JP2000054502A JP10224584A JP22458498A JP2000054502A JP 2000054502 A JP2000054502 A JP 2000054502A JP 10224584 A JP10224584 A JP 10224584A JP 22458498 A JP22458498 A JP 22458498A JP 2000054502 A JP2000054502 A JP 2000054502A
Authority
JP
Japan
Prior art keywords
column
reinforcing column
reinforcing
ceiling
cut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP10224584A
Other languages
Japanese (ja)
Inventor
Yasuhiro Yoda
泰宏 余田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP10224584A priority Critical patent/JP2000054502A/en
Publication of JP2000054502A publication Critical patent/JP2000054502A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PROBLEM TO BE SOLVED: To secure the connection strength of a column-beam joint by butting a notched end face of a partly cut beam against the side face of a reinforcing column and connecting an end plate welded to the notched end face, to a backing plate welded to the side face of the reinforcing column, with bolts. SOLUTION: A beam-omitted building unit 10 has a framework structure in which columns 10, floor beams 12, and ceiling beams 13 are connected to shape a box. A part of the longitudinal side of a ceiling beam 13 is cut to form a partly cut ceiling beam 15, and a reinforcing column 17 and a reinforcing beam 18 are provided to compensate the reduction of strength of the notched part 16 of beam. In the column- beam connection 20 of the partly cut ceiling beam 15 and the reinforcing column 17, the notched end face 15A of the beam is butted against the side face part 17A of the reinforcing column 17, and rigidly connected with bolts 21. The reinforcing column 17 is formed of a square steel pipe and a backing plate 22 is welded to the rear side of one side face, and the partly cut ceiling beam 15 is made of C-shaped steel member, and an end plate 23 is welded to the notched end face 15A of the beam, and the backing plate 22 and the end plate 23 may be fastened to a female screw part 23A with bolts 21. In this way, the connection strength at the time when the reinforcing column is connected to the notched end of beam can be improved and stably kept.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は建物ユニットに関す
る。
The present invention relates to a building unit.

【0002】[0002]

【従来の技術】従来のユニット建物では、特開平6-2723
17号公報に記載の如く、上下階に渡る階段室を設けるに
際し、階段を緩傾斜とするため、その階段室を水平方向
で相隣る 2つの建物ユニットに及ぼすことがある。この
ようなユニット建物では、階段吹抜け部が水平方向で相
隣る 2つの建物ユニットに渡るものとなり、下階建物ユ
ニットの天井梁と上階建物ユニットの床梁の一部で、そ
の階段吹抜け部に位置する部分を欠除せしめるものとな
る。
2. Description of the Related Art In a conventional unit building, Japanese Unexamined Patent Publication No.
As described in Japanese Patent Publication No. 17, when a staircase is provided on the upper and lower floors, the staircase may be applied to two horizontally adjacent building units in order to make the stairs gentle. In such a unit building, the stairwell spans two building units that are adjacent to each other in the horizontal direction. Will be omitted.

【0003】従来技術において、上述の如くに天井梁の
一部を欠除した梁省略建物ユニットでは、その天井梁の
欠除端に補強柱を付加し、当該建物ユニットの骨組強度
を補強することとしている。
[0003] In the prior art, in a building unit in which a part of a ceiling beam is omitted as described above, a reinforcing column is added to a cut end of the ceiling beam to reinforce the frame strength of the building unit. And

【0004】従来の補強柱1は、図7に示す如く、天井
梁2の欠除端の下面部に突き当ててボルト接合されてい
る。このとき、補強柱1はその上端部に接合板1Aを溶
接され、接合板1Aを柱1の中心軸に対する片側に張り
出した逆L字状とされ、柱1の接合板1Aを天井梁2の
下面部に梁勝ちでボルト接合することとしている。
As shown in FIG. 7, a conventional reinforcing column 1 is bolted to the lower end of a cut off end of a ceiling beam 2 so as to abut it. At this time, the reinforcing column 1 is welded to the joining plate 1A at the upper end thereof, and the joining plate 1A is formed into an inverted L-shape in which the joining plate 1A projects to one side with respect to the center axis of the column 1. It will be bolted to the lower surface by beam.

