CN220482041U - Multilayer manufacturing mould platform of cement prefabricated plate - Google Patents

Multilayer manufacturing mould platform of cement prefabricated plate Download PDF

Info

Publication number
CN220482041U
CN220482041U CN202322069406.2U CN202322069406U CN220482041U CN 220482041 U CN220482041 U CN 220482041U CN 202322069406 U CN202322069406 U CN 202322069406U CN 220482041 U CN220482041 U CN 220482041U
Authority
CN
China
Prior art keywords
support
bracket
cement
template
roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322069406.2U
Other languages
Chinese (zh)
Inventor
孙汉兵
孙思耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Yixinda Building Materials Technology Co ltd
Original Assignee
Qingdao Yixinda Building Materials Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Yixinda Building Materials Technology Co ltd filed Critical Qingdao Yixinda Building Materials Technology Co ltd
Priority to CN202322069406.2U priority Critical patent/CN220482041U/en
Application granted granted Critical
Publication of CN220482041U publication Critical patent/CN220482041U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model discloses a multilayer manufacturing die platform of a cement precast slab, and relates to the technical field of cement precast slab processing. According to the utility model, the plurality of forming cavities are vertically distributed on the first bracket and the first bracket through the arrangement of the first bracket, the second bracket, the roller, the supporting wheel and the roller, so that the transverse space occupied by the die platform is reduced, meanwhile, the second bracket can transversely slide through the supporting wheel, so that the excessive cement in most of forming cavities is pushed out, the cement precast slab is more flat after being formed, meanwhile, the abrasion between the second bracket and the first bracket during sliding is reduced through the arrangement of the roller and the roller, the occupied space of the die is reduced, and the excessive cement is convenient to clean, so that the precast slab is more flat.

Description

Multilayer manufacturing mould platform of cement prefabricated plate
Technical Field
The utility model relates to the technical field of cement precast slab processing, in particular to a multi-layer manufacturing die platform of a cement precast slab.
Background
The cement precast slab refers to a cement slab manufactured in advance in a prefabrication processing plant, and is mainly characterized in that bundled reinforcing steel bars are placed in a die, cement concrete is poured into the die, the cavity and bubbles are eliminated through vibration, the cement precast slab is compact, and the die is disassembled after the cement precast slab is solidified and molded, so that the cement precast slab can be taken out.
The mould platform used in the existing cement precast slab manufacturing is convenient for quicken the production speed and usually processes a plurality of cement precast slabs once, but the distribution mode of mould is usually rectangular array form distribution along the horizontal direction, leads to mould platform usually bulky, and occupation space is more, leads to needing great space to place mould platform in the processing chamber, in addition cement pouring equipment and the required activity space of transport fork truck, makes in the processing factory usually only place a small amount of mould platforms, and space utilization is relatively poor consequently needs great space, and then leads to manufacturing cost to be higher.
Disclosure of Invention
Based on the above, the utility model aims to provide a multi-layer manufacturing mould platform for cement precast slabs so as to solve the technical problem that a plurality of moulds are horizontally distributed and require a large space.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a multilayer preparation mould platform of cement prefabricated plate, includes first support, first support side is connected with the second support, and is connected with the supporting wheel under the second support, first support surface is connected with the cylinder, and runs through on the first support has the gyro wheel.
Through adopting above-mentioned technical scheme, with a plurality of forming cavities vertical distribution on first support and first support, and then reduce the required horizontal space that occupies of mould platform, but the second support passes through the backing wheel lateral sliding simultaneously, and then with unnecessary cement push out in the most forming cavities, and then make cement prefabricated plate shaping back more level and smooth, reduce the wearing and tearing between second support slip time and the first support through the setting of cylinder and gyro wheel simultaneously.
Further, be connected with first template on the first support, and be connected with the second template on the first support, and be connected with the bolt between first template and the second template, first support top is provided with the shaping chamber.
Through adopting above-mentioned technical scheme, put into the shaping intracavity with the reinforcing bar that ties up, pour cement concrete to the shaping intracavity through pouring equipment after placing the reinforcing bar, take off the bolt after the cement prefabricated plate solidification shaping and end the spacing to first template and second template, take off the bolt after taking off first template and second template again take out the cement prefabricated plate.
Further, the second support is movably connected with the first support.
Through adopting above-mentioned technical scheme, a plurality of forming cavities vertical distribution is on first support and first support, and the second support passes through the backing wheel and can transversely slide, and then pushes away unnecessary cement in the most forming cavities, and then makes more level and smooth behind the cement prefabricated plate shaping.
Furthermore, the cross sections of the first bracket and the second bracket are I-shaped, and the first bracket and the second bracket are distributed in a staggered manner.
Through adopting above-mentioned technical scheme, with a plurality of forming chamber vertical distribution on first support and first support, and then reduce the required horizontal space that occupies of mould platform, the section of I shape avoids second support and first support separation simultaneously.
Further, the rollers are provided with a plurality of rollers, and the rollers are respectively and movably connected with the first bracket and the second bracket.
Through adopting above-mentioned technical scheme, but the second support passes through the backing wheel lateral sliding, and then releases unnecessary cement in the most molding chamber, reduces the wearing and tearing between second support slip time and the first support through the setting of cylinder and gyro wheel simultaneously.
Further, the plurality of rollers are arranged and distributed in a rectangular array.
Through adopting above-mentioned technical scheme, pulling the second support to the right makes the second support slide rightwards through the supporting wheel and stretches out from first support, reduces the wearing and tearing between first support and the second support through rolling 6 and gyro wheel simultaneously.
Further, the first template is movably connected with the first support, and the second template is movably connected with the first template.
Through adopting above-mentioned technical scheme, the bolt of removing ends the spacing to first template and second template, later alright directly take off a plurality of first templates and second templates from first support and second support respectively to be convenient for take out cement prefabricated plate.
In summary, the utility model has the following advantages:
according to the utility model, the plurality of forming cavities are vertically distributed on the first bracket and the first bracket through the arrangement of the first bracket, the second bracket, the roller, the supporting wheel and the roller, so that the transverse space occupied by the die platform is reduced, meanwhile, the second bracket can transversely slide through the supporting wheel, so that the excessive cement in most of forming cavities is pushed out, the cement precast slab is more flat after being formed, meanwhile, the abrasion between the second bracket and the first bracket during sliding is reduced through the arrangement of the roller and the roller, the occupied space of the die is reduced, and the excessive cement is convenient to clean, so that the precast slab is more flat.
Drawings
FIG. 1 is a schematic view of a mold platform according to the present utility model when unfolded;
FIG. 2 is a schematic cross-sectional view of a mold platform of the present utility model when closed;
FIG. 3 is a schematic view of a first bracket structure according to the present utility model;
fig. 4 is a schematic view of a second bracket structure according to the present utility model.
In the figure: 1. a first bracket; 2. a second bracket; 3. a first template; 4. a second template; 5. a bolt; 6. a roller; 7. a support wheel; 8. a roller; 9. and forming the cavity.
Detailed Description
The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. The embodiments described below by referring to the drawings are illustrative only and are not to be construed as limiting the utility model.
Hereinafter, an embodiment of the present utility model will be described in accordance with its entire structure.
The utility model provides a multilayer preparation mould platform of cement prefabricated plate, as shown in fig. 1-4, including first support 1, first support 1 one side runs through there is second support 2, vertical distribution and then reduce the required horizontal space who occupies of mould platform, and be connected with supporting wheel 7 under the second support 2, but lateral sliding release unnecessary cement, the surface and the back of first support 1 and second support 2 are connected with a plurality of cylinders 6 respectively, and a plurality of cylinders 6 respectively with first support 1 and second support 2 rotate and be connected, and first support 1 and second support 2 top one side run through respectively have a plurality of gyro wheels 8, and a plurality of gyro wheels 8 are rectangular array form distribution, reduce the wearing and tearing between second support 2 and the first support 1 when sliding, first support 1 and second support 2 top all are connected with a plurality of first templates 3, and first support 1 and second support 2 top opposite side all are connected with a plurality of second templates 4, a plurality of first templates 3 respectively with first support 1 and second support 2 between be connected with bolt 5, and a plurality of first templates 3 respectively with second templates are connected with 5 with a plurality of second templates 5, and make the prefabricated plate take out the cement shaping more convenient for the top is formed into shape, the prefabricated plate is convenient for take out the second template 2, the cement prefabricated plate takes out more than the top is convenient for take out the more than the second template, the top is convenient for take out the cement prefabricated plate is formed with more than 5.
Referring to fig. 1-4, in the above embodiment, the second bracket 2 is slidably connected with the first bracket 1 through the roller 6 and the roller 8, the sections of the first bracket 1 and the second bracket 2 are in an "i" shape, the first bracket 1 and the second bracket 2 are distributed in a staggered manner, the first mold plate 3 is detachably connected with the first bracket 1 through bolts, and the second mold plate 4 is detachably connected with the first mold plate 3 through bolts, so that the occupied space of the mold is reduced.
The implementation principle of the embodiment is as follows: firstly, a worker pulls the second bracket 2 rightwards, so that the second bracket 2 slides rightwards through the supporting wheel 7 to extend out of the first bracket 1, meanwhile, abrasion between the first bracket 1 and the second bracket 2 is reduced through the roller 6 and the roller 8, the worker places the bundled reinforcing steel bars into the forming cavity 9, the worker pours cement concrete into the forming cavity 9 through pouring equipment after placing the reinforcing steel bars, the worker pushes the second bracket 2 leftwards after pouring, the second bracket 2 enters the first bracket 1, meanwhile, the second bracket 2 is closed with the first bracket 1, and excessive cement in most of the forming cavity 9 is extruded out, so that a cement precast slab is more flat after being formed;
unloading, cement prefabricated plate solidification shaping back staff pulls second support 2 rightwards makes second support 2 stretch out from first support 1, later the staff remove bolt 5 and end the spacing to first template 3 and second template 4, and the staff just directly takes off first template 3 and second template 4 after removing bolt 5 to the staff takes out cement prefabricated plate.
Although embodiments of the utility model have been shown and described, the detailed description is to be construed as exemplary only and is not limiting of the utility model as the particular features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples, and modifications, substitutions, variations, etc. may be made in the embodiments as desired by those skilled in the art without departing from the principles and spirit of the utility model, provided that such modifications are within the scope of the appended claims.

Claims (7)

1. The utility model provides a multilayer preparation mould platform of cement prefabricated plate, includes first support (1), its characterized in that: the side of the first support (1) is connected with a second support (2), a supporting wheel (7) is connected under the second support (2), the surface of the first support (1) is connected with a roller (6), and a roller (8) penetrates through the first support (1).
2. The multi-layer construction mold platform for cement precast slabs of claim 1, wherein: the novel plastic forming device is characterized in that a first template (3) is connected to the first support (1), a second template (4) is connected to the first support (1), a bolt (5) is connected between the first template (3) and the second template (4), and a forming cavity (9) is formed in the top of the first support (1).
3. The multi-layer construction mold platform for cement precast slabs of claim 1, wherein: the second bracket (2) is movably connected with the first bracket (1).
4. A multi-layer construction mold platform for cement precast slabs according to claim 3, wherein: the sections of the first support (1) and the second support (2) are I-shaped, and the first support (1) and the second support (2) are distributed in a staggered mode.
5. The multi-layer construction mold platform for cement precast slabs of claim 1, wherein: the rollers (6) are provided with a plurality of rollers, and the rollers (6) are respectively and movably connected with the first bracket (1) and the second bracket (2).
6. The multi-layer construction mold platform for cement precast slabs of claim 1, wherein: the plurality of rollers (8) are arranged, and the plurality of rollers (8) are distributed in a rectangular array shape.
7. A multi-layer construction mold platform for cement precast slabs according to claim 2, wherein: the first template (3) is movably connected with the first bracket (1), and the second template (4) is movably connected with the first template (3).
CN202322069406.2U 2023-08-03 2023-08-03 Multilayer manufacturing mould platform of cement prefabricated plate Active CN220482041U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322069406.2U CN220482041U (en) 2023-08-03 2023-08-03 Multilayer manufacturing mould platform of cement prefabricated plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322069406.2U CN220482041U (en) 2023-08-03 2023-08-03 Multilayer manufacturing mould platform of cement prefabricated plate

Publications (1)

Publication Number Publication Date
CN220482041U true CN220482041U (en) 2024-02-13

Family

ID=89828010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322069406.2U Active CN220482041U (en) 2023-08-03 2023-08-03 Multilayer manufacturing mould platform of cement prefabricated plate

Country Status (1)

Country Link
CN (1) CN220482041U (en)

Similar Documents

Publication Publication Date Title
CN106965302B (en) Precast beam type stair, special mold and construction method thereof
CN114888931A (en) Box girder production system
CN220482041U (en) Multilayer manufacturing mould platform of cement prefabricated plate
CN206015540U (en) A kind of box culvert slip form construction device
CN218019118U (en) A former for curb production
CN107035045A (en) A kind of precast concrete bidirectional hollow plate and preparation method thereof
CN217345967U (en) Movable prefabricated box girder template system
CN111350348A (en) Positioning and reinforcing device for outer wall anti-seepage inverted beam template and construction method
CN210011144U (en) Construction site fence prefabricated foundation
CN211806845U (en) Adjustable four-foot cement stirrup mold
CN202517567U (en) Porous foaming concrete block production line
CN208473149U (en) A kind of assembling-type precast stair
CN108661255A (en) A kind of assembling-type precast stair and its production method
CN222741729U (en) Cutting and forming device for producing autoclaved aerated concrete plates
CN113084973A (en) L-shaped and T-shaped prefabricated hollow shear wall plate vertical mold production equipment and working method
CN111702941A (en) Precast concrete spare production line
CN215395894U (en) Stair template of prefabricated stair of fleing
CN219992206U (en) Synchronous quick lifting hydraulic climbing formwork structure of inner and outer formwork
CN212078689U (en) Stair antiskid template
CN210712509U (en) Cast-in-place box girder movable formwork
CN221187013U (en) Combined die for pouring building wall
CN218965724U (en) U-shaped aqueduct drawing type internal mold assembly
CN202784703U (en) Rear portion ferry trolley used in foam slurry core filling building block automatic production line
CN223130985U (en) Prestressed hollow slab beam processing template device
CN221391513U (en) Form removing equipment for ultrahigh-performance concrete slab

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant