[go: up one dir, main page]

JP2001173269A - Construction method of seismic isolation building - Google Patents

Construction method of seismic isolation building

Info

Publication number
JP2001173269A
JP2001173269A JP35505899A JP35505899A JP2001173269A JP 2001173269 A JP2001173269 A JP 2001173269A JP 35505899 A JP35505899 A JP 35505899A JP 35505899 A JP35505899 A JP 35505899A JP 2001173269 A JP2001173269 A JP 2001173269A
Authority
JP
Japan
Prior art keywords
seismic isolation
pillar
building
concrete
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP35505899A
Other languages
Japanese (ja)
Inventor
Mamoru Yoshida
守 吉田
Hidemi Kobayashi
秀実 小林
Hideo Uchimoto
英雄 内本
Katsutoshi Suzuki
勝年 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Takenaka Komuten Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Takenaka Komuten Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Takenaka Komuten Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP35505899A priority Critical patent/JP2001173269A/en
Publication of JP2001173269A publication Critical patent/JP2001173269A/en
Pending legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

(57)【要約】 【課題】 特に、逆打ち工法を利用して地下に免震層を
有する建物を構築する場合に、工期やコストの面で有利
な免震建物の構築方法を提供する。 【解決手段】 免震建物の下層部を構成する柱として、
構真柱16を、その上端が上層部13の地上部にまで到
達するように設置するとともに、構真柱16により、上
層部13を支持させ、下層部14側から上層部13を仮
受けする仮受け部材を設け、構真柱16のうち、免震層
12内に位置する部分を撤去して、そこに免震装置11
を介装し、しかる後に、仮受け部材を撤去する構成にお
いて、構真柱16を設置する際には、免震層12内に位
置する部分の充填コンクリートCの径寸法を、鋼管2の
内径寸法よりも小に形成する。
(57) [Summary] [PROBLEMS] To provide a method of constructing a base-isolated building which is advantageous in terms of construction period and cost, particularly when building a building having a base-isolated layer underground by using a reverse construction method. SOLUTION: As a pillar constituting the lower part of a base-isolated building,
The trussed pillar 16 is installed so that the upper end thereof reaches the above-ground part of the upper layer 13, and the trussed pillar 16 supports the upper layer 13 and temporarily receives the upper layer 13 from the lower layer 14 side. A temporary receiving member is provided, and a portion of the truss pillar 16 located in the seismic isolation layer 12 is removed.
In the configuration in which the temporary receiving member is removed after that, when the straight pillar 16 is installed, the diameter of the filled concrete C in the portion located in the seismic isolation layer 12 is determined by the inner diameter of the steel pipe 2. Form smaller than the dimensions.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、免震建物を構築す
るための方法に関するものである。
TECHNICAL FIELD The present invention relates to a method for constructing a base-isolated building.

【0002】[0002]

【従来の技術】周知のように、建物の基礎や下層部と上
層部との間に免震装置を介装することにより免震層を形
成し、この免震層により、上層部と地盤とを絶縁して、
建物の振動応答の低減を図る免震建物が各種実現してい
る。このような免震建物は、建物の振動応答を大幅に低
減することのできる優れた効果を有するために、その適
用範囲も徐々に広がりつつあり、近年においては、地下
階の免震化を図るために、建物の地下に免震装置を配置
する例も見られるようになっている。
2. Description of the Related Art As is well known, a seismic isolation layer is formed by interposing a seismic isolation device between a foundation of a building and a lower part and an upper part, and the upper part and the ground are formed by the seismic isolation layer. Insulate
Various seismic isolation buildings have been realized to reduce the vibration response of buildings. Such seismic isolation buildings have an excellent effect that can greatly reduce the vibration response of the building, so their application range is gradually expanding, and in recent years, basement floors are being seismically isolated. For this reason, there are cases where seismic isolation devices are installed under the building.

【0003】ところで、上述のように、免震建物は、基
礎または下層部上に免震層を介して上層部が支持された
構成となっていることから、その構築にあたっては、基
礎または下層部を先行して構築し、その後に、基礎また
は下層部上に免震装置を配置し、この免震装置上に上層
部を構築する手法が採用されてきた。
By the way, as described above, a base-isolated building has a structure in which an upper part is supported on a foundation or a lower part via a seismic isolation layer. Has been adopted in advance, and thereafter, a method of arranging a seismic isolation device on a foundation or a lower layer portion and constructing an upper layer portion on the seismic isolation device has been adopted.

【0004】しかしながら、上記の手法によれば、基礎
または下層部を上層部に先行して構築し、順次、施工を
行っていくことが必要であった。したがって、特に免震
装置が地下階に配置される場合においては、地下に位置
する躯体の工事を、免震装置より下方の部分と、免震装
置より上方の部分とに分割して行わなければならず、一
般の建物に比較して工期が長期化するとともに、施工コ
ストも嵩むものとなっていた。
However, according to the above-mentioned method, it is necessary to construct a foundation or a lower layer portion in advance of an upper layer portion and to sequentially perform construction. Therefore, especially when the seismic isolation device is located on the basement floor, the construction of the skeleton located underground must be divided into a part below the seismic isolation device and a part above the seismic isolation device. However, the construction period is longer than that of a general building, and the construction cost is also increased.

【0005】そこで、免震層が地下にある場合でも、山
留め等のコスト削減および工期の短縮化に効果的な逆打
ち工法を適用して免震建物の構築を行うことが提案され
ている。この場合、具体的な施工方法としては、例え
ば、以下のようなものが考えられる。すなわち、建物躯
体の地上部を、基礎杭から構真柱により直接支持しつつ
構築し、同時に、地下部を逆打ち工法で構築し、さら
に、免震層では、下層部側から上層部を仮受けしつつ、
免震層内に位置する構真柱を撤去し、しかる後に、上層
部と下層部との間に免震装置を介装して免震層を形成す
るとともに、仮受け治具を撤去する。
[0005] Therefore, it has been proposed to construct a base-isolated building by applying a reverse hitting method which is effective for cost reduction and shortening of the construction period even when the base-isolated layer is underground. In this case, as a specific construction method, for example, the following method can be considered. In other words, the above-ground part of the building frame is constructed while being supported directly from the foundation piles by timber columns, and at the same time, the underground part is constructed by the reverse striking method. While receiving
The trussed pillar located in the seismic isolation layer is removed, and then the seismic isolation device is interposed between the upper and lower layers to form the seismic isolation layer and the temporary receiving jig is removed.

【0006】このような工法を採用した場合、地上部を
構築しつつ、地下部および免震層を構築することができ
るため、工期を大幅に短縮することができる。また、従
来、根切りを行うにあたって設けられていた切り梁等の
支保工を不要とすることができるため、コストダウンを
図ることができる。
When such a construction method is adopted, the underground part and the seismic isolation layer can be constructed while the above-ground part is being constructed, so that the construction period can be greatly reduced. In addition, since it is not necessary to provide a support such as a cutting beam which is conventionally provided when performing root cutting, cost can be reduced.

【0007】[0007]

【発明が解決しようとする課題】上述の工法において
は、構真柱により、基礎杭側から建物躯体の地上部を支
持しておくこととなるために、構真柱に非常に大きな軸
力が作用する。このため、構真柱としては、図7に示す
ような、コンクリート充填鋼管柱1を採用することが望
ましい。
In the above-mentioned construction method, since the timber columns support the ground part of the building frame from the foundation pile side, a very large axial force is applied to the timber columns. Works. For this reason, it is desirable to adopt a concrete-filled steel pipe column 1 as shown in FIG.

【0008】このコンクリート充填鋼管柱1は、鋼管2
の内部にコンクリートCが充填されたものであり、コン
クリートCによって軸力を受け持つことができるととも
に、コンクリートCの周囲を鋼管2により拘束して、コ
ンクリートCの変形を防ぐことができることから、高度
な軸耐力が発揮可能である。
[0008] The concrete-filled steel pipe column 1 comprises a steel pipe 2
Is filled with concrete C, the concrete C can bear the axial force, and the periphery of the concrete C can be restrained by the steel pipe 2 to prevent the deformation of the concrete C. The shaft proof strength can be exhibited.

【0009】しかしながら、このようなコンクリート充
填鋼管柱1を採用した場合、構真柱の一部を撤去するこ
とが非常に困難となり、工期、コストの面で大きな影響
を及ぼすことが懸念される。
However, when such a concrete-filled steel pipe column 1 is employed, it is very difficult to remove a part of the straight pillar, and there is a concern that it will have a significant effect on the construction period and cost.

【0010】本発明は、上記事情に鑑みなされたもので
あり、特に、逆打ち工法を利用して地下に免震層を有す
る建物を構築する場合に、工期やコストの面で有利な免
震建物の構築方法を提供することを課題とする。
The present invention has been made in view of the above circumstances, and particularly when a building having a seismic isolation layer underground is constructed by using a reverse hitting method, the seismic isolation is advantageous in terms of the construction period and cost. It is an object to provide a building construction method.

【0011】[0011]

【課題を解決するための手段】上記課題を解決するため
に本発明においては、以下の手段を採用した。すなわ
ち、請求項1記載の免震建物の構築方法は、免震層を挟
んで上下に位置する上層部および下層部を備えた免震建
物の構築方法であって、前記下層部を構成する柱とし
て、コンクリート充填鋼管により形成された構真柱を、
その少なくとも上端が前記上層部の地上部にまで到達す
るように設置するとともに、該構真柱により、前記上層
部を支持させ、前記下層部側から前記上層部を仮受けす
る仮受け部材を設け、前記構真柱のうち、前記免震層内
に位置する部分を撤去して、そこに免震装置を介装し、
しかる後に、前記仮受け部材を撤去する構成となってお
り、前記構真柱を設置する際には、前記免震層内に位置
する部分の充填コンクリートの径寸法を、該構真柱の鋼
管の内径寸法よりも小に形成することを特徴としてい
る。
Means for Solving the Problems To solve the above problems, the present invention employs the following means. In other words, the method for constructing a base-isolated building according to claim 1 is a method for constructing a base-isolated building having an upper layer portion and a lower layer portion which are located vertically above and below a seismic isolation layer, wherein the pillars constituting the lower layer portion As a straight pillar formed by concrete filled steel pipe,
At least the upper end is installed so as to reach the above-ground portion of the upper layer portion, and by the straight pillar, the upper layer portion is supported, and a temporary receiving member for temporarily receiving the upper layer portion from the lower layer side is provided, Remove the part located in the seismic isolation layer of the framed pillar, interpose a seismic isolation device there,
Thereafter, the temporary receiving member is removed, and when installing the straight pillar, the diameter of the filled concrete located in the seismic isolation layer is set to the diameter of the steel pipe of the straight pillar. It is characterized in that it is formed smaller than the inner diameter.

【0012】このような構成とされるために、免震層内
においては、構真柱を構成する鋼管の内部に、内管を配
置し、この内管を型枠としてその内部にのみコンクリー
トを充填することにより、構真柱を形成することができ
る。この場合、免震装置を介装するにあたって、免震層
において撤去すべき充填コンクリートは内管部分のみと
なり、構真柱を構成する鋼管にコンクリートがまんべん
なく充填されている場合に比較して、撤去すべきコンク
リートの断面積を小さくすることができる。さらに、内
管は、外側の鋼管に比較してその肉厚を小さくすること
が可能であり、この場合切断を容易なものとすることが
できる。さらに、外側の鋼管とコンクリートとが付着し
てないために、外側の鋼管の切断も容易なものとするこ
とができる。
[0012] In order to have such a configuration, in the seismic isolation layer, the inner pipe is arranged inside the steel pipe constituting the straight pillar, and the inner pipe is used as a form, and concrete is formed only inside the steel pipe. By filling, a straight pillar can be formed. In this case, when installing the seismic isolation device, the only concrete to be removed in the seismic isolation layer is the inner pipe part, which is removed compared to the case where the steel pipes constituting the trussed pillars are evenly filled with concrete. The cross-sectional area of the concrete to be made can be reduced. Furthermore, the inner pipe can be made thinner than the outer steel pipe, and in this case, cutting can be made easier. Further, since the outer steel pipe and the concrete are not attached to each other, the outer steel pipe can be easily cut.

【0013】[0013]

【発明の実施の形態】以下、本発明の一実施の形態を、
図面に基づいて説明する。なお、以下、上記従来の技術
と共通する構成については、同一符号を付し、その説明
を省略する。図5は、本実施の形態における構築方法を
適用することにより構築される免震建物10の概略構成
を示す図である。この免震建物10は、免震装置11を
有する免震層12を挟んで、上下に上層部13および下
層部14が位置する構成とされている。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of the present invention will be described.
Description will be given based on the drawings. Hereinafter, the same components as those of the above-described conventional technology are denoted by the same reference numerals, and description thereof will be omitted. FIG. 5 is a diagram showing a schematic configuration of the base-isolated building 10 constructed by applying the construction method in the present embodiment. This seismic isolation building 10 is configured such that an upper layer portion 13 and a lower layer portion 14 are located vertically above and below a seismic isolation layer 12 having a seismic isolation device 11.

【0014】上層部13および下層部14を構成する柱
としては、下端16aが基礎杭15と一体化された構真
柱16が用いられている。この構真柱16には、図6に
示したコンクリート充填鋼管柱1と同様のコンクリート
充填鋼管柱が用いられている。また、構真柱16は、免
震装置11を挟んで上下に分断された構成となってい
る。
As the pillars constituting the upper layer portion 13 and the lower layer portion 14, a straight pillar 16 having a lower end 16a integrated with a foundation pile 15 is used. As the straight pillar 16, a concrete-filled steel pipe column similar to the concrete-filled steel pipe column 1 shown in FIG. 6 is used. Further, the trussed pillar 16 is configured to be vertically divided with the seismic isolation device 11 interposed therebetween.

【0015】次に、この免震建物10の構築方法につい
て図6および図1から4を参照して説明する。まず、図
6に示すように、地盤G内における免震建物10の設置
対象位置を囲むように山止め壁18,18を設け、山止
め壁18,18の内側の地盤G中に基礎杭15を設置す
る。さらに、基礎杭15の上部に連続させて構真柱16
を形成する。この場合、構真柱16を、その上端が上層
部13の地上部にまで到達するように形成しておく。
Next, a method of constructing the base-isolated building 10 will be described with reference to FIG. 6 and FIGS. First, as shown in FIG. 6, the retaining piles 18, 18 are provided so as to surround the installation target position of the base-isolated building 10 in the ground G, and the foundation pile 15 is provided in the ground G inside the retaining wall 18, 18. Is installed. Further, the column 16 is connected to the
To form In this case, the truss pillar 16 is formed so that the upper end thereof reaches the above-ground portion of the upper layer portion 13.

【0016】図1は、この場合に形成される構真柱16
の要部を拡大して示した図であり、また、図2は、図1
におけるI−I線矢視断面図である。この図に示すよう
に、免震層12内において、構真柱16は、鋼管2の内
側にさらに鋼管からなる内管17が配置された二重管構
造とされており、この内管17内にのみ充填コンクリー
トCが注入された構成となっている。これにより、免震
層12内に位置する部分の充填コンクリートCの径寸法
が、鋼管2の径寸法に比較して小となるように形成され
る。なお、内管17は、鋼管2に比較してその肉厚を薄
くしてある。
FIG. 1 shows a structure pillar 16 formed in this case.
FIG. 2 is an enlarged view of a main part of FIG.
FIG. 2 is a sectional view taken along line II in FIG. As shown in this figure, in the seismic isolation layer 12, the trussed pillar 16 has a double pipe structure in which an inner pipe 17 made of a steel pipe is further disposed inside the steel pipe 2. Is filled with concrete C only. Thereby, the diameter of the portion of the filled concrete C located in the seismic isolation layer 12 is formed to be smaller than the diameter of the steel pipe 2. The inner pipe 17 has a smaller thickness than the steel pipe 2.

【0017】続いて、地盤Gの表面と略同一位置に上層
部13の基礎スラブ19(図6参照)を形成する。この
際、基礎スラブ19は、構真柱16と一体化された状態
で形成される。これにより、構真柱16を介して基礎ス
ラブ19および上層部13が、基礎杭15側から支持さ
れる。
Subsequently, a base slab 19 (see FIG. 6) of the upper layer portion 13 is formed at substantially the same position as the surface of the ground G. At this time, the base slab 19 is formed in a state of being integrated with the straight pillar 16. Thereby, the foundation slab 19 and the upper layer part 13 are supported from the foundation pile 15 side via the straight pillar 16.

【0018】そして、基礎スラブ19の下方の地盤Gを
根切りする。この場合、基礎スラブ19を山止め壁1
8,18を保持するための土圧に対する支保工として利
用する。さらに、基礎スラブ19の下方の空間を一定の
深さ掘削したら、下層部14の上面14aを形成し、さ
らに、その下方を掘削しつつ、下層部14を地盤G中に
形成していく。これにより、図6に示したような構造が
形成される。
Then, the ground G below the foundation slab 19 is cut off. In this case, the foundation slab 19 is
It is used as a support against earth pressure to hold 8,18. Furthermore, when the space below the foundation slab 19 is excavated to a certain depth, the upper surface 14a of the lower layer portion 14 is formed, and the lower layer portion 14 is formed in the ground G while excavating below the lower portion. Thus, a structure as shown in FIG. 6 is formed.

【0019】一方、形成された下層部14の上面14a
と上層部13との間には、免震装置11を介装する。こ
れには、図3に示すように下層部14側から仮受け部材
22を用いて上層部13を仮受けしておき、この状態
で、構真柱16のうち、免震層12内に位置する部分を
切断撤去する。そして、撤去された部分に、図4に示す
ように免震装置11を配置するとともに、免震装置11
により分断された上下の構真柱16を接続し、さらに、
仮受け部材22を撤去する。これにより、免震層12の
構築が完了される。さらに、山止め壁18,18を撤去
することにより、図3に示したような構造が得られる。
On the other hand, the upper surface 14a of the formed lower layer portion 14
A seismic isolation device 11 is interposed between the upper layer 13 and the upper layer 13. For this purpose, as shown in FIG. 3, the upper layer portion 13 is temporarily received from the lower layer portion 14 side by using the temporary receiving member 22, and in this state, the upper portion 13 is positioned within the seismic isolation layer 12 of the truss pillar 16. Cut off the part to be removed. Then, the seismic isolation device 11 is disposed on the removed portion as shown in FIG.
Connect the upper and lower framed pillars 16 divided by
The temporary receiving member 22 is removed. Thereby, the construction of the seismic isolation layer 12 is completed. Further, by removing the retaining walls 18, 18, a structure as shown in FIG. 3 is obtained.

【0020】上述の免震建物10の構築方法において
は、構真柱16のうち、免震層12内に位置する部分に
おける充填コンクリートCの径寸法を、鋼管2の径寸法
に比較して小となるように形成したために、鋼管2内に
充填コンクリートCがくまなく充填されている場合に比
較して、撤去すべき充填コンクリートCの断面積を小さ
くすることができ、これにより充填コンクリートCの切
断撤去を容易なものとすることができる。また、内管1
7は、外側の鋼管2に比較してその肉厚が小さくされて
いるために、切断が容易である。また、鋼管2と充填コ
ンクリートCとが付着してないために、鋼管2の切断も
容易なものとすることができる。以上により、逆打ち工
法を利用して免震建物10を構築する場合において、免
震層12内の構真柱16の撤去を容易化して施工作業の
容易化を図り、工期の短縮化および施工コストの低減を
図ることが可能となる。
In the above-described method of constructing the base-isolated building 10, the diameter of the filled concrete C in the portion of the trussed pillar 16 located in the base-isolated layer 12 is smaller than the diameter of the steel pipe 2. As compared with the case where the filled concrete C is completely filled in the steel pipe 2, the cross-sectional area of the filled concrete C to be removed can be reduced. Cutting and removal can be facilitated. In addition, inner pipe 1
7 is easy to cut because its thickness is smaller than that of the outer steel pipe 2. Further, since the steel pipe 2 and the filled concrete C do not adhere to each other, the steel pipe 2 can be easily cut. As described above, in the case of constructing the base-isolated building 10 by using the reverse striking method, the removal of the timber columns 16 in the base-isolated layer 12 is facilitated to facilitate the construction work, and the construction period is shortened and the construction is completed. Costs can be reduced.

【0021】なお、上記実施の形態において、免震層1
2を、免震建物10の地下階のうちの任意の階に設置す
ることができる。また、上記実施の形態において用いら
れる内管17は、構真柱16の内部に上方から充填コン
クリートCを打設する際に、鋼管2内の底部にまでコン
クリートを充填させるために構真柱16の内部を上下に
連続するものであればよい。したがって内管17は、コ
ンクリートCの打設のための最小限の管径および肉厚と
することができ、これにより撤去を容易とすることがで
きる。また、材料としてはガス管等を適宜選択すること
ができる。
In the above embodiment, the seismic isolation layer 1
2 can be installed on any of the basement floors of the base-isolated building 10. The inner pipe 17 used in the above embodiment is used to fill concrete to the bottom of the steel pipe 2 when the concrete C is poured from above into the straight pillar 16. What is necessary is just to be what continues up and down inside the inside. Therefore, the inner pipe 17 can have a minimum pipe diameter and a minimum wall thickness for placing the concrete C, thereby facilitating removal. In addition, a gas pipe or the like can be appropriately selected as a material.

【0022】[0022]

【発明の効果】以上説明したように、本発明の免震建物
の構築方法によれば、構真柱のうち免震層内の部分にお
いて、充填コンクリートの径寸法が構真柱の鋼管の径寸
法に比較して小となるように形成されるために、撤去す
べき充填コンクリートの断面積を小さくすることができ
る。これにより、切断撤去作業の容易化を図ることがで
きる。また、構真柱のうち、撤去すべき部分において
は、鋼管と充填コンクリートとが付着していないため
に、鋼管の切断が容易となる。以上により、逆打ち工法
を利用して免震建物を構築する際において、施工作業の
容易化を図り、工期の短縮化および施工コストの低減を
図ることが可能となる。
As described above, according to the method of constructing a base-isolated building according to the present invention, the diameter of the concrete filled in the part of the trussed pillar in the seismic isolation layer is the diameter of the steel pipe of the trussed pillar. Since it is formed to be smaller than the dimensions, the cross-sectional area of the packed concrete to be removed can be reduced. Thereby, the cutting and removing operation can be facilitated. Moreover, since the steel pipe and the filled concrete do not adhere to the part to be removed, the steel pipe is easily cut. As described above, when constructing a seismically isolated building using the reverse hitting method, it is possible to facilitate the construction work, to shorten the construction period, and to reduce the construction cost.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の一実施の形態を模式的に示す図であ
って、免震建物を構築する際に用いられる構真柱の要部
拡大立断面図である。
FIG. 1 is a diagram schematically showing an embodiment of the present invention, and is an enlarged vertical sectional view of a main part of a timber column used when constructing a seismic isolation building.

【図2】 図1におけるI−I線矢視断面図である。FIG. 2 is a sectional view taken along line II in FIG.

【図3】 免震建物の上層部および下層部の間に免震装
置を介装するために、上層部を下層部から仮受けした際
の状況を示す立断面図である。
FIG. 3 is an elevational sectional view showing a situation in which an upper layer is temporarily received from a lower layer in order to interpose a seismic isolation device between an upper layer and a lower layer of a base-isolated building.

【図4】 図3に示した状態から上層部および下層部の
間に免震装置を介装した際の状況を示す立断面図であ
る。
4 is an elevational sectional view showing a situation when a seismic isolation device is interposed between an upper layer portion and a lower layer portion from the state shown in FIG. 3;

【図5】 本発明の免震建物の構築方法が適用された免
震建物の概略構成を示す立断面図である。
FIG. 5 is a vertical sectional view showing a schematic configuration of a base-isolated building to which the method of constructing a base-isolated building according to the present invention is applied.

【図6】 図5に示した免震建物を施工する際の状況を
示す立断面図である。
6 is an elevational sectional view showing a situation when the seismic isolation building shown in FIG. 5 is constructed.

【図7】 一般のコンクリート充填鋼管柱の平断面図で
ある。
FIG. 7 is a plan sectional view of a general concrete-filled steel pipe column.

【符号の説明】[Explanation of symbols]

2 鋼管 C 充填コンクリート 10 免震建物 11 免震装置 12 免震層 13 上層部 14 下層部 15 基礎杭 16 構真柱(コンクリート充填鋼管) 22 仮受け部材 2 Steel Pipe C Filled Concrete 10 Seismic Isolation Building 11 Seismic Isolation Device 12 Seismic Isolation Layer 13 Upper Layer 14 Lower Layer 15 Foundation Pile 16 Structural Pillar (Concrete Filled Steel Pipe) 22 Temporary Supporting Member

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小林 秀実 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 内本 英雄 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 鈴木 勝年 愛知県名古屋市中区錦1丁目18番22号 株 式会社竹中工務店名古屋支店内 ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Hidemi Kobayashi 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Hideo Uchimoto 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Katsunori Suzuki 1-18-22 Nishiki, Naka-ku, Nagoya City, Aichi Prefecture Takenaka Corporation Nagoya Branch

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 免震層を挟んで上下に位置する上層部お
よび下層部を備えた免震建物の構築方法であって、 前記下層部を構成する柱として、コンクリート充填鋼管
により形成された構真柱を、その少なくとも上端が前記
上層部の地上部にまで到達するように設置するととも
に、該構真柱により、前記上層部を支持させ、 前記下層部側から前記上層部を仮受けする仮受け部材を
設け、前記構真柱のうち、前記免震層内に位置する部分
を撤去して、そこに免震装置を介装し、しかる後に、前
記仮受け部材を撤去する構成となっており、 前記構真柱を設置する際には、前記免震層内に位置する
部分の充填コンクリートの径寸法を、該構真柱の鋼管の
内径寸法よりも小に形成することを特徴とする免震建物
の構築方法。
1. A method for constructing a base-isolated building having an upper part and a lower part located vertically above and below a seismic isolation layer, wherein the pillars constituting the lower part are formed of concrete-filled steel pipes. A true pillar is installed such that at least the upper end thereof reaches the above-ground part of the upper part, and the straight pillar supports the upper part, and temporarily receives the upper part from the lower part side. A member is provided, a part of the straight pillar positioned in the seismic isolation layer is removed, a seismic isolation device is interposed there, and then, the temporary receiving member is removed. The seismic isolation is characterized in that, when the straight pillar is installed, the diameter of the portion of the filled concrete located in the seismic isolation layer is smaller than the inner diameter of the steel pipe of the straight pillar. How to build a building.
JP35505899A 1999-12-14 1999-12-14 Construction method of seismic isolation building Pending JP2001173269A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35505899A JP2001173269A (en) 1999-12-14 1999-12-14 Construction method of seismic isolation building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35505899A JP2001173269A (en) 1999-12-14 1999-12-14 Construction method of seismic isolation building

Publications (1)

Publication Number Publication Date
JP2001173269A true JP2001173269A (en) 2001-06-26

Family

ID=18441699

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35505899A Pending JP2001173269A (en) 1999-12-14 1999-12-14 Construction method of seismic isolation building

Country Status (1)

Country Link
JP (1) JP2001173269A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011127367A (en) * 2009-12-18 2011-06-30 Takenaka Komuten Co Ltd Method for forming building
JP2012188817A (en) * 2011-03-09 2012-10-04 Taisei Corp Base-isolated building and construction method of base-isolated building
JP2014118756A (en) * 2012-12-17 2014-06-30 Taisei Corp Base-isolated building and construction method for the same
JP2016079596A (en) * 2014-10-14 2016-05-16 株式会社大林組 Construction method for building with underground base isolation layer, and building constructed by the construction method
JP2017218893A (en) * 2017-09-08 2017-12-14 株式会社竹中工務店 Attachment method of seismic isolator

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011127367A (en) * 2009-12-18 2011-06-30 Takenaka Komuten Co Ltd Method for forming building
JP2012188817A (en) * 2011-03-09 2012-10-04 Taisei Corp Base-isolated building and construction method of base-isolated building
JP2014118756A (en) * 2012-12-17 2014-06-30 Taisei Corp Base-isolated building and construction method for the same
JP2016079596A (en) * 2014-10-14 2016-05-16 株式会社大林組 Construction method for building with underground base isolation layer, and building constructed by the construction method
JP2017218893A (en) * 2017-09-08 2017-12-14 株式会社竹中工務店 Attachment method of seismic isolator

Similar Documents

Publication Publication Date Title
JP2001303599A (en) Demolition and construction methods of buildings and buildings
JP2023104993A (en) Foundation construction method of underground structure
JP4558145B2 (en) Seismic isolation method for existing buildings
JP2001311314A (en) Existing building seismic isolation method
JP2001173269A (en) Construction method of seismic isolation building
JPH102126A (en) Seismic isolated building
JP3290887B2 (en) Seismic isolation method for existing building with pile foundation
JP7182485B2 (en) building construction method
JPH1162248A (en) Construction method of building frame using existing outer wall
JP6988047B2 (en) How to reconstruct the underground skeleton
KR20110043976A (en) Inverse perforation using prefabricated columns and building structures thereby
JP2757026B2 (en) Reverse construction method of basement structure
JP2000291031A (en) Construction method of seismic isolation structure
JP2006002428A (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JPH1018322A (en) Construction method for base isolation building by reverse driving construction method
JP3882536B2 (en) Reconstruction method for existing buildings
JP3656452B2 (en) Seismic isolation method for existing buildings
JP5319445B2 (en) Building construction method
JPH09170338A (en) Existing building seismic isolation method
JP4971053B2 (en) Pile and column connection structure of steel building and its construction method
JPH09228398A (en) Construction method of high-rise building supported by piles
JP2016079651A (en) Support structure
JP7554720B2 (en) How to rebuild a building
JP2001159258A (en) Construction method of seismic isolation building
KR100593203B1 (en) Construction method of underground structure using deck support frame for side pressure support formation and deck support frame for side pressure support formation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20061115

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080630

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090818

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20091215