JP2002146720A - Column and beam joint structure - Google Patents
Column and beam joint structureInfo
- Publication number
- JP2002146720A JP2002146720A JP2000346129A JP2000346129A JP2002146720A JP 2002146720 A JP2002146720 A JP 2002146720A JP 2000346129 A JP2000346129 A JP 2000346129A JP 2000346129 A JP2000346129 A JP 2000346129A JP 2002146720 A JP2002146720 A JP 2002146720A
- Authority
- JP
- Japan
- Prior art keywords
- column
- insertion hole
- joint structure
- insert
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は高速道路等に用いら
れる橋脚の柱と横梁の接合構造に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint structure between a pillar and a cross beam of a pier used on a highway or the like.
【0002】[0002]
【従来の技術】都市高速道路の建設においては、高速道
路の下の道路中央分離帯上に柱を構築する「T型鉄筋コ
ンクリート製橋脚」や、道路両側の歩道上に柱を構築す
る「鉄筋コンクリート製ラーメン橋脚」が多く建設され
ている。これらの鉄筋コンクリート製橋脚(以下、RC
橋脚)の断面構造を図7に示す。RC橋脚51は、図7
に示すように、鉄筋コンクリート製柱53(以下、RC
柱53)と、鉄筋コンクリート製横梁55(以下、RC
梁55)から形成されている。そして、これらRC柱5
3とRC梁55の接合は、縦横斜めに複雑に鉄筋57を
組み、型枠をセットしてコンクリートを打設することに
よって行っている。2. Description of the Related Art In the construction of an urban expressway, a "T-type reinforced concrete pier" for constructing a pillar on a median strip below a highway and a "reinforced concrete pier" for constructing a pillar on a sidewalk on both sides of the road are used. Many ramen piers have been constructed. These reinforced concrete piers (hereinafter referred to as RC
FIG. 7 shows a cross-sectional structure of the pier. The RC pier 51 is shown in FIG.
As shown in FIG.
Pillar 53) and reinforced concrete cross beam 55 (hereinafter, RC)
Beam 55). And these RC pillars 5
The joining of the RC beams 55 with the RC beams 55 is performed by assembling reinforcing bars 57 vertically and horizontally and diagonally, setting a formwork, and placing concrete.
【0003】[0003]
【発明が解決しようとする課題】都市高速道路の建設
は、下の道路の交通制限をしながら行われるため、でき
るだれ短工期化することが望まれている。しかしなが
ら、図7に示す従来のようなRC橋脚51のようにRC
柱53とRC梁55の接合を複雑な配筋とコンクリート
の打設によって行う場合には、鉄筋工、型枠工、および
支保工などの作業が必要となり、どうしても工期が長期
化するという問題がある。Since the construction of an urban expressway is performed while restricting traffic on a lower road, it is desired to shorten the construction period as much as possible. However, like the conventional RC pier 51 shown in FIG.
When joining the column 53 and the RC beam 55 by complicated reinforcing arrangement and concrete casting, work such as rebar work, formwork work, and shoring work is required, and there is a problem that the construction period is prolonged. is there.
【0004】本発明はかかる問題点を解決するためにな
されたものであり、都市高速道路建設の短工期化を図る
ことができる柱と梁の接合構造を提供することを目的と
している。The present invention has been made to solve such a problem, and an object of the present invention is to provide a joint structure between a column and a beam, which can shorten the construction period of an urban expressway.
【0005】[0005]
【課題を解決するための手段】本発明に係る柱と梁の接
合構造は、橋脚の柱と梁の接合構造において、内面に突
起を有する挿入孔を柱又は梁に設け、該挿入孔に挿入可
能な外面に突起を有する挿入体を梁又は柱に設け、該挿
入体を前記挿入孔に挿入し、前記挿入孔と前記挿入体の
隙間に充填材を注入することにより柱と梁を接合するも
のである。According to the joint structure of a pillar and a beam according to the present invention, in a joint structure of a pillar and a beam of a pier, an insertion hole having a protrusion on an inner surface is provided in the pillar or the beam, and the insertion hole is inserted into the insertion hole. An insert having a protrusion on a possible outer surface is provided on a beam or a column, the insert is inserted into the insertion hole, and a filler is injected into a gap between the insertion hole and the insert to join the column and the beam. Things.
【0006】また、挿入孔及び挿入体を複数設けたもの
である。Further, a plurality of insertion holes and insertion bodies are provided.
【0007】また、柱と梁の接合部に位置決め手段を設
けたものである。Further, a positioning means is provided at a joint between the column and the beam.
【0008】また、梁を複数に分割したものである。In addition, the beam is divided into a plurality of beams.
【0009】また、挿入孔を内面リブ付き鋼管で構成
し、挿入体を外面リブ付き鋼管で構成したものである。Further, the insertion hole is constituted by a steel pipe having an inner rib, and the insert is constituted by a steel pipe having an outer rib.
【0010】[0010]
【発明の実施の形態】実施の形態1.図1は本発明の一
実施の形態の説明図である。本実施の形態に係るRC柱
1とRC梁11の接合構造においては、接合部となるR
C柱1の上端部に内面リブ付き鋼管3を埋設している。
内面リブ付き鋼管3の所定の深さ位置にはダイヤフラム
5を設置している。また、RC柱1の側壁におけるダイ
ヤフラム設置位置とほぼ同位置には、内面リブ付き鋼管
3の内面に貫通するモルタル注入用の注入孔7が設けら
れている。さらに、RC柱1の上端近傍にはモルタル注
入を確認するための確認孔9が複数設けられている。DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiment 1 FIG. 1 is an explanatory diagram of one embodiment of the present invention. In the joint structure of RC column 1 and RC beam 11 according to the present embodiment, R
A steel pipe 3 with an inner rib is embedded at the upper end of the C column 1.
A diaphragm 5 is provided at a predetermined depth position in the steel pipe 3 with an inner rib. Further, an injection hole 7 for mortar injection penetrating through the inner surface of the steel pipe 3 with the inner surface rib is provided substantially at the same position as the diaphragm on the side wall of the RC column 1. Further, a plurality of confirmation holes 9 for confirming mortar injection are provided near the upper end of the RC column 1.
【0011】一方、RC梁11の下部ほぼ中央部にはR
C柱1の外形と同形の凸部13が形成されている。そし
て、この凸部13には、RC柱1に設けた内面リブ付き
鋼管3に挿入可能な外面リブ付き鋼管15が設置されて
いる。On the other hand, R
A projection 13 having the same shape as the outer shape of the C pillar 1 is formed. The convex portion 13 is provided with an outer ribbed steel pipe 15 that can be inserted into the inner ribbed steel pipe 3 provided on the RC column 1.
【0012】上記のような構成のRC柱1とRC梁11
の接合作業工程について説明する。RC柱1を設置後、
RC梁11をクレーンで吊り込み、RC梁11側の外面
リブ付鋼管15をRC柱1に設けた内面リブ付鋼管3に
挿入するようにしてRC梁11をRC柱1の上方から設
置する。そして、図2に示すように、RC柱1の形状と
RC梁11の凸部13の形状が合うように位置合わせを
した後、注入孔7からモルタルを注入する。そして確認
孔9からモルタルがあふれ出したら注入をやめる。この
とき注入モルタルはダイヤフラム5によってせき止めら
れるので、内面リブ付き鋼管3の下部に落下することは
ない。モルタル注入完了後、モルタルの硬化により、R
C梁11とRC柱1はモルタルを介して強固に接合され
る。The RC column 1 and the RC beam 11 having the above-described configuration.
Will be described. After installing RC pillar 1,
The RC beam 11 is suspended by a crane, and the RC beam 11 is installed from above the RC column 1 such that the steel tube 15 with the external rib on the RC beam 11 side is inserted into the steel tube 3 with the internal rib provided on the RC column 1. Then, as shown in FIG. 2, the mortar is injected from the injection hole 7 after the positioning is performed so that the shape of the RC column 1 and the shape of the convex portion 13 of the RC beam 11 match. When the mortar overflows from the confirmation hole 9, the injection is stopped. At this time, the injected mortar is blocked by the diaphragm 5 and does not fall to the lower part of the steel pipe 3 with the inner surface rib. After the mortar injection is completed, the mortar hardens,
The C beam 11 and the RC column 1 are firmly joined via a mortar.
【0013】以上のように構成された本実施の形態にお
いては、地震時にRC梁11に作用する慣性力は、外面
リブ付鋼管15に伝達され、リブとモルタルとの付着力
により内面リブ付鋼管3を介してRC柱1に伝達される
構造となっている。In the present embodiment configured as described above, the inertial force acting on the RC beam 11 during an earthquake is transmitted to the outer ribbed steel pipe 15, and the inner ribbed steel pipe is attached by the adhesive force between the rib and the mortar. 3 to the RC column 1.
【0014】以上のように本実施の形態によれば、複雑
な鉄筋工、型枠工、および支保工などの作業を低減する
ことが可能となり、ごく短期間でのRC柱1とRC梁1
1の接合が可能となる。As described above, according to the present embodiment, it is possible to reduce the work such as complicated rebar work, formwork work, and support work, and the RC column 1 and the RC beam 1 in a very short period of time.
1 can be joined.
【0015】なお、この種の橋脚の建設においては、R
C梁11上に桁が設置されるため、RC梁11の天場の
高さ精度が要求される。この点、本発明による接合構造
によれば、RC柱1の上面とRC梁11の凸部13の間
にスペーサを挿入することによってRC梁11の天場の
高さの微調整が可能になる。In the construction of this type of pier, R
Since the girder is installed on the C beam 11, the height accuracy of the RC beam 11 at the ceiling is required. In this regard, according to the joint structure of the present invention, the height of the RC beam 11 can be finely adjusted by inserting a spacer between the upper surface of the RC column 1 and the convex portion 13 of the RC beam 11. .
【0016】実施の形態2.図3は本発明の他の実施の
形態の説明図である。本実施の形態においては、RC梁
11の凸部13の下端縁にキー17を形成し、RC柱1
の上端縁にキー17が挿入可能なキー溝19を形成した
ものである。このようにキー17及びキー溝19を設け
ることにより、RC梁11とRC柱1の接合時にその位
置決めを容易かつ確実に行うことが可能となる。Embodiment 2 FIG. 3 is an explanatory diagram of another embodiment of the present invention. In the present embodiment, a key 17 is formed at the lower end edge of the convex portion 13 of the RC beam 11, and the RC column 1
A key groove 19 into which the key 17 can be inserted is formed at the upper end edge of the key. By providing the key 17 and the key groove 19 in this manner, it is possible to easily and surely position the RC beam 11 and the RC column 1 at the time of joining.
【0017】なお、キー17及びキー溝19に代えて、
図4に示すように、凸部13には下方に延出するガイド
板21を設け、RC柱1の上端部にはガイド板21が挿
入可能なガイド孔23を設けるようにしてもよい。In place of the key 17 and the key groove 19,
As shown in FIG. 4, a guide plate 21 extending downward may be provided on the convex portion 13, and a guide hole 23 into which the guide plate 21 can be inserted may be provided on the upper end of the RC column 1.
【0018】実施の形態3.図5は本発明の他の実施の
形態の説明図である。本実施の形態においては、RC柱
1側に4本の内面リブ付き鋼管3を埋設し、RC梁11
側にもこれに対応して4本の外面リブ付き鋼管15を設
置したものである。このように複数のリブ付き鋼管3,
15で接合することによって、接合強度が増すと共に、
リブ付き鋼管相互の挿入が同時にRC柱1とRC梁11
の位置決めにもなり、別途位置決め手段を設ける必要が
なくなる。Embodiment 3 FIG. 5 is an explanatory diagram of another embodiment of the present invention. In the present embodiment, four steel pipes 3 with inner ribs are buried on the RC column 1 side, and RC beams 11
Correspondingly, four steel ribs 15 with external ribs are provided on the side. Thus, a plurality of ribbed steel pipes 3,
By joining at 15, the joining strength increases,
RC column 1 and RC beam 11 are inserted simultaneously into ribbed steel pipes
, And there is no need to provide a separate positioning means.
【0019】なお、このように複数のリブ付き鋼管3,
15で接合する場合には、図6に示すように、RC梁1
1をリブ付き鋼管15ごとに分割してもよい。このよう
に分割することにより、RC梁11の吊り込み時の1ピ
ースの重量を軽量化することができる。The plurality of ribbed steel pipes 3
In the case of joining at 15, as shown in FIG.
1 may be divided for each ribbed steel pipe 15. By dividing as described above, the weight of one piece when the RC beam 11 is suspended can be reduced.
【0020】また、上記の例ではリブ付き鋼管3,15
を4本設けた例を示したが、リブ付き鋼管の数はこれに
限られるものではなく、RC柱1の径、要求される接合
強度等によって適宜選択することができる。In the above example, the ribbed steel pipes 3, 15
Although the example in which four were provided was shown, the number of ribbed steel pipes is not limited to this, and can be appropriately selected depending on the diameter of the RC column 1, the required joining strength, and the like.
【0021】なお、本実施の形態3のように複数のリブ
付き鋼管3,15での接合は、RC柱断面が大きい場合
に特に有効である。The joining with the plurality of ribbed steel pipes 3 and 15 as in the third embodiment is particularly effective when the RC column section is large.
【0022】上記の実施の形態1〜3においては、柱と
梁共に鉄筋コンクリート製であるいわゆる鉄筋コンクリ
ート製橋脚を例に挙げたが、本発明はこれに限られるも
のではなく、鉄筋コンクリート製の柱に鋼製の梁を接合
するいわゆる複合橋脚も含むものである。また、実施の
形態1〜3においては、柱側に挿入孔を設け、梁側に挿
入体を設けた例を示したが、本発明はこれに限られるも
のではなく、柱側に挿入体を設け、梁側に挿入孔を設け
るものも含む。In the first to third embodiments, the so-called reinforced concrete pier, in which both the column and the beam are made of reinforced concrete, is taken as an example. However, the present invention is not limited to this. It also includes so-called composite piers that join steel beams. Further, in Embodiments 1 to 3, the example in which the insertion hole is provided on the pillar side and the insertion body is provided on the beam side has been described, but the present invention is not limited to this, and the insertion body is provided on the pillar side. And those having an insertion hole on the beam side.
【0023】さらに、実施の形態1〜3においては、挿
入孔としてRC柱1の上端部に埋設した内面リブ付き鋼
管3を示し、挿入体としてRC梁11の凸部13に設け
た外面リブ付き鋼管15を示したが、本発明はこれに限
られるものではなく、挿入孔をコンクリートで形成し
て、挿入体として鋼管と同程度の強度を有する部材で形
成してもよい。Further, in the first to third embodiments, the steel pipe 3 with the inner ribs buried at the upper end of the RC column 1 is shown as the insertion hole, and the steel pipe 3 with the outer ribs provided on the projection 13 of the RC beam 11 as the insert. Although the steel pipe 15 has been described, the present invention is not limited to this, and the insertion hole may be formed of concrete, and the insert may be formed of a member having the same strength as the steel pipe.
【0024】また、上記の実施の形態1〜3において
は、充填材としてモルタルを注入する例を示したが、モ
ルタルの他、例えば樹脂などでもよい。要はリブ付き鋼
管との付着力によって応力伝達できるものであればよ
い。Further, in the first to third embodiments, the example in which mortar is injected as a filler has been described. However, in addition to mortar, for example, resin may be used. In short, any material can be used as long as stress can be transmitted by the adhesive force with the ribbed steel pipe.
【0025】[0025]
【発明の効果】以上のように本発明によれば、内面に突
起を有する挿入孔を柱又は梁に設け、該挿入孔に挿入可
能な外面に突起を有する挿入体を梁又は柱に設け、該挿
入体を前記挿入孔に挿入し、前記挿入孔と前記挿入体の
隙間に充填材を注入するようにしたので、通常のRC構
造の場合と比較して、鉄筋工、型枠工などの作業を低減
することが可能となり、短工期化を図ることができる。
その結果、都市部の交通制限を最小限に抑えることがで
きる。As described above, according to the present invention, an insertion hole having a projection on the inner surface is provided in a column or a beam, and an insert having a projection on an outer surface insertable into the insertion hole is provided in the beam or the column. Since the insert is inserted into the insert hole and the filler is injected into the gap between the insert hole and the insert, compared with the case of a normal RC structure, a reinforcing work, a formwork, etc. The work can be reduced, and the construction period can be shortened.
As a result, traffic restrictions in urban areas can be minimized.
【図1】 本発明の実施の形態1の各構成要素の説明図
である。FIG. 1 is an explanatory diagram of each component according to a first embodiment of the present invention.
【図2】 本発明の実施の形態1の組立後の状態の説明
図である。FIG. 2 is an explanatory diagram of a state after assembly according to the first embodiment of the present invention.
【図3】 本発明の実施の形態2の説明図である。FIG. 3 is an explanatory diagram of Embodiment 2 of the present invention.
【図4】 本発明の実施の形態2における他の態様の説
明図である。FIG. 4 is an explanatory diagram of another mode according to the second embodiment of the present invention.
【図5】 本発明の実施の形態3の説明図である。FIG. 5 is an explanatory diagram of a third embodiment of the present invention.
【図6】 本発明の実施の形態3における他の態様の説
明図である。FIG. 6 is an explanatory diagram of another mode according to the third embodiment of the present invention.
【図7】 従来技術の説明図である。FIG. 7 is an explanatory diagram of a conventional technique.
1 柱 3 内面リブ付き鋼管 7 注入孔 11 梁 13 凸部 15 外面リブ付き鋼管 DESCRIPTION OF SYMBOLS 1 Column 3 Steel pipe with internal rib 7 Injection hole 11 Beam 13 Convex part 15 Steel pipe with external rib
───────────────────────────────────────────────────── フロントページの続き Fターム(参考) 2D059 AA03 GG55 2E125 AA04 AA14 AA44 AB12 AC06 AC14 AG03 AG13 AG22 AG32 AG48 BA03 BB08 BB35 BC08 BC09 BD01 BE07 BF04 BF08 CA79 CA82 EA33 ──────────────────────────────────────────────────続 き Continued on the front page F term (reference) 2D059 AA03 GG55 2E125 AA04 AA14 AA44 AB12 AC06 AC14 AG03 AG13 AG22 AG32 AG48 BA03 BB08 BB35 BC08 BC09 BD01 BE07 BF04 BF08 CA79 CA82 EA33
Claims (5)
に突起を有する挿入孔を柱又は梁に設け、該挿入孔に挿
入可能な外面に突起を有する挿入体を梁又は柱に設け、
該挿入体を前記挿入孔に挿入し、前記挿入孔と前記挿入
体の隙間に充填材を注入することにより柱と梁を接合す
ることを特徴とする柱と梁の接合構造。1. In a joint structure of a pillar and a beam of a pier, an insertion hole having a projection on an inner surface is provided in the column or the beam, and an insert having a projection on an outer surface capable of being inserted into the insertion hole is provided in the beam or the column.
A joint structure between a column and a beam, wherein the column and the beam are joined by inserting the insert into the insert hole and injecting a filler into a gap between the insert hole and the insert.
徴とする請求項1記載の柱と梁の接合構造。2. The joint structure between a column and a beam according to claim 1, wherein a plurality of insertion holes and inserts are provided.
ことを特徴とする請求項1又は2記載の柱と梁の接合構
造。3. The joint structure between a column and a beam according to claim 1, wherein positioning means is provided at a joint between the column and the beam.
求項2又は3記載の柱と梁の接合構造。4. A joint structure between a column and a beam according to claim 2, wherein the beam is divided into a plurality of beams.
入体を外面リブ付き鋼管で構成したことを特徴とする請
求項1〜4のいずれかに記載の柱と梁の接合構造。5. The joint structure between a column and a beam according to claim 1, wherein the insertion hole is formed of a steel pipe with an internal rib, and the insert is formed of a steel pipe with an external rib.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000346129A JP2002146720A (en) | 2000-11-14 | 2000-11-14 | Column and beam joint structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000346129A JP2002146720A (en) | 2000-11-14 | 2000-11-14 | Column and beam joint structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2002146720A true JP2002146720A (en) | 2002-05-22 |
Family
ID=18820047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000346129A Pending JP2002146720A (en) | 2000-11-14 | 2000-11-14 | Column and beam joint structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2002146720A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020065413A (en) * | 2002-06-15 | 2002-08-13 | 김태균 | Pier omitted |
JP2012144880A (en) * | 2011-01-11 | 2012-08-02 | Kajima Corp | Junction structure of beam member and column member in precast concrete structure frame |
CN110485264A (en) * | 2019-08-21 | 2019-11-22 | 保利长大工程有限公司 | A kind of center pier great cantilever bent cap and its construction method |
CN110725400A (en) * | 2019-10-24 | 2020-01-24 | 王明明 | Connecting structure and method for constructional engineering steel structure and main body structure |
CN112030724A (en) * | 2020-08-10 | 2020-12-04 | 山东高速建设管理集团有限公司 | A two-way socket-type prefabricated assembled bridge pier and its construction method |
KR20230108564A (en) | 2022-01-11 | 2023-07-18 | 송성민 | Underground structure with precast concrete pile and composite diaphragm wall and the construction method thereof |
-
2000
- 2000-11-14 JP JP2000346129A patent/JP2002146720A/en active Pending
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020065413A (en) * | 2002-06-15 | 2002-08-13 | 김태균 | Pier omitted |
JP2012144880A (en) * | 2011-01-11 | 2012-08-02 | Kajima Corp | Junction structure of beam member and column member in precast concrete structure frame |
CN110485264A (en) * | 2019-08-21 | 2019-11-22 | 保利长大工程有限公司 | A kind of center pier great cantilever bent cap and its construction method |
CN110485264B (en) * | 2019-08-21 | 2020-06-02 | 保利长大工程有限公司 | Construction method of central pier large cantilever cover beam |
US10914043B1 (en) | 2019-08-21 | 2021-02-09 | Poly Changda Engineering Co., Ltd. | Construction method for a cantilever beam on a central pier |
CN110725400A (en) * | 2019-10-24 | 2020-01-24 | 王明明 | Connecting structure and method for constructional engineering steel structure and main body structure |
CN110725400B (en) * | 2019-10-24 | 2020-11-10 | 王明明 | Connecting structure and method for constructional engineering steel structure and main body structure |
CN112030724A (en) * | 2020-08-10 | 2020-12-04 | 山东高速建设管理集团有限公司 | A two-way socket-type prefabricated assembled bridge pier and its construction method |
KR20230108564A (en) | 2022-01-11 | 2023-07-18 | 송성민 | Underground structure with precast concrete pile and composite diaphragm wall and the construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
JP2011144513A (en) | Joint of precast floor slab in bridge | |
JP2002146720A (en) | Column and beam joint structure | |
JPH07292783A (en) | Connective structure of prestressed concrete members | |
JP3336295B2 (en) | Joining method and joining structure of precast reinforced concrete shear walls | |
JPH0480444A (en) | Connection unit of reinforced concrete pole and steel framed beam | |
JP2005330758A (en) | Additional reinforced wall method and additional reinforced wall structure of existing concrete wall | |
JP3851563B2 (en) | Frame reinforcement structure and its construction method | |
JPH03286029A (en) | Steel underground wall and its construction | |
JPH07252884A (en) | Construction method of frame with precast members | |
JP3776330B2 (en) | Seismic walls of existing buildings and construction methods | |
JP2003055961A (en) | Steel / concrete integrated underground wall and method of construction | |
JPH03199528A (en) | Steel frame foundation of construction | |
JP2001254519A (en) | Reinforcing construction and reinforcing method using steel plate with joint bar | |
JP2890983B2 (en) | Beam connection structure of PC column | |
JPH03144041A (en) | Bonding method of precast concrete member | |
JPH11181807A (en) | Construction method for underground story | |
JPH09273245A (en) | Block joint, grooved hollow block and block base | |
JPH07292858A (en) | Structure for connecting pc member | |
JPH04111813A (en) | Retaining wall structure and its construction | |
JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
JPH0754355A (en) | Foundation for small-scale building | |
CN119221615A (en) | Joint connection structure of precast concrete components | |
JPH0350846B2 (en) | ||
JPH11172689A (en) | Anchoring method of leg section of steel-framed column |