CN221856152U
CN221856152U CN202420402892.7U CN202420402892U CN221856152U CN 221856152 U CN221856152 U CN 221856152U CN 202420402892 U CN202420402892 U CN 202420402892U CN 221856152 U CN221856152 U CN 221856152U
Authority
CN
China
Prior art keywords
wall
fixed
ropes
frame
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202420402892.7U
Other languages
Chinese (zh)
Inventor
侯学勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB Fifth Engineering Co Ltd
Original Assignee
CCCC SHB Fifth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB Fifth Engineering Co Ltd filed Critical CCCC SHB Fifth Engineering Co Ltd
Priority to CN202420402892.7U priority Critical patent/CN221856152U/en
Application granted granted Critical
Publication of CN221856152U publication Critical patent/CN221856152U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

本实用新型涉及建筑施工技术领域,具体为一种高层建筑外墙爬架和悬挑架结构。包括:吊箱,吊箱的四角处均固定有绕绳柱,绕绳柱的外端固定有限位块;设于墙体外侧的两个附墙支架A以及设于墙体内侧的两个附墙支架B;固定安装在墙体内侧的支板,支板上安装有用于驱动吊箱升降的卷扬机设备;分别安装在两侧附墙支架A上的两个导向绳,两个导向绳的底端均固定有固定钉;分别固定连接在吊箱两端的两个圆环。本实用新型在驱动吊箱升降的过程中,吊箱侧部连接的圆环在导向绳上滑动,从而能够对吊箱的移动起到导向作用,防止其产生较大幅度的晃动,以提升其安全性。

The utility model relates to the technical field of building construction, specifically a climbing frame and cantilever frame structure for the exterior wall of a high-rise building. It includes: a hanging box, rope winding columns are fixed at the four corners of the hanging box, and the outer ends of the rope winding columns are fixed with limited blocks; two wall-mounted brackets A arranged on the outside of the wall and two wall-mounted brackets B arranged on the inside of the wall; a support plate fixedly installed on the inside of the wall, on which a winch device for driving the lifting of the hanging box is installed; two guide ropes respectively installed on the wall-mounted brackets A on both sides, and the bottom ends of the two guide ropes are fixed with fixing nails; two circular rings respectively fixedly connected to the two ends of the hanging box. In the process of driving the lifting of the hanging box, the circular ring connected to the side of the hanging box slides on the guide rope, so that it can guide the movement of the hanging box and prevent it from shaking to a large extent, so as to improve its safety.

Description

一种高层建筑外墙爬架和悬挑架结构A high-rise building exterior wall climbing frame and cantilever frame structure

技术领域Technical Field

本实用新型涉及建筑施工技术领域,特别是涉及一种高层建筑外墙爬架和悬挑架结构。The utility model relates to the technical field of building construction, in particular to a high-rise building external wall climbing frame and a cantilever frame structure.

背景技术Background Art

建筑外墙爬架是高层建筑施工垂直运输机械的一种,其结构简单,安装、拆除和使用比较方便,在建筑楼层之间需要使用提升架进行上下楼层的物料运输。The building exterior wall climbing frame is a type of vertical transportation machinery for high-rise building construction. It has a simple structure and is easy to install, dismantle and use. A lifting frame is required between building floors to transport materials between upper and lower floors.

授权公告号为CN216042545U的中国专利公开了一种用于高层建筑外墙饰面层施工的吊篮穿爬架结构,包括配重、绳索、爬架和吊篮;爬架可拆卸式固定于墙体外侧,底部走道板封闭;绳索的中部设有用于变向的支撑结构,包括固定端和活动端;固定端与置于墙体内侧楼层地面的配重连接,位于配重下方的楼层设有回顶支撑;走道板上设有贯通的穿爬架管;活动端依次穿过墙体和穿爬架管,与位于爬架下方的吊篮连接,吊篮能在绳索牵引下沿竖直方向上下移动。A Chinese patent with authorization announcement number CN216042545U discloses a hanging basket climbing frame structure for the construction of exterior wall finishing layers of high-rise buildings, including a counterweight, a rope, a climbing frame and a hanging basket; the climbing frame is detachably fixed to the outside of the wall, and the bottom walkway plate is closed; a support structure for changing direction is provided in the middle of the rope, including a fixed end and a movable end; the fixed end is connected to the counterweight placed on the ground of the floor inside the wall, and the floor below the counterweight is provided with a return support; a through climbing frame pipe is provided on the walkway plate; the movable end passes through the wall and the climbing frame pipe in turn, and is connected to the hanging basket located below the climbing frame, and the hanging basket can move up and down in a vertical direction under the traction of the rope.

