JP2005309718A JP2004125017A JP2004125017A JP2005309718A JP 2005309718 A JP2005309718 A JP 2005309718A JP 2004125017 A JP2004125017 A JP 2004125017A JP 2004125017 A JP2004125017 A JP 2004125017A JP 2005309718 A JP2005309718 A JP 2005309718A
Authority
JP
Japan
Prior art keywords
information
schedule
construction
ordering
building material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004125017A
Other languages
Japanese (ja)
Inventor
Masahiro Yoshida
正宏 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ibiken Co Ltd
Original Assignee
Ibiken Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ibiken Co Ltd filed Critical Ibiken Co Ltd
Priority to JP2004125017A priority Critical patent/JP2005309718A/en
Publication of JP2005309718A publication Critical patent/JP2005309718A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a building material ordering and order receipt support system capable of reducing a burden of an orderer by facilitating the setting of delivery dates of a plurality of building materials. <P>SOLUTION: When work information including the using place of building materials and the construction type thereof is input with commodity information from an ordering terminal at the time of ordering, a server 3 stores the commodity information and the work information in association with each other. When a time schedule corresponding to the work information is input from the ordering terminal at the time of time schedule management, the server stores the time schedule in conformation to the work information. When a retrieval with a designated delivery date is instructed at the time of delivering the building materials, on the basis of the time schedule matched to the delivery date, the server extracts work information corresponding to this time schedule from a time schedule information storage means 16, and also extracts all pieces of commodity information relevant to the extracted work information from an ordering information storage means 15. The server further forms a delivery list of building materials on the basis of the extracted commodity information. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、建材の受発注支援システム及びそのプログラムに関するものであり、特に、インターネット等の通信ネットワークを介して、複数の種類の建材を受発注するとともに、工事の日程を管理し指定された納入日に納品させることを可能にする建材の受発注支援システム、及びそのシステムにおいて実行されるプログラムに関するものである。   The present invention relates to a building material ordering support system and program thereof, and in particular, receives and orders a plurality of types of building materials via a communication network such as the Internet, and manages and designates a construction schedule. The present invention relates to a building material ordering support system that enables delivery on a daily basis and a program executed in the system.

見積書を作成する作業は、経験や熟練を必要とするとともに、担当者の負担が大きく、特に、住宅を建設する場合など多種類の建材を取り扱う際には、見積書を作成するのに極めて多くの工数を要していた。また、出先等で商談が行われた際に、カタログや価格表がない場合には、その場で見積書を作成することが難しく、また譬え見積書を作成することができたとしても、作成するまでの比較的長い時間、施主を待たせることになり、円滑に商談を進めることができなくなる恐れがあった。   The work of creating an estimate requires experience and skill, and the burden on the person in charge is large. Especially when handling various types of building materials, such as when constructing a house, it is extremely difficult to prepare an estimate. It took a lot of man-hours. Also, when there is no catalog or price list when a business negotiation is held at a destination, etc., it is difficult to create a quote on the spot, and even if a custom quote can be created, it will be created As a result, the owner was kept waiting for a relatively long time until the transaction was completed, and there was a risk that the negotiation could not proceed smoothly.

そこで、最近では、インターネット等の通信ネットワークに接続されたサーバーを用いて見積書を作成するシステムが提案されている。具体的には、サーバーの記憶手段に、商品の名称、品番、及び価格等の商品情報を記憶するものであり、通信ネットワークを介して端末装置から希望購入情報(希望する商品の情報)が入力されると、これらの希望購入情報と記憶手段に記憶された商品情報とに基づいて見積書を作成し、その見積書を端末装置に送信するものである。そして、商品の購入希望者は、端末装置を介して見積書を受取り、価格等に問題がなければ、その見積書に従って発注することになる。   Therefore, recently, a system for creating an estimate using a server connected to a communication network such as the Internet has been proposed. Specifically, product information such as product name, product number, and price is stored in the storage means of the server, and desired purchase information (information on the desired product) is input from the terminal device via the communication network. Then, an estimate is created based on the desired purchase information and the product information stored in the storage means, and the estimate is transmitted to the terminal device. Then, the person who wants to purchase the product receives the estimate via the terminal device, and if there is no problem with the price or the like, places an order according to the estimate.

ところで、住宅建設では、設計図面等で施主の確認を取ってから施工完了までに数ヶ月の日数を要するが、現場では施工業者を遊ばせることなく商品や材料を納品させることが極めて大切である。なぜなら、工務店では、住宅資材の価格による損失よりも、施工業者の手待ち時間による方が金銭的な損失が大きくなるためである。例えば、工務店が他のメーカーから床材を10%安く購入できても、床材の納入日が一日遅れたら壁下工事も天井工事も全て遅れ、施工業者の手待ち時間により多大な損失を被ることになる。   By the way, in housing construction, it takes several months to complete the construction after confirming the owner with a design drawing etc., but it is extremely important to deliver goods and materials without letting the contractor play at the site. . This is because, in the construction shop, the monetary loss is greater due to the waiting time of the contractor than the loss due to the price of the housing material. For example, even if a construction company can purchase flooring from other manufacturers at a 10% discount, if the delivery date of the flooring is delayed by one day, both the under-wall construction and the ceiling construction will be delayed, resulting in a significant loss due to the waiting time of the contractor Will suffer.

そこで、建築現場に入る施工業者のスケジュールに合わせて納品できるようにした納期管理システムが提案されている。これは、販売店等が管理するサーバーと、工務店等が利用可能な発注用端末とを通信ネットワークを介して接続し、発注用端末において商品の希望納期を入力させるようにしたものである。これによれば、販売店はサーバーによって希望納期を把握することが可能になり、建築現場における施工スケジュールに合わせて必要建材を納品できるようになる。   Therefore, a delivery date management system has been proposed that enables delivery according to the schedule of the construction contractor entering the construction site. In this system, a server managed by a dealer or the like and an ordering terminal that can be used by a construction company or the like are connected via a communication network, and the desired delivery date of the product is input at the ordering terminal. According to this, the store can grasp the desired delivery date by the server, and can deliver necessary building materials according to the construction schedule at the construction site.

以上の従来技術は、当業者において当然として行われているものであり、出願人は、この従来技術が記載された文献を知見していない。   The above prior art is naturally performed by those skilled in the art, and the applicant is not aware of a document describing the prior art.

しかし、上記の納期管理システムによれば、商品毎に希望納期を設定しなければならないため、希望納期の入力作業における工務店等の負担が大きくなっていた。つまり、最小単位である個々の商品毎に希望納期を入力しなければならないため、必要以上に細かな入力作業が強いられるようになり、作業に不満を抱く恐れがあった。なお、納期を設定するにあたり見積情報を利用することも考えられるが、見積情報は工事の進捗状況と関連しないことから、夫々の商品の希望納期を設定する際には互いの整合性を取りながら入力する必要があった。   However, according to the delivery date management system described above, a desired delivery date must be set for each product, which increases the burden on the construction shop and the like in the input operation of the desired delivery date. In other words, since the desired delivery date must be entered for each individual product, which is the smallest unit, the input work becomes more detailed than necessary, and there is a risk of dissatisfaction with the work. Although it is conceivable to use estimated information in setting the delivery date, the estimated information is not related to the progress of the construction. Therefore, while setting the desired delivery date for each product, while maintaining consistency with each other There was a need to enter.

ところで、住宅工事においては、一般に時間軸及び空間軸によって管理されている。すなわち、時間軸上に職種別工事(例えば配管、左官、及び大工による工事)を並べるとともに、工事部位毎つまり住宅の各部屋毎に職人がぶつからないように、各職人及び建材を手配するようにしている。ところが、従来の納期管理システムによれば、商品毎に希望納期を設定することから、全ての建材をジャストタイムで納品することは困難であった。例えば、外観全体のデザインにリズム感を出すために、一階の部屋で使用される窓枠と同じ品番のものを、台所、洗面所、二階の部屋、または廊下等で使用する場合があるが、このような場合、窓枠を取付ける時期が部屋毎に異なっているにも拘わらず、同じ商品であるという理由で、全て同日に納品されていた。この結果、建材を建築現場等で保管しなければならず、特に、これらの建材を設置するためのスペースが確保できない現場においては大きな問題となっていた。   By the way, in housing construction, the time axis and the space axis are generally used. In other words, work by job type (for example, work by pipes, plasterers, and carpenters) is arranged on the time axis, and craftsmen and building materials are arranged so that craftsmen do not collide with each construction site, that is, each room of the house. ing. However, according to the conventional delivery date management system, since a desired delivery date is set for each product, it is difficult to deliver all building materials in a just time. For example, in order to give a sense of rhythm to the overall appearance design, the same part number as the window frame used in the first floor room may be used in the kitchen, washroom, second floor room, hallway, etc. In such a case, all the products were delivered on the same day because the products were the same, even though the window frame installation time was different for each room. As a result, building materials have to be stored at construction sites and the like, and particularly at sites where these building materials cannot be secured.

そこで、本発明は、上記の実状に鑑み、夫々の建材の納入日を容易に設定でき、発注者の負担を軽減することを可能にする建材の受発注支援システム、及びそのプログラムの提供を課題とするものである。   Therefore, in view of the above situation, the present invention has an object to provide a building material ordering support system and a program thereof that can easily set the delivery date of each building material and reduce the burden on the orderer. It is what.

本発明にかかる建材の受発注支援システムは、「複数の種類の建材を発注する発注用端末とサーバーとを通信ネットワークを介して接続した建材の受発注支援システムであって、前記サーバーは、発注の際に、前記発注用端末から、建材の品番及び数量を含む商品情報と、その建材の使用場所及び施工種別を含む工事情報とが入力されると、前記商品情報及び前記工事情報を互いに関連付けて記憶する発注情報記憶手段と、日程管理の際に、前記発注用端末から、前記工事情報に対応する日程が入力されると、該日程及び前記工事情報を互いに関連付けて記憶する日程情報記憶手段と、建材を納品する際に、納入日を指定して検索が指示されると、該納入日に一致する前記日程を基に、該日程に対応する前記工事情報を前記日程情報記憶手段から抽出するとともに、抽出された前記工事情報に関連する全ての前記商品情報を前記発注情報記憶手段から抽出する情報抽出手段と、該情報抽出手段によって抽出された前記商品情報を基に、建材の納品リストを作成するリスト作成手段とを具備する」ものである。   The building material ordering support system according to the present invention is a building material ordering support system in which an ordering terminal for ordering a plurality of types of building materials and a server are connected via a communication network, wherein the server When the product information including the product number and quantity of the building material and the construction information including the use place and construction type of the building material are input from the ordering terminal, the product information and the construction information are associated with each other. And the schedule information storage means for storing the schedule and the construction information in association with each other when the schedule corresponding to the construction information is input from the ordering terminal during schedule management. And when delivering a building material, when a search is instructed by specifying a delivery date, the construction information corresponding to the schedule is stored in the schedule information storage means based on the schedule that matches the delivery date. Information extracting means for extracting all the product information related to the extracted construction information from the order information storage means, and based on the product information extracted by the information extracting means, And a list creation means for creating a delivery list ”.

ここで、「使用場所」は、例えば、物件名(例えば個別邸の識別番号)、部屋名(例えば部屋の種類を示す識別番号)、及び工事対象部位(例えば壁,床,天井等を区別する識別番号)の組合わせから表現することが可能である。また「施工種別」は、大工、左官、配管、及び電気工事といった職種の区分、及び施工順序を示す情報から構成することができる。   Here, “use place” distinguishes, for example, a property name (for example, an identification number of an individual residence), a room name (for example, an identification number indicating the type of a room), and a construction target part (for example, a wall, a floor, a ceiling, etc.) It can be expressed from a combination of (identification numbers). Further, the “construction type” can be configured from information indicating the classification of job types such as carpenter, plasterer, piping, and electrical work, and the construction order.

本発明によれば、サーバーは、発注の際に、発注用端末から、建材の品番及び数量を含む商品情報と、その建材の使用場所及び施工種別を含む工事情報とが入力されると、これらの商品情報及び工事情報を互いに関連付けて記憶する。すなわち、注文する建材の商品情報に加え、夫々の商品の使用場所及び工事の情報を入力させることにより取得する。   According to the present invention, when placing an order, the server inputs product information including the product number and quantity of the building material and construction information including the use location and construction type of the building material from the ordering terminal. Are stored in association with each other. That is, in addition to the product information of the building material to be ordered, the information is acquired by inputting the use location and construction information of each product.

また、日程管理の際に、発注用端末から工事情報に対応する日程が入力されると、サーバーは、その日程と、発注時に入力された工事情報とを互いに関連付けて記憶する。つまり、建材の種類毎に納入日を入力させるのではなく、工事情報に対応させて日程を入力させる。これによれば、ドア枠と壁材とのように、商品の種別が互いに異なっていても、夫々の建材における使用場所及び工事情報が同一の場合(すなわち同日施工が可能な場合)には、同日の日程として設定される。   Further, when a schedule corresponding to the construction information is input from the ordering terminal during schedule management, the server stores the schedule and the construction information input at the time of ordering in association with each other. That is, the delivery date is not input for each type of building material, but the schedule is input according to the construction information. According to this, even if the types of products are different from each other, such as door frames and wall materials, if the location of use and construction information in each building material are the same (that is, the same day construction is possible), It is set as the same day schedule.

一方、建材を納品する際に、納入日を指定して検索が指示されると、サーバーは、その納入日と、日程管理の際に記憶された日程とを照合し、一致する日程を認識するとともに、その日程に対応付けられている工事情報を抽出する。また、抽出された工事情報に関連する全ての商品情報を、発注の際に記憶した商品情報及び工事情報の関連付けを基に抽出する。そして、抽出された商品情報を基に建材の納品リストを作成する。これにより、納入日毎の納品リストが作成され、納品リストを基に建材を手配することが可能になる。   On the other hand, when delivering a building material, when a search is instructed by specifying a delivery date, the server compares the delivery date with the schedule stored during schedule management, and recognizes a matching schedule. At the same time, the construction information associated with the schedule is extracted. Further, all the product information related to the extracted construction information is extracted based on the association between the product information stored at the time of ordering and the construction information. Then, a delivery list of building materials is created based on the extracted product information. Thereby, a delivery list for each delivery date is created, and building materials can be arranged based on the delivery list.

ところで、本発明の建材の受発注支援システムにおいて、「前記施工種別には職種の区分が含まれ、前記発注情報記憶手段に記憶された前記商品情報及び前記工事情報を基に、前記職種毎の見積書を作成する見積書作成手段をさらに備える」構成とすることができる。   By the way, in the ordering support system for building materials according to the present invention, “the construction type includes a category of job type, and based on the product information and the construction information stored in the order information storage unit, for each job type. It may be configured to further include an estimate creation means for creating an estimate.

これによれば、発注情報記憶手段に記憶された情報を基に、職種毎の見積書が作成される。つまり、発注情報記憶手段には、施工種別として職種の区分が記憶されているため、職種毎の見積書を作成することが可能になる。換言すれば、発注の際に入力された工事情報は、建材の納期を設定する場合だけでなく、個別の見積書を作成する場合にも利用される。すなわち、見積書の作成から建材の納品に至る一連の作業において、工事情報が有効に利用される。   According to this, an estimate for each job type is created based on the information stored in the order information storage means. In other words, since the job classification is stored as the construction type in the order information storage means, it is possible to create an estimate for each job type. In other words, the construction information input at the time of placing an order is used not only when setting the delivery date of building materials but also when creating an individual estimate. In other words, the construction information is effectively used in a series of operations from creation of an estimate to delivery of building materials.

ところで、上記の発明は、サーバーにおいて使用されるプログラムとして実現することもできる。すなわち、「複数の商品を発注する発注用端末とサーバーとを通信ネットワークを介して接続した建材の受発注支援システムにおいて使用される受発注支援プログラムであって、発注の際に、前記発注用端末から、建材の品番及び数量を含む商品情報と、その建材の使用場所及び施工種別を含む工事情報とが入力されると、前記商品情報及び前記工事情報を互いに関連付けて記憶する発注情報記憶手段、日程管理の際に、前記発注用端末から、前記工事情報に対応する日程が入力されると、該日程及び前記工事情報を互いに関連付けて記憶する日程情報記憶手段、建材を納品する際に、納入日を指定して検索が指示されると、該納入日に一致する前記日程を基に、該日程に対応する前記工事情報を前記日程情報記憶手段から抽出するとともに、抽出された前記工事情報に関連する全ての前記商品情報を前記発注情報記憶手段から抽出する情報抽出手段、及び、該情報抽出手段によって抽出された前記商品情報を基に、建材の納品リストを作成するリスト作成手段として、前記サーバーを機能させる」ものである。   The above invention can also be realized as a program used in a server. That is, “an ordering support program used in an ordering support system for building materials in which an ordering terminal for ordering a plurality of products and a server are connected via a communication network, and the ordering terminal is used when placing an order. Order information storage means for storing the product information and the construction information in association with each other when the product information including the product number and quantity of the building material and the construction information including the use place and construction type of the building material are input. When a schedule corresponding to the construction information is input from the ordering terminal during schedule management, a schedule information storage means for storing the schedule and the construction information in association with each other, delivered when delivering building materials When a search is instructed by designating a date, the construction information corresponding to the schedule is extracted from the schedule information storage means based on the schedule that matches the delivery date. An information extraction means for extracting all the product information related to the extracted construction information from the order information storage means, and a delivery list of building materials based on the product information extracted by the information extraction means The server is made to function as a list creation means to perform ".

このプログラムによれば、サーバーにおいて実行させることにより、発注の際には商品情報及び工事情報を互いに関連付けて記憶し、日程管理の際には発注時に入力された工事情報及び日程を互いに対応付けて記憶することが可能になる。また、建材を納品する際には納入日を指定して検索が指示されると、納入日毎の納品リストを作成することが可能になる。なお、具体的な処理については、請求項1の作用と同様であるため、ここでは詳細な説明を省略する。   According to this program, by executing on the server, product information and construction information are stored in association with each other at the time of ordering, and construction information and schedule input at the time of ordering are associated with each other at the time of schedule management. It becomes possible to memorize. In addition, when delivering a building material, if a search is instructed by specifying a delivery date, a delivery list for each delivery date can be created. The specific process is the same as that of the first aspect, and a detailed description thereof is omitted here.

このように、本発明の建材の受発注支援システムは、発注時に拾い出された建材の使用場所及び施工種別を、発注時に特定しておくことにより、工事の日程管理にその発注情報を役立てることが可能になる。このため、複数の建材の納入日を容易に設定することが可能となり、発注者の負担を軽減することができる。また、工事情報に対応して日程を設定することから、同じ種類の建材であっても異なる場所に配置する場合には、夫々の場所の施工状況に合わせた納入日に納品することが可能になり、現場における利便性を大きく向上させることができる。   In this way, the building material ordering support system of the present invention makes use of the ordering information for construction schedule management by specifying the use place and construction type of the building material picked up at the time of ordering at the time of ordering. Is possible. For this reason, it becomes possible to set the delivery date of a some building material easily, and can reduce the burden of an orderer. In addition, since the schedule is set according to the construction information, even if the same type of building material is placed in different locations, it can be delivered on the delivery date according to the construction status of each location. Therefore, convenience at the site can be greatly improved.

以下、本発明の一実施形態である建材の受発注支援システムについて、図1乃至図6に基づき説明する。図1は受発注支援システム全体の概略構成を示す説明図であり、図2及び図3は受発注支援システムにおけるサーバー及び発注用端末の機能的構成を示すブロック図である。図4はサーバーに記憶される情報の構成を示す説明図であり、図5は表示画面の一例を示す説明図であり、図6はサーバーにおける処理の流れを示すフローチャートである。   Hereinafter, a building material ordering support system according to an embodiment of the present invention will be described with reference to FIGS. FIG. 1 is an explanatory diagram illustrating a schematic configuration of the entire ordering support system. FIGS. 2 and 3 are block diagrams illustrating functional configurations of a server and an ordering terminal in the ordering support system. 4 is an explanatory diagram showing a configuration of information stored in the server, FIG. 5 is an explanatory diagram showing an example of a display screen, and FIG. 6 is a flowchart showing a flow of processing in the server.

本例の受発注支援システム1は、図1に示すように、メーカー2によって管理されるサーバー3、受注用端末4、及びプリンタ5と、発注者6が利用可能な発注用端末7とを、ネットワーク8を介して接続したものであり、例えば住宅を建築したり改築したりする際に用いられる。なお、ネットワーク8は、電話回線網、及びISP(Internet Service Provider)を含むインターネット等の広域通信ネットワークから構築されている。   As shown in FIG. 1, the ordering support system 1 of this example includes a server 3, an order receiving terminal 4 and a printer 5 managed by a manufacturer 2, and an ordering terminal 7 that can be used by an orderer 6. It is connected via the network 8 and is used, for example, when a house is constructed or renovated. The network 8 is constructed from a wide-area communication network such as the Internet including a telephone line network and an ISP (Internet Service Provider).

サーバー3は、各発注用端末7または受注用端末4から送信されたデータを、ネットワーク8を介して受信し、これらの入力に応じた処理を行うものである。ハード構成としては、汎用のコンピュータと同様、主記憶装置(図示しない)と、演算装置及び制御装置から構成される中央処理装置と、キーボードやポインティングデバイス等、情報を直接入力するための入力装置と、サーバー3の中で処理された情報を取出すディスプレイ等の出力装置と、ネットワーク8を介してデータの送受信を行うモデム等の通信手段と、ハードディスク等から構成された記憶装置とを備えている。   The server 3 receives data transmitted from each ordering terminal 7 or order receiving terminal 4 via the network 8 and performs processing according to these inputs. As with a general-purpose computer, the hardware configuration includes a main storage device (not shown), a central processing unit including an arithmetic device and a control device, and an input device for directly inputting information such as a keyboard and a pointing device. And an output device such as a display for retrieving information processed in the server 3, a communication means such as a modem for transmitting and receiving data via the network 8, and a storage device comprising a hard disk or the like.

なお、通信手段は、図2に示すように、発注用端末7または受注用端末4からデータを受信する受信手段11と、アクセスのあった発注用端末7等にデータを送信する送信手段12とを有する通信制御手段13によって制御されるようになっている。   As shown in FIG. 2, the communication means includes a receiving means 11 for receiving data from the ordering terminal 7 or the order receiving terminal 4, and a transmitting means 12 for transmitting data to the accessed ordering terminal 7 or the like. It is controlled by the communication control means 13 having

サーバー3の記憶装置は、商品情報記憶手段14、発注情報記憶手段15、及び日程情報記憶手段16に大別されている。商品情報記憶手段14には、「商品名」、「品番」、「価格」、及び「商品の説明」等の商品情報が記憶されている。   The storage device of the server 3 is roughly divided into a product information storage unit 14, an order information storage unit 15, and a schedule information storage unit 16. The product information storage means 14 stores product information such as “product name”, “product number”, “price”, and “product description”.

発注情報記憶手段15は、建材9の発注または見積もりの際に入力された情報、具体的には、図4(a)に示すように、建材9の「品番」及び「数量」を含む「商品情報」と、「使用場所」及び「施工種別」を含む「工事情報」とを、互いに関連付けて記憶するものである。ここで、「使用場所」とは、夫々の建材9が使用される場所を示すものであり、本例では、物件名である「個別邸」の識別番号と、部屋の種類を示す「部屋」の識別番号と、壁、床、及び天井等、工事対象の部位を示す「部位」の識別番号との組合わせから構成されている。また、「施工種別」には、大工、左官、配管、及び電気工事といった「職種の区分」と、「施工順序」を示す情報とが含まれている。   The order information storage means 15 is the information input when placing an order for or estimating the building material 9, specifically, as shown in FIG. 4A, a “product” including “article number” and “quantity” of the building material 9. Information "and" construction information "including" use place "and" construction type "are stored in association with each other. Here, “use place” indicates a place where each building material 9 is used. In this example, the identification number of “individual house” which is the property name and the “room” indicating the type of the room. And a “part” identification number indicating a construction target part, such as a wall, a floor, and a ceiling. The “construction type” includes “job category” such as carpenter, plasterer, piping, and electrical work, and information indicating “construction order”.

一方、日程情報記憶手段16は、図4(b)に示すように、工事のスケジュールを管理する際、発注用端末7から「工事情報」、すなわち「使用場所」及び「施工種別」の組合わせに対応する「日程」(日付)が入力されると、その「日程」と「工事情報」とを互いに関連づけて記憶するものである。つまり、「商品情報」に対して「日程」が入力されるのではなく、「工事情報」に対して「日程」が入力されることから、異種の建材9であっても、それらの建材9の「使用場所」及び「施工種別」が互いに一致していれば、同一の日付に使用されるものとして設定される。また、同一の建材9であっても、例えば使用する部屋が互いに異なる場合には個別に日程が設定されることとなる。   On the other hand, as shown in FIG. 4 (b), the schedule information storage means 16 uses a combination of “construction information”, that is, “use place” and “construction type” from the ordering terminal 7 when managing the construction schedule. When the “schedule” (date) corresponding to is input, the “schedule” and “construction information” are stored in association with each other. In other words, since “schedule” is not input for “product information” but “schedule” is input for “construction information”, even for different types of building materials 9, those building materials 9 If the “use place” and “construction type” of the two coincide with each other, they are set to be used on the same date. Moreover, even if it is the same building material 9, a schedule will be set separately, when the room to be used differs, for example.

ところで、このサーバー3には、受発注支援プログラムが記憶されており、このプログラムを実行させることにより、以下に示す機能的構成を有するものになる。   By the way, the server 3 stores an ordering support program. By executing this program, the server 3 has the following functional configuration.

すなわち、図2に示すように、サーバー3は、発注情報を取得するための構成として、発注情報要求手段18及び発注情報認識手段19を備えている。発注情報要求手段18は、「商品情報」及び「工事情報」の入力を、発注用端末7に対して要求するものである。つまり、発注用端末7のディスプレイ34(図3参照)に所定の入力画面を表示させ、「商品情報」及び「工事情報」の入力を促すものである。発注情報認識手段19は、発注用端末7において入力された「商品情報」及び「工事情報」を、受信手段11を介して受信し認識するものである。認識されたこれらの情報は互いに関連付けられ発注情報記憶手段15に記憶される。   That is, as shown in FIG. 2, the server 3 includes an order information request unit 18 and an order information recognition unit 19 as a configuration for acquiring the order information. The order information requesting means 18 requests the ordering terminal 7 to input “product information” and “construction information”. That is, a predetermined input screen is displayed on the display 34 (see FIG. 3) of the ordering terminal 7 to prompt the input of “product information” and “construction information”. The order information recognition unit 19 receives and recognizes “product information” and “construction information” input at the ordering terminal 7 via the reception unit 11. The recognized information is associated with each other and stored in the order information storage unit 15.

また、サーバー3は、見積指示が入力されたことを認識する見積指示認識手段20と、見積書を作成する見積書作成手段21とを備えている。見積書作成手段21は、発注情報記憶手段15に記憶された「商品情報」及び「工事情報」と、商品情報記憶手段14に記憶された「価格」とを基に見積書を作成するものである。特に、発注情報記憶手段15には、「工事情報」として「職種の区分」が記憶されており、見積書作成手段21は、これを基に職種毎の見積書を作成する。例えば図5(a)に示す見積書51は、職種Aに関するものであり、建材9の商品名、品番、数量、及び金額等が一覧として表示される。   In addition, the server 3 includes an estimate instruction recognition unit 20 that recognizes that an estimate instruction has been input, and an estimate creation unit 21 that creates an estimate. The estimate creation unit 21 creates an estimate based on the “product information” and “construction information” stored in the order information storage unit 15 and the “price” stored in the product information storage unit 14. is there. In particular, the “order classification” is stored as “construction information” in the order information storage means 15, and the estimate creation means 21 creates an estimate for each occupation based on this. For example, the estimate 51 shown in FIG. 5A relates to the job type A, and the product name, product number, quantity, amount, and the like of the building material 9 are displayed as a list.

また、サーバー3は、工事の日程を取得するための構成として日程要求手段22及び日程認識手段23を備えている。日程要求手段22は、「工事情報」に対する「日程(日付け)」の入力を、発注用端末7に対して要求するものである。つまり、発注用端末7のディスプレイ34に所定の入力画面を表示させ、「スケジュール」の入力を促すものである。日程認識手段23は、発注用端末7において入力された「日程」を、受信手段11を介して受信し認識するものである。認識された「日程」は工事情報に関連付けられ日程情報記憶手段16に記憶される。   In addition, the server 3 includes a schedule request unit 22 and a schedule recognition unit 23 as a configuration for acquiring a construction schedule. The schedule request means 22 requests the ordering terminal 7 to input “schedule (date)” for “construction information”. That is, a predetermined input screen is displayed on the display 34 of the ordering terminal 7 to prompt the input of “schedule”. The schedule recognizing means 23 receives and recognizes the “schedule” input at the ordering terminal 7 via the receiving means 11. The recognized “schedule” is associated with the construction information and stored in the schedule information storage means 16.

さらに、サーバー3は、建材9の納品を手配するための構成として、検索指示認識手段24、情報抽出手段25、及びリスト作成手段26を備えている。検索指示認識手段24は、受注用端末4において検索が指示されたことを認識するものであり、認識した場合、検索条件である「納入日」を情報抽出手段25に出力する。情報抽出手段25は、検索指示認識手段24によって認識した「納入日」と日程情報記憶手段16に記憶された「日程」とを照合し、一致する「日程」を認識するとともに、その「日程」に対応付けられた「工事情報」を日程情報記憶手段16から抽出する。また、抽出された「工事情報」に関連する全ての商品情報を、発注情報記憶手段15に記憶された「商品情報」及び「工事情報」の関連付けを基に抽出する。リスト作成手段26は、情報抽出手段25によって抽出された「商品情報」を基に、建材9の納品リストを作成するものである。例えば、図4(a)に示す情報が発注情報記憶手段15に記憶され、図4(b)に示す情報が日程情報記憶手段16に記憶されている場合において、納入日として「2004/03/08」を指定して検索が指示されると、図5(b)に示すような納品リスト52を作成し受注用端末4に送信する。なお、納品リスト52をプリンタ5に送出し、紙媒体に印刷することも可能である。   Further, the server 3 includes a search instruction recognition unit 24, an information extraction unit 25, and a list creation unit 26 as a configuration for arranging delivery of the building material 9. The search instruction recognizing means 24 recognizes that a search is instructed in the order receiving terminal 4, and outputs the “delivery date” as a search condition to the information extracting means 25 when it is recognized. The information extraction means 25 collates the “delivery date” recognized by the search instruction recognition means 24 with the “schedule” stored in the schedule information storage means 16, recognizes the matching “schedule”, and the “schedule” Is extracted from the schedule information storage means 16. Further, all the product information related to the extracted “construction information” is extracted based on the association between “product information” and “construction information” stored in the order information storage means 15. The list creation unit 26 creates a delivery list of the building materials 9 based on the “product information” extracted by the information extraction unit 25. For example, when the information shown in FIG. 4A is stored in the order information storage unit 15 and the information shown in FIG. 4B is stored in the schedule information storage unit 16, the delivery date is “2004/03 / When a search is instructed by specifying “08”, a delivery list 52 as shown in FIG. 5B is created and transmitted to the order receiving terminal 4. The delivery list 52 can be sent to the printer 5 and printed on a paper medium.

一方、発注用端末7は、ブラウザソフトがインストールされた汎用のコンピュータであり、主記憶装置、演算装置、及び制御装置から構成されるCPU(中央処理装置)と、ネットワーク8を介して情報を送受信する通信装置とを備えている。なお、図3に示すように、通信装置は、受信手段30及び送信手段31を有する通信制御手段32によって制御される。また、発注用端末7には、キーボードやポインティングデバイス等の入力装置33と、ディスプレイ34を制御する表示制御手段35とが設けられている。   On the other hand, the ordering terminal 7 is a general-purpose computer installed with browser software, and transmits / receives information to / from a CPU (central processing unit) composed of a main storage device, an arithmetic device, and a control device via the network 8. Communication device. As shown in FIG. 3, the communication apparatus is controlled by a communication control unit 32 having a reception unit 30 and a transmission unit 31. Further, the ordering terminal 7 is provided with an input device 33 such as a keyboard or a pointing device, and a display control means 35 for controlling the display 34.

また、発注用端末7は、サーバー3から送信された情報を認識する複数の機能的構成を備えている。すなわち、発注情報の要求を認識する発注要求認識手段36と、見積書を認識する見積書認識手段37と、日程の要求を認識する日程要求認識手段38とを備えている。これらの認識手段によって認識された各情報は、表示制御手段35に送られディスプレイ34に表示される。また、発注用端末7は、機能的構成として、情報の入力を行わせるための複数の手段を備えている。具体的には、建材9の発注情報を入力するための発注情報入力手段39と、入力した発注情報に関して見積書を作成することを指示する見積指示入力手段40と、工事情報に対する日程を入力するための日程入力手段41とを備えている。これらの入力手段39,40,41によって入力された各情報は、送信手段31を介してサーバー3に送信される。   The ordering terminal 7 has a plurality of functional configurations that recognize information transmitted from the server 3. That is, it includes an order request recognition unit 36 for recognizing a request for order information, a quote recognition unit 37 for recognizing an estimate, and a schedule request recognition unit 38 for recognizing a schedule request. Each piece of information recognized by these recognition means is sent to the display control means 35 and displayed on the display 34. In addition, the ordering terminal 7 includes a plurality of means for inputting information as a functional configuration. Specifically, the order information input means 39 for inputting the order information of the building material 9, the estimate instruction input means 40 for instructing the creation of an estimate for the input order information, and the schedule for the construction information are input. The schedule input means 41 is provided. Each information input by these input means 39, 40, 41 is transmitted to the server 3 via the transmission means 31.

次に、本実施形態の受発注支援システム1の動作、特に、サーバー3における処理の流れ(本発明の受発注支援プログラムに相当)について、図6に基づき説明する。まず、サーバー3は、いずれかの発注用端末7からアクセスがあり(ステップS1においてYES)、発注用端末7において建材9の発注モード(発注画面)が選択されると(ステップS2においてYES)、発注用端末7から発注情報(商品情報及び工事情報)が入力されたか否かを判断する(ステップS3)。そして、発注情報が入力された場合には(ステップS3においてYES)、その発注情報を認識し発注情報記憶手段15に記憶する(ステップS4)。なお、この際、商品情報と工事情報とは互いに関連付けて記憶される。   Next, the operation of the ordering support system 1 of the present embodiment, in particular, the processing flow in the server 3 (corresponding to the ordering support program of the present invention) will be described with reference to FIG. First, the server 3 is accessed from any of the ordering terminals 7 (YES in step S1), and when the ordering mode (ordering screen) of the building material 9 is selected in the ordering terminal 7 (YES in step S2), It is determined whether or not ordering information (product information and construction information) is input from the ordering terminal 7 (step S3). When the order information is input (YES in step S3), the order information is recognized and stored in the order information storage means 15 (step S4). At this time, the product information and the construction information are stored in association with each other.

その後、発注用端末7から見積書の指示が入力されたか否かを判断し、その指示が入力された場合には(ステップS5においてYES)、商品情報記憶手段14及び発注情報記憶手段15に記憶された情報を基に、職種毎の見積書51を作成し、発注用端末7に送信する(ステップS6)。   Thereafter, it is determined whether or not an estimate instruction has been input from the ordering terminal 7. If the instruction has been input (YES in step S5), it is stored in the product information storage means 14 and the order information storage means 15. Based on the received information, an estimate 51 for each occupation is created and transmitted to the ordering terminal 7 (step S6).

また、発注用端末7において、工事日程管理モード(日程入力画面)が選択されると(ステップS7においてYES)、工事情報に対応する日程が入力されたか否かを判断する(ステップS8)。そして、日程が入力された場合には(ステップS8においてYES)、その日程を認識し日程情報記憶手段16に記憶する(ステップS9)。なお、この際、日程と工事情報とは対応づけて記憶される。   Further, when the construction schedule management mode (schedule input screen) is selected in the ordering terminal 7 (YES in step S7), it is determined whether or not a schedule corresponding to the construction information has been input (step S8). When the schedule is input (YES in step S8), the schedule is recognized and stored in the schedule information storage means 16 (step S9). At this time, the schedule and the construction information are stored in association with each other.

一方、受注用端末4からアクセスがあり(ステップS10においてYES)、受注用端末4において、「納入日」の指定とともに検索指示が入力されると(ステップS11においてYES)、情報抽出手段25によって、納入日に対応する商品情報を発注情報記憶手段15から抽出し納品リスト52を作成するとともに、作成した納品リスト52を受注用端末4に送信する(ステップS12)。これにより、受注用端末4において、納品リスト52が表示され、納入日毎の納品状況を確認することが可能になる。   On the other hand, when there is an access from the order receiving terminal 4 (YES in step S10) and the search instruction is input together with the designation of “delivery date” in the order receiving terminal 4 (YES in step S11), the information extracting means 25 Product information corresponding to the delivery date is extracted from the order information storage means 15 to create a delivery list 52, and the created delivery list 52 is transmitted to the order receiving terminal 4 (step S12). As a result, the delivery list 52 is displayed on the order receiving terminal 4, and the delivery status for each delivery date can be confirmed.

その後、システムを終了させる旨の指示が入力されたか否かを判断し(ステップS13)、その指示が入力された場合には(YES)、全ての処理を終了し、一方、入力されない場合には(NO)、ステップS1の処理に戻る。   Thereafter, it is determined whether or not an instruction for terminating the system has been input (step S13). If the instruction is input (YES), all the processes are ended. (NO), it returns to the process of step S1.

このように、上記の受発注支援システム1によれば、発注時に拾い出された建材9の使用場所及び施工種別を、発注時に特定しておくことにより、工事の日程管理にその発注情報を役立てることが可能になる。つまり、発注情報を再利用することが可能になる。このため、複数の建材9の納入日を容易に設定することが可能となり、発注者6の負担を軽減することができる。また、工事情報に対応して日程を設定することから、同じ種類の建材9であっても異なる場所に配置する場合には、夫々の場所の施工状況に合わせて納品できるようになり、現場における利便性を大きく向上させることができる。   As described above, according to the ordering support system 1 described above, the use location and construction type of the building material 9 picked up at the time of ordering are specified at the time of ordering, so that the ordering information is used for construction schedule management. It becomes possible. That is, the order information can be reused. For this reason, it becomes possible to easily set the delivery date of the plurality of building materials 9, and the burden on the orderer 6 can be reduced. In addition, since the schedule is set according to the construction information, even if the same type of building material 9 is placed in different places, it can be delivered according to the construction situation of each place, Convenience can be greatly improved.

また、上記の受発注支援システム1によれば、発注情報記憶手段15に記憶された「職種の区分」を基に建材9の見積もりが振り分けられるため、見積書の内容を職種毎に認識することが可能となり、価格の把握やコスト交渉等を容易に且つ円滑に行うことが可能になる。特に、日程の管理上必要となる工事情報が、見積書を作成する際に利用されるため、情報の有効化が図られ、発注者6の手間を一層軽減することができる。   Further, according to the ordering support system 1 described above, since the estimate of the building material 9 is allocated based on the “classification of job type” stored in the ordering information storage means 15, the contents of the estimate sheet are recognized for each job type. This makes it possible to grasp prices and negotiate costs easily and smoothly. In particular, since construction information necessary for schedule management is used when preparing an estimate, the information can be validated and the labor of the orderer 6 can be further reduced.

以上、本発明について好適な実施形態を挙げて説明したが、本発明はこれらの実施形態に限定されるものではなく、以下に示すように、本発明の要旨を逸脱しない範囲において、種々の改良及び設計の変更が可能である。   The present invention has been described with reference to preferred embodiments. However, the present invention is not limited to these embodiments, and various modifications can be made without departing from the spirit of the present invention as described below. And design changes are possible.

すなわち、本実施形態の受発注支援システム1では、発注情報の入力及び日程の入力が、同一の発注用端末7を用いて行われるものを示したが、別々の端末装置を用いて入力されるように構成してもよい。特に、建材9の発注作業が行われる場所と、工事の日程が管理される場所とが互いに異なる場合には、上記のように構成することにより、使い勝手の優れたシステムを実現することが可能になる。   That is, in the ordering support system 1 of the present embodiment, the ordering information and the schedule are input using the same ordering terminal 7, but are input using separate terminal devices. You may comprise as follows. In particular, when the place where the building material 9 is ordered and the place where the construction schedule is managed are different from each other, it is possible to realize an easy-to-use system by configuring as described above. Become.

さらに、本実施形態の受発注支援システム1では、発注用端末7として汎用のコンピュータを示したが、発注用端末7は、ネットワーク8を介してサーバー3にアクセスできるものであればよく、例えば携帯電話等の無線通信機器を利用することも可能である。   Furthermore, in the ordering support system 1 of the present embodiment, a general-purpose computer is shown as the ordering terminal 7. However, the ordering terminal 7 may be anything that can access the server 3 via the network 8, for example, a portable terminal. It is also possible to use a wireless communication device such as a telephone.

本発明の一実施形態である受発注支援システムの概略構成を示す説明図である。It is explanatory drawing which shows schematic structure of the ordering support system which is one Embodiment of this invention. 建材の受発注支援システムにおけるサーバーの機能的構成を示すブロック図である。It is a block diagram which shows the functional structure of the server in the ordering support system of building materials. 建材の受発注支援システムにおける発注用端末の機能的構成を示すブロック図である。It is a block diagram which shows the functional structure of the terminal for ordering in the ordering support system of building materials. サーバーに記憶される情報の構成を説明する説明図である。It is explanatory drawing explaining the structure of the information memorize | stored in a server. 表示画面の一例を示す説明図である。It is explanatory drawing which shows an example of a display screen. サーバーにおける処理の流れを示すフローチャートである。It is a flowchart which shows the flow of the process in a server.

符号の説明Explanation of symbols

1 受発注支援システム(建材の受発注支援システム)
3 サーバー
7 発注用端末
8 ネットワーク(通信ネットワーク)
9 建材
15 発注情報記憶手段
16 日程情報記憶手段
21 見積書作成手段
25 情報抽出手段
26 リスト作成手段
1 Ordering support system (Building materials ordering support system)
3 Server 7 Ordering terminal 8 Network (communication network)
9 Building materials 15 Order information storage means 16 Schedule information storage means 21 Estimate creation means 25 Information extraction means 26 List creation means

Claims (3)

複数の種類の建材を発注する発注用端末とサーバーとを通信ネットワークを介して接続した建材の受発注支援システムであって、
前記サーバーは、
発注の際に、前記発注用端末から、建材の品番及び数量を含む商品情報と、その建材の使用場所及び施工種別を含む工事情報とが入力されると、前記商品情報及び前記工事情報を互いに関連付けて記憶する発注情報記憶手段と、
日程管理の際に、前記発注用端末から、前記工事情報に対応する日程が入力されると、該日程及び前記工事情報を互いに関連付けて記憶する日程情報記憶手段と、
建材を納品する際に、納入日を指定して検索が指示されると、該納入日に一致する前記日程を基に、該日程に対応する前記工事情報を前記日程情報記憶手段から抽出するとともに、抽出された前記工事情報に関連する全ての前記商品情報を前記発注情報記憶手段から抽出する情報抽出手段と、
該情報抽出手段によって抽出された前記商品情報を基に、建材の納品リストを作成するリスト作成手段と
を具備することを特徴とする建材の受発注支援システム。
An ordering support system for building materials in which an ordering terminal that orders multiple types of building materials and a server are connected via a communication network,
The server
When placing an order, product information including the product number and quantity of the building material and construction information including the use location and construction type of the building material are input from the ordering terminal, and the product information and the construction information are mutually exchanged. Order information storage means for storing in association;
A schedule information storage means for storing the schedule and the construction information in association with each other when a schedule corresponding to the construction information is input from the ordering terminal during schedule management;
When delivering a building material, when a search is instructed by specifying a delivery date, the construction information corresponding to the schedule is extracted from the schedule information storage means based on the schedule that matches the delivery date. Information extracting means for extracting all the product information related to the extracted construction information from the order information storage means;
A building material ordering support system, comprising: a list creating means for creating a delivery list of building materials based on the product information extracted by the information extracting means.
前記施工種別には職種の区分が含まれ、
前記発注情報記憶手段に記憶された前記商品情報及び前記工事情報を基に、前記職種毎の見積書を作成する見積書作成手段をさらに備えることを特徴とする請求項1に記載の建材の受発注支援システム。
The construction type includes job category,
The construction material receiving apparatus according to claim 1, further comprising: an estimate creation unit that creates an estimate for each job type based on the product information and the construction information stored in the order information storage unit. Order support system.
複数の商品を発注する発注用端末とサーバーとを通信ネットワークを介して接続した建材の受発注支援システムにおいて使用される受発注支援プログラムであって、
発注の際に、前記発注用端末から、建材の品番及び数量を含む商品情報と、その建材の使用場所及び施工種別を含む工事情報とが入力されると、前記商品情報及び前記工事情報を互いに関連付けて記憶する発注情報記憶手段、
日程管理の際に、前記発注用端末から、前記工事情報に対応する日程が入力されると、該日程及び前記工事情報を互いに関連付けて記憶する日程情報記憶手段、
建材を納品する際に、納入日を指定して検索が指示されると、該納入日に一致する前記日程を基に、該日程に対応する前記工事情報を前記日程情報記憶手段から抽出するとともに、抽出された前記工事情報に関連する全ての前記商品情報を前記発注情報記憶手段から抽出する情報抽出手段、
及び、該情報抽出手段によって抽出された前記商品情報を基に、建材の納品リストを作成するリスト作成手段
として、前記サーバーを機能させることを特徴とする建材の受発注支援プログラム。
An ordering support program used in an ordering support system for building materials in which an ordering terminal for ordering a plurality of products and a server are connected via a communication network,
When placing an order, product information including the product number and quantity of the building material and construction information including the use location and construction type of the building material are input from the ordering terminal, and the product information and the construction information are mutually exchanged. Order information storage means for storing in association;
When a schedule corresponding to the construction information is input from the ordering terminal during schedule management, a schedule information storage means for storing the schedule and the construction information in association with each other,
When delivering a building material, when a search is instructed by specifying a delivery date, the construction information corresponding to the schedule is extracted from the schedule information storage means based on the schedule that matches the delivery date. Information extracting means for extracting all the product information related to the extracted construction information from the order information storage means;
And a building material ordering support program for causing the server to function as a list creating means for creating a delivery list of building materials based on the product information extracted by the information extracting means.
JP2004125017A 2004-04-21 2004-04-21 Building material ordering and order receipt support system and program therefor Pending JP2005309718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004125017A JP2005309718A (en) 2004-04-21 2004-04-21 Building material ordering and order receipt support system and program therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004125017A JP2005309718A (en) 2004-04-21 2004-04-21 Building material ordering and order receipt support system and program therefor

Publications (1)

Publication Number Publication Date
JP2005309718A true JP2005309718A (en) 2005-11-04

Family

ID=35438449

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004125017A Pending JP2005309718A (en) 2004-04-21 2004-04-21 Building material ordering and order receipt support system and program therefor

Country Status (1)

Country Link
JP (1) JP2005309718A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2900751A1 (en) * 2006-05-04 2007-11-09 Aart Farah Architectes Associe Building e.g. hospital center, construction project assisting method for architectural office, involves updating listing of room characteristics from listing of equipments and rules, and merging listings of same type into single listing
KR100992145B1 (en) 2008-01-15 2010-11-04 삼성전자주식회사 Apparatus and method for delivering business information and method of providing business information
JP2013164681A (en) * 2012-02-09 2013-08-22 Ohbayashi Corp Server device and information management system
JP7654267B2 (en) 2022-10-20 2025-04-01 株式会社三富 Trade Management System

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2900751A1 (en) * 2006-05-04 2007-11-09 Aart Farah Architectes Associe Building e.g. hospital center, construction project assisting method for architectural office, involves updating listing of room characteristics from listing of equipments and rules, and merging listings of same type into single listing
KR100992145B1 (en) 2008-01-15 2010-11-04 삼성전자주식회사 Apparatus and method for delivering business information and method of providing business information
JP2013164681A (en) * 2012-02-09 2013-08-22 Ohbayashi Corp Server device and information management system
JP7654267B2 (en) 2022-10-20 2025-04-01 株式会社三富 Trade Management System

Similar Documents

Publication Publication Date Title
JP2003201015A (en) Shipping management system and shipping management program
JP2023106054A (en) Reform matching system
US20150234377A1 (en) Construction management system
JP6022396B2 (en) Estimation support apparatus and estimation support method
JP7107796B2 (en) Information processing device, information processing method, and program
JP2019087185A (en) Product sales system
JP2005309718A (en) Building material ordering and order receipt support system and program therefor
JP6669504B2 (en) Decision Workflow Ordering Device, Decision Workflow Order Method, and Decision Workflow Order Program
JP2021092833A (en) Construction management method and construction management system of building
JP2004362505A (en) System, method and program for sale
JP2017126246A (en) Shipment instruction program, shipment instruction device and shipment instruction system
JP4282980B2 (en) Order support system and program
JP2002236720A (en) System for managing building data
JP7550358B2 (en) Materials management method, program, and materials management system
JP4447828B2 (en) Data management system for housing components
JP2001325326A (en) Method and system device for handling, retrieval, and distribution
JP2002269175A (en) System for placing and receiving order for building materials
JP4204346B2 (en) Shipping management system and shipping management program
JP2005044157A (en) Estimate preparation support system for construction member and estimate preparation support program
JP2002279214A (en) Program, recording medium, information processor, local area network, and building
JP4878383B2 (en) Electronic commerce system, electronic commerce program, and business server
JP2004054765A (en) System and program for supporting delivery schedule preparation
JP2004234281A (en) House remodeling estimate system and house remodeling estimate program
JP2011034288A (en) Real estate information management system
JP2006059231A (en) Acceptance of order and ordering support system and program therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051221

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080619

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080729

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080918

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20081216