステージ40の柵42の内外に立設される。すなわち、手摺25の内側と外側に柵42の縦桟42aを配置し、手摺25の内側に配置された縦桟42aが、手摺25の内側に接して内側から外側に向かって突っ張ることにより、作業ステージ40が横ずれしないようにする。 By using, for example, a single pipe pipe as the vertical rails 42a and the horizontal rails 42b of the fence 42 of the work stage 40, by attaching the vertical rails 42a (single pipe pipe) of the rail 42 to the handrail 25 provided on the upper portion of the carriage 22, A work stage 40 is fixed on the carriage 22. In this case, the work stage 40 is erected inside and outside the fence 42. That is, the vertical rails 42a of the fence 42 are arranged inside and outside the handrail 25, and the vertical rails 42a arranged inside the handrail 25 are in contact with the inside of the handrail 25 and are stretched from the inside to the outside. Make sure that the stage 40 does not laterally shift.

また、柵42の横桟42bは直交クランプを用いて縦桟42aに固定されている。なお、地震の際の揺れ対策を考慮するならば、手摺25と接する柵42の縦桟42aや横桟42bをクランプや番線で緊締すると良い。 The horizontal rail 42b of the fence 42 is fixed to the vertical rail 42a by using an orthogonal clamp. If measures against shaking during an earthquake are taken into consideration, it is advisable to tighten the vertical rails 42a and the horizontal rails 42b of the fence 42, which are in contact with the handrail 25, with clamps or rails.

足場板41は、適当な高さ(例えば、クレーンガータ17の上面から高さ1m近くの位置)に柵42の横桟42bを格子状に組み、その上に載置される。フック等を介して架け渡してもよい。横桟42bを縦桟42aの適当の高さに架け渡して足場板41の高さを調節することで、手摺25上面と隙間をとれ、足場板41が巻き上げユニット部24の上部に接しなくなる。 The scaffolding plate 41 is formed by assembling the horizontal rails 42b of the fence 42 in a lattice shape at an appropriate height (for example, a position near the height of 1 m from the upper surface of the crane gutter 17), and is placed thereon. It may be bridged via a hook or the like. By adjusting the height of the scaffolding board 41 by straddling the horizontal rails 42b to an appropriate height of the vertical rails 42a, a space can be formed between the upper surface of the handrail 25 and the scaffolding board 41 does not contact the upper part of the hoisting unit portion 24.

作業ステージ40は台車22に手摺25を介して取り付けられているため、クレーンガータ17の上面において台車22の走行に伴って移動する。なお、作業ステージ40に作業者aが昇り降りするために、市販の昇降ステップ43が掛けられている。 Since the work stage 40 is attached to the carriage 22 via the handrail 25, the work stage 40 moves on the upper surface of the crane garter 17 as the carriage 22 travels. A commercially available elevating step 43 is hung on the work stage 40 for the worker a to go up and down.

ここで、本発明の実施の形態の一例として、建屋1の高所において天井クレーン1を利用してダクト3を施工する場合を説明する。なお、図示のダクト3は、天井トラス11の上に設けられた主ダクト50に、互いに平行に配置された3系統の枝ダクト51a、51b、51cが接続された構成になっている。例示した主ダクト50は、室外に設けた排気フィルタに接続され、ダクト3は排気ダクトを示している。なお、図示はしないが、排気フィルタの近傍には送風機が設けられている。 Here, as an example of the embodiment of the present invention, a case where the duct 3 is constructed in the high place of the building 1 by using the overhead crane 1 will be described. The illustrated duct 3 has a configuration in which a main duct 50 provided on the ceiling truss 11 is connected with branch ducts 51a, 51b, 51c of three systems arranged in parallel with each other. The illustrated main duct 50 is connected to an exhaust filter provided outdoors, and the duct 3 is an exhaust duct. Although not shown, a blower is provided near the exhaust filter.

また、各枝ダクト51a、51b、51cは、主ダクト50に対して、接続部材としての立下りダクト52(エルボ継手)を介して接続される。すなわち、主ダクト50は天井トラス11に敷いた足場板上で天井トラス11内に敷設されており、各枝ダクト51a、51b、51cは、主ダクト50よりも3m程度低い高さ面に施工する。各枝ダクト51a、51b、51cの設置位置は、天井トラス11の直下である。なお、立下りダクト52の施工は、立下りダクト52をそれぞれ高さ1.5m程度の上下のピースに分割し、上ピースの上側端部を主ダクト50にボルト止めしたあと、フランジを介して、上ピースの下側端部に下ピースの上側端部をボルト止めすることによって行われる。また、かかる上ピースと下ピースの接続作業は、作業ステージ40上で行われる。 Further, each branch duct 51a, 51b, 51c is connected to the main duct 50 via a falling duct 52 (elbow joint) as a connecting member. That is, the main duct 50 is laid inside the ceiling truss 11 on the scaffolding board laid on the ceiling truss 11, and the branch ducts 51a, 51b, 51c are installed on a height surface about 3 m lower than the main duct 50. .. The installation position of each branch duct 51a, 51b, 51c is directly below the ceiling truss 11. In addition, the construction of the falling duct 52 is performed by dividing the falling duct 52 into upper and lower pieces each having a height of about 1.5 m, bolting the upper end of the upper piece to the main duct 50, and then inserting it through a flange. , The upper end of the lower piece is bolted to the lower end of the upper piece. Further, the connecting work of the upper piece and the lower piece is performed on the work stage 40.

3系統の枝ダクト51a、51b、51cは、主ダクト50に接続された部分から、建屋1の天井に沿って室内に向かって同一方向に延びるように互いに平行に延設される。本発明の実施の形態では、作業ステージ40に乗った作業者aにより、これら枝ダクト51a、51b、51cが施工される。 The branch ducts 51a, 51b, 51c of the three systems are extended in parallel from the portion connected to the main duct 50 so as to extend in the same direction toward the room along the ceiling of the building 1. In the embodiment of the present invention, the branch ducts 51a, 51b, 51c are constructed by the worker a on the work stage 40.

これら枝ダクト51a、51b、51cの施工は、作業ステージ40を所望の位置に停止させて、作業ステージ40の範囲内において枝ダクト51a、51b、51cの一部分を施工する工程と、作業ステージ40を移動させる工程を交互に繰り返すことに行われる。すなわち、施工する工程では、作業ステージ40を所望の位置に停止させ、作業ステージ40に乗った作業者aが、手の届く範囲で枝ダクト51a、51b、51cの一部分を施工する。 Construction of these branch ducts 51a, 51b, 51c is performed by stopping the work stage 40 at a desired position and constructing a part of the branch ducts 51a, 51b, 51c within the range of the work stage 40. It is performed by alternately repeating the moving step. That is, in the construction process, the work stage 40 is stopped at a desired position, and the worker a on the work stage 40 constructs part of the branch ducts 51a, 51b, 51c within the reach of the worker.

そして、作業ステージ40の範囲内において枝ダクト51a、51b、51cの一部分を施工する工程が終わると、作業ステージ40を次の位置に移動させる。この作業ステージ40を移動させる工程は、クレーンガータ17上にいる作業者aがリモコンスイッチ34を操作して行うことができる。 Then, when the process of constructing a part of the branch ducts 51a, 51b, 51c within the range of the work stage 40 is completed, the work stage 40 is moved to the next position. The process of moving the work stage 40 can be performed by the operator a on the crane garter 17 by operating the remote control switch 34.

天井クレーン2のクレーンガータ17は、軌道16上を走行することにより、建屋1の上方において端から端まで移動可能であり、また、台車22は、クレーンガータ17の上面における長手方向全長を移動可能である。したがって、このように台車22に取り付けられた作業ステージ40の範囲内において枝ダクト51a、51b、51cの一部分を施工する工程と、作業ステージ40を移動させる工程を交互に繰り返すことにより、建屋1の高所全体に長尺の部材である3系統の枝ダクト51a、51b、51cを施工することが可能となる。また、それぞれの位置において枝ダクト51a、51b、51cの一部分を施工する工程は、作業ステージ40の範囲内において行うため、作業ステージ40の直上が工事作業空間となるので、落下防止用のシートなどの準備作業を省略でき、既設の建物など地上に障害物のある施設でも、3系統の枝ダクト51a、51b、51cを建屋1の高所全体に施工できるようになる。 The crane garter 17 of the overhead crane 2 can move from one end to the other above the building 1 by traveling on the track 16, and the carriage 22 can move the entire length in the longitudinal direction on the upper surface of the crane garter 17. Is. Therefore, by alternately repeating the step of constructing a part of the branch ducts 51a, 51b, 51c within the range of the work stage 40 attached to the carriage 22 and the step of moving the work stage 40, the building 1 It is possible to construct three systems of branch ducts 51a, 51b, 51c, which are long members, over the entire high place. Further, since the step of constructing a part of the branch ducts 51a, 51b, 51c at each position is performed within the range of the work stage 40, the construction work space is directly above the work stage 40, so that a fall prevention sheet, etc. It is possible to omit the preparatory work, and it is possible to construct the branch ducts 51a, 51b, 51c of the three systems in the entire high place of the building 1, even in a facility such as an existing building that has an obstacle on the ground.

なお、かかる枝ダクト51a、51b、51cの施工に要する人員は、作業場所近傍に位置するクレーンオペレータ1名、地上での監督者1名(両者はトランシーバで連絡する)のほか、作業ステージ40上の柵42の中で作業する作業員aが予定される。ダクト3のみの施工では4〜6名、もしも、ダクト3が給気ダクトであったり、断熱を要する必要な流体がダクト3を流れる場合、ダクト工に保温被覆の技能がない場合には、同数の保温工をクレーンガータ17上に配置して、作業ステージ40上での作業を交替させてもよい。 In addition, the number of personnel required to construct such branch ducts 51a, 51b, 51c is one crane operator located near the work site, one supervisor on the ground (both are in contact by transceiver), and on the work stage 40. A worker a who works in the fence 42 is scheduled. If only duct 3 is installed, 4 to 6 people. If duct 3 is an air supply duct, or if a necessary fluid that requires heat insulation flows through duct 3, if the duct worker does not have the heat insulation coating skill, the same number. Alternatively, the heat insulating work may be arranged on the crane garter 17 to alternate the work on the work stage 40.

また、リモコンスイッチ34は、天井クレーン2のクレーンガータ17と台車22をそれぞれ往復動させる信号を発信する機能を持つ。かつリモコンスイッチ34は、荷の吊上げ吊降しのためフック33の昇降を指示する信号を発信する。リモコンスイッチ34は他の機能も有するが、誤操作の事故防止のため、これらの3つの動作を指示する以外の機能は、あらかじめタッチ等の指示操作を無効とするよう設定を変更しておくことが望ましい。また、クレーンガータ17や台車22の移行中は、作業者aは作業ステージ40から降り、クレーンガータ17の上面を囲んでいる柵20に安全帯を掛けて待機する。 Further, the remote control switch 34 has a function of transmitting a signal for reciprocating the crane garter 17 and the carriage 22 of the overhead crane 2. Moreover, the remote control switch 34 transmits a signal for instructing the lifting and lowering of the hook 33 for lifting and lowering the load. Although the remote control switch 34 also has other functions, in order to prevent accidents due to erroneous operations, settings other than those for instructing these three operations can be changed in advance so as to invalidate instructed operations such as touch. desirable. Further, during the transfer of the crane gutter 17 and the trolley 22, the worker a descends from the work stage 40, puts a safety belt on the fence 20 surrounding the upper surface of the crane gutter 17, and stands by.

ここで、これら3系統の枝ダクト51a、51b、51cの敷設作業手順と作業ステージ40の移動手順の態様として、例えば次の2通りが考えられる。 Here, for example, the following two modes are conceivable as the manner of laying the branch ducts 51a, 51b, 51c of these three systems and the procedure of moving the work stage 40.

