[go: up one dir, main page]

JP2640542B2 - Waterproof shaft construction method - Google Patents

Waterproof shaft construction method

Info

Publication number
JP2640542B2
JP2640542B2 JP27936189A JP27936189A JP2640542B2 JP 2640542 B2 JP2640542 B2 JP 2640542B2 JP 27936189 A JP27936189 A JP 27936189A JP 27936189 A JP27936189 A JP 27936189A JP 2640542 B2 JP2640542 B2 JP 2640542B2
Authority
JP
Japan
Prior art keywords
shaft
water
ground
side wall
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP27936189A
Other languages
Japanese (ja)
Other versions
JPH03140594A (en
Inventor
孝行 阿比留
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHINGIJUTSU KOEI KK
Original Assignee
SHINGIJUTSU KOEI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHINGIJUTSU KOEI KK filed Critical SHINGIJUTSU KOEI KK
Priority to JP27936189A priority Critical patent/JP2640542B2/en
Publication of JPH03140594A publication Critical patent/JPH03140594A/en
Application granted granted Critical
Publication of JP2640542B2 publication Critical patent/JP2640542B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、土木建設工事現場等において地盤に止水性
の立坑を築造する工法に関する。
Description: TECHNICAL FIELD The present invention relates to a method of constructing a water-blocking shaft in the ground at a civil engineering construction site or the like.

(従来の技術) 土木建設工事現場等において地盤に止水性立坑を築造
する場合、工事現場が狭くて大型の鋼矢板打設機等が搬
入できないことが多かった。
(Conventional technology) When constructing a water-blocking shaft on the ground at a civil engineering construction site or the like, the construction site is often narrow and a large steel sheet pile driving machine or the like cannot be carried in.

帯水地盤では地盤改良を併用したライナー式立坑が採
用されているが、この場合一般的な立坑施工費の2〜3
倍の費用を要すと共に、隣接構造物へ悪影響を及ぼすこ
とが多く、これに対する補償問題等も発生している。
In the aquifer ground, a liner-type shaft combined with ground improvement has been adopted.
In addition to the double cost, it often has an adverse effect on adjacent structures, and there is a compensation problem for this.

このように従来の立坑築造工法では、狭い場所,帯水
地盤,湧水による周辺地盤沈下が発生している場所等に
おいては立坑築造が極めて困難であったり、不可能であ
った。また従来の立坑築造工法で立坑築造できるとして
も施工費が非常に高かったり、工事現場周辺地域へ悪影
響を及ぼすことが多かった。
As described above, in the conventional shaft construction method, it is extremely difficult or impossible to construct a shaft in a narrow place, in an aquifer, or in a place where the surrounding ground subsidence occurs due to a spring. Even if the shaft can be built using the conventional shaft construction method, the construction cost is extremely high and often adversely affects the area around the construction site.

(発明が解決しようとする課題) 本発明が解決しようとする課題は、従来の立坑築造工
法に改良を加え、狭い場所や帯水地盤等においても立坑
築造が可能で、施工費が安く、工事現場周辺地域へ悪影
響を及ぼすこともない止水性立坑築造工法を提供するこ
とにある。
(Problems to be Solved by the Invention) The problem to be solved by the present invention is to improve the conventional shaft construction method so that the shaft can be built even in a narrow place or in aquifer ground, and the construction cost is low. It is an object of the present invention to provide a water-blocking shaft construction method that does not adversely affect the surrounding area of the site.

(課題を解決するための手段) かかる課題を解決した本発明の要旨は、 1)短い円筒形状をした先端ヘッドの内部の隔壁に、先
端にウイングビットを備え且つ中空パイプを回転軸とす
るスパイラルドリルと、高圧水噴射ノズルと、注水管
と、高圧エア注入管とを取り付けたものを用意し、同先
端ヘッドの下部を地中に向けて設置し、同先端ヘッドに
は所定長さで円筒状の側壁を載荷して同先端ヘッドのウ
イングビットの回転及び高圧水噴射ノズルからの噴射水
で地盤を掘削し且つ同スパイラルドリルで排泥しながら
進行し、同側壁の上部には他の側壁を順次継ぎ足すこと
を繰り返して所定深度まで立坑を形成した後、同スパイ
ラルドリルの回転軸の中空パイプ内を経由して同立坑底
部に硬化剤を注入打設し、その後同先端ヘッドを撤収し
て同硬化剤を硬化させることを特徴とする止水性立坑築
造工法 2)地中に一端を固定したグランドアンカー引張材を強
く把持し、反力拠点として側壁上部に圧力を加えること
を特徴とする請求項1記載の止水性立坑築造工法 3)コンクリートを硬化剤としたことを特徴とする請求
項1または2記載の止水性立坑築造工法 4)コンクリートまたは合成樹脂を材料とする側壁を使
用したことを特徴とする請求項1〜3何れかに記載の止
水性立坑築造工法にある。
(Means for Solving the Problems) The gist of the present invention that has solved the problems is as follows: 1) A spiral having a short pipe having a wing bit at a tip in a partition inside the tip head and a hollow pipe as a rotation axis. Prepare a drill, a high-pressure water injection nozzle, a water injection pipe, and a high-pressure air injection pipe, and set the lower end of the tip head toward the underground. The ground is excavated with the rotation of the wing bit of the head and the jet water from the high-pressure water jet nozzle, and the mud is advanced with the spiral drill. To form a shaft up to a predetermined depth, then inject a hardening agent into the shaft bottom through the hollow pipe of the rotary shaft of the spiral drill, and then withdraw the tip head hand A method for constructing a water-blocking shaft by hardening a hardener 2) Strongly gripping a ground anchor tensile material having one end fixed in the ground, and applying pressure to an upper portion of a side wall as a reaction force base. 3. The water-blocking shaft construction method according to 1), 3) concrete is used as a hardening agent, 3) the water-blocking shaft construction method according to claim 1 or 2, 4) a side wall made of concrete or synthetic resin is used. The watertight shaft construction method according to any one of claims 1 to 3.

(作用) 本発明では、掘削装置及び排泥装置を取り付けた円筒
状の先端ヘッドに円筒状の側壁を載荷し、同側壁の重量
を利用して先端ヘッドの掘削装置で地盤を掘削し且つ排
泥装置で排泥しながら進行していくようになっている。
そして先端ヘッドの進行に従って側壁を順次継ぎ足して
所定深度まで立坑を形成していく。その後、スパイラル
ドリルの回転軸の中空パイプ内を経由して立坑底部にコ
ンクリート等の硬化剤を注入打設し、次に先端ヘッドを
撤収して硬化剤を硬化させて止水性立坑を完成させるよ
うになっている。
(Operation) In the present invention, a cylindrical side wall is loaded on a cylindrical tip head to which a digging device and a mud discharging device are attached, and the ground is digged and evacuated by the digging device of the tip head utilizing the weight of the side wall. It progresses while discharging mud with a mud device.
Then, as the tip head advances, the side walls are sequentially added to form a shaft to a predetermined depth. After that, a hardening agent such as concrete is poured and poured into the shaft bottom through the hollow pipe of the rotary shaft of the spiral drill, and then the tip head is withdrawn and the hardening agent is hardened to complete the water stop shaft. It has become.

本発明では、先端ヘッドで地中を掘削して行く際に先
端ヘッドに載荷した側壁の重量を利用するだけではな
く、立坑築造現場に予め設置したグランドアンカー引張
材を強く把持し反力拠点として側壁上部に圧力を加える
こともある。
In the present invention, when excavating underground with the tip head, not only utilizes the weight of the side wall loaded on the tip head, but also strongly grips the ground anchor tensile material previously installed on the shaft construction site as a reaction force base Pressure may be applied to the upper part of the side wall.

以上のように本発明では、従来のように大型の機械を
必要としないので工事現場が狭くても立坑築造を支障な
く行うことができ、施工費が高くなることもない。
As described above, according to the present invention, a large machine is not required unlike the related art, so that even if the construction site is narrow, the shaft can be erected without any trouble, and the construction cost does not increase.

本発明では先端ヘッドに設けた高圧水噴射ノズル,ウ
イングビットによって地盤の掘削を行ないスパイラルド
リルで排泥を行うので、強い打撃・駆動等を発生するこ
とがなく、工事現場周辺地域に悪影響を及ぼすこともな
い。
In the present invention, since the ground is excavated by the high-pressure water jet nozzle and the wing bit provided in the tip head and the mud is discharged by the spiral drill, strong hitting and driving are not generated, which adversely affects the area around the construction site. Not even.

(実施例) 以下、本発明の実施例を図面に基づいて説明する。(Example) Hereinafter, an example of the present invention will be described with reference to the drawings.

第1図は実施例を示す一部切欠断面図、第2図は同工
程説明図、第3図は同コンクリート側壁の一部切欠斜視
図である。
1 is a partially cutaway sectional view showing an embodiment, FIG. 2 is an explanatory view of the same process, and FIG. 3 is a partially cutaway perspective view of the concrete side wall.

第4図、第5図は他の実施例のコンクリート側壁の一
部切欠斜視図である。
4 and 5 are partially cutaway perspective views of a concrete side wall according to another embodiment.

本実施例においては、先端にウイングビット(1)を
備え、中空パイプ(2)を回転軸とするスパイラルドリ
ル(3)、高圧水噴射ノズル(4),注水管(5),及
び高圧エア注入管(6)を円筒状の先端ヘッド(7)内
部の隔壁(8)に設けたものを使用する。そして先端ヘ
ッド(7)の下部を地中に向けて設置し、先端ヘッド
(7)にはジャッキ(9)と反力板(10)を介して円筒
状のコンクリート側壁(11)を載荷する。更にコンクリ
ート側壁(11)上部には、地中に一端を固定したグラン
ドアンカー引張材(12)を強く把持し反力拠点としてジ
ャッキ(20)で圧力を加えるようになっている。
In the present embodiment, a spiral drill (3) having a wing bit (1) at the tip and a hollow pipe (2) as a rotation axis, a high-pressure water injection nozzle (4), a water injection pipe (5), and high-pressure air injection are provided. A pipe (6) provided on a partition (8) inside a cylindrical tip head (7) is used. Then, the lower part of the tip head (7) is installed facing the ground, and a cylindrical concrete side wall (11) is loaded on the tip head (7) via a jack (9) and a reaction plate (10). Further, on the upper part of the concrete side wall (11), a ground anchor tension member (12), one end of which is fixed in the ground, is strongly grasped and pressure is applied by a jack (20) as a reaction force base.

このような状態で先端ヘッド(7)のウイングビット
(1)の回転及び高圧水噴射ノズル(4)からの噴射水
で地盤(13)を掘削し、且つスパイラルドリル(3)で
排泥しながら進行し、進行に応じてコンクリート側壁
(11)の上部には他のコンクリート側壁(11)を順次継
ぎ足して所定深度まで立坑(14)を形成していく。その
後スパイラルドリル(3)の回転軸の中空パイプ(2)
内を経由して立坑(14)底部にコンクリート(15)等の
硬化剤を注入打設する。次に先端ヘッド(7)を撤収し
てコンクリート(15)を硬化させて止水性立坑(16)を
完成させる。
In such a state, the ground (13) is excavated with the rotation of the wing bit (1) of the tip head (7) and the jet water from the high-pressure water jet nozzle (4), and the mud is removed with a spiral drill (3). It progresses, and according to progress, another concrete side wall (11) is sequentially added to the upper part of the concrete side wall (11), and a shaft (14) is formed to a predetermined depth. Then the hollow pipe (2) of the rotary shaft of the spiral drill (3)
A hardening agent such as concrete (15) is injected into the bottom of the shaft (14) via the inside. Next, the tip head (7) is withdrawn and the concrete (15) is hardened to complete the water-blocking shaft (16).

なお本実施例における先端ヘッド(7)の隔壁(8)
に設けたスパイラルドリル(3)は固定パイプ(17)の
内部で回転駆動機(21)により回転するようになってお
り、上部の排泥口(18)に向かって排泥するようになっ
ている。このとき高圧エア注入管(6)から高圧エアを
注入し排泥を効率良く行うようになっている。排泥口
(18)には開閉用のパイプ(22)を設けているので、エ
アのみ排出されるときにはバルブ(22)を締めるように
なっている。なおスパイラルドリル(3)が排泥で埋ま
るとエアが逃げることはない。また。高圧水噴射ノズル
(4)はノズル回転駆動機(19)により回転し掘削能力
を高めている。
Note that the partition (8) of the tip head (7) in this embodiment.
The spiral drill (3) provided in the container is rotated by a rotary drive (21) inside the fixed pipe (17), and discharges the sludge toward the upper discharge port (18). I have. At this time, high-pressure air is injected from the high-pressure air injection pipe (6) to efficiently discharge sludge. Since the opening and closing pipe (22) is provided in the mud outlet (18), the valve (22) is closed when only air is discharged. When the spiral drill (3) is buried with mud, air does not escape. Also. The high-pressure water injection nozzle (4) is rotated by a nozzle rotation drive (19) to increase the excavation ability.

以上のように本実施例では、従来の工法における鋼矢
板打設機等のような大型機械を必要としないので工事現
場が狭くても立坑築造を支障なく行うことができる。ま
た従来のライナー式立坑のように施工費が高くなること
もない。
As described above, in the present embodiment, a large machine such as a steel sheet pile driving machine in the conventional construction method is not required, so that even if the construction site is narrow, the shaft can be constructed without any trouble. Also, the construction cost does not increase as in the conventional liner type shaft.

本実施例では、先端ヘッド(7)の隔壁(8)に設け
た高圧本噴射ノズル(4)、ウイングビット(1)によ
って地盤の掘削を行ない、スパイラルドリル(3)で排
泥を行うので、強い打撃・振動等を発生することがな
く、工事現場周辺地域に悪影響を及ぼすこともない。
In this embodiment, the ground is excavated by the high-pressure main injection nozzle (4) and the wing bit (1) provided in the partition (8) of the tip head (7), and the mud is discharged by the spiral drill (3). There is no strong impact or vibration, and there is no adverse effect on the area around the construction site.

本実施例ではコンクリート側壁(11)は第3図に示す
ように円筒状をしており、順次継ぎ足していくようにな
っているが、第4図に示すように複数に分割したものを
使用することもできる。また第5図に示すように四角形
のものを使用することも可能である。
In this embodiment, the concrete side wall (11) has a cylindrical shape as shown in FIG. 3 and is successively added. However, as shown in FIG. You can also. It is also possible to use a rectangular one as shown in FIG.

(発明の効果) 本発明により、狭い場所や帯水地盤等においても立坑
築造が可能で、施工費が安く、工事現場周辺地域へ悪影
響を及ぼすこともない止水性立坑築造工法を提供するこ
とができる。
(Effects of the Invention) According to the present invention, it is possible to provide a water-blocking shaft construction method capable of constructing a shaft in a narrow place or in an aquifer ground, at a low construction cost, and without adversely affecting the surrounding area of the construction site. it can.

【図面の簡単な説明】[Brief description of the drawings]

第1図は実施例を示す一部切欠断面図、第2図は同工程
説明図、第3図は同コンクリート側壁の一部切欠斜視図
である。 第4図、第5図は他の実施例のコンクリート側壁の一部
切欠斜視図である。 (1):ウイングビット、(2):中空パイプ (3):スパイラルドリル、(4):高圧水噴射ノズル (5):注水管、(6):高圧エア注入管 (7):先端ヘッド、(8):隔壁 (9):ジャッキ、(10):反力板 (11):コンクリート側壁 (12):グランドアンカー引張材 (13):地盤、(14):立坑 (15):コンクリート、(16):止水性立坑 (17):固定パイプ、(18):排泥口 (19):ノズル回転駆動機、(20):ジャッキ (21):回転駆動機、(22):バルブ
1 is a partially cutaway sectional view showing an embodiment, FIG. 2 is an explanatory view of the same process, and FIG. 3 is a partially cutaway perspective view of the concrete side wall. 4 and 5 are partially cutaway perspective views of a concrete side wall according to another embodiment. (1): Wing bit, (2): hollow pipe (3): spiral drill, (4): high pressure water injection nozzle (5): water injection pipe, (6): high pressure air injection pipe (7): tip head, (8): Partition wall (9): Jack, (10): Reaction plate (11): Concrete sidewall (12): Ground anchor tensile material (13): Ground, (14): Vertical shaft (15): Concrete, ( 16): Waterproof shaft (17): Fixed pipe, (18): Drain outlet (19): Nozzle rotary drive, (20): Jack (21): Rotary drive, (22): Valve

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】短い円筒形状をした先端ヘッドの内部の隔
壁に、先端にウイングビットを備え且つ中空パイプを回
転軸とするスパイラルドリルと、高圧水噴射ノズルと、
注水管と、高圧エア注入管とを取り付けたものを用意
し、同先端ヘッドの下部を地中に向けて設置し、同先端
ヘッドには所定長さで円筒状の側壁を載荷して同先端ヘ
ッドのウイングビットの回転及び高圧水噴射ノズルから
の噴射水で地盤を掘削し且つ同スパイラルドリルで排泥
しながら進行し、同側壁の上部には他の側壁を順次継ぎ
足すことを繰り返して所定深度まで立坑を形成した後、
同スパイラルドリルの回転軸の中空パイプ内を経由して
同立坑底部に硬化剤を注入打設し、その後同先端ヘッド
を撤収して同硬化剤を硬化させることを特徴とする止水
性立坑築造工法。
A spiral drill having a wing bit at a tip thereof and a hollow pipe as a rotating shaft, a high-pressure water injection nozzle,
Prepare a pipe with a water injection pipe and a high-pressure air injection pipe attached, place the lower end of the tip head into the ground, and install a cylindrical side wall with a predetermined length on the tip head. The ground is excavated with the rotation of the wing bit of the head and the injection water from the high-pressure water injection nozzle, and proceeds while muddy with the same spiral drill. After forming a shaft to the depth,
A water-blocking shaft construction method, in which a hardening agent is injected into the bottom of the vertical shaft through the hollow pipe of the rotary shaft of the spiral drill, and then the tip head is withdrawn and the hardening agent is hardened. .
【請求項2】地中に一端を固定したグランドアンカー引
張材を強く把持し、反力拠点として側壁上部に圧力を加
えることを特徴とする請求項1記載の止水性立坑築造工
法。
2. The method for constructing a water-blocking shaft according to claim 1, wherein the ground anchor tension member having one end fixed to the ground is strongly gripped and pressure is applied to an upper portion of the side wall as a reaction force base.
【請求項3】コンクリートを硬化剤としたことを特徴と
する請求項1または2記載の止水性立坑築造工法。
3. The method for constructing a water-blocking shaft according to claim 1, wherein concrete is used as a hardening agent.
【請求項4】コンクリートまたは合成樹脂を材料とする
側壁を使用したことを特徴とする請求項1〜3何れかに
記載の止水性立坑築造工法。
4. The method according to claim 1, wherein a side wall made of concrete or synthetic resin is used.
JP27936189A 1989-10-25 1989-10-25 Waterproof shaft construction method Expired - Fee Related JP2640542B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27936189A JP2640542B2 (en) 1989-10-25 1989-10-25 Waterproof shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27936189A JP2640542B2 (en) 1989-10-25 1989-10-25 Waterproof shaft construction method

Publications (2)

Publication Number Publication Date
JPH03140594A JPH03140594A (en) 1991-06-14
JP2640542B2 true JP2640542B2 (en) 1997-08-13

Family

ID=17610095

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27936189A Expired - Fee Related JP2640542B2 (en) 1989-10-25 1989-10-25 Waterproof shaft construction method

Country Status (1)

Country Link
JP (1) JP2640542B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010067680A (en) * 2001-03-07 2001-07-13 권이현 Clamp-off aufban method for the facilities using earth-anchor
CN110043264B (en) * 2019-05-17 2024-02-09 中铁第六勘察设计院集团有限公司 Construction method for jacking prefabricated rectangular vertical shaft structural type
CN110685695B (en) * 2019-11-28 2021-10-12 中国铁建重工集团股份有限公司 Vertical shaft construction system and method from top to bottom

Also Published As

Publication number Publication date
JPH03140594A (en) 1991-06-14

Similar Documents

Publication Publication Date Title
CN112482357B (en) Drilling tool for pre-blasting cement mixing pile suitable for hard soil layer and application method thereof
JPH0791930B2 (en) Underground drilling machine cement soil equipment
JP2640542B2 (en) Waterproof shaft construction method
SU946409A3 (en) Method for driving lower ends of sheet piles into base soil in erecting sheet piling wall
KR20080112453A (en) Ground Improvement Method Using Ground Improvement Equipment
GB2154630A (en) Construction method for foundation piling
JP2002275892A (en) Method and device for placing steel pipe pile
JPH1150451A (en) Method and device for removing pile head extra-banking part concrete
JP2686445B2 (en) Soil cement water blocking wall construction method and its equipment
KR100609335B1 (en) Reinforcement construction method in the ground
JP2762935B2 (en) Horizontal mortar pile construction method
JPS60119816A (en) Formation of continuous pile
JPH03257215A (en) Pile constructing method
WO2001036753A1 (en) Pile forming
GB2137678A (en) Method and apparatus for pile construction
JPH0978571A (en) Execution method for soil cement pile
JPS6062322A (en) Ground improvement method and hydraulic power monitor used in the method
JP2001241033A (en) Ground improving method in which hardened columnar body can be anchored to hard supporting ground, and ground improving apparatus used for the method
JPS61158517A (en) Method of processing extra-banking concrete for cast-in-place pile
KR0146450B1 (en) Pipe inserting device of underground drill
KR20090095914A (en) J.S.C earth anchor method
JPS63223215A (en) In-situ concrete piling work
JPS61191721A (en) Method of forming earth anchor
JPH0442493B2 (en)
JPH02140323A (en) Method for creating soil cement composite piles

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20090502

LAPS Cancellation because of no payment of annual fees