[go: up one dir, main page]

GB2351301A - Concentric catenary riser - Google Patents

Concentric catenary riser Download PDF

Info

Publication number
GB2351301A
GB2351301A GB9914868A GB9914868A GB2351301A GB 2351301 A GB2351301 A GB 2351301A GB 9914868 A GB9914868 A GB 9914868A GB 9914868 A GB9914868 A GB 9914868A GB 2351301 A GB2351301 A GB 2351301A
Authority
GB
United Kingdom
Prior art keywords
pipe
annulus
riser system
catenary riser
system largely
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
GB9914868A
Other versions
GB9914868D0 (en
Inventor
Stephen Hatton
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to GB9914868A priority Critical patent/GB2351301A/en
Publication of GB9914868D0 publication Critical patent/GB9914868D0/en
Publication of GB2351301A publication Critical patent/GB2351301A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/12Methods or apparatus for controlling the flow of the obtained fluid to or in wells
    • E21B43/121Lifting well fluids
    • E21B43/122Gas lift
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/01Risers
    • E21B17/015Non-vertical risers, e.g. articulated or catenary-type
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/01Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

A catenary riser is formed from a central pipe 1 for the flow of oil or gas and an outer pipe 3. The annular space 4 may contain a service line 2 and be filled with, water, thermal insulation materials, gas for gas lift or injection purposes, a chemical for chemical injection, air or a vacuum.

