[go: up one dir, main page]

JP2005097840A - Slope stabilization method - Google Patents

Slope stabilization method Download PDF

Info

Publication number
JP2005097840A
JP2005097840A JP2003329701A JP2003329701A JP2005097840A JP 2005097840 A JP2005097840 A JP 2005097840A JP 2003329701 A JP2003329701 A JP 2003329701A JP 2003329701 A JP2003329701 A JP 2003329701A JP 2005097840 A JP2005097840 A JP 2005097840A
Authority
JP
Japan
Prior art keywords
slope
spiral
pile
stabilization method
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003329701A
Other languages
Japanese (ja)
Inventor
Takashi Tamura
隆志 田村
Takuo Shinomiya
卓夫 四宮
Nobumitsu Mitsunaga
演允 光永
Takeshi Nakamura
中村  剛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nisshoku Corp
East Japan Railway Co
Original Assignee
Nisshoku Corp
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisshoku Corp, East Japan Railway Co filed Critical Nisshoku Corp
Priority to JP2003329701A priority Critical patent/JP2005097840A/en
Publication of JP2005097840A publication Critical patent/JP2005097840A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a slope stabilization method capable of preventing the collapse of a slope surface layer without damaging a slope at a low cost without taking much time for construction work. <P>SOLUTION: The slope stabilization method is so constituted that a plurality of spiral piles are driven at predetermined intervals, at the same time, the head sections of the spiral piles are connected with a connecting material and that a plurality of stages of a plurality of spiral piles connected with the connecting material can be installed on the slop at predetermined intervals according to a height of the slope. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は螺旋(ラセン)杭を用いて法面を安定化する工法に関する。   The present invention relates to a method for stabilizing a slope using a spiral pile.

特開2002−88769号公報JP 2002-88769 A 特開2002−242191号公報JP 2002-242191 A 特開平8−134923号公報JP-A-8-134923 特開平7−216900号公報JP 7-216900 A

従来、山などの法面の崩壊を防ぐための工法として、例えば、それぞれ支圧板を取り付けたアンカーを法面に複数列設置して各アンカーの頭部間を連結部材で連結し、各アンカーに取り付けた支圧板で地盤に支圧力を付与して法面を安定化するもの(特許文献1)、法面に補強材としてロックボルトを打ち込み、打ち込んだロックボルトにネットを張って法面を安定化するもの(特許文献2)が提案されている。
また、切土によって生じた法面を堅硬な基礎地盤まで削孔し、削孔した孔口の周縁部を凹型に成形して凹型孔孔部とした後、PC鋼線、PC鋼撚線等の引っ張り補強材を挿入し、凹型孔口部に設置した拘束圧付加板を台座として引っ張り補強材に軸力を導入して切土法面を安定化する工法(特許文献3)、切土法面にボルト挿入孔を削孔し、法面にシート状補強材をセットするとともに、ボルト挿入孔に合わせてプレートを固定し、ボルト挿入孔にグラウトを充填した後、プレートを貫通してボルトを挿入し、プレートを緊締する工法(特許文献4)が提案されている。
Conventionally, as a method for preventing the collapse of slopes such as mountains, for example, anchors each having a bearing plate are installed in multiple rows on the slope and the heads of the anchors are connected by connecting members, A mounted bearing plate that applies bearing pressure to the ground to stabilize the slope (Patent Document 1). A lock bolt is driven into the slope as a reinforcing material, and a net is stretched over the driven lock bolt to stabilize the slope. (Patent Document 2) has been proposed.
Also, after drilling the slope generated by the cut to a hard foundation ground, forming the peripheral edge of the drilled hole into a concave mold to make a concave hole, PC steel wire, PC steel stranded wire, etc. A method that stabilizes the cut slope by introducing axial force into the tensile reinforcement using the restraint pressure application plate installed at the concave hole opening as a pedestal (Patent Document 3), the cut method Cut the bolt insertion hole on the surface, set the sheet-like reinforcing material on the slope, fix the plate according to the bolt insertion hole, fill the bolt insertion hole with grout, then pass the bolt through the plate A construction method (Patent Document 4) for inserting and tightening a plate has been proposed.

上記特許文献1、特許文献2の法面安定化工法は施工性がよく、高所、長大法面や凹凸の多い法面への適用性に優れており、特許文献2、特許文献3の工法は地すべりや大規模なすべりに適用されるが、いずれの工法も作業用の装置を現場に持ち込まなければならず、比較的工期が長くなるとともに、工事費もかかるという問題がある。   The slope stabilization method described in Patent Literature 1 and Patent Literature 2 has good workability and is excellent in applicability to high places, long slopes and slopes with many irregularities. Can be applied to landslides and large-scale landslides, but each method has the problem that work equipment must be brought to the site, which requires a relatively long construction period and high construction costs.

本発明は上記課題を解決しようとするもので、施工に時間を要さず、低コストで法面を傷めずに法面表層の崩壊を防止することを目的とする。
そのために本発明は、法面に所定間隔で複数のラセン杭を打ち込むことにより法面を補強したり、また、各ラセン杭の頭部を連結材で連結することによりその連結効果を発揮させて法面を補強することを特徴とする。
更には、上記の法面の補強を実施したのちに、この法面上に各種の法覆工を敷設し、法面の更なる補強や景観の向上を図ることを特徴としている。
An object of the present invention is to solve the above-mentioned problems, and it is an object of the present invention to prevent the slope of the slope surface from collapsing without requiring time for construction and without damaging the slope at a low cost.
For this purpose, the present invention reinforces the slope by driving a plurality of helical piles at a predetermined interval on the slope, and also exhibits the connection effect by connecting the heads of each spiral pile with a connecting material. It is characterized by reinforcing the slope.
Furthermore, after carrying out the reinforcement of the above-mentioned slope, various slope linings are laid on the slope to further enhance the slope and improve the landscape.

以上のように本発明によれば、ラセン杭の打ち込みは人手で十分可能であるため現場に設置用の装置を持ち込む必要がなく、又持ち込んだとしても可搬式など軽微な装置で施工が可能であり、コストが非常に安くすむとともに、草刈りや表層部の整形等の法面整正が不要であり、法面を傷めず、かつ施工速度を非常に速くすることができる。
また、上記のラセン杭による法面補強を施工した後、法面をモルタルや緑化工等の法覆工を敷設すれば、より法面の補強や景観の保全が向上する。
As described above, according to the present invention, it is not necessary to bring a device for installation to the site because the pile pile can be driven manually, and even if it is carried, it can be constructed with a light device such as a portable device. In addition, the cost is very low, and no slope correction such as mowing or shaping of the surface layer is required, so that the slope is not damaged and the construction speed can be made very fast.
In addition, if the slope is laid with a mortar or revegetation, such as mortar, after the slope is reinforced with the above-mentioned spiral pile, the slope will be further reinforced and the landscape will be improved.

以下、本発明の実施の形態について説明する。
図1は本実施形態の法面安定化工法を説明する概念図、図2はラセン杭を説明する図である。
図1(a)に示すように、定着部を螺旋状に加工したラセン杭1を、表層崩壊を抑止したい法面に対して、例えば1m間隔で表層部3を通して深層部4にまで打ち込む。また、杭頭部をアルミ管、ステンレス管或いは鋼棒、ワイヤー等からなる連結材2で連結する。この構造のものを、図1(b)に示すように、法高に応じて、例えば1m間隔で複数段設置する。
このように、ラセン杭1を複数打ち込む構造であるため、法面工として用いた場合、ラセン杭の打ち込みは人手で十分可能であるため現場に設置用の装置を持ち込む必要がなく、コストが非常に安くすむとともに、草刈りや表層部の整形等の法面整正が不要であり、法面を傷めず、施工速度が非常に速いというメリットがある。また、杭頭部を連結材2で連結することにより、個々の杭が連結されてより法面の補強効果が高まる。
図2(a)に示すように、使用するラセン杭1は、定着部を螺旋加工し、頭部を例えば、湾曲状に折り返した鋼製の杭であり、先端を少し打ち込んだ後、頭部の湾曲部にパイプ等を差し込んでこれを回転させることによりねじ込み式に打ち込む。本実施形態では、杭全長557mm、杭螺旋部の円柱径85mm、円柱長208.3mmのものを使用した。図2(b)に示すように、湾曲状に折り返した杭頭部を残してラセン杭を法面に打ち込み、螺旋部が表層部3を通して深層部4に達するように設置する。図3はラセン杭頭部の連結材固定方法を説明する図である。
図3(a)(正面図)、図3(b)(側面図)に示すように、杭頭部に連結材2を固定するためのステンレス製等の固定バンド5を取り付け、これでアルミ管やステンレス管等からなる連結材2を固定する。
図4は連結材同士の連結方法を説明する図である。
本実施形態では、ステンレス製等の取り付け管6を用い、この取り付け管6に両側から連結材2を差し込んで連結する方法を採用している。その際接着剤7を用いて固定する事が有る。
図5はラセン杭の施工方法を説明する図である。
本実施形態では、上記したラセン杭を1m間隔で打ち込んで連結材2によりその頭部を連結する。ここでは連結材として4mのものを使用し、連結材同士は取り付け管6で連結する。このような構造のものを、法高に応じて1m間隔で設置する。
このラセン杭について、モルタル杭と比較して鉛直引き抜き試験、水平裁荷試験を行った。モルタル杭の円柱径は製作上の理由からラセン杭より太いものを使用したため、鉛直引き抜き力、水平耐力ともラセン杭より大きかったが、鉛直引き抜き力は、モルタル杭では杭周面の付着が切れると同時に耐力が低下したのに対して、ラセン杭は最大耐力発揮後も顕著な低下は見られず、高じん性であることが分かった。水平耐力は、モルタル杭では最大耐力発揮後は引き抜けてしまうのに対して、ラセン杭では最大耐力発揮後も耐力の顕著な低下は見られず、完全に引き抜ける直前まで耐力が増加し、ずるずる抜ける傾向があった。また、引き抜き後のラセン杭は、頭部に若干の変形が見られるものの、螺旋加工された定着部にはほとんど変形が見られなかった。
通常、モルタル杭では施工条件によっては耐力が期待できない場合があるが、ラセン杭ではどのような施工条件であっても、引き抜けるまで耐力があり、法面が崩れそうな傾向のあるときでも最後まで崩壊を抑止するように働くことが期待できる。
なお、上記の例ではラセン杭の間隔1m、複数段設置する場合の各段の間隔1mとし、ラセン杭を1本/m2で設置するようにしたが、法面勾配、法高によりラセン杭が負う荷重は変わるので、法面勾配、法高に応じて単位面積当たりのラセン杭の設置本数を適宜変更する必要がある。
図6は施工例を説明する正面図である。
1段目:18.5m、ラセン杭20本、連結材としてステンレス管4m×4+2.5m
2段目:17.5m、ラセン杭19本、連結材としてステンレス管4m×4+1.5m
3段目:16.0m、ラセン杭17本、連結材としてステンレス管4m×4
4段目:16.0m、ラセン杭16本、連結材としてステンレス管4m×4
5段目:8.0m、ラセン杭8本、連結材としてステンレス管4m×2
Embodiments of the present invention will be described below.
FIG. 1 is a conceptual diagram for explaining a slope stabilization method according to this embodiment, and FIG. 2 is a diagram for explaining a spiral pile.
As shown in FIG. 1 (a), a spiral pile 1 having a fixing portion processed into a spiral shape is driven into the deep layer portion 4 through the surface layer portion 3 at intervals of 1 m, for example, with respect to the slope where the surface layer collapse is to be suppressed. Further, the pile heads are connected by a connecting member 2 made of an aluminum tube, a stainless tube, a steel rod, a wire or the like. As shown in FIG. 1B, a plurality of stages having this structure are installed at intervals of 1 m, for example, according to the height of the law.
In this way, since it is a structure in which a plurality of helical piles 1 are driven, when used as a slope work, it is possible to manually drive the helical piles, so it is not necessary to bring equipment for installation at the site, and the cost is very high. In addition, it is advantageous in that it does not require slope correction such as mowing and surface layer shaping, and does not damage the slope and has a very high construction speed. Moreover, by connecting the pile heads with the connecting material 2, the individual piles are connected to enhance the slope reinforcement effect.
As shown in FIG. 2 (a), the spiral pile 1 to be used is a steel pile in which the fixing portion is spirally processed and the head is folded back into a curved shape, for example, and after the head is driven slightly, A pipe or the like is inserted into the curved portion of the tube and rotated to drive it in a screwed manner. In this embodiment, a pile with a total length of 557 mm, a pile spiral portion with a cylinder diameter of 85 mm, and a cylinder length of 208.3 mm was used. As shown in FIG. 2 (b), the spiral pile is driven into the slope with the pile head folded back in a curved shape, and installed so that the spiral portion reaches the deep layer portion 4 through the surface layer portion 3. FIG. 3 is a view for explaining a method for fixing the connecting member of the spiral pile head.
As shown in FIG. 3 (a) (front view) and FIG. 3 (b) (side view), a fixing band 5 made of stainless steel or the like for fixing the connecting material 2 is attached to the pile head, and thereby an aluminum tube The connecting member 2 made of stainless steel or the like is fixed.
FIG. 4 is a diagram for explaining a method of connecting the connecting members.
In this embodiment, the attachment pipe 6 made of stainless steel or the like is used, and the connection material 2 is inserted into the attachment pipe 6 from both sides and connected. At that time, the adhesive 7 may be used for fixing.
FIG. 5 is a diagram for explaining a method for constructing a spiral pile.
In this embodiment, the above-described spiral pile is driven at 1 m intervals, and the heads are connected by the connecting material 2. Here, a 4 m connecting material is used, and the connecting materials are connected by the attachment pipe 6. The thing of such a structure is installed at 1 m intervals according to the legal height.
This spiral pile was subjected to a vertical pull-out test and a horizontal unloading test in comparison with the mortar pile. The column diameter of the mortar pile was larger than that of the spiral pile for manufacturing reasons, so both the vertical pulling force and horizontal proof stress were larger than that of the spiral pile. At the same time, the yield strength decreased, but the spiral pile did not show any significant decrease even after the maximum yield strength was exhibited, indicating that it was highly tough. The horizontal strength is pulled out after the maximum strength is exhibited in the mortar pile, whereas the remarkable decrease in the strength is not seen in the spiral pile even after the maximum strength is exhibited, and the strength increases until it is completely pulled out, and it is slipped. There was a tendency to escape. In addition, the spiral pile after pulling out showed slight deformation at the head, but almost no deformation was observed at the fixing portion that had been spirally processed.
In general, mortar piles may not be able to expect proof strength depending on the construction conditions, but spiral piles are proof until they are pulled out regardless of the construction conditions, even when the slope tends to collapse until the end. It can be expected to work to deter collapse.
In the above example, the distance between the spiral piles is 1 m, and the distance between each stage when multiple stages are installed is 1 m, and the spiral piles are installed at 1 / m 2. Since the load to be loaded changes, it is necessary to change the number of spiral piles per unit area as appropriate according to the slope and height.
FIG. 6 is a front view for explaining a construction example.
First stage: 18.5m, 20 spiral piles, stainless steel tube 4m x 4 + 2.5m as connecting material
2nd stage: 17.5m, 19 spiral piles, stainless steel tube 4m x 4 + 1.5m as connecting material
Third stage: 16.0m, 17 spiral piles, stainless steel tube 4m x 4 as connecting material
4th stage: 16.0m, 16 spiral piles, stainless steel pipe 4m x 4 as connecting material
5th stage: 8.0m, 8 spiral piles, stainless steel tube 4m x 2 as connecting material

上記のような一連のラセン杭工法を施工した後、この上に緑化工やモルタル・コンクリート等の法覆工を施工し、頭部と連結材を埋め殺しする、あるいはラセン杭頭部をキャップ(図示せず)により保護することにより、施工後のメンテナス、草刈作業時などの障害を防止する。
図7は、上記のように、ラセン杭1を法面に打込んで法面の補強を実施する等一連の施工後、この法面上に緑化工やモルタル・コンクリート工等の各種の法覆工7を敷設し、ラセン杭1頭部と連結材2を埋め殺しした法面の断面状況を模式的に図示している。法覆工8の種類は周辺の環境や法面の強度(崩壊のおそれの程度)によって種々選択でき、例えば、崩壊のおそれの高い(法面地盤が脆弱であるとか急勾配であるなど)の場合には強度のあるモルタルやコンクリートの吹付などによる法覆工8を敷設する。これらのモルタルやコンクリート吹付を施工する場合には通常ラス金網(図示せず)を張設した後に吹付けられるので、この場合にはラセン杭の連結材は必ずしも必要としない。
After constructing a series of spiral piles as described above, construct a green lining, mortar, concrete, etc., and bury the head and connecting materials, or cap the spiral pile head ( (Not shown) prevents damages such as maintenance after construction and mowing.
Fig. 7 shows a series of works such as greening, mortar, concrete work, etc. on the slope after a series of constructions such as driving the pile 1 into the slope and reinforcing the slope as described above. The cross-sectional state of the slope where the construction 7 is laid and the spiral pile 1 head and the connecting material 2 are buried is shown schematically. Various types of slope lining 8 can be selected depending on the surrounding environment and the strength of the slope (the degree of fear of collapse). For example, there is a high possibility of collapse (the slope ground is fragile or the slope is steep). In some cases, the lining 8 is laid by spraying strong mortar or concrete. When these mortars and concrete sprays are constructed, they are usually sprayed after a lath wire mesh (not shown) is stretched, and in this case, the connecting material for the spiral pile is not necessarily required.

また、図示は省略するが、上記のラセン杭を法面に施工した後、ラセン杭1をアンカー材として、雑木や雑草の繁茂抑制を目的とした金属、鉱物、化学性等の素材や有機性素材例えばヤシ繊維、ウッドチップ集成材等のマットや木材チップ等を法面に固定することにより、法面の表面侵食の防止を図ると共に法面の草刈作業等を削減する。   In addition, although illustration is omitted, after the above-described spiral pile is constructed on the slope, the pile 1 is used as an anchor material, and materials such as metals, minerals, and chemicals for the purpose of suppressing the growth of miscellaneous trees and weeds, and organic By fixing materials such as mats such as palm fiber and wood chip laminated wood, wood chips, etc. to the slope, it is possible to prevent the surface erosion of the slope and to reduce the grass cutting work of the slope.

また、法面の景観を重視する場合には、上記のラセン杭1を法面に打込んで法面の補強を実施したのちに、法覆工8として、各種の緑化工を敷設することもできる。例えば厚層基材吹付け工法とか、ネットなどに植物種子、肥料等を貼着した緑化資材などを張付けるなどの緑化工を敷設することが有効である。
以上のような法覆工、特に緑化工により、ラセン杭や連結材を被覆してしまうので、法面のメンテナンス、即ち草刈などをおこなう場合、ラセン杭等どの突出物が存在せず、刈払い機等の刃を損傷することがなく、メンテナンス作業が安全である。
In addition, when emphasizing the landscape of the slope, after driving the above-mentioned spiral pile 1 into the slope and reinforcing the slope, various greening works may be laid as the slope lining 8 it can. For example, it is effective to lay a greening method such as thick layer base material spraying method or attaching a greening material with plant seeds, fertilizer or the like attached to a net or the like.
As the above method, especially greening, covers the spiral pile and connecting material, when performing slope maintenance, that is, mowing, there is no protrusion such as the spiral pile, and the cutting is done. Maintenance work is safe without damaging the blades of the machine.

上記実施例で説明をしたラセン杭の形状の他の実施例として、図2(c)に示すように、ラセン形状の羽を持つオーガ−ロッドも本発明のラセン杭として使用でき、この形状とした場合には打ち込みに際して機械施工が可能で、より短時間で、より深度のラセン杭の施工が可能となる。   As another example of the shape of the spiral pile described in the above embodiment, as shown in FIG. 2 (c), an auger rod having a spiral shaped wing can also be used as the spiral pile of the present invention. In this case, it is possible to perform mechanical construction when driving, and it is possible to construct a helical pile with a greater depth in a shorter time.

ラセン杭の頭部の形状として、上記実施例の他に、ラセン形状をそのまま頭部とするもの、L型に曲げ加工したもの、あるいはボルト加工したり、溶接によりねじ込み打込み施工治具の取りつけたもの、その他直線のまま無処理としたものなど各種の形状が実施でき、これらの形状に合わせ、上記のラセン杭の頭部に形成した湾曲部にパイプを差し込んで回転させてラセン杭を打込む方法の他に、可搬式ドリル等の回転機械類を使用して打込むことで実施できる。このような方法を採用すれば、施工のスピード化が図れると共に、より硬質地盤へもラセン杭を打込むことが可能となり、ラセン杭の効果をより確実に発揮させることができる。   As the shape of the head of the spiral pile, in addition to the above example, the spiral shape as it is as the head, the one bent into an L shape, or bolted or screwed in by a welding tool Various shapes such as straight and unprocessed can be implemented, and in accordance with these shapes, the pipe is inserted into the curved part formed on the head of the above-mentioned spiral pile and rotated to drive the spiral pile In addition to the method, it can be carried out by driving using a rotary machine such as a portable drill. If such a method is adopted, the speed of construction can be increased, and the spiral pile can be driven into harder ground, and the effect of the spiral pile can be exhibited more reliably.

ラセン杭の長さについても上記の約60cmの長さの他、50cm以上2m未満の長さが適応でき、施工性とラセン杭の地盤の有効抑止深さから、好ましくは80cm以上1.5m程度が望ましい。   As for the length of the helical pile, in addition to the length of about 60 cm, a length of 50 cm or more and less than 2 m can be applied. From the workability and effective suppression depth of the ground of the pile, preferably about 80 cm to 1.5 m. Is desirable.

また、ラセン杭の連結方法も、上記実施例ように横方向の連結の他に、縦方向、斜め方向或いはこれらを組み合わせた形状も実施でき、こうすることでよりラセン杭の連結性を確実にすることで法面の補強効果を増強することができる。
連結材についても、上記のアルミ管やステンレス管以外に金属製または樹脂製の棒材、管材又は線材(撚り線等も含む)などが使用でき、施工現場の条件、例えば、法面長、法面勾配、地盤の硬さ等により現場条件に合う形状を適宜選択することができる。
In addition to the lateral connection as in the above embodiment, the spiral pile can be connected in the vertical direction, the diagonal direction, or a combination of these, thereby ensuring the connectivity of the spiral pile more reliably. By doing so, the reinforcing effect of the slope can be enhanced.
As for the connecting material, metal or resin rods, pipes or wires (including stranded wires), etc. can be used in addition to the above aluminum tubes and stainless steel tubes. A shape suitable for the site conditions can be selected as appropriate depending on the surface gradient, the hardness of the ground, and the like.

本実施形態の法面安定化工法を説明する概念図である。It is a conceptual diagram explaining the slope stabilization method of this embodiment. ラセン杭を説明する図である。It is a figure explaining a spiral pile. ラセン杭頭部の連結材固定方法を説明する図である。It is a figure explaining the connection material fixing method of a spiral pile head. 連結材同士の連結方法を説明する図である。It is a figure explaining the connection method of connection materials. ラセン杭の施工方法を説明する図である。It is a figure explaining the construction method of a spiral pile. 施工例を説明する正面図である。It is a front view explaining a construction example. 法覆工を敷設した法面の断面図である。It is sectional drawing of the slope which laid the law lining.

符号の説明Explanation of symbols

1 ラセン杭
2 連結材
3 表層部
4 深層部
5 固定バンド
6 取り付け管
7 接着剤
8 法覆工
DESCRIPTION OF SYMBOLS 1 Spiral pile 2 Connecting material 3 Surface layer part 4 Deep layer part 5 Fixed band 6 Attachment pipe 7 Adhesive 8 Method lining

Claims (3)

法面に所定間隔で複数のラセン杭を打ち込むことにより、法面を補強することを特徴とする法面安定化工法。   A slope stabilization method characterized by reinforcing the slope by driving a plurality of helical piles into the slope at predetermined intervals. 法面に所定間隔で複数のラセン杭を等高線状に打ち込むとともに、各ラセン杭の頭部を連結材で等高線状、法長方向或いは斜め方向に連結して法面を補強することを特徴とする法面安定化工法。   A plurality of helical piles are driven into the contour at predetermined intervals, and the head of each spiral pile is connected with a connecting material in the contour, longitudinal direction or diagonal direction to reinforce the slope. Slope stabilization method. 請求項1、2記載のいずれかの法面安定化工法が施工された法面上に、法覆工が敷設されたことを特徴とする法面安定化工法。   A slope stabilization method, wherein a slope lining is laid on the slope where the slope stabilization method according to any one of claims 1 and 2 is applied.
JP2003329701A 2003-09-22 2003-09-22 Slope stabilization method Pending JP2005097840A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003329701A JP2005097840A (en) 2003-09-22 2003-09-22 Slope stabilization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003329701A JP2005097840A (en) 2003-09-22 2003-09-22 Slope stabilization method

Publications (1)

Publication Number Publication Date
JP2005097840A true JP2005097840A (en) 2005-04-14

Family

ID=34458880

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003329701A Pending JP2005097840A (en) 2003-09-22 2003-09-22 Slope stabilization method

Country Status (1)

Country Link
JP (1) JP2005097840A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013039054A (en) * 2011-08-12 2013-02-28 East Japan Railway Co Screw pile, method for driving the same, and construction method of weed-proof sheet
GB2541144A (en) * 2014-08-06 2017-02-08 Gripple Ltd Securing device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013039054A (en) * 2011-08-12 2013-02-28 East Japan Railway Co Screw pile, method for driving the same, and construction method of weed-proof sheet
GB2541144A (en) * 2014-08-06 2017-02-08 Gripple Ltd Securing device
GB2530866B (en) * 2014-08-06 2017-05-03 Gripple Ltd Securing device
JP2017524085A (en) * 2014-08-06 2017-08-24 グリップル・リミテッドGripple Limited Ground anchor
GB2541144B (en) * 2014-08-06 2018-04-04 Gripple Ltd A Drive Transmission Device for a Securing Device
US10167605B2 (en) 2014-08-06 2019-01-01 Gripple Limited Securing device

Similar Documents

Publication Publication Date Title
KR101595306B1 (en) Mechanical fixing earth anchor by rotation and method for constructing this same
JP5150596B2 (en) Anchor device and anchor construction method
JP6284796B2 (en) Slope stabilization method for soil and earthquake resistance
JP2005097840A (en) Slope stabilization method
KR20120102480A (en) Phc pile with improved end bearing capacity and piling method of phc pile using the same
JP4690781B2 (en) Rock fall prevention fence
KR20110038886A (en) Retaining wall connection structure
JP6322490B2 (en) Pile head treatment method for severing material and site-built pile
JP2002047650A (en) Set anchor body and executing method therefor
KR102503844B1 (en) Upper reinforcement support to increase horizontal force of foundation pile
JP4273991B2 (en) Construction method of composite pile foundation
JP2001207437A (en) Reinforcement method of ground below existing structure
CN212129170U (en) Steel flower tube for soft side slope
JP2013241733A (en) Anchor for slope face protection
JP2009041285A (en) Fixing device for car port roof bearing pole
JP2000034731A (en) Wood fence
CN1322273A (en) Jacket tube for drilling and anchoring device
JPH04194227A (en) Earth reinforcing method with tubular reinforcement
JP4240468B2 (en) Slope stabilization method
KR100697001B1 (en) Multi way protectors
RU2587399C1 (en) Screw pile
JP5504463B2 (en) Reinforcing method of concrete frame
JP4354373B2 (en) Construction method for inclined concrete piles
KR20110136126A (en) Hot rolled steel sheet structure and manufacturing method
JP2001107363A (en) Anchor for preventing slope collapse and slop collapse prevention method using the anchor

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20060823

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060825

A521 Written amendment

Effective date: 20060824

Free format text: JAPANESE INTERMEDIATE CODE: A821

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080625

A131 Notification of reasons for refusal

Effective date: 20080708

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080905

A02 Decision of refusal

Effective date: 20090224

Free format text: JAPANESE INTERMEDIATE CODE: A02