EP1258566A1 - Foundation method and foundation slab made by such a method - Google Patents
Foundation method and foundation slab made by such a method Download PDFInfo
- Publication number
- EP1258566A1 EP1258566A1 EP01201765A EP01201765A EP1258566A1 EP 1258566 A1 EP1258566 A1 EP 1258566A1 EP 01201765 A EP01201765 A EP 01201765A EP 01201765 A EP01201765 A EP 01201765A EP 1258566 A1 EP1258566 A1 EP 1258566A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- reinforcement
- concrete
- layer
- foundation
- holders
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
Definitions
- the invention relates to a foundation method and a foundation slab.
- the generally applied foundation methods comprises following steps:
- Another disadvantage of this method is teh stability of the trenches themselves, especially in case of high (ground-)water level.
- the trenches collapse even before the concrete can be poured in, which results in unverifiable dimensions of the foundation trenches.
- the foundation comprises a foundation base made of concrete, which is installed on the ground, and a foundation beam made of steel, secured to the foundation base.
- the foundation beam is tightened to the foundation by anchor bolts previously driven into the foundation base, or is tightened by chemical anchors constructed on-site.
- a connecting piece is welded to the foundation beam in advance.
- the foundation beams of the adjacent foundations are thereby connected together by a tie member comprising reinforcing braces.
- a first disadvantage of this foundation method is that it is still necessary to dig out to an important depth for the construction of the concrete base, whereby also the risk of collapsing of the ground stays.
- a second disadvantage is that the connection of the concrete base with steel foundation beams and tie members results in a rather high foundation construction, which rises more than 800 mm above the ground level.
- the purpose of the invention is to provide a foundation method that resolves the abovementioned disadvantages.
- a foundation method that comprises the steps:
- one or more devices selected from air cushions, recycled PVC-blocks, carton or plastic blocks, etc. are used for said lost shuttering.
- zig-zag meshes are used for said distant holders.
- bended meshes and/or reinforcement baskets are used for said distant holders.
- part of said lost shuttering is replaced by technical supplies such as tanks for rain water, septic tanks, and/or heat exchangers for subfloor heating or cooling.
- the method according to the invention comprises preferably the steps:
- the invention relates to a foundation slab which is made by the method as described above.
- the foundation slab has following sizes:
- a foundation slab (1) according to the invention as shown in figure 1, comprises three major parts:
- Such a concrete slab (1) can be realised in two days:
- parts of these two concrete layers can also be repalced by precasted concrete plates, this in order to accelerate the proces.
- a foundation slab made by a method according to the invention has the advantage that a light-weight foundation is provided, which is applicable on ground with low supporting capacity, where otherwise other expensive foundation techniques need to be applied.
- Another advantage is that an excellent stiffness and flexural strength is obtained, as a result of which setting cracks will be reduced to a minimum.
- This foundation slab ends 20 to 30 cm higher than the original ground level, which is often desired.
- This foundation method has a very fast execution, there is little or no removal of ground.
- a combination with a prefabricated cellar, and eventually with a pile or pit foundation can easily be realised. Reinforced underground beams are not necessary. The required stiffness can be obtained by adding extra reinforcement bars in the slabs at the bottom and the top and in the space within the distant holders.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
The invention relates to a foundation method in which the method comprises
providing a first concrete layer (2), provided with distant holders (6), and optionally
provided with a first reinforcement (5), on the ground; whereafter lost shuttering (7)
which can bear the load of concrete is placed between said distant holders (6); and
whereafter a second concrete layer (8), optionally provided with second
reinforcement (9), is provided on top of said lost shuttering (7) and in the space
created by the distant holders (6). For said lost shuttering (7), preferably polystyrene
blocks are used, and for said distant holders (6) zig-zag-meshes are used. The
invention further relates to a foundation slab made by such a method.
Description
- The invention relates to a foundation method and a foundation slab.
- Until now, the generally applied foundation methods comprises following steps:
- removing the soil layer and/or the stirred toplayers of the ground;
- digging trenches with a depth of 800 mm and a width of 600 - 800 mm;
- filling with concrete up to a height of 400 mm;
- laying a layer of full concrete blocks with a width of 300 mm on top of said concrete filled trenches;
- installing sewers;
- filling the space between said full concrete blocks with sand and stabilizer;
- providing on top of said full concrete blocks and the filled space between them a layer of reinforced concrete.
- The disadvantage of this foundation method is that only the trenches bear the full load of the building that is built on top of the foundation. The rest of the concrete serves nothing.
- Another disadvantage of this method is teh stability of the trenches themselves, especially in case of high (ground-)water level. The trenches collapse even before the concrete can be poured in, which results in unverifiable dimensions of the foundation trenches.
- Still another problem that arises with this method is the heavy weight of concrete. Concrete has a weight of 2500 kg/m3. When such a classic foundation method is exerted on ground with a low supporting capacity, the load that such ground can bear is for a great part already taken up by the load of the foundation slab. This means that the load of the building that has to be build on this foundation slab has to be seriously reduced. When the load of the building is too important, subsidence can occur.
- Till now, this problem is solved by exerting expensive foundation techniques such as piles, or by digging deaper into the ground.
- In JP 07211667, a foundation of building and a method for constructing the same is described for reducing the weight of a foundation and for eliminating the need for ground improvement works, etc.. Therefore, the foundation comprises a foundation base made of concrete, which is installed on the ground, and a foundation beam made of steel, secured to the foundation base. The foundation beam is tightened to the foundation by anchor bolts previously driven into the foundation base, or is tightened by chemical anchors constructed on-site. A connecting piece is welded to the foundation beam in advance. The foundation beams of the adjacent foundations are thereby connected together by a tie member comprising reinforcing braces.
- A first disadvantage of this foundation method is that it is still necessary to dig out to an important depth for the construction of the concrete base, whereby also the risk of collapsing of the ground stays.
- A second disadvantage is that the connection of the concrete base with steel foundation beams and tie members results in a rather high foundation construction, which rises more than 800 mm above the ground level.
- Furthermore, the complexity of execution of this foundation method results in a very expensive method.
- In one respect, the purpose of the invention is to provide a foundation method that resolves the abovementioned disadvantages.
- To achieve this purpose, a foundation method is provided that comprises the steps:
- providing a first concrete layer, provided with distant holders, and optionally provided with a first reinforcement, on the ground;
- placing lost shuttering which can bear the load of concrete between said distant holders;
- providing a second concrete layer, optionally provided with a second reinforcement, on top of said lost shuttering and in the space created by the distant holders. In a preferred foundation method according to the invention, polystyrene blocks are used for said lost shuttering.
- This has the advantage that there is a high insulation value. As a result, a warm feeling flour is obtained.
- In another preferred foundation method according to the invention, one or more devices selected from air cushions, recycled PVC-blocks, carton or plastic blocks, etc. are used for said lost shuttering.
- In a specific foundation method according to the invention, zig-zag meshes are used for said distant holders.
- In another specific foundation method according to the invention, bended meshes and/or reinforcement baskets are used for said distant holders.
- In a more specific foundation method of the invention, part of said lost shuttering is replaced by technical supplies such as tanks for rain water, septic tanks, and/or heat exchangers for subfloor heating or cooling.
- The method according to the invention comprises preferably the steps:
- measuring out the external contours of the building;
- removing the soil layer and/or the stirred toplayers of the ground;
- installing sewers in a layer of stabilisator;
- placing of external shuttering according to the external contours of the building;
- optionally, placing a PE-foil on top of said layer of stabilisator;
- laying a first mesh-reinforcement on the ground;
- fixing zig-zag-meshes to said mesh-reinforcement;
- pouring a first layer concrete on said mesh-reinforcement;
- after curing of said first layer concrete until it is passable, placing polystyrene blocks between said zig-zag-meshes;
- optionally, placing extra reinforcement bars;
- laying a second mesh-reinforcement on top of said polystyrene blocks;
- pouring a second layer concrete on said second mesh-reinforcement and in the space between the polystyrene blocks created by the zig-zag-meshes.
- In another respect, the invention relates to a foundation slab which is made by the method as described above.
- In a preferred embodiment of the foundation slab according to the invention, the foundation slab has following sizes:
- a thickness of 50 to 150 mm for said first concrete layer;
- a thickness varying between 200 and 1200 mm, a width of circa 1000 mm and a length of a couple of meters for said polystyrene blocks;
- a height of 200 to 1200 mm for said distant holders.
- a thickness of 50 to 150 mm for said second concrete layer.
- The invention is now further explained on the basis of the following detailed specification of a preferred foundation slab according to this invention and of the foundation method for making such a foundation slab. The purpose of this specification is only to give a clarifying example and can therefore in no way be interpreted as a restriction on the field of application of the invention or on the patent rights claimed in the claims.
- In this specification reference is made by means of reference numbers to the figures attached hereto, of which
- figure 1 is a cross-section of a foundation slab according to the invention;
- figure 2 is a perspective view of a foundation slab according to the invention;
- figure 3 is a view from above of a foundation slab according to the invention.
- A foundation slab (1) according to the invention, as shown in figure 1, comprises three major parts:
- a first part (10), consisting of a first concrete layer (2) that is laid on a layer of stabilisator (3), on which optionally a PE-foil (4) is spread out, and in which the sewers are installed. This first concrete slab (2) has a relatively low thickness varying from 50 to 150 mm. In most cases, the first concrete slab (2) is reinforced by a first mesh-reinforcement (5). Therefore, this first mesh-reinforcement is placed on top of the layer of stabilisator; optionally more reinforcement may be required. Distant holders (6) with a height of 200 to 1200 mm are fixed appropriately to the first reinforcement (5). Preferably, zig-zag meshes are used. But, also bended meshes or reinforcement baskets can serve as distant holders (6). Hereafter, the concrete is being poured.
- a second part (20), whereby after a minimum of curing of the concrete, i.e. until the concrete is being passable, lost shuttering (7) is placed between the distant holders (6). Preferably, expanded polystyrene blocks with a width of circa 1000 mm, a length of a couple of meters and a thickness varying between 200 and 1200 mm are used. However, carton, plastic blocks, or even air cushions can serve as well. The space between the lost shuttering (7), i.e. where the distant holders (6) are located, might require extra bars, e.g. of iron, as reinforcement.
- a third part (30), whereby on top of the lost shuttering (7) a second reinforced concrete layer (8) is provided. Therefor, a second mesh-reinforcement (9) is provided on top of the second part (20), whereafter a layer concrete with a thickness from 50 to 150 mm is poured on top of the lost shuttering (7) and in the space created by the distant holders (6). This results in a kind of T-rib-floor, with important extra stiffness, which is obtained by the first reinforced concrete layer (2) on the bottom of the foundation slab.
- On top of the third part (30) the facade (11) of the building and a layer of covering (in French "chappe") (12) is placed.
- As a result, a stiff hybride foundation slab of 400 to 1500 mm thickness is obtained, using three different materials with following properties:
- concrete, which has high pressure resistance and is easy to be shaped;
- steel which has a high tensile strength, but which has to be placed as far away as possible from the neutral line to obtain a maximum use of the steel;
- polystyrene, or another light-weight shuttering material, which is light-weight and sufficient pressure resistant to support the poured concrete during its curing time. These light-weight materials are located between the active zones of the slab on the bottom and on the top, i.e. around the neutral line.
- Such a concrete slab (1) can be realised in two days:
- day 1:
- measuring out the external contours (13) of the building;
- removing the soil layer and/or the stirred toplayers of the ground;
- installing sewers in a layer of stabilisator (3);
- placing of external shuttering (14) according to the external contours (13) of the building;
- optionally, placing a PE-foil (2) on top of said layer of stabilisator (3);
- laying a first mesh-reinforcement (5) on the ground;
- fixing zig-zag-meshes (6) to said first mesh-reinforcement (5);
- pouring a first layer concrete (2) on said first mesh-reinforcement (5);
- day 2:
- after curing of said first layer concrete (2) until it is passable, placing polystyrene blocks (7) between said zig-zag-meshes (6);
- optionally, placing extra reinforcement bars;
- laying a second mesh-reinforcement (9) on top of said polystyrene blocks (7);
- pouring a second layer concrete (8) on said second mesh-reinforcement (9) and in the space between the polystyrene blocks (7) created by the zig-zag-meshes (6).
- On
day 3, the building of the facades (11) of the building and the laying of the layer of covering (12) can start. - Before pouring the first (2) and second concrete layer (8), parts of these two concrete layers can also be repalced by precasted concrete plates, this in order to accelerate the proces.
- A foundation slab made by a method according to the invention has the advantage that a light-weight foundation is provided, which is applicable on ground with low supporting capacity, where otherwise other expensive foundation techniques need to be applied.
- Another advantage is that an excellent stiffness and flexural strength is obtained, as a result of which setting cracks will be reduced to a minimum.
- Also no trenches are necessary. As a result, they can not collapse, which happens often in case of ground with low supporting capacity or in case of high ground-water level.
- Little or no ground supplements are required. This foundation slab ends 20 to 30 cm higher than the original ground level, which is often desired.
- This foundation method has a very fast execution, there is little or no removal of ground.
- A combination with a prefabricated cellar, and eventually with a pile or pit foundation can easily be realised. Reinforced underground beams are not necessary. The required stiffness can be obtained by adding extra reinforcement bars in the slabs at the bottom and the top and in the space within the distant holders.
- In other words, a less expensive foundation in comparison with a classic foundation is obtained, which even has better supporting capacity than the foundations known at present.
Claims (9)
- Foundation method, characterised in that the method comprises the steps:providing a first concrete layer (2), provided with distant holders (6), and optionally provided with a first reinforcement (5), on the ground;placing lost shuttering (7) which can bear the load of concrete between said distant holders (6);providing a second concrete layer (8), optionally provided with second reinforcement (9), on top of said lost shuttering (7) and in the space created by the distant holders (6).
- Method according to claim 1, characterised in that polystyrene blocks are used for said lost shuttering (7).
- Method according to claim 1, characterised in that one or more devices selected from air cushions, recycled PVC-blocks, carton or plastic blocks, etc. are used for said lost shuttering (7).
- Method according to claim 1, characterised in that zig-zag meshes are used for said distant holders (6).
- Method according to claim 1, characterised in that bended meshes and/or reinforcement baskets are used for said distant holders (6).
- Method according to one of claims 1 up to and including 3, characterised in that part of said lost shuttering (7) is replaced by replaced by technical supplies such as tanks for rain water, septic tanks, and/or heat exchangers for subfloor heating or cooling.
- Method according to one of claims 1 up to and including 6, characterised in that the method comprises the steps:measuring out the external contours (13) of the building;removing the soil layer and/or the stirred toplayers of the ground;installing sewers in a layer of stabilisator (3);placing of external shuttering (14) according to the external contours (13) of the building;optionally, placing a PE-foil on top of said layer of stabilisator (3);laying a first mesh-reinforcement (5) on the ground;fixing zig-zag-meshes (6) to said mesh-reinforcement (5);pouring a first layer concrete (2) on said mesh-reinforcement (5);after curing of said first layer concrete (2) until it is passable, placing polystyrene blocks (7) between said zig-zag-meshes (6);optionally, placing extra reinforcement bars;laying a second mesh-reinforcement (9) on top of said polystyrene blocks (7);pouring a second layer concrete (8) on said second mesh-reinforcement (9) and in the space between the polystyrene blocks (7) created by the zig-zag-meshes (6).
- Foundation slab, characterised in that the slab is made by the method according to one of the preceeding claims.
- Foundation slab according to claim 8, characterised by following sizes:a thickness of 50 to 150 mm for said first concrete layer (2);a thickness varying between 200 and 1200 mm, a width of circa 1000 mm and a length of a couple of meters for said polystyrene blocks (7);a height of 200 to 1200 mm for said distant holders (6).a thickness of 50 to 150 mm for said second concrete layer (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP01201765A EP1258566A1 (en) | 2001-05-14 | 2001-05-14 | Foundation method and foundation slab made by such a method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP01201765A EP1258566A1 (en) | 2001-05-14 | 2001-05-14 | Foundation method and foundation slab made by such a method |
Publications (1)
Publication Number | Publication Date |
---|---|
EP1258566A1 true EP1258566A1 (en) | 2002-11-20 |
Family
ID=8180295
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP01201765A Withdrawn EP1258566A1 (en) | 2001-05-14 | 2001-05-14 | Foundation method and foundation slab made by such a method |
Country Status (1)
Country | Link |
---|---|
EP (1) | EP1258566A1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007224536A (en) * | 2006-02-22 | 2007-09-06 | Eifs Japan株式会社 | Artificial ground and its construction method |
ES2283160A1 (en) * | 2004-01-23 | 2007-10-16 | Vicente Roca Amenedo | Isolated mould system for foundation, has excavation carrying out on ground running rock and light material blocks, which are constituted by group of prismatic pieces with systems of drainage in their lower base |
BE1022899B1 (en) * | 2015-09-02 | 2016-10-10 | SD Building & Engineering - Group bvba | Method for manufacturing a foundation plate and foundation plate |
JP6944224B1 (en) * | 2021-02-07 | 2021-10-06 | 株式会社ピーエルジー | Foundation structure for structures |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2018875A (en) * | 1978-04-07 | 1979-10-24 | Caledonian Moroccan Constr | Improvements in buildings |
DE4015474A1 (en) * | 1989-05-16 | 1990-11-22 | Tanaka Homes Co | Concrete floor for building - is supported by parallel tubular structural elements |
JPH07166556A (en) * | 1993-12-17 | 1995-06-27 | Kurimoto Ltd | Construction method for hollow foundation slab |
JPH07211667A (en) | 1994-01-26 | 1995-08-11 | Nissan Motor Co Ltd | Fabrication of semiconductor device |
JPH085107A (en) * | 1993-09-02 | 1996-01-12 | Keiji Kosaka | Cooling-heating equipment of house or the like utilizing heat storage function of box type foundation |
JPH1018307A (en) * | 1996-07-08 | 1998-01-20 | Toshin Jiyuuken Kk | Mat foundation and its construction method |
JP2000120077A (en) * | 1998-10-16 | 2000-04-25 | Sadaaki Mochizuki | Housing foundation, construction method thereof, and housing structure |
-
2001
- 2001-05-14 EP EP01201765A patent/EP1258566A1/en not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2018875A (en) * | 1978-04-07 | 1979-10-24 | Caledonian Moroccan Constr | Improvements in buildings |
DE4015474A1 (en) * | 1989-05-16 | 1990-11-22 | Tanaka Homes Co | Concrete floor for building - is supported by parallel tubular structural elements |
JPH085107A (en) * | 1993-09-02 | 1996-01-12 | Keiji Kosaka | Cooling-heating equipment of house or the like utilizing heat storage function of box type foundation |
JPH07166556A (en) * | 1993-12-17 | 1995-06-27 | Kurimoto Ltd | Construction method for hollow foundation slab |
JPH07211667A (en) | 1994-01-26 | 1995-08-11 | Nissan Motor Co Ltd | Fabrication of semiconductor device |
JPH1018307A (en) * | 1996-07-08 | 1998-01-20 | Toshin Jiyuuken Kk | Mat foundation and its construction method |
JP2000120077A (en) * | 1998-10-16 | 2000-04-25 | Sadaaki Mochizuki | Housing foundation, construction method thereof, and housing structure |
Non-Patent Citations (2)
Title |
---|
PATENT ABSTRACTS OF JAPAN vol. 1996, no. 05 31 May 1996 (1996-05-31) * |
PATENT ABSTRACTS OF JAPAN vol. 2000, no. 07 29 September 2000 (2000-09-29) * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ES2283160A1 (en) * | 2004-01-23 | 2007-10-16 | Vicente Roca Amenedo | Isolated mould system for foundation, has excavation carrying out on ground running rock and light material blocks, which are constituted by group of prismatic pieces with systems of drainage in their lower base |
JP2007224536A (en) * | 2006-02-22 | 2007-09-06 | Eifs Japan株式会社 | Artificial ground and its construction method |
BE1022899B1 (en) * | 2015-09-02 | 2016-10-10 | SD Building & Engineering - Group bvba | Method for manufacturing a foundation plate and foundation plate |
JP6944224B1 (en) * | 2021-02-07 | 2021-10-06 | 株式会社ピーエルジー | Foundation structure for structures |
JP2022120861A (en) * | 2021-02-07 | 2022-08-19 | 株式会社ピーエルジー | Foundation structure for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6434900B1 (en) | Prefabricated concrete wall system | |
US9371648B1 (en) | Concrete building structure and method for modular construction of same | |
US8827235B1 (en) | Concrete form for building foundation construction with form insert creating recessed sections | |
KR101627279B1 (en) | Biased soil pressure reinforcement rigid-frame bridge and construction method of the same | |
JP2015518931A (en) | Modular foundation that can withstand ground movement | |
JP7189001B2 (en) | How to construct the foundation of a building | |
WO2011009219A1 (en) | Shoring free excavation and basement construction apparatus and method | |
EP1258566A1 (en) | Foundation method and foundation slab made by such a method | |
US4232491A (en) | Swimming pool deck | |
JPH05230845A (en) | L-shaped block retaining wall structure and construction method thereof | |
KR101808833B1 (en) | Floor structure of underground floor with reduced floor height using shear reinforcement and the construction method thereof | |
JP7016106B2 (en) | Lightweight embankment structure and how to build a lightweight embankment | |
CA2902118A1 (en) | Concrete building structure and method for modular construction of same | |
KR102667832B1 (en) | Design method of underground exterior wall using PHC retaining wall as permanent exterior wall | |
KR200245125Y1 (en) | A pier structure for engineering works | |
EP0910710B1 (en) | Process for carrying out a sheet piling underneath an existing bearing wall or partition | |
KR20010019079A (en) | Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System | |
JPH07310329A (en) | Foundation structure of building and construction method thereof | |
JPH07279184A (en) | Floating underground beam foundation for building | |
JP6032568B2 (en) | Hollow foundation foundation and its construction method | |
KR102264595B1 (en) | Self supporting type phc pile and construction method for the same | |
CN212656215U (en) | Assembled pipe support of cross prefabricated steel concrete pile and steel-pipe column combination | |
JP2876452B2 (en) | Retaining wall construction method | |
JPH03228921A (en) | Execution method for concrete foundation work | |
JP2615344B2 (en) | Foundation using expanded polystyrene and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR |
|
AX | Request for extension of the european patent |
Free format text: AL;LT;LV;MK;RO;SI |
|
AKX | Designation fees paid |
Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20030521 |