DE3516477C2 - - Google Patents
Info
- Publication number
- DE3516477C2 DE3516477C2 DE19853516477 DE3516477A DE3516477C2 DE 3516477 C2 DE3516477 C2 DE 3516477C2 DE 19853516477 DE19853516477 DE 19853516477 DE 3516477 A DE3516477 A DE 3516477A DE 3516477 C2 DE3516477 C2 DE 3516477C2
- Authority
- DE
- Germany
- Prior art keywords
- station
- line
- formwork
- hardening
- preparation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B15/00—General arrangement or layout of plant ; Industrial outlines or plant installations
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
Die Erfindung betrifft eine Anlage zur Herstellung von Betonfertigteilen nach dem Palettenumlaufverfahren mit länglichen, verfahrbaren Paletten, die mit Formen belebt werden oder Formaufsätze aufweisen, mit einer Vorbereitungsstraße, in der die Bewehrungen und Installationen eingebracht werden, einer Betonierstation, einer Härtestraße, einer Entschalstation sowie einer Schaltstation, wobei die Vorbereitungsstraße und die Härtestraße parallel zueinander verlaufen.The invention relates to a plant for the production of Precast concrete parts using the pallet circulation process elongated, movable pallets that enlivened with shapes be or have mold attachments, with a preparation line, in which the reinforcements and installations are introduced a concreting station, a hardening street, a demoulding station and a switching station, where the preparation line and the Härtestrasse parallel to each other.
Eine derartige Anlage ist der DE-AS 20 32 793 entnehmbar. Bei dieser bekannten Anlage werden die fahrbaren Paletten in Längsrichtung hintereinander durch die Straßen bewegt. Zwischen der Vorbereitungsstraße und der Härtestraße ist eine Schal- und Entschalstation angeordnet. In Verlängerung der Vorbereitungsstraße befindet sich eine Verteilerstation, an welche sich eine Abhebestation anschließt. Anschließend an die Schal- und Entschalstation sowie an die Verteilerstation schließt sich eine Reinigungsstation an. Es sind zwei Verschiebebühnen vorgesehen. Such a system is the DE-AS 20 32 793 removable. In this known system, the mobile pallets moved longitudinally through the streets. Between the preparation road and the Härtestrasse a formwork and formwork station arranged. In extension there is a distribution station on the preparation line, which is followed by a lifting station. Subsequently to the formwork and formwork station as well as to the distribution station is followed by a cleaning station. There are two transfer platforms are provided.
Die Arbeitsweise bei dieser bekannten Anlage ist wie folgt: von der ersten Schiebebühne wird eine Palette von der Härtestraße der Entschalstation zugeführt und dort entschalt. Diese erste Verschiebebühne transportiert die Palette über die Verteilerstation zur Abhebestation, wo gekippt und durch einen Abhebekran das Betonfertigteil entfernt wird. Die erste Verschiebebühne fährt sodann zur Härtestraße zurück und übernimmt eine neue Palette. Die in der Abhebestation entleerte Palette wird von einer zweiten Schiebebühne übernommen, über die Verteilerstation der Reinigungsstation zugeführt, dort gereinigt, über die Verteilerstation der Schal- und Entschalstation zugeführt, eingeschalt und über die Verteilerstation in die Vorbereitungsstraße geschoben.The operation in this known system is like follows: a pallet is created from the first transfer table from the Härtestrasse to the demoulding station and unlock there. This first transfer platform transports the pallet via the distribution station to the lifting station, where the precast concrete is tipped and lifted by a lifting crane Will get removed. The first transfer platform moves then back to Härtestrasse and takes over a new one Palette. The pallet emptied in the lifting station is taken over by a second transfer table the distribution station is fed to the cleaning station, cleaned there, via the distribution station of the formwork and Demoulding station fed, switched on and via the distribution station pushed into the preparation line.
Diese bekannte Anlage weist eine Reihe von Nachteilen auf. Die Vorbereitungsstraße ist sehr lang, da dort die Paletten hintereinander in ihrer Längsrichtung verfahren werden. Die Paletten durchfahren die Härtestraße ebenfalls in Längsrichtung. Da die Verweildauer der Paletten in der Härtestraße länger ist als deren Durchlaufzeit durch die Vorbereitungsstraße, müssen in der Härtestraße mehrere Reihen von Paletten angeordnet werden. Das Entschalen und das Abheben des Betonfertigteils muß taktzeitmäßig übereinstimmen mit dem Reinigen und Einschalen. Ein wesentlicher Nachteil ist darin zu sehen, daß eine Produktionsunterbrechung stattfindet, wenn andere Betonfertigteile als die gerade produzierten hergestellt werden sollen. Es besteht nämlich keine Möglichkeit, bei dieser bekannten Anlage Ausweichstationen vorzusehen, wo die Paletten mit anderen Formen belegt werden könnten.This known system has a number of disadvantages. The preparation line is very long because of the pallets be moved one behind the other in their longitudinal direction. The pallets also travel longitudinally along the Härtestrasse. Since the pallet stays in Härtestrasse is longer than their lead time through the Preparation street, must be several in Härtestrasse Rows of pallets can be arranged. The formwork and the lifting of the precast concrete element must be in accordance with the cycle time agree with cleaning and formwork. A The main disadvantage is that a Production interruption takes place when others Prefabricated concrete parts are manufactured than those just produced should be. Because there is no way to provide alternative stations in this known system, where the pallets could be covered with other shapes.
Es stellt sich die Aufgabe, diese Anlage so zu verbessern, daß die Vorbereitungsstraße und die Härtestraße wesentlich kürzer werden und die Flexibilität der Anlage erhöht wird.The task is to improve this system that the preparation line and the hardening line become much shorter and the flexibility the plant is increased.
Gelöst wird diese Aufgabe mit den kennzeichnenden Merkmalen im Anspruch 1. Vorteilhafte Ausgestaltungen sind den Unteransprüchen entnehmbar.This task is solved with the characteristic features in claim 1. Advantageous refinements are the dependent claims.
Ein Ausführungsbeispiel wird anhand der Zeichnung näher erläutert. Es zeigtAn exemplary embodiment is based on the drawing explained. It shows
Fig. 1 eine Draufsicht auf die Anlage, Fig. 1 is a plan view of the plant,
Fig. 2 einen Schnitt längs der Linie A-A in Fig. 1, Fig. 2 shows a section along the line AA in Fig. 1,
Fig. 3 einen Schnitt längs der Linie B-B in Fig. 1, Fig. 3 is a section along the line BB in Fig. 1,
Fig. 4 einen Schnitt längs der Linie C-C in Fig. 1 und Fig. 4 is a section along the line CC in Fig. 1 and
Fig. 5 eine Ansicht in Pfeilrichtung D in Fig. 1. Fig. 5 is a view in direction of arrow D in FIG. 1.
Die Anlage weist eine Vorbereitungsstraße 1 auf, welche die Paletten 2 quer zu ihrer Längsrichtung durchwandern. Diese weisen beispielsweise eine Länge von 15 bis 20 m auf. Sie sind mit Decken- und Wandplattenformen belegt oder weisen Formaufsätze zur Herstellung von Stabteilen unterschiedlicher Art auf. In der Vorbereitungsstraße 1 werden in die Formen die Bewehrung, die Installationen, Türen, Fenster usw. eingebracht. Nachdem die Vorbereitungsstraße in Pfeilrichtung durchwandert ist, wird jeweils eine zum Betonieren vorbereitete Palette am Ende der Vorbereitungsstraße 1 quer zu dieser Straße verschoben und gelangt zu einer Betonierstation 3. In diese Betonierstation 3 wird die Palette quer zu ihrer Längsachse eingeschoben. Es wird dort der Beton eingefüllt und verdichtet. Diese Betonierstation 3 kann gegenüber den übrigen Gebäuden schallisoliert sein. Nach dem Verdichten wird die fahrbare Palette quer zu ihrer Längsachse zurückgeschoben und sodann in ihrer Längsachse verfahren, bis sie sich am Anfang der Härtestraße 4 befindet. Sie durchwandert dann die Härtestraße 4 quer zu ihrer Längsachse. Die Abstände zwischen benachbarten Paletten 2 sind in der Härtestraße 4 wesentlich geringer als in der Vorbereitungsstraße 1.The system has a preparation line 1 , which the pallets 2 traverse transversely to their longitudinal direction. These have a length of 15 to 20 m, for example. They are covered with ceiling and wall plate shapes or have mold attachments for the production of various types of rod parts. Reinforcement, installations, doors, windows, etc. are introduced into the molds in preparation line 1 . After the preparatory line has traveled in the direction of the arrow, a pallet prepared for concreting at the end of preparatory line 1 is shifted transversely to this street and arrives at a concreting station 3 . The pallet is pushed into this concreting station 3 transversely to its longitudinal axis. The concrete is poured in and compacted there. This concreting station 3 can be soundproofed from the other buildings. After compaction, the mobile pallet is pushed back transversely to its longitudinal axis and then moved in its longitudinal axis until it is at the beginning of hardening street 4 . It then traverses Härtestrasse 4 across its longitudinal axis. The distances between adjacent pallets 2 are significantly smaller in Härtestrasse 4 than in preparation street 1 .
Am Ende der Härtestraße 4 befindet sich eine Entschal- und Kippstation 5, wo die Entschalung stattfindet und das entschalte Betonfertigteil von einem Portalkran 6 übernommen wird. Der Portalkran ist in Verlängerung der Härtestraße 4 verfahrbar. Der durch die Härtestraße 4 verlaufende Schienenweg 7 erstreckt sich bis in den Bereich des Portalkranes 6. Dieser sich in den Bereich des Portalkranes 6 erstreckende Teil des Schienenwegs 7 kann als Ausweichstation benutzt werden.At the end of Härtestrasse 4 there is a demoulding and tipping station 5 , where the demolding takes place and the demolded precast concrete part is taken over by a gantry crane 6 . The gantry crane can be moved in the extension of Härtestrasse 4 . The rail path 7 running through Härtestrasse 4 extends into the area of the gantry crane 6 . This part of the rail track 7 extending into the area of the portal crane 6 can be used as an alternative station.
Von der Entschal- und Kippstation 5 werden die Paletten 2 quer zur Härtestraße 4 in Längsrichtung zu einer Reinigungs- und Schalstation 8 verfahren. Sie werden sodann in Längsrichtung an den Anfang der Vorbereitungsstraße 1 gefahren.From the demoulding and tipping station 5 , the pallets 2 are moved transversely to Härtestrasse 4 in the longitudinal direction to a cleaning and formwork station 8 . You will then be driven in the longitudinal direction to the beginning of preparation line 1 .
Bei der Schalstation 8 ist eine Ausweichstation 9 vorgesehen, in welche die Paletten 2 quer zu ihrer Längsachse in Richtung auf die Betonierstation 3 verfahren werden können. In dieser Ausweichstation 9 können die Paletten 2 mit anderen Decken- und Wandplattenformen bzw. mit Formaufsätzen zur Herstellung von Stabteilen belegt werden. In Verlängerung dieser Ausweichstation 9 ist zu diesem Zweck ein Formenlager 10 vorgesehen.At the formwork station 8 , an escape station 9 is provided, into which the pallets 2 can be moved transversely to their longitudinal axis in the direction of the concreting station 3 . In this alternative station 9 , the pallets 2 can be covered with other ceiling and wall plate shapes or with mold attachments for the production of rod parts. An extension of this alternative station 9 is provided with a mold store 10 for this purpose.
Das Rechteck, das einerseits durch die Straßen 1, 4 und andererseits durch die Ausweichstationen 9 und den Verschiebeweg zwischen den Straßen 1, 4 begrenzt ist, wird eingenommen von einer Station 11, in welcher die Armierung hergestellt wird.The rectangle, which is delimited on the one hand by the streets 1, 4 and on the other hand by the alternative stations 9 and the displacement path between the streets 1, 4 , is occupied by a station 11 in which the reinforcement is produced.
Der Bereich von der Betonierstation 3 bis in das Formenlager 10 wird überstrichen von einem Laufkran 12.The area from the concreting station 3 to the mold store 10 is covered by a traveling crane 12 .
In Verlängerung der Härtestraße 4 ist das Fertigteilelager 13 vorgesehen, das vom Portalkran 6 überstrichen wird. In Verlängerung der Vorbereitungsstraße 1 ist ein Palettenlager 14 vorgesehen, das ebenfalls von einem Portalkran 15 überstrichen wird. Der Schienenweg 16 durch die Vorbereitungsstraße 1 erstreckt sich bis in den Bereich des Portalkranes 15. Nicht benötigte Paletten werden in diese Ausweichstation in Verlängerung der Vorbereitungsstraße 1 verschoben und werden vom Kran 15 übernommen. Die Verlängerungen der Schienenwege 7 und 16, die Lager 13, 14 und die Portalkräne 6, 15 sind also im wesentlichen identisch zueinander.In an extension of Härtestraße 4 , the finished parts store 13 is provided, which is covered by the gantry crane 6 . In extension of the preparation line 1 , a pallet warehouse 14 is provided, which is also swept by a gantry crane 15 . The rail track 16 through the preparation road 1 extends into the area of the portal crane 15 . Pallets that are not required are moved to this alternative station as an extension of preparation line 1 and are taken over by crane 15 . The extensions of the rail tracks 7 and 16 , the bearings 13, 14 and the portal cranes 6, 15 are therefore essentially identical to one another.
Oberhalb der Vorbereitungsstraße 1 befindet sich das Lager 17 für die in die Schalungen einzubauenden Einbauteile.Above the preparation line 1 is the warehouse 17 for the built-in parts to be installed in the formwork.
Die in Verlängerung des Schienenweges 7 vorgesehene Ausweichstation ist mit 7′ bezeichnet, während die Ausweichstation in Verlängerung des Schienenweges 16 mit 16′ bezeichnet ist.The provided in the extension of the rail path 7 alternative station is 7 ' , while the alternative station in extension of the rail path 16 is designated 16' .
Die Anlage ist ohne weiteres durch eine weitere Härtestraße 4′ und ein weiteres Fertigteillager 13′ verlängerbar, welche parallel zur Härtestraße 4 und zum Fertigteilelager 13 angeordnet sind.The system can easily be extended by a further hardening line 4 ' and a further finished parts store 13' , which are arranged parallel to the hardening line 4 and the finished parts store 13 .
Beidseits der Betonierstation 3 in Verlängerung der Vorbereitungsstraße 1 und der Härtestraße 4 ist Platz für je eine Rohrziehanlage, was die Herstellung von großformatigen Hohldeckenplatten ermöglicht.On both sides of the concreting station 3, in the extension of the preparation line 1 and the hardening line 4, there is space for a pipe drawing system, which enables the production of large-format hollow ceiling panels.
Der Verteilerwagen, siehe Position 8 in Fig. 3, weist eine eingebaute hydraulische Kippvorrichtung auf, so daß bei der Herstellung von Wandelementen zum Entschalen die Palette auf etwa 80° Neigung gekippt werden kann, um ein senkrechtes Abheben dieser Wandelemente zu ermöglichen.The distribution trolley, see position 8 in Fig. 3, has a built-in hydraulic tilting device, so that the pallet can be tilted to about 80 ° inclination in the manufacture of wall elements for demoulding, in order to enable vertical lifting of these wall elements.
