JP3909817B2 - Architectural design support system and program - Google Patents
Architectural design support system and program Download PDFInfo
- Publication number
- JP3909817B2 JP3909817B2 JP2001339939A JP2001339939A JP3909817B2 JP 3909817 B2 JP3909817 B2 JP 3909817B2 JP 2001339939 A JP2001339939 A JP 2001339939A JP 2001339939 A JP2001339939 A JP 2001339939A JP 3909817 B2 JP3909817 B2 JP 3909817B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- costs
- cost
- unit price
- design value
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A20/00—Water conservation; Efficient water supply; Efficient water use
- Y02A20/20—Controlling water pollution; Waste water treatment
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は建築物の設計支援システム及びプログラムに関し、とくにライフサイクルコストに基づく建築物の構造形式や建築材料及び設備等の設計を支援するシステム及びプログラムに関する。ここにライフサイクルコスト(Life Cycle Cost)とは、建築物を企画・設計・建設し、維持管理して所定期間存続させ、最後に解体・廃棄するまでの建築物の全生涯に要する費用の総額である。
【0002】
【従来の技術】
建築物の設計では、例えばインテリジェントビル等に代表されるように機能の高度化が進み維持管理費が増大するに伴い、建設時のイニシャルコストだけでなく、維持管理を経て解体・廃棄に至るに要するランニングコストを考慮することが求められている。建築物のライフサイクルコストは、イニシャルコストとランニングコストとの合計である。ライフサイクルコストの全体から見れば、建築物の維持管理に必要なランニングコストは、建設や企画・設計に必要なイニシャルコストに比し4〜6倍にもなるといわれている(社団法人建築業協会「建物の生涯価値向上を支援するライフサイクルエンジニアリング」1999年3月)。建築物のランニングコストには、その存続期間(使用年数)中の保全費(設備管理費・清掃費・警備費・保守点検費・消耗品等)、水光熱費、更新・修繕費、廃棄・処分費、及び公租公課・保険その他の一般管理費等が含まれる。
【0003】
また最近では、建築主が客観的に評価できるように、設計者や施工者に対して建築物のライフサイクルコストを算出して分かり易く説明することが要求されている。ライフサイクルコストの算出方法として、従来から、建築物の構造形式や建築材料及び設備の仕様等の設計値に基づいてライフサイクルコストを算出する手法が提案されている。また、与えられた設計値の範囲内でランニングコストを低減するため、高耐久性建築材料の採用、省エネルギー設備の導入等の様々なライフサイクルコストの検討方法が提案されている。
【0004】
【発明が解決しようとする課題】
しかし、従来のライフサイクルコストの算出・検討方法は、建築物の構造形式や建築材料及び設備の仕様等の設計値が決定された後に行うものであり、与えられた設計値の範囲内でランニングコストをある程度低減することは可能であるものの、例えば建築主の予算に制約があるような場合に、ライフサイクルコストを予算額以下に抑えることが難しい場合がある。イニシャルコストとランニングコストとは密接な関係にあり、予算制約内でライフサイクルコストの最適化を図るためには、両者のバランスを取って建築物の企画・設計の再検討を必要とする場合がある。建築物のライフサイクルコストに対する意識が高まる中で、企画・設計段階において、予算内で最適なライフサイクルコストが得られるような建築物の設計値の検討が簡単にできる手法の開発が望まれている。
【0005】
そこで本発明の目的は、予算額に見合ったライフサイクルコストの建築物の設計値が簡単に検討できる建築物の設計支援システム及びプログラムを提供することにある。
【0007】
【課題を解決するための手段】
図1のブロック図及び図2の流れ図を参照するに、本発明による建築物の設計支援システムは、コンピュータ1を用いた建築物の設計支援システムにおいて、建築材料及び設備毎の用途別の建設費・保全費・水光熱費・修繕費を記憶した単価データベース11と建築物の総予算額15とを記憶する記憶手段2、建築物の面積21及び階数22と用途別面積比率23と建築材料及び設備24と存続期間25とからなる設計値20を設定する入力手段3、設計値20からデータベース11に基づき建築物の総建設費と存続期間中の保全費・水光熱費・修繕費の累計との合計を含むライフサイクルコスト30を算出する算出手段6、及び算出したライフサイクルコスト30と予算額15とを比較表示する表示手段7を備え、設計値20を変えながら入力手段3による設定と算出手段6によるライフサイクルコスト30の算出と表示手段7による比較表示とからなるサイクルを繰り返すことにより予算額15に見合ったライフサイクルコスト30を与える設計値20の選択を支援してなるものである。
【0008】
更に図1のブロック図を参照するに、本発明による建築物の設計支援プログラムは、建築物の設計を支援するためにコンピュータ1を、建築材料及び設備毎の用途別の建設費・保全費・水光熱費・修繕費を記憶した単価データベース11と建築物の総予算額15とを記憶する記憶手段2、建築物の面積21及び階数22と用途別面積比率23と建築材料及び設備24と存続期間25とからなる設計値20を設定する入力手段3、設計値20からデータベース11に基づき建築物の総建設費と存続期間中の保全費・水光熱費・修繕費の累計との合計を含むライフサイクルコスト30を算出する算出手段6、及び算出したライフサイクルコスト30と予算額15とを比較表示する表示手段7として機能させるものである。
【0009】
好ましくは、保全費及び修繕費の単価データベースを管理グレード別に記憶し、設計値20に建築物の管理グレード26を含め、建築物のライフサイクルコストを管理グレード26毎に算出する。
【0010】
【発明の実施の形態】
図1は、コンピュータ1を用いた本発明の設計支援システムの一実施例のブロック図を示す。コンピュータ1に、記憶手段2と、コンピュータ1を入力手段3として機能させる入力プログラム5と、コンピュータ1を表示手段9として機能させる表示プログラム9と、コンピュータ1をライフサイクルコストの算出手段6として機能させる算出プログラムとを設ける。コンピュータ1に接続したキーボードやマウス等の入力装置4と入力プログラム5とにより入力手段3を構成し、ディスプレイ8aやプリンタ8b等の表示装置8と表示プログラム9とにより表示手段7を構成する。
【0011】
記憶手段2には建築材料・設備毎の用途別の単価データベース11を記憶する。図示例の単価データベース11は、建築物の主要構造材料毎の単価データベース13と、主要構造以外の材料・設備毎の単価データベース12とからなる。主要構造材料の単価データベース13には、例えば図3(C)に示すように、RC(鉄筋コンクリート)やS(鉄骨)等の主要建築構造材料毎に、仮設工事費、土木・地業費、躯体工事費等の建設費単価を記録する。単価データベース13に主要構造材料毎の廃棄・処分費(解体費)の単価を含めてもよい。単価データベース13に記録した単価は、主に建築物の主要構造のイニシャルコストの算出に用いる。主要構造の維持管理を必要とする場合は、単価データベース13に主要構造の保全費、水光熱費、更新・修繕費(以下、単に修繕費ということがある。)等の単価を含めてもよい。
【0012】
他方、主要構造材料以外の材料・設備の単価データベース12には、例えば図3(A)に示すように、建築物の屋根や外壁、空調設備等の建設費、保全費、水光熱費(単位消費量)、修繕費の単価を、建築物の用途別に記録する。用途別に記録する理由は、同じ材料・設備であっても、建築物の用途(例えば事務所又は住宅等)によりランニングコストが異なるからである。同図の保全費には例えば設備保守費や外壁清掃費等のランニングコストを記録する。修繕費には、各材料・設備の更新・修繕に関するランニングコストを記録する。水光熱費には各材料・設備で消費する水光熱量を記録し、その消費量と後述する水光熱費単価データ17とに基づき水光熱費の単価を算出する。必要に応じて、単価データベース12に建築材料・設備毎の廃棄・処分費の単価を含めてもよい。単価データベース12に記録された各材料・設備の単価は、主要構造以外の材料・設備毎のイニシャルコスト及びランニングコストの算出に用いる。
【0013】
図示例の単価データベース12は、複数の構成品から構成される建築材料・設備を考慮して、修繕費の単価を構成品の種類及び比率として記録している。構成品毎の修繕費単価は、例えば図3(B)に示すように、別に設けた単価データベース12bで管理する。同図(A)及び(B)のデータベースは一体となって建築材料・設備の単価データベース12を構成する。
【0014】
図2は、図1の設計支援システムを用いた建築物の設計支援方法の流れ図の一例を示す。また、図6〜17は入力プログラム5の一例を示し、図18は表示プログラム9の一例を示し、図19〜21は表示プログラム9の表示結果である帳票の一例を示す。以下、図2の流れ図と図6〜21とを参照して本発明の設計支援システム及びプログラムを説明する。
【0015】
図2のステップ201〜204は初期処理を示す。先ずステップ201において、図3(A)〜(C)に示すような建築材料・設備の単価データベース11を作成し、コンピュータ1の記憶手段2に記憶する。単価データベース11は、例えば入力プログラム5の一部であるデータベース入力プログラムを介して入力する。図示例では、図7に示す条件設定画面の左下側の基本データ編集欄をマウス等でクリックすることによりデータベース入力プログラムを起動する。
【0016】
ステップ202では、水光熱費単価データ17を入力して記憶手段2に記憶する。水光熱費単価データ17は、例えば図7の条件設定画面の左側の水光熱費設定欄をクリックすることにより起動される水光熱費単価入力プログラムを介して入力する。水光熱費単価データ17には、例えば図4(A)に示すように、電気・ガス・上下水道・灯油・地域熱源等の料金単価を建築物の用途別に記録する。用途別に記録する理由は、用途により単価が異なる場合があるからである。水光熱費単価データ17は、主に建築物の消費エネルギー(水光熱費)に関するランニングコストの算出に用いる。
【0017】
ステップ203では、保全費単価データ18を入力して記憶手段2に記憶する。保全費単価データ18は、例えば図7の条件設定画面の左側の保全費設定欄又は基本データ編集欄をクリックすることにより起動される保全費単価入力プログラムを介して入力する。保全費単価データ18には、例えば図4(B)に示すように、設備管理費・清掃費・警備費・消耗品等の単価を用途別に記録する。保全費単価データ18は、主に建築物の保全に関するランニングコストの算出に用いる。但し、建築物の保全に関するランニングコストのうち建築材料・設備の保守点検等に関するランニングコストは、材料・設備毎に異なるので、図4(B)の保全費単価データ18ではなく、図3(A)の単価データベース12aに保全費単価として記録している。
【0018】
ステップ204では、固定資産税等の税率、火災保険等の保険料率、金利・物価上昇率・人件費上昇率・水光熱費上昇率等の経済指標を入力して記憶手段2に記憶する。税率・保険料率・経済指標等は、例えば図7の条件設定画面上側の経済指標欄をクリックすることにより起動される図9の経済指標等入力プログラム(画面)を介して入力する。税率・保険料率・経済指標等は、主に建築物の一般管理費に関するランニングコストの算出に用いる。但し、経済指標等は本発明による設計支援に必須のものではなく、ステップ204は省略可能である。
【0019】
ステップ201〜204の初期処理の後、ステップ206において建築物の総予算額15を入力して記憶手段2に記憶する。総予算額は、例えば図7の条件設定画面の上方の与条件入力欄をクリックすることにより起動される図8の予算額入力プログラム(画面)を介して入力する。図8の予算額入力プログラムでは、建設費、水光熱費、保全費、企画・設計費、更新・修繕費、一般管理費別に予算額を入力している。必要に応じて廃棄・処分費(解体費)の予算額を含めてもよい。但し、一般管理費は前述した税率・保険料率等に基づき自動的に計算できるので、税率・保険料率を入力する場合は一般管理費の予算額の入力を省略してもよい。
【0020】
次に、ステップ207において、例えば図7の条件設定入力プログラム(画面)等を介して建築物の設計値20をコンピュータ1に設定する。図1のブロック図に示すように、建築物の設計値20は、建築物の面積の設計値21と、階数の設計値22と、用途別面積比率の設計値23と、建築材料及び設備の設計値24と、存続期間の設計値25とを含む。
【0021】
図7では、建築物の面積の設計値21として、延床面積、建築面積、基準階延床面積及び外壁見付面積を設定する。また、建築物の階数の設計値22として、建築物の地下階数と地上階数、及び最高高さを設定する。面積の設計値21及び階数の設計値22は、何れも建築物のイニシャルコスト(建設費)、及び保全に関するランニングコスト(清掃費、警備費、消耗品等)の算出に用いるものである。但し、面積の設計値21のうち建築物の基準階延床面積・建築面積・外壁見付面積については、延床面積及び階数の設計値から自動的に算出できるので、これらの設計値21について詳細な検討を必要としない場合は設定を省略できる。また、階数の設計値22のうち最高高さについても、地上階数の設計値と経験的な単位階当たりの平均高さとから自動的に算出できるので、最高高さについて詳細な検討を必要としない場合は設定を省略できる。すなわち、条件設定入力プログラムでは、建築物の面積及び階数の設計値21、22として、延床面積と地下・地上階数とを設定すれば足りる。
【0022】
また図7では、建築物の用途別面積比率の設計値23として、建築物の主たる用途・その面積比率・仕様形態と、副たる用途・その面積比率・使用形態と、主用途・副用途別の外部開口比率・単位階(1フロア)当たりの平均部屋数・共用部の面積比率とを設定する。用途・面積比率として、例えば建築物の延床面積のうち事務所又は住宅等として使用する面積比率を設定する。使用形態として、例えば賃貸ビルであるか否か、部分貸しであるか否か等を設定する。外部開口比率は、例えば建築物の窓等の開口部の建設費、清掃費等のライフサイクルコストの算出に用いる。単位階当たりの平均部屋数は、建築物の部屋の建設費、保全費等のライフサイクルコストの算出に用いる。共用部の面積比率は、建築物の共用部のライフサイクルコストの算出に用いる。但し、外部開口比率・単位階当たりの平均部屋数・共用部の面積比率は他の設計値から経験則に基づき推定できるので、これらの設計値23について詳細な検討を必要としない場合は設定を省略できる。すなわち、条件設定入力プログラムでは、用途別面積比率の設計値23として、用途別の面積比率・使用形態を設定すれば足りる。
【0023】
更に図7において、建築材料及び設備24のうち主要構造材料の設計値24aを設定する。主要構造材料の設計値24aは、記憶手段2に記憶した主要構造材料毎の単価データベース13(図3(C)参照)から、何れかの主要構造材料を選択することにより設定する。他方、建築材料及び設備24のうち主要構造以外の建築材料の設計値24b及び建築設備の設計値24cは、図7の条件設定画面の左側の建設費設定欄をクリックすることにより起動される図10〜14の設計値入力プログラム(画面)を介して設定する。
【0024】
図10に示す建築材料の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、屋根・外壁・外壁建具・外部ガラス・内部床・内部天井・内部建具等として使用する建築材料の種類、及び複数の建築材料を使用する場合はそれらの採用比率を設計値24bとして設定する。この場合、建築材料の種類の設計値24bは、記憶手段2に記憶した材料及び設備の単価データベース12(図3(A)及び(B)参照)から、用途に応じて何れかの建築材料を選択することにより設定する。
【0025】
図11に示す空調設備の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、空調設備の種類、空調方式、及び複数の設備や方式を使用する場合の採用比率等の設計値24cを設定する。この場合も、空調設備・空調方式の設計値24cは、図3(A)及び(B)に示す設備の単価データベース12の中から用途に応じて何れかを選択することにより設定する。更に同図の設計値入力プログラムでは、必要に応じて、空調設備としてボイラや吸着式熱交換器を用いる場合のエネルギー種別(ガス、灯油等)、排煙設備の種類・採用比率、コージェネレーション設備の種類・容量・発電効率などの設計値24cを設定する。排煙設備やコージェネレーション設備も、図3(A)及び(B)に示す設備の単価データベース12の中から用途に応じて選択する。
【0026】
図12に示す衛生設備の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、給水設備、雑用水設備、消火設備、排水(中水)処理設備、厨房設備等の設計値24cを設定する。図13に示す電気設備の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、受変電設備、自家発電設備、蓄電池設備等の設計値24cを設定する。また図14に示す昇降機設備の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、常用エレベータの種類及び台数、非常用エレベータの種類及び台数、エスカレータの種類及び台数、屋上ゴンドラの種類及び台数等の設計値24cを設定する。これら衛生設備、電気設備、昇降機設備の設計値24cも、図3(A)及び(B)に示す設備の単価データベース12の中から用途に応じて何れかを選択することにより設定する。
【0027】
更に図15に示す省エネルギー手法の設計値入力プログラム(画面)では、建築物の主用途・副用途別に、空調設備・電気設備(照明設備等)・衛生設備における省エネルギー手法の種類及びその採用率の設計値24cを設定する。また、これらの省エネルギー手法毎に、対応するイニシャルコスト(建設費)の上昇率やランニングコストの低減率を、予め記憶手段2に記憶しておくか又は図15の設計値入力プログラムにより設定する。図15で設定された省エネルギー手法の設計値24cは、建築物の設備のイニシャルコスト及びランニングコストの算出に用いる。但し、省エネルギー手法の設計値24cは本発明に必須のものではない。
【0028】
なお、図7の条件設定入力プログラムでは、空調設備・衛生設備・電気設備・昇降機設備以外の設備の設計値24cとして、機械式駐車場の種類・台数を設定することができる。機械式駐車場の設計値24cも、図3(A)及び(B)に示す材料及び設備の単価データベース12の中から選択することにより設定する。このように本発明では、図3(A)及び(B)に示す材料及び設備の単価データベース12が記憶されていることを条件に、空調設備・衛生設備・電気設備・昇降機設備以外の設備の設計値24cを必要に応じて設定してライフサイクルコストを算出することが可能であり、算出したライフサイクルコストに基づきその設備の設計値24cを検討し直すことができる。
【0029】
ステップ207で建築物の設計値20を設定した後、例えば図7の条件設定画面の上側の計算欄をクリックしてライフサイクルコストの算出プログラム6を起動する。図示例では、算出プログラム6を起動すると図17に示す計算条件設定画面が表示され、計算条件設定画面において建築物の存続期間(計算期間)の設計値25を設定する。存続期間の設計値25は、建築物のランニングコストの算出に利用する。存続期間の設計値25を設定した後、計算条件設定画面の下方の計算実行欄をクリックすることにより、算出プログラム6によるライフサイクルコストの算出を開始する。
【0030】
ステップ208において、算出プログラム6は、先ず建築物の建設費31(イニシャルコスト)を算出する。算出プログラム6は、図1に示すように、建築物の面積の設計値21、階数の設計値22、用途別面積比率の設計値23、及び建築材料・設備の設計値24を入力し、図3(A)〜(C)の単価データベース12a、12b、13に基づき、建築物の建設費31を算出する。図1に示す建築材料・設備の設計値24は、図7で設定された主要構造材料の設計値24aと、図10で設定された主要構造以外の建築材料の設計値24bと、図11〜15で設定された設備の設計値24cとを含む。図15で設備の省エネルギー手法の設計値24cが設定されている場合は、その省エネルギー手法によるイニシャルコストの上昇率に基づいて建築物の建設費31を算出する。好ましくは、建築物のイニシャルコストに、建設費31に定率を乗じて算出した建築物の企画・設計費を含める(図19参照)。
【0031】
イニシャルコストの算出に続き、ステップ209において、建築物のランニングコストを算出する。算出プログラム6は、上述した設計値21〜24と、図17で設定された建築物の存続期間の設計値25とから、上述した単価データベース11と水光熱費単価データ17と保全費単価データ18とに基づき、建築物の存続期間中の経年毎の保全費32・水光熱費33・修繕費34(図19参照)を算出し、存続期間中の保全費32・水光熱費33・修繕費34の累計としてのランニングコストを算出する。現在価値の算出を行う場合は金利を使って計算する。この場合も、設備の省エネルギー手法の設計値24cが設定されている場合はその省エネルギー手法によるランニングコストの低減率に基づいて、またステップ204で経済指標等が設定されている場合はその指標を考慮して、建築物のランニングコストを算出する。好ましくは、建築物のランニングコストに、ステップ204で入力した税率・保険料率に基づき算出した一般管理費37と、単価データベース11に記録された解体費に基づき算出した廃棄・処分費36とを含める(図19参照)。
【0032】
ステップ210において、ステップ208で算出したイニシャルコストとステップ209で算出したランニングコストとの合計として建築物のライフサイクルコスト30を算出し、ステップ211において、表示プログラム9により建築物のライフサイクルコスト30の算出値と建設費の総予算額とを比較表示する(図19参照)。ステップ212において、ライフサイクルコスト30の算出値が予算額以下であるか否かを判断し、ライフサイクルコスト30の算出値が予算額を越える場合はステップ207へ戻り、建築物の面積の設計値21、階数の設計値22、用途別面積比率の設計値23、建築材料・設備の設計値24、及び存続期間の設計値25を設定し直しながらステップ207〜211を繰り返す。ライフサイクルコスト30の算出値が予算額以下となるまでステップ207〜211を繰り返すことにより、予算額に見合った建築物の面積21、階数22、用途別面積比率23、建築材料・設備24、及び存続期間25の設計値20を選択することができる。
【0033】
例えば、建築物の建築材料・設備の設計値24と存続期間の設計値25とを一定としつつ面積の設計値21、階数の設計値22、及び用途別面積比率の設計値23を変更しながらステップ207〜211を繰り返すことにより、その存続期間のライフサイクルが予算額の範囲内となるような建築物の構造形式を選択することができる。建築材料・設備の設計値24も併せて変更することにより、予算額の範囲内となるような建築材料及び設備の設計値24を選択することも可能である。存続期間の設計値25を変更しながらステップ207〜211を繰り返すことにより、予算範囲内のライフサイクルコスト30を与える建築物の存続期間の設計値25を選択することも可能である。
【0034】
また本発明では、図21に示すように、例えば建築物のランニングコストを建築材料及び設備毎に詳細に算出することができるので、どの設計値20を変更すればランニングコストが低減できるかについて比較的容易に判断できる。しかも本発明によれば、設計値20の変更に応じてランニングコストだけでなくイニシャルコストも算出し直すので、常に両者のバランスの取れた最適の設計値20を選択することが期待できる。
【0035】
特定の建築物について所望の設計値20が得られたのち、ステップ213において他の予算額について検討する必要があるか否かを判断し、他の予算額について検討する場合はステップ205へ戻ってステップ205〜212を繰り返す。この場合、単価データベース11、水光熱費単価データ17、及び保全費単価データ18は記憶手段2に既に記憶されているので、予算額を入力するだけで建築物の設計値を比較的簡単に検討できる。本発明によれば、設計者等の技術的な専門家の援助がなくても、ライフサイクルコスト30に基づく建築物の設計値の検討を行うことが可能である。
【0036】
こうして本発明の目的である「予算額に見合ったライフサイクルコストの建築物の設計値が簡単に検討できる建築物の設計支援システム及びプログラム」の提供が達成できる。
【0037】
【実施例】
図5は、建築物の管理グレードの設計値26を検討するための本発明の設計支援方法の流れ図の一例を示す。建築物の管理グレードとは、建築物の保全内容の質を表わす指標である。建築物の保全内容の質を高くすれば、保全に関するランニングコストは高くなるが、例えば修繕に関するランニングコストを低く抑えることができる。逆に、保全内容の質を低くすることにより保全に関するランニングコストを低く抑えることができるが、修繕に関するランニングコストが上昇する場合がある。予算内で最適なライフサイクルコストを与える建築物を企画・設計する場合には、建築物の管理グレードの設計値26も含めて検討することが望ましい。
【0038】
管理グレードの設計値26を検討する図5の流れ図では、ステップ501において単価データベース11を作成する際に、建築材料・設備毎の保全費及び修繕費の単価を管理グレード別に記憶しておく。例えば図3(A)における各建築材料・設備の保全費単価と、図3(B)における各構成品の更新単価・修繕単価とを、建築物の予防保全を十分に行う管理グレードAの単価、必要最小限の保全管理のみを行う管理グレードCの単価、普通の保全管理を行う管理グレードBの三種類の単価に分けて記憶する。但し、管理グレードの種類や内容はこの例に限定されない。
【0039】
ステップ511において、例えば図16の管理グレード設計値入力プログラム(画面)を介して建築物の管理グレードの設計値26をコンピュータ1に設定する。図示例では、図7の条件設定画面の左側の保全費用設定欄をクリックすることにより管理グレード設計値入力プログラムを起動する。図16の設計値入力プログラムにおいて、建築物全体の管理グレードを例えば管理グレードA〜Cから何れかを選択することにより設定する。また図16では、建築物の設備管理、清掃、警備、保守点検等の保全項目毎の管理グレードの設計値26を設定することも可能である。例えば、建築物全体の管理グレードは普通(管理グレードB)とするが、設備については高度な予防保守点検(管理グレードA)を必要とする場合は、図16において、建築物全体の管理グレードの設計値26として管理グレードBを設定すると共に、保守点検の管理グレードの設計値26として管理グレードAを設定する。
【0040】
管理グレードの設計値26を設定した後、ステップ512において建築物のランニングコストを算出する。ランニングコストの算出、ライフサイクルコストの算出、予算額とライフサイクルコストとの比較表示に関するステップ512〜514は、設定された管理グレードに応じて単価データベース11の保全費単価及び修繕費単価を利用する点を除き、図2のステップ209〜211と同様の処理である。ステップ515において、ライフサイクルコストの算出値が予算額以下であるか否かを判断し、ライフサイクルコストの算出値が予算額を越える場合はステップ511へ戻り、管理グレードの設計値26を設定し直しながらステップ511〜515を繰り返す。ライフサイクルコストの算出値が予算額以下となるまでステップ511〜515を繰り返すことにより、予算額に見合った管理グレードの設計値26を選択することができる。ステップ515からステップ507へ戻り、管理グレードの設計値26を、面積21、階数22、用途別面積比率23、建築材料・設備24、及び存続期間25の設計値20と共に検討してもよい。
【0041】
なお、ステップ512において、設定された管理グレードの設計値26に基づきランニングコストを算出すると共に、例えば必要最小限の管理グレードとした場合のランニングコストを算出し、ステップ514において管理グレードが異なる複数のライフサイクルコストの算出値と予算額とを比較表示することができる(図19及び20参照)。この比較表示により、予算額に見合った管理グレードの設計値26の選択の容易化を図ることが可能である。
【0042】
図5の流れ図のステップ501〜508は図2のステップ201〜208と同様の処理を示す。図5では、ステップ508において建築物のイニシャルコストを算出したのち、ステップ509においてイニシャルコストの算出値と建設費の予算額とを比較表示し、ステップ510においてイニシャルコストの算出値が建設費の予算額以下であることを確認した後にランニングコストを算出している。但し、ステップ510における確認は厳密である必要はなく、イニシャルコストの算出値が建設費の予算額を越えた場合でも、その差が許容範囲内である場合はステップ511へ進み、ランニングコストを含めたライフサイクルコスト全体から設計値20を検討することができる。ステップ509及び510は本発明に必須の処理ではなく省略してもよい。
【0043】
図2及び5の流れ図では、建築物のライフサイクルコストの算出に際して建築物の立地(例えば都道府県名等)を入力し、立地を考慮したライフサイクルコストを算出している。建築物の立地によってエネルギー単価や人件費単価が相違する場合があるので、詳細なライフサイクルコストを算出するためには建築物の立地に応じて単価データベース11、水光熱費単価データ17、及び保全費単価データ18を調節することが望ましい。
【0044】
図示例では、図2(D)に示すような立地別の単価換算表16をコンピュータ1に記憶しておき(図1参照)、図2及び5のステップ205及び505において、図6に示す入力プログラムの初期画面を介して建築物の立地及びケース名称(建築物名称)を入力する。その後、初期画面の上方のケース別入力欄をクリックすることにより図7の条件設定入力プログラムを起動して建築物の各種設計値20及び予算額等を設定する。ライフサイクルコストの算出に際し、入力された立地に基づいて図2(D)の単価換算表16から立地に応じた換算指数を選択し、単価データベース11、水光熱費単価データ17、及び保全費単価データ18に記録された単価等を立地に応じた換算指数で補正した後、建築物のイニシャルコスト及びランニングコストを算出する。この補正により、立地に応じた建築物のライフサイクルコストを算出することが可能となる。
【0045】
本発明では、単価データベース11において保全費・水光熱費・修繕費を建設後の経過年度別に記憶しておくことにより、建築物の保全費・水光熱費・修繕費のランニングコストを建設後の経過年度別に詳細に算出できる。例えば、図3(B)の単価データベース12bでは、単価と共に更新・修繕が必要となる期間と比率を記録しているので、各材料・設備毎の修繕に関するランニングコストを経年的に算出できる。また、図4(B)の保全費単価テーブル18では特別清掃を必要とする間隔を記録しているので、特別清掃に関するランニングコストを経度的に算出できる。図3(A)の単価データベース12aの保全費についても、例えば保守点検が必要となる期間を記録しておけば、保守点検に関するランニングコストを経年的に算出できる。
【0046】
従って、図8の予算額入力プログラムにおいて年度別維持費の予算額を入力しておけば、図19〜21に示すように、ライフサイクルコスト中の保全費・水光熱費・修繕費と予算額中の年度別維持費とを経過年度別に比較表示することが可能である。図8では、年度別維持費の予算額を、建設費予算額に対する年度毎の修繕比率、更新比率として入力している。例えば、年度毎の修繕比率・更新比率を建築物の賃料等の収益予測に基づいて定めれば、その収益予測と各材料・設備毎の修繕・更新に関するランニングコストとを比較表示することができ、収益予測内で最適の建築材料・設備の設計値を選択することが可能となる。
【0047】
本発明の設計支援プログラムは各種の記録媒体に記録して提供することができ、その記録媒体をコンピュータ1に読み込ませて図2及び5の流れ図に従って建築物の設計値を検討することができる。また、図1のブロック図において、入力装置4及び表示装置8とコンピュータ1とをインターネット等の通信回線で接続することにより、本発明の設計支援プログラムを遠隔地から利用することも可能である。
【0048】
【発明の効果】
以上説明したように、本発明の建築物の設計支援システム及びプログラムは、建築材料及び設備毎の用途別の単価データベースと建築物の総予算額とをコンピュータに記憶し、建築物の面積及び階数と用途別面積比率と建築材料及び設備と存続期間とからなる設計値をコンピュータに設定し、設計値から前記データベースに基づき算出した建築物のライフサイクルコストと前記予算額とを比較表示し、設計値を変えながら前記設定から表示までのサイクルを繰り返すことにより予算額に見合ったライフサイクルコストを与える設計値を選択するので、次の顕著な効果を奏する。
【0049】
(イ)建築物の企画・設計段階において、予算額に見合ったライフサイクルコストを与える建築物の構造形式や建築材料及び設備の仕様等の設計値を選択できる。
(ロ)予算額内のライフサイクルコストを与える建築物の存続期間の検討にも寄与できる。
(ハ)設計者等の技術的な専門家の援助がなくても、ライフサイクルコストに基づく建築物の設計値の検討を容易に行うことが可能である。
(ニ)設計値の変更に応じてランニングコストだけでなくイニシャルコストも算出し直すので、常に両者のバランスの取れた最適の設計値が選択できる。
(ホ)建築物の管理グレードを設計値に加えることにより、予算内で最適なライフサイクルコストを与える建築物の保全内容の質を検討することができる。
(ヘ)建設材料・設備毎のランニングコストを詳細に算出できるので、建築物の賃料等の収益予測等に基づく更新・修繕計画等の評価への適用が期待できる。
(ト)コンピュータに建築物の設計値についての学習機能を持たせることにより、予算額に見合ったライフサイクルコストを与える建築物の設計値の選択の容易化、自動化への発展も期待できる。
【図面の簡単な説明】
【図1】は、本発明システムの一実施例のブロック図である。
【図2】は、本発明方法及びプログラムを示す流れ図の一例である。
【図3】は、単価データベース及び立地別単価換算表の一例の説明図である。
【図4】は、水光熱費単価データ及び保全費単価データの一例の説明図である。
【図5】は、本発明方法及びプログラムを示す流れ図の他の一例である。
【図6】は、入力プログラム(初期画面)の説明図である。
【図7】は、条件設定入力プログラム(画面)の説明図である。
【図8】は、予算額入力プログラム(画面)の説明図である。
【図9】は、経済指標等入力プログラム(画面)の説明図である。
【図10】は、建築材料の設計値入力プログラム(画面)の説明図である。
【図11】は、空調設備の設計値入力プログラム(画面)の説明図である。
【図12】は、衛生設備の設計値入力プログラム(画面)の説明図である。
【図13】は、電気設備の設計値入力プログラム(画面)の説明図である。
【図14】は、昇降機設備の設計値入力プログラム(画面)の説明図である。
【図15】は、省エネルギー手法の設計値入力プログラム(画面)の説明図である。
【図16】は、管理グレードの設計値入力プログラム(画面)の説明図である。
【図17】は、算出プログラムの計算条件設定画面の説明図である。
【図18】は、表示プログラム(画面)の説明図である。
【図19】は、ライフサイクルコストと予算額との比較帳票の一例の説明図である。
【図20】は、ライフサイクルコストと予算額との比較帳票の他の一例の説明図である。
【図21】は、ライフサイクルコストと予算額との比較帳票の更に他の一例の説明図である。
【符号の説明】
1…コンピュータ 2…記憶手段
3…入力手段 4…入力装置
5…入力プログラム
6…算出手段(算出プログラム)
7…表示手段 8…表示装置
8a…ディスプレイ 8b…プリンタ
9…表示プログラム 10…帳票
11…単価データベース
12…主要構造材料の単価データベース
13…主要構造以外の建築材料及び設備の単価データベース
15…総予算額 16…立地別単価換算表
17…水光熱費単価データ 18…保全費単価データ
20…設計値 21…面積の設計値
22…階数の設計値 23…用途別面積比率の設計値
24…建築材料及び設備の設計値
24a…主要構造材料の設計値
24b…主要構造材料以外の建築材料の設計値
24c…建築設備の設計値
25…存続期間の設計値
26…管理グレードの設計値
27…立地(都道府県)
30…ライフサイクルコスト
31…建設費 32…保全費
33…水光熱費 34…修繕費
35…企画・設計 37…一般管理費
36…廃棄・処分費[0001]
BACKGROUND OF THE INVENTION
The present invention is a building design support system. as well as A system that supports the design of building structures, building materials, equipment, etc., based on life cycle costs, especially for programs as well as Regarding the program. The life cycle cost is the total cost of the entire life of the building, from planning, design and construction to maintenance, management and survival for a specified period of time until the final dismantling and disposal. It is.
[0002]
[Prior art]
In the design of buildings, as the sophistication of functions progresses and maintenance costs increase as represented by, for example, intelligent buildings, not only initial costs at the time of construction but also dismantling and disposal through maintenance management. It is required to consider the running cost required. The life cycle cost of the building is the sum of the initial cost and the running cost. From the viewpoint of life cycle cost as a whole, it is said that the running cost required for building maintenance is 4 to 6 times higher than the initial cost required for construction, planning and design. “Lifecycle Engineering to Support Lifetime Value Improvement of Buildings” March 1999). Building running costs include maintenance costs (equipment management costs, cleaning costs, security costs, maintenance costs, consumables, etc.), utility costs, renewal / repair costs, disposal / Includes disposal costs, taxes, taxes, insurance and other general administrative expenses.
[0003]
In recent years, it has been demanded that designers and contractors should calculate and explain the life cycle cost of buildings in an easy-to-understand manner so that the owner can evaluate objectively. Conventionally, as a method for calculating the life cycle cost, a method for calculating the life cycle cost based on design values such as the structure type of the building and the specifications of the building material and equipment has been proposed. In order to reduce running costs within a range of given design values, various life cycle cost examination methods such as adoption of highly durable building materials and introduction of energy saving equipment have been proposed.
[0004]
[Problems to be solved by the invention]
However, the conventional life cycle cost calculation / examination method is performed after design values such as building structure type and building material and equipment specifications are determined, and running within the range of the given design values. Although it is possible to reduce the cost to some extent, it may be difficult to keep the life cycle cost below the budget amount, for example, when the budget of the builder is limited. Initial costs and running costs are closely related, and in order to optimize life cycle costs within budget constraints, it may be necessary to reexamine the planning and design of buildings by balancing the two. is there. As awareness of the life cycle cost of buildings increases, it is desirable to develop a method that can easily examine the design values of buildings so that the optimum life cycle cost can be obtained within the budget at the planning and design stage. Yes.
[0005]
Accordingly, an object of the present invention is to provide a design support system for a building in which a design value of a building having a life cycle cost corresponding to the budget amount can be easily examined. And programs Is to provide.
[0007]
[Means for Solving the Problems]
Block diagram of FIG. And the flow chart of FIG. The building design support system according to the present invention is a building design support system using the
[0008]
Further, referring to the block diagram of FIG. 1, a building design support program according to the present invention uses a
[0009]
Preferably, a unit price database of maintenance costs and repair costs is stored for each management grade, the
[0010]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 shows a block diagram of an embodiment of a design support system of the present invention using a
[0011]
The
[0012]
On the other hand, the
[0013]
The
[0014]
FIG. 2 shows an example of a flowchart of a building design support method using the design support system of FIG. 6 to 17 show an example of the input program 5, FIG. 18 shows an example of the
[0015]
[0016]
In
[0017]
In
[0018]
In
[0019]
After the initial processing of
[0020]
Next, in
[0021]
In FIG. 7, the total floor area, the building area, the standard floor total floor area, and the outer wall found area are set as the
[0022]
In addition, in FIG. 7, as the
[0023]
Further, in FIG. 7, the design value 24a of the main structural material among the building materials and
[0024]
In the building material design value input program (screen) shown in Fig. 10, building materials used as roofs, exterior walls, exterior wall fixtures, exterior glass, interior floors, interior ceilings, interior fixtures, etc., according to the main usage and secondary usage of the building When a plurality of building materials are used, their adoption ratio is set as the design value 24b. In this case, the design value 24b of the type of building material is obtained from the
[0025]
In the design value input program (screen) for the air conditioning equipment shown in FIG. 11, the design of the type of air conditioning equipment, the air conditioning method, and the adoption ratio when using a plurality of facilities and methods, for each main use / sub-use of the building. Set the value 24c. Also in this case, the design value 24c of the air conditioning equipment / air conditioning system is set by selecting one of the equipment
[0026]
In the design value input program (screen) for sanitary facilities shown in Fig. 12, design values for water supply facilities, miscellaneous water facilities, fire extinguishing facilities, wastewater (middle water) treatment facilities, kitchen facilities, etc., for each main use / sub-use of the building Set 24c. In the design value input program (screen) for electrical equipment shown in FIG. 13, design values 24c for receiving / transforming equipment, private power generation equipment, storage battery equipment, etc. are set for each main use / sub-use of the building. In addition, in the elevator design value input program (screen) shown in FIG. 14, the type and number of service elevators, the type and number of emergency elevators, the type and number of escalators, the roof gondola for each main use / sub-use of buildings. Design value 24c such as type and number of units is set. The design value 24c of these sanitary equipment, electrical equipment, and elevator equipment is also set by selecting one of the equipment
[0027]
Furthermore, in the design value input program (screen) of the energy saving method shown in FIG. 15, the types of energy saving methods used in air conditioning equipment, electrical equipment (lighting equipment, etc.) and sanitary equipment and their adoption rates are classified according to the main use and sub use of the building. Set the design value 24c. Further, for each of these energy saving methods, the corresponding initial cost (construction cost) increase rate and running cost reduction rate are stored in advance in the storage means 2 or set by the design value input program of FIG. The design value 24c of the energy saving method set in FIG. 15 is used to calculate the initial cost and running cost of the building equipment. However, the design value 24c of the energy saving method is not essential for the present invention.
[0028]
In the condition setting input program shown in FIG. 7, the type and number of mechanical parking lots can be set as the design value 24c of equipment other than air conditioning equipment, sanitary equipment, electrical equipment, and elevator equipment. The design value 24c of the mechanical parking lot is also set by selecting from the
[0029]
After setting the
[0030]
In
[0031]
Following the calculation of the initial cost, in
[0032]
In
[0033]
For example, while changing the
[0034]
Further, in the present invention, as shown in FIG. 21, for example, the running cost of a building can be calculated in detail for each building material and equipment, so a comparison is made as to which
[0035]
After the desired
[0036]
Thus, the object of the present invention is “a building design support system that can easily examine the design value of a building having a life cycle cost commensurate with the budget amount”. And programs Can be achieved.
[0037]
【Example】
FIG. 5 shows an example of a flow chart of the design support method of the present invention for examining the
[0038]
In the flow chart of FIG. 5 in which the
[0039]
In
[0040]
After setting the management
[0041]
In
[0042]
[0043]
In the flowcharts of FIGS. 2 and 5, the location of the building (for example, the name of a prefecture) is input when calculating the life cycle cost of the building, and the life cycle cost considering the location is calculated. Since the unit price of energy and the unit cost of labor costs may differ depending on the location of the building, in order to calculate detailed life cycle costs, the
[0044]
In the illustrated example, a unit price conversion table 16 according to location as shown in FIG. 2D is stored in the computer 1 (see FIG. 1), and the input shown in FIG. 6 is performed in
[0045]
In the present invention, maintenance costs, utility costs, and repair costs are stored in the
[0046]
Therefore, if the budget amount for annual maintenance costs is input in the budget amount input program of FIG. 8, as shown in FIGS. 19 to 21, maintenance costs, utility costs, repair costs and budget amounts in the life cycle costs are shown. It is possible to compare and display maintenance costs by year in each year. In FIG. 8, the budget for maintenance costs by year is input as the repair ratio and renewal ratio for each fiscal year against the budget for construction costs. For example, if the repair ratio and renewal ratio for each fiscal year are determined based on revenue predictions such as building rents, the revenue prediction and running costs related to repair and renewal for each material and facility can be displayed in comparison. Therefore, it is possible to select the optimum building material / equipment design value within the earnings forecast.
[0047]
The design support program of the present invention can be provided by being recorded on various recording media, and the design value of the building can be examined according to the flowcharts of FIGS. In the block diagram of FIG. 1, the design support program of the present invention can be used from a remote location by connecting the
[0048]
【The invention's effect】
As explained above, the architectural design support system of the present invention as well as The program stores the unit price database for each building material and facility and the total budget of the building in the computer, and consists of the area and floor number of the building, the area ratio by use, the building material and facility, and the lifetime. The design value is set in the computer, the life cycle cost of the building calculated from the design value based on the database is compared with the budget amount, and the budget is obtained by repeating the cycle from the setting to the display while changing the design value. Since the design value that gives the life cycle cost commensurate with the forehead is selected, the following remarkable effects can be obtained.
[0049]
(B) At the planning and design stage of a building, it is possible to select design values such as the structure type of the building and the specifications of building materials and equipment that give a life cycle cost commensurate with the budget amount.
(B) It can also contribute to the study of the lifetime of buildings that give life cycle costs within the budget amount.
(C) It is possible to easily examine the design value of a building based on the life cycle cost without the assistance of a technical expert such as a designer.
(D) Since not only the running cost but also the initial cost is recalculated in accordance with the change in the design value, it is possible to always select the optimum design value in which both are balanced.
(E) By adding the management grade of the building to the design value, it is possible to examine the quality of the maintenance content of the building that gives the optimum life cycle cost within the budget.
(F) Since the running cost for each construction material / equipment can be calculated in detail, it can be expected to be applied to the evaluation of renewal / repair plans based on earnings forecasts such as building rents.
(G) By providing the computer with a learning function for the design value of the building, it is possible to facilitate the selection of the design value of the building that gives the life cycle cost corresponding to the budget amount and to develop it to automation.
[Brief description of the drawings]
FIG. 1 is a block diagram of an embodiment of the system of the present invention.
FIG. 2 is an example of a flowchart showing the method and program of the present invention.
FIG. 3 is an explanatory diagram of an example of a unit price database and a unit price conversion table by location.
FIG. 4 is an explanatory diagram of an example of utility cost unit price data and maintenance cost unit price data.
FIG. 5 is another example of a flowchart showing the method and program of the present invention.
FIG. 6 is an explanatory diagram of an input program (initial screen).
FIG. 7 is an explanatory diagram of a condition setting input program (screen).
FIG. 8 is an explanatory diagram of a budget amount input program (screen).
FIG. 9 is an explanatory diagram of an economic index etc. input program (screen).
FIG. 10 is an explanatory diagram of a design value input program (screen) for building materials.
FIG. 11 is an explanatory diagram of a design value input program (screen) for air conditioning equipment;
FIG. 12 is an explanatory diagram of a design value input program (screen) for sanitary facilities.
FIG. 13 is an explanatory diagram of a design value input program (screen) for electrical equipment.
FIG. 14 is an explanatory diagram of a design value input program (screen) for elevator equipment.
FIG. 15 is an explanatory diagram of a design value input program (screen) of an energy saving method.
FIG. 16 is an explanatory diagram of a management grade design value input program (screen);
FIG. 17 is an explanatory diagram of a calculation condition setting screen of a calculation program.
FIG. 18 is an explanatory diagram of a display program (screen).
FIG. 19 is an explanatory diagram of an example of a comparison form between a life cycle cost and a budget amount.
FIG. 20 is an explanatory diagram of another example of a comparison form between a life cycle cost and a budget amount.
FIG. 21 is an explanatory diagram of still another example of a comparison form between a life cycle cost and a budget amount.
[Explanation of symbols]
1.
3 ... Input means 4 ... Input device
5 ... Input program
6 ... Calculation means (calculation program)
7: Display means 8 ... Display device
8a…
9 ...
11… Unit price database
12… Unit price database of main structural materials
13… Unit price database of building materials and equipment other than main structures
15…
17… Unit price data for utility costs 18… Unit price data for maintenance costs
20…
22… Design value of
24… Design values of building materials and equipment
24a: Design values of main structural materials
24b… Design values of building materials other than main structural materials
24c… Design value of building equipment
25 ... Lifetime design value
26 ... Design value of management grade
27… Location (prefecture)
30… Life cycle cost
31 ... Construction costs 32 ... Maintenance costs
33… Utilities 34… Repair costs
35… Planning and
36… Disposal and disposal costs
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001339939A JP3909817B2 (en) | 2001-11-05 | 2001-11-05 | Architectural design support system and program |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001339939A JP3909817B2 (en) | 2001-11-05 | 2001-11-05 | Architectural design support system and program |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003141178A JP2003141178A (en) | 2003-05-16 |
JP3909817B2 true JP3909817B2 (en) | 2007-04-25 |
Family
ID=19154213
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001339939A Expired - Lifetime JP3909817B2 (en) | 2001-11-05 | 2001-11-05 | Architectural design support system and program |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3909817B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20200284458A1 (en) * | 2019-03-06 | 2020-09-10 | Hitachi-Johnson Controls Air Conditioning, Inc | Air condition management apparatus, system, and method |
Families Citing this family (26)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4588530B2 (en) * | 2005-05-20 | 2010-12-01 | 鹿島建設株式会社 | Asset management support system, asset management support method, program, recording medium |
JP5002287B2 (en) * | 2007-03-07 | 2012-08-15 | 株式会社野村総合研究所 | Facility management system and program |
US8442855B2 (en) * | 2008-03-28 | 2013-05-14 | Christopher R. DiPaolo | Method of designing and building to a targeted cost for high tech facilities |
SG181884A1 (en) * | 2009-12-23 | 2012-07-30 | AEA Integration | System and method for automated building services design |
JP6238051B2 (en) * | 2013-08-29 | 2017-11-29 | 清水建設株式会社 | Energy-saving technology proposal device, energy-saving technology proposal method, and program |
JP6270039B2 (en) * | 2014-05-14 | 2018-01-31 | 国立大学法人名古屋大学 | Building design support system |
KR101500554B1 (en) * | 2014-05-28 | 2015-03-12 | (주)엘씨씨코리아 | Prediction method of life cycle cost depending on variables for educational facilities and Back tracking method |
US11010846B2 (en) | 2017-01-12 | 2021-05-18 | Johnson Controls Technology Company | Building energy storage system with multiple demand charge cost optimization |
US11061424B2 (en) | 2017-01-12 | 2021-07-13 | Johnson Controls Technology Company | Building energy storage system with peak load contribution and stochastic cost optimization |
US10949777B2 (en) | 2017-06-07 | 2021-03-16 | Johnson Controls Technology Company | Building energy optimization system with economic load demand response (ELDR) optimization |
US11238547B2 (en) | 2017-01-12 | 2022-02-01 | Johnson Controls Tyco IP Holdings LLP | Building energy cost optimization system with asset sizing |
US10282796B2 (en) | 2017-01-12 | 2019-05-07 | Johnson Controls Technology Company | Building energy storage system with multiple demand charge cost optimization |
US10324483B2 (en) | 2017-01-12 | 2019-06-18 | Johnson Controls Technology Company | Building energy storage system with peak load contribution cost optimization |
US11847617B2 (en) | 2017-02-07 | 2023-12-19 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system with financial analysis functionality |
US11900287B2 (en) | 2017-05-25 | 2024-02-13 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system with budgetary constraints |
US11487277B2 (en) | 2017-05-25 | 2022-11-01 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system for building equipment |
US11747800B2 (en) | 2017-05-25 | 2023-09-05 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system with automatic service work order generation |
US11120411B2 (en) | 2017-05-25 | 2021-09-14 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system with incentive incorporation |
US11416955B2 (en) | 2017-05-25 | 2022-08-16 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system with integrated measurement and verification functionality |
US12242259B2 (en) | 2017-05-25 | 2025-03-04 | Tyco Fire & Security Gmbh | Model predictive maintenance system with event or condition based performance |
US11636429B2 (en) | 2017-05-25 | 2023-04-25 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance systems and methods with automatic parts resupply |
US11409274B2 (en) | 2017-05-25 | 2022-08-09 | Johnson Controls Tyco IP Holdings LLP | Model predictive maintenance system for performing maintenance as soon as economically viable |
US11022947B2 (en) | 2017-06-07 | 2021-06-01 | Johnson Controls Technology Company | Building energy optimization system with economic load demand response (ELDR) optimization and ELDR user interfaces |
JP2021009694A (en) | 2019-06-28 | 2021-01-28 | ジョンソン コントロールズ テクノロジー カンパニーJohnson Controls Technology Company | Model predicting maintenance system involving budget restrictions |
US11480360B2 (en) | 2019-08-06 | 2022-10-25 | Johnson Controls Tyco IP Holdings LLP | Building HVAC system with modular cascaded model |
JP7103678B2 (en) * | 2020-10-27 | 2022-07-20 | 有限会社小山直樹一級建築士事務所 | Building design support system |
-
2001
- 2001-11-05 JP JP2001339939A patent/JP3909817B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20200284458A1 (en) * | 2019-03-06 | 2020-09-10 | Hitachi-Johnson Controls Air Conditioning, Inc | Air condition management apparatus, system, and method |
US10962251B2 (en) * | 2019-03-06 | 2021-03-30 | Hitachi-Johnson Controls Air Conditioning, Inc. | Air condition management apparatus, system, and method |
Also Published As
Publication number | Publication date |
---|---|
JP2003141178A (en) | 2003-05-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3909817B2 (en) | Architectural design support system and program | |
Fuller et al. | Impact of past and future residential housing development patterns on energy demand and related emissions | |
Langston et al. | Strategic assessment of building adaptive reuse opportunities in Hong Kong | |
Crawford et al. | Demolition or Refurbishment of Social Housing? A review of the evidence | |
Dodd et al. | Identifying macro-objectives for the life cycle environmental performance and resource efficiency of EU buildings | |
Seo | International review of environmental assessment tools and databases | |
Mercader-Moyano et al. | Integrated urban regeneration for high-rise multi-family buildings by providing a multidimensional assessment model and decision support system | |
Alshamrani | Evaluation of school buildings using sustainability measures and life-cycle costing technique | |
JP7466922B2 (en) | Asset management support system, asset management support method and program | |
Yang et al. | Developing a dynamic life cycle assessment framework for buildings through integrating building information modeling and building energy modeling program | |
Cormick | Comparing three building life cycle assessment tools for the canadian construction industry | |
Aygenç | Life Cycle Assessment (LCA) of a LEED-Certified Green Building using two different LCA tools | |
JP6831122B2 (en) | Asset management support system, asset management support method and program | |
JP6992998B2 (en) | Asset management support system, asset management support method and program | |
Gardezi et al. | Life cycle carbon footprint assessments, case study of Malaysian housing sector | |
Pandey | Decarbonizing Metropolises: Analyzing New York’s LL97 and Boston’s Berdo Net Zero Policies | |
Burnett et al. | Costs and financial benefits of undertaking green building assessments | |
Haibo | Whole building life cycle assessment for residential buildings: a design improvement framework | |
Robinson et al. | Theories and principles of design Economics | |
Nacer et al. | Sustainability assessment of an existing school building in Ifrane Morocco using LEED and WELL certification and environmental approach | |
Donatello et al. | EU Green Public Procurement (GPP) criteria for the design, construction, renovation, demolition and management of buildings. | |
Mercader-Moyano et al. | Sustainable renovation of buildings: building information modelling | |
Ramon et al. | Sustainability assessment of a Flemish office building with Level (s): a Level 1 assessment | |
Ali | Whole building life cycle Assessment (WBLCA) of an adaptive reuse of a heritage building: A case study of an Industrial building | |
Goins et al. | Oak Ridge National Laboratory FY 2023 Site Sustainability Plan With FY 2022 Performance Data |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040617 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061023 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061213 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070122 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070122 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3909817 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100202 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130202 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160202 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |