DE19858934A1 - Concrete shaft under part production process - Google Patents
Concrete shaft under part production processInfo
- Publication number
- DE19858934A1 DE19858934A1 DE1998158934 DE19858934A DE19858934A1 DE 19858934 A1 DE19858934 A1 DE 19858934A1 DE 1998158934 DE1998158934 DE 1998158934 DE 19858934 A DE19858934 A DE 19858934A DE 19858934 A1 DE19858934 A1 DE 19858934A1
- Authority
- DE
- Germany
- Prior art keywords
- core
- shaft
- distributor
- press
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/16—Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes
- B28B7/168—Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes for holders or similar hollow articles, e.g. vaults, sewer pits
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/02—Manhole shafts or other inspection chambers; Snow-filling openings; accessories
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Moulds, Cores, Or Mandrels (AREA)
Abstract
Description
Es sind Verfahren zur Herstellung von Schachtunterteilen aus Beton mit selbsttragenden Einbauten aus Kunststoff und anderen Werkstoffen aus der Patentanmeldung P 320 5833.0.25, der Offenlegungsschrift DE 44 18 370 A1 sowie dem Europäischen Patent EP 0454098 A2 bekannt.There are processes for manufacturing manhole bases made of concrete with self-supporting internals Plastic and other materials from patent application P 320 5833.0.25, the published patent application DE 44 18 370 A1 and the European patent EP 0454098 A2 are known.
Für diese Anmeldungen ist bezeichnend, daß die Schachtunterteile gegenüber der Gebrauchslage kopfüber gefertigt werden. Dies geschieht in Formen (Fig. 1), die aus einem Formkern 1, einem Formmantel 2, einer Hubeinrichtung 3 sowie einer Preßglocke 4 bestehen. Kern 1 und Formmantel 2 sind einander fest zugeordnet und dabei starr. Sie bilden einen konzentrischen Spalt. Preßglocke 4 und Hubeinrichtung 3 sind in der Höhe verstellbar.For these applications, it is significant that the manhole bases are manufactured upside down compared to the position of use. This is done in molds ( Fig. 1), which consist of a mold core 1 , a mold shell 2 , a lifting device 3 and a press bell 4 . Core 1 and molded jacket 2 are firmly assigned to each other and rigid. They form a concentric gap. Press bell 4 and lifting device 3 are adjustable in height.
Bei Beginn der Fertigung wird die Hubeinrichtung 3 mit einer Untermuffe in ihre tiefste Position gefahren. Dabei wird der konzentrische Spalt zwischen Formkern 1 und Formmantel 2 nach unten hin dicht verschlossen. Darauf wird dem Formkern 1 ein Schachtboden aus Kunststoff oder ein anderes selbsttragendes Einbauelement aufgesetzt, Beton aufgefüllt und verdichtet.At the start of production, the lifting device 3 is moved to its lowest position with a lower sleeve. The concentric gap between the mold core 1 and the mold jacket 2 is tightly sealed at the bottom. On top of the mold core 1, a manhole base made of plastic or another self-supporting built-in element is placed, concrete is filled up and compacted.
Schließlich fährt die Preßglocke 4 abwärts, taucht in den Formmantel 2 ein (Fig. 2) und glättet den Schachtboden. Danach wird die Untermuffe 5 und mit ihr das frisch geschüttete Schachtunterteil durch die Hubeinrichtung 3 aus der Form gehoben und somit entschalt. Es läßt sich abtransportieren; ein neuer Produktionszyklus kann beginnen.Finally, the press bell 4 moves downwards, dips into the molded casing 2 ( FIG. 2) and smoothes the shaft floor. Then the lower sleeve 5 and with it the freshly poured manhole base are lifted out of the mold by the lifting device 3 and thus released. It can be removed; a new production cycle can begin.
Die im folgenden beschriebene Erfindung stellt ein Verfahren zur Fertigung von Schachtunterteilen vor, bei dem der Formkern ansteigt und variabel eingerichtet werden kann. Dadurch lassen sich Schachtunterteile mit unterschiedlicher Nutzhöhe herstellen.The invention described below presents a method for manufacturing manhole bases, at which the mold core rises and can be set up variably. This allows manhole bases to be used produce different usable heights.
Dies geschieht unter Zuhilfenahme von selbsttragenden Schachtböden oder von Einlegeelementen, die nach der Fertigung als verlorene Schalung im Schachtunterteil verbleiben. Die Schachtböden besitzen integrierte Gerinne mit Muffen für Rohranschlüsse. Mit solchen Böden gefertigte Schächte sind dem jeweiligen Anwendungsfall genau angepaßt und nach der Fertigung sowie Aushärtung sofort einsetzbar.This is done with the help of self-supporting shaft floors or insert elements that follow of production remain as lost formwork in the lower part of the manhole. The shaft floors have integrated Channel with sleeves for pipe connections. Shafts made with such floors are appropriate for each Application precisely adapted and can be used immediately after production and curing.
Schachtunterteile mit Einlegeböden sind Rohlinge und als solche nur nutzbar, wenn bei der Fertigung Muffen bzw. Dichtungen für Rohranschlüsse mit eingerüttelt werden. Dies sieht das Verfahren mit vor.Manhole bases with shelves are blanks and can only be used as such when they are being manufactured Sleeves or seals for pipe connections must also be shaken in. This is part of the procedure.
Fig. 3 läßt sich entnehmen, daß der Kern 1 mit einem Rüttelring 2 versehen ist. Mit diesem Rüttelring 2 nimmt er die Untermuffe (3) auf, bekommt einen Schachtboden 4 oder Einlegeelement aufgelegt und fährt aufwärts in eine festgelegte Position. Parallel oder zeitlich versetzt fährt der Formmantel 5 abwärts, zentriert sich mit dem Kern 1 und wird auf der Bodenplatte 6 abgestellt. Fig. 3 shows that the core 1 is provided with a vibrating ring 2 . With this vibrating ring 2 , he picks up the lower sleeve ( 3 ), receives a shaft base 4 or insert element and moves upwards into a fixed position. In parallel or at different times, the shaped jacket 5 moves downwards, centers with the core 1 and is placed on the base plate 6 .
Hierauf geht der Beschicker, mit dem Beschickungswagen 8 und Verteiler 9 in Funktion. Der Beschickungs wagen 8 fährt vor bis der Verteiler 9 achsgleich über der Formeinrichtung steht und gibt ihr gleichmäßig Beton auf - was der Verteiler 9 bewirkt.Then the feeder, with the loading trolley 8 and distributor 9 , functions. The loading trolley 8 moves forward until the distributor 9 is coaxially above the molding device and gives it concrete evenly - which the distributor 9 does.
Ist ausreichend Beton aufgefüllt, fährt der Beschickungswagen 8 zurück. Die Presse 10 bewegt sich abwärts, taucht in den Formmantel 2 ein und preßt und glättet den Boden des gerüttelten Schachtunterteils 11 oder Rohlings (Fig. 4). Darauf taucht der Kern 1 ab und läßt die Untermuffe mit dem gefertigten Schachtunterteil 11 bzw. Rohling auf der Bodenplatte 6 zurück. Ob Schachtunterteil oder Rohling, ein Abfahrwagen oder Stapler besorgt den Abtransport zum Stell- und Trockenplatz, ein neuer Zyklus kann beginnen.If sufficient concrete is filled in, the loading trolley 8 moves back. The press 10 moves downward, dips into the mold jacket 2 and presses and smoothes the bottom of the vibrated manhole base 11 or blank ( Fig. 4). Then the core 1 dips and leaves the lower sleeve with the manhole base 11 or blank made on the base plate 6 . Whether the lower part of the manhole or the blank, a moving cart or a forklift takes care of the removal to the parking and drying area, a new cycle can begin.
Die bei der Fertigung eingesetzten selbsttragenden Schachtböden 4 bzw. Einlegeelemente ragen zwar in den konzentrischen Spalt zwischen Kern 1 und Formmantel 5 lassen aber mindestens 70% dieses Spalts frei. Dadurch ist gewährleistet, daß sich der Spalt mit Beton auffüllt und auch die Einbauten den auf ihnen lastenden Beton tragen.The self-supporting shaft floors 4 or insert elements used in the production project into the concentric gap between the core 1 and the shaped jacket 5 , but leave at least 70% of this gap free. This ensures that the gap fills up with concrete and that the internals also carry the concrete on them.
Die Erfindung sieht alternativ mit vor, die tragende Funktion des auf dem Kern 1 aufgezogenen Rüttel ringes 2 einer Hubeinrichtung 12 zu übertragen (Fig. 3), sonst aber am bereits beschriebenen Verfahrensablauf festzuhalten.The invention provides, alternatively, with before, the supporting function of the tires fitted to the core 1 vibrating ring 2 to transfer a lifting device 12 (Fig. 3), but otherwise stick to the already described procedure.
Zudem kann das eingangs beschriebene Problem auch dadurch gelöst werden, daß die Untermuffe 3 auf der
Bodenplatte 6 abgestellt wird, der Kern 1 hindurchfährt, den Schachtboden 4 oder das Einlegeelement
aufgesetzt bekommt, sich dann die Nutzhöhe sucht und dort verharrt, bis die Fertigung des
Schachtunterteiles abgeschlossen ist. Dies hat jedoch folgende Nachteile:
In addition, the problem described at the outset can also be solved by placing the lower sleeve 3 on the base plate 6, driving the core 1 through it, placing the shaft bottom 4 or the insert element on it, then searching for the useful height and remaining there until the production of the shaft lower part is completed. However, this has the following disadvantages:
- a) Es müssen entweder verschieden hohe Formmäntel 5 zum Einsatz gelangen und der Beschicker 8 in der Höhe verstellbar angeordnet werden odera) Either mold shells 5 of different heights must be used and the feeder 8 must be adjustable in height or
- b) es muß ein Verteiler 9 zum Einsatz gelangen, der unterschiedlich tief in den Formmantel eintaucht und zudem noch Unterstützung durch eine Teleskoppresse erhält.b) a distributor 9 must be used, which dips into the molded jacket to different depths and also receives support from a telescopic press.
Beide Varianten sind technisch aufwendig, werden aber nicht ausgeschlossen. Both variants are technically complex, but are not excluded.
11
Formkern
Mold core
22nd
Formmantel
Molded jacket
33rd
Hubeinrichtung
Lifting device
44th
Preßglocke
Press bell
55
Untermuffe
Subframe
11
Formkern
Mold core
22nd
Rüttelring
Vibrating ring
33rd
Untermuffe
Subframe
44th
Schachtboden
Manhole bottom
55
Formmantel
Molded jacket
66
Bodenplatte
Base plate
77
Arbeitsbühne
Working platform
88th
Beschickerwagen
Loading trolley
99
Verteiler
Distributor
1010th
Preßkopf
Press head
1111
Schachtunterteil
Manhole base
1212th
Hubeinrichtung
Lifting device
Claims (8)
Das Verfahren umfaßt die Schritte:
- a) Aufnehmen einer Untermuffe (3) durch den Kern (1) oder mit einer Hubeinrichtung (12)
- b) Auflegen eines Schachtbodens (4) oder eines Einlegeelementes auf den Kern (1)
- c) Fahren der Untermuffe (3) und des Schachtbodens (4) oder des Einlegeelementes in eine der vorgegebenen Nutzhöhe entsprechende Höhenposition
- d) Abstellen des Formmantels (5) auf der Bodenplatte (6) bei gleichzeitiger Zentrierung und Herstellung eines exakt konzentrischen Spaltes zwischen Kern (1) und Formmantel (5)
- e) Beschickung der Formeinrichtung mit Beton bei gleichmäßiger Verteilung des selben mit dem Verteiler (9) des Beschickers
- f) Verdichten des eingefüllten Betons durch formbedingte Vibration - kernseitig oder mantelseitig
- g) Fahren des Beschickerwagens (8) mit dem Verteiler (9) zurück in die Ausgangsposition
- h) Pressen und Glätten des Schachtbodens mit der Presse (10)
- i) Entschalen und Abfahren des Schachtunterteiles (11) oder Rohlings zur Stellfläche.
The process comprises the steps:
- a) receiving a lower sleeve ( 3 ) through the core ( 1 ) or with a lifting device ( 12 )
- b) placing a shaft floor ( 4 ) or an insert element on the core ( 1 )
- c) driving the lower sleeve ( 3 ) and the shaft bottom ( 4 ) or the insert element into a height position corresponding to the predetermined usable height
- d) placing the shaped jacket ( 5 ) on the base plate ( 6 ) while simultaneously centering and producing an exactly concentric gap between the core ( 1 ) and the shaped jacket ( 5 )
- e) loading the molding device with concrete with uniform distribution of the same with the distributor ( 9 ) of the feeder
- f) Compacting the filled concrete by shape-related vibration - core or shell side
- g) driving the feeder wagon ( 8 ) with the distributor ( 9 ) back to the starting position
- h) Pressing and smoothing the shaft bottom with the press ( 10 )
- i) Demoulding and lowering the manhole base ( 11 ) or blank to the footprint.
Der Ablauf dabei ist folgender:
- a) Auflegen der Untermuffe (3) auf der Schachtplatte (6)
- b) Fahren des Kernes (1) durch die Untermuffe (3) aufwärts
- c) Auflegen des Schachtbodens (4) oder Einlegeelementes auf den Kern (1)
- d) Abstellen des Formmantels (5) auf der Bodenplatte (6) unter Beachtung ihrer Zentrierung entsprechend Anspruch 1
- e) Schwenken eines außerhalb angeordneten Verteilers (9) über den Formmantel (5)
- f) Absenken des Verteilers (9) in den Formmantel (5)
- g) Beschicken der Formeinrichtung mit Beton, Verdichten und Verteilen des Betons
- h) Fahren des Verteilers (9) aus dem Formmantel (5) zurück in seine Ausgangsposition
- i) Abfahren der Presse (10) hinein in die Form
- j) Pressen und Glätten des Schachtbodens
- k) Auseinanderfahren der Formeinrichtung, Entschalen und Abfahren des Schachtunterteiles (11) oder Rohlings zur Stellfläche.
The process is as follows:
- a) Place the lower sleeve ( 3 ) on the shaft plate ( 6 )
- b) driving the core ( 1 ) up through the lower sleeve ( 3 )
- c) placing the shaft bottom ( 4 ) or insert element on the core ( 1 )
- d) placing the shaped jacket ( 5 ) on the base plate ( 6 ), taking into account their centering in accordance with claim 1
- e) swiveling a distributor ( 9 ) arranged outside over the shaped jacket ( 5 )
- f) lowering the distributor ( 9 ) into the molded jacket ( 5 )
- g) loading the molding device with concrete, compacting and distributing the concrete
- h) moving the distributor ( 9 ) out of the molded jacket ( 5 ) back to its starting position
- i) moving the press ( 10 ) into the mold
- j) pressing and smoothing the shaft floor
- k) Moving the molding device apart, demoulding and moving the lower shaft part ( 11 ) or blank to the footprint.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998158934 DE19858934A1 (en) | 1998-12-08 | 1998-12-08 | Concrete shaft under part production process |
PCT/EP1999/009761 WO2000034018A1 (en) | 1998-12-08 | 1999-12-07 | Method and device for producing concrete shaft blanks |
AU18641/00A AU1864100A (en) | 1998-12-08 | 1999-12-07 | Method and device for producing concrete shaft blanks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998158934 DE19858934A1 (en) | 1998-12-08 | 1998-12-08 | Concrete shaft under part production process |
Publications (1)
Publication Number | Publication Date |
---|---|
DE19858934A1 true DE19858934A1 (en) | 1999-07-29 |
Family
ID=7891890
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1998158934 Withdrawn DE19858934A1 (en) | 1998-12-08 | 1998-12-08 | Concrete shaft under part production process |
Country Status (3)
Country | Link |
---|---|
AU (1) | AU1864100A (en) |
DE (1) | DE19858934A1 (en) |
WO (1) | WO2000034018A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2003086723A1 (en) * | 2002-04-12 | 2003-10-23 | Wagener & Polascheck Vertriebsgesellschaft Mbh & Co. Kg | Method for manufacturing a shaft bottom part with lateral exits |
CN101508144B (en) * | 2009-03-02 | 2011-03-23 | 深圳港创建材股份有限公司 | Concrete casting production technique with energy-saving environmental-protection function |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU514036B2 (en) * | 1977-03-29 | 1981-01-22 | Castings & Forgings Pty. Ltd. | Concrete Sewer manhole |
DE3805550C2 (en) * | 1988-02-23 | 1998-08-06 | Prinzing Georg Gmbh Co Kg | Process and device for the production of concrete parts |
JPH045906U (en) * | 1990-04-27 | 1992-01-20 | ||
DE4209395A1 (en) * | 1992-03-23 | 1993-09-30 | Baumgaertner Maschf Gmbh | Molding device for the production of concrete pipes |
DE4342518A1 (en) * | 1993-12-13 | 1995-06-14 | Baumgaertner Maschf Gmbh | Mechanism to manufacture concrete shaft end parts |
DE4418370A1 (en) * | 1994-05-26 | 1995-11-30 | Raiss Gmbh & Co Kg E | System for manufacturing concrete drain components |
-
1998
- 1998-12-08 DE DE1998158934 patent/DE19858934A1/en not_active Withdrawn
-
1999
- 1999-12-07 WO PCT/EP1999/009761 patent/WO2000034018A1/en active Application Filing
- 1999-12-07 AU AU18641/00A patent/AU1864100A/en not_active Abandoned
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2003086723A1 (en) * | 2002-04-12 | 2003-10-23 | Wagener & Polascheck Vertriebsgesellschaft Mbh & Co. Kg | Method for manufacturing a shaft bottom part with lateral exits |
CN101508144B (en) * | 2009-03-02 | 2011-03-23 | 深圳港创建材股份有限公司 | Concrete casting production technique with energy-saving environmental-protection function |
Also Published As
Publication number | Publication date |
---|---|
WO2000034018A1 (en) | 2000-06-15 |
AU1864100A (en) | 2000-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0649715A1 (en) | Device for making annular or tubular articles from concrete | |
EP3597385B1 (en) | Mould for concrete blocks with (large) level differences, such as kerbstones/blocks/lock stones with or without cavities/drain | |
DE19858934A1 (en) | Concrete shaft under part production process | |
CN206066652U (en) | A kind of precast concrete automatic forming device | |
DE60213425T2 (en) | IN PARTICULAR FOR THE MANUFACTURE OF ELECTRODE CERTAIN CASTING SYSTEM AND METHOD USED IN SUCH AN APPENDIX | |
DE19912829B4 (en) | Plant for the production of cup-shaped concrete bodies | |
DE3719700C2 (en) | ||
DE19924926C1 (en) | Stone forming machine for masonry stones has upper and lower mould sections with guide for lower section | |
EP0175038A1 (en) | Method of making building blocks with at least one cavity and apparatus for carrying out this method | |
AT410295B (en) | Method for casting concrete bowl-shaped bodies for shaft base | |
DE2830479A1 (en) | Concrete mould filling process - lowers component initially shutting off mould flush with top during filling | |
DE3515986C2 (en) | Method for producing a concrete part serving as a manhole base or shaft bottom and device for carrying out the method | |
DE69929138T2 (en) | Multifunctional plant for the production of prefabricated concrete objects | |
DE826721C (en) | Method and device for manufacturing components | |
JPH06134740A (en) | Instant demolding automatic forming machine of large-sized concrete product and forming method therewith | |
CN221291743U (en) | Double-layer heat-insulating brick mold | |
DE2804754C2 (en) | Process for the production of molded bodies from concrete | |
DE19621161A1 (en) | Manufacture of concrete blocks with at least one cavity | |
EP0476245B1 (en) | Process for making concrete products | |
AT403447B (en) | Method and apparatus for the production of manhole lower parts | |
EP0568490B1 (en) | Process and apparatus for making an article from ceramic material | |
HU200811B (en) | Method and apparatus for making intercepting channel | |
AT409471B (en) | Method for casting concrete bowl-shaped bodies for shaft base | |
DE19805067B4 (en) | Process for producing concrete parts | |
AT206345B (en) | Method and device for the production of roof tiles, building panels or the like from concrete |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OAV | Applicant agreed to the publication of the unexamined application as to paragraph 31 lit. 2 z1 | ||
8122 | Nonbinding interest in granting licenses declared | ||
8127 | New person/name/address of the applicant |
Owner name: AUMUELLER GMBH & CO. BETONWERK KG, 14822 LINTHE, D |
|
8139 | Disposal/non-payment of the annual fee |