Vynález se týká spoje stěnových panelů, zejména železobetonových, se spodní skeletovou konstrukcí, v němž jsou stěnové panely horní části budovy uloženy na přechodových stěnových prvcích.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the connection of wall panels, in particular of reinforced concrete, with a subframe structure in which the wall panels of the upper part of the building are supported on transition wall elements.
Jsou známy spoje stěnových panelů s přechodovými stavebními prvky, u nichž stěnové panely dosedají na okraje stropu po celé své délce a přechodové stavební prvky zase dosedají na nosník skeletové konstrukce po celé jeho délce a tudíž zatěžují tento nosník rovnoměrně po celé jeho délce.Connections of wall panels with transition building elements are known, in which the wall panels abut the edges of the ceiling along their entire length and the transition building elements in turn abut the skeletal beam over its entire length and thus load the beam evenly over its entire length.
Pro takový spoj panelů se stavebními dílci skeletu musí být nosník dimenzován jako nosník rovnoměrně zatížený po celé své délce. To ovšem znamená značnou spotřebu materiálu, práce, vysoké dopravní a montážní náklady. Nevýhoda tohoto uspořádání je i v tom, že ve spárách vznikají značná napětí, čímž se snižuje počet podlaží panelové nástavby, které je možno usadit na spodní část skeletu.For such joints of panels with structural members of the skeleton, the beam must be dimensioned as a beam evenly loaded over its entire length. However, this means considerable material consumption, labor, high transport and assembly costs. A disadvantage of this arrangement is that considerable stresses are created in the joints, thereby reducing the number of storeys of the panel body that can be placed on the lower part of the skeleton.
Nedostatky známých konstrukcí jsou odstraněny vytvořením spoje stěnových panelů, zejména železobetonových panelů, se spodní skeletovou konstrukcí, v němž jsou stěnové panely horní části budovy uloženy v přechodových stavebních prvcích, jež se od známých provedení podle vynálezu odlišují tím, že stěnové panely jsou krajními částmi svých spodních ložných ploch uloženy na přechodových stavebních prvcích, tvořených nosníkem portálového tvaru, jehož plnostěnné koncové části jsou nahoře vzájemné spojeny horní příčlí, vytvořenou vcelku s plnostěnnými koncovými částmi, a dole jsou plnostěnné koncové části vzájemně spojeny táhlem, procházejícím dolním podélným vybráním mezi plnostěnnými koncovými částmi, omezeným shora horní příčlí, přičemž na horní ložné ploše přechodového stavebního prvku v její střední částí je vytvořeno horní podélné vybrání jako odlehčovací mezera mezi přechodovým stavebním prvkem a stěnovým panelem. Výhoda spoje stěnových panelů, zejména železobetonových, se spodní skeletovou konstrukcí, vytvořeného podle vynálezu, je zejména v tom, že lze optimálně vzájemně spojit dva na sobě nezávislé konstrukční systémy a to panelovou konstrukci se skeletovou konstrukcí, jejichž stavební prvky jsou sériově vyráběny, přiěemž podíl skeletové a panelové konstrukce není spojem nijak předurčen. Uplatnění spoje podle vynálezu přináší dále značné materiálové úspory. Příklad provedení spoje podle vynálezu je uveden na připojených výkresech, kde na obr. 1 je znázorněn svislý řez částí budovy a na obr. 2 je axonometrický pohled na stěnové panely, uložené na přechodových stavebních prvcích.The drawbacks of the known structures are eliminated by forming a joint of the wall panels, in particular of reinforced concrete panels, with a lower skeleton structure in which the wall panels of the upper part of the building are housed in transition elements which differ from the known embodiments of the invention in that the wall panels are the outermost parts of their the lower loading surfaces are supported on transition building elements formed by a girder-shaped beam, the full-length end portions of which are connected to each other by an upper beam formed integrally with the full-length end portions; an upper longitudinal recess is provided on the upper loading surface of the transition element in its central portion as a relief gap m limited by the upper upper rung at the top, between the building element and the wall panel. The advantage of joining wall panels, especially of reinforced concrete, with the lower frame structure according to the invention is, in particular, that two mutually independent structural systems can be connected to one another, namely a panel structure with a skeletal structure, the components of which are produced in series while skeletal and panel construction is not predetermined by the joint. The application of the joint according to the invention further brings considerable material savings. An exemplary embodiment of a joint according to the invention is shown in the accompanying drawings, wherein Fig. 1 is a vertical sectional view of a building and Fig. 2 is an axonometric view of wall panels mounted on transition elements.
Stěnové panely 1 panelové části budovy jsou spojeny s přechodovými stavebními prvky 3 na okrajových částech 2 svých ložných ploch. Ložné plochy stěnových panelů 1 v jejich okrajových částech 2, jakož i protilehlé plochy přechodových stavebních prvků 3 jsou opatřeny zazubením nebo jsou vytvořeny jako třecí plochy. Přechodový stavební prvek 3 je vytvořen jako portálový nosník o dvou plnostěnných koncových částech 4, jež jsou na své horní straně vzájemně spojeny horní příčlí 5, do níž nejsou vnášena žádná zatížení ze stěnových panelů I.The wall panels 1 of the panel part of the building are connected to the transition building elements 3 on the edge portions 2 of their loading surfaces. The bearing surfaces of the wall panels 1 in their edge portions 2 as well as the opposite surfaces of the transition building elements 3 are provided with a toothing or are formed as friction surfaces. The transition building element 3 is formed as a portal girder with two full-wall end portions 4, which at their upper side are connected to each other by an upper rung 5 into which no loads from the wall panels I are introduced.
Plnostěnné koncové části 4 přechodových stavebních prvků 3 jsou na své spodní straně vzájemně spojeny táhly β po celé délce svého dolního podélného vybrání, které je bočně omezeno plnostěnnými koncovými částmi 4 a shora horní příčlí 5. Na horní straně horní příčle 5 je vytvořeno horní podélné vybrání 11, které je případně vyplněno plastickou vložkou. Tím je znemožněn styk stěnového panelu 1 s přechodovým stavebním prvkem 3 v oblasti nad horním podélným vybráním 8 a tím i přenos svislých sil na horní příčlí 5, takže celá tíha stěnového panelu I se přenáší pouze jeho okrajovými částmi 2, jež jsou nad plnostěnnými koncovými částmi 4 přechodového stavebního prvku 3, Plnostěnné koncové části 4 jsou spodní stranou opřeny o svislé nosné prvky nosného skeletu spodní části budovy. Přechodové stavební prvky 3 se vzájemně spojují do řad, uložených na svislých nosných prvcích skeletu pomocí spojovacích ok 3, zalitých do vnějších stran přechodových stavebních prvků 3.The solid-wall end portions 4 of the transition building elements 3 are connected to each other on their underside by rods β along the entire length of their lower longitudinal recess, which is laterally limited by the full-length end portions 4 and from the top to the top 5. 11, which is optionally filled with a plastic insert. Thereby, the wall panel 1 is prevented from contacting the transition element 3 in the area above the upper longitudinal recess 8, thereby transferring the vertical forces to the upper rung 5, so that the entire weight of the wall panel I is transmitted only by its edge portions 2 which are above the full end portions. 4 of the intermediate building element 3, the full-wall end portions 4 are supported by the underside of the supporting structure of the supporting structure of the lower part of the building. The transition building elements 3 are connected to each other in rows mounted on vertical skeletal support elements by means of connecting eyes 3 embedded in the outer sides of the transition building elements 3.