JP3634324B2 - The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method - Google Patents
The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method Download PDFInfo
- Publication number
- JP3634324B2 JP3634324B2 JP2002154138A JP2002154138A JP3634324B2 JP 3634324 B2 JP3634324 B2 JP 3634324B2 JP 2002154138 A JP2002154138 A JP 2002154138A JP 2002154138 A JP2002154138 A JP 2002154138A JP 3634324 B2 JP3634324 B2 JP 3634324B2
- Authority
- JP
- Japan
- Prior art keywords
- blocking wall
- water blocking
- dam
- piece
- dam body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は砂防ダムのスリット設置工法に関する技術であり、特に既設のダム堤体にスリットを設ける際の堤体仮締め切り工法及び同工法に使用する止水プロテクターに関する。
【0002】
【従来の技術】
砂防ダムは、大雨・洪水時に流出する有害土砂、流木等をせき止めるために設置する構造物である。
従来の砂防ダムは、ダム堤体で土石流を遮断し、上流のポケットで土砂を堆積させ流出する砂量を調節する仕組みのクローズドダム(不透過型ダム)が一般的であった。このようなクローズド砂防ダムは貯砂量に限界があるため、土砂が堆積して満砂の状態となると砂防ダムとして機能しなくなる。そこで堆積した土砂を取り除いて砂防ダムとしての機能を回復させようとしても、新しい砂防ダムを建設するのと同等の費用がかかり、実際に浚渫が行われることは殆どなかった。
【0003】
最近の砂防事業においては、ダム堤体の中央部に開口(スリット)を設けて、平常時は無害の土砂をスリットから自然に下流に流し、異常時の巨石礫、流木は土砂災害を防ぐために止める仕組みのスリットダム(透過型ダム)が積極的に施工される傾向になっている。
その理由は、土石流が発生した際にスリットダム(透過型ダム)が巨石や流木を止め、一方平常時には細かい土砂を下流に流すことで下流の侵食を抑えることができ、河床の低下、扇状地の消失、海岸線の後退を防ぐとともに水中の栄養分の供給を図り、かつ魚等の水棲生物の移動を可能にして、河川環境を自然に近い環境に保つ利点機能がある等自然環境を配慮した構造物であることによる。
【0004】
そこで、既設のクローズド砂防ダム(不透過型ダム)の堤体にスリットを設けることで透過型に改修し、土石流発生時には巨石や流木を止め、平常時は細かい土砂を下流に流すことで河川生態系への影響を改善する計画が土石流危険地域で立案され、既に一部地域では実施に移されている。
【0005】
【発明が解決しようとする課題】
既設の砂防ダムのスリット設置工事は、通常ワイヤーソー工法を用いて行われる。この工法はコンクリート製堤体に小さい穴をあけてワイヤーソーを通し、この穴を利用してワイヤーソーを高速駆動させて堤体を縦または横に切断してスリットを設置する工法である。しかし、既設の砂防ダムは、前述のようにダムポケットに相当量の土砂が堆積しているとともに、土砂の上に相当量の水が溜まっている場合があり、もしくは堤体頭頂から溢流水が常に流下している場合がある。このような既設の砂防ダムにおいて、スリット設置工事を行う際に、貯水が深い場合は潜水夫が水中に潜って穴を開けるなどの作業をしなければならず、また貯水が少なくても容量の大きいポンプを使って掘削工事に支障がないように排水して水位を下げなければならない。また溢流水がある場合は水路を別に切廻して設けるなどして現場をドライの状態にしなければならなかった。
いずれにしても作業手間が多くかかり、ポンプ設備の据付や仮設水路の設置などが必要で、どうしても工事が大掛かりとなる問題がある。
【0006】
また、次に述べるような問題もある。ダムのスリット設置工事は通常渇水期に行われる。しかし、そのスリット設置工事期間中に万一、現場に降水があると増水に伴う危険をさけるために工事を中断することがある。そして大雨が降り土石流が発生したときには、スリット設置のために堆積土砂を浚渫して剥き出しにした堤体が再び土砂に埋没し、あるいは堤体に開けたワイヤーソーの穴に土砂が詰まって工事をはじめからやり直す必要等が生ずる。また仮にそのような事がなくても増水や鉄砲水等から、作業員の人命安全性の確保する仮締め切り設備を設ける必要があるといった配慮が必要である。