Description

2351301 BRITISH PATENT APLICATION CONCENTRIC CATENARY RISER (CCR) This
invention concerns a steel catenary riser system used in the recovery of offshore oil and gas reserves in deep water envirorn-lients. The presented system offers the means to provide effective thermal insulation, riser base gas lift, active production fluid heating, chemical injection, fatigue resistant hardware and straightfoiward installation using conventional pipeline and riser installation tectiniques.
Background to the Invention
As oil exploration and production moves into deeper water there is a need to develop both technically viable and cost effective riser systems. Risers may take many forms but typically consist of a single or a bundle of pipes that extend vertically or in a catenary from the seabed and connect to the vessel or terminate near the vessel. As water depths increase there is increasing need for riser systems with high levels of thermal insulation to maintain arrival temperatures and to prevent hydrates and wax deposition during shutdown periods.
Summary of Invention
The present invention proposes a catenary riser configuration, Figure 1, which may be installed either by tow out following onshore assembly or by offshore assembly using a pipe lay vessel or drilling rig. The riser cross section consists of a single primary flow path, which takes the form of a concentric bundle arrangement of a pipe in pipe. In addition one or more smaller diameter service or control lines may also be included on the outside or within the annulus of the pipe in pipe system. A typical arrangement is shown in Figure 2 in which a central flow path 1 and a service line 2 are located inside an outer pipe 3. The annular space 4 may be filled with water, thermal insulation materials, gas such as methane for gas lift or injection purposes, chemical injection such as glycol, air or be vacuumed.
Different fluids may be used in the annulus depending on the riser operating mode. Gas lift can be performed down the annulus and provides a convenient way of also heating the central flow 1 path. As the gas is hot, following compression, the riser acts like a Ion. heat exchanger transferring licat from the gas into the production fluid. Air filling or evacuating the annulus to a 1:1 C.
near vactiurn provides an economical means of thermal insulation and may be considered during shut down periods. In addition thermal insulation and buoyancy materials may also be used in the annular space and/or attached to the outside of the outer pipe.
The annulus may also be water flooded. This increases the riser weight, which can significantly improve the response particularly at the point where the riser touches the seabed. For this reason, it is possible that such an arrangement can accommodate higher vessel motions and more severe environmental loading than when gas filled. For this reason it is proposed that the riser is water flooded at tirries of extreme storm. After the storm has passed the water is purged out of the annulus using an air drive. A further benefit of the concentric bundle arrangement is that it provides a second pressure barrier, enhancing the reliability and ability to detect leaks or failure of the inner pipe (2) As the configuration has a single main flow path, it is anticipated that a number of such CCRs will be required to accommodate the development requirements of a large deepwater field.
Description of Invention
In the present invention the riser is configured in a simple catenary. It is attached to the vessel via a flex joint and extends down to the seabed where it is connected to a subsea flowline. The riser cross section consists of a central pipe, located within a larger diameter external pipe and with a small chemical injection or control line pipe located in the annulus. The smaller service lines in the armulus are wrapped around the central pipe in a helical fashion so as to accommodate thermal and pressure end cap effects. The outside surface of the outer pipe is coated with a corrosion protection material such as fusion-bonded epoxy or thermally sprayed aluminium.
The central pipe diameter is sized for the main flow path. The annulus between the central and outer pipe is filled with air, which together with a coating if necessary on the outer pipe provides the desired thermal insulation to the production pipe.
The steel pipes are fon-ned from high strength seamless pipe and may be either welded or connected using mechanical connections. The wall thickness of the pipes is determined using relevant codes and standards, with subsequent analysis undertaken to optimise the riser configuration under dynamic loading. The size and wall thickness of each pipe varies from riser to riser depending on water depth, reservoir flow characteristics and production requirements.
At the vessel the riser is terminated with a flex joint 5, swivel or other compliant device that allows relative angular motion between the riser and vessel. The flex joint has a single flow path I for the central production line. The annulus 6 and the smaller lines are ported around the flex joint using a flexible jumper or other compliant pipe work as shown in Figure 3.
The upper end of the central pipe is ten-ninated in thickened section or hanger 7, which locates in a bowl 8 welded to the top end of the outer pipe. The interface between the hanger and bowl is scaled usinOIr a replaceable seal assembly 9. The weight of the outer pipe is supported off the hanger via the bowl using a load shoulder and series of dogs 10. A side port I lwith a studded flange face is provided in the bowl allowing access into the annulus. The port is isolated by valve, which is connected by flexible piping to the vessel tennination.
On the seabed the riser connects to the subsea flowline 12 some distance away from the vessel. The interface is located in a static portion of the pipeline i.e. a section which does not lift on and off the seabed as a result of vessel i-notions. A riser termination manifold is installed at the interface, Figure 4. The manifold consists of a for-ed steel block 13 that is machined with a central horizontal bore. Each end of the forging is machined with a studded flange face to connect the riser and flowline pipe sections respectively. The bore of the forging is machined with a profile that is designed to remotely align, capture, lock and seal the lower end of the iriner pipe. The capture and locking mechanism is achieved by a series of dogs 14 that are hydraulically actuated either from the vessel or by a local ROV hot stab. A flow loop 15 is provided allowing circulation between the central pipe and annulus. This flow loop is isolated by hydraulically operated gate valves 16, operated from the platforin using a control line run in the annulus.
(3) An alternative arrangement, Figure 5, uses a packerl7, run on the inner pipe. The packer is the same design as used in down hole applications. Once the inner pipe is run into the correct position, the packer is actuated forming a seal between the inner and outer pipe and locking the movement. A cross over 18 between the annulus and inner pipe is provided below the packer similar to above.
The riser system is installed by first installing the flowline section from a pipe lay vessel. The riser terinination manifold is flanged onto the flowline section ensuring correct rotational orientation. The outer riser pipe is flanged onto the opposite end of the forging to the flowline and the laying of the outer pipe is continued to the production vessel. Once the correct length of outer pipe Is installed, the upper bowl is fitted to the end of the last pipe section. The outer pipe is suspended from the lay vessel ramp and the inner pipe is assembled starting with the profiled thick walled section that mates and connects in the bore of the riser termination manifold. Subsequent pipe sections are added and the inner pipe is lowered into the bore of the suspended outer pipe. The process continues until the inner pipe reaches the termination manifold where it is locked and scaled. The inner pipe is pre- tensioned against the outer pipe and the hanger is landed 1D and locked into the upper bowl. The upper flex joint and annulus piping is assembled prior to hand over and comiection to the vessel. The vessel pipe work and control lines are connected allowing the manifold valves to be functioned and the riser flow paths circulated and pressure tested.
The subsea flowline may have a different design and thermal insulation configuration and be installed by a separate installation activity. In which case the connection between the CCR and flowline termination manifold can be achieved either subsea or at the surface by recovery of the flowline and manifold to the CCR lay vessel.
(4)

Claims (11)

Claims
1. A pipe in pipe catenary riser system largely as described comprising a pipe in pipe bundle where the annulus may be filled with a variety of liquids and gases depending on service and operation.
2. A pipe in pipe catenary riser system largely as described in which thermal insulation is provided by air or gas filling or vacuuming the annulus.
1
3. A pipe in pipe catenary riser system largely as described in which the annulus is used to pump hot gas or liquid with the objective of transferring heat in to the production fluids.
1
4. A pipe in pipe catenary riser system largely as described in which the annulus is used as a method of providing riser base gas lift.
5. A pipe in pipe catenary riser system largely as described in which the annulus is used as a flow path for water or gas injection services.
6. A pipe in pipe catenary riser system largely as described in which a riser termination manifold is used to provide circulation between the central pipe and annulus or any other pipe in the bundle.
7. A pipe in pipe catenary riser system largely as described in which the inner pipe or pipes are installed by sliding them inside a preinstalled outer pipe.
8. A pipe in pipe catenary riser system largely as described in which the inner pipe or pipes are terminated at a subsea structure providing sealing and/or axially locking of one pipe with t> W respect to the other.
9. A pipe in pipe catenary riser system largely as described in which the weight of the outer pipe is hung off the inner pipe via a mechanical or welded connection located near the top of the riser.
10. A pipe in pipe catenary riser system as claimed in any 1 to 9 in which the annulus is flooded during storin conditions with the objective of increasing the weight of the riser and improving its response.
11. A pipe in pipe catenary riser system largely as described in claims 1 to 9 where external buoyancy is used to fomi a more compliant shape containing an arch or wave.
GB9914868A 1999-06-25 1999-06-25 Concentric catenary riser Withdrawn GB2351301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
GB9914868A GB2351301A (en) 1999-06-25 1999-06-25 Concentric catenary riser

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB9914868A GB2351301A (en) 1999-06-25 1999-06-25 Concentric catenary riser

Publications (2)

Publication Number Publication Date
GB9914868D0 GB9914868D0 (en) 1999-08-25
GB2351301A true GB2351301A (en) 2000-12-27

Family

ID=10856049

Family Applications (1)

Application Number Title Priority Date Filing Date
GB9914868A Withdrawn GB2351301A (en) 1999-06-25 1999-06-25 Concentric catenary riser

Country Status (1)

Country Link
GB (1) GB2351301A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002063128A1 (en) * 2001-01-08 2002-08-15 Stolt Offshore Sa Marine riser tower
EP1247935A1 (en) * 2001-04-05 2002-10-09 Norsk Hydro ASA Production riser
WO2003102357A1 (en) * 2002-05-31 2003-12-11 Stolt Offshore S.A. Flowline insulation system
FR2875285A1 (en) * 2004-09-13 2006-03-17 Technip France Sa MULTI-CONDUIT FLEXIBLE PIPES PRESERVED OF CORROSION
US7104330B2 (en) 2001-01-08 2006-09-12 Stolt Offshore S.A. Marine riser tower
US7434624B2 (en) 2002-10-03 2008-10-14 Exxonmobil Upstream Research Company Hybrid tension-leg riser
FR2931188A1 (en) * 2008-05-13 2009-11-20 Denis Ernest Celestin Buffet Sub-marine pipe heating device for petroleum field, has heating tube surrounded with high temperature insulator and embedded in low temperature insulating envelope for being placed close to and in contact with envelope
WO2012051149A3 (en) * 2010-10-12 2013-04-04 Bp Corporation North America Inc. Marine subsea free-standing riser systems and methods
GB2525609A (en) * 2014-04-28 2015-11-04 Acergy France SAS Riser system with gas-lift facility
CN108612505A (en) * 2018-04-20 2018-10-02 林继承 A kind of offshore oil exploitation method
WO2019123008A2 (en) 2017-12-20 2019-06-27 Acergy France SAS Insulation of pipe-in-pipe systems
RU2721011C1 (en) * 2019-01-29 2020-05-15 Шинда (Тангшан) Креатив Оил Енд Гас Екуипмент Ко., Лтд. Pipe with steel casing, providing super long thermal insulation, and method of machining thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695872B (en) * 2015-02-26 2017-02-01 徐州徐工基础工程机械有限公司 Multilayer drill pipe structure of pneumatic down-hole hammer

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2280460A (en) * 1993-07-23 1995-02-01 Altra Consultants Limited Apparatus for inserting into a conduit
GB2330157A (en) * 1997-10-07 1999-04-14 Bluewater Terminal Systems Nv Riser system for connecting a seabed installation with a floating vessel

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2280460A (en) * 1993-07-23 1995-02-01 Altra Consultants Limited Apparatus for inserting into a conduit
GB2330157A (en) * 1997-10-07 1999-04-14 Bluewater Terminal Systems Nv Riser system for connecting a seabed installation with a floating vessel