Claims (11)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19853516477 DE3516477A1 (en) | 1985-05-08 | 1985-05-08 | Installation for producing precast concrete parts |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19853516477 DE3516477A1 (en) | 1985-05-08 | 1985-05-08 | Installation for producing precast concrete parts |
Publications (2)
Publication Number | Publication Date |
---|---|
DE3516477A1 DE3516477A1 (en) | 1986-11-13 |
DE3516477C2 true DE3516477C2 (en) | 1993-09-02 |
Family
ID=6270097
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19853516477 Granted DE3516477A1 (en) | 1985-05-08 | 1985-05-08 | Installation for producing precast concrete parts |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE3516477A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10222989A1 (en) * | 2002-05-24 | 2003-12-24 | Christian Prilhofer | Pallet production process for thick walls smooth on both sides involved mold preparation, closing circulating pallet with counter-pallet, filling and leaving to set |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ES2127057B1 (en) * | 1995-06-02 | 1999-11-16 | Abadia Herranz Jose Gerardo | SYSTEM FOR OBTAINING PREFABRICATED ELEMENTS FOR CONSTRUCTION. |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT302872B (en) * | 1969-07-03 | 1972-10-25 | Hugo Mischek Dipl Ing | System and process for shuttering and demoulding, cleaning and emptying of mold trolleys |
-
1985
- 1985-05-08 DE DE19853516477 patent/DE3516477A1/en active Granted
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10222989A1 (en) * | 2002-05-24 | 2003-12-24 | Christian Prilhofer | Pallet production process for thick walls smooth on both sides involved mold preparation, closing circulating pallet with counter-pallet, filling and leaving to set |
DE10222989B4 (en) * | 2002-05-24 | 2004-08-26 | Christian Prilhofer | Process for the production of solid formwork walls smooth on both sides using the pallet circulation process |
Also Published As
Publication number | Publication date |
---|---|
DE3516477A1 (en) | 1986-11-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2334646A1 (en) | METHOD FOR MANUFACTURING ROOM BOXES FOR FABRIC HOUSES | |
DE3615460C1 (en) | Device for the production of reinforcements of reinforced concrete slabs for prefabricated ceilings | |
DE2257768A1 (en) | PLANT FOR PRODUCING PRE-FABRICATED CONCRETE PARTS | |
DE3516477C2 (en) | ||
DE2845106A1 (en) | Reinforced concrete cell prodn. system - transports assembled reinforcing cage into formwork and tips it into pouring position | |
EP0032959A1 (en) | Method and falsework for constructing bridges of prestressed concrete | |
DE2032793C3 (en) | System and method for shuttering, demoulding, cleaning and emptying of mold trolleys | |
AT400457B (en) | COMPONENT AND METHOD FOR THE PRODUCTION THEREOF | |
DE2145746A1 (en) | METHOD AND DEVICE FOR MANUFACTURING A CONCRETE FORMING BLOCK | |
EP0536600B1 (en) | Device for producing reinforcements | |
DE2206170A1 (en) | METHOD OF MANUFACTURING ROOM BOXES FOR FABRIC HOUSES | |
DE3416028C2 (en) | ||
DE4133589A1 (en) | Steel reinforcement mfr. for concrete slabs - involves industrial robots to place reinforcement elements in position | |
EP0689913A1 (en) | Auxiliary device for making shuttering parts | |
DE1683943C3 (en) | ||
DE2531957B2 (en) | PROCESS FOR THE AUTOMATIC PRE-FABRICATION OF WALL PARTS FROM BLOCK BRICKS OR DGL. | |
DE3344034A1 (en) | Installation for assembly-line production of precast concrete parts, in particular of large panels | |
DE2264886C3 (en) | System for the horizontal production of cuboid reinforced concrete room cells open at the front | |
DE1584448C (en) | Facility for the production of precast concrete | |
DE1459230A1 (en) | Steaming tunnel to accelerate the setting of precast concrete parts | |
DE1584609C3 (en) | Plant for casting, of concrete building panels with a battery of casting molds | |
DE2510338A1 (en) | CONVEYOR BELT ARRANGEMENT FOR THE PRODUCTION OF COMPONENTS | |
DE2147748B2 (en) | PROCESS FOR CREATING A STRUCTURE FROM A SERIES OF PREFABRICATED ELEMENTS | |
DE2410025A1 (en) | Concrete component track production system - has pallet track with intermediate lifting devices above or below production track | |
DE2649030A1 (en) | Concrete slab casting installation - has central track and cross tracks between filling and hardening stations, with vibrator and reverser at one end |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8110 | Request for examination paragraph 44 | ||
D2 | Grant after examination | ||
8364 | No opposition during term of opposition | ||
8339 | Ceased/non-payment of the annual fee |