JP2023015912A - How to replace wall balustrades - Google Patents

How to replace wall balustrades Download PDF

Info

Publication number
JP2023015912A
JP2023015912A JP2021119995A JP2021119995A JP2023015912A JP 2023015912 A JP2023015912 A JP 2023015912A JP 2021119995 A JP2021119995 A JP 2021119995A JP 2021119995 A JP2021119995 A JP 2021119995A JP 2023015912 A JP2023015912 A JP 2023015912A
Authority
JP
Japan
Prior art keywords
wall balustrade
balustrade
wall
existing
replacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2021119995A
Other languages
Japanese (ja)
Other versions
JP7021386B1 (en
Inventor
昂太 庄野
Kota Shono
明夫 正司
Akio Shoji
裕司 神谷
Yuji Kamiya
昭一 小坂
Shoichi Kosaka
寛幸 一ノ瀬
Hiroyuki Ichinose
幸生 夛田
Yukio Tada
進 松崎
Susumu Matsuzaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
K Con Co Ltd
Central Nippon Expressway Co Ltd
Oriental Shiraishi Corp
Original Assignee
K Con Co Ltd
Central Nippon Expressway Co Ltd
Oriental Shiraishi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by K Con Co Ltd, Central Nippon Expressway Co Ltd, Oriental Shiraishi Corp filed Critical K Con Co Ltd
Priority to JP2021119995A priority Critical patent/JP7021386B1/en
Application granted granted Critical
Publication of JP7021386B1 publication Critical patent/JP7021386B1/en
Publication of JP2023015912A publication Critical patent/JP2023015912A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【課題】最小限の交通規制で施工が可能な壁高欄の取替方法を提供する。【解決手段】鉄筋コンクリート製の既設の壁高欄(RC壁高欄10)を鉄筋コンクリート製の新設の壁高欄(PCa壁高欄1)に取り替える壁高欄の取替方法において、既設の床版11の水切り部14を斫り取る既設水切り部斫り工程を行った後、新設の水切り部14’を既設の壁高欄(RC壁高欄10)の撤去前に先行施工する新設水切り部先行施工工程を行う。【選択図】図4[Problem] To provide a method for replacing a wall railing that can be constructed with minimal traffic restrictions. [Solution] In a wall balustrade replacement method of replacing an existing wall balustrade made of reinforced concrete (RC wall balustrade 10) with a new wall balustrade made of reinforced concrete (PCa wall balustrade 1), a drainage portion 14 of an existing floor slab 11 is provided. After carrying out the process of cutting out the existing draining part, a new draining part preliminary construction process is carried out in which a new draining part 14' is constructed in advance before the removal of the existing wall railing (RC wall railing 10). [Selection diagram] Figure 4

Description

本発明は、壁高欄の取替方法に関し、詳しくは、既設の鉄筋コンクリート製の壁高欄をプレキャスト鉄筋コンクリート製のPCa壁高欄に取り替える壁高欄の取替方法に関する。 TECHNICAL FIELD The present invention relates to a method for replacing wall balustrades, and more particularly to a method for replacing existing reinforced concrete wall balustrades with PCa wall balustrades made of precast reinforced concrete.

高架橋や道路から車両等が路外や歩道等に逸脱するのを防ぐとともに、車両乗員の傷害及び車両の破損を最小限にとどめて、車両を正常な進行方向に復元させることを目的とする剛性防護柵である既設の壁高欄を取り替える際には、道路を通過する車両等の交通規制が必要となる。また、交通規制の期間を短くすることは、経済損失を抑えることにつながるため、交通規制期間を最小限にとどめたいとい要請が極めて強い。また、道路使用者からの苦情等を減少させることにつながるため、工事のスムーズな進行を促進させることとなる。 Rigidity designed to prevent vehicles from deviating from elevated bridges and roads to the outside of roads and sidewalks, minimize injuries to vehicle occupants and damage to vehicles, and restore vehicles to the normal direction of travel. When replacing the existing wall balustrade, which is a protective fence, it is necessary to restrict traffic such as vehicles passing on the road. In addition, since shortening the period of traffic regulation leads to restraining economic loss, there is a strong demand for minimizing the period of traffic regulation. In addition, since it leads to a reduction in complaints from road users, it promotes the smooth progress of construction work.

そこで、本発明では、既設の壁高欄を床版上面及び床版側面の壁高欄に面した部位から撤去する際に、事前に床版側面部を撤去しておき、後から床版上面を撤去し、新設の壁高欄を設置することとした。床版側面(水切り部)の撤去作業を交通規制せずにあるいは最小限の交通規制(車線規制、路肩規制など)にて行えるため、交通規制にともなう交通渋滞を最小限に抑えることが可能になるからである。特に、水切り部である床版側面には、横締定着具や横締PC鋼材が配置されているものや、主桁から鉄筋が配置されているものがあるため、慎重に撤去する必要がある。この慎重に時間をかけて作業を行う必要のある床版側面部の撤去作業を、交通規制を行わない、あるいは最小限の交通規制で行えるため、交通規制にともなう交通渋滞を最小限に抑えることが可能になる。 Therefore, in the present invention, when removing the existing wall balustrade from the part facing the floor slab upper surface and floor slab side wall balustrade, the floor slab side part is removed in advance, and the floor slab upper surface is removed later. However, it was decided to install a new wall balustrade. It is possible to minimize traffic congestion due to traffic regulations because the removal work of the side of the floor slab (drainage part) can be done without traffic restrictions or with minimal traffic restrictions (lane restrictions, road shoulder restrictions, etc.) Because it becomes In particular, on the side of the floor slab, which is the drainage part, there are horizontal tightening fixtures, horizontal tightening PC steel materials, and reinforcing bars from the main girder, so it is necessary to carefully remove them. . The removal work of the side of the floor slab, which requires a lot of time and care, can be done without traffic restrictions or with minimal traffic restrictions, thus minimizing traffic congestion caused by traffic restrictions. becomes possible.

一方、特許文献1には、張出し方向の一方の側から順次、複数の桁ブロック2の側部に地覆5を設けてゆくとともに、張出方向の一方の側から順次、地覆5を設けた桁ブロック2に対し、挿通孔に定着筋3を挿通させて壁高欄ブロック7を固定設置し、複数の壁高欄ブロック7を橋軸方向に並設して高欄を構築するようにした橋梁の施工方法が開示されている(特許文献1の特許請求の範囲の請求項1、明細書の段落[0019]~[0028]、図面の図1,図2等参照)。 On the other hand, in Patent Document 1, the ground guard 5 is sequentially provided on the side of a plurality of girder blocks 2 from one side in the overhang direction, and the ground guard 5 is provided sequentially from one side in the overhang direction. A wall balustrade block 7 is fixedly installed by inserting a fixing bar 3 through an insertion hole to a girder block 2, and a plurality of wall balustrade blocks 7 are arranged side by side in the bridge axis direction to construct a balustrade. A construction method is disclosed (see claim 1 of patent document 1, paragraphs [0019] to [0028] of the specification, Figs. 1 and 2 of the drawings, etc.).

しかし、特許文献1に記載の橋梁の施工方法は、橋梁の新設時に、床版にプレストレスをかけるPC鋼材の定着具廻りをコンクリートで覆って端部処理するために、壁高欄ブロック7設置前に先行して地覆5を構築するものであり、壁高欄の取替作業に適用できるものではなく、当然、交通規制を短縮できるものでもなかった。 However, in the bridge construction method described in Patent Document 1, at the time of new construction of a bridge, in order to cover the surroundings of the fixture of the PC steel material that applies prestress to the floor slab with concrete and to process the end, However, it is not applicable to the replacement work of the wall balustrade, and of course, it is not possible to shorten the traffic regulation.

また、特許文献2には、橋梁10に打設される壁高欄の路面10rとは反対側に取り付けられるプレキャストコンクリート側溝1を、プレキャスト壁高欄のコンクリートが打設前に設置するプレキャストコンクリート側溝の取付方法が開示されている(特許文献2の明細書の段落[0026]~[0044]、図面の図2~図5等参照)。 Moreover, in Patent Document 2, a precast concrete gutter 1 is installed on the side opposite to the road surface 10r of the wall balustrade placed on the bridge 10. A method is disclosed (see paragraphs [0026] to [0044] of the specification of Patent Document 2, FIGS. 2 to 5 of the drawings, etc.).

しかし、特許文献2に記載のプレキャストコンクリート側溝の取付方法も、橋梁の新設時の側溝の取付方法に付随して、床版側面を先行施工するものであり、特許文献1に記載の橋梁の施工方法と同様に、壁高欄の取替作業に適用できるものではなく、当然、交通規制を短縮できるものでもなかった。 However, the method for installing a precast concrete gutter described in Patent Document 2 is also accompanied by the method for installing a gutter at the time of constructing a new bridge, and the floor slab side is precedently constructed, and the construction of the bridge described in Patent Document 1 As with the method, it was not applicable to replacement work of wall balustrades, and of course, it was not possible to shorten traffic regulations.

特開2018-178588号公報JP 2018-178588 A 特開2019-131960号公報JP 2019-131960 A

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、最小限の交通規制で施工が可能な壁高欄の取替方法を提供することにある。 SUMMARY OF THE INVENTION Accordingly, the present invention has been devised in view of the above problems, and its object is to provide a method for replacing wall balustrades that can be constructed with minimal traffic restrictions.

請求項1に係る壁高欄の取替方法は、鉄筋コンクリート製の既設の壁高欄を鉄筋コンクリート製の新設の壁高欄に取り替える壁高欄の取替方法であって、既設の床版の水切り部を斫り取る既設水切り部斫り工程を行った後、新設の水切り部を前記既設の壁高欄の撤去前に先行施工する新設水切り部先行施工工程を行うことを特徴とする。 A wall balustrade replacement method according to claim 1 is a wall balustrade replacement method for replacing an existing reinforced concrete wall balustrade with a new reinforced concrete wall balustrade. After performing the step of removing the existing draining part, a new draining part precedent construction process is performed in which the new draining part is preliminarily constructed before the existing wall balustrade is removed.

請求項2に係る壁高欄の取替方法は、請求項1に係る壁高欄の取替方法において、前記既設水切り部斫り工程及び前記新設水切り部先行施工工程は、仮設足場から車線規制を行わないで行うことを特徴とする。 The wall balustrade replacement method according to claim 2 is the wall balustrade replacement method according to claim 1, wherein the step of removing the existing draining portion and the preceding step of constructing the new draining portion include lane control from temporary scaffolding. It is characterized in that it is performed without

請求項3に係る壁高欄の取替方法は、請求項1又は2に係る壁高欄の取替方法において、前記新設水切り部先行施工工程を行う前に、前記新設の水切り部を支持する埋込み鉄筋用のアンカー孔を削孔するアンカー孔削孔工程を行うことを特徴とする。 The wall balustrade replacement method according to claim 3 is the method for replacing wall balustrades according to claim 1 or 2, wherein embedded reinforcing bars for supporting the newly-established ditching section are performed before performing the newly-established ditching section preceding construction step. An anchor hole drilling step is performed to drill an anchor hole for use.

請求項4に係る壁高欄の取替方法は、請求項1ないし3のいずれかに記載の壁高欄の取替方法において、前記新設の壁高欄を設置する壁高欄設置工程では、プレキャスト鉄筋コンクリート製のPCa壁高欄を設置することを特徴とする。 A wall balustrade replacement method according to claim 4 is the wall balustrade replacement method according to any one of claims 1 to 3, wherein in the wall balustrade installation step of installing the new wall balustrade, precast reinforced concrete It is characterized by installing PCa wall balustrades.

請求項5に係る壁高欄の取替方法は、請求項4に記載の壁高欄の取替方法において、前記壁高欄設置工程では、床版を貫通して両端に支圧板が装着されたアンカー部材で前記PCa壁高欄を固定することを特徴とする。 A wall balustrade replacement method according to claim 5 is the wall balustrade replacement method according to claim 4, wherein in the wall balustrade installation step, anchor members having bearing pressure plates attached to both ends through a floor slab are installed. and fixing the PCa wall balustrade.

請求項6に係る壁高欄の取替方法は、請求項4又は5に記載の壁高欄の取替方法において、前記壁高欄設置工程では、床版及び前記PCa壁高欄の外側面には、炭素繊維シート接着することを特徴とする。 The wall balustrade replacement method according to claim 6 is the wall balustrade replacement method according to claim 4 or 5, wherein in the wall balustrade installation step, the outer surface of the floor slab and the PCa wall balustrade is coated with carbon. It is characterized by bonding fiber sheets.

請求項1~6に係る発明によれば、既設の床版の水切り部を斫り取った後、新設の水切り部を既設の壁高欄の撤去前に先行施工するので、最小限の交通規制で既設の壁高欄を新しい壁高欄に取り替えることができる。また、請求項1~6に係る発明によれば、慎重に作業する必要のある水切り部を斫り取って撤去する作業を、足場上作業として車線規制を行わない車線規制外作業として行うことができる。このため、車線規制の規制時間を気にせず、時間をかけて慎重に水切り部の撤去作業を行うことが可能となる。 According to the inventions according to claims 1 to 6, after scraping off the draining part of the existing floor slab, the new draining part is constructed prior to the removal of the existing wall balustrade, so traffic regulation is minimized. The existing balustrade can be replaced with a new balustrade. In addition, according to the inventions of claims 1 to 6, the work of scraping off and removing the draining part, which needs to be done carefully, can be performed as a work on the scaffolding that does not carry out lane regulations and is outside lane regulations. can. For this reason, it is possible to carefully remove the water draining portion over time without worrying about the regulation time of the lane regulation.

特に、請求項3に係る発明によれば、アンカー孔削孔工程を行うので、次工程である新設水切り部先行施工工程をより短時間に効率よく行うことができる。 In particular, according to the third aspect of the invention, since the anchor hole drilling step is performed, the next step, the pre-construction step of the newly installed draining portion, can be efficiently performed in a shorter time.

特に、請求項4に係る発明によれば、PCa壁高欄を設置するので、コンクリートが所定の強度を発現する養生期間を大幅に短縮して壁高欄の取替作業を行うことができる。 In particular, according to the fourth aspect of the invention, since the PCa wall balustrade is installed, the wall balustrade can be replaced while the curing period required for the concrete to develop a predetermined strength is greatly shortened.

特に、請求項5に係る発明によれば、床版を貫通して両端に支圧板が装着されたアンカー部材でPCa壁高欄を固定するので、PCa壁高欄を設置する作業をさらに短縮することができる。 In particular, according to the fifth aspect of the invention, since the PCa wall balustrade is fixed by the anchor member that penetrates the floor slab and has bearing pressure plates attached to both ends, the work for installing the PCa wall balustrade can be further shortened. can.

特に、請求項6に係る発明によれば、床版及びPCa壁高欄の外側面に炭素繊維シートを接着するので、橋梁外側からの衝突荷重とは逆向きの外力にも対応することができる。 In particular, according to the sixth aspect of the invention, since the carbon fiber sheet is adhered to the outer surface of the floor slab and the PCa wall balustrade, it is possible to cope with an external force in the direction opposite to the collision load from the outside of the bridge.

図1は、既設のRC壁高欄の構造を示すRC壁高欄を橋軸方向に見た鉛直である。FIG. 1 is a vertical view of the RC wall balustrade showing the structure of the existing RC wall balustrade in the direction of the bridge axis. 図2は、本発明の実施形態に係る壁高欄の取替方法の既設水切り部斫り工程を説明する工程説明図である。FIG. 2 is a process explanatory diagram for explaining a process of stripping the existing draining part of the method for replacing the wall balustrade according to the embodiment of the present invention. 図3は、同上の壁高欄の取替方法のアンカー孔削孔工程を示す工程説明図である。FIG. 3 : is process explanatory drawing which shows the anchor hole drilling process of the replacement method of a balustrade same as the above. 図4は、同上の壁高欄の取替方法の新設水切り部先行施工工程を示す工程説明図である。FIG. 4 is a process explanatory diagram showing a new water drain section precedent construction process of the method for replacing the wall balustrade same as the above. 図5は、同上の壁高欄の取替方法の壁高欄切断撤去工程を示す工程説明図である。FIG. 5 : is process explanatory drawing which shows the wall balustrade cutting removal process of the replacement method of a wall balustrade same as the above. 図6は、同上の壁高欄の取替方法の壁高欄設置工程を示す工程説明図である。FIG. 6 : is process explanatory drawing which shows the wall balustrade installation process of the replacement method of a wall balustrade same as the above.

以下、本発明に係る壁高欄の取替方法の一実施形態について、図面を参照しながら詳細に説明する。 Hereinafter, one embodiment of a method for replacing a wall balustrade according to the present invention will be described in detail with reference to the drawings.

本発明の実施形態に係る壁高欄の取替方法は、既設のRC壁高欄10(鉄筋コンクリート製の壁高欄)をPCa壁高欄1(プレキャスト鉄筋コンクリート製の壁高欄)に取り替える際に好適に適用される。図1は、既設のRC壁高欄の構造を示すRC壁高欄を橋軸方向に見た鉛直断面図である。 The wall balustrade replacement method according to the embodiment of the present invention is preferably applied when replacing the existing RC wall balustrade 10 (reinforced concrete wall balustrade) with the PCa wall balustrade 1 (precast reinforced concrete wall balustrade). . FIG. 1 is a vertical sectional view showing the structure of an existing RC wall balustrade as viewed in the bridge axis direction.

先ず、簡単に既設のRC壁高欄10及びその周辺の構成について説明する。図1に示すように、既設のRC壁高欄10は、橋梁の外縁に沿って床版11の上面より段違いに高くなるよう地覆部12が形成され、この地覆部12を基礎として床版11の外縁に沿って地覆部12の上方に突設されている。 First, the structure of the existing RC wall balustrade 10 and its periphery will be briefly described. As shown in FIG. 1, the existing RC wall balustrade 10 is formed with a covering portion 12 along the outer edge of the bridge so as to be higher than the upper surface of the floor slab 11. 11 is protruded above the ground covering portion 12 along the outer edge of the base portion 11 .

また、既設の床版11の外側面には、下端が床版11の一般部13より下端面が低くなるように水切り部14が形成されている。この水切り部14は、一般部13の下面より水切り部14の下端面が低くなっていることで、雨水等の降水が、床版11の上面から側面を伝って回り込んで一般部13の下面に到達することを軽減する機能を有している。 In addition, a draining portion 14 is formed on the outer surface of the existing floor slab 11 so that the lower end surface is lower than the general portion 13 of the floor slab 11 . Since the lower end surface of the water draining portion 14 is lower than the lower surface of the general portion 13 , precipitation such as rainwater flows from the upper surface of the floor slab 11 along the side surface and wraps around the lower surface of the general portion 13 . It has a function to reduce reaching

[壁高欄の取替方法]
次に、図2~図6を用いて、本発明の実施形態に係る壁高欄の取替方法について説明する。図2は、本発明の実施形態に係る壁高欄の取替方法の既設水切り部斫り工程を説明する工程説明図である。
[How to replace wall balustrades]
Next, a method for replacing a wall balustrade according to an embodiment of the present invention will be described with reference to FIGS. 2 to 6. FIG. FIG. 2 is a process explanatory diagram for explaining a process of stripping the existing draining part of the method for replacing the wall balustrade according to the embodiment of the present invention.

(水切り部斫り工程:車線規制外足場作業)
先ず、図2に示すように、本実施形態に係る壁高欄の取替方法では、既設の床版11の外側面に相当する水切り部14を斫り取る既設水切り部斫り工程を行う。本工程は、地覆部12の直下及びその外側に吊足場などの仮設足場を設置し、足場上作業として車線規制を行わない車線規制外作業として行う。
(Draining process: scaffolding work outside lane regulations)
First, as shown in FIG. 2, in the method for replacing the wall balustrade according to the present embodiment, an existing draining portion scraping step is performed to scrape off the draining portion 14 corresponding to the outer surface of the existing floor slab 11 . In this step, a temporary scaffolding such as a suspended scaffolding is installed immediately below and outside of the ground protection part 12, and the work is performed as work outside the lane regulation, which is not carried out as work on the scaffolding.

具体的には、本工程では、エアーピックなどの斫り機を用いて、図2の斜線部で示す床版11の水切り部14を斫り落とす。このとき、地覆部12の斜線部で示す外側の下角部も一緒に斫り取る。後述の水切り部新設工程でコンクリートを流し込むスペースと棒状バイブレータを差し込むスペースを確保するためである。但し、床版11は、道路の本線として供用中であるため、斫り取る部分は、最小限に止まるように注意する。 Specifically, in this step, a scraping machine such as an air pick is used to scrape off the draining portion 14 of the floor slab 11 indicated by the hatched portion in FIG. At this time, the outer lower corner portion indicated by the hatched portion of the ground covering portion 12 is also scraped off. This is to secure a space for pouring concrete and a space for inserting a rod-shaped vibrator in the later-described step of installing a draining portion. However, since the floor slab 11 is in service as the main road, care should be taken to keep the scraped portion to a minimum.

なお、本工程では、コンクリートを斫り取った後の既設の水切り部14及び地覆部12の不要となる一部の鉄筋も撤去する。 In addition, in this step, some unnecessary reinforcing bars of the existing drainage part 14 and the ground covering part 12 after scraping off the concrete are also removed.

背景技術で述べたように、水切り部14である床版側面には、横締定着具や横締PC鋼材が配置されているものや、主桁から鉄筋が配置されているものがあるため、慎重に撤去する必要がある。しかし、本実施形態に係る壁高欄の取替方法では、本工程を足場上作業として車線規制を行わない車線規制外作業として行うため、規制時間を気にせず、時間をかけて慎重に行うことが可能となる。このため、PC鋼材を誤って傷つけ切断し、プレストレスの緊張力が開放されてPC鋼材が突出するような重大な事故が起こるおそれを低減することができる。 As described in the background art, on the side of the floor slab, which is the draining part 14, there are cases where horizontal tightening fixtures and horizontal tightening PC steel materials are arranged, and there are cases where reinforcing bars are arranged from the main girder. It must be removed carefully. However, in the method for replacing the wall balustrade according to the present embodiment, this process is carried out as a work on the scaffolding and as a work outside the lane regulation without lane regulation. becomes possible. For this reason, it is possible to reduce the risk of a serious accident in which the PC steel material is accidentally damaged and cut, and the tension of the prestress is released, causing the PC steel material to protrude.

(アンカー孔削孔工程:車線規制外足場作業)
次に、図3に示すように、本実施形態に係る壁高欄の取替方法では、新設の水切り部14’を支持する埋込み鉄筋用の横方向アンカー孔15を削孔するアンカー孔削孔工程を行う(図4も参照)。また、車線規制作業を減らすために、横方向アンカー孔15の削孔作業と同時並行して、本工程では、後述のアンカー部材2を挿通する上下貫通アンカー孔17も削孔する。本工程も、前工程と同様に、足場上作業として車線規制を行わない車線規制外作業として行う。図3は、本実施形態に係る壁高欄の取替方法のアンカー孔削孔工程を示す工程説明図である。
(Anchor hole drilling process: Scaffolding work outside lane restrictions)
Next, as shown in FIG. 3, in the wall balustrade replacement method according to the present embodiment, an anchor hole drilling step of drilling the horizontal anchor holes 15 for the embedded reinforcing bars that support the newly installed drain section 14'. (see also Figure 4). In addition, in order to reduce lane control work, in parallel with the drilling work of the lateral anchor holes 15, in this step, the vertical through anchor holes 17 through which the anchor members 2 described later are inserted are also drilled. As in the previous process, this process is also carried out as a work on the scaffolding that does not have lane restrictions and is outside lane restrictions. FIG. 3 is a process explanatory diagram showing the anchor hole drilling process of the method for replacing the wall balustrade according to the present embodiment.

具体的には、本工程では、埋込み鉄筋16としてD16の異形鋼棒を想定していることから、ダイヤモンドコアビットを装着したコアドリル等を用いて直径φ26mm×深さ250mmの横方向アンカー孔15を削孔する。また、後述のように、アンカー部材2としてM24×510mmのアンカーボルト20を想定している。よって、本工程では、横方向アンカー孔15の削孔作業と並行して、コアドリル等を用いて、床版11の下面から床版11を貫通して地覆部12に達する直径φ44mm程度の上下貫通アンカー孔17を削孔する。 Specifically, in this process, since a D16 deformed steel bar is assumed as the embedded reinforcing bar 16, a horizontal anchor hole 15 with a diameter of φ26 mm and a depth of 250 mm is drilled using a core drill or the like equipped with a diamond core bit. pierce. Moreover, as will be described later, an anchor bolt 20 of M24×510 mm is assumed as the anchor member 2 . Therefore, in this process, in parallel with the drilling work of the horizontal anchor holes 15, a core drill or the like is used to penetrate the floor slab 11 from the bottom surface of the floor slab 11 and reach the ground covering portion 12. A through anchor hole 17 is drilled.

なお、本実施形態に係る壁高欄の取替方法では、既設橋梁の劣化度から横方向アンカー孔15の削孔中の周囲のコンクリートの剥落が懸念される場合を考慮して、既設の床版11の床版厚220mmで1段の配筋として、床版厚の中央付近に一か所の削孔としている。勿論、埋込み鉄筋16は、既設の床版11の床版厚やコンクリートの劣化度に応じて適宜設定して配筋すればよいことは云うまでもない。 In the method for replacing the wall balustrade according to this embodiment, considering the degree of deterioration of the existing bridge, the surrounding concrete may fall off during the drilling of the lateral anchor holes 15. 11 with a floor slab thickness of 220 mm and a one-stage bar arrangement, with one hole drilled near the center of the floor slab thickness. Needless to say, the embedded reinforcing bars 16 may be appropriately set and arranged according to the floor slab thickness of the existing floor slab 11 and the degree of deterioration of the concrete.

(新設水切り部先行施工工程:車線規制外足場作業)
次に、図4に示すように、本実施形態に係る壁高欄の取替方法では、新設の水切り部14’を既設のRC壁高欄10の撤去前に先行施工する新設水切り部先行施工工程を行う。本工程も、前工程や水切り部斫り工程と同様に、足場上作業として車線規制を行わない車線規制外作業として行う。図4は、本実施形態に係る壁高欄の取替方法の新設水切り部先行施工工程を示す工程説明図である。
(Preceding construction process for the new drainage section: Scaffolding work outside lane regulations)
Next, as shown in FIG. 4, in the method for replacing the wall balustrade according to the present embodiment, a new water draining portion precedent construction process is performed in which the new water draining portion 14 ′ is precedently constructed before the existing RC wall balustrade 10 is removed. conduct. This process, like the previous process and the water draining process, is also performed as a work outside the lane restriction as a work on the scaffolding. FIG. 4 is a process explanatory diagram showing a new draining section precedent construction process of the wall balustrade replacement method according to the present embodiment.

具体的には、埋込み鉄筋16として高付着型のエポキシ樹脂被覆鉄筋からなるL字状のD16の異形鋼棒を横方向アンカー孔15に変性ビニルエステル樹脂やエポキシ樹脂などの薬剤を用いて化学的に固着するとともに、配力筋などの所定の配筋を行う。その後、埋込み鉄筋16の周囲に70mm以上の所定のかぶり厚さを確保して型枠を設置し、小型の棒状バイブレータB1等を用いて締め固めを行いながら経時硬化材を充填して新設の水切り部14’を先行施工する。 Specifically, an L-shaped D16 deformed steel bar made of a high-adhesion type epoxy resin-coated reinforcing bar as the embedded reinforcing bar 16 is chemically applied to the horizontal anchor hole 15 using a chemical such as a modified vinyl ester resin or an epoxy resin. , and perform the prescribed reinforcement such as distributing reinforcement. After that, secure a predetermined cover thickness of 70 mm or more around the embedded reinforcing bars 16, install a formwork, and fill the time-hardened material while compacting it using a small bar-shaped vibrator B1 or the like to newly drain the water. The part 14' is preliminarily constructed.

このとき、新設の水切り部14’は、既設のコンクリートである既設の床版11との接触面の面積が小さく、しかも鉛直面で接しているため、肌別れしやすい構造となっている。このため、打設する経時硬化材は、ポリマーセメントモルタルなどの収縮率が小さく、既設コンクリートとの付着力に優れた材料が好ましい。 At this time, the newly installed water draining part 14' has a small contact surface area with the existing floor slab 11, which is the existing concrete, and is in contact with the existing floor slab 11 on the vertical plane, so that the structure is easy to separate. For this reason, it is preferable to use a material such as polymer cement mortar, which has a small shrinkage rate and excellent adhesion to the existing concrete, as the hardening material to be placed over time.

(壁高欄切断撤去工程:車線規制作業)
次に、図5に示すように、本実施形態に係る壁高欄の取替方法では、既設の地覆部12及びRC壁高欄10を切断撤去する壁高欄切断撤去工程を行う。本工程は、剛性防護柵であるRC壁高欄10を撤去するため、一部車線を通行止めにするなど車線規制を行って作業を行う。図5は、本実施形態に係る壁高欄の取替方法の壁高欄切断撤去工程を示す工程説明図である。
(Wall balustrade cutting and removal process: lane regulation work)
Next, as shown in FIG. 5 , in the wall balustrade replacement method according to the present embodiment, a wall balustrade cutting and removing step is performed to cut and remove the existing ground guard portion 12 and RC wall balustrade 10 . In this process, in order to remove the RC wall balustrade 10, which is a rigid protective fence, the work is carried out with lane restrictions such as closing some lanes. FIG. 5 is a process explanatory diagram showing a wall balustrade cutting and removing process of the wall balustrade replacement method according to the present embodiment.

具体的には、既設の床版11の上面に沿ってワイヤソーやウォールソーを用いて、既設の床版11の上面より上方となる既設の地覆部12及びRC壁高欄10を切断し、撤去する。 Specifically, using a wire saw or a wall saw along the upper surface of the existing floor slab 11, the existing ground covering portion 12 and the RC wall balustrade 10 above the upper surface of the existing floor slab 11 are cut and removed. do.

(壁高欄設置工程:車線規制作業)
次に、図6に示すように、本実施形態に係る壁高欄の取替方法では、新設のPCa壁高欄1を設置する壁高欄設置工程を行う。本工程は、前工程と同様に、一部車線を通行止めにするなど車線規制を行って作業を行う。図6は、本実施形態に係る壁高欄の取替方法の壁高欄設置工程を示す工程説明図である。
(Wall railing installation process: lane regulation work)
Next, as shown in FIG. 6, in the wall balustrade replacement method according to the present embodiment, a wall balustrade installation step of installing a new PCa wall balustrade 1 is performed. In this process, as in the previous process, work is carried out with lane restrictions such as closing some lanes. FIG. 6 is a process explanatory diagram showing a wall balustrade installation process of the wall balustrade replacement method according to the present embodiment.

具体的には、新設のPCa壁高欄1を搬入して、既設の床版11の外側の縁沿いに載置し、車線規制外足場作業として前述のアンカー孔削孔工程で削孔した上下貫通アンカー孔17にアンカーボルト20を挿通し、床版11を貫通するアンカー部材2でPCa壁高欄1をボルト止めして固定する。また、アンカー部材2の周り及びPCa壁高欄1と床版11との間には、斜線部で示すように、無収縮モルタルが充填される。 Specifically, the newly installed PCa wall balustrade 1 is brought in and placed along the outer edge of the existing floor slab 11, and the upper and lower penetrating holes drilled in the above-mentioned anchor hole drilling process as scaffolding work outside the lane regulation Anchor bolts 20 are inserted into the anchor holes 17, and the PCa wall balustrade 1 is fixed by bolting with the anchor members 2 penetrating the floor slab 11. - 特許庁In addition, non-shrinkage mortar is filled around the anchor members 2 and between the PCa balustrade 1 and the floor slab 11 as indicated by the shaded areas.

このアンカー部材2は、合金メッキされたS45CHからなるM24×長さ510mmのアンカーボルト20を基体とする部材であり、両端に、合金メッキされたSS400からなる直径φ140mm×厚さ25mmの円盤状の支圧板21が装着されている。この支圧板21は、緩止めナット22で止め付けられている。また、PCa壁高欄1に埋設された支圧板21の直下には、合金メッキされたSGDMからなる高ナット23が介装されており、PCa壁高欄1の下端から支圧板21までの所定の距離を確保している。なお、この高ナット23の周りには、直径φ6mmの丸鋼が餅網状に溶接されてエポキシ樹脂で被覆されたグリッド筋24が配筋されている。 This anchor member 2 is a member based on an anchor bolt 20 made of alloy-plated S45CH and measuring M24×length 510 mm. A bearing pressure plate 21 is attached. This bearing pressure plate 21 is fixed by a locking nut 22 . A high nut 23 made of alloy-plated SGDM is interposed directly below the bearing plate 21 embedded in the PCa wall balustrade 1, and a predetermined distance from the lower end of the PCa wall balustrade 1 to the bearing plate 21 is interposed. is ensured. Around the high nut 23, a grid bar 24 is arranged, which is made by welding round steel bars with a diameter of 6 mm in a mochi net shape and coating with epoxy resin.

また、本工程では、床版11の下方に設置されるアンカー部材2の下方の支圧板21の周りには、型枠が設置されて、セメントグラウト25が充填されて固結される。このアンカー部材2の下方の支圧板21には、無収縮モルタル26の充填を確認するための図示しない孔が形成されている。 Further, in this step, a formwork is installed around the bearing plate 21 below the anchor member 2 installed below the floor slab 11, and the cement grout 25 is filled and solidified. A hole (not shown) is formed in the bearing plate 21 below the anchor member 2 for checking the filling of the non-shrinkable mortar 26 .

そして、無収縮モルタル26の排出孔を塞ぐとともに補強するために、2方向200g/m2の目付量の上下幅720mmの補強用の炭素繊維シート3が床版11の外側面の下端付近から新設のPCa壁高欄1の外側面に亘り接着される。この炭素繊維シート3は、橋梁の外側から内側にPCa壁高欄1を押し倒すような外力に対抗する機能を有している。 A carbon fiber sheet 3 for reinforcement with a basis weight of 200 g/m 2 in two directions and a vertical width of 720 mm is newly installed near the lower end of the outer surface of the floor slab 11 in order to block the discharge hole of the non-shrinkable mortar 26 and reinforce it. is adhered over the outer surface of the PCa balustrade 1. This carbon fiber sheet 3 has a function of resisting an external force pushing down the PCa balustrade 1 from the outside to the inside of the bridge.

以上説明した本発明の実施形態に係る壁高欄の取替方法によれば、最小限の交通規制で既設のRC壁高欄10をPCa壁高欄1に取り替えることができる。また、本発明の実施形態に係る壁高欄の取替方法によれば、慎重に作業する必要のある水切り部14を斫り取って撤去する作業を、足場上作業として車線規制を行わない車線規制外作業として行うことができる。このため、本発明の実施形態に係る壁高欄の取替方法によれば、車線規制の規制時間を気にせず、時間をかけて慎重に水切り部14の撤去作業を行うことが可能となる。よって、PC鋼材を誤って傷つけ切断し、プレストレスの緊張力が開放されてPC鋼材が突出するような重大な事故が起こるおそれを低減することができる。 According to the wall balustrade replacement method according to the embodiment of the present invention described above, the existing RC wall balustrade 10 can be replaced with the PCa wall balustrade 1 with minimal traffic restrictions. Further, according to the method for replacing the wall balustrade according to the embodiment of the present invention, the work of scraping off and removing the draining part 14, which needs to be done carefully, is regarded as the work on the scaffolding, and the lane regulation is not performed. Can be done as outside work. Therefore, according to the method for replacing the wall balustrade according to the embodiment of the present invention, it is possible to carefully remove the water draining portion 14 over time without worrying about the regulation time of lane regulation. Therefore, it is possible to reduce the risk of a serious accident in which the PC steel material is erroneously damaged and cut, and the tension of the prestress is released, causing the PC steel material to protrude.

以上、本発明の実施形態に係る壁高欄の取替方法について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎない。よって、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。特に、各部材の素材や寸法等は、一例として例示したものであり、適宜、設計変更してよいことは云うまでもない。 The method for replacing the wall balustrade according to the embodiments of the present invention has been described in detail above, but the above-described or illustrated embodiments are all specific embodiments for carrying out the present invention. Not too much. Therefore, the technical scope of the present invention should not be construed to be limited by these. In particular, the material and dimensions of each member are given as an example, and needless to say, the design may be changed as appropriate.

1:PCa壁高欄(新設の壁高欄)
2:アンカー部材
20:アンカーボルト
21:支圧板
22:緩止めナット
23:高ナット
24:グリッド筋
25:セメントグラウト
26:無収縮モルタル
3:炭素繊維シート
10:RC壁高欄(既設の壁高欄)
11:床版
12:地覆部
13:一般部(床版)
14:水切り部(床版)
15:横方向アンカー孔
16:埋め込み鉄筋
17:上下貫通アンカー孔
B1:棒状バイブレータ
1: PCa wall balustrade (new wall balustrade)
2: Anchor member 20: Anchor bolt 21: Bearing plate 22: Locking nut 23: High nut 24: Grid line 25: Cement grout 26: Non-shrinking mortar 3: Carbon fiber sheet 10: RC wall balustrade (existing wall balustrade)
11: Floor slab 12: Undercover part 13: General part (floor slab)
14: Draining section (floor slab)
15: Horizontal anchor hole 16: Embedded reinforcing bar 17: Vertical penetration anchor hole B1: Rod-shaped vibrator

請求項1に係る壁高欄の取替方法は、鉄筋コンクリート製の既設の壁高欄を鉄筋コンクリート製の新設の壁高欄に取り替える壁高欄の取替方法であって、既設の床版の水切り部を斫り取る既設水切り部斫り工程を行い、次に、新設の水切り部を支持する埋込み鉄筋用のアンカー孔を削孔するアンカー孔削孔工程を行った後、前記新設の水切り部を前記既設の壁高欄の撤去前に先行施工する新設水切り部先行施工工程を行うことを特徴とする。
また、請求項2に係る壁高欄の取替方法は、鉄筋コンクリート製の既設の壁高欄を鉄筋コンクリート製の新設の壁高欄に取り替える壁高欄の取替方法であって、既設の床版の水切り部を斫り取る既設水切り部斫り工程を行った後、新設の水切り部を前記既設の壁高欄の撤去前に先行施工する新設水切り部先行施工工程を行い、前記新設の壁高欄を設置する壁高欄設置工程では、床版を貫通して両端に支圧板が装着されたアンカー部材でプレキャスト鉄筋コンクリート製のPCa壁高欄を固定して設置することを特徴とする。
A wall balustrade replacement method according to claim 1 is a wall balustrade replacement method for replacing an existing reinforced concrete wall balustrade with a new reinforced concrete wall balustrade. After performing the step of removing the existing draining portion , and then performing the anchor hole drilling step of drilling the anchor hole for the embedded reinforcing bar that supports the newly installed draining portion, the newly installed draining portion is removed from the existing The method is characterized in that a pre-construction process for a new water draining section, which is pre-constructed before the removal of the wall balustrade, is performed.
A wall balustrade replacement method according to claim 2 is a wall balustrade replacement method for replacing an existing reinforced concrete wall balustrade with a new reinforced concrete wall balustrade. After performing the step of scraping off the existing draining part, the new draining part is precedently constructed before removing the existing wall balustrade, and the wall balustrade for installing the new wall balustrade. In the installation step, the PCa wall balustrade made of precast reinforced concrete is fixed and installed by anchor members having pressure plates attached to both ends through the floor slab.

請求項に係る壁高欄の取替方法は、請求項1又は2に係る壁高欄の取替方法において、前記既設水切り部斫り工程及び前記新設水切り部先行施工工程は、仮設足場から車線規制を行わないで行うことを特徴とする。 A wall balustrade replacement method according to claim 3 is the wall balustrade replacement method according to claim 1 or 2 , wherein the step of removing the existing water drain and the preceding construction step of the new water drain are performed from temporary scaffolding to lane regulation. It is characterized by performing without performing

請求項に係る壁高欄の取替方法は、請求項に記載の壁高欄の取替方法において、前記壁高欄設置工程では、床版及び前記PCa壁高欄の外側面には、炭素繊維シート接着することを特徴とする。 A wall balustrade replacement method according to claim 4 is the wall balustrade replacement method according to claim 2 , wherein in the wall balustrade installation step, a carbon fiber sheet is applied to the outer surface of the floor slab and the PCa wall balustrade. It is characterized by bonding.

請求項1~に係る発明によれば、既設の床版の水切り部を斫り取った後、新設の水切り部を既設の壁高欄の撤去前に先行施工するので、最小限の交通規制で既設の壁高欄を新しい壁高欄に取り替えることができる。また、請求項1~に係る発明によれば、慎重に作業する必要のある水切り部を斫り取って撤去する作業を、足場上作業として車線規制を行わない車線規制外作業として行うことができる。このため、車線規制の規制時間を気にせず、時間をかけて慎重に水切り部の撤去作業を行うことが可能となる。
それに加え、請求項1に係る発明によれば、アンカー孔削孔工程を行うので、次工程である新設水切り部先行施工工程をより短時間に効率よく行うことができる。
According to the inventions of Claims 1 to 4 , after scraping off the draining part of the existing floor slab, the new draining part is constructed prior to the removal of the existing wall balustrade, so traffic regulation is minimized. The existing balustrade can be replaced with a new balustrade. In addition, according to the inventions of claims 1 to 4 , the work of scraping off and removing the draining part, which needs to be done carefully, can be done as a work on the scaffolding that does not carry out lane regulations and is outside lane regulations. can. For this reason, it is possible to carefully remove the water draining portion over time without worrying about the regulation time of the lane regulation.
In addition, according to the first aspect of the invention, since the anchor hole drilling process is performed, the next process, which is the pre-construction process for the new water draining portion, can be efficiently performed in a shorter time.

特に、請求項に係る発明によれば、PCa壁高欄を設置するので、コンクリートが所定の強度を発現する養生期間を大幅に短縮して壁高欄の取替作業を行うことができる。
また、請求項2に係る発明によれば、床版を貫通して両端に支圧板が装着されたアンカー部材でPCa壁高欄を固定するので、PCa壁高欄を設置する作業をさらに短縮することができる。
In particular, according to the second aspect of the invention, since the PCa wall balustrade is installed, it is possible to perform the wall balustrade replacement work while greatly shortening the curing period for the concrete to develop a predetermined strength.
In addition, according to the second aspect of the invention, the PCa wall balustrade is fixed by the anchor member that penetrates the floor slab and has bearing plates attached to both ends, so that the work for installing the PCa wall balustrade can be further shortened. can.

特に、請求項に係る発明によれば、床版及びPCa壁高欄の外側面に炭素繊維シートを接着するので、橋梁外側からの衝突荷重とは逆向きの外力にも対応することができる。 In particular, according to the fourth aspect of the invention, since the carbon fiber sheet is adhered to the outer surface of the floor slab and the PCa balustrade, it is possible to cope with an external force in the direction opposite to the collision load from the outside of the bridge.

Claims (6)

鉄筋コンクリート製の既設の壁高欄を鉄筋コンクリート製の新設の壁高欄に取り替える壁高欄の取替方法であって、
既設の床版の水切り部を斫り取る既設水切り部斫り工程を行った後、
新設の水切り部を前記既設の壁高欄の撤去前に先行施工する新設水切り部先行施工工程を行うこと
を特徴とする壁高欄の取替方法。
A wall balustrade replacement method for replacing an existing reinforced concrete wall balustrade with a new reinforced concrete wall balustrade,
After performing the existing water draining process to remove the water draining part of the existing floor slab,
A method for replacing a wall balustrade, characterized by performing a pre-construction process for a new water-draining section in which a new water-draining section is constructed prior to removal of the existing wall balustrade.
前記既設水切り部斫り工程及び前記新設水切り部先行施工工程は、仮設足場から車線規制を行わないで行うこと
を特徴とする請求項1に記載の壁高欄の取替方法。
2. The method for replacing a wall balustrade according to claim 1, wherein the step of removing the existing water drain and the preceding construction step of the new water drain are performed without lane restrictions from temporary scaffolding.
前記新設水切り部先行施工工程を行う前に、前記新設の水切り部を支持する埋込み鉄筋用のアンカー孔を削孔するアンカー孔削孔工程を行うこと
を特徴とする請求項1又は2に記載の壁高欄の取替方法。
3. The anchor hole drilling step of drilling an anchor hole for an embedded reinforcing bar that supports the newly installed draining portion is performed before performing the new draining portion precedent construction step. How to replace the wall balustrade.
前記新設の壁高欄を設置する壁高欄設置工程では、プレキャスト鉄筋コンクリート製のPCa壁高欄を設置すること
を特徴とする請求項1ないし3のいずれかに記載の壁高欄の取替方法。
The wall balustrade replacement method according to any one of claims 1 to 3, wherein PCa wall balustrades made of precast reinforced concrete are installed in the wall balustrade installation step of installing the new wall balustrade.
前記壁高欄設置工程では、床版を貫通して両端に支圧板が装着されたアンカー部材で前記PCa壁高欄を固定すること
を特徴とする請求項4に記載の壁高欄の取替方法。
5. The method for replacing a wall balustrade according to claim 4, wherein in the wall balustrade installation step, the PCa wall balustrade is fixed by anchor members having bearing pressure plates attached to both ends of the floor slab.
前記壁高欄設置工程では、床版及び前記PCa壁高欄の外側面には、炭素繊維シートを接着すること
を特徴とする請求項4又は5に記載の壁高欄の取替方法。
6. The method for replacing a wall balustrade according to claim 4 or 5, wherein, in the wall balustrade installation step, a carbon fiber sheet is adhered to the outer surface of the floor slab and the PCa balustrade.
JP2021119995A 2021-07-20 2021-07-20 How to replace the wall rail Active JP7021386B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021119995A JP7021386B1 (en) 2021-07-20 2021-07-20 How to replace the wall rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021119995A JP7021386B1 (en) 2021-07-20 2021-07-20 How to replace the wall rail

Publications (2)

Publication Number Publication Date
JP7021386B1 JP7021386B1 (en) 2022-02-16
JP2023015912A true JP2023015912A (en) 2023-02-01

Family

ID=80948532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021119995A Active JP7021386B1 (en) 2021-07-20 2021-07-20 How to replace the wall rail

Country Status (1)

Country Link
JP (1) JP7021386B1 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146721A (en) * 2000-11-14 2002-05-22 Chiyoda Engineering Consultants Co Ltd Precast wall railing installation method
JP2004092171A (en) * 2002-08-30 2004-03-25 Metropolitan Expressway Public Corp Repair method for concrete viaduct
KR100473477B1 (en) * 2004-11-29 2005-03-14 강명석 Bridge guirail reinforcement method of non-dismantle for bridge curbstone
JP2008002259A (en) * 2007-03-03 2008-01-10 Kcon Kk Improving method of deteriorated wall handrail of roadbed side end part of viaduct of automobile road
JP2010270514A (en) * 2009-05-22 2010-12-02 Nakanihon Highway Engineering Nagoya Kk Concrete-surface repair structure
JP2016061071A (en) * 2014-09-18 2016-04-25 株式会社大林組 Floor slab widening method
JP2016075046A (en) * 2014-10-03 2016-05-12 東日本高速道路株式会社 Widening method for existing road bridge
JP2018178588A (en) * 2017-04-17 2018-11-15 清水建設株式会社 Bridge construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146721A (en) * 2000-11-14 2002-05-22 Chiyoda Engineering Consultants Co Ltd Precast wall railing installation method
JP2004092171A (en) * 2002-08-30 2004-03-25 Metropolitan Expressway Public Corp Repair method for concrete viaduct
KR100473477B1 (en) * 2004-11-29 2005-03-14 강명석 Bridge guirail reinforcement method of non-dismantle for bridge curbstone
JP2008002259A (en) * 2007-03-03 2008-01-10 Kcon Kk Improving method of deteriorated wall handrail of roadbed side end part of viaduct of automobile road
JP2010270514A (en) * 2009-05-22 2010-12-02 Nakanihon Highway Engineering Nagoya Kk Concrete-surface repair structure
JP2016061071A (en) * 2014-09-18 2016-04-25 株式会社大林組 Floor slab widening method
JP2016075046A (en) * 2014-10-03 2016-05-12 東日本高速道路株式会社 Widening method for existing road bridge
JP2018178588A (en) * 2017-04-17 2018-11-15 清水建設株式会社 Bridge construction method

Also Published As

Publication number Publication date
JP7021386B1 (en) 2022-02-16

Similar Documents

Publication Publication Date Title
KR101630235B1 (en) Precast truss wall structure and construction method of underground structure using thereof
KR100958014B1 (en) Construction method of steel composite girder bridge
KR100837608B1 (en) J.K Bracket Method
CN114837088A (en) A kind of construction method of bearing platform on highway
JP5766544B2 (en) Slab track reinforcement method and protrusion alternative structure
CN107100083A (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
JP6811678B2 (en) Method of joining concrete structures and concrete members to which continuous fiber reinforced concrete is applied
JP7134133B2 (en) Bridge railing construction method
KR101701220B1 (en) Road expansion structure and construction method thereof
CN108547209A (en) A kind of single hole precast hollow slab jointless bridge and its construction method
JP2023015912A (en) How to replace wall balustrades
JP2007247225A (en) Continuous girder structure and construction method using multiple simple girder bridges
JP5041481B2 (en) Updating method and structure of existing bearing device
KR100966639B1 (en) Manhole repair method
CN114045750B (en) Construction method of high pier column tie beam
JP6845456B1 (en) How to replace concrete bridges with precast floor slabs
JP7455473B2 (en) Pavement replacement method
JP6995584B2 (en) Bearing replacement method for existing concrete girders
KR100473477B1 (en) Bridge guirail reinforcement method of non-dismantle for bridge curbstone
JP7711117B2 (en) Buried formwork unit and wall parapet construction method
CN116608324B (en) Underground pipeline reinforcing structure below river-crossing bridge under tunnel construction
CN219011874U (en) Elevartor shaft reinforcing bar net protection platform
KR20060079395A (en) Integral teaching device and its installation method
KR102413916B1 (en) Construction method of pre-buried anchor in formwork perforation type for installation of bridge inspection facility

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20211008

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20211008

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211220

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220201

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220203

R150 Certificate of patent or registration of utility model

Ref document number: 7021386

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250