[go: up one dir, main page]

JP2018071159A - Duct construction method - Google Patents

Duct construction method Download PDF

Info

Publication number
JP2018071159A
JP2018071159A JP2016210980A JP2016210980A JP2018071159A JP 2018071159 A JP2018071159 A JP 2018071159A JP 2016210980 A JP2016210980 A JP 2016210980A JP 2016210980 A JP2016210980 A JP 2016210980A JP 2018071159 A JP2018071159 A JP 2018071159A
Authority
JP
Japan
Prior art keywords
duct
precast
wall
construction
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016210980A
Other languages
Japanese (ja)
Other versions
JP6842881B2 (en
Inventor
健二 植田
Kenji Ueda
健二 植田
中川 英樹
Hideki Nakagawa
英樹 中川
正行 奥田
Masayuki Okuda
正行 奥田
俊司 山本
Shunji Yamamoto
俊司 山本
崇宏 待永
Takahiro Machinaga
崇宏 待永
淳二 山本
Junji Yamamoto
淳二 山本
伸顕 佐藤
Nobuaki Sato
伸顕 佐藤
啓介 大知
Keisuke Ochi
啓介 大知
哲也 ▲濱▼田
哲也 ▲濱▼田
Tetsuya Hamada
史郎 織井
Shiro Orii
史郎 織井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2016210980A priority Critical patent/JP6842881B2/en
Publication of JP2018071159A publication Critical patent/JP2018071159A/en
Application granted granted Critical
Publication of JP6842881B2 publication Critical patent/JP6842881B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Duct Arrangements (AREA)

Abstract

PROBLEM TO BE SOLVED: To shorten the period of duct construction, reduce cost including a pedestal expense, and reduce space necessary for duct construction while improving duct fire resistance, durability, and quality.SOLUTION: A precast duct material 10 in which a concrete outer peripheral wall 12 is integrally formed on the outer peripheral side of a cylindrical duct component material 11 is first formed, then the precast duct material 10 is lifted to the installation position of a duct construction place of a building, and the lifted precast duct material 10 is fixed to the building frame 2 of the building.SELECTED DRAWING: Figure 4

Description

本発明は、集合住宅や商業施設等の建物にダクトを構築するダクト構築方法に関する。   The present invention relates to a duct construction method for constructing a duct in a building such as an apartment house or a commercial facility.

上述のダクト構築方法として、例えば、特許文献1に開示されている鉄筋コンクリート造建物の構築方法においては、柱、梁接合部を含む鉄筋コンクリート造の柱と梁を一体化した躯体ブロック材を予め形成し、この躯体ブロック材を、下層階の躯体ブロック材の鉄筋コンクリート柱及び同一階層の他の躯体ブロック材の鉄筋コンクリート梁にそれぞれ接合して躯体骨組を構築し、この躯体骨組の鉄筋コンクリート梁の上側に床スラブブロック材を敷設して躯体を構築する。
床スラブブロック材は、鉄筋コンクリート梁で区画される格子状の一つの升目全体を覆うプレキャスト版(PCa版)によって形成され、この床スラブブロック材には、空調ダクト、天井下地材が予め取付けられている。
As the above-described duct construction method, for example, in the construction method of a reinforced concrete building disclosed in Patent Document 1, a frame block material in which a column and a beam of a reinforced concrete structure including columns and beam joints are integrated is formed in advance. This frame block material is joined to the reinforced concrete column of the lower level frame block material and the reinforced concrete beam of other frame block material of the same level to construct the frame frame, and the floor slab above the reinforced concrete beam of this frame frame Laying block material to build the frame.
The floor slab block material is formed of a precast plate (PCa plate) that covers the entire grid of grids partitioned by reinforced concrete beams. The floor slab block material is preinstalled with air conditioning ducts and ceiling base materials. Yes.

しかし、上述の構築方法では、PCa版製の床スラブブロック材に空調ダクトを予め取付けるという点が開示されているだけであり、空調ダクトの具体的な構造及び構築方法については記載されていない。そのため、耐火性が要求されるダクトの構築には対応できない。   However, the above construction method only discloses that the air conditioning duct is attached in advance to the floor slab block material made of PCa plate, and does not describe the specific structure and construction method of the air conditioning duct. Therefore, it cannot cope with construction of a duct that requires fire resistance.

そこで、耐火性が要求されるダクトの構築方法として、例えば、建物の吹き抜け部の躯体に排煙・換気用の竪ダクトを構築する場合において、躯体工事が完了した躯体のダクト構築箇所に鉄骨下地を取付ける鉄骨下地工事と、躯体の壁面との間でダクト取付け空間を区画形成する軽量気泡コンクリート壁(ALC壁)を鉄骨下地に取付けるALC壁工事と、鉄骨下地に耐火被覆を施す耐火被覆工事と、ダクト取付け空間内にダクトを配置するダクト工事とを実行するダクト構築方法が考えられる。   Therefore, as a method of constructing a duct that requires fire resistance, for example, when constructing a smoke duct for ventilation in the frame of a blow-off part of a building, a steel foundation is installed at the duct construction location of the frame for which the frame work has been completed. A steel base construction for mounting the steel, an ALC wall construction that attaches a lightweight cellular concrete wall (ALC wall), which forms a duct installation space between the walls of the frame, to the steel base, and a fireproof construction that applies a fireproof coating to the steel base A duct construction method for performing duct work for arranging a duct in the duct installation space is conceivable.

特開平8−302812号公報JP-A-8-302812

上述のダクト構築方法は、ダクトの配置スペース以外に、躯体の壁面との間でダクト取付け空間を区画形成するALC壁の配置スペースと、建物の吹き抜け部内に総足場を構築するスペースとを確保する必要がある。しかも、吹き抜け部内での足場の架払工事が発生する。そのため、仮設資材の数量だけでなく、その搬入・搬出や架払にかかる作業量が増加する。
さらに、躯体工事の完了後に鉄骨下地工事、ALC壁工事、耐火被覆工事、ダクト工事を実行するため、ダクト施工を含む工期の長期化とコストの高騰化を招来し易い。
The above-described duct construction method secures, in addition to the duct arrangement space, an ALC wall arrangement space that forms a duct mounting space with the wall surface of the housing, and a space for constructing a total scaffold in the atrium of the building. There is a need. In addition, the construction of scaffolding within the atrium is required. For this reason, not only the quantity of temporary materials but also the amount of work for carrying in / out and overloading increases.
In addition, since the steel foundation work, ALC wall work, fireproof coating work, and duct work are executed after the completion of the frame work, the construction period including the duct work is likely to be prolonged and the cost is likely to rise.

この実情に鑑み、本発明の主たる課題は、ダクトの耐火性、耐久性、品質を確保しながら、構造の簡素化、ダクト施工を含む工期短縮、架払費を含むコストの縮減、ダクト施工に要するスペースの削減を図ることのできるダクト構築方法を提供する点にある。   In view of this situation, the main problems of the present invention are to simplify the structure, shorten the construction period including duct construction, reduce the cost including overhead cost, and install the duct while ensuring the fire resistance, durability and quality of the duct. The object is to provide a duct construction method capable of reducing space.

本発明による第1の特徴構成は、ダクト構築方法であって、筒状のダクト構成材の外周側にコンクリート外周壁が一体形成されたプレキャストダクト材を予め製作したのち、前記プレキャストダクト材を建物のダクト構築箇所の据付位置に揚重し、揚重された前記プレキャストダクト材を前記建物の躯体に固定する点にある。   A first characteristic configuration according to the present invention is a duct construction method, in which a precast duct material in which a concrete outer peripheral wall is integrally formed on an outer peripheral side of a cylindrical duct constituent material is manufactured in advance, and then the precast duct material is built. The precast duct material is lifted to the installation position of the duct construction site and the lifted precast duct material is fixed to the building frame.

上記構成によれば、ダクト材を、筒状のダクト構成材とそれの外周側に一体形成されるコンクリート外周壁との複数層構造とすることにより、単層構造のダクト材でダクトを構成する場合に比較して、構造の簡素化を図りながらダクトの耐火性及び耐久性を確保することができる。   According to the said structure, a duct is comprised with the duct material of a single layer structure by making a duct material into the multilayer structure of the cylindrical duct component material and the concrete outer peripheral wall integrally formed in the outer peripheral side of it. Compared to the case, it is possible to ensure the fire resistance and durability of the duct while simplifying the structure.

しかも、このダクト材をプレキャスト化(PCa化)して予め製作するので、その製作されたプレキャストダクト材を建物のダクト構築箇所の据付位置に揚重し、この揚重されたプレキャストダクト材を建物の躯体に固定するだけで済む。そのため、上述の躯体工事完了後のダクト構築方法における鉄骨下地工事、ALC壁工事、耐火被覆工事を削減することができるとともに、仮設資材の数量及びそれの搬入・搬出や架払にかかる作業量、スペースを軽減することができる。   Moreover, since this duct material is precast (PCa) and manufactured in advance, the manufactured precast duct material is lifted to the installation position of the duct construction site of the building, and this lifted precast duct material is used in the building. You just need to fix it to the housing. Therefore, it is possible to reduce the steel foundation work, ALC wall work, fireproof covering work in the duct construction method after the completion of the above-mentioned frame work, and the amount of temporary materials and the amount of work for carrying in / out and overloading, Space can be reduced.

したがって、ダクトの複数層構造でのPCa化により、耐火性、耐久性、品質を確保しながら、ダクト施工を含む工期短縮、架払費を含むコストの縮減、ダクト施工に要するスペースの削減を図ることができる。   Therefore, by adopting PCa with a multi-layered duct structure, while ensuring fire resistance, durability, and quality, shorten the construction period including duct construction, reduce costs including overhead costs, and reduce the space required for duct construction. Can do.

本発明による第2の特徴構成は、前記プレキャストダクト材を前記躯体に固定しながら順次縦方向に積み上げることにより、前記建物のダクト構築置箇所に竪ダクトを構築する点にある。   A second characteristic configuration according to the present invention is that a vertical duct is constructed at a duct construction location of the building by sequentially stacking the precast duct material in the vertical direction while being fixed to the structural body.

上記構成によれば、プレキャストダクト材と躯体とを強固に固定することができ、安定した状態でプレキャストダクト材を順次縦方向に積み上げて竪ダクトを構築することができる。しかも、躯体工事の進行に伴ってプレキャストダクト材を躯体の階層毎に固定しながら順次縦方向に積み上げる工法を採用することができ、躯体工事と竪ダクト工事とを略同時期に完了させることができる。
それ故に、上述の躯体工事完了後のダクト構築方法に比較して工期短縮化を一層図ることができる。
According to the said structure, a precast duct material and a housing can be fixed firmly, and a precast duct material can be piled up one by one in the vertical direction in the stable state, and a coffin duct can be constructed | assembled. In addition, it is possible to adopt a construction method in which the precast duct material is stacked in the vertical direction sequentially while fixing the frame work as the frame work progresses, and the frame work and the duct work can be completed almost simultaneously. it can.
Therefore, the construction period can be further shortened as compared with the duct construction method after the completion of the above-described frame construction.

本発明による第3の特徴構成は、前記ダクト構築箇所の据付位置に揚重された後続の前記プレキャストダクト材は、据付けられた先行の前記プレキャストダクト材との接合面間にパッキンを圧縮状態に配置した状態で積み上げられている点にある。   According to a third characteristic configuration of the present invention, the subsequent precast duct material lifted to the installation position of the duct construction place is compressed in a compressed state between the joint surfaces of the installed precast duct material. It is in the point piled up in the state of arrangement.

上記構成によれば、積み上げられた両プレキャストダクト材の接合面間を、圧縮状態に配置されたパッキンで確実に密封して、竪ダクトの気密性を向上することができる。   According to the said structure, between the joint surfaces of the piled up both precast duct materials can be reliably sealed with the packing arrange | positioned in the compression state, and the airtightness of a gutter duct can be improved.

本発明による第4の特徴構成は、前記プレキャストダクト材の前記コンクリート外周壁の一側部が、構築後に前記躯体の一部を構成する壁部に構成されている点にある。   The 4th characteristic structure by this invention exists in the point by which the one side part of the said concrete outer peripheral wall of the said precast duct material is comprised by the wall part which comprises a part of said housing after construction.

上記構成によれば、躯体工事に合わせて竪ダクト工事を階層毎に完結することができるとともに、PCa化されたプレキャストダクト材の一側部をもって構築後に躯体の一部を構成するので、プレキャストダクト材と躯体とを一体化によって強固に固定することができるとともに、躯体工事及び竪ダクト工事の工期短縮化を図ることができる。   According to the above configuration, the dredging duct work can be completed for each level in accordance with the frame construction, and a part of the frame is constructed after construction with one side part of the precast duct material made of PCa. The material and the casing can be firmly fixed by integration, and the construction period of the casing construction and the duct construction can be shortened.

本発明による第5の特徴構成は、前記ダクト構築箇所の据付位置に据付けられた先行の前記プレキャストダクト材の接合面における前記壁部に相当する部位と、後続の前記プレキャストダクト材の接合面における前記壁部に相当する部位との間にグラウトを充填することにより、先行の前記プレキャストダクト材の前記壁部と後続の前記プレキャストダクト材の前記壁部とを固定する点にある。   A fifth characteristic configuration according to the present invention includes a portion corresponding to the wall portion in the joint surface of the preceding precast duct material installed at the installation position of the duct construction location, and a joint surface of the subsequent precast duct material. By filling grout between the portions corresponding to the wall portions, the wall portion of the preceding precast duct material and the wall portion of the subsequent precast duct material are fixed.

上記構成によれば、積み上げられた両プレキャストダクト材のうち、構築後に躯体の一部を構成する壁部同士をグラウトで強固に固定することができるので、プレキャストダクト材同士を適切な相対姿勢で長期間に亘って確実、強固に固定することができる。   According to the above configuration, among the two precast duct materials stacked, the wall portions constituting a part of the housing can be firmly fixed with a grout after the construction, so that the precast duct materials are in an appropriate relative posture. It can be securely and firmly fixed over a long period of time.

建物の吹き抜け部を構成する躯体の耐震壁及び竪ダクトの工事完成時の水平断面図Horizontal cross-sectional view of the seismic wall and the duct of the building that make up the atrium of the building プレキャストダクト材の製作時の水平断面図Horizontal sectional view during production of precast duct material 一節分のプレキャストダクト材の揚重時の縦断側面図Side view of vertical section of precast duct material for one section when lifting 二節分のプレキャストダクト材の揚重時の縦断側面図Longitudinal side view during lifting of precast duct material for two nodes プレキャストダクト材の揚重接合時のパッキン配置を示す水平断面図(a)と縦断側面図(b)Horizontal sectional view (a) and longitudinal sectional side view (b) showing packing arrangement at the time of lifting and joining of precast duct material 二節分のプレキャストダクト材の据付時の縦断側面図Longitudinal side view when installing precast duct material for two nodes 両プレキャストダクト材の接合完了時のパッキン配置を示す水平断面図(a)と縦断側面図(b)Horizontal sectional view (a) and vertical side view (b) showing packing arrangement at the completion of joining of both precast duct materials ハーフプレキャスト壁の据付時の水平断面図Horizontal sectional view when installing half precast wall ハーフプレキャスト壁の製作時の斜視図Perspective view of half precast wall 製作されたハーフプレキャスト壁に対する配管取付け時の側面図Side view when installing pipes on the manufactured half precast wall

〔第1実施形態〕
図1は、集合住宅や商業施設等の建物の略中央部を構成するセンターコア構造の一部を示す。このセンターコア構造の内部には、エレベータ、階段、タワーパーキング、機械室、配管等の設備が集合配置され、センターコア構造の周囲には共用廊下や居住空間等が構成される。
本実施形態おいては、タワーパーキング等を設置する吹き抜け部1を区画形成する躯体2の耐震壁(コア壁)3のダクト構築箇所には、ダクトの一例である竪ダクト4が構築されている。この竪ダクト4は、PCa工場やPCa製作サイト等のPCa製作場において予め製作されたプレキャストダクト材10を躯体2のダクト構築位置に固定しながら順次縦方向に積み上げることにより構築されている。
[First Embodiment]
FIG. 1 shows a part of a center core structure that constitutes a substantially central part of a building such as an apartment house or a commercial facility. Inside the center core structure, equipment such as elevators, stairs, tower parking, machine room, and piping are collectively arranged, and a common corridor, a living space, and the like are formed around the center core structure.
In the present embodiment, a saddle duct 4 that is an example of a duct is constructed at a duct construction location of a seismic wall (core wall) 3 of a housing 2 that defines and forms a blow-off portion 1 in which tower parking or the like is installed. The saddle duct 4 is constructed by sequentially stacking the precast duct material 10 produced in advance in a PCa production site such as a PCa factory or a PCa production site in the longitudinal direction while fixing the precast duct material 10 to the duct construction position of the enclosure 2.

竪ダクト4を構成する各プレキャストダクト材10は、横断面形状が矩形となる角筒状に製作された耐食性に優れた金属製(例えば、溶融亜鉛メッキ鋼板)のダクト構成部材11と、それの外周側を囲繞する状態で一体形成される鉄筋コンクリート製のコンクリート外周壁12とからなる。
コンクリート外周壁12の四つの側面を構成する第1コンクリート側壁部12A〜第4コンクリート側壁部12Dのうち、躯体2の耐震壁3と一体形成される一側面(一側部)の第1コンクリート側壁部12Aは、躯体2の耐震壁3の厚みよりも大なる厚みに構成されている。残りの三つの側面を構成する第2コンクリート側壁部12B〜第4コンクリート側壁部12Dは、耐震壁3の厚みよりも小なる厚みに統一構成されている。
Each of the precast duct members 10 constituting the 竪 duct 4 is made of a metal (for example, hot-dip galvanized steel plate) duct component member 11 made of a rectangular tube having a rectangular cross-sectional shape, and a duct component member 11 thereof. It consists of a concrete outer peripheral wall 12 made of reinforced concrete that is integrally formed so as to surround the outer peripheral side.
Of the first concrete side wall portion 12A to the fourth concrete side wall portion 12D constituting the four side surfaces of the concrete outer peripheral wall 12, one side surface (one side portion) of the first concrete side wall is integrally formed with the seismic wall 3 of the frame 2. The portion 12A is configured to have a thickness larger than the thickness of the earthquake-resistant wall 3 of the casing 2. The second concrete side wall portion 12 </ b> B to the fourth concrete side wall portion 12 </ b> D constituting the remaining three side surfaces are integrally configured to have a thickness smaller than the thickness of the earthquake resistant wall 3.

耐震壁3の他の一部は、図8〜図10に示すように、トラス筋41のトップ側が露出する状態で予め製作されたハーフプレキャスト壁(例えば、オムニア版)40を耐震壁構築箇所に揚重して据付け固定し、現場でのコンクリート打設によって耐震壁3が構築されている。このハーフプレキャスト壁40の室内側内面には、図10に示すように、所定数の配管Pが予め取付けられているとともに、ハーフプレキャスト壁40には、図8、図10に示すように、外型枠46を所定間隔で取付けるためのセパレータ42が予め取付けられている。   As shown in FIGS. 8 to 10, another part of the earthquake-resistant wall 3 is a half-precast wall (for example, an omnia version) 40 manufactured in advance with the top side of the truss bar 41 exposed. The seismic wall 3 is constructed by lifting, fixing and fixing the concrete on site. As shown in FIG. 10, a predetermined number of pipes P are attached in advance to the inner surface of the half precast wall 40 on the indoor side, and the half precast wall 40 is externally attached to the half precast wall 40 as shown in FIGS. 8 and 10. A separator 42 for attaching the formwork 46 at predetermined intervals is attached in advance.

次に、上述の竪ダクト4を構築するダクト構築方法について説明する。
[1]プレキャストダクト材10の製作工程
図2に示すように、PCa製作場において、横断面形状が矩形となる角筒状の金属製のダクト構成部材11を内型枠として固定配置する。このダクト構成部材11の外周面11a側には、ダクト軸方向に沿う複数のダクト縦筋13Aとダクト帯筋13C及び、耐震壁3の壁連結筋44と接続される複数のダクト横筋13Bとを配筋する。この配筋の外側位置に、外型枠15としてのコンクリート型枠を固定配置する。この外型枠15の内面15aとダクト構成部材11の外周面11aとの間隔は、コンクリート外周壁12における第1コンクリート側壁部12A〜第4コンクリート側壁部12Dの各厚みに相当する設定間隔に規制する。
この状態でダクト構成部材11の外周面11aと外型枠15の内面15aとの成形空間内にコンクリートを打設する。打設コンクリートの養生後に外型枠15を撤去することにより、金属製のダクト構成部材11の外周面11aにコンクリート外周壁12が一体成形されたプレキャストダクト材10を製作することができる。
Next, a duct construction method for constructing the above-described saddle duct 4 will be described.
[1] Manufacturing Process of Precast Duct Material 10 As shown in FIG. 2, a rectangular tube-shaped metal duct constituent member 11 having a rectangular cross section is fixedly disposed as an inner mold frame in the PCa manufacturing site. On the outer peripheral surface 11a side of the duct component member 11, a plurality of duct vertical bars 13A and duct strips 13C along the duct axial direction, and a plurality of duct transverse bars 13B connected to the wall connecting bars 44 of the earthquake-resistant wall 3 are provided. Arrange the bars. A concrete mold as the outer mold 15 is fixedly arranged at the outer position of the bar arrangement. The interval between the inner surface 15a of the outer mold 15 and the outer peripheral surface 11a of the duct component 11 is regulated to a set interval corresponding to each thickness of the first concrete side wall portion 12A to the fourth concrete side wall portion 12D in the concrete outer peripheral wall 12. To do.
In this state, concrete is placed in the molding space between the outer peripheral surface 11 a of the duct component member 11 and the inner surface 15 a of the outer mold 15. By removing the outer mold 15 after curing the cast concrete, the precast duct material 10 in which the concrete outer peripheral wall 12 is integrally formed on the outer peripheral surface 11a of the metal duct component 11 can be manufactured.

本実施形態においては、図3、図4に示すように、第1コンクリート側壁部12Aに配置されるダクト縦筋13Aの下端部には、モルタル等のグラウト充填式の鉄筋継手スリーブ13Eが設けられている。第1コンクリート側壁部12Aに配置されるダクト縦筋13Aの上端部には、上階側のプレキャストダクト材10の鉄筋継手スリーブ13Eに対してダクト軸方向から挿入接続可能な接続代でコンクリート外周壁12の上端面12bから突出する連結筋部13aが形成されている。
また、図3、図4に示すように、一節のプレキャストダクト材10が据付固定される設置階の床スラブ5には、一節のプレキャストダクト材10の鉄筋継手スリーブ13Eに対してダクト軸方向から挿入接続可能な接続代で床スラブ5の上面5aから突出する連結筋部13Fが設けられている。
In this embodiment, as shown in FIGS. 3 and 4, a grout-filled reinforcing bar joint sleeve 13 </ b> E such as mortar is provided at the lower end portion of the duct vertical bars 13 </ b> A arranged on the first concrete side wall 12 </ b> A. ing. At the upper end of the duct vertical bars 13A arranged on the first concrete side wall part 12A, the concrete outer peripheral wall with a connection allowance that can be inserted and connected from the duct axial direction to the reinforcing bar joint sleeve 13E of the precast duct material 10 on the upper floor side. 12 is formed with a connecting bar portion 13a protruding from the upper end surface 12b of the twelve.
As shown in FIGS. 3 and 4, the floor slab 5 on the installation floor on which the one-section precast duct material 10 is installed and fixed is located from the duct axial direction with respect to the reinforcing bar joint sleeve 13 </ b> E of the one-section precast duct material 10. A connecting bar portion 13 </ b> F that protrudes from the upper surface 5 a of the floor slab 5 with a connection allowance for insertion is provided.

さらに、本実施形態においては、図1、図2に示すように、ダクト横筋13Bの両端部には、耐震壁3の壁連結筋44との接続代で第1コンクリート側壁部12Aの左右の両外側面から突出する連結筋部13bが形成されている。
また、竪ダクト4を構築する各プレキャストダクト材10は、図4に示すように、設置階の床スラブ5の上面5aから上階の床スラブ5の上面5aまでの高さに相当する又は略相当する高さに設定されている。
Further, in the present embodiment, as shown in FIGS. 1 and 2, both the left and right sides of the first concrete side wall 12A are connected to the both ends of the duct transverse bar 13B at the connection margin with the wall connecting bar 44 of the seismic wall 3. A connecting bar portion 13b protruding from the outer surface is formed.
Moreover, each precast duct material 10 that constructs the eaves duct 4 corresponds to or substantially corresponds to the height from the upper surface 5a of the floor slab 5 on the installation floor to the upper surface 5a of the floor slab 5 on the upper floor, as shown in FIG. The corresponding height is set.

[2]一節のプレキャストダクト材10の揚重・据付工程
図3に示すように、一節のプレキャストダクト材10の上端部に吊りボルト16を取付け、タワークレーン等でプレキャストダクト材10を設置階の床スラブ5の上面5aにおけるダクト形成箇所に揚重して据付固定する。据付固定された状態では、プレキャストダクト材10の鉄筋継手スリーブ13Eが、床スラブ5の上面5aから突出する連結筋部13Fに対してダクト軸方向から差し込み接続されている。このプレキャストダクト材10の鉄筋継手スリーブ13Eと床スラブ5側の連結筋部13Fとは、鉄筋継手スリーブ13Eに充填されたグラウトで固定される。
[2] Lifting / Installation Process of One-Section Precast Duct Material 10 As shown in FIG. 3, a suspension bolt 16 is attached to the upper end of the one-cast precast duct material 10, and the precast duct material 10 is installed on the installation floor with a tower crane or the like. The floor slab 5 is lifted and fixed to a duct forming portion on the upper surface 5a. In the installed and fixed state, the reinforcing bar joint sleeve 13E of the precast duct material 10 is inserted and connected to the connecting bar portion 13F protruding from the upper surface 5a of the floor slab 5 from the duct axial direction. The reinforcing bar joint sleeve 13E of the precast duct material 10 and the connecting bar part 13F on the floor slab 5 side are fixed by a grout filled in the reinforcing bar joint sleeve 13E.

さらに、設置階の床スラブ5の上面5aと一節のプレキャストダクト材10のコンクリート外周壁12の下端面12aとの接合面間には、図5、図7に示すように、据付けられた先行(下階)のプレキャストダクト材10のコンクリート外周壁12の上端面12bと後続(上階)のプレキャストダクト材10のコンクリート外周壁12の下端面12aとの接合面間を密封接合する密封接合構造と同一又は略同一の密封接合構造が構成されている。そのため、設置階の床スラブ5と一節のプレキャストダクト材10との接合面間の密封接合構造については、後述の両プレキャストダクト材10の接合面間の密封接合構造において詳述する。   Further, as shown in FIG. 5 and FIG. 7, an installation precedent (between the upper surface 5 a of the floor slab 5 on the installation floor and the lower end surface 12 a of the concrete outer peripheral wall 12 of the one-step precast duct material 10 is installed. A sealing joint structure for hermetically joining a joint surface between the upper end surface 12b of the concrete outer peripheral wall 12 of the precast duct material 10 on the lower floor and the lower end surface 12a of the concrete outer peripheral wall 12 of the subsequent precast duct member 10 on the upper floor; The same or substantially the same sealed joint structure is configured. Therefore, the sealing joint structure between the joint surfaces of the floor slab 5 on the installation floor and the one-step precast duct material 10 will be described in detail in the sealing joint structure between the joint surfaces of both precast duct members 10 described later.

次に、図1、図8に示すように、プレキャストダクト材10の隣接の耐震壁構築位置には、PCa製作場で製作されたハーフプレキャスト壁40が揚重されて設置されている。このハーフプレキャスト壁40のトラス筋41の露出側に壁連結筋44や壁縦筋45等の配筋を施すとともに、配筋されたハーフプレキャスト壁40側の壁連結筋44とプレキャストダクト材10の壁連結筋44とを接続する。その後、ハーフプレキャスト壁40に予め設けられているセパレータ42に、外型枠46としてのコンクリート型枠を取付け、ハーフプレキャスト壁40とプレキャストダクト材10及び外型枠46とで形成される成形空間にコンクリート47を打設する。   Next, as shown in FIGS. 1 and 8, a half precast wall 40 manufactured at the PCa manufacturing site is lifted and installed at the adjacent earthquake resistant wall construction position of the precast duct material 10. The bar connecting bar 44 and the wall vertical bar 45 are arranged on the exposed side of the truss bar 41 of the half precast wall 40, and the wall connecting bar 44 and the precast duct member 10 on the half precast wall 40 side are arranged. The wall connecting bar 44 is connected. Thereafter, a concrete mold as an outer mold 46 is attached to a separator 42 provided in advance on the half precast wall 40, and a molding space formed by the half precast wall 40, the precast duct material 10 and the outer mold 46 is formed. Concrete 47 is placed.

この打設コンクリート47の養生により、ハーフプレキャスト壁40を用いた耐震壁3の構築が完了すると同時に、プレキャストダクト材10のコンクリート外周壁12における一側部の第1コンクリート側壁部12Aが、構築後に躯体2の耐震壁3の一部を構成する壁部3Aとなる。この耐震壁構成用の壁部3Aは、図1に示すように、第1コンクリート側壁部12Aのうち、少なくとも耐震壁3の室内側壁面3a及び室外側壁面面3bの延長線間に相当する領域をもって構成されている。そのため、躯体工事に合わせて竪ダクト工事を階層毎に完結することができるとともに、PCa化されたプレキャストダクト材10の一側部である第1コンクリート側壁部12Aをもって構築後に躯体2の耐震壁3の一部を構成するので、躯体工事の能率化を図ることができる。   With the curing of the cast concrete 47, the construction of the earthquake resistant wall 3 using the half precast wall 40 is completed, and at the same time, the first concrete side wall 12A on one side of the concrete outer peripheral wall 12 of the precast duct material 10 is It becomes the wall portion 3 </ b> A constituting a part of the seismic wall 3 of the frame 2. As shown in FIG. 1, the wall portion 3 </ b> A for the seismic wall structure is a region corresponding to at least an extension line between the indoor side wall surface 3 a and the outdoor side wall surface 3 b of the earthquake resistant wall 3 in the first concrete side wall portion 12 </ b> A. It is configured with. Therefore, the dredging duct work can be completed for each level in accordance with the frame construction, and the seismic wall 3 of the frame 2 after the construction with the first concrete side wall 12A which is one side part of the precast duct material 10 made of PCa. As part of the construction, the efficiency of the frame construction can be improved.

[3]二節のプレキャストダクト材10の揚重・据付工程
図4に示すように、一節のプレキャストダクト材10の据付工事が完了すると、現場において、プレキャストダクト材10の上部にコンクリートを打設し、枝ダクト用取出口17を区画形成する側壁部18を形成するとともに、上階の梁6及び床スラブ5の施工を実施する。
その後、二節のプレキャストダクト材10の上端部に吊りボルト16を取付け、タワークレーン等で二節のプレキャストダクト材10を、次のダクト構築箇所の据付位置である一節のプレキャストダクト材10の上端部に揚重して据付固定する。据付固定された状態では、上階の二節のプレキャストダクト材10の鉄筋継手スリーブ13Eが、先に据付固定されている下階の一節のプレキャストダクト材10の上端面12bから突出するダクト縦筋13Aの連結筋部13aに対してダクト軸方向から嵌合接続されている。
上階のプレキャストダクト材10の鉄筋継手スリーブ13Eと下階のプレキャストダクト材10の連結筋部13aとは、鉄筋継手スリーブ13Eに充填されたグラウトで固定される。
[3] Lifting / Installation Process of Precast Duct Material 10 in Section 2 As shown in FIG. 4, when installation of the precast duct material 10 in section 1 is completed, concrete is placed on top of the precast duct material 10 on site. Then, the side wall 18 that defines the branch duct outlet 17 is formed, and the upper floor beam 6 and the floor slab 5 are installed.
Thereafter, the suspension bolt 16 is attached to the upper end portion of the two-node precast duct material 10, and the two-node precast duct material 10 is attached to the upper end portion of the one-node precast duct material 10, which is the installation position of the next duct construction site. Lift and fix to the part. In the installed and fixed state, the reinforcing bar joint sleeve 13E of the two-stage precast duct material 10 on the upper floor is projected from the upper end surface 12b of the one-node precast duct material 10 on the lower floor that has been previously installed and fixed. It is fitted and connected to the connecting bar portion 13a of 13A from the duct axial direction.
The reinforcing bar joint sleeve 13E of the upper floor precast duct material 10 and the connecting bar portion 13a of the lower floor precast duct material 10 are fixed by a grout filled in the reinforcing bar joint sleeve 13E.

据付固定されている下階のプレキャストダクト材10の上端面12bと上階のプレキャストダクト材10の下端面12aとは密封接合構造で接合されている。この密封接合構造には、図7に示すように、両プレキャストダクト材10の接合面間を密封するためのパッキン30が設けられている。このパッキン30は、ダクト内外方向で最大5層となる第1パッキン部材30A〜第5パッキン部材30Eから構成されている。
最内側に位置する第1パッキン部材30Aは、ダクト構成部材11のダクト軸方向の端面に沿って接触状態で矩形環状に配置される排煙パッキンから構成されている。
最内から二番目に位置する第2パッキン部材30Bは、矩形環状の第1パッキン部材30Aの外側面に沿って接触状態で矩形環状に配置されるブチルゴムから構成されている。
最内から三番目に位置する第3パッキン部材30Cは、矩形環状の第2パッキン部材30Bの外側面のうち、第2コンクリート側壁部12B〜第4コンクリート側壁部12Dの接合領域に位置する外側面に沿って接触状態でコの字状に配置されるクロロプレンゴムから構成されている。
最内から四番目に位置する第4パッキン部材30Dは、第3パッキン部材30Cの外側面に沿って接触状態でコの字状に配置されるロックウールから構成されている。
最外側に位置する第5パッキン部材30Eは、第2コンクリート側壁部12B〜第4コンクリート側壁部12Dの接合領域における第4パッキン部材30Dの外方側の接合面間に充填されるコーキング材から構成されている。
The upper end surface 12b of the precast duct material 10 on the lower floor, which is installed and fixed, and the lower end surface 12a of the precast duct material 10 on the upper floor are joined with a hermetic joint structure. As shown in FIG. 7, this sealed joint structure is provided with a packing 30 for sealing between the joint surfaces of the two precast duct members 10. The packing 30 is composed of a first packing member 30A to a fifth packing member 30E having a maximum of five layers in the duct inner and outer directions.
The first packing member 30 </ b> A located on the innermost side is composed of a smoke exhaust packing arranged in a rectangular ring shape in contact with the end surface of the duct component member 11 in the duct axial direction.
The second packing member 30B located second from the innermost side is made of butyl rubber arranged in a rectangular ring shape in contact with the outer surface of the rectangular ring-shaped first packing member 30A.
The third packing member 30C located third from the innermost side is an outer surface located in the joining region of the second concrete side wall part 12B to the fourth concrete side wall part 12D among the outer side faces of the rectangular annular second packing member 30B. The chloroprene rubber is arranged in a U shape in contact with the chloroprene rubber.
The fourth packing member 30D located fourth from the innermost side is made of rock wool arranged in a U shape in contact with the outer surface of the third packing member 30C.
5th packing member 30E located in the outermost side is comprised from the caulking material with which it fills between the outer side joining surfaces of 4th packing member 30D in the joining area | region of 2nd concrete side wall part 12B-4th concrete side wall part 12D. Has been.

更に、本実施形態の密封接合構造では、図7に示すように、両プレキャストダクト材10の第1コンクリート側壁部12Aの接合面間における第2パッキン部材30Bの外方側部位には、グラウト31が充填されている。この充填されたグラウト31の固化により、下階のプレキャストダクト材10の第1コンクリート側壁部12Aをもって構成される耐震壁構成用の壁部3Aと、上階のプレキャストダクト材10の第1コンクリート側壁部12Aをもって構成される耐震壁構成用の壁部3Aとが一体的に固定される。
そして、縦方向に積み上げられた両プレキャストダクト材10のうち、構築後に躯体2の耐震壁3の一部を構成する壁部3A同士をグラウト31で強固に固定することができるので、プレキャストダクト材10同士を適切な相対姿勢で長期間に亘って確実、強固に固定することができる。
Further, in the sealed joint structure of the present embodiment, as shown in FIG. 7, a grout 31 is provided on the outer side portion of the second packing member 30 </ b> B between the joint surfaces of the first concrete side wall portions 12 </ b> A of both precast duct members 10. Is filled. By solidifying the filled grout 31, the wall portion 3A for the seismic wall structure constituted by the first concrete side wall portion 12A of the precast duct material 10 on the lower floor and the first concrete side wall of the precast duct material 10 on the upper floor. The wall portion 3A for the seismic wall construction constituted by the portion 12A is fixed integrally.
And since both wall parts 3A which comprise a part of earthquake-resistant wall 3 of the housing 2 after construction among the two precast duct materials 10 piled up in the vertical direction can be firmly fixed with the grout 31, the precast duct material 10 can be firmly and firmly fixed to each other in an appropriate relative posture over a long period of time.

また、図5、図7に示すように、各プレキャストダクト材10のコンクリート外周壁12の下端面12aの複数個所(本実施形態では四箇所)、つまり、ロックウール製の第4パッキン部材30Dの配置領域における各辺の中央位置、及び、グラウト31の充填領域における中央位置の各々には、下階側のプレキャストダクト材10のコンクリート外周壁12の上端面12bとの当接により、両プレキャストダクト材10の接合面間の隙間34を設定間隔に規制する隙間調節手段の一例である隙間調節ボルト35が螺合装着されている。
複数の隙間調節ボルト35は、下階側のプレキャストダクト材10上に揚重された上階側のプレキャストダクト材10を載置したとき、パッキン30中の第1パッキン部材30A〜第3パッキン部材30Cが適切な圧縮状態となる設定間隔に規制する。
そして、上述のように複数の隙間調節ボルト35によって両プレキャストダクト材10に接合面間の隙間34が設定間隔に確実に維持されるので、パッキン30中の第1パッキン部材30A〜第3パッキン部材30Cを適切な密封状態に維持することができる。
さらに、複数の隙間調節ボルト35で水平調節することにより、各プレキャストダクト材10を縦方向に精度良く積み上げることができる。
Moreover, as shown in FIGS. 5 and 7, a plurality of locations (four locations in the present embodiment) of the lower end surface 12a of the concrete outer peripheral wall 12 of each precast duct material 10, that is, the fourth packing member 30D made of rock wool. Both the precast ducts are brought into contact with the upper end surface 12b of the concrete outer peripheral wall 12 of the precast duct material 10 on the lower floor side at the center position of each side in the arrangement area and the center position in the filling area of the grout 31. A gap adjusting bolt 35 which is an example of a gap adjusting means for restricting the gap 34 between the joining surfaces of the material 10 to a set interval is screwed and attached.
When the upper floor precast duct material 10 lifted on the lower floor side precast duct material 10 is placed, the plurality of gap adjusting bolts 35 are provided with the first packing member 30A to the third packing member in the packing 30. 30C is regulated to a set interval at which the compression state is appropriate.
And as above-mentioned, since the clearance gap 34 between joining surfaces is reliably maintained by the setting space | interval in both the precast duct materials 10 with the some clearance adjustment bolt 35, the 1st packing member 30A-the 3rd packing member in the packing 30 is maintained. 30C can be maintained in a proper sealed condition.
Furthermore, by horizontally adjusting the plurality of gap adjusting bolts 35, the precast duct members 10 can be stacked with high accuracy in the vertical direction.

尚、図4、図5、図7に示すように、両プレキャストダクト材10のコンクリート外周壁12の下端面12a及び上端面12bのうち、第2コンクリート側壁部12B〜第4コンクリート側壁部12Dの接合領域に対応する部位には、クロロプレンゴム製の第3パッキン部材30Cの上側部及び下側部が嵌合装着される位置決め用の装着溝32,33が形成されている。   In addition, as shown in FIG.4, FIG.5, FIG.7, among the lower end surface 12a and the upper end surface 12b of the concrete outer peripheral wall 12 of both the precast duct materials 10, of 2nd concrete side wall part 12B-4th concrete side wall part 12D. Positioning mounting grooves 32 and 33 into which the upper side and lower side of the third packing member 30C made of chloroprene rubber are fitted and mounted are formed at portions corresponding to the joining region.

次に、上述の密封接合構造の施工手順について説明する。
上階側のプレキャストダクト材10を、先に据付固定されている下階側のプレキャストダクト材10の上端部に揚重するとき、図示は省略するが、下階側のプレキャストダクト材10のコンクリート外周壁12の上端面12bには、第1パッキン部材30A〜第3パッキン部材30Cを予め配置しておく。このとき、第3パッキン部材30Cの下側部は、下階側のプレキャストダクト材10のコンクリート外周壁12の上端面12bに形成されている装着溝33に嵌合装着されている。
下階側のプレキャストダクト材10の上端部に上階側のプレキャストダクト材10が据付固定された状態では、第3パッキン部材30Cの上側部は、上階側のプレキャストダクト材10のコンクリート外周壁12の下端面12aに形成されている装着溝32に嵌合装着された状態にあるので、第1パッキン部材30A〜第4パッキン部材30Dの位置ずれを抑制することができる。
その後、第2コンクリート側壁部12B〜第4コンクリート側壁部12Dの接合領域における第4パッキン部材30Dの外方側の接合面間に、第5パッキン部材30Eを構成するコーキング材を充填する。さらに、両プレキャストダクト材10の第1コンクリート側壁部12Aの接合面間における第2パッキン部材30Bの外方側部位に、グラウト31を充填する。
Next, the construction procedure of the above-described sealed joint structure will be described.
When the upper floor side precast duct material 10 is lifted to the upper end portion of the lower floor side precast duct material 10 that has been previously installed and fixed, the concrete of the lower floor side precast duct material 10 is omitted although illustration is omitted. A first packing member 30 </ b> A to a third packing member 30 </ b> C are arranged in advance on the upper end surface 12 b of the outer peripheral wall 12. At this time, the lower side portion of the third packing member 30C is fitted and mounted in a mounting groove 33 formed on the upper end surface 12b of the concrete outer peripheral wall 12 of the precast duct material 10 on the lower floor side.
In the state where the upper floor side precast duct material 10 is installed and fixed to the upper end portion of the lower floor side precast duct material 10, the upper portion of the third packing member 30C is the concrete outer peripheral wall of the upper floor side precast duct material 10 12 is fitted and mounted in the mounting groove 32 formed in the lower end surface 12a of the twelve lower end surface 12a, so that the displacement of the first packing member 30A to the fourth packing member 30D can be suppressed.
Then, the caulking material which comprises the 5th packing member 30E is filled between the joint surfaces of the 4th packing member 30D in the outer side in the joining area | region of 2nd concrete side wall part 12B-4th concrete side wall part 12D. Further, the grout 31 is filled in the outer side portion of the second packing member 30B between the joint surfaces of the first concrete side wall portions 12A of the two precast duct members 10.

尚、設置階の床スラブ5と一節のプレキャストダクト材10との接合面間の密封接合構造及び施工手順は、上述の両プレキャストダクト材10の接合面間の密封接合構造及び施工手順と同一である。   In addition, the sealing joint structure and construction procedure between the joint surfaces of the floor slab 5 of the installation floor and the precast duct member 10 of the passage are the same as the above-described sealed joint structure and construction procedure between the joint surfaces of the two precast duct members 10. is there.

図9は、PCa製作場において、耐震壁3を構成するハーフプレキャスト壁40の製作説明図である。本実施形態では、ハーフプレキャスト壁40に対応する水平な成形型枠内に、トラス筋41、セパレータ42等を配筋するとともに、配管Pの支持金具50を取付けるための取付け金具(図示せず)をインサート状態で配置し、トラス筋41のトップ側及びセパレータ42の一端側が露出する状態でコンクリート48を打設する。
このPCa製作場においては、ハーフプレキャスト壁40の複数のセパレータ42の上端部に係合する位置決め用の定規49が取付けられている。
FIG. 9 is a production explanatory view of the half precast wall 40 constituting the earthquake resistant wall 3 in the PCa production site. In the present embodiment, a truss bar 41, a separator 42, and the like are arranged in a horizontal mold corresponding to the half precast wall 40, and a mounting bracket (not shown) for mounting the support bracket 50 of the pipe P is provided. Is placed in an insert state, and concrete 48 is placed in a state where the top side of the truss bar 41 and one end side of the separator 42 are exposed.
In this PCa manufacturing site, a positioning ruler 49 that is engaged with the upper ends of the plurality of separators 42 of the half precast wall 40 is attached.

製作されたハーフプレキャスト壁40は、図10に示すように、PCa製作場の床面から所定高さ位置に縦向き姿勢に保持し、ハーフプレキャスト壁40にインサートされている取付け金具に支持金具50を固定連結し、支持金具50に集合配水管等の配管Pを取付ける。配管Pは、ハーフプレキャスト壁40の下端よりも下方に所定長さ突出し、耐震壁構築箇所に揚重されたとき、耐震壁構築箇所の床スラブ5に形成されている配管孔(図示せず)に各配管Pの下側突出管部を挿入する。   As shown in FIG. 10, the manufactured half precast wall 40 is held in a vertical posture at a predetermined height position from the floor surface of the PCa production site, and the mounting bracket 50 inserted into the half precast wall 40 is supported by the support bracket 50. Are fixedly connected, and a pipe P such as a collecting water pipe is attached to the support fitting 50. The pipe P protrudes below the lower end of the half precast wall 40 by a predetermined length, and when it is lifted to the earthquake-resistant wall construction site, a pipe hole (not shown) formed in the floor slab 5 of the earthquake-resistant wall construction site. The lower projecting pipe portion of each pipe P is inserted into

〔その他の実施形態〕
(1)上述の実施形態では、PCa製作場において、筒状の金属製のダクト構成部材11を外周面11aを内型枠としてコンクリートを打設して、ダクト構成部材11の外周面11aにコンクリート外周壁12が一体成形されたプレキャストダクト材10を製作したが、この構成に限定されるものではない。例えば、PCa製作場において、筒状の金属製のダクト構成部材11の外周側に、予め筒状に製作されたコンクリート外周壁12又はダクト構成部材11の各側面に対応する大きさで予め製作された分割構造のコンクリート外周壁12を取付け金具で一体的に取付け構成してもよい。
[Other Embodiments]
(1) In the above-described embodiment, in the PCa production site, concrete is placed using the cylindrical metal duct constituent member 11 as the outer peripheral surface 11 a as the inner mold frame, and the concrete is applied to the outer peripheral surface 11 a of the duct constituent member 11. Although the precast duct material 10 in which the outer peripheral wall 12 is integrally formed is manufactured, it is not limited to this configuration. For example, in the PCa production site, the outer peripheral side of the cylindrical metal duct constituent member 11 is manufactured in advance in a size corresponding to each side surface of the concrete outer peripheral wall 12 or duct constituent member 11 manufactured in advance in a cylindrical shape. Alternatively, the concrete outer peripheral wall 12 having a divided structure may be integrally mounted with a mounting bracket.

(2)上述の実施形態では、PCa化されたプレキャストダクト材10の一側部である第1コンクリート側壁部12Aをもって、構築後に躯体2の耐震壁3の一部の壁部3Aを構成したが、この構成に限定されるものではない。例えば、プレキャストダクト材10の直交する二辺(二側部)のコンクリート側壁部をもって、構築後に躯体2の耐震壁3の一部の壁部3Aを構成してもよい。   (2) In the above-described embodiment, the first concrete side wall portion 12A that is one side portion of the PCa precast duct material 10 is used to configure a part of the wall portion 3A of the seismic wall 3 of the housing 2 after construction. However, the present invention is not limited to this configuration. For example, a part of the wall portion 3A of the seismic wall 3 of the housing 2 may be configured after construction by using the concrete side wall portions of two orthogonal sides (two side portions) of the precast duct material 10.

(3)上述の実施形態では、据付固定されている下階のプレキャストダクト材10の上端面12bと上階のプレキャストダクト材10の下端面12aとの密封接合構造を、ダクト内外方向で最大5層となるパッキン30から構成したが、単一のパッキン30又は5層以外の複数層のパッキン30から構成してもよい。   (3) In the above-described embodiment, the upper end surface 12b of the lower floor precast duct material 10 which is fixedly installed and the lower end surface 12a of the upper floor precast duct material 10 have a maximum of 5 in the duct inside / outside direction. Although composed of the packing 30 as a layer, it may be composed of a single packing 30 or a plurality of packings 30 other than five layers.

(4)上述の実施形態では、プレキャストダクト材10を躯体2に固定しながら順次縦方向に積み上げることにより、建物のダクト構築箇所に竪ダクト4を構築したが、プレキャストダクト材10を躯体2に固定しながら順次横方向に接合して、建物のダクト構築箇所に横ダクトを構築してもよい。   (4) In the above-described embodiment, the precast duct material 10 is fixed to the housing 2 and stacked in the vertical direction in order to construct the firewood duct 4 at the duct construction location of the building. You may construct | assemble a horizontal duct in the duct construction location of a building by joining sequentially in the horizontal direction, fixing.

(5)上述の実施形態では、プレキャストダクト材10のコンクリート外周壁12の一側部が、構築後に躯体2の一部を構成する壁部3Aに構成されている形態を例示したが、本発明は、プレキャストダクト材10のコンクリート外周壁12の一側部が、構築後に躯体2の一部を構成しない形態を含むものである。   (5) In the above-mentioned embodiment, although the one side part of the concrete outer peripheral wall 12 of the precast duct material 10 illustrated the form comprised by the wall part 3A which comprises some housings 2 after construction, this invention Includes a form in which one side portion of the concrete outer peripheral wall 12 of the precast duct material 10 does not constitute a part of the housing 2 after construction.

(6)上述の実施形態では、プレキャストダクト材10のPCa化にあたって、構築後に躯体2の耐震壁3の一部を構成する壁部3Aを含めてコンクリート外周壁12全体を完成又は略完成状態で予め製作したが、このプレキャストダクト材10をハーフプレキャストから構成してもよい。例えば、プレキャストダクト材10のコンクリート外周壁12の四つの側面を構成する第1コンクリート側壁部12A〜第4コンクリート側壁部12Dのうち、躯体2の耐震壁3と一体形成される一側面(一側部)の第1コンクリート側壁部12Aを、トラス筋等の配筋及び型枠取付け用のセパレータが露出する状態で設定厚みよりも小なる厚みで製作する。
そして、ダクト構築位置に揚重して据付けられたハーフプレキャストのプレキャストダクト材10に予め設けられているセパレータに、型枠としてのコンクリート型枠を取付ける。また、耐震壁構築位置に揚重して据付けられたハーフプレキャスト壁40に予め設けられているセパレータ42に、外型枠46としてのコンクリート型枠を取付ける。この状態でコンクリートを打設して、竪ダクト4と耐震壁3とを一体的に構築する。
(6) In the above-described embodiment, when the precast duct material 10 is converted to PCa, the entire concrete outer peripheral wall 12 including the wall portion 3A constituting a part of the earthquake-resistant wall 3 of the housing 2 after construction is completed or substantially completed. Although prefabricated, this precast duct material 10 may be composed of half precast. For example, one side surface (one side) of the first concrete side wall portion 12A to the fourth concrete side wall portion 12D constituting the four side surfaces of the concrete outer peripheral wall 12 of the precast duct material 10 that is integrally formed with the earthquake resistant wall 3 of the casing 2. Part) of the first concrete side wall 12A is manufactured with a thickness smaller than the set thickness in a state where the reinforcing bars such as truss bars and the separator for attaching the formwork are exposed.
And the concrete formwork as a formwork is attached to the separator previously provided in the precast duct material 10 of the half precast lifted and installed in the duct construction position. In addition, a concrete formwork as an outer formwork 46 is attached to a separator 42 provided in advance on a half precast wall 40 that is lifted and installed at the seismic wall construction position. Concrete is cast in this state, and the culvert duct 4 and the earthquake-resistant wall 3 are constructed integrally.

2 躯体
3A 壁部
4 ダクト(竪ダクト)
10 プレキャストダクト材
11 ダクト構成部材
12 コンクリート外周壁
30 パッキン
31 グラウト
2 Housing 3A Wall 4 Duct
DESCRIPTION OF SYMBOLS 10 Precast duct material 11 Duct component 12 Concrete outer peripheral wall 30 Packing 31 Grout

Claims (5)

筒状のダクト構成材の外周側にコンクリート外周壁が一体形成されたプレキャストダクト材を予め製作したのち、前記プレキャストダクト材を建物のダクト構築箇所の据付位置に揚重し、揚重された前記プレキャストダクト材を前記建物の躯体に固定するダクト構築方法。   After the precast duct material in which the concrete outer peripheral wall is integrally formed on the outer peripheral side of the cylindrical duct component material is manufactured in advance, the precast duct material is lifted to the installation position of the duct construction location of the building and lifted. A duct construction method for fixing a precast duct material to the building frame. 前記プレキャストダクト材を前記躯体に固定しながら順次縦方向に積み上げることにより、前記建物のダクト構築箇所に竪ダクトを構築する請求項1記載のダクト構築方法。   The duct construction method according to claim 1, wherein the precast duct material is sequentially stacked in a vertical direction while being fixed to the housing, thereby constructing a duct duct at a duct construction location of the building. 前記ダクト構築箇所の据付位置に揚重された後続の前記プレキャストダクト材は、据付られた先行の前記プレキャストダクト材との接合面間にパッキンを圧縮状態に配置した状態で積み上げられている請求項2記載のダクト構築方法。   The subsequent precast duct material lifted to the installation position of the duct construction site is stacked in a state in which packing is arranged in a compressed state between the joint surfaces with the installed previous precast duct material. 2. The duct construction method according to 2. 前記プレキャストダクト材の前記コンクリート外周壁の一側部が、構築後に前記躯体の一部を構成する壁部に構成されている請求項2又は3記載のダクト構築方法。   The duct construction method according to claim 2 or 3, wherein one side portion of the concrete outer peripheral wall of the precast duct material is configured as a wall portion that constitutes a part of the frame after construction. 前記ダクト構築箇所の据付位置に据付られた先行の前記プレキャストダクト材の接合面における前記壁部に相当する部位と、後続の前記プレキャストダクト材の接合面における前記壁部に相当する部位との間にグラウトを充填することにより、先行の前記プレキャストダクト材の前記壁部と後続の前記プレキャストダクト材の前記壁部とを固定する請求項4記載のダクト構築方法。   Between the part corresponding to the wall part in the joint surface of the preceding precast duct material installed at the installation position of the duct construction part and the part corresponding to the wall part in the joint surface of the subsequent precast duct material The duct construction method according to claim 4, wherein the wall portion of the preceding precast duct material and the wall portion of the subsequent precast duct material are fixed by filling grout into the wall.
JP2016210980A 2016-10-27 2016-10-27 Duct construction method Active JP6842881B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016210980A JP6842881B2 (en) 2016-10-27 2016-10-27 Duct construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016210980A JP6842881B2 (en) 2016-10-27 2016-10-27 Duct construction method

Publications (2)

Publication Number Publication Date
JP2018071159A true JP2018071159A (en) 2018-05-10
JP6842881B2 JP6842881B2 (en) 2021-03-17

Family

ID=62114827

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016210980A Active JP6842881B2 (en) 2016-10-27 2016-10-27 Duct construction method

Country Status (1)

Country Link
JP (1) JP6842881B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519867A (en) * 2020-04-28 2020-08-11 河南远大可持续建筑科技有限公司 Fireproof plugging process for inner wall of steel-structure elevator shaft
CN113503000A (en) * 2021-08-04 2021-10-15 六安金安区环保烟道厂 Precast layer-by-layer assembled forming flue
CN115262960A (en) * 2022-07-04 2022-11-01 福建建工集团有限责任公司 Vertical pipe-wrapped construction method for cast-in-place concrete by adopting shaping mold
CN115341741A (en) * 2022-03-04 2022-11-15 深圳泛华工程集团有限公司 Flue structure and construction method
KR102526359B1 (en) * 2022-09-19 2023-05-04 (주)피씨엠글로벌기술사건축사사무소 One-piece construction method for vertical windpipes among firefighting ventilation systems

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4931139A (en) * 1972-07-19 1974-03-20
JPH07155083A (en) * 1993-12-08 1995-06-20 Kajima Corp Pigeon hut assembly method
JPH0849227A (en) * 1994-08-05 1996-02-20 Maeda Seikan Kk Construction method for annexed structure to dam body, and block for forming structure
JP2001020297A (en) * 1999-07-12 2001-01-23 Norie Yukimura Sc-structured footing beam method for building
JP2004352457A (en) * 2003-05-29 2004-12-16 Ohbayashi Corp Junction structure for shaft unit in elevator shaft
JP2008107061A (en) * 2006-10-27 2008-05-08 Toshiba Corp Air-conditioning duct straightening plate slit, constructing method of air-conditioning duct straightening plate slit and radioactive substance storage building
CN204645727U (en) * 2015-05-11 2015-09-16 有利华建筑预制件有限公司 Prefabricated toilet

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4931139A (en) * 1972-07-19 1974-03-20
JPH07155083A (en) * 1993-12-08 1995-06-20 Kajima Corp Pigeon hut assembly method
JPH0849227A (en) * 1994-08-05 1996-02-20 Maeda Seikan Kk Construction method for annexed structure to dam body, and block for forming structure
JP2001020297A (en) * 1999-07-12 2001-01-23 Norie Yukimura Sc-structured footing beam method for building
JP2004352457A (en) * 2003-05-29 2004-12-16 Ohbayashi Corp Junction structure for shaft unit in elevator shaft
JP2008107061A (en) * 2006-10-27 2008-05-08 Toshiba Corp Air-conditioning duct straightening plate slit, constructing method of air-conditioning duct straightening plate slit and radioactive substance storage building
CN204645727U (en) * 2015-05-11 2015-09-16 有利华建筑预制件有限公司 Prefabricated toilet

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519867A (en) * 2020-04-28 2020-08-11 河南远大可持续建筑科技有限公司 Fireproof plugging process for inner wall of steel-structure elevator shaft
CN113503000A (en) * 2021-08-04 2021-10-15 六安金安区环保烟道厂 Precast layer-by-layer assembled forming flue
CN115341741A (en) * 2022-03-04 2022-11-15 深圳泛华工程集团有限公司 Flue structure and construction method
CN115341741B (en) * 2022-03-04 2024-09-06 深圳泛华工程集团有限公司 Flue structure and construction method
CN115262960A (en) * 2022-07-04 2022-11-01 福建建工集团有限责任公司 Vertical pipe-wrapped construction method for cast-in-place concrete by adopting shaping mold
KR102526359B1 (en) * 2022-09-19 2023-05-04 (주)피씨엠글로벌기술사건축사사무소 One-piece construction method for vertical windpipes among firefighting ventilation systems

Also Published As

Publication number Publication date
JP6842881B2 (en) 2021-03-17

Similar Documents

Publication Publication Date Title
JP2018071159A (en) Duct construction method
US9243398B2 (en) Modular building system for constructing multi-story buildings
EP3907339A1 (en) Integrated steel concrete building and construction method thereof
CN108005265B (en) Multilayer prefabricated steel reinforced concrete shear wall structure and preparation and construction methods thereof
ES2333636B1 (en) PRE-MANUFACTURED SEMIRRESISTENT MODULE FOR CONSTRUCTION AND PROCEDURE ASSEMBLY ON THE WORK OF THE SAME.
WO2019121958A1 (en) Construction element, a module and a construction comprising such an element and method of assembly of such a construction
CN102877646A (en) Method for building grouted overlapping assembly type reinforced concrete shear wall structure
JP2004285691A (en) Earthquake-resisting reinforced extension method of building and earthquake-resisting reinforced extension building
US3527002A (en) Modular building structure
CN108005266B (en) Strip steel frame precast reinforced concrete shear wall structure and preparation and installation methods
CN212295078U (en) Steel assembled synthetic concrete building
JP5865567B2 (en) Connecting slab and its construction method
JP4399676B2 (en) Building structure and its construction method
CN111980220A (en) Assembled integral multi-cavity steel plate composite shear wall and construction method thereof
JP2013238095A (en) Construction method of reinforced concrete skeleton and reinforced concrete structural skeleton
JP4520242B2 (en) Frame structure of apartment house
KR101826086B1 (en) The Horizontal And Vertical Expansion Of Public Housing Methods Applied Post-Tensioning
JPH1113189A (en) Half-precast floor slab and floor structure using the same
KR100228016B1 (en) Flexible frame structure and its manufacturing method
CN218990778U (en) Assembled smoke prevention and exhaust air duct for building
CN213329469U (en) Sectional type steel construction modularization node and assembled building
KR102659857B1 (en) Precast Concrete Panel for exterior wall and construction method
CN214364135U (en) Sectional type steel structure modular node with short beam and assembly type building
KR100711484B1 (en) Stand-alone construction equipment and construction method of middle-tier steel house using it
HK40029402A (en) Integrated steel concrete building and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200731

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200805

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200925

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210210

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210222

R150 Certificate of patent or registration of utility model

Ref document number: 6842881

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150