【0005】[0005]

【発明が解決しようとする課題】然しながら、従来技術
では、補強柱1の接合板1Aが該補強柱1の中心軸の片
側にのみ張り出され、この接合板1Aの片側に張り出さ
れた部分を天井梁2に対するボルト接合部としている。
このため、補強柱1の中心軸の両側を天井梁2にボルト
接合するものに比して、天井梁2の軸方向に作用する軸
力Fが、補強柱1と天井梁2の仕口を開くように該柱1
を図6のB方向に曲げ変形させるものとなり、この柱−
梁接合仕口部に所望の仕口強度を確保できない。
However, in the prior art, the joining plate 1A of the reinforcing column 1 projects only on one side of the center axis of the reinforcing column 1, and the portion extending on one side of the joining plate 1A. Are bolt joints to the ceiling beam 2.
For this reason, the axial force F acting in the axial direction of the ceiling beam 2 causes the connection between the reinforcement column 1 and the ceiling beam 2 to be larger than that in which the both sides of the central axis of the reinforcement column 1 are bolted to the ceiling beam 2. The pillar 1 to open
Is bent in the direction B in FIG.
The desired joint strength cannot be secured at the beam joint.

【0006】本発明の課題は、建物ユニットの一部欠除
天井梁の梁欠除端に補強柱を接合するに際し、その仕口
強度を向上することにある。
SUMMARY OF THE INVENTION An object of the present invention is to improve the strength of a joint when a reinforcing column is joined to a beam-cut end of a partially-cut ceiling beam of a building unit.

【0007】[0007]

【課題を解決するための手段】請求項1に記載の本発明
は、建物ユニットの梁の一部を欠除し、該一部欠除梁の
梁欠除端に補強柱が接合され、一部欠除梁の梁欠除端面
部を補強柱の側面部に突き当ててボルト接合してなるよ
うにしたものである。
According to the first aspect of the present invention, a part of a beam of a building unit is cut off, and a reinforcing column is joined to a beam cut end of the partially cut off beam. The beam-cutting end face of the beam is cut off by abutting against the side face of the reinforcing column.

【0008】請求項2に記載の本発明は、請求項1に記
載の本発明において更に、前記補強柱の側面部に裏当て
板を設けるとともに、前記一部欠除梁の梁欠除端面部に
端板を固定し、該補強柱の側面部の裏当て板と該一部欠
除梁の梁欠除端面部の端板とをボルト締結してなるよう
にしたものである。
According to a second aspect of the present invention, in the first aspect of the present invention, a backing plate is further provided on a side surface of the reinforcing column, and a beam-cutting end surface of the partially-cut beam. , And a backing plate on the side surface of the reinforcing column and an end plate on the beam-cutting end surface of the partially cut-off beam are bolted together.

【0009】請求項3に記載の本発明は、請求項2に記
載の本発明において更に、前記補強柱が管材からなり、
該補強柱における前記一部欠除梁の梁欠除端面部に接す
る側面部に裏当て板を設け、ボルトの頭部もしくはナッ
トを該裏当て板に直接当接してなるようにしたものであ
る。
According to a third aspect of the present invention, in the second aspect of the present invention, the reinforcing column is made of a pipe material.
A backing plate is provided on a side surface of the reinforcing pillar that is in contact with the beam-cutting end surface of the partially cut-off beam, and a head or nut of a bolt is directly in contact with the backing plate. .

【0010】[0010]

【作用】請求項1の本発明によれば下記の作用があ
る。 一部欠除梁の梁欠除端面部を補強柱の側面部に柱勝ち
で突き当ててボルト接合した。従って、一部欠除梁の軸
方向に作用する軸力により補強柱が変位しても、補強柱
の側面部と一部欠除梁の梁欠除端面部とは互いに離れる
ことなく一体となって変位する。これにより、補強柱と
一部欠除梁の仕口は開くことなく、この柱−梁接合仕口
部に所望の仕口強度を確保できる。
According to the first aspect of the present invention, the following operations are provided. The beam-cutting end face of the partially cut-off beam was abutted against the side face of the reinforcing column, and bolted. Therefore, even if the reinforcing column is displaced by the axial force acting in the axial direction of the partially cut-off beam, the side surface portion of the reinforcing column and the beam-cutting end surface of the partially cut-off beam are united without being separated from each other. Displace. As a result, a desired joint strength can be ensured at the joint between the pillar and the beam without opening the joint between the reinforcing column and the partially missing beam.

【0011】請求項2の本発明によれば下記の作用が
ある。 柱−梁接合仕口部を構成する補強柱の側面部に裏当て
板を設けた(図3(A))。従って、補強柱の板厚が薄
い場合にも、補強柱の側面部の剛性を高め、この補強柱
の側面部が、一部欠除梁の軸方向に作用する引張軸力に
よりボルト接合部回りで局部的にふくれ変形することが
なく、この柱−梁接合仕口部の仕口強度を安定維持する
(図3(B))。
According to the second aspect of the present invention, the following operations are provided. A backing plate was provided on the side surface of the reinforcing column that forms the column-beam joint (FIG. 3A). Therefore, even when the thickness of the reinforcing column is small, the rigidity of the side portion of the reinforcing column is increased, and the side portion of the reinforcing column is rotated around the bolt joint by the tensile axial force acting in the axial direction of the partially missing beam. Thus, the joint strength of the column-beam joint is stably maintained without causing local bulging (FIG. 3 (B)).

【0012】請求項3の本発明によれば下記の作用が
ある。 ボルトの頭部もしくはナットを、補強柱の裏当て板に
直接当接せしめた(図3(A))。従って、ボルトの頭
部もしくはナットを、補強柱において一部欠除梁の梁欠
除端面部に接する側面部に相対する外側の側面部に当接
する場合の、その外側の側面部のつぶれ変形を招く虞れ
がない(図3(C))。また、そのつぶれ変形を回避す
るため、補強柱において一部欠除梁の梁欠除端面部に接
する側面部と、これに相対する外側の側面部との間に隙
間(g)のないスペーサ3を設ける如くの施工上の困難
を伴わない(図3(D))。即ち、ボルトの頭部もしく
はナットを、補強柱の裏当て板に直接当接せしめること
により、この柱−梁接合仕口部に所望の仕口強度を簡易
に確保できる。
According to the third aspect of the present invention, the following operations are provided. The head or nut of the bolt was directly in contact with the backing plate of the reinforcing column (FIG. 3 (A)). Therefore, when the head or nut of the bolt abuts on the outer side surface portion of the reinforcing column that is in contact with the side surface portion that is in contact with the beam lacking end surface portion of the partially missing beam, the crush deformation of the outer side surface portion is prevented. There is no fear of inviting (FIG. 3C). Further, in order to avoid the crushing deformation, the spacer 3 having no gap (g) between the side surface portion of the reinforcing column that is in contact with the beam-cutting end surface portion of the partially cut-off beam and the outer side surface portion opposite thereto. (Fig. 3 (D)). That is, by directly contacting the head or nut of the bolt with the backing plate of the reinforcing column, a desired joint strength can be easily secured at the column-beam joint.

【0013】[0013]

【発明の実施の形態】図1は建物ユニットの柱上端側の
柱−梁接合仕口部を示す模式図、図2は図1の柱−梁接
合仕口部のボルト配置状態を示す模式図、図3は本発明
に係る柱−梁接合仕口部の作用効果を示す模式図、図4
は柱下端側の柱−梁接合仕口部を示す模式図、図5は建
物ユニットの他の柱−梁接合仕口部を示す模式図、図6
は図5の柱−梁接合仕口部のボルト配置状態を示す模式
図、図7は従来の柱−梁接合仕口部を示す模式図であ
る。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a schematic view showing a column-beam joint at the upper end of a column of a building unit, and FIG. 2 is a schematic view showing a bolt arrangement at the column-beam joint in FIG. FIG. 3 is a schematic diagram showing the operation and effect of the column-beam joint according to the present invention, and FIG.
Is a schematic diagram showing a column-beam joint at the lower end of the column, FIG. 5 is a schematic diagram showing another column-beam joint at the building unit, and FIG.
FIG. 7 is a schematic view showing a bolt-arranged state of a column-beam joint in FIG. 5, and FIG. 7 is a schematic view showing a conventional column-beam joint.

【0014】図1(A)の梁省略建物ユニット10は、
他の建物ユニットとともにユニット建物を構成するもの
であり、基本的には、柱11と床梁12と天井梁13を
箱形に接合した骨組構造体である。然るに、この梁省略
建物ユニット10にあっては、これが構成するユニット
建物内において階段吹抜け部14を形成するため、 1本
の天井梁13をその長手方向の一部を欠除した一部欠除
天井梁15としている。そして、梁省略建物ユニット1
0にあっては、梁欠除部16の存在による強度低下を補
うため、一部欠除天井梁15の梁欠除端とその下方の床
梁12との間に補強柱17を設け、一部欠除天井梁15
の梁欠除端とその側方の他の天井梁13との間に補強梁
18を設けている。
The building unit 10 with no beams shown in FIG.
A unit building is formed together with other building units, and is basically a skeleton structure in which columns 11, floor beams 12, and ceiling beams 13 are joined in a box shape. However, in the building unit 10 in which the beam is omitted, in order to form the stairwell 14 in the unit building constituted by the unit, one ceiling beam 13 is partially cut away by removing a part in the longitudinal direction. The ceiling beam 15 is used. And the building unit 1 without beams
In the case of No. 0, a reinforcing column 17 is provided between the beam cut end of the partially cut ceiling beam 15 and the floor beam 12 thereunder to compensate for the strength reduction due to the presence of the beam cut portion 16. Partial ceiling beam 15
A reinforcing beam 18 is provided between the beam lacking end of the above and another ceiling beam 13 on the side thereof.

【0015】以下、一部欠除天井梁15と補強柱17の
上端部との柱−梁接合仕口部20の構造について説明す
る。柱−梁接合仕口部20にあっては、図1(B)に示
す如く、一部欠除天井梁15の梁欠除端面部15Aを補
強柱17の上端部の側面部17Aに突き当てて、両者を
ボルト21(高力ボルト)で剛接合している。
The structure of the column-to-beam joint 20 between the partly omitted ceiling beam 15 and the upper end of the reinforcing column 17 will be described below. In the column-beam joint 20, as shown in FIG. 1 (B), the partially cut end beam 15 </ b> A of the partially cut ceiling beam 15 abuts against the side face 17 </ b> A of the upper end of the reinforcing pillar 17. Thus, the two members are rigidly connected by bolts 21 (high-strength bolts).

【0016】このとき、補強柱17を例えば角鋼管にて
形成し、補強柱17の側面部17Aを構成する一側面の
裏側に裏当て板22を溶接している。また、一部欠除天
井梁15を例えばC形鋼にて形成し、一部欠除天井梁1
5の梁欠除端面部15Aに端板23を溶接している。そ
して、補強柱17の側面部17Aの裏当て板22と、一
部欠除天井梁15の梁欠除端面部15Aの端板23とを
ボルト締結すべく、ボルト21を端板23に設けためね
じ部23Aに締結している。
At this time, the reinforcing column 17 is formed of, for example, a square steel pipe, and the backing plate 22 is welded to the back of one side surface of the side surface portion 17A of the reinforcing column 17. In addition, the partially missing ceiling beam 15 is formed of, for example, a C-shaped steel, and the partially missing ceiling beam 1 is formed.
5, the end plate 23 is welded to the beam-missing end surface 15A. Then, the bolts 21 are provided on the end plate 23 so that the backing plate 22 of the side surface portion 17A of the reinforcing pillar 17 and the end plate 23 of the beam cut end surface portion 15A of the partially cut ceiling beam 15 are bolted. It is fastened to the screw portion 23A.

【0017】また、補強柱17において一部欠除天井梁
15の梁欠除端面部15Aに接する側面部17Aに相対
する外側の側面部17Bにボルト貫通孔17Cを設け、
このボルト貫通孔17Cから挿通したボルト21の頭部
21Aを補強柱17の裏当て板22に直接当接させてい
る。
Further, a bolt through hole 17C is provided in an outer side surface portion 17B opposite to a side surface portion 17A which is in contact with the beam lacking end surface portion 15A of the partly-removed ceiling beam 15 in the reinforcing pillar 17,
The head 21A of the bolt 21 inserted through the bolt through hole 17C is directly in contact with the backing plate 22 of the reinforcing column 17.

【0018】尚、柱−梁接合仕口部20にあっては、図
2(A)に示す如く、ボルト21を、補強柱17の側面
部17Aの裏当て板22から一部欠除天井梁15の梁欠
除端面部15Aの端板23に挿通した後、該端板23の
裏側に配置したナット24に締結するものであっても良
い。また、柱−梁接合仕口部20にあっては、図2
(B)に示す如く、ボルト21を、一部欠除天井梁15
の梁欠除端面部15Aの端板23に挿通した後、補強柱
17の側面部17Aの裏当て板22に設けためねじ部に
締結するものであっても良い。
As shown in FIG. 2A, bolts 21 are partially removed from the backing plate 22 of the side surface 17A of the reinforcing column 17 in the column-beam joint 20. After being inserted into the end plate 23 of the 15 beam-cutting end face portion 15A, the nut may be fastened to a nut 24 arranged on the back side of the end plate 23. In the column-beam joint 20, FIG.
As shown in (B), the bolt 21 is partially removed from the ceiling beam 15.
After being inserted into the end plate 23 of the beam lacking end surface portion 15A, the reinforcing member 17 may be fastened to a screw portion to be provided on the backing plate 22 of the side surface portion 17A of the reinforcing column 17.

【0019】図4は、補強柱17の下端部と床梁12と
の柱−梁接合仕口部100の構造を示している。柱−梁
接合仕口部100は、補強柱17の下端部に溶接してあ
る端板101を、H形鋼の床梁12にボルト102(高
力ボルト)で剛接合するに際し、端板101を補強柱1
7の両側に張出し、この両側の張出し部103のそれぞ
れに座ぐり穴104を設けた例である。床梁12は、補
強柱17との接合部にスチフナ105、105を備え
る。ボルト102の頭部102Aを座ぐり穴104に納
めても、ナット102Bを座ぐり穴104に納めても良
いが、端板101の剛性を上げるためにその板厚tを大
きくする場合にも、ボルト102の端板101からの突
出寸法hを極力小さくできる。
FIG. 4 shows the structure of a column-beam joint 100 between the lower end of the reinforcing column 17 and the floor beam 12. When the end plate 101 welded to the lower end portion of the reinforcing column 17 is rigidly joined to the H-shaped steel floor beam 12 with bolts 102 (high-strength bolts), the end plate 101 Reinforced column 1
7 is an example in which a counterbore 104 is provided in each of the projecting portions 103 on both sides. The floor beam 12 is provided with stiffeners 105 at the joint with the reinforcing column 17. Although the head 102A of the bolt 102 may be accommodated in the counterbore 104 or the nut 102B may be accommodated in the counterbore 104, even when the plate thickness t is increased to increase the rigidity of the end plate 101, The protrusion dimension h of the bolt 102 from the end plate 101 can be minimized.

【0020】従って、本実施形態によれば、以下の作用
がある。 一部欠除天井梁15の梁欠除端面部15Aを補強柱1
7の側面部17Aに柱勝ちで突き当ててボルト接合し
た。従って、一部欠除天井梁15の軸方向に作用する軸
力により補強柱17が変位しても、補強柱17の側面部
17Aと一部欠除天井梁15の梁欠除端面部15Aとは
互いに離れることなく一体となって変位する。これによ
り、補強柱17と一部欠除天井梁15の仕口は開くこと
なく、この柱−梁接合仕口部20に所望の仕口強度を確
保できる。
Therefore, according to the present embodiment, the following operations are provided. Reinforcement pillar 1 for partially missing end 15A of ceiling beam 15
7 was bolted by abutting against the side surface 17A. Therefore, even if the reinforcing column 17 is displaced by an axial force acting in the axial direction of the partially-removed ceiling beam 15, the side portion 17A of the reinforcing column 17 and the beam-removed end surface portion 15A of the partially-removed ceiling beam 15 are removed. Are displaced together without separating from each other. As a result, the connection between the reinforcing column 17 and the partly-removed ceiling beam 15 is not opened, and a desired connection strength can be secured in the column-beam joint 20.

【0021】柱−梁接合仕口部20を構成する補強柱
17の側面部17Aに裏当て板22を設けた(図3
(A))。従って、補強柱17の板厚が薄い場合にも、
補強柱17の側面部17Aの剛性を高め、この補強柱1
7の側面部17Aが、一部欠除天井梁15の軸方向に作
用する引張軸力によりボルト接合部回りで局部的にふく
れ変形することがなく、この柱−梁接合仕口部20の仕
口強度を安定維持する(図3(B))。
A backing plate 22 is provided on the side surface 17A of the reinforcing column 17 constituting the column-beam joint 20 (FIG. 3).
(A)). Therefore, even when the plate thickness of the reinforcing column 17 is thin,
The rigidity of the side portion 17A of the reinforcing column 17 is increased,
7 does not locally bulge around the bolted joint due to the tensile axial force acting in the axial direction of the partially cut ceiling beam 15, and the joint of the column-beam joint 20 is not deformed. The mouth strength is maintained stably (FIG. 3 (B)).

【0022】ボルト21の頭部もしくはナット24
を、補強柱17の裏当て板22に直接当接せしめた(図
3(A))。従って、ボルト21の頭部もしくはナット
24を、補強柱17において一部欠除天井梁15の梁欠
除端面部15Aに接する側面部17Aに相対する外側の
側面部17Bに当接する場合の、その外側の側面部17
Bのつぶれ変形を招く虞れがない(図3(C))。ま
た、そのつぶれ変形を回避するため、補強柱17におい
て一部欠除天井梁15の梁欠除端面部15Aに接する側
面部17Aと、これに相対する外側の側面部17Bとの
間に隙間(g)のないスペーサ3を設ける如くの施工上
の困難を伴わない(図3(D))。即ち、ボルト21の
頭部もしくはナット24を、補強柱17の裏当て板22
に直接当接せしめることにより、この柱−梁接合仕口部
20に所望の仕口強度を簡易に確保できる。
The head or nut 24 of the bolt 21
Was directly brought into contact with the backing plate 22 of the reinforcing column 17 (FIG. 3A). Therefore, when the head 21 or the nut 24 of the bolt 21 abuts on the outer side portion 17B opposite to the side portion 17A of the reinforcing column 17 which is in contact with the beam lacking end surface portion 15A of the partially cut ceiling beam 15, Outer side 17
There is no danger of crushing deformation of B (FIG. 3C). Further, in order to avoid the crushing deformation, a gap is formed between the side surface portion 17A of the reinforcing pillar 17 which is in contact with the partially cut off end surface portion 15A of the ceiling beam 15 and the outer side surface portion 17B opposed thereto. There is no difficulty in construction such as providing the spacer 3 without g) (FIG. 3D). That is, the head or nut 24 of the bolt 21 is attached to the backing plate 22 of the reinforcing column 17.
The desired contact strength can be easily secured to the column-beam joint 20 by directly contacting the joint 20 with the column.

【0023】尚、梁省略建物ユニット10にあっては、
一部欠除天井梁15と補強柱17とを接合する等の組立
製造段階で、一部欠除天井梁15を軸方向で挟んで相対
する柱11、11間における一部欠除天井梁15の直線
性等の建物ユニット10の組立寸法精度を確保するた
め、梁欠除部16に仮梁31を仮設置している。そこ
で、梁省略建物ユニット10の梁欠除部16に接する 1
つのコーナー部に位置する柱11に対する天井梁13と
仮梁31の柱−梁接合仕口部40の構造について説明す
る。
In the building unit 10 without beams,
At an assembly manufacturing stage such as joining the partially-cut ceiling beam 15 and the reinforcing column 17, the partially-cut ceiling beam 15 between the columns 11 and 11 facing each other with the partially-cut ceiling beam 15 sandwiched in the axial direction. In order to secure the assembly dimensional accuracy of the building unit 10 such as the linearity, a temporary beam 31 is temporarily installed in the beam lacking portion 16. Therefore, it comes into contact with the beam lacking portion 16 of the beam omitted building unit 10 1
The structure of the column beam-to-column joint 40 of the ceiling beam 13 and the temporary beam 31 for the column 11 located at one corner will be described.

【0024】柱−梁接合仕口部40にあっては、図5に
示す如く、柱11を例えば角鋼管にて形成し、柱11の
相交差する 2つの側面部11A、11Bの裏側に断面L
型の裏当て板41(裏当て板41は熱間押し出し形鋼も
しくは鋳鋼による一体成形品或いは平板鋼材による溶接
品とすることができる)を溶接している。他方、天井梁
13の端面部13Aに端板42を溶接し、仮梁31の端
面部31Aに端板43を溶接している。そして、天井梁
13の端面部13Aの端板42をボルト44により柱1
1の側面部11Aの裏側の裏当て板41に締結し、仮梁
31の端面部31Aの端板43をボルト45により柱1
1の側面部11Bの裏側の裏当て板41に締結する。
In the column-beam joint 40, as shown in FIG. 5, the column 11 is formed of, for example, a square steel pipe, and a cross section is formed on the back side of two intersecting side portions 11A and 11B of the column 11. L
The backing plate 41 of the mold is welded (the backing plate 41 can be an integrally formed product made of hot extruded steel or cast steel or a welded product made of a flat steel material). On the other hand, an end plate 42 is welded to the end surface 13A of the ceiling beam 13 and an end plate 43 is welded to the end surface 31A of the temporary beam 31. Then, the end plate 42 of the end face portion 13A of the ceiling beam 13 is
1 is fastened to the backing plate 41 on the back side of the side surface portion 11A, and the end plate 43 of the end surface portion 31A of the temporary beam 31 is
The first side portion 11B is fastened to the backing plate 41 on the back side.

【0025】このとき、ボルト44、45は、図6
(A)に示す如く、天井梁13、仮梁31の端板42、
43に挿通した後、柱11の側面部11A、11Bの裏
側の裏当て板41に設けためねじ部に締結することがで
きる。尚、図6(B)に示す如く、柱11の外側の側面
部11C、11Dに設けたボルト挿通孔46A、46B
から柱11の内部に挿通したボルト44、45を、柱1
1の側面部11A、11Bの裏当て板41から天井梁1
3、仮梁31の端板42、43に挿通した後、それら端
板42、43の裏側に配置したナット47、48に締結
するものであっても良い。
At this time, the bolts 44 and 45 are
As shown in (A), the ceiling beam 13, the end plate 42 of the temporary beam 31,
After being inserted into the column 43, it can be fastened to a screw portion to be provided on the backing plate 41 on the back side of the side surfaces 11 </ b> A and 11 </ b> B of the column 11. As shown in FIG. 6 (B), bolt insertion holes 46A, 46B provided in the side surfaces 11C, 11D outside the pillar 11 are provided.
The bolts 44 and 45 inserted into the pillar 11 from the
1 to the ceiling beam 1 from the backing plate 41 of the side portions 11A and 11B.
3. After being inserted through the end plates 42, 43 of the temporary beam 31, they may be fastened to nuts 47, 48 arranged on the back side of the end plates 42, 43.

【0026】また、梁省略建物ユニット10にあって
は、梁欠除部16に接しない 3つのコーナー部に位置す
る柱11に対する天井梁13、一部欠除天井梁15の柱
−梁接合仕口部の構造として、上述した図5、図6と同
一構造のものを採用できる。
In the building unit 10 where the beams are omitted, the beam-to-column joints of the ceiling beams 13 and the partially omitted ceiling beams 15 with respect to the columns 11 located at three corners which do not contact the beam lacking portion 16 are provided. As the structure of the mouth, the same structure as that of FIGS. 5 and 6 can be adopted.

【0027】以上、本発明の実施の形態を図面により詳
述したが、本発明の具体的な構成はこの実施の形態に限
られるものではなく、本発明の要旨を逸脱しない範囲の
設計の変更等があっても本発明に含まれる。例えば、本
発明は、建物ユニットの床梁の一部を欠除し、該床梁の
梁欠除端に補強柱を接合するに際し、床梁の梁欠除端面
部を補強柱の側面部に突き当ててボルト接合するもので
あっても良い。
The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and the design can be changed without departing from the scope of the present invention. The present invention is also included in the present invention. For example, according to the present invention, a part of a floor beam of a building unit is chipped, and a reinforcing column is joined to a beam split end of the floor beam. Butting and bolting may be used.

【0028】[0028]

【発明の効果】以上のように本発明によれば、建物ユニ
ットの一部欠除天井梁の梁欠除端に補強柱を接合するに
際し、その仕口強度を向上することができる。
As described above, according to the present invention, it is possible to improve the strength of the joint when reinforcing columns are joined to the beam-cutting ends of the partially cut ceiling beams of the building unit.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は建物ユニットの柱上端側の柱−梁接合仕
口部を示す模式図である。
FIG. 1 is a schematic view showing a column-beam joint at an upper end of a column of a building unit.

【図2】図2は図1の柱−梁接合仕口部のボルト配置状
態を示す模式図である。
FIG. 2 is a schematic view showing a bolt arrangement state of a column-beam joint in FIG. 1;

【図3】図3は本発明に係る柱−梁接合仕口部の作用効
果を示す模式図である。
FIG. 3 is a schematic view showing the operation and effect of the column-beam joint according to the present invention.

【図4】図4は柱下端側の柱−梁接合仕口部を示す模式
図である。
FIG. 4 is a schematic view showing a column-beam joint at a column lower end side.

【図5】図5は建物ユニットの他の柱−梁接合仕口部を
示す模式図である。
FIG. 5 is a schematic diagram showing another pillar-beam joint of the building unit.

【図6】図6は図5の柱−梁接合仕口部のボルト配置状
態を示す模式図である。
FIG. 6 is a schematic view showing a bolt arrangement state of a column-beam joint in FIG. 5;

【図7】図7は従来の柱−梁接合仕口部を示す模式図で
ある。
FIG. 7 is a schematic view showing a conventional column-beam joint.

【符号の説明】[Explanation of symbols]

10 建物ユニット 13 天井梁 15 一部欠除天井梁 15 梁欠除部 15A 梁欠除端面部 17 補強柱 17A 側面部 20 柱−梁接合仕口部 21 ボルト 22 裏当て板 23 端板 10 Building Unit 13 Ceiling Beam 15 Partially Missing Ceiling Beam 15 Beam Missing Part 15A Beam Missing End Face 17 Reinforcement Column 17A Side Part 20 Column-Beam Joint Portion 21 Bolt 22 Backing Plate 23 End Plate

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 建物ユニットの梁の一部を欠除し、該一
部欠除梁の梁欠除端に補強柱が接合され、一部欠除梁の
梁欠除端面部を補強柱の側面部に突き当ててボルト接合
してなることを特徴とする建物ユニット。
1. A part of a beam of a building unit is cut off, a reinforcing column is joined to a beam cut end of the partially cut beam, and a beam cut end surface of the partially cut beam is connected to the reinforcing column. A building unit characterized by being bolted against the side.
【請求項2】 前記補強柱の側面部に裏当て板を設ける
とともに、前記一部欠除梁の梁欠除端面部に端板を固定
し、該補強柱の側面部の裏当て板と該一部欠除梁の梁欠
除端面部の端板とをボルト締結してなる請求項1記載の
建物ユニット。
2. A backing plate is provided on a side surface of the reinforcing column, and an end plate is fixed to a beam-cutting end surface of the partially-removed beam. 2. The building unit according to claim 1, wherein the partially cut beam is bolted to an end plate at a beam cut end surface.
【請求項3】 前記補強柱が管材からなり、該補強柱に
おける前記一部欠除梁の梁欠除端面部に接する側面部に
裏当て板を設け、ボルトの頭部もしくはナットを該裏当
て板に直接当接してなる請求項2記載の建物ユニット。
3. The reinforcing column is made of a tubular material, and a backing plate is provided on a side portion of the reinforcing column in contact with a beam-cutting end surface of the partially-cut beam, and a head or nut of a bolt is attached to the backing plate. 3. The building unit according to claim 2, wherein the building unit comes into direct contact with the board.
JP10224584A 1998-08-07 1998-08-07 Building unit Withdrawn JP2000054502A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10224584A JP2000054502A (en) 1998-08-07 1998-08-07 Building unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10224584A JP2000054502A (en) 1998-08-07 1998-08-07 Building unit

Publications (1)

Publication Number Publication Date
JP2000054502A true JP2000054502A (en) 2000-02-22

Family

ID=16816033

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10224584A Withdrawn JP2000054502A (en) 1998-08-07 1998-08-07 Building unit

Country Status (1)

Country Link
JP (1) JP2000054502A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052436A (en) * 2009-09-01 2011-03-17 Sekisui Chem Co Ltd Column-omitted joint structure, column-omitted building unit, and unit building
JP2016118017A (en) * 2014-12-19 2016-06-30 アロン化成株式会社 Temporary handrail
JP2016223111A (en) * 2015-05-28 2016-12-28 株式会社渋谷 Unit Building

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052436A (en) * 2009-09-01 2011-03-17 Sekisui Chem Co Ltd Column-omitted joint structure, column-omitted building unit, and unit building
JP2016118017A (en) * 2014-12-19 2016-06-30 アロン化成株式会社 Temporary handrail
JP2016223111A (en) * 2015-05-28 2016-12-28 株式会社渋谷 Unit Building

Similar Documents

Publication Publication Date Title
US4905436A (en) Column/beam joint structure
JP2001342611A (en) Bridge girder
JP2000054502A (en) Building unit
JP4157211B2 (en) Steel segment and its manufacturing method
JP3327184B2 (en) Column-to-beam joints between steel pipe structure or filled steel pipe concrete structure column and SRC structure beam
JP3828641B2 (en) Column and beam connection structure
JP2004156291A (en) Bridge girder structure and bridge girder erection method
JP2719543B2 (en) Beam-column joint
JP3571913B2 (en) Column and beam joint structure, beam to beam joint structure, building unit, unit building and building
JPH0220323Y2 (en)
JP2516831B2 (en) Large beam and small beam connection structure
JPH0450724Y2 (en)
JP2000054504A (en) Connection structure of building unit whose beam is omitted
JP2749491B2 (en) Temporary beam mounting structure of building unit
JPH0220322Y2 (en)
JPS6334795Y2 (en)
JPH04124338A (en) Column/beam joint structure
JP2778352B2 (en) Joint structure of mating columns
JP2751777B2 (en) Column, beam joint structure
JP2000110247A (en) Beam-omitted building unit, and its building method
JP2510454Y2 (en) Joint structure of steel rebar concrete girder and half precast concrete girder
JPH11148176A (en) Unit building
JP3341918B2 (en) Connection structure of steel frame
JPH0841987A (en) Box section brace
JP2000054500A (en) Beam-omitted building unit and unit building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050616

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070221

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070228

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070418

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070627

A761 Written withdrawal of application

Free format text: JAPANESE INTERMEDIATE CODE: A761