EP1532319A1 - Damn structure for liquids and bulk material - Google Patents

Damn structure for liquids and bulk material

Info

Publication number
EP1532319A1
EP1532319A1 EP03794938A EP03794938A EP1532319A1 EP 1532319 A1 EP1532319 A1 EP 1532319A1 EP 03794938 A EP03794938 A EP 03794938A EP 03794938 A EP03794938 A EP 03794938A EP 1532319 A1 EP1532319 A1 EP 1532319A1
Authority
EP
European Patent Office
Prior art keywords
pallets
pressure
dam
support
pallet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP03794938A
Other languages
German (de)
French (fr)
Other versions
EP1532319B1 (en
Inventor
Holger Pötzsch
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from DE2002140779 external-priority patent/DE10240779A1/en
Priority claimed from DE2002153889 external-priority patent/DE10253889B4/en
Priority claimed from DE2002158087 external-priority patent/DE10258087B4/en
Application filed by Individual filed Critical Individual
Publication of EP1532319A1 publication Critical patent/EP1532319A1/en
Application granted granted Critical
Publication of EP1532319B1 publication Critical patent/EP1532319B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Definitions

  • the invention relates to a dam structure for liquids and bulk goods with two rows of inclined pressure pallets and support pallets and a sealing film on the pressure side of the pressure pallet.
  • Such dam structures are required, for example, to achieve an increase in the dike crown of an existing dike. They can also be used to build a temporary dike on streets or other areas. For this purpose, it is known to place pallets arranged in two rows at an angle to one another, so that a triangular cross-section is formed, on the pressure side of which a sealing film is attached for sealing. The lower edge of the sealing film is usually fixed by sandbag pads.
  • Dam structures can also be used to set up a receiving basin for water or other liquids or bulk goods on a flat surface. It is important that such dam structures can be erected quickly and with little work and that they can also be dismantled easily and without residue. To this end, materials that are readily available on site should be used to a significant extent.
  • Pallets that can be used for these purposes are available in the form of the standardized, commercially available Euro nail pallets on a large scale wherever goods are on Pallets are transported and stored.
  • the risk of such instabilities in the dam structure is particularly great if the subsurface does not give the dam structure and in particular the pallets a sufficiently secure hold.
  • a major disadvantage of the previously known dam structures made from pallets was that they could not statically withstand the pressures that occurred.
  • the object of the invention is therefore to design a dam structure of the type mentioned at the outset in such a way that a safe and stable connection of the dam structure is achieved with simple and rapid erection.
  • This object is achieved in that the pressure pallets and the support pallets are each connected to one another by tension-pressure anchors.
  • Longitudinal dam-extending tension-pressure anchors are achieved in a stable, triangular-shaped dam structure that does not lose its basic structure even with relief or increased loads and in particular does not collapse if the pressure pallets or the support pallets do not hold sufficiently on the find the respective surface.
  • pressure pallets Context referred to as "pressure pallets" and the pallets on the support side (referred to in this context as “support pallets”), even on smooth surfaces such as concrete surfaces, asphalt roads, sidewalks, paving, etc.
  • support pallets are offset from the pressure pallets arranged so that one support pallet bridges the butt joint between the two opposite pressure pallets and vice versa. This creates a coherent, three-dimensional network.
  • the pressure pallets and the support pallets with their lower edges are positively received in pressure-side and support-side channel profiles each passing through a plurality of pallets, and that the pressure-side and support-side channel profiles are provided the connecting bars forming tension-pressure anchors are connected to one another.
  • the joints of the channel profiles are bridged by the set pallets and also result in a bond.
  • the channel profiles correspond to these pallet edges in their areas receiving the pallet edges.
  • the channel profiles give the lower edges of the pallets a secure hold and at the same time create a connection between adjacent pallets.
  • the channel profiles serve to absorb the forces from the connecting strips, which in this embodiment form the tension-pressure anchors according to the invention.
  • connection anchors forming tension-pressure anchors.
  • accumulation profiles can be placed, which protrude above the upper edge of the pressure pallets and offer the possibility of further increasing the dam to be formed.
  • the pressure-side sealing film is attached to the top edge of the pressure pallets or - if available - by means of film clips that can be attached from above Traffic jam elevation profile can be determined. This not only establishes the sealing film, but also connects adjacent pressure pallets or adjacent accumulation profiles.
  • upper support pallets are arranged, which support the accumulation profile with their upper edge.
  • the upper support pallets are preferably connected at their lower edges to the lower edge of the lower support pallets via tie rods. As a result, the supporting force absorbed by the upper support pallets is transferred to the entire structure of the dam structure has been initiated, so that it receives a high degree of inherent stability even without separate fixing on the ground.
  • the anchor post extends through a suitable opening of a section of the train connection anchor lying on the floor, so that the train connection anchor is secured against horizontal displacement directly on the floor surface,
  • the inventive solution namely connecting strips or connecting anchors and possibly gutter profiles, a complete inherent stability of the dam construction will be using a few simple additional components, achieved ', which is thus firmly on soft or elastic surface. All parts of the dam structure can be transported easily and quickly are erected, result in a stable structure and are reusable. The result is an exactly formed dam structure that hardly leaves any contamination when removed. These dam structures can be used both as a preventive safety measure and as a dike elevation.
  • Pallet stocks can be used.
  • the dam structure can be used worldwide and can be quickly assembled and disassembled without additional tools. All parts are reusable and have a long service life even under extreme environmental influences.
  • the weight of all parts that are required for the dam construction according to the invention is relatively low; therefore, the transport of the parts to the place of use is much easier compared to sandbag dams.
  • the invention also relates to the use of clamping elements for fastening the films to the pressure pallets, the spaces between pallet boards forming cutouts for receiving the clamping elements clamping the film.
  • the clamping element can consist of a clamping body (61) which has at least one rising cam surface on its circumference. It is provided that at least on the cam surface and / or on the circumferential surface opposite it, a ridge running in the circumferential direction projects radially out of the cam surface and / or the opposite circumferential surface, and that the clamping body has a key attachment which is accessible on the front side.
  • FIG. 4 is a view in the direction of arrow IV in FIG. 3, the sealing film having been omitted,
  • 15 shows a further dam structure in cross section and 16 is a plan view in the direction of arrow XVI in FIG. 15, the sealing film having been omitted,
  • FIG. 19 in a representation similar to Fig. 1
  • Fig. 25 in an enlarged vertical partial section a pressure-side channel profile piece of a dam structure and 26 is a plan view in the direction of arrow XXVI in FIG. 25.
  • the dam structure shown in FIG. 1 in a vertical cross-section has two rows of pressure pallets 1 and support pallets 2 which are offset at an angle to one another and which are preferably wooden nail pallets in the standardized dimensions of Euro pallets.
  • On the pressure side (right in Fig. 1) on which the water to be retained is another
  • Foil clips 4 is set at the top of the printing pallets 3.
  • the lower edge of the sealing film 3 is secured by a series of sandbags 5 and fixed to the bottom 6, for example a dike crown.
  • the support pallets 2 reach under the upper edge of the pressure pallets 1.
  • the two rows of pressure pallets 1 and support pallets 2 are connected to one another in their lower region by tension-pressure anchors.
  • the pressure pallets 1 have their lower edges in pressure-side channel profiles 7 (FIG. 9) which run through a plurality of pallets and are extruded.
  • the lower edges of the support pallets 2 are in the support side
  • Channel profiles 8 (Fig. 10), which are also extruded from plastic. On both channel profiles 7 and 8, In each case, an upwardly open channel 9 or 10 is formed, in which the pallet edges are appropriately set in the required inclination and are thus received in a form-fitting manner.
  • a sharp rib 10a projecting into the trough 10 or 9 (only shown in FIG. 10) claws into the end wood of the pallet set up there and gives it additional support.
  • the channel profiles 7 and 8 are connected to one another by the connecting strips 11 forming the tension-pressure anchors.
  • the connecting strips 11 engage in recesses 12, 13 of flange strips 14 and 15 of the channel profiles 7 and 8, which are parallel to the floor, and are hooked there in a form-fitting manner.
  • the two channel profiles 7, 8 also have a flange strip 16 and 17, which is also parallel to the floor.
  • the flanged strips 14, 15, 16 and 17 create a broadened dividing surface of the channel profiles 7 and 8, so that they do not sink into soft ground.
  • one projection 18 or 19 on the underside of the channel profile 7 or 8 forms an anchoring projection which secures the position of the dam structure. The pressure exerted on the dam structure in the event of a load also holds the dam structure on the ground.
  • the dam structure shown in FIG. 2 differs from the previously described dam structure essentially in that the tension-pressure anchor connecting the pressure-side pallets 1 and the support-side pallets 2 is preferably made of metal Connection anchor 20 (Fig. 5, 6) is formed, which connects the pressure pallets 1 and support pallets 2 with each other in a form-fitting manner.
  • the connecting anchor 20, which is preferably produced by folding from a sheet steel strip and / or welding or by extrusion, and which is shown in a side view in FIG. 5 and in a plan view in FIG. 6, has a downwardly open clamp end piece 21 or 22, which can be plugged onto a lower longitudinal board of the pressure pallet 1 or the support pallet 2.
  • the connecting anchor 20 which is preferably produced by folding from a sheet steel strip and / or welding or by extrusion, and which is shown in a side view in FIG. 5 and in a plan view in FIG. 6, has a downwardly open clamp end piece 21 or 22, which can be plugged onto a lower longitudinal board of the pressure pallet 1 or the support
  • One of the one clamp end piece 22 obliquely projecting supporting spur 25 serves to further support within the support pallet 2. In the erected state of the ⁇ dam construction, the connecting anchor 20 is not 'be removed.
  • 1 accumulation increase profiles 28 are placed on the upper edge of the pressure pallets, which also preferably consist of extruded material and protrude beyond the upper edge of the pressure pallets 1.
  • a foot piece 29 of the traffic jam elevation profile 28 engages around two longitudinal boards of the pressure pallets 1 and is supported with a central part 30 on the upper edge thereof. The pressure exerted on the dam structure in the event of a load additionally holds the accumulation profile 28.
  • the sealing film 3 is placed over the upper edge of the traffic jam elevation profile 28 and fixed and secured there by means of a film clip 4 '(FIG. 14) from above, which at the same time forms a connection between adjacent traffic jam elevation profiles 28.
  • FIG. 3 shown embodiment of a dam structure differs from the embodiment of FIG. 2 only in that, in addition to the connecting anchors 20 in the foot region of the pallets 1 and 2, a connection via channel profiles 7, 8 and connecting strips 11 connecting them is also provided, as in FIG. 1 described.
  • the dam structure shown in a vertical cross section like the previously described embodiments, has two rows of oblique opposed pressure pallets 1 and lower support pallets 2, which are preferably wooden nail pallets in the standardized dimensions of Euro pallets.
  • At the top of the pressure pallets 1 are made of sheet steel or aluminum
  • a sealing film 34 On the pressure side (on the right in Fig. 15) on which the water to be retained, another liquid or a flowable bulk material is present, on the outside of the pressure pallet 1 and the accumulation profile 33 there is a sealing film 34, which over the upper edge of the in a Row arranged traffic jam elevation profiles 33 placed and fixed by means of spaced, from above attached film clips 35 on the upper edge of the traffic jam elevation profiles 33.
  • the lower edge of the sealing film 34 is secured by a series of sandbags ⁇ " or bricks and - on the floor 36, - for example, a dike crown or a road surface.
  • the sealing film 34 which is made of high-strength film material, preferably has on its edge lying on the bottom 36 a prefabricated edge strip 34a made of soft film, on which the sandbags or bricks lie.
  • the softer film material of the edge strip 34a ensures a better seal • at the bottom 36.
  • ready-made film corners can be arranged which overlap the sealing film there.
  • the sealing film can also consist in one piece of a uniform film material that has an optimal sealing effect in the sealing area on the bottom, but is sufficiently tear-resistant and extends over the entire height of the dike structure, which is, for example, 800 or 1150 mm.
  • the lower support pallets 2 reach under the upper edge of the print pallets 1.
  • the two rows of print pallets 1 and lower support pallets 2 are in their lower
  • tension-pressure anchors which are designed as connecting anchors 37.
  • upper support pallets 38 are arranged, which support the accumulation wall increase profiles 33 with their upper edge.
  • the upper support pallets 38 are arranged ' at a lateral distance from one another ' in this exemplary embodiment, in such a way that the upper support pallets 38 each engage the joint of two accumulation migration profiles 33.
  • the upper support pallets are each connected at their lower edge to the lower edge of the lower support pallet 2 via tension connection anchors 39.
  • Each tie link 39 engages with an upwardly extending hook 40 in the lower edge of the upper support pallet 38, while a hook 41 formed on the opposite edge of the tie link 39 opens downward around the lower board at the lower edge of the lower support pallet 2 attacks. In this way, a tensile connection of the two support pallets 38 and 2 is made at their lower edges.
  • each anchor post 42 extends through a suitable opening 43 of a section of the train connection anchor 39 lying on the floor 36 in order to secure this and thus also the support pallets 2 and 38 against horizontal displacement.
  • the anchor post 42 is supported on an edge 44 of the lower edge of the upper support pallet 38 which runs at a distance above the floor 36 and is thereby secured against bending even in the case of a thin version.
  • Section 47 which engages in the print pallet 1. It is expediently provided that the connecting anchors each have a downwardly open clamp end piece at both ends, which can be plugged onto a lower longitudinal board of the pressure pallet 1 or the lower support pallet 2.
  • the dam construction described takes into account in particular the fact that there is a triple pressure in the lower half of the dam height in comparison to the upper half. This pressure distribution is optimally supported.
  • the dam structure is inherently stable and stable, and its stability can be increased by the anchor posts 42, which are, however, only mandatory for smooth floors.
  • clamping elements 50 each consist of a clamping body 61 which, together with the film 34 forming a pocket, is inserted into the intermediate space between adjacent pallet boards 2 and holds the film 34 in a clamping manner.
  • the space between adjacent pallet boards 2 here forms a recess 63 receiving the clamping body 61.
  • the clamping body 61 consists of an oval disk, the circumferential areas of which increase from the smallest to the largest disk diameter
  • a ridge 66 extending in the circumferential direction and extending over the entire disk circumference of the clamping body 61 projects radially from the circumferential surface 65 of the clamping body 61 forming the cam surface.
  • the ridge 66 is approximately roof-shaped in cross section and has a tip angle of 120 ° in cross section. Its height is approximately 1.5 mm.
  • the clamping body 61 has a key attachment which is accessible from the front and which in the exemplary embodiment shown is a hexagon socket recess 67 into which a conventional hexagon socket key fits.
  • the ridge 66 forms the radially most protruding peripheral region at each peripheral point.
  • the cam surface 65 extends from the ridge 66 on both sides.
  • 19 and 20 show that the pressure pallets 1 are connected to the support pallets 2 by brackets 68, the end boards 69 respectively being adjacent Reach around the pressure pallets 1 and are hooked with their hook-like ends 68a under each of the upper, longitudinal boards 70 of the support pallets 2.
  • brackets 68 the end boards 69 respectively being adjacent Reach around the pressure pallets 1 and are hooked with their hook-like ends 68a under each of the upper, longitudinal boards 70 of the support pallets 2.
  • leveling pieces 71 are fitted onto the accumulation profile 28, which serve to compensate for an uneven ground profile in such a way that the upper edge of the dam structure runs largely horizontally.
  • Leveling pieces 71 are aligned in the same width in each case in alignment with the assigned pressure pallets 1 and accumulation wall increase profiles 28. It is shown on the right in FIG. 21 that the leveling pieces 71 can also be arranged offset in each case such that they each bridge the joint between adjacent traffic jam elevation profiles 28.
  • a plug-in body 71a is provided on the back of each, which can be inserted into an associated recess 28a of the accumulation profile 28.
  • Sealing film for example in one of the previously described embodiments, to form a channel 73 can be connected to each other by tie rods 74.
  • Channels 73 formed in this way can serve to divert a stream or river.
  • the forces acting between the two dam structures 72 are absorbed by the tie rods 74. 23 and 24, the tie rods 74 engage the connecting anchors 37, which connect the pressure pallets 1 and the support pallets 2 of each of the two dam structures 72.
  • the tie rods 74 are one-piece strips which are connected in an articulated manner to the connecting anchors 37. 24 shows that the tie rods 74 can be chains, for example. If the pressure pallets are received in pressure-side channel profile pieces 7, as is shown in FIG. 3, the tie rods 74 connecting the two dam structures 72 can engage on the channel profile pieces 7 of the two dam structures 72 via insertable shaped pieces 75 (FIGS. 25 and 26). These fittings 75 are longitudinally displaceable on profiled edge strips 76 of the channel profile pieces 7.
  • the longitudinally displaceable shaped pieces 75 each have a bolt 77 which bridges a recess 78 on the shaped piece 75 and on which the chains forming the tie rods 74 engage.
  • the chains can for example

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Pallets (AREA)
  • Materials For Medical Uses (AREA)
  • Soil Conditioners And Soil-Stabilizing Materials (AREA)
  • Revetment (AREA)
  • Graft Or Block Polymers (AREA)

Abstract

A damn structure for liquids and bulk material, comprising two rows of pressure pallets (1), which are arranged in such a way that they are placed against each other and inclined in an offset manner, and support pallets (2) and a sealing film (3) disposed on the pressure side of the pressure pallets (1). The pressure pallets (1) and the support pallets (2) are respectively connected to each other by means of traction-pressure tie elements (11) forming a static assembly. The lower edges of the pressure pallets (1) and the support pallets (2) can be received in a positive fit by pressure-sided and support-sided groove profiles (7,8) which respectively extend through several pallets (1,2) and are connected to each other by means of the traction-pressure tie elements (11).

Description

Dammaufbau für Flüssigkeiten und SchüttgüterDam construction for liquids and bulk goods
Die Erfindung betrifft einen Dammaufbau für Flüssigkeiten und Schüttgüter mit zwei Reihen von schräg gegeneinander gestellten Druckpaletten und Stützpaletten und einer Dichtungsfolie auf der Druckseite der Druckpalette.The invention relates to a dam structure for liquids and bulk goods with two rows of inclined pressure pallets and support pallets and a sealing film on the pressure side of the pressure pallet.
Derartige Dammaufbauten werden beispielsweise benötigt, um eine Erhöhung der Deichkrone eines bestehenden Deichs zu erreichen. Sie können aber auch dazu dienen, auf Straßen oder sonstigen Flächen einen provisorischen Deich zu errichten. Hierzu ist es bekannt, in zwei Reihen angeordnete Paletten schräg gegeneinander zu stellen, so dass ein im Querschnitt dreieckförmiger Aufbau entsteht, an dessen Druckseite zur Abdichtung eine Dichtungsfolie angebracht wird. Üblicherweise wird die Dichtungsfolie an ihrem unteren Rand durch Sandsackauflagen festgelegt .Such dam structures are required, for example, to achieve an increase in the dike crown of an existing dike. They can also be used to build a temporary dike on streets or other areas. For this purpose, it is known to place pallets arranged in two rows at an angle to one another, so that a triangular cross-section is formed, on the pressure side of which a sealing film is attached for sealing. The lower edge of the sealing film is usually fixed by sandbag pads.
Neben dem Einsatz bei Hochwasser können derartigeIn addition to use during floods, such
Dammaufbauten auch eingesetzt werden, um auf einer ebenen Fläche ein Aufnahmebecken für Wasser oder andere Flüssigkeiten oder auch Schüttgüter zu errichten. Wichtig ist, dass solche Dammaufbauten schnell und mit geringem Arbeitsaufwand errichtet werden können und auch leicht und rückstandslos wieder abzubauen sind. Hierbei sollen in wesentlichem Umfang Materialien verwendet werden, die vor Ort leicht verfügbar sind.Dam structures can also be used to set up a receiving basin for water or other liquids or bulk goods on a flat surface. It is important that such dam structures can be erected quickly and with little work and that they can also be dismantled easily and without residue. To this end, materials that are readily available on site should be used to a significant extent.
Paletten, die für diese Zwecke brauchbar sind, stehen in Form der genormten, handelsüblichen Euro-Nagelpaletten in großem Umfang überall dort zur Verfügung, wo Güter auf Paletten transportiert und gelagert werden. Es hat sich aber gezeigt, dass durch das einfache Gegeneinandersteilen von Paletten keine ausreichende Stabilität des so hergestellten Dammaufbaus erzielt werden kann. Sowohl bei Endlastung als auch bei einer erhöhten Belastung besteht die Gefahr, dass der Dammaufbau in sich zusammenfällt und damit seine Funktionsfähigkeit verliert. Die Gefahr solcher Instabilitäten des Dammaufbaus ist besonders groß, wenn der Untergrund dem Dammaufbau und insbesondere den Paletten keinen ausreichend sicheren Halt gibt. Ein wesentlicher Nachteil der bisher bekannten Dammaufbauten aus Paletten bestand darin, dass diese statisch den auftretenden Drücken nicht standhalten konnten.Pallets that can be used for these purposes are available in the form of the standardized, commercially available Euro nail pallets on a large scale wherever goods are on Pallets are transported and stored. However, it has been shown that simply dividing pallets against each other cannot achieve sufficient stability for the dam structure thus produced. There is a risk that the dam structure will collapse and lose its functionality, both in the event of a final load and an increased load. The risk of such instabilities in the dam structure is particularly great if the subsurface does not give the dam structure and in particular the pallets a sufficiently secure hold. A major disadvantage of the previously known dam structures made from pallets was that they could not statically withstand the pressures that occurred.
Die Verwendung von Sandsackwällen als Dammaufbauten für die Erhöhung von Deichkronen oder die Errichtung von Notdeichen ist im Ergebnis sehr unsicher, aufwendig und mit einer Kontamination der Umgebung verbunden. Die bekannte Verwendung von folienbespannten, lose zusammengestellten Palettengerüsten, insbesondere aus Euro-Paletten, ist zwar einfacher, aber im Ergebnis unsicher, da der zur Abtragung der auftretenden Kräfte erforderliche statische Verbund in weichen Dammkronen oder auf glatten Fläche nicht oder nur durch das Einschlagen von Arretierungen zu erreichen ist .The use of sandbag walls as dam structures for the elevation of dike crowns or the construction of emergency dikes is very unsafe, complex and associated with contamination of the environment. The known use of film-covered, loosely assembled pallet frames, in particular from euro pallets, is simpler, but the result is uncertain because the static bond required to remove the forces occurring in soft embankment crowns or on smooth surfaces is not or only by locking can be reached.
Aufgabe der Erfindung ist es daher, einen Dammaufbau der eingangs genannten Gattung so auszuführen, dass bei einfacher und schneller Errichtung ein sicherer und stabiler Zusammenhang des Dammaufbaus erreicht wird. Diese Aufgabe wird erfindungsgemäß dadurch gelöst, dass die Druckpaletten und die Stützpaletten jeweils durch Zug-Druck-Anker miteinander verbunden sind.The object of the invention is therefore to design a dam structure of the type mentioned at the outset in such a way that a safe and stable connection of the dam structure is achieved with simple and rapid erection. This object is achieved in that the pressure pallets and the support pallets are each connected to one another by tension-pressure anchors.
Durch die Verbindung durch sich quer zurThrough the connection through itself across
Dammlängsrichtung erstreckende Zug-Druck-Anker wird ein in sich stabiler, im Querschnitt dreieckförmiger Dammaufbau erzielt, der auch bei Entlastungen oder erhöhten Belastungen seine grundsät liche Struktur nicht verliert und insbesondere nicht in sich zusammenfällt, wenn die Druckpaletten oder die Stützpaletten keinen ausreichenden Halt auf dem jeweiligen Untergrund finden.Longitudinal dam-extending tension-pressure anchors are achieved in a stable, triangular-shaped dam structure that does not lose its basic structure even with relief or increased loads and in particular does not collapse if the pressure pallets or the support pallets do not hold sufficiently on the find the respective surface.
Man erreicht somit einen statisch sicheren Verbund der auf der Druckseite stehenden Paletten (in diesemA statically secure bond of the pallets on the pressure side (in this
Zusammenhang als "Druckpaletten" bezeichnet) und der auf der Stützseite stehenden Paletten (in diesem Zusammenhang als "Stützpaletten" bezeichnet) , und zwar auch auf glattem Untergrund, wie Betonflächen, Asphaltstraßen, Gehwegen, Pflasterungen usw. Vorzugsweise sind die Stützpaletten gegenüber den Druckpaletten versetzt angeordnet, so dass jeweils eine Stützpalette die Stoßfuge zwischen den beiden gegenüber liegenden Druckpaletten überbrückt und umgekehrt. Dadurch entsteht ein zusammenhängender, dreidimensionaler Verbund.Context referred to as "pressure pallets") and the pallets on the support side (referred to in this context as "support pallets"), even on smooth surfaces such as concrete surfaces, asphalt roads, sidewalks, paving, etc. Preferably, the support pallets are offset from the pressure pallets arranged so that one support pallet bridges the butt joint between the two opposite pressure pallets and vice versa. This creates a coherent, three-dimensional network.
Gemäß einer Ausgestaltung des Erfindungsgedankens ist vorgesehen, dass die Druckpaletten und die Stützpaletten mit ihren unteren Rändern in jeweils über mehrere Paletten durchlaufenden druckseitigen und stutzseitigen Rinnenprofilen formschlüssig aufgenommen sind und dass die druckseitigen und stutzseitigen Rinnenprofile durch die Zug-Druck-Anker bildende Verbindungsleisten miteinander verbunden sind. Die Stöße der Rinnenprofile werden durch die eingestellten Paletten überbrückt und ergeben auch hier einen Verbund. Die Rinnenprofile entsprechen in ihren die Palettenränder aufnehmenden Bereichen diesen Palettenrändern.According to an embodiment of the inventive concept, it is provided that the pressure pallets and the support pallets with their lower edges are positively received in pressure-side and support-side channel profiles each passing through a plurality of pallets, and that the pressure-side and support-side channel profiles are provided the connecting bars forming tension-pressure anchors are connected to one another. The joints of the channel profiles are bridged by the set pallets and also result in a bond. The channel profiles correspond to these pallet edges in their areas receiving the pallet edges.
Die Rinnenprofile geben den unteren Rändern der Paletten einen sicheren Halt und stellen zugleich eine Verbindung zwischen nebeneinander stehenden Paletten her. Außerdem dienen die Rinnenprofile zur Aufnahme der Kräfte aus den Verbindungsleisten, die bei dieser Ausführung die Zug- Druck-Anker gemäß der Erfindung bilden.The channel profiles give the lower edges of the pallets a secure hold and at the same time create a connection between adjacent pallets. In addition, the channel profiles serve to absorb the forces from the connecting strips, which in this embodiment form the tension-pressure anchors according to the invention.
Gemäß einer anderen Ausführung der Erfindung ist vorgesehen, dass die Druckpaletten und die Stützpaletten durch die Zug-Druck-Anker bildende Verbindungsanker miteinander verbunden sind. Diese Verbindungsanker greifen an den Paletten selbst an, so dass hierbei die Verwendung von Rinnenprofilen nicht unbedingt erforderlich, in vielen Fällen aber gleichwohl zweckmäßig ist .According to another embodiment of the invention, it is provided that the pressure pallets and the support pallets are connected to one another by the connection anchors forming tension-pressure anchors. These connecting anchors engage the pallets themselves, so that the use of channel profiles is not absolutely necessary, but is nevertheless advisable in many cases.
Am oberen Rand der Druckpaletten sind Stauwanderhöhungsprofile aufsetzbar, die über die Oberkante der Druckpaletten hinausragen und die Möglichkeit zu einer weiteren Erhöhung des zu bildenden Damms bieten.On the upper edge of the pressure pallets, accumulation profiles can be placed, which protrude above the upper edge of the pressure pallets and offer the possibility of further increasing the dam to be formed.
Die druckseitige Dichtungsfolie ist mittels von oben aufsetzbarer Folienklammern am oberen Rand der Druckpaletten oder - sofern vorhanden - des Stauwanderhöhungsprofils festlegbar. Damit wird nicht nur eine Festlegung der Dichtungsfolie, sondern auch eine Verbindung benachbarter Druckpaletten bzw. benachbarter Stauwanderhöhungsprofile erreicht .The pressure-side sealing film is attached to the top edge of the pressure pallets or - if available - by means of film clips that can be attached from above Traffic jam elevation profile can be determined. This not only establishes the sealing film, but also connects adjacent pressure pallets or adjacent accumulation profiles.
Gemäß einer bevorzugten Ausgestaltung der Erfindung ist vorgesehen, dass mindestens abschnittsweise über den die Druckpaletten stützenden, unteren Stützpaletten obere Stützpaletten angeordnet sind, die mit ihrem oberen Rand die Stauwanderhöhungsprofile stützen.According to a preferred embodiment of the invention it is provided that at least in sections above the lower support pallets supporting the pressure pallets, upper support pallets are arranged, which support the accumulation profile with their upper edge.
Dadurch wird einerseits die Möglichkeit geschaffen, eine wesentliche Erhöhung des Dammaufbaus durch die Verwendung verhältnismäßig hoher Stauwanderhöhungsprofile zu erreichen, weil diese durch die zusätzlichen oberenOn the one hand, this creates the possibility of achieving a substantial increase in the dam structure through the use of relatively high accumulation profiles, because this is due to the additional upper ones
Stützpaletten gestützt werden. Zugleich wird aber auch insgesamt eine weitere Erhöhung der Stabilität und Festigkeit des Dammaufbaus erreicht, so dass auch die durch die Vergrößerung der Stauhöhe erhöhten Druckkräfte durch einen sicheren dreidimensionalen statischen Verbund aufgenommen werden können, der durch die miteinander verschränkten Paletten erzielt wird. Trotz der Vergrößerung der Stauhöhe besteht keine Gefahr, dass der Deichaufbau nach hinten kippt, weil die auf der Vorderseite angeordnete Dichtungsfolie den Dammaufbau an der Vorderseite im befluteten Zustand nach unten zieht und hält .Support pallets are supported. At the same time, however, overall a further increase in the stability and strength of the dam structure is achieved, so that the pressure forces increased by increasing the dam height can also be absorbed by a secure three-dimensional static bond which is achieved by the intertwined pallets. Despite the increase in the accumulation height, there is no danger that the dike structure will tip backwards because the sealing film arranged on the front side pulls and holds the dam structure on the front side in the flooded state.
Vorzugsweise sind die oberen Stützpaletten an ihrem unteren Rand jeweils über Zuganker mit dem unteren Rand der unteren Stützpaletten verbunden. Dadurch wird die von den oberen Stützpaletten aufgenommene Stützkraft in den gesamten Verbund des Dammaufbaus eingeleitet, so dass dieser auch bereits ohne gesonderte Festlegung am Boden eine hohe Eigenstabilität erhält.The upper support pallets are preferably connected at their lower edges to the lower edge of the lower support pallets via tie rods. As a result, the supporting force absorbed by the upper support pallets is transferred to the entire structure of the dam structure has been initiated, so that it receives a high degree of inherent stability even without separate fixing on the ground.
Besonders vorteilhaft ist es aber, den unteren Rand der unteren Stützpaletten und/oder die Zugverbindungsanker, die die obere und die untere Stützpalette an ihren unteren Rändern verbinden, durch in den Boden eingeschlagene Ankerpfosten zu sichern. Die auftretenden Horizontalkräfte werden dadurch über die Ankerpfosten in den Boden abgetragen, so dass eine Horizontalverschiebung des Dammaufbaues sicher verhindert wird.It is particularly advantageous, however, to secure the lower edge of the lower support pallets and / or the tension connection anchors, which connect the upper and lower support pallets at their lower edges, by anchor posts hammered into the floor. The horizontal forces that occur are thereby dissipated into the ground via the anchor posts, so that a horizontal displacement of the dam structure is reliably prevented.
Besonders zweckmäßig ist es, wenn sich der Ankerpfosten durch eine passende Öffnung eines am Boden liegenden Abschnitts des Zugverbindungsankers erstreckt, so dass der Zugverbindungsanker unmittelbar an der Bodenfläche gegen eine HorizontalVerschiebung gesichert wird,It is particularly expedient if the anchor post extends through a suitable opening of a section of the train connection anchor lying on the floor, so that the train connection anchor is secured against horizontal displacement directly on the floor surface,
Eine Verbiegung auch verhältnismäßig dünner Ankerpfosten kann vorteilhaft dadurch verhindert werden, dass sich der Ankerpfosten an einer im Abstand über dem Boden verlaufenden Kante des unteren Randes der oberen Stützpalette abstützt.Bending of even relatively thin anchor posts can advantageously be prevented by the anchor post being supported on an edge of the lower edge of the upper support pallet running at a distance above the floor.
Durch die erfindungsgemäße Lösung wird unter Verwendung von wenigen und einfachen zusätzlichen Bauteilen, nämlich Verbindungsleisten oder Verbindungsankern und ggf. Rinnenprofilen, eine vollständige Eigenstabilität des Dammaufbaus erzielt', der somit auch auf weichem oder elastischem Untergrund fest steht. Alle Teile des Dammaufbaus können leicht transportiert und schnell aufgerichtet werden, ergeben einen stabilen Aufbau und sind wieder verwendbar. Es ergibt sich ein exakt ausgebildeter Dammaufbau, der beim Abtragen kaum Kontaminierungen hinterlässt . Diese Dammaufbauten können sowohl als präventive Sicherheitsmaßnahme als auch als Deicherhöhung eingesetzt werden.The inventive solution namely connecting strips or connecting anchors and possibly gutter profiles, a complete inherent stability of the dam construction will be using a few simple additional components, achieved ', which is thus firmly on soft or elastic surface. All parts of the dam structure can be transported easily and quickly are erected, result in a stable structure and are reusable. The result is an exactly formed dam structure that hardly leaves any contamination when removed. These dam structures can be used both as a preventive safety measure and as a dike elevation.
Ein Falschaufbau ist nicht möglich. Eine sichere Statik des Dammaufbaus ist durchgehend gewährleistet, wobei durch die Palettenanordnung eine Eigenstabilisierung erzielt wird. Die Grundbauelemente, nämlich Euro- Paletten, Folien und Sandsäcke oder statt dessen Ziegelsteine zur Festlegung der Folie sind weltweit in ausreichender Menge vorhanden. In Notfallsituationen kann auf die in der Industrie und beim Handel verfügbarenIncorrect construction is not possible. A safe statics of the dam structure is continuously guaranteed, whereby the pallet arrangement ensures self-stabilization. The basic components, namely euro pallets, foils and sandbags or instead bricks for fixing the foil are available in sufficient quantities worldwide. In emergency situations, you can refer to those available in industry and trade
Palettenbestände zurückgegriffen werden. Der Dammaufbau ist weltweit einsetzbar und ohne zusätzliche Werkzeuge schnell montierbar und demontierbar. Alle Teile sind wiederverwendbar und haben auch unter extremen Umgebungseinflüssen eine lange Standzeit.Pallet stocks can be used. The dam structure can be used worldwide and can be quickly assembled and disassembled without additional tools. All parts are reusable and have a long service life even under extreme environmental influences.
Das Gewicht aller Teile, die für den erfindungsgemäßen Dammaufbau benötigt werden, ist verhältnismäßig gering; daher ist der Transport der Teile zum Einsatzort im Vergleich zu Sandsackdämmen ganz wesentlich erleichtert.The weight of all parts that are required for the dam construction according to the invention is relatively low; therefore, the transport of the parts to the place of use is much easier compared to sandbag dams.
Die Erfindung betrifft auch die Verwendung von Klemmelementen zur Befestigung der Folien an den Druckpaletten, wobei die Zwischenräume zwischen Palettenbrettern Aussparungen zur Aufnahme der die Folie klemmenden Klemmelemente bilden. Das Klemmelement kann aus einem Klemmkörper (61) bestehen, der an seinem Umfang mindestens eine ansteigende Nockenfläche aufweist. Dabei ist vorgesehen, dass mindestens an der Nockenfläche und/oder an der ihr gegenüberliegenden Umfangsflache ein in Umfangsriehtung verlaufender Grat aus der Nockenfläche und/oder der gegenüberliegenden Umfangsflache radial vorspringt und dass der Klemmkörper einen stirnseitig zugänglichen Schlüsselansatz aufweist.The invention also relates to the use of clamping elements for fastening the films to the pressure pallets, the spaces between pallet boards forming cutouts for receiving the clamping elements clamping the film. The clamping element can consist of a clamping body (61) which has at least one rising cam surface on its circumference. It is provided that at least on the cam surface and / or on the circumferential surface opposite it, a ridge running in the circumferential direction projects radially out of the cam surface and / or the opposite circumferential surface, and that the clamping body has a key attachment which is accessible on the front side.
Weitere vorteilhafte Ausgestaltungen der Erfindung sind Gegenstand weiterer abhängiger Ansprüche.Further advantageous embodiments of the invention are the subject of further dependent claims.
Die Erfindung wird nachfolgend an Ausführungsbeispielen näher erläutert, die in der Zeichnung dargestellt sind. Es zeigt :The invention is explained in more detail below using exemplary embodiments which are illustrated in the drawing. It shows :
Fig. 1 eine 'Dammaufbau im Querschnitt,1 is a ' dam structure in cross section,
Fig. 2 einen abgewandelten Dammaufbau im Querschnitt,2 shows a modified dam structure in cross section,
Fig. 3 einen weiteren abgewandelten Dammaufbau im Querschnitt,3 shows a further modified dam structure in cross section,
Fig. 4 eine Ansicht in Richtung des Pfeiles IV in Fig. 3, wobei die Dichtungsfolie weggelassen wurde,4 is a view in the direction of arrow IV in FIG. 3, the sealing film having been omitted,
Fig. 5-14 einzelne Bauteile der dargestellten Dammaufbauten,5-14 individual components of the illustrated dam structures,
Fig. 15 einen weiteren Dammaufbau im Querschnitt und Fig. 16 eine Draufsicht in Richtung des Pfeiles XVI in Fig. 15, wobei die Dichtungsfolie weggelassen wurde,15 shows a further dam structure in cross section and 16 is a plan view in the direction of arrow XVI in FIG. 15, the sealing film having been omitted,
Fig. 17 in einem vergrößerten Teilschnitt aus Fig. 15 ein Klemmelement zur Befestigung der Folie,17 in an enlarged partial section from FIG. 15, a clamping element for fastening the film,
Fig. 18 eine Stirnansicht des Klemmelements gemäß Fig. 17,18 shows an end view of the clamping element according to FIG. 17,
Fig. 19 in einer Darstellung ähnlich der Fig. 1 dieFig. 19 in a representation similar to Fig. 1
Verbindung der Druckpaletten mit den Stützpaletten durch Klammern,Connection of the pressure pallets with the support pallets by means of clamps,
Fig. 20 eine Ansicht in Richtung des Pfeiles XX in Fig. 19,20 is a view in the direction of arrow XX in Fig. 19,
Fig. 21 einen Dammaufbau in einer Seitenansicht mit aufgesetzten Niveauausgleichsstücken,21 a dam structure in a side view with attached leveling pieces,
Fig. 22 in vergrößerter Darstellungsweise die Rückseite der in Fig. 21 gezeigten Niveauausgleichsstücke,22 is an enlarged representation of the back of the leveling pieces shown in FIG. 21,
Fig. 23 die Verbindung zweier Dammaufbauten zur Bildung eines Kanals,23 shows the connection of two dam structures to form a channel,
Fig. 24 Einzelheiten einer abgewandelten Ausführungsform der Verbindung nach Fig. 23,24 shows details of a modified embodiment of the connection according to FIG. 23,
Fig. 25 in einem vergrößerten senkrechten Teilschnitt ein druckseitiges Rinnenprofilstück eines Dammaufbaus und Fig. 26 eine Draufsicht in Richtung des Pfeiles XXVI in Fig. 25.Fig. 25 in an enlarged vertical partial section a pressure-side channel profile piece of a dam structure and 26 is a plan view in the direction of arrow XXVI in FIG. 25.
Der in Fig. 1 in einem senkrechten Querschnitt dargestellte Dammaufbau weist zwei Reihen von schräg gegeneinander versetzt gestellten Druckpaletten 1 und Stützpaletten 2 auf, bei denen es sich vorzugsweise um Holz-Nagelpaletten in den genormten Abmessungen von Euro- Paletten handelt. Auf der Druckseite (rechts in Fig. 1), auf der das zurückzuhaltende Wasser, eine andereThe dam structure shown in FIG. 1 in a vertical cross-section has two rows of pressure pallets 1 and support pallets 2 which are offset at an angle to one another and which are preferably wooden nail pallets in the standardized dimensions of Euro pallets. On the pressure side (right in Fig. 1) on which the water to be retained is another
Flüssigkeit oder ein fließfähiges Schüttgut ansteht, liegt an der Außenseite der Druckpalette 1 eine Dichtungsfolie 3, die über den oberen Rand der in einer Reihe angeordneten Druckpalette 1 gelegt und mittels in Abständen angeordneten, von oben aufsetzbarenIf liquid or a flowable bulk material is present, there is a sealing film 3 on the outside of the pressure pallet 1, which is placed over the upper edge of the pressure pallet 1 arranged in a row and by means of spaced, attachable from above
Folienklammern 4 am oberen Rand der Druckpaletten 3 festgelegt ist. Der untere Rand der Dichtungsfolie 3 wird durch eine Reihe von Sandsäcken 5 gesichert und am Boden 6, beispielsweise einer Deichkrone, festgelegt. Die Stützpaletten 2 greifen unter den oberen Rand der Druckpaletten 1.Foil clips 4 is set at the top of the printing pallets 3. The lower edge of the sealing film 3 is secured by a series of sandbags 5 and fixed to the bottom 6, for example a dike crown. The support pallets 2 reach under the upper edge of the pressure pallets 1.
Die beiden Reihen von Druckpaletten 1 und Stützpaletten 2 sind in ihrem unteren Bereich durch Zug-Druck-Anker miteinander verbunden. Bei dem in Fig. 1 dargestellten Ausführungsbeispiel stehen die Druckpaletten 1 mit ihren unteren Rändern in jeweils über mehrere Paletten durchlaufenden druckseitigen Rinnenprofilen 7 (Fig. 9) , die stranggepresst sind. In ähnlicher Weise stehen die unteren Ränder der Stützpaletten 2 in stutzseitigenThe two rows of pressure pallets 1 and support pallets 2 are connected to one another in their lower region by tension-pressure anchors. In the exemplary embodiment shown in FIG. 1, the pressure pallets 1 have their lower edges in pressure-side channel profiles 7 (FIG. 9) which run through a plurality of pallets and are extruded. Similarly, the lower edges of the support pallets 2 are in the support side
Rinnenprofilen 8 (Fig. 10) , die ebenfalls aus Kunststoff stranggepresst sind. An beiden Rinnenprofilen 7 und 8 ist , jeweils eine nach oben offene Rinne 9 bzw. 10 ausgebildet, in die die Palettenränder passend in der jeweils erforderlichen Schrägstellung eingestellt und somit formschlüssig aufgenommen sind. Eine in die Rinne 10 oder 9 vorspringende scharfe Rippe 10a (nur in Fig. 10 dargestellt) krallt sich in das Stirnholz der dort aufgestellten Palette und gibt ihr zusätzlichen Halt.Channel profiles 8 (Fig. 10), which are also extruded from plastic. On both channel profiles 7 and 8, In each case, an upwardly open channel 9 or 10 is formed, in which the pallet edges are appropriately set in the required inclination and are thus received in a form-fitting manner. A sharp rib 10a projecting into the trough 10 or 9 (only shown in FIG. 10) claws into the end wood of the pallet set up there and gives it additional support.
Die Rinnenprofile 7 und 8 sind durch die Zug-Druck-Anker bildende Verbindungsleisten 11 miteinander verbunden. Die Verbindungsleisten 11 greifen in Ausnehmungen 12, 13 von bodenparallelen Flanschstreifen 14 bzw. 15 der Rinnenprofile 7 bzw. 8 und werden dort formschlüssig eingehakt .The channel profiles 7 and 8 are connected to one another by the connecting strips 11 forming the tension-pressure anchors. The connecting strips 11 engage in recesses 12, 13 of flange strips 14 and 15 of the channel profiles 7 and 8, which are parallel to the floor, and are hooked there in a form-fitting manner.
Jeweils an der Außenseite des Dammaufbaus weisen die beiden Rinnenprofile 7, 8 einen ebenfalls bodenparallelen Flanschstreifen 16 bzw. 17 auf. Durch die Flanschstreifen 14, 15, 16 und 17 wird eine verbreiterte Aufsteilfläche der Rinnenprofile- 7 und 8 geschaffen, so dass diese auch in weichen Boden nicht einsinken. Jeweils ein Vorsprung 18 bzw. 19 an der Unterseite des Rinnenprofils 7 bzw. 8 bildet einen Verankerungsvorsprung, der den Dammaufbau in seiner Stellung sichert. Der auf den Dammaufbau im Belastungsfall ausgeübte Druck hält den Dammaufbau zusätzlich am Boden fest.Each on the outside of the dam structure, the two channel profiles 7, 8 also have a flange strip 16 and 17, which is also parallel to the floor. The flanged strips 14, 15, 16 and 17 create a broadened dividing surface of the channel profiles 7 and 8, so that they do not sink into soft ground. In each case one projection 18 or 19 on the underside of the channel profile 7 or 8 forms an anchoring projection which secures the position of the dam structure. The pressure exerted on the dam structure in the event of a load also holds the dam structure on the ground.
Der in Fig. 2 gezeigte Dammaufbau unterscheidet sich von dem vorher beschriebenen Dammaufbau im wesentlichen dadurch, dass der die druckseitigen Paletten 1 und die stutzseitigen Paletten 2 verbindende Zug-Druck-Anker durch einen vorzugsweise aus Metall bestehenden Verbindungsanker 20 (Fig. 5, 6) gebildet wird, der die Druckpaletten 1 und Stützpaletten 2 miteinander formschlüssig verbindet. Der vorzugsweise durch Abkanten aus einem Stahlblechstreifen und/oder Schweißen oder durch Strangpressen hergestellte Verbindungsanker 20, der in Fig. 5 in einer Seitenansicht und in Fig. 6 in einer Draufsicht gezeigt ist, weist an beiden Enden jeweils ein nach unten offenes Klammerendstück 21 bzw. 22 auf, das auf ein unteres Längsbrett der Druckpalette 1 bzw. der Stützpalette 2 aufsteckbar ist. Oberhalb desThe dam structure shown in FIG. 2 differs from the previously described dam structure essentially in that the tension-pressure anchor connecting the pressure-side pallets 1 and the support-side pallets 2 is preferably made of metal Connection anchor 20 (Fig. 5, 6) is formed, which connects the pressure pallets 1 and support pallets 2 with each other in a form-fitting manner. The connecting anchor 20, which is preferably produced by folding from a sheet steel strip and / or welding or by extrusion, and which is shown in a side view in FIG. 5 and in a plan view in FIG. 6, has a downwardly open clamp end piece 21 or 22, which can be plugged onto a lower longitudinal board of the pressure pallet 1 or the support pallet 2. Above the
Klammerendstücks 21 bzw. 22 ist ein sich am nächst oberen Längsbrett der Druckpalette 1 bzw. Stützpalette 2 abstützender Anschlag 23 bzw. 24 vorgesehen, der. nach dem Einhängen der Klammerendstücke 21 und 22 ein unbeabsichtigtes Ausheben des Verbindungsankers 20 ausschließt. Ein von dem einen Klammerendstück 22 schräg abstehender Stützsporn 25 dient zur weiteren Abstützung innerhalb der Stützpalette 2. In aufgerichteten Zustand des Dammaufbaus kann der Verbindungsanker 20 nicht ' entfernt werden.Clamp end piece 21 or 22, a stop 23 or 24, which is supported on the next upper longitudinal board of the pressure pallet 1 or support pallet 2, is provided. after the clip end pieces 21 and 22 have been hooked in, inadvertent lifting out of the connecting anchor 20 rules out. One of the one clamp end piece 22 obliquely projecting supporting spur 25 serves to further support within the support pallet 2. In the erected state of the dam construction, the connecting anchor 20 is not 'be removed.
Um eine sichere Festlegung des in sich statisch stabilen Dammaufbaus gemäß Fig. 2 am Boden 6 zu erreichen, der beispielsweise eine glatte Straßenoberfläche od.dgl. sein kann, sind in den Boden 6 einschlagbare Häringe 26 (Fig. 7 und 8) vorgesehen. Auf die unteren Ränder der Paletten 1 und 2 aufnehmende Rinnenprofile 7 und 8 wurde bei der Ausführung gemäß Fig. 2 verzichtet.In order to achieve a secure fixing of the inherently stable dam structure according to FIG. 2 on the floor 6, which, for example, has a smooth road surface or the like. can be in the bottom 6 foldable herring 26 (Fig. 7 and 8) are provided. On the lower edges of the pallets 1 and 2 receiving channel profiles 7 and 8 was omitted in the embodiment according to FIG. 2.
Mittels Kabelbindern 27 können in der in den Fig. 1 und 2 dargestellten Weise vorläufige Verbindungen der oberen Ränder der Paletten 1 und 2 hergestellt werden, wodurch die Errichtung des weiteren Aufbaus erleichtert wird.By means of cable ties 27, provisional connections of the upper ones can be made in the manner shown in FIGS Edges of pallets 1 and 2 are made, which facilitates the erection of the further structure.
Um eine weitere Erhöhung des Dammaufbaus zu erreichen, sind beim Ausführungsbeispiel nach Fig. 2 am oberen Rand der Druckpaletten 1 Stauwanderhöhungsprofile 28 (Fig. 12) aufgesetzt, die ebenfalls vorzugsweise aus stranggepresstem Material bestehen und über die Oberkante der Druckpaletten 1 hinausragen. Ein Fußstück 29 des Stauwanderhöhungsprofils 28 umgreift zwei Längsbretter der Druckpaletten 1 und stützt sich mit einem Mittelteil 30 an deren Oberkante ab. Der auf den Dammaufbau im Belastungsfall ausgeübte Druck hält die Stauwanderhöhungsprofile 28 zusätzlich fest.In order to achieve a further increase in the dam structure, in the exemplary embodiment according to FIG. 2, 1 accumulation increase profiles 28 (FIG. 12) are placed on the upper edge of the pressure pallets, which also preferably consist of extruded material and protrude beyond the upper edge of the pressure pallets 1. A foot piece 29 of the traffic jam elevation profile 28 engages around two longitudinal boards of the pressure pallets 1 and is supported with a central part 30 on the upper edge thereof. The pressure exerted on the dam structure in the event of a load additionally holds the accumulation profile 28.
Die Dichtungsfolie 3 ist über den oberen Rand des Stauwanderhöhungsprofils 28 gelegt und dort mittels einer von oben aufgesetzten Folienklammer 4 ' (Fig . 14) festgelegt und gesichert , die zugleich eine- erbindung benachbarter Stauwanderhöhungsprof ile 28 bildet .The sealing film 3 is placed over the upper edge of the traffic jam elevation profile 28 and fixed and secured there by means of a film clip 4 '(FIG. 14) from above, which at the same time forms a connection between adjacent traffic jam elevation profiles 28.
Das in Fig . 3 dargestellte Aus führungsbei spiel eines Dammaufbaus unterscheidet sich von dem Ausführungsbeispiel nach Fig . 2 nur dadurch, dass zusätzlich zu den Verbindungsankern 20 im Fußbereich der Paletten 1 und 2 auch eine Verbindung über Rinnenprofile 7 , 8 und diese verbindende Verbindungsleisten 11 vorgesehen ist , wie bei Fig . 1 beschrieben.The in Fig. 3 shown embodiment of a dam structure differs from the embodiment of FIG. 2 only in that, in addition to the connecting anchors 20 in the foot region of the pallets 1 and 2, a connection via channel profiles 7, 8 and connecting strips 11 connecting them is also provided, as in FIG. 1 described.
Der in Fig . 15 in einem senkrechten Querschnitt dargestellte Dammaufbau weist ebenso wie die vorher beschriebenen Ausführungen zwei Reihen von schräg gegeneinander gestellten Druckpaletten 1 und unteren Stützpaletten 2 auf, bei denen es sich vorzugsweise um Holz-Nagelpaletten in den genormten Abmessungen von Euro- Paletten handelt. Am oberen Rand der Druckpaletten 1 sind aus Stahlblech oder Aluminium bestehendeThe in Fig. The dam structure shown in a vertical cross section, like the previously described embodiments, has two rows of oblique opposed pressure pallets 1 and lower support pallets 2, which are preferably wooden nail pallets in the standardized dimensions of Euro pallets. At the top of the pressure pallets 1 are made of sheet steel or aluminum
Stauwanderhöhungsprofile 33 in einer durchgehenden, die Druckpaletten übergreifenden Reihe aufgesteckt.Accumulation profile 33 in a continuous row across the pressure pallets.
Auf der Druckseite (rechts in Fig. 15) , auf der das zurückzuhaltende Wasser, eine andere Flüssigkeit oder ein fließfähiges Schüttgut ansteht, liegt an der Außenseite der Druckpalette 1 und des Stauwanderhöhungsprofils 33 eine Dichtungsfolie 34 an, die über den oberen Rand der in einer Reihe angeordneten Stauwanderhöhungsprofile 33 gelegt und mittels in Abständen angeordneten, von oben aufgesetzten Folienklammern 35 am oberen Rand- der Stauwanderhöhungsprofile 33 festgelegt ist. Der untere Rand der Dichtungsfolie 34 wird durch eine Reihe von Sandsäckeή" oder Ziegelsteinen gesichert und- am Boden 36,- beispielsweise einer Deichkrone oder einer Straßenoberfläche, festgelegt.On the pressure side (on the right in Fig. 15) on which the water to be retained, another liquid or a flowable bulk material is present, on the outside of the pressure pallet 1 and the accumulation profile 33 there is a sealing film 34, which over the upper edge of the in a Row arranged traffic jam elevation profiles 33 placed and fixed by means of spaced, from above attached film clips 35 on the upper edge of the traffic jam elevation profiles 33. The lower edge of the sealing film 34 is secured by a series of sandbagsή " or bricks and - on the floor 36, - for example, a dike crown or a road surface.
Die aus hochfestem Folienmaterial bestehende Dichtungsfolie 34 weist vorzugsweise an ihrem am Boden 36 liegenden Rand einen ankonfektionierten Randstreifen 34a aus Weichfolie auf, auf dem die Sandsäcke oder Ziegelsteine liegen. Das weichere Folienmaterial des Randstreifens 34a gewährleistet eine bessere Abdichtung • am Boden 36. An Ecken des Dammverlaufs können konfektionierte Folienecken angeordnet werden, die die Dichtfolie dort überlappen. Die Dichtungsfolie kann als sogenannte Monofolie auch einstückig aus einem einheitlichen Folienmaterial bestehen, das im Dichtungsbereich am Boden eine optimale Dichtwirkung hat, dabei aber ausreichend reißfest ist und sich über die ganze Höhe des Deichaufbaus erstreckt, die beispielsweise 800 oder 1150 mm beträgt.The sealing film 34, which is made of high-strength film material, preferably has on its edge lying on the bottom 36 a prefabricated edge strip 34a made of soft film, on which the sandbags or bricks lie. The softer film material of the edge strip 34a ensures a better seal • at the bottom 36. At the corners of the course of the dam, ready-made film corners can be arranged which overlap the sealing film there. As a so-called monofilm, the sealing film can also consist in one piece of a uniform film material that has an optimal sealing effect in the sealing area on the bottom, but is sufficiently tear-resistant and extends over the entire height of the dike structure, which is, for example, 800 or 1150 mm.
Die unteren Stützpaletten 2 greifen unter den oberen Rand der Druckpaletten 1. Die beiden Reihen von Druckpaletten 1 und unteren Stützpaletten 2 sind in ihrem unterenThe lower support pallets 2 reach under the upper edge of the print pallets 1. The two rows of print pallets 1 and lower support pallets 2 are in their lower
Bereich durch Zug-Druckanker miteinander verbunden, die als Verbindungsanker 37 ausgeführt sind.Area connected to each other by tension-pressure anchors, which are designed as connecting anchors 37.
Über den die Druckpaletten 1 stützenden, unteren Stützpaletten 2 sind obere Stützpaletten 38 angeordnet, die mit ihrem oberen Rand die Stauwanderhöhungsprofile 33 stützen. Wie man aus der Draufsicht in Fig. 16 erkennt, sind die oberen Stützpaletten 38 bei diesem Ausführungsbeispiel 'mit seitlichem Abstand zueinander' angeordnet, und zwar so, dass die oberen Stützpaletten 38 jeweils am Stoß zweier Stauwanderhδhungsprofile 33 angreifen.Above the lower support pallets 2 supporting the pressure pallets 1, upper support pallets 38 are arranged, which support the accumulation wall increase profiles 33 with their upper edge. As can be seen from the top view in FIG. 16, the upper support pallets 38 are arranged ' at a lateral distance from one another ' in this exemplary embodiment, in such a way that the upper support pallets 38 each engage the joint of two accumulation migration profiles 33.
Die oberen Stützpaletten sind an ihrem unteren Rand jeweils über Zugverbindungsanker 39 mit dem unteren Rand der unteren Stützpalette 2 verbunden. Jeder Zugverbindungsanker 39 greift mit einem sich nach oben erstreckenden Haken 40 in den unteren Rand der oberen Stützpalette 38 formschlüssig ein, während ein am entgegengesetzten Rand des Zugverbindungsankers 39 ausgebildeter, nach unten geöffneter Haken 41 um das untere Brett am unteren Rand der unteren Stützpalette 2 greift. Auf diese Weise wird eine zugfeste Verbindung der beiden Stützpaletten 38 und 2 an ihren unteren Rändern hergestellt.The upper support pallets are each connected at their lower edge to the lower edge of the lower support pallet 2 via tension connection anchors 39. Each tie link 39 engages with an upwardly extending hook 40 in the lower edge of the upper support pallet 38, while a hook 41 formed on the opposite edge of the tie link 39 opens downward around the lower board at the lower edge of the lower support pallet 2 attacks. In this way, a tensile connection of the two support pallets 38 and 2 is made at their lower edges.
Der untere Rand der unteren Stützpaletten 2 und/die Zugverbindungsanker 39 sind durch in den Boden 36 eingeschlagene Ankerpfosten 42 gesichert. Jeder Ankerpfosten 42 erstreckt sich durch eine passende Öffnung 43 eines am Boden 36 liegenden Abschnitts des Zugverbindungsankers 39, um diesen und somit auch die Stützpaletten 2 und 38 gegen eine horizontale Verschiebung zu sichern.The lower edge of the lower support pallets 2 and / the train connection anchors 39 are secured by anchor posts 42 hammered into the floor 36. Each anchor post 42 extends through a suitable opening 43 of a section of the train connection anchor 39 lying on the floor 36 in order to secure this and thus also the support pallets 2 and 38 against horizontal displacement.
Der Ankerpfosten 42 stützt sich an einer im Abstand über dem Boden 36 verlaufenden Kante 44 des unteren Rands der oberen Stützpalette 38 ab und ist dadurch auch bei dünner Ausführung gegen ein Umbiegen gesichert.The anchor post 42 is supported on an edge 44 of the lower edge of the upper support pallet 38 which runs at a distance above the floor 36 and is thereby secured against bending even in the case of a thin version.
An der Rückseite der Stauwanderhöhungsprofile 33 vorspringende Nasen 45 greifen formschlüssig am oberenOn the back of the accumulation profile 33 protruding lugs 45 engage positively on the top
Rand der oberen Stützpalette 38 an und verhindern, dass sich die obere Stützpalette 38 bei erhöhter Druckbelastung des Stauwanderhöhungsprofils 33 nach hinten wegbewegt .Edge of the upper support pallet 38 and prevent the upper support pallet 38 from moving backwards with increased pressure load on the accumulation profile 33.
An der Rückseite der Stauwanderhöhungsprofile 33 sind vorspringende Arretierungshaken 46 vorgesehen, die nach unten geöffnet sind und formschlüssig am oberen Rand der Druckpalette 1 angreifen. Auch das untere Ende des Stauwanderhöhungsprofils 33 weist einen abgekröpftenOn the back of the traffic jam elevation profiles 33, projecting locking hooks 46 are provided, which are open at the bottom and engage positively on the upper edge of the pressure pallet 1. The lower end of the traffic jam elevation profile 33 also has an offset
Abschnitt 47 auf, der in die Druckpalette 1 eingreift. Zweckmäßigerweise ist vorgesehen, dass die Verbindungsanker an beiden Enden jeweils ein nach unten offenes Klammerendstück aufweisen, das auf ein unteres Längsbrett der Druckpalette 1 bzw. der unteren Stützpalette 2 aufsteckbar ist.Section 47, which engages in the print pallet 1. It is expediently provided that the connecting anchors each have a downwardly open clamp end piece at both ends, which can be plugged onto a lower longitudinal board of the pressure pallet 1 or the lower support pallet 2.
Der beschriebene Dammaufbau trägt besonders dem Umstand Rechnung, dass in der jeweils unteren Hälfte der Stauhöhe ein im Vergleich zur oberen Hälfte dreifacher Druck anliegt. Diese Druckverteilung wird optimal abgestützt. Der Dammaufbau ist in sich stabil und standfest, wobei seine Standfestigkeit noch durch die Ankerpfosten 42 erhöht werden kann, die aber nur bei glatten Böden zwingend erforderlich sind.The dam construction described takes into account in particular the fact that there is a triple pressure in the lower half of the dam height in comparison to the upper half. This pressure distribution is optimally supported. The dam structure is inherently stable and stable, and its stability can be increased by the anchor posts 42, which are, however, only mandatory for smooth floors.
In mittlerer Höhe des Dammaufbaus ist die Folie 3 an den die Druckpaletten 1 bildenden Holzpaletten durch Klemmelemente 50 befestigt (Fig. 15) . Diese Klemmelemente 50 bestehen jeweils aus einem Klemmkörper 61, der zusammen mit der hierbei eine Tasche bildenden Folie 34 in den Zwischenraum zwischen benachbarte Palettenbretter 2 eingesetzt ist und die Folie 34 klemmend festhält. Der Zwischenraum zwischen benachbarten Palettenbrettern 2. bildet hierbei eine den Klemmkörper 61 aufnehmende Aussparung 63.In the middle of the dam structure, the film 3 is fastened to the wooden pallets forming the pressure pallets 1 by means of clamping elements 50 (FIG. 15). These clamping elements 50 each consist of a clamping body 61 which, together with the film 34 forming a pocket, is inserted into the intermediate space between adjacent pallet boards 2 and holds the film 34 in a clamping manner. The space between adjacent pallet boards 2 here forms a recess 63 receiving the clamping body 61.
Bei dem in den Fig. 17 und 18 dargestelltenIn the one shown in FIGS. 17 and 18
Ausführungsbeispiel besteht der Klemmkörper 61 aus einer ovalen Scheibe, deren vom kleinsten zum größten Scheibendurchmesser ansteigende Umfangsbereiche jeweilsIn the exemplary embodiment, the clamping body 61 consists of an oval disk, the circumferential areas of which increase from the smallest to the largest disk diameter
Nockenflächen bilden, die beim Verdrehen des Klemmkörpers 61 gegen die Innenrandflächen 64 der Ausnehmung 63 gedrückt werden, die vorzugsweise rechtwinklig zur Wandfläche gerichtet sind.Form cam surfaces which, when the clamping body 61 is rotated, against the inner edge surfaces 64 of the recess 63 are pressed, which are preferably directed at right angles to the wall surface.
Ein in Umf ngsriehtung verlaufender, sich über den gesamten Scheibenumfang des Klemmkörpers 61 erstreckender Grat 66 springt aus der die Nockenfläche bildenden Umfangsflache 65 des Klemmkörpers 61 radial vor. Beim Drehen des Klemmkörpers 61 in der Ausnehmung 63 wird die zwischen dem Klemmkörper 61 und den Innenwandflächen 64 befindliche Folie 34 festgeklemmt, wobei sich im Bereich des Grats 66 die Folien 34 in die Innenrandflache 64 hineindrückt, ohne dass die Folie dabei beschädigt wird.A ridge 66 extending in the circumferential direction and extending over the entire disk circumference of the clamping body 61 projects radially from the circumferential surface 65 of the clamping body 61 forming the cam surface. When the clamping body 61 is rotated in the recess 63, the film 34 located between the clamping body 61 and the inner wall surfaces 64 is clamped, the films 34 being pressed into the inner edge surface 64 in the region of the ridge 66 without the film being damaged in the process.
Der Grat 66 ist im Querschnitt angenähert dachförmig und hat im Querschnitt einen Spitzenwinkel von 120°. Seine Höhe beträgt etwa 1,5 mm.The ridge 66 is approximately roof-shaped in cross section and has a tip angle of 120 ° in cross section. Its height is approximately 1.5 mm.
Damit der Klemmkörper 61 gedreht werden kann, weist er einen stirnseitig zugänglichen Schlüsselansatz auf, der beim dargestellten Ausführungsbeispiel eine Innensechskant-Ausnehmung 67 ist, in die ein herkömmlicher Innensechskant-Schlüssel passt.So that the clamping body 61 can be rotated, it has a key attachment which is accessible from the front and which in the exemplary embodiment shown is a hexagon socket recess 67 into which a conventional hexagon socket key fits.
Bei dem in Fig. 17 und 18 dargestellten Ausführungsbeispiel eines Klemmkörpers 61 bildet der Grat 66 an jeder Umfangsstelle den radial am weitesten vorstehenden Umfangsbereich. Die Nockenfläche 65 erstreckt sich beiderseits vom Grat 66.In the exemplary embodiment of a clamping body 61 shown in FIGS. 17 and 18, the ridge 66 forms the radially most protruding peripheral region at each peripheral point. The cam surface 65 extends from the ridge 66 on both sides.
In den Fig. 19 und 20 ist gezeigt, dass die Druckpaletten 1 mit den Stützpaletten 2 durch Klammern 68 verbunden sind, die jeweils Endbretter 69 benachbarter Druckpaletten 1 umgreifen und mit ihren hakenartigen Enden 68a unter jeweils die oberen, längsverlaufenden Bretter 70 der Stützpaletten 2 eingehängt sind. Dadurch wird nicht nur eine stabile Verbindung der Druckpaletten 1 mit den Stützpaletten 2, sondern auch eine Verbindung aneinanderstoßender Druckpaletten 1 bzw. Druckpaletten 2 erreicht .19 and 20 show that the pressure pallets 1 are connected to the support pallets 2 by brackets 68, the end boards 69 respectively being adjacent Reach around the pressure pallets 1 and are hooked with their hook-like ends 68a under each of the upper, longitudinal boards 70 of the support pallets 2. As a result, not only a stable connection of the pressure pallets 1 with the support pallets 2, but also a connection of abutting pressure pallets 1 or pressure pallets 2 is achieved.
Wie in Fig. 21 dargestellt, sind auf die Stauwanderhöhungsprofile 28 Niveauausgleichsstücke 71 aufgesteckt, die dazu dienen, einen unebenen Bodenverlauf so auszugleichen, dass die Oberkante des Dammaufbaus weitgehend horizontal verläuft.As shown in FIG. 21, leveling pieces 71 are fitted onto the accumulation profile 28, which serve to compensate for an uneven ground profile in such a way that the upper edge of the dam structure runs largely horizontally.
Wie in Fig. 21 links gezeigt, können dieAs shown in Fig. 21 on the left, the
Niveauausgleichsstücke 71 jeweils in gleicher Breite fluchtend zu den zugeordneten Druckpaletten 1 und Stauwanderhöhungsprofilen 28 ausgerichtet werden. Rechts in Fig. 21 ist gezeigt, dass die Niveauausgleichsstücke 71 auch jeweils so versetzt angeordnet werden können, dass sie jeweils die Fuge zwischen benachbarten Stauwanderhöhungsprofilen 28 überbrücken.Leveling pieces 71 are aligned in the same width in each case in alignment with the assigned pressure pallets 1 and accumulation wall increase profiles 28. It is shown on the right in FIG. 21 that the leveling pieces 71 can also be arranged offset in each case such that they each bridge the joint between adjacent traffic jam elevation profiles 28.
Zur Anbringung der Niveauausgleichsstücke 71 ist an deren Rückseite jeweils ein Einsteckkδrper 71a vorgesehen, der in eine zugehörige Ausnehmung 28a des Stauwanderhöhungsprofils 28 eingesteckt werden kann.To attach the leveling pieces 71, a plug-in body 71a is provided on the back of each, which can be inserted into an associated recess 28a of the accumulation profile 28.
In Fig. 23 ist gezeigt, dass zwei Dammaufbauten 72, vorzugsweise mit durchgehender gemeinsamer23 shows that two dam structures 72, preferably with a continuous joint
Dichtungsfolie, beispielsweise in einer der bisher beschriebenen Ausführungsformen, zur Bildung eines Kanals 73 durch Zuganker 74 mit einander verbunden werden können. So gebildete Kanäle 73 können dazu dienen, einen Bach oder Fluss umzuleiten.Sealing film, for example in one of the previously described embodiments, to form a channel 73 can be connected to each other by tie rods 74. Channels 73 formed in this way can serve to divert a stream or river.
Die zwischen den beiden Dammaufbauten 72 wirkenden Kräfte werden durch die Zuganker 74 aufgenommen. Bei den Ausführungsbeispielen nach den Fig. 23 und 24 greifen die Zuganker 74 an den Verbindungsankern 37 an, die die Druckpaletten 1 und die Stützpaletten 2 jedes der beiden Dammaufbauten 72 verbinden.The forces acting between the two dam structures 72 are absorbed by the tie rods 74. 23 and 24, the tie rods 74 engage the connecting anchors 37, which connect the pressure pallets 1 and the support pallets 2 of each of the two dam structures 72.
Beim Beispiel nach Fig. 23 sind die Zuganker 74 einstückige Leisten, die gelenkig an den Verbindungsankern 37 angeschlossen sind. In Fig. 24 ist gezeigt, dass die Zuganker 74 beispielsweise Ketten sein können. Wenn die Druckpaletten in druckseitigen Rinnenprofilstücken 7 aufgenommen sind, wie dies in Fig. 3 dargestellt ist, dann können die die beiden Dammaufbauten 72 verbindenden Zuganker 74 über einhängbare Formstücke 75 (Fig. 25 und 26) an den Rinnenprofilstücken 7 der beiden Dammaufbauten 72 angreifen. Diese Formstücke 75 sind längsverschiebbar an profilierten Randstreifen 76 der Rinnenprofilstücke 7 aufgenommen.In the example according to FIG. 23, the tie rods 74 are one-piece strips which are connected in an articulated manner to the connecting anchors 37. 24 shows that the tie rods 74 can be chains, for example. If the pressure pallets are received in pressure-side channel profile pieces 7, as is shown in FIG. 3, the tie rods 74 connecting the two dam structures 72 can engage on the channel profile pieces 7 of the two dam structures 72 via insertable shaped pieces 75 (FIGS. 25 and 26). These fittings 75 are longitudinally displaceable on profiled edge strips 76 of the channel profile pieces 7.
Fig. 26 zeigt in einer Draufsicht, dass die längsverschiebbaren Formstücke 75 jeweils einen Bolzen 77 aufweisen, der eine Aussparung 78 am Formstück 75 überbrückt und an dem die die Zuganker 74 bildenden Ketten angreifen. Die Ketten können beispielsweise26 shows in a top view that the longitudinally displaceable shaped pieces 75 each have a bolt 77 which bridges a recess 78 on the shaped piece 75 and on which the chains forming the tie rods 74 engage. The chains can for example
Abschnitte eines beliebig langen Kettenstrangs sein, der ohne Zerteilung mehrere Zuganker 74 bildet. Sections of an arbitrarily long chain strand, which forms several tie rods 74 without being divided.

Claims

P a t e n t a n s p r ü c h e Patent claims
1. Dammaufbau für Flüssigkeiten und Schüttgüter mit zwei Reihen von schräg gegeneinander gestellten Druckpaletten und Stützpaletten und einer Dichtungsfolie auf der Druckseite der Druckpalette, dadurch gekennzeichnet, dass die Druckpaletten (1) und die Stützpaletten (2) jeweils durch Zug-Druck-Anker (11, 20, 37) miteinander verbunden sind.1. Dam construction for liquids and bulk goods with two rows of obliquely opposed pressure pallets and support pallets and a sealing film on the pressure side of the pressure pallet, characterized in that the pressure pallets (1) and the support pallets (2) each by tension-pressure anchors (11 , 20, 37) are interconnected.
2. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass die Druckpaletten (1) und die Stützpaletten (2) mit ihren unteren Rändern in jeweils über mehrere Paletten (1, 2) durchlaufenden druckseitigen und stutzseitigen.. Rinnenprofilen' (7, 8) formschlüssig aufgenommen sind und dass die druckseitigen und stutzseitigen Rinnenprofile (7, 8) durch die Zug-Druck-Anker bildende Verbindungsleisten (11) miteinander verbunden sind.2. Dam structure according to claim 1, characterized in that the pressure pallets (1) and the support pallets (2) with their lower edges in each case via a plurality of pallets (1, 2) continuous pressure-side and support-side .. channel profiles ' (7, 8) positively and that the pressure-side and support-side channel profiles (7, 8) are connected to one another by the connecting strips (11) forming the tension-pressure anchors.
3. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass die Druckpaletten (1) und die Stützpaletten (2) durch die Zug-Druck-Anker bildende Verbindungsanker (20) miteinander verbunden sind.3. Dam structure according to claim 1, characterized in that the pressure pallets (1) and the support pallets (2) are connected to one another by the connecting anchors (20) forming the tension-pressure anchors.
4. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass am oberen Rand der Druckpaletten (1)4. dam construction according to claim 1, characterized in that at the upper edge of the pressure pallets (1)
Stauwanderhöhungsprofile (28) aufsetzbar sind, die über die Oberkante der Druckpaletten (1) hinausragen. Accumulation profiles (28) can be placed, which protrude beyond the upper edge of the pressure pallets (1).
5. Dammaufbau nach Anspruch 1 oder 4 , dadurch gekennzeichnet, dass eine druckseitige Dichtungsfolie (34) mittels von oben aufsetzbarer Folienklammern (4, 4') am oberen Rand der Druckpalette (1) oder des Stauwanderhöhungsprofils (28) festlegbar ist.5. Dam structure according to claim 1 or 4, characterized in that a pressure-side sealing film (34) by means of film clips (4, 4 ') from above at the top of the pressure pallet (1) or the accumulation profile (28) can be fixed.
6. Dammaufbau nach Anspruch 2, dadurch gekennzeichnet, dass die Verbindungsleisten (11) in Ausnehmungen (12, 13) von bodenparallelen Flanschstreifen (14, 15) der Rinnenprofile (7, 8) einhängbar sind.6. dam structure according to claim 2, characterized in that the connecting strips (11) in recesses (12, 13) of parallel flange strips (14, 15) of the channel profiles (7, 8) can be hung.
7. Dammaufbau nach Anspruch 3, dadurch gekennzeichnet, dass die Verbindungsanker (20) an beiden Enden jeweils ein nach unten offenes Klammerendstück (21, 22) aufweisen, das auf ein unteres Längsbrett der Druckpalette (1) bzw. der Stützpalette (2) aufsteckbar ist.7. dam structure according to claim 3, characterized in that the connecting anchors (20) have at both ends a downwardly open clamp end piece (21, 22) which can be plugged onto a lower longitudinal board of the pressure pallet (1) or the support pallet (2) is.
8. Dammaufbau nach Anspruch 7, dadurch gekennzeichnet, das oberhalb des Klammerendstücks (21 bzw. 22) ein sich' am nächstoberen Längsbrett der Palette (1 bzw. 2) abstützender Anschlag (23 bzw. 24) vorgesehen ist.8. dam structure according to claim 7, characterized in that above the clamp end piece (21 or 22) 'on the next upper longitudinal board of the pallet (1 or 2) supporting stop (23 or 24) is provided.
9. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass mindestens abschnittsweise über den die Druckpaletten (1) stützenden, unteren Stützpaletten (2) obere Stützpaletten (38) angeordnet sind, die mit Ihrem oberen Rand die Stauwanderhöhungsprofile (33) stützen. 9. dam structure according to claim 1, characterized in that at least in sections above the pressure pallets (1) supporting, lower support pallets (2) upper support pallets (38) are arranged, which support the accumulation profile (33) with their upper edge.
10. Dammaufbau nach Anspruch 9, dadurch gekennzeichnet, dass die oberen Stützpaletten (38) jeweils am Stoß zweier Stauwanderhöhungsprofile (33) angreifen.10. Dam construction according to claim 9, characterized in that the upper support pallets (38) each engage at the joint of two accumulation profiles (33).
11. Dammaufbau nach Anspruch 9, dadurch gekennzeichnet, dass die oberen Stützpaletten (38) mit Abstand zueinander angeordnet sind.11. Dam construction according to claim 9, characterized in that the upper support pallets (38) are arranged at a distance from one another.
12. Dammaufbau nach einem der Ansprüche 9-11, dadurch gekennzeichnet, dass die oberen Stützpaletten (38) an ihrem Rand jeweils über Zugverbindungsanker (39) mit dem unteren Rand der unteren Stützpaletten (2) verbunden sind.12. Dam structure according to one of claims 9-11, characterized in that the upper support pallets (38) are connected at their edge in each case via train connection anchors (39) to the lower edge of the lower support pallets (2).
13. Dammaufbau nach einem der Ansprüche 1-12, dadurch gekennzeichnet, dass der untere Rand der unteren Stützpaletten (2) und/oder die Zugverbindungsanker (39) durch in den Boden (36) eingeschlagene Ankerpfosten (42) gesichert sind.13. Dam structure according to one of claims 1-12, characterized in that the lower edge of the lower support pallets (2) and / or the train connection anchors (39) are secured by anchor posts (42) hammered into the floor (36).
14. Dammaufbau nach Anspruch 13, dadurch gekennzeichnet, dass sich der Ankerpfosten (42) durch eine passende Öffnung (43) eines am Boden (36) liegenden Abschnitts des Zugverbindungsankers (39) erstreckt.14. Dam structure according to claim 13, characterized in that the anchor post (42) extends through a suitable opening (43) of a section of the train connection anchor (39) lying on the floor (36).
15. Dammaufbau nach Anspruch 14, dadurch gekennzeichnet, dass sich der Ankerpfosten (12) an einer im Abstand über dem Boden (6) verlaufenden Kante (14) des unteren Rands der oberen Stützpalette (8) abstützt.15. Dam structure according to claim 14, characterized in that the anchor post (12) is supported on an edge (14) of the lower edge of the upper support pallet (8) which runs at a distance above the floor (6).
16. Dammaufbau nach Anspruch 9, dadurch gekennzeichnet, dass an der Rückseite des Stauwanderhöhungsprofils (33) vorspringende Nasen (45) formschlüssig am oberen Rand der oberen Stützpalette (38) angreifen.16. Dam construction according to claim 9, characterized in that on the back of the accumulation profile (33) Grip the projecting lugs (45) positively on the upper edge of the upper support pallet (38).
17. Dammaufbau nach Anspruch 9, dadurch gekennzeichnet, dass an der Rückseite der Stauwanderhöhungsprofile (33) vorspringende Arretierungshaken (46) formschlüssig am oberen Rand der Druckpalette (1) angreifen.17. Dam construction according to claim 9, characterized in that on the back of the accumulation profiles (33) projecting locking hooks (46) engage positively on the upper edge of the pressure pallet (1).
18. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass die Dichtungsfolie (34) an ihrem am Boden (36) liegenden Rand einen ankonfektionierten Randstreifen (34a) aus Weichfolie aufweist.18. Dam structure according to claim 1, characterized in that the sealing film (34) has a prefabricated edge strip (34a) made of soft film on its edge lying on the bottom (36).
19. Dammaufbau nach einem der Ansprüche 1 -18, gekennzeichnet durch die Verwendung von Klemmelementen (50) zur Befestigung der Folien (3, 34) an den Druckpaletten- (1, 2) , wobei die Zwischenräume (13) zwischen Palettenbrettern (62) Aussparungen zur Aufnahme der die Folie (3, 34) klemmenden Klemmelemente- (50) bilden.19. Dam structure according to one of claims 1-18, characterized by the use of clamping elements (50) for fastening the foils (3, 34) to the pressure pallet (1, 2), the spaces (13) between pallet boards (62) Form recesses for receiving the film (3, 34) clamping elements (50).
20. Dammaufbau nach Anspruch 19, dadurch gekennzeichnet, dass das Klemmelement (50) aus einem Klemmkörper (61) besteht, der an seinem Umfang mindestens eine ansteigende Nockenfläche (65) aufweist, dass mindestens an der20. Dam structure according to claim 19, characterized in that the clamping element (50) consists of a clamping body (61) which has at least one rising cam surface (65) on its circumference that at least on the
Nockenfläche (65) und/oder an der ihr gegenüberliegenden Umfangsflache ein in Umfangsrichtung verlaufender Grat {66) aus der Nockenfläche (65) und/oder der gegenüberliegenden Umfangsflache radial vorspringt, und dass der Klemmkörper (61) einen stirnseitig zugänglichen Schlüsselansatz (77) aufweist. Cam surface (65) and / or on the opposite circumferential surface a radially extending ridge {66) protrudes radially out of the cam surface (65) and / or the opposite circumferential surface, and that the clamping body (61) has a key attachment (77) accessible from the front ,
21. Dammaufbau nach Anspruch 20, dadurch gekennzeichnet, dass der Klemmkörper (61) aus einer ovalen Scheibe besteht, deren vom kleinsten zum größten Scheibendurchmesser ansteigende Umfangsbereiche jeweils die Nockenflächen (65) bilden.21. Dam structure according to claim 20, characterized in that the clamping body (61) consists of an oval disc, the circumferential areas increasing from the smallest to the largest disc diameter each form the cam surfaces (65).
22. Dammaufbau nach Anspruch 1, dadurch gekennzeichnet, dass die Druckpaletten (1) mit den Stützpaletten (2) durch Klammern (68) verbunden sind, die jeweils Endbretter (69) benachbarter Druckpaletten (1) umgreifen und mit ihren Enden unter Bretter (70) der Stützpaletten (2) eingehängt sind.22. Dam construction according to claim 1, characterized in that the pressure pallets (1) are connected to the support pallets (2) by brackets (68), each of which engages around end boards (69) of adjacent pressure pallets (1) and with their ends under boards (70 ) the support pallets (2) are attached.
23. Dammaufbau nach Anspruch 4, dadurch gekennzeichnet, dass auf die Stauwanderhöhungsprofile (28)23. Dam construction according to claim 4, characterized in that on the dam increase profiles (28)
Niveauausgleichsstücke (71) aufsteckbar sind.Leveling pieces (71) can be plugged on.
24. Verbindung zweier Dammaufbauten nach einem der Ansprüche.1 - 23, wobei die beiden Dammaufbauten (72) zur Bildung eines Kanals (73) durch Zuganker (74) miteinander verbunden sind.24. Connection of two dam structures according to one of claims 1-23, wherein the two dam structures (72) are connected to one another by tie rods (74) to form a channel (73).
25. Verbindung zweier Dammaufbauten nach Anspruch 24, dadurch gekennzeichnet, dass die Zuganker (74). an Verbindungsankern (37) angreifen, die die Druckpaletten (1) und die Stützpaletten (2) jedes Dammaufbaus (72) verbinden.25. Connection of two dam structures according to claim 24, characterized in that the tie rods (74). engage connecting anchors (37) that connect the pressure pallets (1) and the support pallets (2) of each dam structure (72).
26. Verbindung zweier Dammaufbauten nach Anspruch 24, dadurch gekennzeichnet, dass die Zuganker (74) über einhängbare Formstücke (75) an druckseitigen Rinnenprofilstücken (7) der beiden Dammaufbauten (72) angreifen.26. Connection of two dam structures according to claim 24, characterized in that the tie rods (74) via insertable shaped pieces (75) on the pressure side Grip the channel profile pieces (7) of the two dam structures (72).
27. Verbindung zweier Dammaufbauten nach Anspruch 26, dadurch gekennzeichnet, dass die einhängbaren Formstücke (75) längsverschiebbar an profilierten Randstreifen (76) der Rinnenprofilstücke (7) aufgenommen sind.27. Connection of two dam structures according to claim 26, characterized in that the attachable shaped pieces (75) are accommodated in a longitudinally displaceable manner on profiled edge strips (76) of the channel profile pieces (7).
28. Verbindung zweier Dammaufbauten nach einem der Ansprüche 24 - 27, dadurch gekennzeichnet, dass die28. Connection of two dam structures according to one of claims 24-27, characterized in that the
Zuganker (74) Ketten sind. Tie rods (74) are chains.
EP03794938A 2002-08-30 2003-08-26 Damm structure for liquids and bulk material Expired - Lifetime EP1532319B1 (en)

Applications Claiming Priority (7)

Application Number Priority Date Filing Date Title
DE10240779 2002-08-30
DE2002140779 DE10240779A1 (en) 2002-08-30 2002-08-30 Dam structure used as a dike for liquids and bulk material comprises two rows of pressure pallets and support pallets arranged at an angle to each other and joined together by traction-pressure tie elements
DE10253889 2002-11-18
DE2002153889 DE10253889B4 (en) 2002-11-18 2002-11-18 Clamping element for flexible material webs and use thereof
DE10258087 2002-12-11
DE2002158087 DE10258087B4 (en) 2002-12-11 2002-12-11 Dam construction for liquids and bulk materials
PCT/EP2003/009431 WO2004025033A1 (en) 2002-08-30 2003-08-26 Damn structure for liquids and bulk material

Publications (2)

Publication Number Publication Date
EP1532319A1 true EP1532319A1 (en) 2005-05-25
EP1532319B1 EP1532319B1 (en) 2005-11-09

Family

ID=31998411

Family Applications (1)

Application Number Title Priority Date Filing Date
EP03794938A Expired - Lifetime EP1532319B1 (en) 2002-08-30 2003-08-26 Damm structure for liquids and bulk material

Country Status (5)

Country Link
EP (1) EP1532319B1 (en)
AT (1) ATE309418T1 (en)
AU (1) AU2003266309A1 (en)
DE (1) DE50301634D1 (en)
WO (1) WO2004025033A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE531421C2 (en) 2007-06-08 2009-03-31 Feros Ab Device intended to be used as a boundary between two areas
US9409707B2 (en) * 2013-05-31 2016-08-09 Falcon Technologies And Services, Inc. Secondary containment unit and methods
SE1500403A1 (en) * 2015-10-07 2017-04-08 Kullberg Sten-Magnus Water barrier element

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE8808124U1 (en) * 1988-06-24 1988-10-20 Lohmar, Hans Josef, 5000 Köln Protective wall, especially for protection against flooding
SE507170C2 (en) * 1995-08-11 1998-04-20 Sten Kullberg Procedure and arrangement in preparing a water dam
SE523055C2 (en) * 2000-04-27 2004-03-23 Sten-Magnus Kullberg flood barrier

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2004025033A1 *

Also Published As

Publication number Publication date
WO2004025033A1 (en) 2004-03-25
AU2003266309A1 (en) 2004-04-30
EP1532319B1 (en) 2005-11-09
ATE309418T1 (en) 2005-11-15
DE50301634D1 (en) 2005-12-15

Similar Documents

Publication Publication Date Title
DE102019127941A1 (en) Mobile flood protection system
DE10216914C1 (en) Pile foundation for building roof support has upper and lower frames with spacing uprights to define gap between them
DE8010258U1 (en) COMPONENT, PARTICULARLY CONCRETE
DE102018105336A1 (en) Basin, scaffolding and side segment
EP1532319B1 (en) Damm structure for liquids and bulk material
DE3015407A1 (en) REINFORCEMENT ELEMENT FOR TRANSMITTING LATERAL FORCES IN PANEL-LIKE SUPPORT LINKS, e.g. FLAT CEILINGS
DE8401849U1 (en) TRANSPORTABLE FLOOD PROTECTIVE WALL
DE10240779A1 (en) Dam structure used as a dike for liquids and bulk material comprises two rows of pressure pallets and support pallets arranged at an angle to each other and joined together by traction-pressure tie elements
EP0190374A1 (en) Self-supporting floor panel
DE2841001A1 (en) Stable L=shaped concrete slab for retaining wall - has base panel on base slab protruding rearward and form locked to it
DE3416482A1 (en) Covered footpath which can be dismantled
DE69303623T2 (en) COVERAGE TO BRIDGE OBSTACLES
DE3910176A1 (en) Protection and sealing of steep slopes, in particular of waste heaps and the like
DE3448322C2 (en) Flood water protection wall
EP0286957B1 (en) Vegetation-sustaining noise barrier
DE10258087B4 (en) Dam construction for liquids and bulk materials
DE3129213A1 (en) Set of structural elements for retaining walls
DE102004036647B4 (en) Waterproof manhole cover
DE1609530A1 (en) Intermediate floor part for a prefabricated house
DD292290A5 (en) PROFILSTAB MIT BIEGESTEIFEN RAHMENECKEN AND USE THEREOF
DE19636168C2 (en) Device for controlling the movement of quick and flying sand and method for the production thereof
EP0382889B1 (en) Section bar with an angle member stiffened against bending, and its use
DE3406248C2 (en)
DE19964360B4 (en) Joint sealing device
DE1970492U (en) EMBOSSING MAT FOR SECURING EARTH STRUCTURES.

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

17P Request for examination filed

Effective date: 20050212

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL LT LV MK

RTI1 Title (correction)

Free format text: DAMM STRUCTURE FOR LIQUIDS AND BULK MATERIAL

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR

DAX Request for extension of the european patent (deleted)
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20051109

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

Ref country code: IE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REF Corresponds to:

Ref document number: 50301634

Country of ref document: DE

Date of ref document: 20051215

Kind code of ref document: P

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20060209

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20060209

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20060209

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20060220

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 20060306

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20060410

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: ISLER & PEDRAZZINI AG

Ref country code: HU

Ref legal event code: AG4A

Ref document number: E000220

Country of ref document: HU

REG Reference to a national code

Ref country code: IE

Ref legal event code: FD4D

ET Fr: translation filed
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20060831

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20060810

REG Reference to a national code

Ref country code: CH

Ref legal event code: PCAR

Free format text: ISLER & PEDRAZZINI AG;POSTFACH 1772;8027 ZUERICH (CH)

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20060826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20051109

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: HU

Payment date: 20080826

Year of fee payment: 6

Ref country code: SE

Payment date: 20080825

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090827

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20090827

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20130830

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20131230

Year of fee payment: 11

Ref country code: AT

Payment date: 20140102

Year of fee payment: 11

Ref country code: GB

Payment date: 20131230

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20131230

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20131230

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CZ

Payment date: 20140116

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20131231

Year of fee payment: 11

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 50301634

Country of ref document: DE

REG Reference to a national code

Ref country code: NL

Ref legal event code: V1

Effective date: 20150301

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 309418

Country of ref document: AT

Kind code of ref document: T

Effective date: 20140826

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20140826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140831

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140831

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140831

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150301

Ref country code: CZ

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140826

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 50301634

Country of ref document: DE

Effective date: 20150303

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140826

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20150430

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140826

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150303

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140901