上述公开的专利仍存在有以下技术缺陷:所设置的吊篮会受到外界风速的影响,风速过大则容易导致其产生晃动,从而影响其安全性能。The above-mentioned patent still has the following technical defects: the hanging basket is affected by the external wind speed, and excessive wind speed can easily cause it to shake, thus affecting its safety performance.

实用新型内容Utility Model Content

本实用新型目的是针对背景技术中存在的问题,提出一种高层建筑外墙爬架和悬挑架结构。The utility model aims to solve the problems existing in the background technology and proposes a high-rise building external wall climbing frame and cantilever frame structure.

本实用新型的技术方案,一种高层建筑外墙爬架和悬挑架结构,包括:The technical solution of the utility model is a high-rise building exterior wall climbing frame and cantilever frame structure, comprising:

吊箱,吊箱的四角处均固定有绕绳柱,绕绳柱的外端固定有限位块;A hanging box, with rope winding columns fixed at the four corners of the hanging box, and limited blocks fixed at the outer ends of the rope winding columns;

设于墙体外侧的两个附墙支架A以及设于墙体内侧的两个附墙支架B,对应侧的附墙支架A与附墙支架B之间为可拆卸连接结构;Two wall-mounted brackets A are arranged on the outside of the wall and two wall-mounted brackets B are arranged on the inside of the wall, and the wall-mounted brackets A and B on the corresponding sides are detachably connected.

固定安装在墙体内侧的支板,支板上安装有用于驱动吊箱升降的卷扬机设备;A support plate fixedly installed on the inner side of the wall, on which a winch device for driving the hoisting box to rise and fall is installed;

分别安装在两侧附墙支架A上的两个导向绳,两个导向绳的底端均固定有固定钉;Two guide ropes are respectively installed on the wall brackets A on both sides, and the bottom ends of the two guide ropes are fixed with fixing nails;

分别固定连接在吊箱两端的两个圆环,两侧的导向绳分别活动贯穿两个圆环的内侧。Two circular rings are respectively fixedly connected to the two ends of the hanging box, and the guide ropes on both sides are movably passed through the inner sides of the two circular rings.

优选的,卷扬机设备包括伺服电机、减速机、传动轴A、两个收卷盘A和两条吊绳,支板上并排设置有两个安装座,传动轴A转动安装在两个安装座之间,伺服电机和减速机均安装在安装座上,减速机的输入轴与伺服电机的输出轴连接,减速机的输出轴与传动轴A连接,两个收卷盘A均固定在传动轴A上,两条吊绳分别固定在两侧的收卷盘A上,且吊绳贯穿墙壁,两条吊绳的端部均固定连接有两条分绳,四条分绳分别固定在四个绕绳柱上,附墙支架A和附墙支架B上分别固定有安装架A和安装架C,安装架A和安装架C上分别安装有定滑轮A和定滑轮C,且吊绳绕设在定滑轮A和定滑轮C上。Preferably, the winch equipment includes a servo motor, a reducer, a transmission shaft A, two winding drums A and two lifting ropes. Two mounting seats are arranged side by side on the support plate, and the transmission shaft A is rotatably installed between the two mounting seats. The servo motor and the reducer are both installed on the mounting seats. The input shaft of the reducer is connected to the output shaft of the servo motor, and the output shaft of the reducer is connected to the transmission shaft A. The two winding drums A are fixed on the transmission shaft A, and the two lifting ropes are respectively fixed on the winding drums A on both sides, and the lifting ropes pass through the wall. The ends of the two lifting ropes are fixedly connected with two branch ropes, and the four branch ropes are respectively fixed on four rope winding columns. The wall-mounted bracket A and the wall-mounted bracket B are respectively fixed with mounting frame A and mounting frame C, and the mounting frame A and the mounting frame C are respectively installed with fixed pulleys A and fixed pulleys C, and the lifting ropes are wound around the fixed pulleys A and fixed pulleys C.

优选的,附墙支架A和附墙支架B上分别设置有安装架B和安装架D,安装架B和安装架D上分别安装有定滑轮B和定滑轮D,定滑轮B与定滑轮D之间绕设有贯穿墙壁的安全绳,安全绳的底端固定有两条分绳,四条分绳分别固定在四个绕绳柱上,两个安装座之间转动安装有传动轴B,传动轴B上固定有两个收卷盘B,两条安全绳分别固定在两侧的收卷盘B上,传动轴A和传动轴B的端部均固定有齿轮,两个齿轮啮合连接。Preferably, a mounting frame B and a mounting frame D are respectively provided on the wall-mounted bracket A and the wall-mounted bracket B, and fixed pulleys B and D are respectively installed on the mounting frame B and the mounting frame D, a safety rope passing through the wall is wound between the fixed pulleys B and D, two branch ropes are fixed to the bottom end of the safety rope, and the four branch ropes are respectively fixed to four rope winding columns, a transmission shaft B is rotatably installed between the two mounting seats, two winding drums B are fixed on the transmission shaft B, and the two safety ropes are respectively fixed to the winding drums B on both sides, and gears are fixed to the ends of the transmission shaft A and the transmission shaft B, and the two gears are meshingly connected.

优选的,安装架A与安装架B之间的顶端固定有安装架E,安装架E上转动安装有两个限位轮。Preferably, a mounting frame E is fixed at the top between the mounting frame A and the mounting frame B, and two limiting wheels are rotatably mounted on the mounting frame E.

优选的,附墙支架A上固定有弯管,导向绳活动贯穿弯管,弯管上螺纹连接有多个蝶形螺栓。Preferably, a bent pipe is fixed on the wall-mounted bracket A, the guide rope movably passes through the bent pipe, and a plurality of butterfly bolts are threadedly connected on the bent pipe.

与现有技术相比,本实用新型具有如下有益的技术效果:在驱动吊箱升降的过程中,吊箱侧部连接的圆环在导向绳上滑动,从而能够对吊箱的移动起到导向作用,防止其产生较大幅度的晃动,以提升其安全性。Compared with the prior art, the utility model has the following beneficial technical effects: in the process of driving the hanging box to rise and fall, the circular ring connected to the side of the hanging box slides on the guide rope, thereby guiding the movement of the hanging box and preventing it from shaking significantly, thereby improving its safety.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1-图3均为本实用新型的结构示意图。Fig. 1-Fig. 3 are schematic diagrams of the structure of the present invention.

图4为图1的A处局部放大结构示意图。FIG. 4 is a schematic diagram of a partially enlarged structure of point A in FIG. 1 .

图5为图1的B处局部放大结构示意图。FIG. 5 is a schematic diagram of a partially enlarged structure of point B in FIG. 1 .

附图标记:1、吊箱;2、附墙支架A;3、附墙支架B;4、支板;51、吊绳;52、安全绳;501、分绳;6、导向绳;7、固定钉;8、安装座;9、伺服电机;10、减速机;111、传动轴A;112、传动轴B;121、收卷盘A;122、收卷盘B;131、安装架A;132、安装架B;133、安装架C;134、安装架D;141、定滑轮A;142、定滑轮B;143、定滑轮C;144、定滑轮D;15、安装架E;16、限位轮;17、弯管;18、蝶形螺栓;19、齿轮;20、绕绳柱;21、限位块;22、圆环。: 1. hanging box; 2. wall bracket A; 3. wall bracket B; 4. support plate; 51. lifting rope; 52. safety rope; 501. dividing rope; 6. guide rope; 7. fixing nail; 8. mounting seat; 9. servo motor; 10. reducer; 111. transmission shaft A; 112. transmission shaft B; 121. take-up reel A; 122. take-up reel B; 131. mounting frame A; 132. mounting frame B; 133. mounting frame C; 134. mounting frame D; 141. fixed pulley A; 142. fixed pulley B; 143. fixed pulley C; 144. fixed pulley D; 15. mounting frame E; 16. limiting wheel; 17. bent pipe; 18. butterfly bolt; 19. gear; 20. rope winding column; 21. limiting block; 22. ring.

具体实施方式DETAILED DESCRIPTION

实施例Example

如图1-图5所示,本实施例提出的一种高层建筑外墙爬架和悬挑架结构,包括吊箱1、两个附墙支架A2以及两个附墙支架B3,吊箱1的四角处均固定有绕绳柱20,四个绕绳柱20的设置可保证吊箱1升降过程中的稳定性,避免其产生晃动,绕绳柱20的外端固定有限位块21;两个附墙支架B3和附墙支架A2分别设于墙体内外两侧,对应侧的附墙支架A2与附墙支架B3之间为可拆卸连接结构。As shown in Figures 1 to 5, a high-rise building exterior wall climbing frame and cantilever frame structure proposed in this embodiment includes a hanging box 1, two wall-mounted brackets A2 and two wall-mounted brackets B3. Rope winding columns 20 are fixed at the four corners of the hanging box 1. The arrangement of the four rope winding columns 20 can ensure the stability of the hanging box 1 during the lifting process to prevent it from shaking. A limiting block 21 is fixed at the outer end of the rope winding column 20; the two wall-mounted brackets B3 and the wall-mounted bracket A2 are respectively arranged on both sides of the inside and outside of the wall, and the wall-mounted bracket A2 and the wall-mounted bracket B3 on the corresponding side are a detachable connection structure.

高层建筑外墙爬架和悬挑架结构还包括固定安装在墙体内侧的支板4,支板4上安装有用于驱动吊箱1升降的卷扬机设备,卷扬机设备包括伺服电机9、减速机10、传动轴A111、两个收卷盘A121和两条吊绳51,支板4上并排设置有两个安装座8,传动轴A111转动安装在两个安装座8之间,伺服电机9和减速机10均安装在安装座8上,减速机10的输入轴与伺服电机9的输出轴连接,伺服电机9和减速机10的配合能够获得更大的扭矩,其负载能力得以提高,减速机10的输出轴与传动轴A111连接,两个收卷盘A121均固定在传动轴A111上,两条吊绳51分别固定在两侧的收卷盘A121上,且吊绳51贯穿墙壁,两条吊绳51的端部均固定连接有两条分绳501,四条分绳501分别固定在四个绕绳柱20上,附墙支架A2和附墙支架B3上分别固定有安装架A131和安装架C133,安装架A131和安装架C133上分别安装有定滑轮A141和定滑轮C143,且吊绳51绕设在定滑轮A141和定滑轮C143上。The climbing frame and cantilever frame structure of the external wall of the high-rise building also include a support plate 4 fixedly installed on the inner side of the wall, a winch device for driving the lifting of the hanging box 1 is installed on the support plate 4, the winch device includes a servo motor 9, a reducer 10, a transmission shaft A111, two winding drums A121 and two hanging ropes 51, two mounting seats 8 are arranged side by side on the support plate 4, the transmission shaft A111 is rotatably installed between the two mounting seats 8, the servo motor 9 and the reducer 10 are both installed on the mounting seats 8, the input shaft of the reducer 10 is connected to the output shaft of the servo motor 9, the cooperation of the servo motor 9 and the reducer 10 can obtain a greater torque, its load capacity is improved, and the reducer The output shaft of the machine 10 is connected to the transmission shaft A111, and the two winding drums A121 are fixed on the transmission shaft A111. The two suspension ropes 51 are respectively fixed on the winding drums A121 on both sides, and the suspension ropes 51 pass through the wall. The ends of the two suspension ropes 51 are fixedly connected with two branch ropes 501, and the four branch ropes 501 are respectively fixed on the four rope winding columns 20. The wall-mounted bracket A2 and the wall-mounted bracket B3 are respectively fixed with mounting brackets A131 and mounting brackets C133, and the mounting brackets A131 and mounting brackets C133 are respectively installed with fixed pulleys A141 and fixed pulleys C143, and the suspension ropes 51 are wound around the fixed pulleys A141 and fixed pulleys C143.

高层建筑外墙爬架和悬挑架结构还包括两个弯管17、两个导向绳6以及两个圆环22,两个导向绳6分别安装在两侧附墙支架A2上,两个导向绳6的底端均固定有固定钉7,两个圆环22分别固定连接在吊箱1两端,两侧的导向绳6分别活动贯穿两个圆环22的内侧,两个弯管17分别固定在两侧的附墙支架A2上,导向绳6活动贯穿弯管17,弯管17上螺纹连接有多个蝶形螺栓18,在将固定钉7固定在地面上以后,使得导向绳6上端穿过弯管17,并使得导向绳6处于绷直状态,随后转动多个蝶形螺栓18,由此实现对导向绳6的夹紧固定工作。The high-rise building exterior wall climbing frame and cantilever frame structure also includes two bent pipes 17, two guide ropes 6 and two rings 22. The two guide ropes 6 are respectively installed on the wall brackets A2 on both sides. The bottom ends of the two guide ropes 6 are fixed with fixing nails 7. The two rings 22 are respectively fixedly connected to the two ends of the hanging box 1. The guide ropes 6 on both sides are respectively movable through the inner sides of the two rings 22. The two bent pipes 17 are respectively fixed on the wall brackets A2 on both sides. The guide rope 6 is movable through the bent pipes 17. A plurality of butterfly bolts 18 are threadedly connected to the bent pipes 17. After the fixing nails 7 are fixed to the ground, the upper end of the guide rope 6 is passed through the bent pipe 17, and the guide rope 6 is in a straight state. Then, the plurality of butterfly bolts 18 are rotated to achieve the clamping and fixing of the guide rope 6.

本实施例中,在将附墙支架A2安装完成后,将导向绳6底端的固定钉7插入到泥土中,随后使得导向绳6绷直,在驱动吊箱1升降的过程中,吊箱1侧部连接的圆环22在导向绳6上滑动,从而能够对吊箱1的移动起到导向作用,防止其产生较大幅度的晃动,以提升其安全性。In this embodiment, after the wall-mounted bracket A2 is installed, the fixing nail 7 at the bottom end of the guide rope 6 is inserted into the soil, and then the guide rope 6 is straightened. In the process of driving the hanging box 1 to rise and fall, the circular ring 22 connected to the side of the hanging box 1 slides on the guide rope 6, thereby guiding the movement of the hanging box 1 and preventing it from shaking significantly, thereby improving its safety.

实施例Example

如图1-图5所示,本实施例提出的一种高层建筑外墙爬架和悬挑架结构,相较于实施例一,本实施例中,附墙支架A2和附墙支架B3上分别设置有安装架B132和安装架D134,安装架B132和安装架D134上分别安装有定滑轮B142和定滑轮D144,定滑轮B142与定滑轮D144之间绕设有贯穿墙壁的安全绳52,安全绳52的底端固定有两条分绳501,四条分绳501分别固定在四个绕绳柱20上,两个安装座8之间转动安装有传动轴B112,传动轴B112上固定有两个收卷盘B122,两条安全绳52分别固定在两侧的收卷盘B122上,传动轴A111和传动轴B112的端部均固定有齿轮19,两个齿轮19啮合连接;安装架A131与安装架B132之间的顶端固定有安装架E15,安装架E15上转动安装有两个限位轮16。As shown in FIGS. 1 to 5 , a high-rise building exterior wall climbing frame and cantilever frame structure proposed in this embodiment, compared with the first embodiment, in this embodiment, the wall-mounted bracket A2 and the wall-mounted bracket B3 are respectively provided with a mounting frame B132 and a mounting frame D134, and the mounting frame B132 and the mounting frame D134 are respectively provided with a fixed pulley B142 and a fixed pulley D144, and a safety rope 52 penetrating the wall is wound between the fixed pulley B142 and the fixed pulley D144, and two branch ropes 501 are fixed to the bottom end of the safety rope 52, and four branch ropes 501 are fixed to the bottom end of the safety rope 52. The rope 501 is respectively fixed on the four rope winding columns 20, and a transmission shaft B112 is rotatably installed between the two mounting seats 8. Two winding drums B122 are fixed on the transmission shaft B112. Two safety ropes 52 are respectively fixed on the winding drums B122 on both sides. Gears 19 are fixed on the ends of the transmission shaft A111 and the transmission shaft B112, and the two gears 19 are meshed and connected; a mounting frame E15 is fixed on the top end between the mounting frame A131 and the mounting frame B132, and two limiting wheels 16 are rotatably installed on the mounting frame E15.

本实施例中,安全绳52始终处于松弛的状态,当吊绳51断裂后所设置的安全绳52能够防止吊箱1下坠,以提升设备的安全性。In this embodiment, the safety rope 52 is always in a loose state. When the suspension rope 51 breaks, the safety rope 52 can prevent the suspension box 1 from falling, so as to improve the safety of the equipment.

上面结合附图对本实用新型的实施方式作了详细说明,但是本实用新型并不限于此,在所属技术领域的技术人员所具备的知识范围内,在不脱离本实用新型宗旨的前提下还可以作出各种变化。The implementation modes of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited thereto, and various changes can be made within the knowledge scope of technicians in the relevant technical field without departing from the purpose of the present invention.

Claims (5)

1. The utility model provides a high-rise building outer wall climbs frame and cantilever structure which characterized in that includes:
The lifting box (1), four corners of the lifting box (1) are respectively fixed with a rope winding column (20), and the outer ends of the rope winding columns (20) are fixed with limiting blocks (21);
Two wall-attached brackets A (2) arranged on the outer side of the wall body and two wall-attached brackets B (3) arranged on the inner side of the wall body, wherein a detachable connection structure is arranged between the wall-attached brackets A (2) and the wall-attached brackets B (3) on the corresponding sides;
The support plate (4) is fixedly arranged on the inner side of the wall body, and hoisting equipment for driving the hanging box (1) to lift is arranged on the support plate (4);
two guide ropes (6) respectively arranged on the wall-attached brackets A (2) at two sides, and fixing nails (7) are fixed at the bottom ends of the two guide ropes (6);
two circular rings (22) which are respectively and fixedly connected with two ends of the hanging box (1), and guide ropes (6) at two sides respectively and movably penetrate through the inner sides of the two circular rings (22).
2. The climbing frame and cantilever frame structure according to claim 1, wherein the hoisting machine comprises a servo motor (9), a speed reducer (10), a transmission shaft A (111), two winding discs A (121) and two lifting ropes (51), two mounting seats (8) are arranged on the support plate (4) side by side, the transmission shaft A (111) is rotatably mounted between the two mounting seats (8), the servo motor (9) and the speed reducer (10) are both mounted on the mounting seats (8), an input shaft of the speed reducer (10) is connected with an output shaft of the servo motor (9), an output shaft of the speed reducer (10) is connected with the transmission shaft A (111), the two winding discs A (121) are both fixed on the transmission shaft A (111), the two lifting ropes (51) are respectively fixed on the winding discs A (121) on two sides, the ends of the two lifting ropes (51) are both fixedly connected with two sub-ropes (501), the four sub-ropes (501) are respectively fixed on the four sub-ropes (20), the support bracket A (2) and the support bracket A (131) and the support bracket C (131) are respectively mounted on the support bracket C (133), and the lifting rope (51) is wound on the fixed pulley A (141) and the fixed pulley C (143).
3. The climbing frame and cantilever frame structure of the outer wall of the high-rise building according to claim 2, characterized in that, a mounting frame B (132) and a mounting frame D (134) are respectively arranged on a wall attaching bracket A (2) and a wall attaching bracket B (3), a fixed pulley B (142) and a fixed pulley D (144) are respectively arranged on the mounting frame B (132) and the mounting frame D (134), a safety rope (52) penetrating through the wall is wound between the fixed pulley B (142) and the fixed pulley D (144), two sub ropes (501) are fixed at the bottom end of the safety rope (52), four sub ropes (501) are respectively fixed on four rope winding columns (20), a transmission shaft B (112) is rotatably arranged between the two mounting seats (8), two winding discs B (122) are fixed on the transmission shaft B (112), the two safety ropes (52) are respectively fixed on the winding discs B (122) at two sides, gears (19) are respectively fixed at the ends of the transmission shaft A (111) and the transmission shaft B (112), and the two gears (19) are in meshed connection.
4. A high-rise building outer wall climbing frame and cantilever frame structure according to claim 3, wherein a mounting frame E (15) is fixed at the top end between a mounting frame a (131) and a mounting frame B (132), and two limiting wheels (16) are rotatably mounted on the mounting frame E (15).
5. The climbing frame and cantilever frame structure for the outer wall of the high-rise building according to claim 1, wherein the bent pipe (17) is fixed on the wall attaching bracket A (2), the guide rope (6) movably penetrates through the bent pipe (17), and a plurality of butterfly bolts (18) are connected to the bent pipe (17) in a threaded mode.
CN202420402892.7U 2024-03-01 2024-03-01 A high-rise building exterior wall climbing frame and cantilever frame structure Active CN221856152U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202420402892.7U CN221856152U (en) 2024-03-01 2024-03-01 A high-rise building exterior wall climbing frame and cantilever frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202420402892.7U CN221856152U (en) 2024-03-01 2024-03-01 A high-rise building exterior wall climbing frame and cantilever frame structure

Publications (1)

Publication Number Publication Date
CN221856152U true CN221856152U (en) 2024-10-18

Family

ID=93045339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202420402892.7U Active CN221856152U (en) 2024-03-01 2024-03-01 A high-rise building exterior wall climbing frame and cantilever frame structure

Country Status (1)

Country Link
CN (1) CN221856152U (en)

Similar Documents

Publication Publication Date Title
CN108590172A (en) A kind of integral lifting hoistway formwork supporting mechanism
CN221856152U (en) A high-rise building exterior wall climbing frame and cantilever frame structure
CN209907218U (en) A self-anchored suspension bridge main cable strand double-wire circulating traction system
CN2410277Y (en) All slewing crane with lifting cradle
CN211115085U (en) Platform over-and-under type single tub of communication tower convenient to maintenance operation
CN221140834U (en) Steel construction section bar lifting device
CN216711434U (en) High-lift hoister
CN210369651U (en) Orchestra pond lifting type railing
CN111362157A (en) Hoist device for construction
CN112661077B (en) A high-safety engineering material lifting device for industrial and civil construction
CN202670960U (en) Safe and energy-saving construction elevator
CN209816674U (en) A prestressed tension jack installation tool in the cast-in-place box girder box
CN214942442U (en) Super high-rise horizontal structure construction is with hanging mould platform device
CN214995832U (en) Rail crane ship capable of horizontally and vertically walking for high-altitude suspension construction of building
CN213416059U (en) Building construction tower crane with cable stabilizing mean
CN207142600U (en) A kind of elevator
JPS6026054Y2 (en) Sheave wheel for elevator
WO2021035864A1 (en) Winding structure of traction type building construction elevator
CN219411898U (en) Tool type platform truck for hanging and unloading floor-mounted pipe
CN207497947U (en) Disc type hoist engine with deflecting roller
JPH0867458A (en) Balance rope lifting device
CN218174447U (en) Double-drum European crane trolley
CN207497948U (en) Disc type hoist engine
CN222699827U (en) A kind of building steel structure hoisting equipment
CN221543904U (en) Building wallboard lifting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant