JP3225456B2 - How to build a building - Google Patents
How to build a buildingInfo
- Publication number
- JP3225456B2 JP3225456B2 JP24168194A JP24168194A JP3225456B2 JP 3225456 B2 JP3225456 B2 JP 3225456B2 JP 24168194 A JP24168194 A JP 24168194A JP 24168194 A JP24168194 A JP 24168194A JP 3225456 B2 JP3225456 B2 JP 3225456B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- pillar
- roof frame
- frame
- constructing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、例えば、火力発電所に
備えるボイラー等、大型の機器や設備等を収容する建屋
を構築するのに用いて好適な建屋の構築方法に関するも
のである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building suitable for constructing a building for accommodating large-scale equipment and equipment, such as a boiler for a thermal power plant.
【0002】[0002]
【従来の技術】一般に、火力発電所のボイラー等、大型
の機器や設備を収容する建屋は、大断面を有した鉄骨か
ら構成されている。従来、このような鉄骨造の建屋を構
築するには、大型の揚重機を用いて下方から上方に向け
て鉄骨を建方していき、建方が完了した後、機器や設備
を内部に搬入・設置していた。2. Description of the Related Art In general, a building for accommodating large-scale equipment and facilities, such as a boiler of a thermal power plant, is formed of a steel frame having a large cross section. Conventionally, to construct such a steel-framed building, a large lifting machine was used to construct the steel frame from the bottom up, and after the construction was completed, equipment and facilities were brought inside.・ It was installed.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上述し
たような従来の建屋の構築方法には、以下のような問題
が存在する。まず、建屋を構成する鉄骨を建方するため
には、これら鉄骨が大断面であるため、これを吊り上げ
るのに大型の揚重機を用いる必要がある。このため、構
築すべき建屋の敷地が狭隘な場合には、このような揚重
機を設置するスペースの確保が困難となったり、また、
仮設用地が不足したりするという問題が発生する。ま
た、屋根架構を施工するに際しては、この作業が高所作
業となるため、安全性の面で向上の余地がある。さらに
は、機器や設備の早期の運転開始が望まれる場合には、
機器や設備の搬入を早める必要がある。しかし、搬入時
に大型の機器や設備の荷重を支持するためには、建屋が
所要の強度を有していなければならない。このため、建
屋の構築完了前に機器や設備の搬入作業を行うには、大
量の仮設の補強部材を用いて建屋を補強しなければなら
ず、非常に手間がかかるため、建屋の構築作業が完了す
るまでは機器や設備の搬入作業を行えないのが実情であ
り、したがって機器や設備の運転開始の早期化を図るの
は困難であった。本発明は、以上のような点を考慮して
なされたもので、狭隘な敷地であっても施工が可能で、
かつその施工作業を安全に行うことができ、さらには収
容した機器や設備の早期の運転開始を可能とする建屋の
構築方法を提供することを目的とする。However, the conventional building construction method as described above has the following problems. First, in order to construct the steel frames constituting the building, since these steel frames have a large cross section, it is necessary to use a large lifting machine to lift them. For this reason, if the site of the building to be built is narrow, it is difficult to secure space for installing such a crane,
The problem that shortage of temporary land occurs occurs. In addition, when installing the roof frame, since this work is performed at a high place, there is room for improvement in terms of safety. Furthermore, if it is desired to start operation of equipment and facilities early,
It is necessary to speed up the loading of equipment and facilities. However, in order to support the load of large-sized equipment and equipment at the time of loading, the building must have a required strength. For this reason, to carry in equipment and facilities before the completion of building construction, the building must be reinforced with a large number of temporary reinforcing members, which is very time-consuming and requires a lot of time. It is a fact that the carrying-in work of the equipment and the facilities cannot be performed until the operation is completed. Therefore, it is difficult to accelerate the operation start of the equipments and the facilities. The present invention has been made in consideration of the above points, and can be constructed even on a narrow site,
It is another object of the present invention to provide a method for constructing a building that can safely perform the construction work and that can start operation of the housed equipment and facilities at an early stage.
【0004】[0004]
【課題を解決するための手段】請求項1に係る発明は、
大型の機器や設備等を収容する建屋の構築方法であっ
て、前記建屋の柱を構築した後、該柱上に屋根架構を構
築する第一の工程と、収容すべき前記機器,設備を前記
屋根架構に備えた吊下手段で吊り込んで定められた位置
に設置する第二の工程と、前記建屋の外周をなす外周架
構を構築する第三の工程とからなり、前記第一の工程に
おいて前記柱を構築するに際しては、まず、一定長の仮
設支柱を形成して、該仮設支柱の上部に前記建屋の屋根
架構を一体に設けた後、前記柱の全長のうちの一部を立
設し、しかる後に、前記仮設支柱に備えたジャッキアッ
プ手段で前記柱に反力を得て前記仮設支柱と屋根架構と
を一体にクライミングさせるクライミング作業と、クラ
イミングさせた該屋根架構の下方において前記柱を延長
構築する柱延長作業とを交互に繰り返すようにしたこと
を特徴としている。The invention according to claim 1 is
A method for constructing a building for accommodating large-scale equipment, facilities, and the like, wherein after constructing a pillar of the building, a first step of constructing a roof frame on the pillar, A second step of suspending by a suspension means provided on the roof frame and installing at a predetermined position, and a third step of constructing an outer peripheral frame forming an outer periphery of the building, wherein in the first step When constructing the pillar, first, a temporary pillar of a certain length is formed, and a roof frame of the building is integrally provided on the temporary pillar, and then a part of the total length of the pillar is erected. Then, after that, a climbing operation for obtaining a reaction force on the pillar by jack-up means provided on the temporary pillar to climb the temporary pillar and the roof frame integrally, and the pillar below the climbed roof frame. Pillar extension work to extend Is characterized in that the repeated alternately.
【0005】請求項2に係る発明は、請求項1記載の建
屋の構築方法において、前記第一の工程の後に、前記第
一の工程で構築した屋根架構の下面に前記外周架構の一
部を先付けして前記柱と一体化し、しかる後に前記第二
の工程を行うことを特徴としている。According to a second aspect of the present invention, in the method for constructing a building according to the first aspect, after the first step, a part of the outer peripheral frame is attached to a lower surface of the roof frame constructed in the first step. It is characterized in that it is pre-attached and integrated with the pillar, and then the second step is performed.
【0006】[0006]
【作用】請求項1記載の発明では、第一の工程で建屋の
柱と屋根架構とを構築し、第二の工程で屋根架構に備え
た吊下手段で機器,設備を吊り込んでこれを定められた
位置に設置し、第三の工程で外周架構を構築することに
よって、建屋を構築する構成とした。このようにして、
建屋の柱と屋根架構を構築した時点で、外周架構の構築
に先立って機器,設備を設置するようにしたので、機
器,設備の試運転などを早期から行うことが可能とな
る。また、第一の工程において前記柱を構築するに際し
て、まず、仮設支柱の上部に建屋の屋根架構を設けた
後、本設の柱の全長のうちの一部を立設し、しかる後に
前記仮設支柱および屋根架構のクライミング作業と、柱
延長作業とを交互に繰り返す構成とした。これにより、
地上において屋根架構の構築作業を行うことができる。
また、屋根架構に例えばホイストクレーン等の揚重手段
を備えることによって、特に他の揚重機器等を地上に設
置することなく、建屋の施工を行うことが可能となる。According to the first aspect of the present invention, in the first step, the pillars and the roof frame of the building are constructed, and in the second step, the equipment and facilities are suspended by the suspension means provided on the roof frame, and this is suspended. The building was constructed by installing it at a predetermined position and constructing the outer frame in the third step. In this way,
When the pillars and the roof frame of the building are constructed, the equipment and facilities are installed prior to the construction of the outer frame, so that the test operation of the equipment and facilities can be performed from an early stage. Further, in constructing the pillar in the first step, first, a roof frame of a building is provided above the temporary pillar, then a part of the total length of the permanent pillar is erected, and then the temporary The construction was such that the climbing work for the columns and the roof frame and the column extension work were alternately repeated. This allows
Construction work of the roof frame can be performed on the ground.
In addition, by providing the roof frame with a lifting means such as a hoist crane, it is possible to construct the building without installing other lifting equipment or the like particularly on the ground.
【0007】請求項2記載の発明では、第一の工程の後
に、構築した屋根架構の下面に一定長の外周架構を先付
けして柱と一体化し、しかる後に第二の工程を行う構成
とした。これにより、先付けした外周架構によって、屋
根架構と柱とから構成される架構が補強されて強固なも
のとなり、第二の工程で機器や設備を吊り込むに際し
て、その荷重に抗することが可能となる。According to the second aspect of the present invention, after the first step, a fixed length outer peripheral frame is attached to the lower surface of the constructed roof frame to be integrated with the pillar, and then the second step is performed. . With this, the frame consisting of the roof frame and the pillars is reinforced by the pre-installed outer frame and becomes strong, and it is possible to withstand the load when suspending equipment and facilities in the second step. Become.
【0008】[0008]
【実施例】以下、本発明を図面に示す一実施例を参照し
て説明する。ここでは、例えば、火力発電所に備えるボ
イラーを収容するための建屋を構築する場合の実施例を
用いて説明する。図1は、本発明に係る建屋の構築方法
を適用して構築した建屋を示すものである。この図にお
いて、符号1は、ボイラー(機器)、2はボイラー1を
収容する建屋、3は建屋2を構成する柱、4は屋根架
構、5は建屋2の外周部をなす外周架構(図1(a)に
おいて斜線部で示した)を示している。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an embodiment shown in the drawings. Here, for example, an example in which a building for housing a boiler provided in a thermal power plant is constructed will be described. FIG. 1 shows a building constructed by applying the building construction method according to the present invention. In this figure, reference numeral 1 denotes a boiler (equipment), 2 denotes a building that houses the boiler 1, 3 denotes a pillar that forms the building 2, 4 denotes a roof frame, and 5 denotes an outer frame that forms an outer peripheral portion of the building 2 (FIG. (Indicated by the hatched portion in (a)).
【0009】図1に示すように、ボイラー1は、建屋2
の中央部に収容されており、支持台6上に設置された構
成となっている。As shown in FIG. 1, a boiler 1 includes a building 2
And is installed on the support 6.
【0010】建屋2を構成する柱3,3,…は、建屋2
の内方側において、ボイラー1の周囲四方に位置するよ
う配置されている。各柱3は、鉄筋コンクリート造で、
かつ断面視矩形の筒状をなしたボックス柱から形成され
ている。The pillars 3, 3,... Constituting the building 2 are
Are disposed on four sides around the boiler 1. Each pillar 3 is made of reinforced concrete,
It is formed from a box column having a rectangular tubular shape in cross section.
【0011】屋根架構4は、柱3,3,…上に支持され
て設けられ、柱3,3,…よりも水平方向外方に一定寸
法張り出した構成となっている。この屋根架構4は、鉄
骨造で、上弦材7と、下弦材8と、これらを連結する連
結部材9と、ラチス材10とがトラス状に組まれて形成
されている。The roof frame 4 is provided so as to be supported on the columns 3, 3,..., And projects a certain dimension outwardly in the horizontal direction from the columns 3, 3,. The roof frame 4 is made of steel, and is formed by assembling an upper chord material 7, a lower chord material 8, a connecting member 9 for connecting these members, and a lattice material 10 in a truss shape.
【0012】外周架構5は、柱3,3,…の外周側を囲
うように形成されており、各柱3の外周面および屋根架
構4の張り出し部4aの下面に接合されている。この外
周架構5は、多数のブロック状の外周モジュール11か
ら構成されている。各外周モジュール11は、鉄骨造
で、外周架構5の柱を構成する鉛直部材12と、梁を構
成する水平部材13と、これらを補強するブレース材1
4とから形成されている。The outer peripheral frame 5 is formed so as to surround the outer peripheral side of the columns 3, 3,... And is joined to the outer peripheral surface of each column 3 and the lower surface of the overhang portion 4a of the roof frame 4. The outer frame 5 is composed of a number of block-shaped outer modules 11. Each of the outer peripheral modules 11 is made of a steel frame and has a vertical member 12 that forms a column of the outer frame 5, a horizontal member 13 that forms a beam, and a brace material 1 that reinforces these members.
4.
【0013】次に、上記のような構成からなる建屋2の
構築方法について、図1ないし図8を参照して説明す
る。Next, a method of constructing the building 2 having the above configuration will be described with reference to FIGS.
【0014】[第一の工程]まず、図2に示すように、
地上において、各柱3を立設すべき位置に、仮設支柱2
0を立設する。各仮設支柱20は、鉄骨造で、上下方向
に一定長を有しており、かつ構築すべき前記柱3内に収
納可能な外形断面寸法を有している。そして、各仮設支
柱20には、図示しないクライミング機構(ジャッキア
ップ手段)が備えられ、柱3に反力をとって上下方向に
昇降できるようになっている。[First Step] First, as shown in FIG.
On the ground, place the temporary columns 2 at the positions where the columns 3 should be erected.
0 is erected. Each temporary support column 20 is made of steel, has a certain length in the vertical direction, and has an outer cross-sectional dimension that can be stored in the column 3 to be constructed. Each temporary support column 20 is provided with a climbing mechanism (jack-up means) (not shown) so that the temporary support column 20 can move up and down in a vertical direction by applying a reaction force to the column 3.
【0015】次いで、地上において屋根架構4を組み立
て、これを仮設支柱20,20,…に接合して一体化す
る。Next, the roof frame 4 is assembled on the ground, and this is joined to the temporary supports 20, 20,.
【0016】続いて、図3に示すように、各仮設支柱2
0の外周部に型枠(図示なし)を組み立ててここに鉄筋
を配筋し、さらにコンクリートを打設することにより、
一定長の柱3,3,…を形成する。このときに用いる型
枠(図示なし)としては、スリップフォーム工法用の型
枠(図示なし)が好適である。Subsequently, as shown in FIG.
By assembling a formwork (not shown) on the outer periphery of No. 0, arranging reinforcing steel there, and further placing concrete,
The columns 3, 3,... Of a certain length are formed. As a mold (not shown) used at this time, a mold (not shown) for a slip foam method is suitable.
【0017】また、屋根架構4の上面にはジブクレーン
(吊下手段)21を、下面には揚重機構(吊下手段)2
2をそれぞれ設置する。揚重機構22は、水平方向に移
動自在で、かつ資材等を上下方向に搬送できるホイスト
クレーン等から構成されている。A jib crane (suspension means) 21 is provided on the upper surface of the roof frame 4 and a lifting mechanism (suspension means) 2 is provided on the lower surface.
2 is installed respectively. The lifting mechanism 22 is composed of a hoist crane or the like that can move in the horizontal direction and can transport materials and the like in the vertical direction.
【0018】そして、各仮設支柱20のコンクリートが
硬化した後、各仮設支柱20に備えたクライミング機構
(図示なし)を同時に作動させて、各仮設支柱20を一
斉にクライミングさせる。すると、これにより、仮設支
柱20,20,…と一体化された屋根架構4がジャッキ
アップされて上方にクライミングすることになる。After the concrete of each temporary support 20 has hardened, the climbing mechanism (not shown) provided for each temporary support 20 is simultaneously operated to simultaneously climb each temporary support 20. Then, the roof frame 4 integrated with the temporary supports 20, 20,... Is jacked up and climbs upward.
【0019】次いで、この後、先に形成した各柱3上に
前記と同様にして柱3を一定長形成してこれを延長する
柱延長作業と、屋根架構4のクライミング作業とを交互
に繰り返していき、各柱3を所定長まで構築する。な
お、この時、柱延長作業においては、型枠を上方へスラ
イドさせていくスリップフォーム工法を適用する。ま
た、鉄筋等の必要な資材は、前記ジブクレーン21およ
び揚重機構22によって揚重するようにする。Then, after that, the column extension work for forming the column 3 to a predetermined length on each of the columns 3 previously formed and extending the same and the climbing operation of the roof frame 4 are alternately repeated. Each pillar 3 is constructed to a predetermined length. At this time, in the column extension work, a slip form method in which the form is slid upward is applied. Necessary materials such as reinforcing bars are lifted by the jib crane 21 and the lifting mechanism 22.
【0020】図4に示すように、このようにして柱3,
3,…を所定長まで構築した後には、ジブクレーン21
で各仮設支柱20(図3参照)を解体撤去して、屋根架
構4を柱3,3,…上に載置・固定する。このようにし
て構築された柱3と屋根架構4とから、ボイラー1(図
1参照)を搬入するときにその荷重を支持するためのコ
ア架構23が構成されたことになる。As shown in FIG.
After constructing 3, ... to a predetermined length, the jib crane 21
Then, the temporary columns 20 (see FIG. 3) are dismantled and removed, and the roof frame 4 is placed and fixed on the columns 3, 3,. The pillar 3 and the roof frame 4 constructed in this manner constitute a core frame 23 for supporting the load when the boiler 1 (see FIG. 1) is carried in.
【0021】続いて、外周架構4の相対向する側面A,
B側において、最上部に位置すべき外周モジュール11
aを揚重機構22で吊り上げ、図5に示すように柱3の
外周面および屋根架構4の張り出し部4aの下面に接合
して取り付ける。次いで、取り付けた外周モジュール1
1a,11aと直交する側面C,D側において、外周モ
ジュール11b,11bを、前記と同様にして吊り上げ
て柱3,3間に取り付ける。これにより、コア架構23
の柱3と屋根架構4との接合部が、外周モジュール11
a,11a,11b,11bによって補強されたことに
なる。Subsequently, opposed side surfaces A,
On the B side, the outer peripheral module 11 to be positioned at the top
a is lifted by the lifting mechanism 22 and attached to the outer peripheral surface of the pillar 3 and the lower surface of the overhang portion 4a of the roof frame 4 as shown in FIG. Next, the attached outer peripheral module 1
On the side surfaces C and D orthogonal to 1a and 11a, the outer peripheral modules 11b and 11b are lifted and attached between the columns 3 and 3 in the same manner as described above. Thereby, the core frame 23
The joint between the pillar 3 and the roof frame 4 is the outer peripheral module 11
a, 11a, 11b, and 11b.
【0022】[第二の工程]次に、このようにして構築
したコア架構23の内方に、ボイラー1を搬入・設置す
る。これには、まず、図6に示すように、側面B側にお
いて、先に取り付けた外周モジュール11aの下方に、
外周モジュール11,11,…を上方から下方に向けて
順次取り付ける。ただし、これは、構築すべき建屋2の
敷地が狭隘で、側面B側からは資材を搬入することがで
きない場合にのみ行う。[Second Step] Next, the boiler 1 is loaded and installed inside the core frame 23 constructed as described above. First, as shown in FIG. 6, on the side B, below the outer module 11a attached earlier,
Are sequentially mounted from top to bottom. However, this is performed only when the site of the building 2 to be constructed is narrow and it is not possible to carry in materials from the side B side.
【0023】続いて、設置すべきボイラー1の上半部1
aを移動台車24上に搭載し、これを側面A側から図中
矢印(イ)方向に移動させて建屋2内の所定の位置まで
搬入する。そして、このボイラー1の上半部1aを、屋
根架構4に備えた揚重機構(図示なし)で吊り上げて保
持する。Subsequently, the upper half 1 of the boiler 1 to be installed
a is mounted on the movable trolley 24, and is moved from the side A to the predetermined position in the building 2 by moving it in the direction of the arrow (a) in the figure. Then, the upper half 1a of the boiler 1 is lifted and held by a lifting mechanism (not shown) provided on the roof frame 4.
【0024】次いで、図7に示すように、ボイラー1の
下半部1bを、同様にして側面A側から建屋2内の所定
位置まで移動台車24で搬入する。そして、吊り上げて
いたボイラー1の上半部1aを下降させて下半部1bに
当接させた後、上半部1aと下半部1bとを溶接して一
体化する。この時、溶接時の防風のため、ボイラー1の
周囲には、養生シート25を張設する。この後、一体化
したボイラー1を揚重機構(図示なし)で吊り上げてお
いて、その下方から移動台車24を引き出す。そして、
図8に示すように、ボイラー1を下降させて支持台6上
にボイラー1を載置・固定する。Next, as shown in FIG. 7, the lower half 1b of the boiler 1 is carried in a similar manner from the side A to a predetermined position in the building 2 by the movable carriage 24. Then, the upper half 1a of the boiler 1 that has been lifted is lowered and brought into contact with the lower half 1b, and then the upper half 1a and the lower half 1b are welded and integrated. At this time, a curing sheet 25 is stretched around the boiler 1 to prevent wind during welding. Thereafter, the integrated boiler 1 is lifted by a lifting mechanism (not shown), and the movable cart 24 is pulled out from below. And
As shown in FIG. 8, the boiler 1 is lowered to place and fix the boiler 1 on the support base 6.
【0025】[第三の工程]このようにしてボイラー1
を設置した後、外周架構5を構築する。側面C,D側に
おいて、それぞれ、外周モジュール11,11,…を順
次下方から上方に向けて揚重機構22で取り付けてい
く。そして最後に、同様にして外周モジュール11,1
1,…を側面A側に取り付けていく。このようにして、
図1に示したように、外周架構5の構築が完了した後、
揚重機構22を解体,撤去することによって、建屋2の
構築が完了する。[Third Step] Thus, the boiler 1
After the installation, the outer frame 5 is constructed. On the side surfaces C and D, the outer peripheral modules 11, 11,... Are sequentially mounted upward from below by the lifting mechanism 22. And finally, in the same manner, the outer peripheral modules 11, 1
Are attached to the side A side. In this way,
As shown in FIG. 1, after the construction of the outer frame 5 is completed,
By dismantling and removing the lifting mechanism 22, the construction of the building 2 is completed.
【0026】上述した建屋2の構築方法では、第一の工
程で柱3と屋根架構4とを構築してコア架構23を形成
し、第二の工程でコア架構23にボイラー1を吊り込ん
でこれを定められた位置に設置し、第三の工程で外周架
構5を構築することによって、建屋2を構築する構成と
した。このようにして、建屋2の柱3と屋根架構4とを
構築してコア架構23を構築した時点で、外周架構5の
構築に先立ってボイラー1を設置するようにしたので、
外周架構5の構築作業と並行してボイラー1の試運転等
を行うことができ、これによってボイラー1の運転開始
を早期化することが可能となる。In the construction method of the building 2 described above, the pillar 3 and the roof frame 4 are constructed in the first step to form the core frame 23, and the boiler 1 is suspended in the core frame 23 in the second step. The building 2 was constructed by setting this at a predetermined position and constructing the outer frame 5 in the third step. As described above, when the pillar 3 and the roof frame 4 of the building 2 were constructed and the core frame 23 was constructed, the boiler 1 was installed prior to the construction of the outer frame 5.
A trial run of the boiler 1 and the like can be performed in parallel with the construction work of the outer peripheral frame 5, whereby the start of operation of the boiler 1 can be accelerated.
【0027】また、第一の工程でコア架構23を構築し
た後に、屋根架構4の下面に外周架構5の上層部を構成
する外周モジュール11a,11bを先付けする構成と
した。これにより、先付けした外周モジュール11a,
11bをによってコア架構23が強化され、第二の工程
でボイラー1を吊り込むに際して、その荷重に抗するこ
とが可能となる。この結果、ボイラー1を吊り込むため
の剛性確保のためだけに設置する仮設の補強部材を最小
限とすることができ、これとともに屋根架構4を構成す
る部材の断面を最小限まで小さくしてコストを抑さえる
ことが可能となる。After the core frame 23 is constructed in the first step, the outer modules 11a and 11b constituting the upper layer of the outer frame 5 are attached to the lower surface of the roof frame 4 in advance. As a result, the outer peripheral modules 11a,
11b strengthens the core frame 23, and when the boiler 1 is suspended in the second step, it becomes possible to withstand the load. As a result, it is possible to minimize the number of temporary reinforcing members installed only for securing the rigidity for suspending the boiler 1, and to reduce the cross section of the members constituting the roof frame 4 to a minimum, thereby reducing costs. Can be suppressed.
【0028】さらに、第一の工程において柱3を構築す
るに際して、まず、仮設支柱20の上部に建屋2の屋根
架構4を設けた後、柱3の全長のうちの一部を立設し、
しかる後に屋根架構4のクライミング作業と、柱3の延
長作業とを交互に繰り返して柱3を所定長まで構築する
構成とした。これにより、地上において屋根架構4の構
築作業を行うことができ、高所作業を削減して作業の安
全性を大幅に向上させることができる。また、屋根架構
4にジブクレーン21,揚重機構22を備える構成とし
たので、特に他の揚重機器等を地上に設置することなく
建屋2の施工を行うことができ、従来の工法では建屋2
を構築することができなかった狭隘な敷地であっても建
屋2を構築することが可能となる。Further, in constructing the pillar 3 in the first step, first, the roof frame 4 of the building 2 is provided on the temporary support 20 and then a part of the entire length of the pillar 3 is erected.
Thereafter, the climbing work of the roof frame 4 and the work of extending the pillar 3 are alternately repeated to construct the pillar 3 to a predetermined length. Thereby, the construction work of the roof frame 4 can be performed on the ground, and the work at high places can be reduced, and the safety of the work can be greatly improved. Further, since the roof frame 4 is provided with the jib crane 21 and the lifting mechanism 22, the building 2 can be constructed without installing other lifting equipment and the like particularly on the ground.
It is possible to construct the building 2 even in a narrow site where the construction could not be performed.
【0029】加えて、外周架構5を多数の外周モジュー
ル11から構成するようにしたので、この点からも高所
作業を削減して作業の安全性を向上させることができ
る。In addition, since the outer peripheral frame 5 is composed of a large number of outer peripheral modules 11, work from high places can be reduced and the safety of the work can be improved.
【0030】また、柱3をボックス柱からなる構成と
し、さらに仮設支柱20を柱3の内方に収納した状態で
クライミングさせる構成としたので、構築すべき柱3の
周囲に十分なスペースがない場合にも柱3を構築するこ
とが可能となる。さらに、柱3を構築するに際して、ス
リップフォーム工法を適用するようにしたので、この点
からも作業エリアが狭くても作業を円滑に進めることが
可能となる。Further, since the pillar 3 is constituted by a box pillar and the temporary support 20 is climbed while being housed inside the pillar 3, there is not enough space around the pillar 3 to be constructed. In this case, the pillar 3 can be constructed. Further, when the pillar 3 is constructed, the slip-form method is applied, so that the work can be performed smoothly even in a narrow work area.
【0031】なお、上記実施例において、仮設支柱20
を柱3の内方に収納した状態でクライミングさせる構成
としたが、もちろん、柱3の外周面に沿って仮設支柱2
0をクライミングさせる構成としてもよい。また、柱3
を建屋2の内方に位置する構成としたが、柱3が建屋2
の四隅に位置する構成であっても、上記と同様の効果を
得ることが可能である。さらには、建屋2の用途は上記
に限定するものではなく、ボイラー1以外の機器や設備
を収納する構成としてもよいのは言うまでもない。In the above embodiment, the temporary support 20
Is climbed in a state in which it is stored inside the pillar 3, but, of course, the temporary support 2 is extended along the outer peripheral surface of the pillar 3.
0 may be configured to be climbed. Pillar 3
Is located inside the building 2, but the pillar 3 is
The same effect as described above can be obtained even with the configuration located at the four corners. Further, the use of the building 2 is not limited to the above, and it goes without saying that a configuration for storing equipment and facilities other than the boiler 1 may be used.
【0032】[0032]
【発明の効果】以上説明したように、請求項1に係る建
屋の構築方法によれば、第一の工程で建屋の柱と屋根架
構とを構築し、第二の工程で機器,設備を吊下手段で吊
り込んで定められた位置に設置し、第三の工程で外周架
構を構築することによって、建屋を構築する構成とし
た。これにより、建屋の柱と屋根架構を構築した時点
で、外周架構の構築に先立って機器,設備を設置するよ
うにしたので、外周架構の構築作業と並行して機器,設
備の試運転等を行うことができ、これによって機器,設
備の運転開始を早期化することが可能となる。また、第
一の工程において前記柱を構築するに際して、まず、仮
設支柱の上部に建屋の屋根架構を設けた後、柱の全長の
うちの一部を立設し、しかる後に仮設支柱および屋根架
構のクライミング作業と、柱延長作業とを交互に繰り返
す構成とした。これにより、地上において屋根架構の構
築作業を行うことができ、高所作業を大幅に削減して作
業の安全性を大幅に向上させることができる。また、屋
根架構に例えばホイストクレーン等の揚重手段を備える
ことによって、特に他の揚重機器等を地上に設置するこ
となく建屋の施工を行うことができ、従来の工法では建
屋を構築することができなかった狭隘な敷地であっても
建屋を構築することが可能となる。As described above, according to the building construction method of the first aspect, the pillars and the roof frame of the building are constructed in the first step, and the equipment and facilities are suspended in the second step. The building was constructed by suspending it with the lower means and installing it at a predetermined position, and constructing the outer frame in the third step. As a result, when the pillars and the roof frame of the building are constructed, the equipment and facilities are installed prior to the construction of the outer frame, so that the equipment and facilities are tested in parallel with the construction of the outer frame. As a result, the operation of the equipment and the equipment can be started earlier. Further, in constructing the pillar in the first step, first, a roof frame of the building is provided above the temporary pillar, then a part of the entire length of the pillar is erected, and then the temporary pillar and the roof frame are provided. The climbing work and the pillar extension work are alternately repeated. Thereby, the construction work of the roof frame can be performed on the ground, and the work in high places can be greatly reduced, and the safety of the work can be greatly improved. In addition, by providing lifting means such as a hoist crane on the roof frame, it is possible to construct the building without installing other lifting equipment, etc., especially on the ground. It is possible to build a building even on a narrow site that could not be completed.
【0033】請求項2に係る建屋の構築方法によれば、
第一の工程の後に、構築した屋根架構の下面に一定長の
外周架構を先付けし、しかる後に第二の工程を行う構成
とした。これにより、先付けした外周架構によって屋根
架構と柱とから構成される架構が強固なものとなり、第
二の工程で機器や設備を吊り込むに際して、その荷重に
抗することが可能となる。この結果、機器や設備を吊り
込むための剛性確保のためだけに設置する仮設の補強部
材を最小限とすることができ、これとともに屋根架構等
を構成する部材の断面を最小限まで小さくしてコストを
抑さえることが可能となる。According to the building construction method of the second aspect,
After the first step, a fixed-length outer peripheral frame was attached to the lower surface of the constructed roof frame, and then the second step was performed. Thus, the frame composed of the roof frame and the pillars is strengthened by the attached outer frame, and it becomes possible to withstand the load when suspending equipment and facilities in the second step. As a result, it is possible to minimize the number of temporary reinforcing members installed only for securing rigidity for suspending equipment and facilities, and to reduce the cross section of members constituting the roof frame and the like to the minimum. Costs can be reduced.
【図1】本発明に係る建屋の構築方法を適用して構築し
た建屋の一例を示す平面図および側面図である。FIG. 1 is a plan view and a side view showing an example of a building constructed by applying a building construction method according to the present invention.
【図2】前記建屋の構築方法の工程を示す図であって、
仮設支柱と屋根架構とを構築した状態を示す平面図およ
び正面図である。FIG. 2 is a diagram showing steps of the building construction method,
It is the top view and front view which show the state which constructed the temporary support | pillar and the roof frame.
【図3】同、柱を一定長構築し、仮設支柱と屋根架構と
リフトアップした状態を示す平面図および正面図であ
る。3A and 3B are a plan view and a front view, respectively, showing a state in which a column is constructed to have a fixed length, and a temporary column and a roof frame are lifted up.
【図4】同、柱の全長の構築が完了し、最上部の外周架
構を取り付けている状態を示す平面図および側面図であ
る。FIG. 4 is a plan view and a side view showing a state in which the construction of the full length of the pillar is completed and the outermost frame at the top is attached.
【図5】同、前記最上部の他の外周架構を取り付けてい
る状態を示す平面図および正面図である。FIGS. 5A and 5B are a plan view and a front view showing a state in which another outer peripheral frame of the uppermost portion is attached.
【図6】同、建屋に収容する機器の上半部を搬入した状
態を示す平面図および側面図である。FIG. 6 is a plan view and a side view showing a state in which the upper half of the equipment housed in the building is carried in.
【図7】同、前記機器の下半部を搬入した状態を示す平
面図および側面図である。FIG. 7 is a plan view and a side view showing a state where the lower half of the device is carried in the same.
【図8】同、前記機器の設置が完了した状態を示す平面
図および正面図である。FIG. 8 is a plan view and a front view showing a state where the installation of the device is completed.
1 ボイラー(機器) 2 建屋 3 柱 4 屋根架構 5 外周架構 20 仮設支柱 DESCRIPTION OF SYMBOLS 1 Boiler (equipment) 2 Building 3 Column 4 Roof frame 5 Outer frame 20 Temporary support
───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−185124(JP,A) 特開 平6−158733(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04H 5/02 E04B 1/35 ────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-6-185124 (JP, A) JP-A-6-158733 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E04H 5/02 E04B 1/35
Claims (2)
築方法であって、前記建屋の柱を構築した後、該柱上に
屋根架構を構築する第一の工程と、収容すべき前記機
器,設備を前記屋根架構に備えた吊下手段で吊り込んで
定められた位置に設置する第二の工程と、前記建屋の外
周をなす外周架構を構築する第三の工程とからなり、 前記第一の工程において前記柱を構築するに際しては、
まず、一定長の仮設支柱を形成して、該仮設支柱の上部
に前記建屋の屋根架構を一体に設けた後、前記柱の全長
のうちの一部を立設し、しかる後に、前記仮設支柱に備
えたジャッキアップ手段で前記柱に反力を得て前記仮設
支柱と屋根架構とを一体にクライミングさせるクライミ
ング作業と、クライミングさせた該屋根架構の下方にお
いて前記柱を延長構築する柱延長作業とを交互に繰り返
すようにしたことを特徴とする建屋の構築方法。1. A method for constructing a building for accommodating large-scale equipment, facilities, and the like, comprising: constructing a pillar of the building, and then constructing a roof frame on the pillar; A second step of suspending the equipment and facilities by a suspending means provided on the roof frame and installing the apparatus at a predetermined position, and a third step of constructing an outer frame constituting the outer periphery of the building, In constructing the pillar in the first step,
First, a temporary support column having a fixed length is formed, and a roof frame of the building is integrally provided on the temporary support column. Then, a part of the total length of the column is erected, and then the temporary support column is provided. A climbing operation in which the temporary support and the roof frame are integrally climbed by obtaining a reaction force on the column with jack-up means provided in; and a column extension operation for extending and building the column below the climbed roof frame. The building construction method characterized by alternately repeating.
て、前記第一の工程の後に、前記第一の工程で構築した
屋根架構の下面に前記外周架構の一部を先付けして前記
柱と一体化し、しかる後に前記第二の工程を行うことを
特徴とする建屋の構築方法。2. The method for building a building according to claim 1, wherein after the first step, a part of the outer peripheral frame is pre-attached to a lower surface of the roof frame constructed in the first step, and the column is formed. A method for constructing a building, comprising integrating and then performing the second step.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24168194A JP3225456B2 (en) | 1994-10-05 | 1994-10-05 | How to build a building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24168194A JP3225456B2 (en) | 1994-10-05 | 1994-10-05 | How to build a building |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08105229A JPH08105229A (en) | 1996-04-23 |
JP3225456B2 true JP3225456B2 (en) | 2001-11-05 |
Family
ID=17077943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24168194A Expired - Fee Related JP3225456B2 (en) | 1994-10-05 | 1994-10-05 | How to build a building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3225456B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6503673B2 (en) | 2000-10-24 | 2003-01-07 | Mitsubishi Paper Mills Limited | Phthalocyanine composition, process for production thereof, and electrophotographic photoreceptor |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1162244A (en) * | 1997-08-25 | 1999-03-05 | Shimizu Corp | Frame for frame building and frame building method using the same |
CN105735688A (en) * | 2016-03-07 | 2016-07-06 | 苏州保酚环境科技有限公司 | Reinforced type steel-structure supporting frame used for carrying filtering bag dust remover |
CN109399432B (en) * | 2018-11-23 | 2019-12-03 | 燕山大学 | A kind of hoistway job platform that climbs certainly |
-
1994
- 1994-10-05 JP JP24168194A patent/JP3225456B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6503673B2 (en) | 2000-10-24 | 2003-01-07 | Mitsubishi Paper Mills Limited | Phthalocyanine composition, process for production thereof, and electrophotographic photoreceptor |
Also Published As
Publication number | Publication date |
---|---|
JPH08105229A (en) | 1996-04-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0487516B1 (en) | Construction apparatus and construction method | |
JP3225456B2 (en) | How to build a building | |
JP3446153B2 (en) | Construction method of building | |
JP6391134B2 (en) | Dismantling method and dismantling system | |
JP2957328B2 (en) | Peripheral holding self-elevating construction method | |
JP3225455B2 (en) | How to build a building | |
JP3445419B2 (en) | Double slab construction method | |
CN218091933U (en) | Device for integrally lifting elevator shaft frame body | |
JP2761527B2 (en) | How to build structures | |
JP3200788B2 (en) | Installation structure of the frame of the external curing coating | |
JP3239154B2 (en) | Lift-up device for all-weather temporary roof | |
JP3060333B2 (en) | Construction method of building frame | |
JP2513376B2 (en) | How to build a building | |
JP2761528B2 (en) | How to build structures | |
JP2718188B2 (en) | Building exterior wall mounting method | |
JP3368483B2 (en) | Bridge pier construction method | |
JP2884396B2 (en) | Construction method of building structure and lifting device of building structure | |
JP2939752B2 (en) | Lift-up method in which an outer wall plate is attached to the floor plate | |
JP3055076B2 (en) | Construction method of building frame | |
JP2884398B2 (en) | Construction method of building structure and lifting device of building structure | |
JP2843042B2 (en) | Steel framing unit scaffolding method | |
JP2600443B2 (en) | How to build high-rise buildings | |
JP2761526B2 (en) | How to build structures | |
JP2946372B2 (en) | Construction method of structure | |
JPH0335468B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20010724 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110831 Year of fee payment: 10 |
|
LAPS | Cancellation because of no payment of annual fees |