JP2565458B2 JP29637492A JP29637492A JP2565458B2 JP 2565458 B2 JP2565458 B2 JP 2565458B2 JP 29637492 A JP29637492 A JP 29637492A JP 29637492 A JP29637492 A JP 29637492A JP 2565458 B2 JP2565458 B2 JP 2565458B2
Authority
JP
Japan
Prior art keywords
long
elevator body
bearing member
floor
long bearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP29637492A
Other languages
Japanese (ja)
Other versions
JPH06115858A (en
Inventor
実 斎藤
龍夫 内藤
行正 荻原
松生 鶴岡
敏和 颯田
興平 三尾
俊輔 白井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP29637492A priority Critical patent/JP2565458B2/en
Publication of JPH06115858A publication Critical patent/JPH06115858A/en
Application granted granted Critical
Publication of JP2565458B2 publication Critical patent/JP2565458B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建物、建造物の施工で
使用する揚重装置とその使用方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a lifting device used in the construction of buildings and structures and a method of using the lifting device.

【0002】[0002]

【従来の技術】建設工事というものはその作業内容を分
解してみると上下、水平の荷役の意味をもった資材の移
動運搬作業が大半を占めている。そして一口に揚重装置
といっても多種多様であり、クレーン、デリック、エレ
ベーター、建設用リフト、チェンブロック類、ジャッキ
類等が挙げられる。
2. Description of the Related Art When disassembling the work contents of construction work, most of the work involves moving and transporting materials having the meaning of vertical and horizontal cargo handling. There are a wide variety of lifting devices, including cranes, derricks, elevators, construction lifts, chain blocks, and jacks.

【0003】このうち、エレベーターや建設用リフトは
一例として図7に示すように、支柱やガイド等の長尺支
承部材3と、この支承部材3に沿って昇降するケージや
荷台等の昇降機体4とからなるものであり、これを建設
中の建物のコンクリートの柱・梁や鉄骨骨組等の躯体1
内に設ける場合には、図7に示すように各階の床に通常
上下に貫通する開口2(いわゆるダメ穴)を確保し、こ
の開口2の周囲に前記長尺支承部材3を設置する。
Of these, as shown in FIG. 7, an elevator and a construction lift are long supporting members 3 such as columns and guides, and an elevator body 4 such as a cage or a loading platform which moves up and down along the supporting members 3. And the frame 1 of concrete pillars / beams or steel frames of the building under construction.
When provided inside, as shown in FIG. 7, an opening 2 (a so-called useless hole) that normally penetrates vertically is secured in the floor of each floor, and the long bearing member 3 is installed around the opening 2.

【0004】なお、昇降機体4を昇降させるための昇降
装置は、長尺支承部材3にラック5を設け、昇降機体4
に減速機付きのモーター6を設け、該モーター6のピニ
オン7をラック5に噛合させたものである。
The elevator device for raising and lowering the elevator body 4 is provided with a rack 5 on the long support member 3 and the elevator body 4 is lifted.
A motor 6 with a speed reducer is provided in the rack, and a pinion 7 of the motor 6 is meshed with the rack 5.

【0005】[0005]

【発明が解決しようとする課題】このような従来のエレ
ベーターや建設用リフトは、支柱やガイド等の長尺支承
部材3は躯体1の地上階から作業階まで貫通するように
設けられる。しかし、建築現場で仮設資材の大半は転用
資材であり、これらは1階(地上階)よりも上の任意階
から作業階へ上げたり、作業階から任意階へ下げたりす
ることが多く、下方階の部分の利用頻度は少ない。
In such conventional elevators and construction lifts, long supporting members 3 such as struts and guides are provided so as to penetrate from the ground floor of the frame 1 to the working floor. However, most of the temporary materials at construction sites are diverted materials, and these are often raised from the arbitrary floor above the first floor (ground floor) to the working floor or lowered from the working floor to the arbitrary floor. The frequency of using the floor is low.

【0006】また、前記開口2はこれらエレベーターや
建設用リフトを撤去するまで残ってしまい工事の完了が
それだけ遅くなる。なお、躯体1の外部にエレベーター
や建設用リフトを設ける場合でも同様であり、建物の外
部仕上げがその部分だけできないことになる。
Further, the opening 2 remains until these elevators and construction lifts are removed, which delays the completion of the work. The same applies to the case where an elevator or a construction lift is provided outside the skeleton 1, and the exterior finishing of the building cannot be performed only at that portion.

【0007】本発明の目的は前記従来例の不都合を解消
し、機器を必要な長さのものに限定してこれを転用する
ことで不使用となる無駄の部分を無くし、また、この転
用のための移動や昇降機体の移動は自動的に安定した状
態で行われ、しかも、移動後のだめ穴等の未作業部分の
存在を少なくして工期の短縮化が実現できる揚重装置お
よびその使用方法を提供することにある。
The object of the present invention is to eliminate the inconvenience of the above-mentioned conventional example, to limit the equipment to the required length and to divert it, thereby eliminating the wasteful portion which is not used, and to divert the diversion. The lifting device and the method of using the lifting device can be automatically moved in a stable state and the unworked parts such as dead holes after the movement can be reduced to shorten the construction period. To provide.

【0008】[0008]

【課題を解決するための手段】本発明は前記目的を達成
するため、揚重装置としては、支柱やガイド等の長尺支
承部材側のラックと、ケージや荷台等の昇降機体に設け
たモーターのピニオンとを噛合して長尺支承部材に沿っ
て昇降機体が昇降する揚重装置において、前記長尺支承
部材は、3階以上の数階分を掛渡せる長さからなり、建
物躯体の床に着脱自在に係止する係止部材を長尺支承部
材の途中に、また、折り畳み可能な頂部サポートを頂部
に設け、建物躯体側に前記長尺支承部材を抱持する枠状
の転倒防止金物を取付け可能とし、一方、前記昇降機体
には建物躯体の床への係止部材を着脱自在に取付けるこ
とを要旨とするものである。
In order to achieve the above-mentioned object, the present invention relates to a lifting device, which is a motor provided on a rack on the side of a long supporting member such as a support or a guide and an elevator body such as a cage or a loading platform. In the lifting device in which the elevator body is moved up and down along the long bearing member by meshing with the pinion, the long bearing member has a length that can span several floors of three or more floors, and the floor of the building frame. A frame-shaped fall-prevention hardware for holding the long bearing member on the side of the building body by providing a locking member for detachably locking the long bearing member in the middle of the long bearing member and a foldable top support at the top. On the other hand, the gist of the present invention is to attach detachably a locking member to the floor of the building frame to the elevator body.

【0009】揚重装置の使用方法としては、支柱やガイ
ド等の長尺支承部材側のラックと、ケージや荷台等の昇
降機体に設けたモーターのピニオンとを噛合して長尺支
承部材に沿って昇降する昇降機体で揚重を行う揚重方法
において、長尺支承部材は、3階以上の数階分を掛渡せ
る長さからなり、建物躯体に着脱自在に係止する係止部
材を長尺支承部材の途中に、また、折り畳み可能な頂部
サポートを頂部に設け、建物躯体側に前記長尺支承部材
を抱持する枠状の転倒防止金物を取付け可能とし、一
方、前記昇降機体には建物躯体の床部分への係止部材を
着脱自在に取付ける揚重装置を使用し、揚重時には、長
尺支承部材を係止部材及び頂部サポートにより建物躯体
に係止し、昇降機体を昇降させ、非揚重時に、昇降機体
を係止部材を介して建物躯体に係止し、転倒防止金物を
取付けて長尺支承部材を抱持し、昇降機体に対して係止
部材及び頂部サポートでの係止を解除した長尺支承部材
を前記昇降機体に設けたモーターの駆動で長手方向の延
長線上に昇降させることを要旨とするものである。
As a method of using the lifting device, a rack on the side of a long supporting member such as a column or a guide is engaged with a pinion of a motor provided on an elevator body such as a cage or a loading platform so as to follow the long supporting member. In the hoisting method of hoisting with an elevator body that elevates and lowers, the long support member has a length that can span several floors of three or more floors, and the locking member that detachably locks to the building frame is long. In the middle of the length support member, a foldable top support is provided at the top, and a frame-shaped fall-prevention hardware holding the long support member can be attached to the building body side, while the elevator body is attached to the elevator body. A lifting device that detachably attaches the locking member to the floor of the building frame is used, and at the time of lifting, the long support member is locked to the building frame by the locking member and the top support to raise and lower the elevator body. , When not hoisting, lift the elevator body through the locking member Provided on the elevator body with a long support member that is locked to the building body, attaches a fall-prevention hardware, holds the long support member, and releases the locking member and the top support from the elevator body. The gist is to drive the motor to raise and lower along the extension line in the longitudinal direction.

【0010】[0010]

【作用】請求項1及び請求項2記載の本発明によれば、
支柱やガイド等の長尺支承部材自体も上昇させて転用で
きるので、この長尺支承部材は無駄な部分がない。ま
た、長尺支承部材を移動した後にはだめ穴を適宜塞ぐこ
とで未作業部分の存在を無くして工期を短縮できる。
According to the present invention described in claims 1 and 2,
Since the long supporting members themselves such as the columns and guides can also be raised and diverted, the long supporting members have no useless portion. Further, after moving the long bearing member, by appropriately closing the dead hole, it is possible to eliminate the existence of an unworked portion and shorten the construction period.

【0011】しかも、昇降機体は、3回以上の数階分の
長さからなる長尺支承部材の長さ範囲内であれば、モー
ターの駆動により簡単かつ迅速に、しかもラックとピニ
オンの噛合により確実に昇降される。また、長尺支承部
材を昇降させる場合には、係止部材と頂部サポートの建
物躯体の床部分との係合を解除するだけで、前記ラック
により自動的に簡単、迅速かつ的確にこの長尺支承部材
を昇降移動してくる。
Moreover, the elevator body is easily and quickly driven by the motor and is engaged by the engagement of the rack and the pinion as long as it is within the length range of the long bearing member having a length of several steps of three times or more. It can be lifted and lowered reliably. Further, when elevating and lowering the long supporting member, the engagement between the locking member and the floor portion of the building body of the top support is simply released, and the rack automatically and simply, quickly and accurately The support member moves up and down.

【0012】また、昇降機体の昇降の際には、長尺支承
部材がその途中の係止部材で固定することの他にその頂
部の頂部サポートによりしっかりと固定されていること
から安定している。さらに、長尺支承部材の移動をする
場合には、昇降機体を係止部材で固定することの他に、
枠状の転倒防止金物で長尺支承部材を抱持するので、そ
の長手方向の延長線上への昇降が安定する。
Further, when the elevator body is moved up and down, the long bearing member is not only fixed by the locking member in the middle but also firmly fixed by the top support at the top thereof, which is stable. . Furthermore, when moving the long bearing member, in addition to fixing the elevator body with a locking member,
Since the long support member is held by the frame-shaped fall-prevention hardware, the elevating and lowering on the extension line in the longitudinal direction is stable.

【0013】[0013]

【実施例】以下、図面について本発明の実施例を詳細に
説明する。図1は本発明の揚重装置の1実施例を示す側
面図、図2は同上正面図、図3〜図6は本発明の揚重装
置の使用方法の工程説明図で、前記従来例を示す図7と
同一構成要素には同一参照符号を付したものである。
Embodiments of the present invention will now be described in detail with reference to the drawings. FIG. 1 is a side view showing an embodiment of a lifting device of the present invention, FIG. 2 is a front view of the same, and FIGS. 3 to 6 are process explanatory diagrams of a method of using the lifting device of the present invention. The same components as those shown in FIG. 7 are designated by the same reference numerals.

【0014】本発明の揚重装置も支柱やガイド等の長尺
支承部材3と、この支承部材3に沿って昇降するケージ
や荷台等からなるものであり、該昇降機体4を昇降させ
るための昇降装置は、長尺支承部材3にラック5を設
け、昇降機体4は減速機付きのモーター6を備え、該モ
ーター6で回転するピニオン7をラック5に噛合させた
ものである。
The hoisting device of the present invention also comprises a long support member 3 such as a column or a guide, and a cage or a loading platform which moves up and down along the support member 3 for raising and lowering the elevator body 4. In the lifting device, a rack 5 is provided on the long support member 3, a lifting machine body 4 is provided with a motor 6 with a reduction gear, and a pinion 7 rotating by the motor 6 is meshed with the rack 5.

【0015】図示は躯体1内に設ける場合で、各階の床
に通常上下に貫通する開口2を確保し、この開口2の周
囲に前記長尺支承部材3を設置するが、本発明ではこの
長尺支承部材3は躯体1の全体の階のうち少なくとも3
階以上の数階分を掛渡しできる長さからなるものとす
る。
In the case shown in the figure, the structure is provided in the frame 1, and an opening 2 that normally penetrates vertically is secured in the floor of each floor, and the long bearing member 3 is installed around the opening 2. The shaku supporting member 3 is at least 3 of the entire floors of the body 1.
The length shall be such that several floors above the floor can be transferred.

【0016】また、建物躯体1の各階の床部分側にレー
ルサポート10を設置し、この長尺支承部材3はその途中
を係止部材としての固定ピン8でこのレールサポート10
に着脱自在に係止する。また、レールサポート10には長
尺支承部材3に対するガイドローラ11を設けた。
Further, a rail support 10 is installed on the floor portion side of each floor of the building frame 1, and this long support member 3 is provided with a fixing pin 8 as a locking member in the middle thereof.
Removably lock to. Further, the rail support 10 is provided with a guide roller 11 for the long bearing member 3.

【0017】前記長尺支承部材3の頂部に、頂部サポー
ト12を端部を軸着して折り畳み可能に設け、下端にはバ
ッファスプリング13を配設する。図中14は前記ラック5
よりも上方位置で長尺支承部材3に沿って移動可能なガ
イドローラであり、このガイドローラ14のホルダーから
吊り材15で昇降機体4を吊り支承する。
A top support 12 is provided on the top of the long support member 3 so that the top support 12 is axially foldable and a buffer spring 13 is provided at the bottom. In the figure, 14 is the rack 5
It is a guide roller that can move along the long support member 3 at a position higher than the above, and the elevator body 4 is suspended and supported by the suspension member 15 from the holder of the guide roller 14.

【0018】なお、特定階のレールサポート10には、長
尺支承部材3を抱持する枠状の転倒防止金物17を着脱自
在に取付ける。また、昇降機体4は、その下部に、後述
するように、サポート16で建物躯体1の床部分側に固定
するH型鋼などによる受け梁状の支持金物9を取付け可
能とする。
A frame-shaped fall-prevention hardware 17 for holding the long bearing member 3 is detachably attached to the rail support 10 on the specific floor. Further, the elevator body 4 can have a beam-like support metal 9 made of H-shaped steel or the like, which is fixed to a floor portion side of the building frame 1 by a support 16, at a lower portion thereof, as will be described later.

【0019】図1に示すように各階の床に通常上下に貫
通する開口2(いわゆるダメ穴)を確保し、この開口2
の周囲に長尺支承部材3を設置するが、このようにして
1階と5階の間は長尺支承部材3に沿って昇降機体4が
昇降し、この昇降機体4で資材や人の昇降を行う。
As shown in FIG. 1, an opening 2 (a so-called useless hole) that normally penetrates vertically is secured in the floor of each floor, and this opening 2
A long support member 3 is installed around the floor, and in this way the elevator body 4 moves up and down along the long support member 3 between the first floor and the fifth floor, and the elevator body 4 raises and lowers materials and people. I do.

【0020】次に、移動方法について説明する。図3に
示すように昇降機体4を上端まで昇らせ、係止部材とし
て、H型鋼などによる受け梁状の支持金物9を昇降機体
4の下部に介在させ、この支持金物9をサポート16で建
物躯体1の床部分側に固定する。そして、前記固定ピン
8をレールサポート10から外してレールサポート10と長
尺支承部材3の結合を解除し、また、頂部サポート12を
外して畳む。さらに、特定階のレールサポート10に枠状
の転倒防止金物17を取付けてあるので、これで長尺支承
部材3を抱持する。
Next, the moving method will be described. As shown in FIG. 3, the elevator body 4 is lifted to the upper end, and a supporting beam-shaped support metal 9 made of H-shaped steel or the like is interposed below the elevator body 4 as a locking member. It is fixed to the floor side of the body 1. Then, the fixing pin 8 is removed from the rail support 10 to release the connection between the rail support 10 and the long support member 3, and the top support 12 is removed to fold it. Further, since the frame-shaped fall-prevention hardware 17 is attached to the rail support 10 on the specific floor, the long support member 3 is held by this.

【0021】これで、長尺支承部材3と躯体1の係止は
解除されてので、昇降機体4側にモーター6のピニオン
7を逆回転させれば、これに噛合するラック5である長
尺支承部材3は図4に示すようにその長手方向の延長線
上で上昇する。
With this, since the engagement between the long bearing member 3 and the frame 1 is released, if the pinion 7 of the motor 6 is reversely rotated to the side of the elevator body 4, the rack 5, which is meshed with the pinion 7, is elongated. The support member 3 rises on its longitudinal extension as shown in FIG.

【0022】図5に示すように固定ピン8や頂部サポー
ト12で長尺支承部材3を再び、上部階の床部分に固定
し、また、図6に示すように昇降機体4の下方の支持金
物9や転倒防止金物17を撤去して、上部階での資材や人
の昇降を行う。また、下部階以下の開口2はレールサポ
ート10を撤去してこれを塞ぐことができる。
As shown in FIG. 5, the long support member 3 is again fixed to the floor portion of the upper floor by the fixing pin 8 and the top support 12, and as shown in FIG. 9 and fall prevention hardware 17 are removed, and materials and people are moved up and down on the upper floor. In addition, the rail support 10 can be removed to close the opening 2 below the lower floor.

【0023】このように、揚重時には長尺支承部材3を
固定ピン8等により建物躯体1に係止し、非揚重時に昇
降機体4を支持金物9等により建物躯体1に係止し、こ
の昇降機体4に対して固定ピン8等を外した長尺支承部
材3を昇降させることを繰り返して、順次上部階への設
置に切り換えていく。
In this way, the long bearing member 3 is locked to the building frame 1 by the fixing pins 8 and the like during lifting, and the elevator body 4 is locked to the building frame 1 by the support hardware 9 and the like when not lifting, The elongate support member 3 from which the fixing pins 8 and the like have been removed is repeatedly moved up and down with respect to the elevator body 4, and the installation is sequentially switched to the upper floor.

【0024】なお、図示の例は本発明装置を躯体1内に
設ける場合であるが、躯体1外に設ける場合も同様であ
り、その場合には支持金物9は躯体1から突出するよう
に設けるものとなる。
Although the illustrated example shows the case where the device of the present invention is provided inside the frame 1, the same applies to the case where the device is provided outside the frame 1, in which case the supporting metal 9 is provided so as to project from the frame 1. Will be things.

【0025】[0025]

【発明の効果】以上述べたように本発明の揚重装置およ
びその使用方法は、機器を必要な長さのものに限定して
これを転用することで不使用となる無駄の部分を無く
し、また、この転用のための移動や昇降機体の移動は自
動的に安定した状態で行われ、しかも、移動後のだめ穴
等の未作業部分の存在を少なくして工期の短縮化が実現
できるものである。
As described above, the hoisting device and the method of using the hoisting device of the present invention eliminate the wasteful part which is not used by limiting the equipment to a required length and diverting it. In addition, the movement for this diversion and the movement of the elevator body are automatically performed in a stable state, and further, the existence of unworked parts such as dead holes after the movement can be reduced to shorten the construction period. is there.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の揚重装置の1実施例を示す側面図であ
る。
FIG. 1 is a side view showing an embodiment of a lifting device of the present invention.

【図2】本発明の揚重装置の1実施例を示す正面図であ
る。
FIG. 2 is a front view showing an embodiment of a lifting device of the present invention.

【図3】本発明の揚重装置の昇降時の第1工程の説明図
である。
FIG. 3 is an explanatory diagram of a first step of lifting and lowering the lifting device of the present invention.

【図4】本発明の揚重装置の昇降時の第2工程の説明図
である。
FIG. 4 is an explanatory view of a second step of lifting and lowering the lifting device of the present invention.

【図5】本発明の揚重装置の昇降時の第3工程の説明図
である。
FIG. 5 is an explanatory view of a third step of lifting and lowering the lifting device of the present invention.

【図6】本発明の揚重装置の昇降時の第4工程の説明図
である。
FIG. 6 is an explanatory view of a fourth step of lifting and lowering the lifting device of the present invention.

【図7】従来例を示す説明図である。FIG. 7 is an explanatory diagram showing a conventional example.

【符号の説明】[Explanation of symbols]

1…躯体 2…開口 3…長尺支承部材 4…昇降機体 5…ラック 6…モーター 7…ピニオン 8…固定ピン 9…支持金物 10…レールサポ
ート 11…ガイドローラ 12…頂部サポー
ト 13…バッファスプリング 14…ガイドロー
ラ 15…吊り材 16…サポート 17…転倒防止金物
1 ... Frame 2 ... Opening 3 ... Long support member 4 ... Elevator body 5 ... Rack 6 ... Motor 7 ... Pinion 8 ... Fixing pin 9 ... Support metal 10 ... Rail support 11 ... Guide roller 12 ... Top support 13 ... Buffer spring 14 … Guide rollers 15… Hanging materials 16… Supports 17… Fall prevention hardware

───────────────────────────────────────────────────── フロントページの続き (72)発明者 荻原 行正 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 鶴岡 松生 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 颯田 敏和 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 三尾 興平 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 白井 俊輔 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平3−259887(JP,A) 特公 昭59−17020(JP,B2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yukimasa Ogihara 1-2-7 Moto Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Matsuo Tsuruoka 1-2-7 Moto-Akasaka, Minato-ku, Tokyo No. Kashima Construction Co., Ltd. (72) Inventor Toshikazu Isada 1-2-7 Moto Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Kohei Mio 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima In Construction Co., Ltd. (72) Inventor Shunsuke Shirai, 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (56) Reference JP-A-3-259887 (JP, A) Japanese Patent Publication Sho 59-17020 (JP, B2)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 支柱やガイド等の長尺支承部材側のラッ
クと、ケージや荷台等の昇降機体に設けたモーターのピ
ニオンとを噛合して長尺支承部材に沿って昇降機体が昇
降する揚重装置において、前記長尺支承部材は、3階以
上の数階分を掛渡せる長さからなり、建物躯体の床に着
脱自在に係止する係止部材を長尺支承部材の途中に、ま
た、折り畳み可能な頂部サポートを頂部に設け、建物躯
体側に前記長尺支承部材を抱持する枠状の転倒防止金物
を取付け可能とし、一方、前記昇降機体には建物躯体の
床への係止部材を着脱自在に取付けることを特徴とする
揚重装置。
1. A hoist that raises and lowers an elevator body along a long bearing member by engaging a rack on the side of the long bearing member such as a column and a guide with a pinion of a motor provided on the elevator body such as a cage and a loading platform. In the heavy equipment, the long bearing member has a length that can span several floors of three or more floors, and a locking member that is detachably locked to the floor of the building frame is provided in the middle of the long bearing member. , A foldable top support is provided at the top, and a frame-shaped fall prevention hardware that holds the long support member can be attached to the building body side, while the elevator body is locked to the floor of the building body. A lifting device characterized in that members are detachably attached.
【請求項2】 支柱やガイド等の長尺支承部材側のラッ
クと、ケージや荷台等の昇降機体に設けたモーターのピ
ニオンとを噛合して長尺支承部材に沿って昇降する昇降
機体で揚重を行う揚重方法において、長尺支承部材は、
3階以上の数階分を掛渡せる長さからなり、建物躯体に
着脱自在に係止する係止部材を長尺支承部材の途中に、
また、折り畳み可能な頂部サポートを頂部に設け、建物
躯体側に前記長尺支承部材を抱持する枠状の転倒防止金
物を取付け可能とし、一方、前記昇降機体には建物躯体
の床部分への係止部材を着脱自在に取付ける揚重装置を
使用し、揚重時には、長尺支承部材を係止部材及び頂部
サポートにより建物躯体に係止し、昇降機体を昇降さ
せ、非揚重時に、昇降機体を係止部材を介して建物躯体
に係止し、転倒防止金物を取付けて長尺支承部材を抱持
し、昇降機体に対して係止部材及び頂部サポートでの係
止を解除した長尺支承部材を前記昇降機体に設けたモー
ターの駆動で長手方向の延長線上に昇降させることを特
徴とする揚重装置の使用方法。
2. A hoist that lifts up and down along a long bearing member by engaging a rack on the side of the long bearing member such as a column or a guide with a pinion of a motor provided on the elevator body such as a cage or a loading platform. In the lifting method of carrying out weight, the long bearing member is
It has a length that can span several floors of the third floor and above, and a locking member that removably locks to the building frame is provided in the middle of the long bearing member.
Further, a foldable top support is provided at the top, and a frame-shaped fall-prevention hardware for holding the long support member can be attached to the side of the building body, while the elevator body is attached to the floor portion of the building body. Using a lifting device that detachably attaches the locking member, at the time of lifting, the long bearing member is locked to the building frame by the locking member and the top support to raise and lower the elevator body The body is locked to the building frame via the locking member, the fall prevention hardware is attached, the long support member is held, and the locking member and the top support are unlocked from the elevator body. A method of using a hoisting device, characterized in that a supporting member is moved up and down along an extension line in a longitudinal direction by driving a motor provided on the elevator body.
JP29637492A 1992-10-07 1992-10-07 Lifting device and method of using the same Expired - Lifetime JP2565458B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29637492A JP2565458B2 (en) 1992-10-07 1992-10-07 Lifting device and method of using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29637492A JP2565458B2 (en) 1992-10-07 1992-10-07 Lifting device and method of using the same

Publications (2)

Publication Number Publication Date
JPH06115858A JPH06115858A (en) 1994-04-26
JP2565458B2 true JP2565458B2 (en) 1996-12-18

Family

ID=17832729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29637492A Expired - Lifetime JP2565458B2 (en) 1992-10-07 1992-10-07 Lifting device and method of using the same

Country Status (1)

Country Link
JP (1) JP2565458B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006019622A1 (en) * 2006-04-25 2007-11-15 Hek Manufacturing B.V. Mast platform and method for height adjustment
DE102006029653B4 (en) 2006-06-28 2009-02-12 Doka Industrie Gmbh Lifting platform and method for building a lifting platform
JP7133509B2 (en) * 2019-05-28 2022-09-08 大成建設株式会社 Vertical shaft construction stage system and vertical shaft construction method
CN112320588A (en) * 2020-11-02 2021-02-05 四川沿江攀宁高速公路有限公司 A large-section foundation pit manual excavation auxiliary device
IT202100025607A1 (en) * 2021-10-07 2023-04-07 Fiorenzo Sartor CONSTRUCTION HOISTS AND PROCEDURE FOR THE PREPARATION OF A CONSTRUCTION HOIST

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5917020A (en) * 1982-07-20 1984-01-28 Toshiba Corp Rotary body supporter
JPH03259887A (en) * 1990-03-09 1991-11-19 Hazama Gumi Ltd Lifter for building work and its transferring

Also Published As

Publication number Publication date
JPH06115858A (en) 1994-04-26

Similar Documents

Publication Publication Date Title
CN111491885A (en) Lifting platform system for multi-storey building construction
JP2565458B2 (en) Lifting device and method of using the same
WO2020142001A1 (en) A moveable platform
KR20040104223A (en) Scaffolding having vertically moving workplace
JP2612974B2 (en) Mounting method of outer wall PC members
JP3411845B2 (en) Lifting mechanism and construction machinery
JP2001039652A (en) Self climbing lift
JP2702052B2 (en) Windbreak equipment for cargo handling equipment
JP3422585B2 (en) Elevating construction elevator and method of extending the elevator mast in the descending direction
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JPH092780A (en) Jib-type traveling crane with jack-up
JP2512196B2 (en) Construction material hoisting device and hoisting method
JPH1088787A (en) Knocked-down gondola in elevatable parking device
JPH10167668A (en) Vertical and horizontal transporting device and its operation
JPH0949334A (en) Traveling carriage to carry building member and carrying method of building member
JPH10140845A (en) Fall preventive device of horizontal opening part
JPH0530009Y2 (en)
JP3024523U (en) Lift-up device used for construction work
JP2666204B2 (en) Lifting equipment
JPH11106164A (en) Temporary elevator device for construction equipment and material conveyance
JPH0262306A (en) Climbing construction method of tower crane
JPH06219515A (en) In/out device with cab
JPH09100629A (en) Beam member fitting device and beam member fitting method
JPH07286368A (en) Method and device for lifting up the top floor frame for structure construction
JPS5855236Y2 (en) Converter bricklaying equipment