JP2572680B2 - Underground structure by reverse strike method - Google Patents
Underground structure by reverse strike methodInfo
- Publication number
- JP2572680B2 JP2572680B2 JP2274895A JP27489590A JP2572680B2 JP 2572680 B2 JP2572680 B2 JP 2572680B2 JP 2274895 A JP2274895 A JP 2274895A JP 27489590 A JP27489590 A JP 27489590A JP 2572680 B2 JP2572680 B2 JP 2572680B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- steel
- cutting
- beams
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は、地下逆打ち工法に関する。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to an underground reverse beating method.
(従来の技術と発明が解決しようとする課題) 従来の地下掘削工法において、一般とは逆に上階から
下階にむけて地下部分の構築を進めてゆく逆打ち工法が
採用されることがある。(Conventional technology and problems to be solved by the invention) In the conventional underground excavation method, the reverse striking method is adopted in which the construction of the underground part is advanced from the upper floor to the lower floor, contrary to the general method. is there.
この工法は、周囲に山留め壁等があらかじめ形成され
た掘削部分に構真柱を所定本数埋設後、この構真柱で荷
重を受けながら地下階の本設の鉄骨鉄筋コンクリート製
の柱、梁及び床を掘削と並行して上から下に向けて順次
構築してゆくものである。In this method, after a predetermined number of trussed pillars are buried in an excavated part where a mountain retaining wall or the like is formed in advance, a steel reinforced concrete pillar, beam and floor are installed on the basement floor while receiving a load with these trussed pillars. Are constructed sequentially from top to bottom in parallel with excavation.
しかしながら、従来の逆打ち工法の場合、山留め壁か
らの土圧を受けるには鉄骨製の柱、梁のみでは圧縮耐力
が不足して不可能か、もしくは柱、梁の断面を不必要に
大きくする必要があるため、どうしても掘削と並行して
柱、梁、床のコンクリートを同時に打設しなければなら
なかった。However, in the case of the conventional reverse striking method, it is impossible to receive the earth pressure from the retaining wall by using only steel columns and beams because of insufficient compressive strength, or the cross sections of the columns and beams are made unnecessarily large. Because of the necessity, the concrete for the pillars, beams and floor had to be poured simultaneously in parallel with the excavation.
このコンクリート工事を行うため、柱、梁、床の型枠
組や配筋作業が煩雑で、かつ時間もかかり、さらに床コ
ンクリートを打設して行くため、下方の掘削土砂の搬出
が困難となるなどの欠点があった。Performing this concrete work requires complicated and time-consuming work for pillars, beams, and floor formwork and rebar arrangements, and it also makes it difficult to carry out excavated earth and sand below because concrete is put into place. There were drawbacks.
本発明は、かかる従来の課題を解決しうる逆打ち工法
による地下構造を提供することを目的とするものであ
る。An object of the present invention is to provide an underground structure by a reverse striking method capable of solving such a conventional problem.
(課題を解決するための手段) 上記目的を達成するため、本発明に係る逆打ち工法に
よる地下構造においては、山留め壁からの土圧を受ける
切梁として、内部にコンクリートを充填した鉄骨材で形
成し、この鉄骨コンクリート梁を本設の梁として使用し
うるようにするとともに、当該切梁のうち最下部のもの
を基礎梁内の上部に埋設して一体化したことを特徴とす
るものである。(Means for Solving the Problems) In order to achieve the above object, in the underground structure by the reverse hitting method according to the present invention, as a cutting beam receiving earth pressure from the retaining wall, a steel frame material filled with concrete is used. It is characterized in that this steel frame concrete beam can be used as a permanent beam, and the lowest one of the cut beams is embedded in the upper part of the foundation beam and integrated. is there.
(実施例) 以下、本発明の好適な実施例を図面により説明する。(Embodiment) Hereinafter, a preferred embodiment of the present invention will be described with reference to the drawings.
第1図乃至第5図は本発明の一実施例を示すものであ
り、第1図及び第2図に示すように本実施例に係る地下
逆打ち掘削工法においては、山止めの施工手順としては
従来と同様に、周囲に連続壁、矢板等の土止め壁1をあ
らかじめ形成しておき、当該土止め壁1で囲まれた掘削
部分2に構真柱3を所定本数埋設後、土砂を掘削してゆ
き、該掘削作業に並行して腹起し部材4、切梁5を順次
上階から下階にかけて構築してゆくものである。FIGS. 1 to 5 show an embodiment of the present invention. As shown in FIGS. 1 and 2, in the underground reverse excavation method according to the present embodiment, as a construction procedure of a valley, In the same manner as in the prior art, a retaining wall 1 such as a continuous wall, a sheet pile or the like is formed in advance, and a predetermined number of timber pillars 3 are buried in an excavated portion 2 surrounded by the retaining wall 1, and soil and sand are removed. Excavation is performed, and the bulging members 4 and the cutting beams 5 are sequentially constructed from the upper floor to the lower floor in parallel with the excavation work.
ここで、本実施例に係る切梁5は、第3図に示すよう
に内部に中空部6を有するように一対の溝形鋼7、7と
該一対の溝形鋼7の下部を連結する型枠兼用の連結鋼板
8で形成されており、上部にはコンクリート打設用の開
口部9が形成されている鉄骨部分を有している。Here, the cutting beam 5 according to the present embodiment connects a pair of channel steels 7 with a lower portion of the pair of channel steels 7 so as to have a hollow portion 6 inside as shown in FIG. It is formed of a connection steel plate 8 which also serves as a formwork, and has a steel frame portion in which an opening 9 for placing concrete is formed at the upper part.
そして、かかる鉄骨部分を構真柱3間、あるいは構真
柱3と前記腹起し材4間の所定位置に配置後に前記中空
部6にコンクリート10を打設して本設の鉄骨コンクリー
ト梁として利用しうるように断面設定したものである。Then, after arranging such a steel frame portion at a predetermined position between the straight columns 3 or between the straight columns 3 and the protruding members 4, concrete 10 is poured into the hollow portion 6 to form a permanent steel concrete beam. The cross section is set so that it can be used.
なお、切梁5はあらかじめ鉄骨コンクリート梁として
形成してから現場に搬入するようにしてもよい。In addition, the cutting beam 5 may be formed as a steel concrete beam in advance and then carried into the site.
また、前記構真柱3も第3図に示すように通常の単一
鉄骨材ではなく、内部にコンクリート10が充填された鋼
管コンクリート柱として形成されており、本構真柱3も
本設の柱として利用しうるような断面設定がなされてい
る。Also, as shown in FIG. 3, the straight pillar 3 is not formed of a normal single steel frame material, but is formed as a steel pipe concrete pillar having a concrete 10 filled therein. The cross section is set so that it can be used as a pillar.
しかして、構真柱3と切梁5との接合は、第4図に示
すように構真柱3の対応位置に一対のガセットプレート
11を一体に固着し、該ガセットプレート11と切梁5の端
部とをボルト12で接合するようになっている。なお、第
4図では一方向の切梁5と接合部のみを示し、他の3方
向からの切梁5との接合部を便宜上省略しているが、こ
れらの接合部も同様の構成となる。Then, as shown in FIG. 4, the pair of trussed pillars 3 and the cutting beams 5 are joined at a corresponding position of the trussed pillars 3 by a pair of gusset plates.
The gusset plate 11 and the end of the cutting beam 5 are joined together by bolts 12. In FIG. 4, only the cut beam 5 in one direction and the joint are shown, and the joints with the cut beam 5 from the other three directions are omitted for convenience, but these joints also have the same configuration. .
また、本実施例における上記腹起し材4は、本設の梁
として使用してもよい。Moreover, the above-mentioned belly material 4 in the present embodiment may be used as a permanent beam.
しかして、本実施例では、第1図に示すように掘削作
業に並行して腹起し部材4、切梁5を順次上階から下階
にかけて構築してゆき、最下部の切梁5が配設された
ら、当該切梁5により土圧を負担しながら、その下部に
基礎梁を形成するのに必要な深さの掘削を行なう。In this embodiment, as shown in FIG. 1, the bulging member 4 and the cutting beam 5 are sequentially constructed from the upper floor to the lower floor in parallel with the excavation work. After being disposed, excavation is performed to a depth necessary for forming a foundation beam below the earth beam while bearing earth pressure by the cutting beam 5.
そして、第5図及び第6図に示すように基礎梁15の形
成にあたっては、前記最下部に切梁5を基礎梁15の上部
に配置した状態で所定の配筋16、型枠作業を行ない、切
梁5を埋設、一体化した鉄骨鉄筋コンクリート造の基礎
梁15を構築するようになっている。In forming the foundation beam 15 as shown in FIG. 5 and FIG. 6, predetermined reinforcing bars 16 and formwork are performed in a state where the cutting beam 5 is arranged at the lowermost portion above the foundation beam 15. In addition, a foundation beam 15 made of a steel-framed reinforced concrete structure in which the cutting beam 5 is embedded and integrated is constructed.
かかる構成からなる本実施例においては、従来仮設材
としてのみ使用されていた構真柱3及び切梁5を各々鉄
骨コンクリート製のものとして、本設の柱、梁として利
用しうるように断面設計がなされているため、剛性、圧
縮強度が高くこれらの柱、梁のみで土圧等に抵抗可能と
なり、コンクリートの床梁を形成することなく自立しう
るから、開放空間が大きく、下方の掘削土砂の搬出が非
常に効率良く行なえる。In the present embodiment having such a configuration, the cross-section design is made so that the straight columns 3 and the cutting beams 5 which have been conventionally used only as temporary materials are made of steel-frame concrete, and can be used as the main columns and beams. Because of its high rigidity and compressive strength, it is possible to resist earth pressure and the like only with these columns and beams, and it can stand up without forming a concrete floor beam. Can be carried out very efficiently.
また、同様に従来のように逆打ち工法のため梁や床の
型枠組や配筋作業が煩雑となる問題も解消して掘削の時
間が短くなり、さらに、解体作業が不要であるから省力
化を図ることができる。In addition, similarly, the problem of complicated beam and floor formwork and rebar arrangement work due to the reverse striking method as in the past has been resolved, shortening the excavation time, and labor saving because no dismantling work is required. Can be achieved.
さらに、最下部の切梁5は基礎梁15の一部としても活
用することができるため、合理的であり、また、鉄骨鉄
筋コンクリート造の基礎梁15となるため上端の鉄筋16の
量を減少させることが可能となる。Furthermore, the lowermost cutting beam 5 can be used also as a part of the foundation beam 15, so that it is rational. Also, since the foundation beam 15 is made of steel reinforced concrete, the amount of the reinforcing bar 16 at the upper end is reduced. It becomes possible.
なお、切梁5の断面構成については、上記実施例の他
に、適宜断面構成とすることが可能であり、また、構真
柱3についても、円形鋼管、あるいはH形鋼などを利用
することができ、この場合の切梁5との接合も上記実施
例に準じて行なえばよい等、本発明は上記実施例に限定
されるものではなく本発明の要旨を逸脱しない範囲内で
種々の変形例が可能なことは言うまでもない。In addition to the above embodiment, the cross-sectional configuration of the cutting beam 5 can be appropriately set to a cross-sectional configuration. Also, for the straight columns 3, circular steel pipes or H-shaped steels are used. In this case, the present invention is not limited to the above-described embodiment. For example, various modifications can be made without departing from the gist of the present invention. It goes without saying that examples are possible.
(発明の効果) 本発明は上述した如く構成されており、床コンクリー
ト等を打設することなく、本設の鉄骨コンクリート梁を
切梁として利用できるため、強度が高く、掘削空間を大
きくとれ、下方の掘削土砂の搬出が非常に効率良く行う
ことができる。(Effects of the Invention) The present invention is configured as described above, and since it is possible to use a permanent steel concrete beam as a cutting beam without placing floor concrete or the like, the strength is high and a large excavation space can be taken. The lower excavated soil can be carried out very efficiently.
また、従来のように掘削中の梁や床の型枠組や配筋作
業や、解体作業が無くなるため、工期も早く、かつ煩雑
さも解消できる。Further, since the work of arranging the beams and floors during excavation, the arrangement of the reinforcing bars, and the dismantling work as in the prior art are eliminated, the construction period can be shortened and the complexity can be eliminated.
さらに、最下部の切梁は基礎梁の一部としても活用す
ることができるため、合理的であり、また、鉄骨鉄筋コ
ンクリート造の基礎梁となるため上端鉄筋量を減少させ
ることが可能となる。Further, the lowermost cut beam can be used as a part of the foundation beam, so that it is rational, and since it becomes a steel-frame reinforced concrete foundation beam, it is possible to reduce the amount of upper rebar.
第1図乃至第6図は本発明の一実施例を示し、第1図は
本実施例に係る逆打ち工法による山止めの構成を示す概
念図、第2図は第1図の概念的平面図、第3図は切梁の
構成を示す断面図、第4図(a)及び第4図(b)は各
々構真柱と切梁との接合部を示す説明図、第5図は基礎
梁形成後の構成を示す概念図、第6図は基礎梁の構成を
示す断面図である。 1……土止め壁、3……構真柱、 4……腹起し材、 5……切梁、6……中空部、 10……コンクリート、 15……基礎梁、16……鉄筋。1 to 6 show an embodiment of the present invention. FIG. 1 is a conceptual diagram showing a configuration of a shoring by a reverse striking method according to the present embodiment. FIG. 2 is a conceptual plan view of FIG. FIGS. 3 and 4 are cross-sectional views showing the structure of the cut beam, FIGS. 4 (a) and 4 (b) are explanatory views each showing a joint between the straight column and the cut beam, and FIG. FIG. 6 is a conceptual diagram showing the configuration after the beam is formed, and FIG. 6 is a sectional view showing the configuration of the foundation beam. 1 ... Retaining wall, 3 ... Structural pillar, 4 ... Wrapped material, 5 ... Section beam, 6 ... Hollow section, 10 ... Concrete, 15 ... Foundation beam, 16 ... Rebar.
Claims (1)
用し、当該切梁のうち最下部のものを基礎梁内の上部に
埋設して一体化したことを特徴とする逆打ち工法による
地下構造。An underground construction method using a reverse striking method, wherein a steel concrete beam is permanently used as a cutting beam, and the lowest one of the cutting beams is buried in an upper part of a foundation beam and integrated. Construction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2274895A JP2572680B2 (en) | 1990-10-12 | 1990-10-12 | Underground structure by reverse strike method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2274895A JP2572680B2 (en) | 1990-10-12 | 1990-10-12 | Underground structure by reverse strike method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04149321A JPH04149321A (en) | 1992-05-22 |
JP2572680B2 true JP2572680B2 (en) | 1997-01-16 |
Family
ID=17548026
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2274895A Expired - Lifetime JP2572680B2 (en) | 1990-10-12 | 1990-10-12 | Underground structure by reverse strike method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2572680B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6226123B2 (en) * | 2013-09-11 | 2017-11-08 | 株式会社竹中工務店 | Building construction method |
-
1990
- 1990-10-12 JP JP2274895A patent/JP2572680B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH04149321A (en) | 1992-05-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR200370107Y1 (en) | Forms for edge girder construction | |
JP4407716B2 (en) | Construction method of earth retaining wall | |
JP2572680B2 (en) | Underground structure by reverse strike method | |
KR102482690B1 (en) | Bridge foundation construction method using formwork integrated PC panels | |
JPS5829922A (en) | Constructing method for underground outer wall | |
JPS6137692Y2 (en) | ||
KR200370135Y1 (en) | Forms for edge girder construction | |
JP4243069B2 (en) | Construction method of earth retaining wall | |
JPS63280153A (en) | Underground inverted lining method | |
JP3882536B2 (en) | Reconstruction method for existing buildings | |
JP2769937B2 (en) | Steel tube concrete column in underground reverse driving method | |
JPH0754364A (en) | Basement floor construction method | |
JP2757209B2 (en) | Cut-and-joint underground construction method using synthetic steel beams | |
JP3406370B2 (en) | Horizontal shaft construction method | |
JP2894217B2 (en) | Building structural frame | |
JP2763488B2 (en) | Prefabricated pillar and inverted ramen prefabricated construction method | |
JPH07103583B2 (en) | Construction method for large span underground structure | |
JPH0657769A (en) | Underground structure and its construction method | |
JPH0781274B2 (en) | How to build a beam on an underground wall | |
JPH04360908A (en) | Underground wall construction method and underground wall construction formwork | |
JPH076204B2 (en) | How to build an underground structure | |
JP3061934B2 (en) | Retaining wall construction method | |
JPH05118047A (en) | Constructing method for foundation structure | |
JPH0347320A (en) | Base structure by inverted placing method |