一つの移動手順の態様は、各系統の枝ダクト51a、51b、51cごとに作業ステージ40を長手方向に往復移動させ、各系統の枝ダクト51a、51b、51cを順次施工していく手順である。その一例として、図4に示すように、一番目に枝ダクト51a、二番目に枝ダクト51b、三番目に枝ダクト51cの順に施工していく場合を説明する。 One aspect of the moving procedure is a procedure in which the work stage 40 is reciprocally moved in the longitudinal direction for each branch duct 51a, 51b, 51c of each system, and the branch ducts 51a, 51b, 51c of each system are sequentially installed. .. As an example, as shown in FIG. 4, a case will be described in which the branch duct 51a is first installed, the branch duct 51b is installed second, and the branch duct 51c is installed third.

最初に、主ダクト50に対する一番目の枝ダクト51aの接続位置A1に、作業ステージ40を移動させる。そして、この位置A1において、まず主ダクト50に立下りダクト52を接続し、さらに、立下りダクト52に一番目の枝ダクト51aの基端部分を接続する。なお、立下りダクト52の施工は、立下りダクト52をそれぞれ高さ1.5m程度の上下のピースに分割し、上ピースの上側端部を主ダクト50にボルト止めしたあと、フランジを介して、上ピースの下側端部に下ピースの上側端部をボルト止めすることによって行われる。そして、作業ステージ40上の工事作業空間において、枝ダクト51aの一部分となるダクトピースを立下りダクト52の下端に接続する。 First, the work stage 40 is moved to the connection position A1 of the first branch duct 51a with respect to the main duct 50. Then, at this position A1, first, the falling duct 52 is connected to the main duct 50, and further, the base end portion of the first branch duct 51a is connected to the falling duct 52. In addition, the construction of the falling duct 52 is performed by dividing the falling duct 52 into upper and lower pieces each having a height of about 1.5 m, bolting the upper end of the upper piece to the main duct 50, and then inserting it through a flange. , The upper end of the lower piece is bolted to the lower end of the upper piece. Then, in the construction work space on the work stage 40, a duct piece that is a part of the branch duct 51 a is connected to the lower end of the falling duct 52.

次に、作業ステージ40を、作業ステージ40の幅(枝ダクト51aの延びる方向の作業ステージ40の長さ)の分だけ走行させ、次の位置A2に移動させる。そして、この置A2において、枝ダクト51aの一部分となるダクトピースを順次接続し、作業ステージ40の幅の分だけ一番目の枝ダクト51aを延設していく。これらの作業も同様に、作業ステージ40上の工事作業空間において行われる。 Next, the work stage 40 is moved by the width of the work stage 40 (the length of the work stage 40 in the direction in which the branch duct 51a extends), and is moved to the next position A2. Then, in this placement A2, the duct pieces that are a part of the branch duct 51a are sequentially connected, and the first branch duct 51a is extended by the width of the work stage 40. These operations are similarly performed in the construction work space on the work stage 40.

以後、同様の作業を繰り返しながら、枝ダクト51aの先端部分の位置Anまで作業ステージ40を移動させ、位置Anまでダクトピースを接続することによって、所定の長さを有する一番目の枝ダクト51aが施工される。その後、作業ステージ40は、位置An、・・・、位置A2、位置A1の順に戻される。このように、作業ステージ40が位置Anから位置A1に戻される際に、各位置An、・・・、位置A2、位置A1において、枝ダクト51aの各部分毎に施工の確認を行う。 After that, by repeating the same operation, the work stage 40 is moved to the position An of the tip portion of the branch duct 51a, and the duct piece is connected to the position An so that the first branch duct 51a having a predetermined length is formed. It will be constructed. After that, the work stage 40 is returned in the order of positions An,..., Position A2, and position A1. In this way, when the work stage 40 is returned from the position An to the position A1, the construction confirmation is performed for each part of the branch duct 51a at each position An,..., Position A2, position A1.

こうして、一番目の枝ダクト51aの長手方向(延設方向)に沿って作業ステージ40を往復移動させ、作業ステージ40の往路移動の際に枝ダクト51aを順次施工していき、作業ステージ40の復路移動の際に施工の確認を行うことにより、一番目の枝ダクト51aの施工と確認が完了する。 In this way, the work stage 40 is reciprocally moved along the longitudinal direction (extension direction) of the first branch duct 51a, and the branch duct 51a is sequentially constructed when the work stage 40 moves forward. The construction and confirmation of the first branch duct 51a is completed by confirming the construction during the return movement.

こうして、一番目の枝ダクト51aの施工と確認が完了した後、次に、主ダクト50に対する二番目の枝ダクト51bの接続位置B1に、作業ステージ40を移動させる。そして、同様にまず主ダクト50に立下りダクト52を接続した後、各位置B1、B2、・・・、Bnにおいて枝ダクト51bの一部分となるダクトピースを順次接続し、所定の長さを有する二番目の枝ダクト51bが施工される。また、同様にして、作業ステージ40が位置Bnから位置B1に戻される際に、各位置Bn、・・・、位置B2、位置B1において、枝ダクト51bの各部分毎に施工の確認を行う。 After the construction and confirmation of the first branch duct 51a are completed in this way, the work stage 40 is then moved to the connection position B1 of the second branch duct 51b with respect to the main duct 50. Then, similarly, first, the falling duct 52 is connected to the main duct 50, and then the duct pieces that are a part of the branch duct 51b are sequentially connected at each position B1, B2,..., Bn to have a predetermined length. The second branch duct 51b is constructed. Similarly, when the work stage 40 is returned from the position Bn to the position B1, the construction confirmation is performed for each part of the branch duct 51b at each position Bn,..., Position B2, and position B1.

こうして、二番目の枝ダクト51bの長手方向(延設方向)に沿って作業ステージ40を往復移動させ、作業ステージ40の往路移動の際に枝ダクト51bを順次施工していき、作業ステージ40の復路移動の際に施工の確認を行うことにより、二番目の枝ダクト51bの施工と確認が完了する。 In this way, the work stage 40 is reciprocally moved along the longitudinal direction (extension direction) of the second branch duct 51b, and the branch duct 51b is sequentially constructed when the work stage 40 moves forward, so that the work stage 40 The construction and confirmation of the second branch duct 51b are completed by confirming the construction during the return movement.

さらに、同様に、三番目の枝ダクト51cの長手方向(延設方向)に沿って作業ステージ40を往復移動させ、作業ステージ40の往路移動の際に枝ダクト51cを順次施工していき、作業ステージ40の復路移動の際に施工の確認を行うことにより、二番目の枝ダクト51cの施工と確認が完了する。 Further, similarly, the work stage 40 is reciprocally moved along the longitudinal direction (extending direction) of the third branch duct 51c, and the branch duct 51c is sequentially constructed when the work stage 40 moves forward. The construction and the confirmation of the second branch duct 51c are completed by confirming the construction when the stage 40 moves back.

こうして、一つの移動手順の態様によって、建屋1の高所に長尺の構造物である3系統の枝ダクト51a、51b、51cが施工される。 In this way, the branch ducts 51a, 51b, and 51c of three systems, which are long structures, are constructed at a high place of the building 1 according to one mode of movement procedure.

次に、もう一つの移動手順の態様は、各系統の枝ダクト51a、51b、51cと交差する方向に作業ステージ40を往復移動させ、三系統の枝ダクト51a、51b、51cを同時進行で施工していく手順である。 Next, as another aspect of the moving procedure, the work stage 40 is reciprocated in a direction intersecting with the branch ducts 51a, 51b, 51c of the respective systems, and the branch ducts 51a, 51b, 51c of the three systems are simultaneously constructed. It is a procedure to do.

図5に示すように、最初に、主ダクト50に対する一番目の枝ダクト51aの接続位置A1に、作業ステージ40を移動させる。そして、この位置A1において、まず主ダクト50に立下りダクト52を接続し、さらに、立下りダクト52に一番目の枝ダクト51aの基端部分を接続する。なお、立下りダクト52の施工は、立下りダクト52をそれぞれ高さ1.5m程度の上下のピースに分割し、上ピースの上側端部を主ダクト50にボルト止めしたあと、フランジを介して、上ピースの下側端部に下ピースの上側端部をボルト止めすることによって行われる。そして、作業ステージ40上の工事作業空間において、枝ダクト51aの一部分となるダクトピースを立下りダクト52の下端に接続する。 As shown in FIG. 5, first, the work stage 40 is moved to the connection position A1 of the first branch duct 51a with respect to the main duct 50. Then, at this position A1, first, the falling duct 52 is connected to the main duct 50, and further, the base end portion of the first branch duct 51a is connected to the falling duct 52. In addition, the construction of the falling duct 52 is performed by dividing the falling duct 52 into upper and lower pieces each having a height of about 1.5 m, bolting the upper end of the upper piece to the main duct 50, and then inserting it through a flange. , The upper end of the lower piece is bolted to the lower end of the upper piece. Then, in the construction work space on the work stage 40, a duct piece that is a part of the branch duct 51 a is connected to the lower end of the falling duct 52.

次に、主ダクト50に対する二番目の枝ダクト51bの接続位置B1に、作業ステージ40を移動させる。そして、この位置B1において、主ダクト50に立下りダクト52を接続し、さらに、立下りダクト52に二番目の枝ダクト51bの基端部分を接続する。なお、立下りダクト52の施工は、位置A1の場合と同様に、上下のピースによって行われ、枝ダクト51bの一部分となるダクトピースを立下りダクト52の下端に接続する。 Next, the work stage 40 is moved to the connection position B1 of the second branch duct 51b with respect to the main duct 50. Then, at this position B1, the falling duct 52 is connected to the main duct 50, and further, the base end portion of the second branch duct 51b is connected to the falling duct 52. Note that the construction of the falling duct 52 is performed by the upper and lower pieces, as in the case of the position A1, and the duct piece forming a part of the branch duct 51b is connected to the lower end of the falling duct 52.

次に、主ダクト50に対する三番目の枝ダクト51cの接続位置C1に、作業ステージ40を移動させる。そして、この位置C1において、主ダクト50に立下りダクト52を接続し、さらに、立下りダクト52に三番目の枝ダクト51cの基端部分を接続する。なお、立下りダクト52の施工は、位置A1、B1の場合と同様に、上下のピースによって行われ、枝ダクト51cの一部分となるダクトピースを立下りダクト52の下端に接続する。 Next, the work stage 40 is moved to the connection position C1 of the third branch duct 51c with respect to the main duct 50. Then, at this position C1, the falling duct 52 is connected to the main duct 50, and further, the base end portion of the third branch duct 51c is connected to the falling duct 52. As in the case of the positions A1 and B1, the construction of the falling duct 52 is performed by the upper and lower pieces, and the duct piece which is a part of the branch duct 51c is connected to the lower end of the falling duct 52.

こうして、三系統の枝ダクト51a、51b、51cの各基端部分の施工が終了する。その後、作業ステージ40は、位置C1、位置B1、位置A1の順に戻される。このように、作業ステージ40が位置C1から位置A1に戻される際に、各位置C1、位置B1、位置A1において、三系統の枝ダクト51a、51b、51cの各基端部分毎に施工の確認を行う。 In this way, the construction of the base end portions of the three-system branch ducts 51a, 51b, 51c is completed. After that, the work stage 40 is returned in the order of the position C1, the position B1, and the position A1. In this way, when the work stage 40 is returned from the position C1 to the position A1, at each of the positions C1, B1, and A1, confirmation of the construction is performed for each base end portion of the branch ducts 51a, 51b, 51c of the three systems. I do.

こうして、各系統の枝ダクト51a、51b、51cと交差する方向に作業ステージ40を往復移動させ、作業ステージ40の往路移動の際に三系統の枝ダクト51a、51b、51cの各基端部分の施工を行い、作業ステージ40の復路移動の際に施工の確認を行う。 In this way, the work stage 40 is reciprocated in the direction intersecting with the branch ducts 51a, 51b, 51c of each system, and when the work stage 40 moves forward, the base end portions of the branch ducts 51a, 51b, 51c of the three systems are moved. Construction is performed, and the construction is confirmed when the work stage 40 moves back.

そして、三系統の枝ダクト51a、51b、51cの各基端部分の施工と確認が完了した後、次に、作業ステージ40を、作業ステージ40の幅(枝ダクト51aの延びる方向の作業ステージ40の長さ)の分だけ走行させ、一番目の枝ダクト51aの次の位置A2に移動させる。そして、この位置A2において、枝ダクト51aの一部分となるダクトピースを順次接続し、作業ステージ40の幅の分だけ一番目の枝ダクト51aを延設していく。これらの作業も同様に、作業ステージ40上の工事作業空間において行われる。 Then, after the construction and confirmation of the respective base end portions of the branch ducts 51a, 51b, 51c of the three systems are completed, next, the work stage 40 is moved to the width of the work stage 40 (the work stage 40 in the direction in which the branch duct 51a extends). The length of the first branch duct 51a is moved to a position A2 next to the first branch duct 51a. Then, at this position A2, the duct pieces forming a part of the branch duct 51a are sequentially connected, and the first branch duct 51a is extended by the width of the work stage 40. These operations are similarly performed in the construction work space on the work stage 40.

次に、作業ステージ40を、各系統の枝ダクト51a、51b、51cと交差する方向に走行させ、作業ステージ40を二番目の枝ダクト51bの次の位置B2に移動させる。そして、この位置B2において、枝ダクト51bの一部分となるダクトピースを順次接続し、作業ステージ40の幅の分だけ二番目の枝ダクト51bを延設していく。これらの作業も同様に、作業ステージ40上の工事作業空間において行われる。 Next, the work stage 40 is caused to travel in a direction intersecting with the branch ducts 51a, 51b, 51c of each system, and the work stage 40 is moved to the position B2 next to the second branch duct 51b. Then, at this position B2, the duct pieces forming a part of the branch duct 51b are sequentially connected, and the second branch duct 51b is extended by the width of the work stage 40. These operations are similarly performed in the construction work space on the work stage 40.

次に、作業ステージ40を、各系統の枝ダクト51a、51b、51cと交差する方向に走行させ、作業ステージ40を三番目の枝ダクト51cの次の位置C2に移動させる。そして、この位置C2において、枝ダクト51cの一部分となるダクトピースを順次接続し、作業ステージ40の幅の分だけ三番目の枝ダクト51cを延設していく。これらの作業も同様に、作業ステージ40上の工事作業空間において行われる。 Next, the work stage 40 is moved in a direction intersecting the branch ducts 51a, 51b, 51c of each system, and the work stage 40 is moved to the position C2 next to the third branch duct 51c. Then, at this position C2, the duct pieces forming a part of the branch duct 51c are sequentially connected, and the third branch duct 51c is extended by the width of the work stage 40. These operations are similarly performed in the construction work space on the work stage 40.

こうして、三系統の枝ダクト51a、51b、51cのそれぞれにおける次の部分の施工が終了する。その後、作業ステージ40は、位置C2、位置B2、位置A2の順に戻される。このように、作業ステージ40が位置C2から位置A2に戻される際に、各位置C2、位置B2、位置A2において、三系統の枝ダクト51a、51b、51cのそれぞれにおける次の部分について施工の確認を行う。 In this way, the construction of the next portion in each of the three branch ducts 51a, 51b, 51c is completed. Then, the work stage 40 is returned to the position C2, the position B2, and the position A2 in this order. In this way, when the work stage 40 is returned from the position C2 to the position A2, at each position C2, position B2, and position A2, confirmation of the construction of the next portion in each of the three branch ducts 51a, 51b, 51c is confirmed. I do.

以後、同様の作業を繰り返しながら、三系統の枝ダクト51a、51b、51cのそれぞれの先端部分の位置An、Bn、Cnまで施工とその確認を繰り返し行うことにより、三系統の枝ダクト51a、51b、51cの施工と確認が完了する。 After that, while repeating the same operation, the branch ducts 51a, 51b of the three systems are repeatedly installed and confirmed up to the positions An, Bn, Cn of the tip portions of the branch ducts 51a, 51b, 51c of the three systems. , 51c construction and confirmation is completed.

こうして、もう一つの移動手順の態様によって、建屋1の高所に長尺の部材である3系統の枝ダクト51a、51b、51cが同時進行で施工される。 In this way, according to another mode of the moving procedure, the branch ducts 51a, 51b, 51c of three systems, which are long members, are simultaneously installed at a high place of the building 1.

以上に説明した二つの移動手順のどちらを採用するかは、地上の作業との兼ね合いが影響する。すなわち、枝ダクト51a、51b、51cの施工中に休止してよい作業をクレーンガータ17の移動方向と設定するなら前者を、クレーンガータ17の移動方向と直交する方向に設定するなら後者を選択できる。その他、後者の移動手順を採用する場合、作業ステージ40の柵42が施工済みとなった枝ダクト51a、51b、51cに邪魔されて横移動できないことを避けるため、いったん作業ステージ40の柵42を外す手間も考えられ、それらも工法選択の考慮要因である。なお、発明者の試行では前者の移動手順で約50mの枝ダクトを1系統を敷設する(断熱無・後述する吸込口取付を含む)のに夜間工事を含まない日中作業のみで1週間を要している。 Which of the two movement procedures described above is used depends on the balance with the work on the ground. That is, if the work that may be suspended during the construction of the branch ducts 51a, 51b, 51c is set as the moving direction of the crane garter 17, the former can be selected, and if the work is set in the direction orthogonal to the moving direction of the crane garter 17, the latter can be selected. .. In addition, when the latter movement procedure is adopted, the fence 42 of the work stage 40 is temporarily moved in order to prevent the fence 42 of the work stage 40 from being laterally moved by being obstructed by the branch ducts 51a, 51b, 51c that have been constructed. It may be troublesome to remove it, and these are also factors to consider when selecting a construction method. In the trial of the inventor, a single branch duct of about 50 m was laid by the former transfer procedure (without heat insulation, including suction port installation described later), but no nighttime work was included. I need it.

なお、立下りダクト52の上下のピースや枝ダクト51a、51b、51cのダクトピースなどの揚重は、例えばトラック式高所作業車の荷台に各部材を載せ、天井クレーン2に配置した作業員との間で受け渡しし、軌道(ランウェイ)16上に配置する。高所作業車の立ち入れない場合は、天井クレーン2に沿ってあらかじめ建屋1の鉄骨に仮設ウインチを設け、所定位置に仮置きした各部材を吊り上げてもよい。仮設ウインチは、作業員が天井トラス11内のキャットウォークを渡り既設鉄骨上に据え付けることができる。 The lifting of the upper and lower pieces of the falling duct 52 and the duct pieces of the branch ducts 51a, 51b, and 51c is performed by, for example, a worker who places each member on the loading platform of a truck-type aerial work vehicle and arranges it on the overhead crane 2. It is delivered to and from the vehicle and placed on the track (runway) 16. When the aerial work vehicle cannot be entered, a temporary winch may be provided in advance on the steel frame of the building 1 along the overhead crane 2 and each member temporarily placed at a predetermined position may be lifted. The temporary winch can be installed on the existing steel frame by a worker crossing the catwalk in the ceiling truss 11.

また、枝ダクト51a、51b、51cの施工には、吊りボルトまたは鋼材によってダクトピース(枝ダクト51a、51b、51c)を天井トラス11に支持する必要がある。この場合、既設の鋼材を利用して支持することができる。まず、枝ダクト51a、51b、51cの施工に先立って、天井トラス11に吊ボルトなどの鋼材を吊っておく。すなわち、天井トラス11の形鋼のフランジ部に鋼材の金具を取り付ける。この金具は、フランジ部に嵌める溝を有し付属のボルトを締めて固定するもので、ネグロス電工株式会社のS-HBRHなどの汎用品を利用できる。この金具のボルト穴にセットされた吊ボルトとダクト受け具にダクトピースを敷設していく。 Further, in constructing the branch ducts 51a, 51b, 51c, it is necessary to support the duct pieces (branch ducts 51a, 51b, 51c) on the ceiling truss 11 with hanging bolts or steel materials. In this case, the existing steel material can be used for support. First, prior to the construction of the branch ducts 51a, 51b, 51c, a steel material such as a hanging bolt is hung on the ceiling truss 11. That is, a metal fitting is attached to the flange of the structural steel of the ceiling truss 11. This metal fitting has a groove to be fitted in the flange portion and is fixed by tightening an attached bolt, and a general-purpose product such as S-HBRH of Negros Electric Works Co., Ltd. can be used. The duct piece is laid on the suspension bolt and the duct receiver set in the bolt hole of this metal fitting.

また、発明者は、主に長さ900mmのダクトピースを用い、作業ステージ40上の一回の施工工程では、4本分のダクトピースを延設し、1単位の施工範囲を3600mmとした。また、鋼材による吊ピッチは3mとした。もっとも、主ダクト50の近くでは、枝ダクト51a、51b、51cは太くなり、ダクトピースは太く重くなるので、ダクトピースの分割幅も吊ピッチも小刻みとする。一方、送風機から遠い枝ダクト51a、51b、51cの先端側ではダクトピースを細くしてよいことは勿論である。なお、1単位の施工範囲である3600mmは、クレーンガータ17の幅の約半分であり、作業進捗に応じて作業ステージ40を小刻みに動かしてもよいし、クレーンガータ17の幅の約半分ずつ移動させて、1施工単位で2回移動としてもよい。 Further, the inventor mainly used a duct piece having a length of 900 mm, and in one construction process on the work stage 40, four duct pieces were extended, and the construction range of one unit was 3600 mm. The suspension pitch of steel material was 3 m. However, in the vicinity of the main duct 50, the branch ducts 51a, 51b, 51c become thicker and the duct pieces become thicker and heavier. Therefore, the division width of the duct pieces and the hanging pitch are made small. On the other hand, it goes without saying that the duct pieces may be thinned at the tip ends of the branch ducts 51a, 51b, 51c far from the blower. It should be noted that 3600 mm, which is the construction range of one unit, is about half the width of the crane gutter 17, and the work stage 40 may be moved in small steps according to the progress of work, or the width of the crane gutter 17 may be moved by about half each. Alternatively, the movement may be performed twice in one construction unit.

また、以上に説明した実施の形態は、ダクト3として排気ダクトを例示しており、各枝ダクト51a、51b、51cの下面(室内側)には、室内空気を吸込む吸込口が設けられる。吸込口をダクトピースと一体に製作しトラック搬送すると吸込口に傷がつくおそれがある。そのため、吸込口接続用の短管を取り付けてあるダクトピースを工場で製作し、それと別途搬入した吸込口を楊重することが好ましい。なお、ダクト3が空調給気ダクトなら、吸込口でなく吹出口を設けることになる。吸込口としてHS、吹出口としてVHSのような一般的な制気口を採用できるが金網に替えたり、または各枝ダクト51a、51b、51cの下面に長手方向に沿ってスリットを形成するなど、単なる開口で済ませる場合もある。 Further, the above-described embodiment exemplifies an exhaust duct as the duct 3, and suction ports for sucking indoor air are provided on the lower surfaces (inside the room) of the branch ducts 51a, 51b, 51c. If the suction port is manufactured integrally with the duct piece and transported by truck, the suction port may be damaged. Therefore, it is preferable that a duct piece to which a short pipe for connecting the suction port is attached is manufactured in a factory, and the suction port separately carried in is dug up. If the duct 3 is an air-conditioning air supply duct, a blowout port is provided instead of the suction port. A general air control port such as HS as the suction port and VHS as the air outlet can be adopted, but it may be replaced with a wire mesh, or slits may be formed on the lower surface of each branch duct 51a, 51b, 51c along the longitudinal direction. In some cases, the opening may be sufficient.

そのほか、ダクト3の耐震振れ止めとして、C型鋼ボルトを利用した構造や、吊ボルトに対してボルト材を筋交状に組む方法を採用することができる。 In addition, as a seismic anti-sway of the duct 3, a structure using a C-shaped steel bolt or a method of assembling the bolt material in a bracing manner with the suspension bolt can be adopted.

なお、施工を確認する作業では、例えばフランジのボルトナットの締め忘れ有無の確認をする。ここで、ダクトピースの接続作業の際にボルトねじ山の出代部分にシーラーを塗布しておくと、確認は目視のみで済むことになる。シーラー塗布はマーキング効果のほか、ねじロックの効果もあり推奨される。 In addition, in the work for confirming the construction, for example, it is confirmed whether or not the bolt nuts of the flange have been forgotten to be tightened. Here, if a sealer is applied to the protruding portion of the bolt thread at the time of connecting the duct piece, the confirmation can be done only by visual inspection. Sealer application is recommended as it has a marking effect as well as a screw lock effect.

以上、本発明の実施の形態を例示して説明したが、本発明はかかる例に限定されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において、各種の変更例または修正例に想到しうることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 Although the embodiments of the present invention have been illustrated and described above, the present invention is not limited to such examples. It is obvious to those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and of course, the technical scope of the present invention is also applicable to them. Understood to belong to.

以上の実施の形態では、主ダクト50の寸法が大きく特に高さ方向で1mを超えており、主ダクト50の施工に本工法を採用すると天井トラス11に干渉する(天井クレーン2の上部空間に納まらない)ため、天井トラス11の下方に枝ダクト51a、51b、51cを施工するように計画したが、施工環境・条件が許せば、ダクト3のすべてを本工法で実施して差し支えない。 In the above embodiment, the size of the main duct 50 is large and exceeds 1 m particularly in the height direction, and if this construction method is adopted for construction of the main duct 50, it interferes with the ceiling truss 11 (in the upper space of the overhead crane 2). Therefore, the branch ducts 51a, 51b, and 51c are planned to be installed below the ceiling truss 11, but if the construction environment and conditions permit, all of the ducts 3 may be implemented by this method.

また例えば、以上の実施の形態では、クレーンガータ17の往復移動方向に沿って枝ダクト51a、51b、51cを敷設する例を示しているが、クレーンガータ17の長手方向を作業域とすることができるので、枝ダクト51a、51b、51cから分岐をとり、クレーンガータ17と水平または偏心した方向に分岐の小径ダクトを施工することも可能である。また、長尺の部材として、SGP等の配管を施工することもできる。その場合の配管ユニットは、フレーム材に冷水・温水・フロン系冷媒・ドレンなど異種流体を流すパイプを組み付けたものとしてもよい。そこでの管種は冷媒用銅管やビニル管など異種の管種が束ねられる。 Further, for example, in the above embodiment, an example is shown in which the branch ducts 51a, 51b, 51c are laid along the reciprocating movement direction of the crane garter 17, but the longitudinal direction of the crane garter 17 may be the working area. Therefore, it is also possible to take a branch from the branch ducts 51a, 51b, 51c and construct a branch small-diameter duct in a direction horizontal or eccentric with the crane garter 17. Further, as the long member, piping such as SGP can be installed. In this case, the piping unit may be one in which a pipe through which a different fluid such as cold water, hot water, a CFC-based refrigerant, and a drain flows is attached to the frame material. The pipe types there are bundled with different types such as copper pipes for refrigerants and vinyl pipes.

また、部材の付属品としてはダクトに対する風量測定口や、温度計等の計器があってもよい。ダクトに対するダンパやパイプに対するバルブ、これらを自動制御するならば、モータや信号受信器が取り付けられたユニットとしてもよい。もっとも精密な部材は本体ユニットと別に現場に搬入されクレーン上での組み付け作業となる。自動制御のための配線工事も同様である。 Further, as an accessory of the member, there may be an air flow measuring port for the duct or a measuring instrument such as a thermometer. If a damper for a duct and a valve for a pipe are automatically controlled, a unit equipped with a motor and a signal receiver may be used. The most precise members are carried into the site separately from the main unit and assembled on a crane. The same applies to wiring work for automatic control.

建屋1の高所に独立した機器を点在して設けるのであれば、高所作業車を用いた作業が考えられるが、施工範囲が広く近傍範囲で連続した作業が生ずるダクト、配管の工事で本発明は特に効果を発揮する。 If independent equipment is scattered at high places in the building 1, work using aerial work vehicles may be possible, but the work range is wide, and ducts and piping work that causes continuous work in the vicinity The present invention is particularly effective.

1 建屋
2 天井クレーン
3 ダクト
10 屋根
11 天井トラス
15 壁
16 軌道
17 クレーンガータ
18 車輪
20 柵
21 レール
22 台車
23 基台部
24 巻き上げユニット部
25 手摺
30 車輪
31 モータ
32 ワイヤ
33 フック
34 リモコンスイッチ
40 作業ステージ
41 足場板
42 柵
42a 縦桟
42b 横桟
43 昇降ステップ
50 主ダクト
51a、51b、51c 枝ダクト
52 立下りダクト
a 作業者
1 Building 2 Ceiling Crane 3 Duct 10 Roof 11 Ceiling Truss 15 Wall 16 Track 17 Crane Garter 18 Wheel 20 Fence 21 Rail 22 Bogie 23 Base Unit 24 Hoisting Unit 25 Handrail 30 Wheel 31 Motor 32 Wire 33 Hook 34 Remote Control Switch 40 Work Stage 41 Scaffolding board 42 Fence 42a Vertical bar 42b Horizontal bar 43 Lifting step 50 Main ducts 51a, 51b, 51c Branch duct 52 Falling duct a Worker

Claims (6)

建屋の両側の壁に設けられた一対の軌道と、該一対の軌道に跨るように配置され該軌道上を移動可能に設けられたクレーンガータと、前記クレーンガータに設けられた柵と、前記クレーンガータに設置されたレール上を走行自在に設けられフックが吊り下げられた台車と、を有する天井クレーンを利用して、建屋の高所に長尺の部材を施工する方法であって、
前記台車の上方に縦桟と横桟とを有してなる柵を取り付け、該柵に作業者の足場となる足場板を設置して作業ステージを取り付け、
前記作業ステージの範囲内において部材の一部分を施工する工程と、前記作業ステージを移動させる工程を順次繰り返すことにより、建屋の高所に長尺の部材を施工することを特徴とする、天井クレーンを用いた高所施工方法。
A pair of tracks provided on the walls on both sides of the building, a crane garter which is arranged so as to straddle the pair of tracks and is movable on the track, a fence provided on the crane garter, and the crane a carriage the installed Re et disposed for free travel on rails off click is suspended garter, using an overhead crane with a method of installing a member of the elongate in altitude of the building ,
A fence having vertical rails and horizontal rails is attached above the carriage, and a scaffolding board serving as a foothold for workers is installed on the fence to attach a work stage,
A step of constructing a part of a member within the range of the work stage and a step of moving the work stage are sequentially repeated to construct a long member at a high place of the building, High-place construction method used.
互いに同一方向に延びる長尺の部材が複数系統あり、
各系統ごとに、前記作業ステージを長尺の部材の長手方向に往復移動させ、
前記作業ステージの往路移動の際に施工を行い、
前記作業ステージの復路移動の際に施工の確認を行うことを特徴とする、請求項1に記載の天井クレーンを用いた高所施工方法。
There are multiple long members that extend in the same direction,
For each system, reciprocating the working stage in the longitudinal direction of the long member,
Performing construction when moving the work stage on the outward path,
The method for constructing a high place using an overhead crane according to claim 1, wherein the construction is confirmed when the work stage is moved back.
互いに同一方向に延びる長尺の部材が複数系統あり、
前記作業ステージを長尺の部材と交差する方向に往復移動させ、
前記作業ステージの往路移動の際に施工を行い、前記作業ステージの復路移動の際に施工の確認を行うことを繰り返すことにより、複数系統の長尺の部材を同時進行で施工することを特徴とする、請求項1に記載の天井クレーンを用いた高所施工方法。
There are multiple long members that extend in the same direction,
Reciprocating the working stage in a direction intersecting the long member,
By performing the construction at the time of the forward movement of the work stage, and by repeating the confirmation of the construction at the time of the return movement of the work stage, it is possible to construct a long member of a plurality of systems simultaneously. The method for constructing a high place using the overhead crane according to claim 1.
前記作業ステージの移動は、クレーンガータ上の作業者がリモコンスイッチを操作して行うことを特徴とする、請求項1〜3のいずれか一項に記載の天井クレーンを用いた高所施工方法。 The method for constructing a high place using an overhead crane according to claim 1, wherein the work stage is moved by an operator on a crane garter operating a remote control switch. 前記作業ステージの柵を構成する縦桟は、前記台車に設けられた手摺に取り付けられていることを特徴とする、請求項1〜4のいずれか一項に記載の天井クレーンを用いた高所施工方法。 A vertical rail using a ceiling crane according to any one of claims 1 to 4, characterized in that a vertical rail constituting the fence of the work stage is attached to a handrail provided on the carriage. Construction method. 長尺の部材は、前記クレーンガータに直行する方向に複数系統設けられるものであり、前記作業ステージの範囲内において前記長尺の部材の一部を施工した後に、前記作業ステージを移動させて次の一部を施工することを特徴とする、請求項1〜5のいずれか一項に記載の天井クレーンを用いた高所施工方法。
The long member is provided in a plurality of systems in a direction orthogonal to the crane garter, and after operating a part of the long member within the range of the work stage, the work stage is moved to the next position. The method for constructing a high place using the overhead crane according to any one of claims 1 to 5, wherein a part of the above is constructed .
JP2016045382A 2016-03-09 2016-03-09 High altitude construction method using overhead crane Active JP6723032B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016045382A JP6723032B2 (en) 2016-03-09 2016-03-09 High altitude construction method using overhead crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016045382A JP6723032B2 (en) 2016-03-09 2016-03-09 High altitude construction method using overhead crane

Publications (2)

Publication Number Publication Date
JP2017160659A JP2017160659A (en) 2017-09-14
JP6723032B2 true JP6723032B2 (en) 2020-07-15

Family

ID=59857600

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016045382A Active JP6723032B2 (en) 2016-03-09 2016-03-09 High altitude construction method using overhead crane

Country Status (1)

Country Link
JP (1) JP6723032B2 (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54103225A (en) * 1978-02-01 1979-08-14 Osawa Masaya Scaffold moving at height
JPS56151293U (en) * 1980-04-10 1981-11-12
JPS6286268A (en) * 1985-10-09 1987-04-20 川崎製鉄株式会社 High place moving scaffold apparatus in building having ceiling running crane beam
US5159993A (en) * 1991-10-15 1992-11-03 Gestion Des Brevets Fraco Limitee Self-raising work platform assembly
JPH06146574A (en) * 1992-11-05 1994-05-27 Asia Yusoki Kk Transferable working platform for ceiling in building

Also Published As

Publication number Publication date
JP2017160659A (en) 2017-09-14

Similar Documents

Publication Publication Date Title
JP6786070B2 (en) Permanent scaffolding installation method for bridge inspection
JP6312109B1 (en) Safety device for temporary scaffold
JP5090577B1 (en) Suspension frame for suspension scaffold
CN206707237U (en) Cable-stayed type top layer construction platform for elevator installation
CN205099298U (en) Adhere to installation and maintenance platform and tower machine
JPH0754491A (en) Erecting device for exterior curtain wall of building
JP6723032B2 (en) High altitude construction method using overhead crane
JP4284225B2 (en) Mobile scaffolding system
JPH05178561A (en) Installation method for guide rail for elevator
JP6151528B2 (en) Air conditioning unit construction method
JP5670152B2 (en) Cable rack installation method in the vertical direction and cable rack mounting brackets used in the method
CN117703041A (en) A method of installation and construction of suspended ceilings for ultra-large-span heavy-duty steel corridors
CN113137072B (en) Construction method of high-altitude track mobile steel platform
CN110282557A (en) Assist mounting platform and the method with high vacant duct in bridge crane installation workshop
JP2023129823A (en) Piping unit, working carriage, and construction method
JP2580734Y2 (en) Mobile hanging scaffolding equipment
JP5766005B2 (en) Piping auxiliary device and piping method in railway facility tunnel
CN209244301U (en) A kind of packaged type high-altitude protective net installation component
CN210713763U (en) Construction platform device
KR20080100002A (en) Construction device and method
CN211973153U (en) Equipment storage platform
JPH06703Y2 (en) A device for installing a water conduit in a tunnel
JPH04237761A (en) Method for constructing high place facility
JP2021092064A (en) Underground work trolley
JPH08209849A (en) Installation construction of ceiling and attic facility

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190208

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20190222

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20191226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200114

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200316

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200526

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200623

R150 Certificate of patent or registration of utility model

Ref document number: 6723032

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150