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002063128A1 (en) * 2001-01-08 2002-08-15 Stolt Offshore Sa Marine riser tower
US7100694B2 (en) 2001-01-08 2006-09-05 Stolt Offshore S.A. Marine riser tower
US7104330B2 (en) 2001-01-08 2006-09-12 Stolt Offshore S.A. Marine riser tower
EP1247935A1 (en) * 2001-04-05 2002-10-09 Norsk Hydro ASA Production riser
NO339764B1 (en) * 2002-05-31 2017-01-30 Acergy France SAS Strømningsrørisolasjonssystem
WO2003102357A1 (en) * 2002-05-31 2003-12-11 Stolt Offshore S.A. Flowline insulation system
GB2404714A (en) * 2002-05-31 2005-02-09 Stolt Offshore Sa Flowline insulation system
GB2404714B (en) * 2002-05-31 2005-08-17 Stolt Offshore Sa Flowline insulation system
US7441602B2 (en) 2002-05-31 2008-10-28 Acergy France S.A. Flowline insulation system
US7434624B2 (en) 2002-10-03 2008-10-14 Exxonmobil Upstream Research Company Hybrid tension-leg riser
WO2006030085A1 (en) * 2004-09-13 2006-03-23 Technip France Flexible pipeline with multiple pipes protected against corrosion
AU2005284061B2 (en) * 2004-09-13 2010-04-29 Technip France Flexible pipeline with multiple pipes protected against corrosion
US7784498B2 (en) 2004-09-13 2010-08-31 Technip France Flexible pipeline with multiple pipes protected against corrosion
FR2875285A1 (en) * 2004-09-13 2006-03-17 Technip France Sa MULTI-CONDUIT FLEXIBLE PIPES PRESERVED OF CORROSION
FR2931188A1 (en) * 2008-05-13 2009-11-20 Denis Ernest Celestin Buffet Sub-marine pipe heating device for petroleum field, has heating tube surrounded with high temperature insulator and embedded in low temperature insulating envelope for being placed close to and in contact with envelope
WO2012051149A3 (en) * 2010-10-12 2013-04-04 Bp Corporation North America Inc. Marine subsea free-standing riser systems and methods
US8960302B2 (en) 2010-10-12 2015-02-24 Bp Corporation North America, Inc. Marine subsea free-standing riser systems and methods
US9297214B2 (en) 2010-10-12 2016-03-29 Bp Corporation North America Inc. Marine subsea free-standing riser systems and methods
CN103154424B (en) * 2010-10-12 2016-05-18 Bp北美公司 The vertical riser systems of seabed Free Station and method
CN103154424A (en) * 2010-10-12 2013-06-12 Bp北美公司 Marine subsea free-standing riser systems and methods
GB2525609A (en) * 2014-04-28 2015-11-04 Acergy France SAS Riser system with gas-lift facility
GB2525609B (en) * 2014-04-28 2017-04-19 Acergy France SAS Riser system with gas-lift facility
US9982518B2 (en) 2014-04-28 2018-05-29 Acergy France SAS Production riser with a gas lift facility
WO2019123008A2 (en) 2017-12-20 2019-06-27 Acergy France SAS Insulation of pipe-in-pipe systems
US11280442B2 (en) 2017-12-20 2022-03-22 Acergy France SAS Insulation of pipe-in-pipe systems
CN108612505A (en) * 2018-04-20 2018-10-02 林继承 A kind of offshore oil exploitation method
CN108612505B (en) * 2018-04-20 2020-10-30 淮安奥正网络科技有限公司 Offshore oil exploitation method
RU2721011C1 (en) * 2019-01-29 2020-05-15 Шинда (Тангшан) Креатив Оил Енд Гас Екуипмент Ко., Лтд. Pipe with steel casing, providing super long thermal insulation, and method of machining thereof

Also Published As

Publication number Publication date
GB9914868D0 (en) 1999-08-25

Similar Documents

Publication Publication Date Title
GB2351301A (en) Concentric catenary riser
US4153278A (en) Hydraulically operated misalignment connector
US20130269947A1 (en) Marine Subsea Assemblies
EP2458132B1 (en) Gas handler, riser assembly, and method
US7025535B2 (en) Seafloor/surface connecting installation for a submarine pipeline which is connected to a riser by means of at least one elbow pipe element that is supported by a base
US20120273213A1 (en) Marine subsea riser systems and methods
US9695665B2 (en) Subsea chemical injection system
US4260022A (en) Through the flow-line selector apparatus and method
NO330442B1 (en) System and method for producing hydrocarbons from a subsea well
NO20121224A1 (en) Underwater wellhead with segmented fatigue reduction sleeve
EA026518B1 (en) Assembly for connecting a subsea riser
GB2346188A (en) Concentric offset riser
US10022756B2 (en) Method and system for recovering and displacing fluid from a pipe
CA2055437C (en) Device for protecting wells from corrosion or deposits caused by the nature of the fluid produced or located therein
US5462119A (en) Tubing hanging set for a submarine oil-well, running tool for its placing and handling method
US9255458B2 (en) Method and system for sealing and handling pipe
WO2011039587A2 (en) Riser termination
AU2016259436B2 (en) Side entry flow spool and use thereof
RU2731435C1 (en) Above-water circulating head
AU2017379548B2 (en) Subsea wellhead monitoring and controlling
RU2763188C1 (en) Device for temporary conservation
Ritter et al. Popeye project: Subsea system
SU1594267A1 (en) Downhole equipment for washing and isolating annulus and tube space
de Cerqueira et al. Subsea Pipeline Gathering System
US20070209730A1 (en) Sub-sea pipe-in-pipe riser/production system

Legal Events

Date Code Title Description
WAP Application withdrawn, taken to be withdrawn or refused ** after publication under section 16(1)