【0007】
従って本発明の目的は、既設のダム堤体にスリットを設ける工事において、仮締め切り設備を設けることで、施工時の人員の安全確保と作業性を向上させることができる堤体仮締め切りスリット設置工法及び同工法に使用する止水プロテクターを提供することにある。
【0008】
【課題を解決するための手段】
上記目的を達成するために採用した本発明の工法は次の通りである。すなわち、砂防ダムの堤体上流面に仮締め切り止水壁を設けてスリット施工を行う工法であって、
形鋼材により内側フレームを組立てるとともに、該内側フレームの外側に鋼板または鉄板製の壁パネルを張設することで、人間が入れる内部中空のスペースを形成させ、かつそのスペース下側にとがった先端ピースを有する下部止水壁ピースと、前記下部の先端ピースを除いて下部止水壁ピースと同様な構造を有した上部止水壁ピースとを用い、
前記下部止水壁ピースの上方に1個又は複数個の上部止水壁ピースを積上げ配置し、前記上部止水壁ピースを下部止水壁ピースに対しボルト接続することで、上部から下部に向かって楔形に細くなるように内部中空の楔構造体を形成し、
前記下部止水壁ピースは堤体の上流側法面に吊下ろして仮置し、その下部止水壁ピース上に上部止水壁ピースを積重ねて前記両止水壁ピースの相互を水面上でボルト接合してから堤体の上流側法面に沿って定位置に移動して設置後、楔構造体内部の水位を下げ止水処理を行い、該楔構造体内部から両止水壁ピースを堤体にアンカー止めし、次いで堤体の上流側よりワイヤーソーを通す穴を削孔し、該孔を利用して堤体にスリットを施工する各段階からなることを特徴とする堤体仮締め切りスリット設置工法である。
【0009】
また本発明のプロテクターは、砂防ダムの堤体上流面に構築する仮締め切り止水プロテクターであって、該止水プロテクターは、形鋼材により内側フレームを組立てるとともに、該内側フレームの外側に鋼板または鉄板製の壁パネルを張設することで人間が入れる内部中空のスペースを形成させ、かつそのスペース下側にとがった先端ピースを有する下部止水壁ピースと、前記下部の先端ピースを除いて下部止水壁ピースと同様な構造を有した上部止水壁ピースとを用い、
前記下部止水壁ピースの上方に1個又は複数個の上部止水壁ピースを積上げ配置し、前記上部止水壁ピースを下部止水壁ピースに対しボルト接続することで、上部から下部に向かって楔形に細くなるように内部中空の楔構造体に形成したことを特徴とするダム堤体にスリットを設置するための堤体仮締め切り止水プロテクターである。
【0010】
前記止水プロテクターは、その横断面がほぼコ字型またはアーチ型に形成されていることを特徴としている。
【0011】
また、下部止水壁ピースは、その下側に横断面が半円錐型または半角錐型形状とした先端ピースが接続された構成である。
【0012】
【発明の実施の形態】
以下、本発明の実施形態を図面に基づき説明するが、本発明はこれにより限定されるものではない。
図1は既存のコンクリート砂防ダム(クローズドダム)の一例を示す模式図であり、図1(a)は該砂防ダムを上流側より見た斜視図、図1(b)は側面図である。本発明は、上記のようなタイプの砂防ダムの堤体1の中央部に、水通し部頭頂から河床に到達するスリット(開口)2を設置して透過型とするための堤体の仮締め切りスリット設置工法及び同工法に使用する止水壁用プロテクターを提案するものである。図1(a)ではスリット2を形成する位置を斜線で示している。
スリット2の幅は、土砂の流出・堆積状況など現場の状況に応じて適宜設計される。スリットは必要に応じて二つ以上設けられることもあるが、図1においては、ひとつとなっている。
符号3で示すものが本発明の止水プロテクターであり、このプロテクター3は予め工場等で鋼材を使用して上部から下部に向かって細くなった楔体形状に製作され、楔体内部は複数の人間が入ってスリット設置作業が行えるスペースを有するような中空構造になっている。そしてこのプロテクター3は、後述のように上下方向に2〜数個に小分割されて、小型車両等で山岳部へ搬入できるピースに形成されている。
分割された各ピースは、堤体1に設置しようとするスリット2の位置に合わせて堤体の上流側法面に吊りおろして一体になるように積み上げた後、堤体にアンカー止めして取り付けられる。
【0013】
図2は本発明プロテクターの一実施例を示す側面図、図3は図3のa−a矢示図、図4は図2のb−b矢示図である。図2〜4に示すように、本実施例のプロテクター3は数個のピース、すなわち下部止水壁ピースと上部止水壁ピースとを縦方向に積み上げてボルト接続して構成される。以下本実施例のプロテクターの具体的構成を説明する。図示の例は、5個のピース(P1〜P5)を堤体1の上流側法面に5段積み上げて構成した例である。この実施例の場合、積み上げ後のプロテクターは、高さ8m、幅3.2m、奥行き2.5mに形成されている。
このプロテクター3は、形鋼材4を縦、横フレーム並びに上下フレームとして使用し、必要に応じて方杖5を設置した上で、その外側に壁パネル6を張り付けて形成された複数の仮締切り止水壁ピースを縦方向に積み上げて組み立てられたものである。すなわち、図示例は内側のフレームとしてH鋼を使用し、同じH鋼製方杖を設置した上で、フレームの外側に止水壁となる3枚の矩形状及び/又は台形状の鋼板又は鉄板6を溶接及び/またはボルト留めし、横断面でほぼコ字型をなすように組み立てられている。
【0014】
このプロテクターを使用して行う既設のダム堤体にスリットを設置する施工順序を図5〜11で説明する。まず、先端がとがった下部止水壁ピース(先端ピース)No.1をクレーン等により堤体の上流側法面に吊下ろしてから、堤体にワイヤーで仮とめした後、その下部止水壁ピース上に上部止水壁ピースNo.2を積重ねて、水面上で相互にボルト接合してから堤体の上流側法面に沿って定位置まで移動する。その後、楔体内部の水をポンプでくみ上げて楔内部の水位を下げる。このように内部の水をポンプでくみ上げていくと、No.1とNo.2のピース(プロテクター)は浮力で押し上げられることもなく、水圧により堤体に次第に強く押し付けられることとになり、そのため楔内部への浸水量は次第に少なくなっていく。このように楔体内部の水位を順次下げながら継ぎ目にコーキングを施す。次いで内部からピース全体を堤体にアンカー止めした後、堤体の下流側よりワイヤーソーを通す穴7を堤体1に削孔する。次いで堤体の上部にワイヤーソーを設置し、該穴7を利用して堤体1にスリットを順次施工する。
以上のようにして、所定のスリット施工完了後プロテクターを撤去すればスリット設置工事は完了する。
図5(a)(b)〜図11(a)(b)は、本発明工法による既設のダム堤体にプロテクターを設置する順序を示している。
【0015】
図示のプロテクターは、止水壁6が鋼板で、横断面がほぼコ字型をなすように組み立てられているがアーチ型であってもよい。また、下部先端ピースも横断面が半円錐型または半角錐型にすることも可能である。
【0016】
【発明の効果】
本発明によれば、既設の砂防ダムの堤体にスリット設置工事を行う際に、貯水量が深い場合でも、潜水夫が水中に潜って穴を開けるなどの作業をする必要はない。また、大掛かりなポンプ設備の据付や仮設水路の設置なども必要がない。更に万一、そのスリット設置工事期間中に大雨が降り土石流が発生したとき、本仮締め切り設備により、剥き出しにした堤体が土砂に埋没し、あるいは堤体に開けたワイヤーソーの穴に土砂がつまることもなく、そのうえ増水や鉄砲水等から作業員の人命安全性の確保することができる効果がある。
本発明に使用するプロテクターは上下方向に2〜数個に小分割でき、小型車両等で山岳部へ容易に搬入して組み立てることができる。また使用に際し、浮力で押し上げられることもなく、水圧により堤体に次第に強く押し付けられる効果を有する。
【図面の簡単な説明】
【図1】図1(a)は該砂防ダムを上流側より見た斜視図、図1(b)は側面図である。
【図2】図2は本発明プロテクターの一実施例を示す側面図である。
【図3】図3は図2のa−a矢示図である。
【図4】図4は図2のb−b矢示図である。
【図5】図5(a)と(b)は本工法の第1工程を示す。
【図6】図6(a)と(b)は本工法の第2工程を示す。
【図7】図7(a)と(b)は本工法の第3工程を示す。
【図8】図8(a)と(b)は本工法の第4工程を示す。
【図9】図9(a)と(b)は本工法の第5工程を示す。
【図10】図10(a)と(b)は本工法の第6工程を示す。
【図11】図11(a)と(b)は本工法の第7工程を示す。
【符号の説明】
1 堤体1
2 スリット
3 プロテクター
4 フレーム
5 方杖
6 止水壁(鋼板又は鉄板)
7 ワイヤーソーを通す穴[0001]
BACKGROUND OF THE INVENTION
TECHNICAL FIELD The present invention relates to a technique for installing a slit in a sabo dam, and more particularly, to a dam body temporary closing method when a slit is provided in an existing dam dam body and a water stop protector used in the method.
[0002]
[Prior art]
Sabo dams are structures that are installed to dampen harmful earth and sand, driftwood, etc. that flow out during heavy rains and floods.
Conventional sabo dams are generally closed dams (impervious dams) that block the debris flow at the dam body and deposit sediment in the upstream pockets to adjust the amount of sand that flows out. Since such a closed sabo dam has a limit in the amount of sand stored, it will not function as a sabo dam when sediment accumulates and becomes full sand. Therefore, even if it was attempted to restore the function of the sabo dam by removing the accumulated earth and sand, it cost as much as constructing a new sabo dam, and dredging was rarely actually performed.
[0003]
In recent sabo projects, an opening (slit) is provided in the center of the dam body, so that innocuous earth and sand are allowed to flow naturally downstream from the slit during normal times. Slit dams (transmission type dams) with a mechanism of stopping tend to be actively constructed.
The reason for this is that when a debris flow occurs, a slit dam (transmission dam) stops megaliths and driftwood. On the other hand, by flowing fine earth and sand downstream, it is possible to suppress downstream erosion. A structure that takes into account the natural environment, such as preventing the disappearance and retreating of the coastline, providing nutrients in the water, and enabling the movement of aquatic organisms such as fish to maintain the river environment close to nature. Because it is.
[0004]
Therefore, the existing closed sabo dam (impervious dam) is cut into a translucent structure by providing slits. When debris flow occurs, megaliths and driftwood are stopped, and during normal times, fine sediment is flowed downstream. Plans to improve the impact on the system have been drafted in debris flow hazard areas and have already been implemented in some areas.
[0005]
[Problems to be solved by the invention]
The slit installation work of the existing sabo dam is usually performed using the wire saw method. In this method, a small hole is drilled in a concrete dam body, a wire saw is passed through, and the wire saw is driven at a high speed using this hole to cut the levee body vertically or horizontally to install a slit. However, in existing sabo dams, a considerable amount of sediment has accumulated in the dam pockets as described above, and a considerable amount of water may have accumulated on the sediment, or there is overflow from the top of the dam body. There may be a constant flow. In such existing sabo dams, when the slit installation work is done, if the reservoir is deep, the diver must work such as diving in the water to make a hole. The water level must be lowered by draining with a large pump so that the excavation work is not hindered. Also, if there was overflow water, the site had to be made dry, such as by turning the waterway separately.
In any case, it takes a lot of work, and it is necessary to install a pump facility or a temporary water channel, which inevitably requires a large amount of work.
[0006]
There are also the following problems. Dam slit installation work is usually done during drought. However, if there is rain on the site during the slit installation work, the work may be interrupted to avoid the dangers associated with increased water. When heavy rain falls and debris flow occurs, the embankment that has been stripped of sedimented sediment for the installation of slits is buried again in the sediment, or the hole is drilled into the hole of the wire saw. Need to start over from the beginning. Even if there is no such thing, it is necessary to consider that it is necessary to provide a provisional deadline facility for ensuring the safety of workers' lives due to water increase or flash flood.
[0007]
Therefore, the purpose of the present invention is to provide a temporary deadline slit installation method for the dam body temporary deadline that can improve the safety and workability of personnel during construction by providing a temporary deadline facility in the construction of providing a slit in an existing dam bank. And it is providing the still water protector used for the construction method.
[0008]
[Means for Solving the Problems]
The method of the present invention employed to achieve the above object is as follows. In other words, it is a construction method that performs slit construction by providing a temporary cutoff water wall on the upstream surface of the dam body of the sabo dam,
Assemble the inner frame with the shape steel material and stretch the wall panel made of steel plate or iron plate outside the inner frame to form a hollow space inside which a human can enter, and the tip piece pointed below the space A lower water blocking wall piece, and an upper water blocking wall piece having the same structure as the lower water blocking wall piece except for the lower tip piece,
One or more upper water blocking wall pieces are stacked and arranged above the lower water blocking wall piece, and the upper water blocking wall piece is bolted to the lower water blocking wall piece so that the upper water blocking wall piece extends from the upper part to the lower part. Forming an internal hollow wedge structure so that it becomes thin in a wedge shape ,
The lower water blocking wall piece is suspended and temporarily placed on the upstream slope of the dam body, and the upper water blocking wall piece is stacked on the lower water blocking wall piece so that the two water blocking wall pieces are mutually on the water surface. after installation by moving from the bolted in position along the upstream side slopes of the dam body, performs a waterproofing treatment to lower the water level inside the wedge structure, both water-stop wall piece from the wedge structure section The dam body temporary deadline characterized by comprising the steps of anchoring to the levee body, then drilling a hole through which the wire saw passes from the upstream side of the dam body, and constructing a slit in the dam body using the hole It is a slit installation method.
[0009]
The protector according to the present invention is a temporary closing water protector constructed on the upstream surface of the dam body of the sabo dam, and the water protector assembles the inner frame with the shape steel material, and a steel plate or an iron plate outside the inner frame. A hollow wall panel made by humans is formed to form a hollow space inside which a human can enter, and a lower water blocking wall piece having a tip piece pointed on the lower side of the space, and a lower stop piece except for the lower tip piece. Using the upper water blocking wall piece having the same structure as the water wall piece,
One or more upper water blocking wall pieces are stacked and arranged above the lower water blocking wall piece, and the upper water blocking wall piece is bolted to the lower water blocking wall piece so that the upper water blocking wall piece extends from the upper part to the lower part. A dam body temporary closing water protector for installing a slit in a dam dam body, which is formed in an internal hollow wedge structure so as to become thin in a wedge shape .
[0010]
The water stop protector is characterized in that its cross section is formed in a substantially U shape or an arch shape.
[0011]
The lower water blocking wall piece has a configuration in which a tip piece whose cross section is a semiconical shape or a half pyramid shape is connected to the lower side of the lower waterstop wall piece.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings, but the present invention is not limited thereto.
FIG. 1 is a schematic view showing an example of an existing concrete sabo dam (closed dam). FIG. 1 (a) is a perspective view of the sabo dam viewed from the upstream side, and FIG. 1 (b) is a side view. The present invention provides a dam body temporary cut-off for installing a slit (opening) 2 that reaches the river bed from the top of the water passage at the center of the
The width of the
What is indicated by
Each divided piece is hung on the upstream slope of the levee body according to the position of the
[0013]
2 is a side view showing an embodiment of the protector of the present invention, FIG. 3 is an aa arrow view of FIG. 3, and FIG. 4 is an bb arrow view of FIG. As shown in FIGS. 2 to 4, the
This
[0014]
The construction sequence for installing the slits in the existing dam body using this protector will be described with reference to FIGS. First, the lower water blocking wall piece (tip piece) No. 1 was suspended from the upstream slope of the dam by a crane or the like, and then temporarily fastened with a wire to the dam body, then the upper water barrier piece No. 1 was placed on the lower water barrier piece. 2 are stacked, bolted to each other on the water surface, and then moved to a fixed position along the upstream slope of the bank. Thereafter, the water inside the wedge body is pumped up to lower the water level inside the wedge. In this way, when pumping up the internal water, no. 1 and No. The second piece (protector) is not pushed up by buoyancy, and is gradually pushed strongly against the dam by water pressure, so that the amount of water intruding into the wedge gradually decreases. In this way, caulking is performed on the seam while the water level inside the wedge body is sequentially lowered. Next, the whole piece is anchored to the bank body from the inside, and then a hole 7 through which the wire saw is passed is drilled in the
As described above, if the protector is removed after completion of the predetermined slit construction, the slit installation construction is completed.
FIGS. 5 (a) (b) to 11 (a) (b) show the order in which the protectors are installed on the existing dam body according to the construction method of the present invention.
[0015]
The illustrated protector is constructed such that the
[0016]
【The invention's effect】
According to the present invention, when slit installation work is performed on a bank of an existing sabo dam, even if the amount of stored water is deep, there is no need for a diver to dive into the water and open a hole. In addition, there is no need to install a large-scale pump facility or a temporary waterway. In the unlikely event that heavy rain falls and debris flows occur during the installation of the slits, the temporary cut-off facility causes the exposed dam body to be buried in the earth or sand, or the earth and sand to fall into the wire saw hole opened in the dam body. In addition, there is an effect that it is possible to ensure the safety of workers' lives due to water increase or flash flood.
The protector used in the present invention can be subdivided into two or more pieces in the vertical direction, and can be easily carried into a mountainous area and assembled by a small vehicle or the like. In use, it is not pushed up by buoyancy, and has the effect of being strongly pushed against the dam by water pressure.
[Brief description of the drawings]
FIG. 1 (a) is a perspective view of the sabo dam as viewed from the upstream side, and FIG. 1 (b) is a side view.
FIG. 2 is a side view showing an embodiment of the protector of the present invention.
3 is a view taken along the line aa in FIG. 2;
4 is a view taken along the line bb in FIG. 2;
FIGS. 5 (a) and 5 (b) show a first step of the present construction method.
6 (a) and 6 (b) show a second step of the present construction method.
FIGS. 7A and 7B show the third step of the present construction method.
FIGS. 8A and 8B show a fourth step of the present construction method.
9 (a) and 9 (b) show a fifth step of the present construction method.
FIGS. 10A and 10B show a sixth step of the present construction method.
FIGS. 11 (a) and 11 (b) show a seventh step of the present construction method.
[Explanation of symbols]
1
2 slit 3 protector 4
7 Hole for wire saw
Claims (4)
形鋼材により内側フレームを組立てるとともに、該内側フレームの外側に鋼板または鉄板製の壁パネルを張設することで人間が入れる内部中空のスペースを形成させ、かつそのスペース下側にとがった先端ピースを有する下部止水壁ピースと、前記下部の先端ピースを除いて下部止水壁ピースと同様な構造を有した上部止水壁ピースとを用い、
前記下部止水壁ピースの上方に1個又は複数個の上部止水壁ピースを積上げ配置し、前記上部止水壁ピースを下部止水壁ピースに対しボルト接続することで上部から下部に向かって楔形に細くなるように内部中空の楔構造体を形成し、
前記下部止水壁ピースは堤体の上流側法面に吊下ろして仮置し、その下部止水壁ピース上に上部止水壁ピースを積重ねて前記両止水壁ピース相互を水面上でボルト接合してから堤体の上流側法面に沿って定位置に移動して設置後、楔構造体内部の水位を下げ止水処理を行い、該楔構造体内部から両止水壁ピースを堤体にアンカー止めし、次いで堤体の上流側よりワイヤーソーを通す穴を削孔し、該孔を利用して堤体にスリットを施工することを特徴とする堤体仮締め切りスリット設置工法。It is a construction method for slit construction by providing a temporary cutoff water wall on the upstream surface of the dam body of the sabo dam,
Assemble the inner frame with the shape steel material and stretch the wall panel made of steel plate or steel plate outside the inner frame to form an internal hollow space for humans to insert, and the tip piece pointed below the space Using a lower water blocking wall piece and an upper water blocking wall piece having the same structure as the lower water blocking wall piece except for the lower tip piece,
One or a plurality of upper water blocking wall pieces are stacked and arranged above the lower water blocking wall piece, and the upper water blocking wall piece is bolted to the lower water blocking wall piece from the upper part toward the lower part. An internal hollow wedge structure is formed so as to become thin in a wedge shape ,
The lower water blocking wall piece is suspended and temporarily placed on the upstream slope of the dam body, and the upper water blocking wall piece is stacked on the lower water blocking wall piece, and the water blocking wall pieces are bolted to each other on the water surface. after installation moved from bonded in position along the upstream side slopes of the dam body, performs a waterproofing treatment to lower the water level inside the wedge structure, Tsutsumi both water-stop wall piece from the wedge structure section A dam body temporary closing slit installation method characterized by anchoring to a body, then drilling a hole through which a wire saw passes from the upstream side of the dam body, and constructing a slit in the dam body using the hole.
前記下部止水壁ピースの上方に1個又は複数個の上部止水壁ピースを積上げ配置し、前記上部止水壁ピースは下部止水壁ピースに対しボルト接続することで上部から下部に向かって楔形に細くなるように内部中空の楔構造体に形成したことを特徴とするダム堤体にスリットを設置するための堤体仮締め切り止水プロテクター。 A temporary water stop protector constructed on the upstream surface of a dam body of a sabo dam, wherein the water stop protector assembles an inner frame with a shape steel material and stretches a wall panel made of a steel plate or an iron plate outside the inner frame. A lower water blocking wall piece having a tip piece that is pointed below the space, and a structure similar to the lower water blocking wall piece except for the lower tip piece. Using the upper water blocking wall piece
One or a plurality of upper water blocking wall pieces are stacked above the lower water blocking wall piece, and the upper water blocking wall piece is bolted to the lower water blocking wall piece from the upper part toward the lower part. A dam body temporary closing water protector for installing a slit in a dam dam body, which is formed in a hollow wedge structure so as to be thin in a wedge shape .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002154138A JP3634324B2 (en) | 2002-05-28 | 2002-05-28 | The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002154138A JP3634324B2 (en) | 2002-05-28 | 2002-05-28 | The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003342940A JP2003342940A (en) | 2003-12-03 |
JP3634324B2 true JP3634324B2 (en) | 2005-03-30 |
Family
ID=29771002
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002154138A Expired - Fee Related JP3634324B2 (en) | 2002-05-28 | 2002-05-28 | The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3634324B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104047268A (en) * | 2014-05-26 | 2014-09-17 | 江苏鼎泰工程材料有限公司 | Dam reinforcement method |
CN106702968A (en) * | 2017-03-14 | 2017-05-24 | 长沙理工大学 | Arc type overflow dam capable of automatically washing away sand and reducing siltation and running method of arc type overflow dam |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6362471B2 (en) * | 2014-08-07 | 2018-07-25 | 株式会社丸島アクアシステム | Temporary deadline for repairing spillway gate of dam body |
CN106168028B (en) * | 2016-08-27 | 2018-06-26 | 南通格瑞环保科技有限公司 | A kind of cantilevered reservoir dam template |
-
2002
- 2002-05-28 JP JP2002154138A patent/JP3634324B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104047268A (en) * | 2014-05-26 | 2014-09-17 | 江苏鼎泰工程材料有限公司 | Dam reinforcement method |
CN106702968A (en) * | 2017-03-14 | 2017-05-24 | 长沙理工大学 | Arc type overflow dam capable of automatically washing away sand and reducing siltation and running method of arc type overflow dam |
CN106702968B (en) * | 2017-03-14 | 2019-05-21 | 长沙理工大学 | It is a kind of can automatic sand washing subtract the arc line type overflow dam and its operation method of silt |
Also Published As
Publication number | Publication date |
---|---|
JP2003342940A (en) | 2003-12-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5157710B2 (en) | Embankment reinforcement structure | |
KR100766364B1 (en) | Temporary barrier using pipe and water gate and its construction method | |
US20110033237A1 (en) | Device and method for floor protection, coastal protection, or scour protection | |
CN105735208A (en) | Dam exceeding-standard flood diversion siphon frieze group | |
CN109610405A (en) | Half lunar crater shape water pond and its construction method | |
JP3634324B2 (en) | The dam body temporary deadline slit installation method in Sabo Dam and the protector used for the method | |
RU2498007C1 (en) | Reserve spillway of earth dam | |
JP2016503467A (en) | Assembling-type variable height type blocking structure with wave barrier function | |
CN112502092A (en) | Water gate and pump station double-layer integrated structure and operation method thereof | |
CN105603942B (en) | Dykes and dams super standard flood flood diversion siphon pipe band | |
JP6659489B2 (en) | Breakwater structure | |
RU2317369C1 (en) | Method for river bank consolidation | |
JP4000513B2 (en) | High tide prevention sluice | |
RU2312949C1 (en) | Method for flooding water rise control | |
JP4097222B2 (en) | River / Sabo Structure and Block Material for River / Sabo Structure Construction | |
KR200450426Y1 (en) | Lightning channel | |
CN111236149A (en) | Hydraulic engineering retaining wall and construction method thereof | |
JP3696963B2 (en) | Commutation structure in construction of concrete dam. | |
TW201016930A (en) | Regulation method for river with the function of protecting bridge pier and dike, and with the function of forming sand and stone collecting specific area | |
CN117328410B (en) | Dam blocking construction method with low excavation quantity and rapid construction | |
CN211200318U (en) | Abrupt groove structure of reservoir spillway | |
Khatua et al. | Management of High Flood in Mahanadi & Its Tributaries below Naraj | |
RU121270U1 (en) | SUPPORT WEIR (OPTIONS) AND FLEXIBLE CONCRETE MAT FOR ITS CREATION | |
KR20140020548A (en) | System for preventing erosion and the concreting method therefor | |
KR100965522B1 (en) | Reinforcement material for slope ditch and slope ditch structure using the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040707 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040721 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040915 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041201 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041222 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090107 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100107 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100107 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110107 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110107 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120107 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120107 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130107 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140107 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |