[go: up one dir, main page]

JP2009173435A - Safety stock quantity calculation system and safety stock quantity calculation program - Google Patents

Safety stock quantity calculation system and safety stock quantity calculation program Download PDF

Info

Publication number
JP2009173435A
JP2009173435A JP2008016224A JP2008016224A JP2009173435A JP 2009173435 A JP2009173435 A JP 2009173435A JP 2008016224 A JP2008016224 A JP 2008016224A JP 2008016224 A JP2008016224 A JP 2008016224A JP 2009173435 A JP2009173435 A JP 2009173435A
Authority
JP
Japan
Prior art keywords
safety stock
day
stock quantity
arrival
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
JP2008016224A
Other languages
Japanese (ja)
Inventor
Hiroshi Fujiwara
寛 藤原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Electric Works Co Ltd
Original Assignee
Panasonic Electric Works Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panasonic Electric Works Co Ltd filed Critical Panasonic Electric Works Co Ltd
Priority to JP2008016224A priority Critical patent/JP2009173435A/en
Publication of JP2009173435A publication Critical patent/JP2009173435A/en
Ceased legal-status Critical Current

Links

Images

Landscapes

  • General Factory Administration (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To calculate appropriate safe stock quantities considering arrival delay of commercial products. <P>SOLUTION: This system 1 for calculating safe stock quantities stores actual arrival quantity of commercial produces relative to quantity scheduled for arrival with respect to each day; calculates a differential value between the quantity scheduled for arrival and the actual arrival quantity as a first differential value with respect to each day within an evaluation period; executes a process with respect to each day within the evaluation period to calculate a value by accumulating the first differential values for procurement days as a first cumulative difference; calculates an average value of the first cumulative differences for the respective days within the evaluation period and a standard deviation value; and calculates the safe stock quantities of the commercial products with respect to the arrival delay by using the calculated average value of the first cumulative differences and the standard deviation value. <P>COPYRIGHT: (C)2009,JPO&amp;INPIT

Description

本発明は、商品の安全在庫数を算出するための安全在庫数算出システム及び安全在庫数算出プログラムに関する。   The present invention relates to a safe stock quantity calculation system and a safe stock quantity calculation program for calculating a safe stock quantity of a product.

従来の商品の発注処理では、現時点における商品の消費予定数(需要予測数)と入荷予定数に基づいて商品の調達期間(調達日数)だけ先の商品の在庫数を推定し、推定された在庫数が商品の消費予定数と安全在庫数の和以下になる場合にその差分を発注数として商品を発注していた。より具体的には、現時点が4月1日、調達期間が4日、調達期間だけ先、すなわち4月4日における商品の消費予定数が65個、調達期間が経過する前日、すなわち4月3日時点における商品の在庫数が60個、安全在庫数が10個である場合、従来の商品の発注処理では、4月4日に商品が65個消費されたとしても10個の商品が安全在庫として残るように、4月1日の時点で15個(消費予定分5個+安全在庫分10個)の商品を発注する。
特開2005−306543号公報
In the conventional product ordering process, the number of products in stock ahead is estimated for the product procurement period (number of procurement days) based on the current number of products expected to be consumed (demand forecast number) and the expected number of goods received. When the number is less than or equal to the sum of the planned consumption of the product and the number of safety stock, the product is ordered using the difference as the order quantity. More specifically, the current time is April 1, the procurement period is 4 days, the procurement period is ahead, that is, the planned consumption number of products on April 4 is 65, the day before the procurement period elapses, that is, April 3 If the number of items in stock at the time of day is 60 and the number of safety stocks is 10, in the conventional ordering process for products, even if 65 items are consumed on April 4, 10 items remain in safe stock. As of April 1, 15 items (5 for consumption and 10 for safety stock) are ordered.
JP-A-2005-306543

通常であれば商品は発注してから調達期間後に予定通り入荷するが、場合によっては商品の入荷が遅れることがある。しかしながら従来の商品の発注処理では、商品の入荷遅れを考慮せずに安全在庫数を設定しているために、安全在庫が多くなりすぎたりする等、安全在庫数が不適切な数になることがあった。   Normally, merchandise is received as scheduled after the procurement period after placing an order, but in some cases, the arrival of merchandise may be delayed. However, in the conventional product ordering process, the safety stock number is set without taking into account the arrival delay of the product, so the safety stock number becomes inappropriate, such as excessive safety stock. was there.

本発明は、上記課題を解決するためになされたものであり、その目的は、商品の入荷遅れを考慮して適切な安全在庫数を算出可能な安全在庫数算出システム及び安全在庫数算出プログラムを提供することにある。   The present invention has been made to solve the above-described problems, and an object of the present invention is to provide a safety stock number calculation system and a safety stock number calculation program capable of calculating an appropriate safety stock number in consideration of arrival delay of goods. It is to provide.

本発明に係る安全在庫数算出システム及び安全在庫数算出プログラムは、商品の入荷予定数に対する入荷実績数を日毎に記憶し、評価期間内の各日について入荷予定数と入荷実績数の差分値を算出し、差分値を調達日数分加算した値を累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の累積差の平均値と標準偏差値を算出し、算出された累積差の平均値と標準偏差値を用いて商品の安全在庫数を算出する。   The safety stock quantity calculation system and the safety stock quantity calculation program according to the present invention memorize the number of actual arrivals with respect to the expected arrival number of goods for each day, and calculate the difference between the expected arrival quantity and the actual arrival number for each day in the evaluation period. Calculate and execute a process of calculating a difference value added for the number of days of procurement as a cumulative difference for each day in the evaluation period, and calculate an average value and a standard deviation value of the cumulative difference for each day in the evaluation period, The safety stock number of the product is calculated using the average value and the standard deviation value of the calculated cumulative difference.

本発明に係る安全在庫数算出システム及び安全在庫数算出プログラムによれば、商品の入荷遅れを考慮して適切な安全在庫数を算出することができる。   According to the safety stock quantity calculation system and the safety stock quantity calculation program according to the present invention, it is possible to calculate an appropriate safety stock quantity in consideration of the arrival delay of goods.

本発明の実施形態となる安全在庫数算出システム1は、ワークステーション等の汎用又は専用の情報処理装置により構成され、図1に示すように、データベース2と、入荷予定履歴格納部3と、消費予定履歴格納部4と、安全在庫数算出部5とを主な構成要素として備える。データベース2は、商品の調達に要する日数(調達期間)のデータを商品毎に格納する調達期間マスタDB6と、調達期間だけ先の日の入荷予定数のデータを商品及び日単位で格納する入荷予定履歴DB7と、入荷実績数のデータを商品及び日単位で格納する入荷実績履歴DB8と、調達期間だけ先の日の消費予定数のデータを商品及び日単位で格納する消費予定履歴DB9と、消費実績数のデータを商品及び日単位で格納する消費実績履歴DB10と、安全在庫数のデータを商品毎に格納する安全在庫数格納DB11とを備える。   A safety stock quantity calculation system 1 according to an embodiment of the present invention is configured by a general-purpose or dedicated information processing device such as a workstation. As shown in FIG. 1, a database 2, a scheduled arrival history storage unit 3, a consumption The scheduled history storage unit 4 and the safety stock quantity calculation unit 5 are provided as main components. The database 2 includes a procurement period master DB 6 that stores data on the number of days required for product procurement (procurement period) for each product, and an arrival schedule that stores data on the number of products scheduled to be received the day before the procurement period on a product and daily basis. A history DB 7, an arrival history DB 8 that stores data on the number of arrivals in units of goods and days, a consumption schedule history DB 9 that stores data on the number of scheduled consumptions in the days ahead of the procurement period, and consumption A consumption history DB 10 that stores data on the number of records in units of products and days, and a safety stock number storage DB 11 that stores data on the number of safety stocks for each product are provided.

入荷予定履歴格納部3は、情報処理装置内のCPUがROM内に記憶されたコンピュータプログラムを実行することにより、調達期間マスタDB6から各商品の調達期間のデータを取得し、調達期間だけ先の日付の商品の入荷予定数を日単位で算出し、算出された入荷予定数のデータを入荷予定履歴DB7内に格納する。消費予定履歴格納部4は、情報処理装置内のCPUがROM内に記憶されたコンピュータプログラムを実行することにより、調達期間マスタDB6から各商品の調達期間のデータを取得し、調達期間だけ先の日付の商品の消費予定数を日単位で算出し、算出された消費予定数のデータを消費予定履歴DB9内に格納する。安全在庫数算出部5は、情報処理装置内のCPUがROM内に記憶されたコンピュータプログラムを実行することにより、データベース2内に格納されているデータを利用して各商品の安全在庫数を算出し、算出された安全在庫数のデータを安全在庫数格納DB11内に格納する。   The arrival schedule history storage unit 3 acquires the procurement period data of each product from the procurement period master DB 6 by executing the computer program stored in the ROM by the CPU in the information processing apparatus. The scheduled arrival number of the product on the date is calculated on a daily basis, and the calculated scheduled arrival number data is stored in the arrival schedule history DB 7. The consumption schedule history storage unit 4 acquires the procurement period data of each product from the procurement period master DB 6 by executing the computer program stored in the ROM by the CPU in the information processing apparatus. The number of scheduled consumptions of the product on the date is calculated on a daily basis, and the calculated scheduled consumption number data is stored in the consumption schedule history DB 9. The safety stock quantity calculation unit 5 calculates the safety stock quantity of each product using the data stored in the database 2 by the CPU in the information processing apparatus executing a computer program stored in the ROM. Then, the calculated safety stock quantity data is stored in the safety stock quantity storage DB 11.

このような構成を有する安全在庫数算出システム1は、以下に示す差分値算出処理(1),(2)と安全在庫数算出処理を実行することにより、商品の入荷遅れを考慮して適切な安全在庫数を算出すると同時に消費予定数が消費実績数よりも多い場合に必要量以上の安全在庫数が算出されことを防止する。以下、図2乃至図4に示すフローチャートを参照して、差分値算出処理及び安全在庫数算出処理を実行する際の安全在庫数算出システム1の動作について詳しく説明する。   The safety stock quantity calculation system 1 having such a configuration performs appropriate processing in consideration of the arrival delay of goods by executing the following difference value calculation processes (1) and (2) and the safety stock quantity calculation process. At the same time as calculating the number of safety stocks, it is prevented that the number of safety stocks exceeding the necessary amount is calculated when the planned consumption number is larger than the actual consumption number. Hereinafter, the operation of the safety stock quantity calculation system 1 when executing the difference value calculation process and the safety stock quantity calculation process will be described in detail with reference to the flowcharts shown in FIGS.

〔差分値算出処理(1)〕
図2に示すフローチャートは、各日の所定時刻に開始となり、この差分値算出処理はステップS1の処理に進む。なおこの差分値算出処理におけるステップS2の処理は、必ずしも日毎に行う必要はなく、安全在庫数を算出する際に評価期間内の各日について一度に行うようにしてもよい。
[Difference calculation process (1)]
The flowchart shown in FIG. 2 starts at a predetermined time on each day, and the difference value calculation process proceeds to the process of step S1. Note that the process of step S2 in this difference value calculation process does not necessarily have to be performed every day, and may be performed once for each day in the evaluation period when calculating the number of safety stocks.

ステップS1の処理では、入荷予定履歴格納部3が、調達期間だけ先の日付の商品の入荷予定数を算出して入荷予定履歴DB7に格納する。具体的には本日の日付が4月1日であり、調達期間が4日である場合、入荷予定履歴格納部3は4月4日の入荷予定数を算出して入荷予定履歴DB7に格納する。また図示しない情報処理装置が、その日の入荷実績数を集計して入荷実績履歴DB8に格納する。これにより、ステップS1の処理は完了し、差分値算出処理はステップS2の処理に進む。   In the process of step S1, the arrival schedule history storage unit 3 calculates the expected arrival number of the product with the date earlier than the procurement period and stores it in the arrival schedule history DB 7. Specifically, when today's date is April 1 and the procurement period is 4 days, the arrival schedule history storage unit 3 calculates the number of arrivals scheduled for April 4 and stores it in the arrival schedule history DB 7. . Further, an information processing device (not shown) counts the number of arrivals of the day and stores it in the arrivals history log DB 8. Thereby, the process of step S1 is completed and a difference value calculation process progresses to the process of step S2.

ステップS2の処理では、安全在庫数算出部4が、その日の入荷実績数と入荷予定数の差分値(入荷予定数−入荷実績数)を入荷遅れ数(第1の差分値)として算出して安全在庫数格納DB11内に格納する。具体的には本日の日付が4月1日である場合、安全在庫数算出部4は4月1日の入荷実績数と入荷予定数の差分値を算出して安全在庫数格納DB11内に格納する。これにより、ステップS2の処理は完了し、一連の差分値算出処理は終了する。   In the process of step S2, the safety stock quantity calculation unit 4 calculates the difference value (the expected arrival quantity-the actual arrival quantity) between the actual arrival quantity and the expected arrival quantity on that day as the arrival delay quantity (first difference value). Store in the safety stock quantity storage DB 11. Specifically, when today's date is April 1, the safety stock quantity calculation unit 4 calculates a difference value between the actual arrival quantity and the expected arrival quantity on April 1 and stores it in the safe stock quantity storage DB 11. To do. Thereby, the process of step S2 is completed and a series of difference value calculation processes are complete | finished.

〔差分値算出処理(2)〕
図3に示すフローチャートは、各日の所定時刻に開始となり、この差分値算出処理はステップS11の処理に進む。なおこの差分値算出処理におけるステップS12の処理は、必ずしも日毎に行う必要はなく、安全在庫数を算出する際に評価期間内の各日について一度に行うようにしてもよい。
[Difference calculation process (2)]
The flowchart shown in FIG. 3 starts at a predetermined time of each day, and the difference value calculation process proceeds to the process of step S11. Note that the process of step S12 in the difference value calculation process is not necessarily performed every day, and may be performed at once for each day in the evaluation period when calculating the safety stock quantity.

ステップS11の処理では、消費予定履歴格納部4が、調達期間だけ先の日付の商品の消費予定数を算出して消費予定履歴DB9に格納する。具体的には本日の日付が4月1日であり、調達期間が4日である場合、消費予定履歴格納部4は4月4日の消費予定数を算出して消費予定履歴DB9に格納する。また図示しない情報処理装置が、その日の消費実績数を集計して消費実績履歴DB10に格納する。これにより、ステップS11の処理は完了し、差分値算出処理はステップS12の処理に進む。   In the process of step S11, the consumption schedule history storage unit 4 calculates the planned consumption number of the product with the date earlier than the procurement period and stores it in the consumption schedule history DB 9. Specifically, when today's date is April 1 and the procurement period is 4 days, the consumption schedule history storage unit 4 calculates the number of consumption scheduled for April 4 and stores it in the consumption schedule history DB 9. . In addition, an information processing device (not shown) counts the number of consumption records for the day and stores it in the consumption record history DB 10. Thereby, the process of step S11 is completed and a difference value calculation process progresses to the process of step S12.

ステップS12の処理では、安全在庫数算出部5が、その日の消費実績数と消費予定数の差分値(消費実績数−消費予定数)を第2の差分値として算出して安全在庫数格納DB11内に格納する。具体的には本日の日付が4月1日である場合、安全在庫数算出部5は4月1日の消費実績数と消費予定数の差分値を算出して安全在庫数格納DB11内に格納する。これにより、ステップS12の処理は完了し、一連の差分値算出処理は終了する。   In the process of step S12, the safety stock quantity calculation unit 5 calculates the difference value (consumption actual number-consumed consumption number) between the actual consumption number and the expected consumption number on the day as the second difference value, and stores the safe stock quantity storage DB11. Store in. Specifically, when today's date is April 1, the safe stock quantity calculation unit 5 calculates a difference value between the actual consumption quantity and the planned consumption quantity on April 1 and stores it in the safe stock quantity storage DB 11. To do. Thereby, the process of step S12 is completed and a series of difference value calculation processes are complete | finished.

〔安全在庫数算出処理〕
図4に示すフローチャートは、図示しない入力装置を介してユーザが安全在庫数の算出を指示したタイミングで開始となり、安全在庫数算出処理はステップS21の処理に進む。なお安全在庫数の算出を指示する際、ユーザは安全在庫数を評価する期間(評価期間)も指定する。また以下に示す安全在庫数算出処理は商品毎に個別に実行されるものとする。
[Safety inventory calculation process]
The flowchart shown in FIG. 4 starts at the timing when the user instructs the calculation of the safety stock quantity via an input device (not shown), and the safety stock quantity calculation process proceeds to the process of step S21. When instructing the calculation of the safety stock quantity, the user also specifies a period (evaluation period) for evaluating the safety stock quantity. In addition, the safety stock quantity calculation process shown below is executed individually for each product.

ステップS21の処理では、安全在庫数算出部5が、安全在庫数格納DB11から評価期間内の各日の第1及び第2の差分値を読み出し、読み出された第1の第2の差分値をそれぞれ調達期間分加算して第1及び第2の累積差を算出する処理を評価期間内の各日について実行する。具体的には、調達期間が4日であり、現在の日付が4月1日である場合、安全在庫数算出部5は、図5に示すように、4月4日から4月7日までの第1の差分値の和(65+0+0+0=65)を4月4日における入荷遅れ累積差(第1の累積差)として算出する。そして評価期間が6日である場合には、安全在庫数算出部5は、図5に示すように、4月4日から4月9日までの各日について入荷遅れ累積差を算出する。また同様に安全在庫数算出部5は、図6に示すように、4月4日から4月7日までの第2の差分値の和(10+5+0−5=10)を4月4日における第2の累積差として算出する。そして評価期間が6日である場合には、安全在庫数算出部5は、図6に示すように、4月4日から4月9日までの各日について第2の累積差を算出する。これにより、ステップS21の処理は完了し、安全在庫数算出処理はステップS22の処理に進む。   In the process of step S21, the safety stock quantity calculation unit 5 reads the first and second difference values for each day in the evaluation period from the safety stock quantity storage DB 11, and the read first second difference value. Are added for each procurement period to calculate the first and second cumulative differences for each day in the evaluation period. Specifically, when the procurement period is 4 days and the current date is April 1, the safety stock quantity calculation unit 5 performs the operation from April 4 to April 7 as shown in FIG. The sum of the first difference values (65 + 0 + 0 + 0 = 65) is calculated as the arrival delay accumulated difference (first accumulated difference) on April 4. When the evaluation period is 6 days, the safety stock quantity calculation unit 5 calculates the arrival delay cumulative difference for each day from April 4 to April 9, as shown in FIG. Similarly, as shown in FIG. 6, the safety stock quantity calculation unit 5 calculates the sum (10 + 5 + 0−5 = 10) of the second difference value from April 4 to April 7 as the fourth difference. Calculated as a cumulative difference of 2. When the evaluation period is 6 days, the safety stock quantity calculation unit 5 calculates the second cumulative difference for each day from April 4 to April 9, as shown in FIG. Thereby, the process of step S21 is completed and the safety stock quantity calculation process proceeds to the process of step S22.

ステップS22の処理では、安全在庫数算出部5が、ステップS21の処理により算出された各日の第1及び第2の累積差の平均値を算出する。具体的には、図5に示す例で言えば、安全在庫数算出部5は、4月4日から4月9日までの各日の入荷遅れ累積差の平均値((65+0+5+15+15+15)/6=19.2)を算出する。また図6に示す例で言えば、安全在庫数算出部5は、4月4日から4月9日までの各日の第2の累積差の平均値((10+5−5−5−10−15)/6=−3.3)を算出する。この図6に示す例では、消費予定数が消費実績数よりも多くなる日(対象日付:4月7日,9日)が多いので、第2の累積差の平均値は負値となる。これにより、ステップS22の処理は完了し、安全在庫数算出処理はステップS23の処理に進む。   In the process of step S22, the safety stock quantity calculation unit 5 calculates the average value of the first and second cumulative differences calculated for each day by the process of step S21. Specifically, in the example shown in FIG. 5, the safe stock quantity calculation unit 5 calculates the average value of the arrival delay cumulative difference of each day from April 4 to April 9 ((65 + 0 + 5 + 15 + 15 + 15) / 6 = 19.2) is calculated. In the example shown in FIG. 6, the safety stock quantity calculation unit 5 calculates the average value of the second cumulative difference for each day from April 4 to April 9 ((10 + 5-5-5-10− 15) /6=-3.3) is calculated. In the example shown in FIG. 6, since there are many days (target dates: April 7th and 9th) when the planned consumption number is larger than the actual consumption number, the average value of the second cumulative difference is a negative value. Thereby, the process of step S22 is completed, and the safety stock quantity calculation process proceeds to the process of step S23.

ステップS23の処理では、安全在庫数算出部5が、ステップS21の処理により算出された各日の第1及び第2の累積差の標準偏差を算出する。具体的には、図5に示す例で言えば、安全在庫数算出部5は、4月4日から4月9日までの各日の入荷遅れ累積差の標準偏差(23.3)を算出する。また図6に示す例で言えば、安全在庫数算出部5は、4月4日から4月9日までの各日の第2の累積差の標準偏差(9.3)を算出する。これにより、ステップS23の処理は完了し、安全在庫数算出処理はステップS24の処理に進む。   In the process of step S23, the safe stock quantity calculation unit 5 calculates the standard deviation of the first and second cumulative differences calculated for each day by the process of step S21. Specifically, in the example shown in FIG. 5, the safety stock quantity calculation unit 5 calculates the standard deviation (23.3) of the arrival delay cumulative difference of each day from April 4th to April 9th. To do. In the example shown in FIG. 6, the safety stock quantity calculation unit 5 calculates the standard deviation (9.3) of the second cumulative difference for each day from April 4th to April 9th. Thereby, the process of step S23 is completed, and the safety stock quantity calculation process proceeds to the process of step S24.

ステップS24の処理では、安全在庫数算出部5が、ステップS22及びステップS23の処理により算出された第1及び第2の累積差の平均値及び標準偏差をそれぞれ以下の数式(1),(2)に代入することにより入荷遅れ及び消費変動に対する商品の安全在庫数を算出する。具体的には、数式(1),(2)中の安全係数αの値を1.65とすると、図5に示す例では、安全在庫数算出部5は数式(1)から入荷遅れを考慮した安全在庫数を57.6(=19.2+1.65×23.3)と算出する。また図6に示す例では、安全在庫数算出部5は数式(2)から消費変動を考慮した安全在庫数を12.0(=−3.3+1.65×9.3)と算出する。そして安全在庫数算出部5は、入荷遅れに対する商品の安全在庫数と消費変動に対する商品の安全在庫数の和69.6(=57.6+12.0)を商品の安全在庫数として出力する。以後ユーザが出力された商品の安全在庫数を考慮して4月1日の必要発注数を決定する。これにより、一連の安全在庫数算出処理は終了する。   In the process of step S24, the safety stock quantity calculation unit 5 calculates the average values and standard deviations of the first and second cumulative differences calculated by the processes of steps S22 and S23, respectively, by the following formulas (1) and (2 ) To calculate the safety stock quantity of goods against arrival delays and consumption fluctuations. Specifically, when the value of the safety coefficient α in the formulas (1) and (2) is 1.65, in the example shown in FIG. 5, the safety stock quantity calculation unit 5 considers the arrival delay from the formula (1). The calculated safety stock number is calculated as 57.6 (= 19.2 + 1.65 × 23.3). In the example shown in FIG. 6, the safety stock quantity calculation unit 5 calculates the safety stock quantity considering consumption fluctuation as 12.0 (= −3.3 + 1.65 × 9.3) from Equation (2). Then, the safety stock quantity calculation unit 5 outputs the sum 69.6 (= 57.6 + 12.0) of the safety stock quantity of the product with respect to the arrival delay and the safety stock quantity of the product with respect to the consumption fluctuation as the safety stock quantity of the product. Thereafter, the required order quantity on April 1 is determined in consideration of the safety stock quantity of the commodity output by the user. Thereby, a series of safety stock number calculation processing is completed.

入荷遅れに対する安全在庫数=MAX(第1の累積数(4日分)の平均値+安全係数α×第1の累積数(4日分)の標準偏差,0)…(1)
消費変動に対する安全在庫数=MAX(第2の累積数(4日分)の平均値+安全係数α×第2の累積数(4日分)の標準偏差,0)…(2)
以上の説明から明らかなように、本発明の実施形態となる安全在庫数算出システム1は、商品の入荷予定数に対する入荷実績数を日毎に記憶し、評価期間内の各日について入荷予定数と入荷実績数の差分値を第1の差分値として算出し、第1の差分値を調達日数分加算した値を第1の累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の第1の累積差の平均値と標準偏差値を算出し、算出された第1の累積差の平均値と標準偏差値を用いて入荷遅れに対する商品の安全在庫数を算出する。このような構成によれば、商品の入荷遅れを考慮して安全在庫数を算出できるので、安全在庫が多くなりすぎたりする等、安全在庫数が不適切になることを抑制できる。
Number of safety stock for delayed arrival = MAX (average value of first cumulative number (for 4 days) + safety factor α × standard deviation of first cumulative number (for 4 days), 0) (1)
Number of safety stocks against consumption fluctuation = MAX (average value of second cumulative number (for 4 days) + safety coefficient α x standard deviation of second cumulative number (for 4 days), 0) (2)
As is clear from the above description, the safety stock quantity calculation system 1 according to the embodiment of the present invention stores the number of actual arrivals with respect to the expected arrival quantity of goods every day, and the expected arrival quantity for each day within the evaluation period. The difference value of the actual number of arrivals is calculated as the first difference value, and the process of calculating the value obtained by adding the first difference value for the number of procurement days as the first cumulative difference is executed for each day in the evaluation period, and the evaluation The average value and standard deviation value of the first cumulative difference for each day within the period are calculated, and the safety stock quantity of the product against the arrival delay is calculated using the calculated average value and standard deviation value of the first cumulative difference. To do. According to such a configuration, the safety stock number can be calculated in consideration of the arrival delay of goods, so that it is possible to prevent the safety stock number from becoming inappropriate, for example, the safety stock becomes excessive.

また本発明の実施形態となる安全在庫数算出システム1は、商品の消費予定数に対する消費実績数を日毎に記憶し、評価期間内の各日について消費予定数と消費実績数の差分値を第2の差分値として算出し、第2の差分値を調達日数分加算した値を第2の累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の第2の累積差の平均値と標準偏差値を算出し、算出された第2の累積差の平均値と標準偏差値を用いて消費変動に対する商品の安全在庫数を算出する。このような構成によれば、消費予定数が消費実績数よりも多い場合には第2の累積差の平均値が負値になることによって安全在庫数が少なく算出されるので、消費予定数が消費実績数よりも多い場合に必要数以上の安全在庫数が算出されことを防止し、適切な安全在庫数を算出することができる。また消費実績数と消費予定数の差分値のばらつきは消費実績数のばらつきよりも小さいので、本発明の実施形態となる安全在庫数算出システム1によれば、消費実績数のばらつきを用いて安全在庫数を算出する手法と比較して、安全在庫数を適切に算出することができる。   The safety stock quantity calculation system 1 according to the embodiment of the present invention stores the number of actual consumptions with respect to the planned consumption quantity of the product for each day, and calculates the difference value between the scheduled consumption quantity and the actual consumption quantity for each day in the evaluation period. 2 for each day in the evaluation period, and the second cumulative value is calculated for each day in the evaluation period. An average value and a standard deviation value of the cumulative difference are calculated, and a safety stock quantity of the product against consumption fluctuation is calculated using the calculated second average value and standard deviation value of the cumulative difference. According to such a configuration, when the planned consumption number is larger than the actual consumption number, the average value of the second cumulative difference becomes a negative value so that the safety stock number is calculated to be small. When the number is greater than the actual consumption number, it is possible to prevent the safety stock number from being calculated more than necessary, and to calculate the appropriate safety stock number. In addition, since the variation in the difference value between the actual consumption number and the planned consumption number is smaller than the variation in the actual consumption number, the safety stock number calculation system 1 according to the embodiment of the present invention uses the variation in the actual consumption number for safety. Compared to the method of calculating the stock quantity, the safe stock quantity can be appropriately calculated.

上記実施形態において、図7に示すように、消費予定数が消費実績数より多い日付(図7に示す例では対象日付が4月7日,9日,11日)については、消費実績数と消費予定数の差分値をゼロとしてもよい。このような構成によれば、消費実績数が消費予定数より多い場合の差分値だけで安全在庫数を算出することになるので、差分値の分布が偏りを持つ場合であっても安全在庫数を正しく算出することができる。また上記実施形態において、第2の累積差の平均値及び標準偏差値に代わりに、図8に示すように、消費実績数と消費予定数の差分値の平均値及び標準偏差を用いて安全在庫数を算出するようにしてもよい。このような構成によれば、蓄積されたデータの数が少ない場合であっても適切な安全在庫数を算出することができる。   In the above embodiment, as shown in FIG. 7, for the dates whose planned consumption number is greater than the actual consumption number (in the example shown in FIG. 7, the target dates are April 7, 9, and 11), The difference value of the planned consumption number may be zero. According to such a configuration, since the safety stock number is calculated only by the difference value when the actual consumption number is larger than the planned consumption number, even if the difference value distribution is uneven, Can be calculated correctly. In the above embodiment, instead of the average value and standard deviation value of the second cumulative difference, as shown in FIG. 8, the safety stock is calculated using the average value and standard deviation of the difference value between the actual consumption number and the planned consumption number. The number may be calculated. According to such a configuration, an appropriate number of safety stocks can be calculated even when the number of accumulated data is small.

以上、本発明者らによってなされた発明を適用した実施の形態について説明したが、この実施の形態による本発明の開示の一部をなす論述及び図面により本発明は限定されることはない。すなわち、上記実施の形態に基づいて当業者等によりなされる他の実施の形態、実施例及び運用技術等は全て本発明の範疇に含まれることは勿論であることを付け加えておく。   As mentioned above, although the embodiment to which the invention made by the present inventors was applied has been described, the present invention is not limited by the description and the drawings that form part of the disclosure of the present invention according to this embodiment. That is, it should be added that other embodiments, examples, operation techniques, and the like made by those skilled in the art based on the above embodiments are all included in the scope of the present invention.

本発明の実施形態となる安全在庫数算出システムの構成を示すブロック図である。It is a block diagram which shows the structure of the safe stock quantity calculation system used as embodiment of this invention. 本発明の実施形態となる差分値算出処理(1)の流れを示すフローチャート図である。It is a flowchart figure which shows the flow of the difference value calculation process (1) used as embodiment of this invention. 本発明の実施形態となる差分値算出処理(2)の流れを示すフローチャート図である。It is a flowchart figure which shows the flow of the difference value calculation process (2) used as embodiment of this invention. 本発明の実施形態となる安全在庫数算出処理の流れを示すフローチャート図である。It is a flowchart figure which shows the flow of the safe stock quantity calculation process used as embodiment of this invention. 本発明に係る入荷遅れに対する安全在庫数算出処理の一例を説明するための図である。It is a figure for demonstrating an example of the safety stock number calculation process with respect to the arrival delay based on this invention. 本発明に係る消費変動に対する安全在庫数算出処理の一例を説明するための図である。It is a figure for demonstrating an example of the safety stock number calculation process with respect to the consumption fluctuation | variation which concerns on this invention. 本発明に係る安全在庫数算出処理の応用例を説明するための図である。It is a figure for demonstrating the application example of the safety stock number calculation process which concerns on this invention. 本発明に係る安全在庫数算出処理の応用例を説明するための図である。It is a figure for demonstrating the application example of the safety stock number calculation process which concerns on this invention.

符号の説明Explanation of symbols

1:安全在庫数算出システム
2:データベース
3:入荷予定履歴格納部
4:消費予定履歴格納部
5:安全在庫数算出部
6:調達期間マスタDB
7:入荷予定履歴DB
8:入荷実績履歴DB
9:消費予定履歴DB
10:消費実績履歴DB
11:安全在庫数格納DB
1: Safety stock number calculation system 2: Database 3: Arrival schedule history storage unit 4: Consumption schedule history storage unit 5: Safety stock number calculation unit 6: Procurement period master DB
7: Arrival schedule history DB
8: Arrival history DB
9: Consumption schedule history DB
10: Consumption result history DB
11: Safety stock quantity storage DB

Claims (4)

商品の入荷予定数に対する入荷実績数を日毎に記憶する入荷実績数記憶部と、
前記入荷実績数記憶部内に記憶されている情報を参照して、評価期間内の各日について入荷予定数と入荷実績数の差分値を第1の差分値として算出し、第1の差分値を調達日数分加算した値を第1の累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の第1の累積差の平均値と標準偏差値を算出し、算出された第1の累積差の平均値と標準偏差値を用いて入荷遅れに対する商品の安全在庫数を算出する安全在庫数算出部と
を備えることを特徴とする安全在庫数算出システム。
An actual arrival number storage unit for storing the actual arrival number for the expected arrival number of products every day;
With reference to the information stored in the arrival record number storage unit, the difference value between the scheduled arrival number and the arrival record number is calculated as the first difference value for each day in the evaluation period, and the first difference value is calculated. The process of calculating the value added for the number of procurement days as the first cumulative difference is executed for each day in the evaluation period, and the average value and the standard deviation value of the first cumulative difference in each day in the evaluation period are calculated. A safety stock quantity calculation system, comprising: a safety stock quantity calculation unit that calculates a safety stock quantity of a product against arrival delay using the calculated first cumulative difference average value and standard deviation value.
請求項1に記載の安全在庫数算出システムにおいて、
調達期間だけ先の日付の商品の消費予定数を日毎に記憶する消費予定数記憶部と、
前記商品の消費実績数を日毎に記憶する消費実績数記憶部とを備え、
前記安全在庫数算出部は、前記消費予定数記憶部内及び前記消費実績数記憶部内に記憶されている情報を参照して、評価期間内の各日について消費実績数と消費予定数の差分値を第2の差分値として算出し、第2の差分値を調達日数分加算した値を第2の累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の第2の累積差の平均値と標準偏差値を算出し、算出された第2の累積差の平均値と標準偏差値を用いて消費変動に対する商品の安全在庫数を算出し、入荷遅れに対する商品の安全在庫数と消費変動に対する商品の安全在庫数の和を商品の安全在庫数として算出すること
を特徴とする安全在庫数算出システム。
In the safety stock number calculation system according to claim 1,
The planned consumption number storage unit that stores the planned consumption number of products with a date earlier than the procurement period every day,
A consumption record number storage unit for storing the consumption record number of the product every day,
The safety stock quantity calculation unit refers to information stored in the planned consumption number storage unit and the actual consumption number storage unit, and calculates a difference value between the actual consumption number and the planned consumption number for each day in the evaluation period. A process of calculating as a second difference value and calculating a value obtained by adding the second difference value for the number of procurement days as a second cumulative difference is performed for each day in the evaluation period, 2. Calculate the average value and standard deviation value of the cumulative difference of 2, calculate the safety stock quantity of the product against consumption fluctuations using the calculated average value and standard deviation value of the second cumulative difference, A safety stock quantity calculation system that calculates the sum of the safety stock quantity and the product safety stock quantity against consumption fluctuations as the product safety stock quantity.
請求項2に記載の安全在庫数算出システムにおいて、
前記安全在庫数算出部は、消費予定数が消費実績数より大きい日についてはその日の第2の差分値をゼロとすることを特徴とする安全在庫数算出システム。
In the safety stock number calculation system according to claim 2,
The safety stock quantity calculation unit sets the second difference value of the day to zero for a day when the planned consumption quantity is greater than the actual consumption quantity, and the safety stock quantity calculation system is characterized in that it is zero.
商品の入荷予定数に対する入荷実績数を日毎に入荷実績数記憶部内に記憶する処理と、
前記入荷実績数記憶部内に記憶されている情報を参照して、評価期間内の各日について入荷実績数と入荷予定数の差分値を算出し、差分値を調達日数分加算した値を累積差として算出する処理を評価期間内の各日について実行し、評価期間内における各日の累積差の平均値と標準偏差値を算出し、算出された累積差の平均値と標準偏差値を用いて入荷遅れに対する商品の安全在庫数を算出する処理と
をコンピュータに実行させることを特徴とする安全在庫数算出プログラム。
A process of storing the actual number of arrivals for the expected number of arrivals of goods in the arrival history number storage unit every day,
Referring to the information stored in the actual arrival number storage unit, the difference value between the actual arrival number and the expected arrival number is calculated for each day in the evaluation period, and the difference value is added by the number of procurement days. Is executed for each day in the evaluation period, the average value and the standard deviation value of the cumulative difference for each day in the evaluation period are calculated, and the calculated average value and standard deviation value of the cumulative difference are used. A safety stock quantity calculation program that causes a computer to execute a process of calculating a safety stock quantity of a product in response to arrival delay.
JP2008016224A 2008-01-28 2008-01-28 Safety stock quantity calculation system and safety stock quantity calculation program Ceased JP2009173435A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008016224A JP2009173435A (en) 2008-01-28 2008-01-28 Safety stock quantity calculation system and safety stock quantity calculation program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008016224A JP2009173435A (en) 2008-01-28 2008-01-28 Safety stock quantity calculation system and safety stock quantity calculation program

Publications (1)

Publication Number Publication Date
JP2009173435A true JP2009173435A (en) 2009-08-06

Family

ID=41028981

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008016224A Ceased JP2009173435A (en) 2008-01-28 2008-01-28 Safety stock quantity calculation system and safety stock quantity calculation program

Country Status (1)

Country Link
JP (1) JP2009173435A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020197838A (en) * 2019-05-31 2020-12-10 キヤノンマーケティングジャパン株式会社 Information processor, control method and program

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992018939A1 (en) * 1991-04-19 1992-10-29 Meiji Milk Products Co., Ltd. Sale quantity characteristics classification system and supplementary ordering system
JPH0962941A (en) * 1995-08-23 1997-03-07 Hitachi Ltd Safety stock amount calculation method
JP2002012308A (en) * 2000-06-30 2002-01-15 Hitachi Ltd Inventory management method
JP2004070612A (en) * 2002-08-06 2004-03-04 Hitachi Ltd Inventory control system, inventory control method, charging method in inventory control system, inventory control program, and storage medium therefor
JP2004078487A (en) * 2002-08-15 2004-03-11 Hitachi Ltd Distribution management method and information processing device
JP2004118429A (en) * 2002-09-25 2004-04-15 Matsushita Electric Works Ltd Reasonable inventory quantity calculation method and its system
JP2004115190A (en) * 2002-09-26 2004-04-15 Mitsubishi Motors Corp Inventory management method
JP2004359415A (en) * 2003-06-05 2004-12-24 Canon Inc Safety stock calculating device, its calculation method, program for operating its calculation method, and storage medium
JP2005306543A (en) * 2004-04-20 2005-11-04 Canon System Solutions Inc Stock management program, stock management device and its method
JP2006171877A (en) * 2004-12-13 2006-06-29 Mitsubishi Materials Corp Production management system and production management method
JP2007018216A (en) * 2005-07-07 2007-01-25 Nec Corp Reasonable inventory quantity calculation system and reasonable inventory quantity calculation method

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992018939A1 (en) * 1991-04-19 1992-10-29 Meiji Milk Products Co., Ltd. Sale quantity characteristics classification system and supplementary ordering system
JPH0962941A (en) * 1995-08-23 1997-03-07 Hitachi Ltd Safety stock amount calculation method
JP2002012308A (en) * 2000-06-30 2002-01-15 Hitachi Ltd Inventory management method
JP2004070612A (en) * 2002-08-06 2004-03-04 Hitachi Ltd Inventory control system, inventory control method, charging method in inventory control system, inventory control program, and storage medium therefor
JP2004078487A (en) * 2002-08-15 2004-03-11 Hitachi Ltd Distribution management method and information processing device
JP2004118429A (en) * 2002-09-25 2004-04-15 Matsushita Electric Works Ltd Reasonable inventory quantity calculation method and its system
JP2004115190A (en) * 2002-09-26 2004-04-15 Mitsubishi Motors Corp Inventory management method
JP2004359415A (en) * 2003-06-05 2004-12-24 Canon Inc Safety stock calculating device, its calculation method, program for operating its calculation method, and storage medium
JP2005306543A (en) * 2004-04-20 2005-11-04 Canon System Solutions Inc Stock management program, stock management device and its method
JP2006171877A (en) * 2004-12-13 2006-06-29 Mitsubishi Materials Corp Production management system and production management method
JP2007018216A (en) * 2005-07-07 2007-01-25 Nec Corp Reasonable inventory quantity calculation system and reasonable inventory quantity calculation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020197838A (en) * 2019-05-31 2020-12-10 キヤノンマーケティングジャパン株式会社 Information processor, control method and program

Similar Documents

Publication Publication Date Title
WO2004022463A1 (en) Safe stock amount calculation method, safe stock amount calculation device, order making moment calculation method, order making moment calculation device, and order making amount calculation method
JP2009187151A (en) Inventory management system and order quantity calculation program
JP6766024B2 (en) Order management system, order management device and order management program
Valliathal et al. Optimal replenishment policies of an EOQ model for non-instantaneous Weibull deteriorating items with ramp-type of demand under shortages
US20080154414A1 (en) Lead time and validity based supply determination
Hu et al. (s, S) inventory systems with correlated demands
JP2009173435A (en) Safety stock quantity calculation system and safety stock quantity calculation program
WO2018008303A1 (en) Opportunity loss calculation system, opportunity loss calculation method, and opportunity loss calculation program
KR102061853B1 (en) Demand forecasting method, computer program implementing the same and demand forecasting system configured to perform the same
CN108681838B (en) Scheduling plan determining method and device
Jaggi et al. Inventory and pricing strategies for deteriorating items with limited capacity and time-proportional backlogging rate
JP5123592B2 (en) Safety stock quantity calculation system and safety stock quantity calculation program
JP4996107B2 (en) Order priority calculation device based on management index, order priority calculation method based on management index, order priority calculation program based on management index
Boute et al. Bullwhip in a multi-product production setting
JP2002007671A (en) Demand prediction device, method, computer program, and computer-readable recording medium
JP2009126621A (en) Appropriate inventory amount determination system and appropriate inventory amount determination method
Suhandi et al. ONE-TIME ORDER INVENTORY MODEL FOR DETERIORATING AND SHORT MARKET LIFE ITEMS WITH TRAPEZOIDAL TYPE DEMAND RATE.
JP2003316862A (en) Inventory planning method
JP2003263213A (en) Production management system and production management method
JP2010181963A (en) Demand prediction device, demand prediction method and program
Sarker et al. Improving service rate for a tree-type three-echelon supply chain system with backorders at retailer's level
JP2000293582A (en) Production management device, production management system, production planning method, and storage medium
CN117333103B (en) Article dispatching method, device, electronic device and storage medium
Xu et al. Decision analysis for supplier in two-echelon supply chain with discrete demand via dynamic game
JP5984686B2 (en) Information processing apparatus and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20101118

Free format text: JAPANESE INTERMEDIATE CODE: A621

A711 Notification of change in applicant

Effective date: 20120111

Free format text: JAPANESE INTERMEDIATE CODE: A712

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121126

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130108

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130311

A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20131001

Free format text: JAPANESE INTERMEDIATE CODE: A01

A045 Written measure of dismissal of application

Effective date: 20140225

Free format text: JAPANESE INTERMEDIATE CODE: A045