DE19826989C2 - U- or H-shaped segment of a hydraulic structure - Google Patents
U- or H-shaped segment of a hydraulic structureInfo
- Publication number
- DE19826989C2 DE19826989C2 DE1998126989 DE19826989A DE19826989C2 DE 19826989 C2 DE19826989 C2 DE 19826989C2 DE 1998126989 DE1998126989 DE 1998126989 DE 19826989 A DE19826989 A DE 19826989A DE 19826989 C2 DE19826989 C2 DE 19826989C2
- Authority
- DE
- Germany
- Prior art keywords
- segment
- base
- lines
- segments
- open
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000011010 flushing procedure Methods 0.000 claims description 5
- 210000002414 leg Anatomy 0.000 claims 4
- 108090000623 proteins and genes Proteins 0.000 claims 1
- 210000000689 upper leg Anatomy 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 238000010276 construction Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 239000004575 stone Substances 0.000 description 3
- 241001080526 Vertica Species 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 210000004072 lung Anatomy 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Description
Die Erfindung betrifft ein Segment eines Wasserbauwerks. Aus erfindungsgemäßen Segmenten lassen sich Bauwerke des Wasser baus wie Molen, Kais, Piers, Dämme, Anlegestege, Wellenbre cher, Buhnen usw. errichten.The invention relates to a segment of a hydraulic structure. Out segments of the invention can be buildings of water Build like jetties, quays, piers, dams, jetties, waves erect groynes, groynes, etc.
Küsten- und Uferbereiche von Meeren, Seen und Flüssen sind der Kraft der Wasser- und Wellenbewegung ausgesetzt. Infolge der erodierenden Kraft des Wassers sind diese Bereiche einer ständigen Veränderung unterworfen. Für weite Teile der Kü sten- und Uferbereiche ist es aus ökologischen Aspekten geboten, die natürlichen Veränderungen in diesen Zonen hinzu nehmen. Daneben gibt es Küsten- und Uferbereiche, an denen Küsten-, Ufer- und Hochwasserschutz- sowie Infrastrukturbau werke zu errichten sind, die eine der ständigen Belastung entsprechende Stabilität und Lebensdauer haben müssen.Coastal and bank areas of seas, lakes and rivers are exposed to the force of water and waves. As a result These areas are one of the eroding power of water subject to constant change. For large parts of the kitchen Most areas and banks are from ecological aspects commanded to add the natural changes in these zones to take. There are also coastal and bank areas on which Coastal, bank and flood protection as well as infrastructure construction works to be erected which are one of the constant stress must have appropriate stability and lifespan.
Küsten-, Ufer-, Hochwasserschutz- und Infrastrukturbauwerke werden in zum Teil seit Jahrhunderten bewährter Weise errich tet.Coastal, bank, flood protection and infrastructure structures are built in ways that have been tried and tested for centuries tet.
So wird der Dammkörper einer Buhne entweder aus einer Stein schüttung oder in der Form einer Spundwand, Pfahlreihe oder mit Hilfe von Faschinen errichtet. The dam body of a groyne is either made of a stone fill or in the form of a sheet pile, row of piles or built with the help of machines.
Pier- und Kaianlagen, die dem Be- und Entladen von Schiffen oder als Wellenbrecher zum Schutz eines Hafens dienen, werden bautechnisch durch Spundwände, Pfahlroste oder Schwerge wichtsbauwerke ausgeführt.Pier and quay facilities for loading and unloading ships or serve as a breakwater to protect a port in terms of construction through sheet piling, pile gratings or heavy racks weight structures executed.
Die Art der Errichtung dieser Bauwerke und die verwendeten Materialien haben sich bewährt und zeigen hinsichtlich der Belastbarkeit und der Lebensdauer gute Ergebnisse. Von Nach teil ist aber der hohe technische Aufwand und der hohe Mate rialeinsatz, der mit der Errichtung dieser Bauwerke verbunden ist. Das Errichten von Spundwänden, Pfahlreihen, Pfahlrosten und der Einsatz von Faschinen erfordert, da eine Vielzahl von Elementen einzeln in den Untergrund eingebracht und miteinan der zu verbinden sind, einen hohen Aufwand, der sich in entsprechenden Kosten niederschlägt. Einen ähnlich hohen Aufwand erfordern Steinschüttungen, wobei hier der wegen des zu beachtenden und einzuhaltenden Böschungswinkels erforder liche Material- und Platzbedarf besonders ins Gewicht fällt.The type of construction of these structures and the ones used Materials have proven themselves and show in terms of Resilience and durability good results. From to part is the high technical effort and the high mate rial deployment associated with the construction of these structures is. The erection of sheet piling, pile rows, pile gratings and the use of machinery requires a variety of Elements individually brought into the underground and together which are to be connected, a great deal of effort which can be found in corresponding costs. A similarly high one Effort requires stone fillings, but here because of the slope angle to be observed and observed material and space requirements are particularly important.
Es sind schon U- oder H-förmige Segmente für Wasserbauwerke vorgeschlagen worden (DE-OS 44 03 204 A1; DE-OS 36 24 009 A1; DE-OS 35 00 560 A1; DE-OS 27 00 415 A1; DE-PS 952 787), die eine rechteckige, horizontale Basis und zwei vertikale Schen kel an den gegenüberliegenden Seiten der horizontalen Basis bestehen. Aus diesen Segmenten werden größere Wasserbauwerke zusammengesetzt. Von Nachteil ist, daß diese Segmente im Unterwasserbereich nur mit hohem Aufwand exakt positioniert und zueinander ausgerichtet werden können.They are already U or H-shaped segments for hydraulic structures have been proposed (DE-OS 44 03 204 A1; DE-OS 36 24 009 A1; DE-OS 35 00 560 A1; DE-OS 27 00 415 A1; DE-PS 952 787), the a rectangular, horizontal base and two vertical legs on the opposite sides of the horizontal base consist. These segments become larger hydraulic structures composed. The disadvantage is that these segments in Exactly positioned underwater area only with great effort and can be aligned with each other.
Aufgabe der Erfindung ist es daher, ein Segment für Bauwerke des Wasserbaus vorzuschlagen, daß einfach herzustellen, zu transportieren, zu verlegen und zu einer größeren Einheit zu verbinden ist. The object of the invention is therefore a segment for buildings of hydraulic engineering to propose that easy to manufacture, too transport, relocate and become a larger unit connect is.
Gelöst wird diese Aufgabe durch ein Segment nach Anspruch 1. Zweckmäßige Ausgestaltungen der Erfindung sind in den Un teransprüchen angegeben.This problem is solved by a segment according to claim 1. Appropriate embodiments of the invention are in the Un claims specified.
Nachfolgend wird die Erfindung anhand von Ausführungsbeispie len erläutert.The invention is described below with reference to exemplary embodiments len explained.
Es zeigen:Show it:
Fig. 1 ein erfindungsgemäßes Segment in perspek tivischer Darstellung, Fig. 1 shows an inventive segment in perspec TiVi shear representation,
Fig. 2 das Segment nach Fig. 1 im Schnitt Fig. 2 shows the segment of Fig. 1 in section
Fig. 3 eine Variante des erfindungsgemäßen Segmentes in perspektivischer Darstel lung, Figure 3 shows a variant of the segment according to the invention lung. Depicting in perspective,
Fig. 4 das Segment nach Fig. 3 im Schnitt, Fig. 4 shows the segment of FIG. 3 in section,
Fig. 5 ein aus mehreren Segmenten gebildetes Bauwerk, Fig. 5 is a formed from a plurality of segments building,
Fig. 6 ein Segment, kombiniert mit weiteren Bauelementen, Fig. 6 is a segment, combined with further components,
Fig. 7 mit Hilfe von Verbindungselementen gefüg te Segmente. Fig. 7 with the help of joining elements te segments.
Das in den Fig. 1 und 2 dargestellte erfindungsgemäße Segment 1 besteht aus einer rechteckigen, horizontalen Basis 2 und zwei vertikalen Schenkeln 3 an den beiden gegenüberlie genden Seiten der Basis 2. Die Basis 2 und die Schenkel 3 bilden gemeinsam einen U-förmigen Querschnitt. Die vertikalen Schenkel 3 sind über die Länge verteilt von rohrförmigen Spülleitungen 4 durchdrungen, die an den Unterseiten der Schenkel 3 münden. Die horizontale Basis 2 ist mit Durchbrü chen 5 versehen.The segment 1 according to the invention shown in FIGS . 1 and 2 consists of a rectangular, horizontal base 2 and two vertical legs 3 on the two opposite sides of the base 2nd The base 2 and the legs 3 together form a U-shaped cross section. The vertical legs 3 are penetrated over the length by tubular flushing lines 4 which open on the undersides of the legs 3 . The horizontal base 2 is provided with openings 5 .
Die Spülleitungen 4 können über eine Leitung 6, die innerhalb des Schenkels 3 angeordnet ist, miteinander verbunden sein und/oder sich in Leitungen 7 verzweigen. Die Zweigleitungen 7 münden an der Unterseite der Schenkel 3, wobei einzelne Zweigleitungen 7 in die Basis 2 führen und an deren Untersei te münden können.The flushing lines 4 can be connected to one another via a line 6 , which is arranged inside the leg 3 , and / or can branch into lines 7 . The branch lines 7 open on the underside of the legs 3 , wherein individual branch lines 7 lead into the base 2 and can open at the underside thereof.
Das in den Fig. 3 und 4 dargestellte erfindungsgemäße Segment 1 besteht aus einer rechteckigen, horizontalen Basis 2 und zwei vertikalen Schenkeln 3 an den beiden gegenüberlie genden Seiten der Basis 2. Die Basis 2 und die Schenkel 3 bilden gemeinsam einen H-förmigen Querschnitt. Die vertikalen Schenkel 3 sind über die Länge verteilt von rohrförmigen Spülleitungen 4 durchdrungen, die an der Unterseite des Schenkels 3 münden. Die horizontale Basis 2 ist mit Durchbrü chen 5 versehen.The segment 1 according to the invention shown in FIGS . 3 and 4 consists of a rectangular, horizontal base 2 and two vertical legs 3 on the two opposite sides of the base 2nd The base 2 and the legs 3 together form an H-shaped cross section. The vertical legs 3 are penetrated over the length by tubular flushing lines 4 , which open at the bottom of the leg 3 . The horizontal base 2 is provided with openings 5 .
Die Spülleitungen 4 können über eine Leitung 6 miteinander verbunden sein und/oder sich in Leitungen 7 verzweigen. Die Zweigleitungen 7 münden an den Unterseiten der Schenkel 3, wobei einzelne Zweigleitungen 7 in die Basis 2 führen und an deren Unterseite münden können.The flushing lines 4 can be connected to one another via a line 6 and / or branch into lines 7 . The branch lines 7 open on the undersides of the legs 3 , wherein individual branch lines 7 lead into the base 2 and can open on the underside thereof.
Das erfindungsgemäße Segment 1 gemäß der Fig. 1 bis 4 ist geeignet, mit weiteren Segmenten 1 auf dem Grund oder am Ufer von Gewässern mit einem Untergrund aus Schlick, Sand, Mud oder Mergel zu größeren Einheiten, wie etwa Molen, Kais, Piers, Dämmen, Anlegestegen, Wellenbrechern und Buhnen, zusammengesetzt zu werden. Zu diesem Zweck wird ein Segment 1 an der Baustelle auf dem Grund aufgesetzt. Von einer Spülsta tion wird Wasser in die Spülleitungen 4 geleitet, durch die der Untergrund im erforderlichen Maße aufgespült wird, bis das Segment die vorgesehene Lage erreicht hat. Um das Absen ken des Segmentes 1 in den Grund steuert zu können, kann die Spülwasserzufuhr zu jeder der Spülleitungen 4 einzeln gere gelt und verändert werden. Die Durchbrüche 5 in der vertika len Basis 2 gewährleisten einen gleichmäßigen Abfluß des Spülgutes.The segment 1 according to the invention according to FIGS. 1 to 4 is suitable, with further segments 1 on the bottom or on the bank of waters with a subsoil of silt, sand, mud or marl to larger units, such as jetties, quays, piers, dams , Jetties, breakwaters and groynes to be put together. For this purpose, a segment 1 is placed on the construction site on the ground. From a rinsing station water is passed into the rinsing lines 4 through which the subsurface is rinsed to the required extent until the segment has reached the intended position. In order to be able to control the lowering of the segment 1 into the ground, the rinse water supply to each of the rinse lines 4 can be regulated and changed individually. The openings 5 in the vertica len base 2 ensure a uniform drain of the wash ware.
Neben dem verlegten Segment 1 kann eine beliebige Anzahl weiterer Segmente 1 (Fig. 5) verlegt werden, bis das zu errichtende Bauwerk vollendet ist.In addition to the installed segment 1 , any number of additional segments 1 ( FIG. 5) can be installed until the building to be erected is completed.
Das erfindungsgemäße Segment 1 gemäß Fig. 1 und 2 ist beson ders für den Einsatz im flachen Wasser (bis zu einer Wasser tiefe von etwa 3 m) geeignet.The segment 1 according to FIGS . 1 and 2 is particularly suitable for use in shallow water (up to a water depth of about 3 m).
Das erfindungsgemäße Segment 1 gemäß der Fig. 3 und 4 ist besonders für den Einsatz in einem festeren Untergrund geeig net, da die über die Basis 2 hinaus verlängerten vertikalen Schenkel 3 besser in den Untergrund eindringen können als die Basis 2.The segment 1 according to the invention according to FIGS. 3 and 4 is particularly suitable for use in a firmer ground, since the vertical legs 3 , which are extended beyond the base 2 , can penetrate better into the ground than the base 2 .
Der über der Basis 2 befindliche U-förmige Raum kann nach dem Absenken der Segmente 1 mit Steinen o. ä. gefüllt werden. Auf den verlegten Segmenten können in Abhängigkeit von der beab sichtigten Nutzung des Bauwerkes weitere Bauelemente angeord net sein, wie Fahrbahnen, Gehwege, Geländer, Gleiskörper, Poller, Beleuchtungskörper, Wasser- und Stromleitungen (Fig. 6).The U-shaped space located above the base 2 can be filled with stones or the like after the segments 1 have been lowered. Depending on the intended use of the building, other components can be arranged on the installed segments, such as roadways, walkways, railings, track bodies, bollards, lighting fixtures, water and power lines ( FIG. 6).
Die erfindungsgemäßen Segmente können in Abhängigkeit vom Verwendungszweck in verschiedenen Größen aus Beton herge stellt werden. Die Segmente 1 können mit Verbindungselementen 8 und 9 versehen sein, die das Zusammenfügen der Segmente 1 zu einer größeren Einheit und die Stabilität der Verbindung günstiger gestalten. Fig. 7 zeigt die Draufsicht auf ein Bauwerk, das aus mit Verbindungselementen 8 und 9 ausgestatte ten Segmenten 1 errichtet ist. The segments of the invention can be made of concrete in various sizes depending on the intended use. The segments 1 can be provided with connecting elements 8 and 9 , which make the joining together of the segments 1 into a larger unit and the stability of the connection more favorable. Fig. 7 shows the top view of a building that is constructed from connecting elements 8 and 9 with th segments 1 .
11
Segment
segment
22nd
horizontale Basis
horizontal base
33rd
vertikaler Schenkel
vertical leg
44
Spülleitung
Flush line
55
Durchbruch
breakthrough
66
Verbindungsleitung
Connecting line
77
Zweigleitung
Branch line
88th
Verbindungselement
Fastener
99
Verbindungselement
Fastener
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998126989 DE19826989C2 (en) | 1998-06-18 | 1998-06-18 | U- or H-shaped segment of a hydraulic structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1998126989 DE19826989C2 (en) | 1998-06-18 | 1998-06-18 | U- or H-shaped segment of a hydraulic structure |
Publications (2)
Publication Number | Publication Date |
---|---|
DE19826989A1 DE19826989A1 (en) | 2000-02-10 |
DE19826989C2 true DE19826989C2 (en) | 2001-03-22 |
Family
ID=7871163
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1998126989 Expired - Fee Related DE19826989C2 (en) | 1998-06-18 | 1998-06-18 | U- or H-shaped segment of a hydraulic structure |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE19826989C2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2460342B (en) * | 2008-05-30 | 2012-06-27 | Biomedy Ltd | Construction of tidal wall |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE952787C (en) * | 1955-03-17 | 1956-11-22 | Arno Schmakowski | Process for the production of a dike from lowerable concrete floating boxes |
DE2700415A1 (en) * | 1977-01-07 | 1978-07-13 | Louis Pohl | Prefabricated concrete caisson for making dams - has parallel separated bodies filled with sand and stones for anchoring |
DE3500560A1 (en) * | 1985-01-10 | 1985-07-04 | Klaus 7527 Kraichtal Fichtner | Hose for protecting against oil, chemicals and high water |
DE3624009A1 (en) * | 1986-07-16 | 1988-01-28 | Hupfeld Beton Gmbh & Co | Coastal protection element |
DE4403204A1 (en) * | 1994-02-03 | 1995-08-10 | Heinrich Lahme | Interlocking constructional beam providing protection against water |
-
1998
- 1998-06-18 DE DE1998126989 patent/DE19826989C2/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE952787C (en) * | 1955-03-17 | 1956-11-22 | Arno Schmakowski | Process for the production of a dike from lowerable concrete floating boxes |
DE2700415A1 (en) * | 1977-01-07 | 1978-07-13 | Louis Pohl | Prefabricated concrete caisson for making dams - has parallel separated bodies filled with sand and stones for anchoring |
DE3500560A1 (en) * | 1985-01-10 | 1985-07-04 | Klaus 7527 Kraichtal Fichtner | Hose for protecting against oil, chemicals and high water |
DE3624009A1 (en) * | 1986-07-16 | 1988-01-28 | Hupfeld Beton Gmbh & Co | Coastal protection element |
DE4403204A1 (en) * | 1994-02-03 | 1995-08-10 | Heinrich Lahme | Interlocking constructional beam providing protection against water |
Also Published As
Publication number | Publication date |
---|---|
DE19826989A1 (en) | 2000-02-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5087150A (en) | Method of constructing a seawall reinforcement or jetty structure | |
DE2628618C3 (en) | Process for building a quay wall in the water and structural element for carrying out the process | |
WO2009129809A2 (en) | Device and method for flood protection, coastal protection and scour protection | |
DE3936705A1 (en) | MODULAR WALL CONSTRUCTION FROM POST AND PANELS | |
DE69032103T2 (en) | CELLULAR STRUCTURES TO SUPPORT WALLS | |
DE2558404A1 (en) | DEVICE FOR PROTECTING THE FOOT OF A STRUCTURE RISING OR ERECTING ON THE GROUND OF A WATER SURFACE AGAINST WATER FLOOD | |
US3465530A (en) | Dam construction | |
DE2062477A1 (en) | Method and device for protecting and / or stabilizing inclined surfaces | |
DE19826989C2 (en) | U- or H-shaped segment of a hydraulic structure | |
AT352639B (en) | SHORE SHORING | |
DE2439576A1 (en) | DRILL RIG | |
DE1634589B2 (en) | PILE GRATING MADE FROM CONCRETE PILES | |
EP1707685A2 (en) | Foundation for a high water barrier | |
DE1958814B1 (en) | Construction element made of concrete and wall made therefrom, in particular quay wall, pier or the like. | |
DE4021220A1 (en) | Erosion protection measures and installation procedure - involve double T=shaped interlocking concrete revetment blocks | |
DE2242358A1 (en) | EQUIPMENT FOR FASTENING GROUND AND EMBEDDING AND ARTIFICIAL MOLDED STONE FOR THEIR PRODUCTION | |
DE2317803A1 (en) | METHOD OF ESTABLISHING A FOUNDATION IN WATER | |
DE2647935C3 (en) | Harbor made up of individual floating pontoons that support each other | |
DE609289C (en) | Procedure for the installation of floating foundation bodies | |
DE10245303A1 (en) | Dyke structure to prevent flooding uses system of plates of solid and hollow body structure of different dimensions and different materials and filled with different fillers | |
DE632171C (en) | Groyne with a vault-like upper part and a pile substructure | |
DE1634589C3 (en) | Pile grid made of concrete piles | |
DE2614438A1 (en) | CONCRETE COMPONENT FOR CONSTRUCTION OF MOLES, QUARRY WALLS OR THE SAME AND METHOD OF MANUFACTURING THEM | |
DE610692C (en) | System for securing embankments and similar embankments in hydraulic structures | |
DE2348043C3 (en) | Component for securing slopes or the like |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OP8 | Request for examination as to paragraph 44 patent law | ||
D2 | Grant after examination | ||
8339 | Ceased/non-payment of the annual fee | ||
8370 | Indication of lapse of patent is to be deleted | ||
8364 | No opposition during term of opposition | ||
8339 | Ceased/non-payment of the annual fee |