CN219931660U - Steel construction wallboard installation auxiliary assembly - Google Patents

Steel construction wallboard installation auxiliary assembly Download PDF

Info

Publication number
CN219931660U
CN219931660U CN202321483716.2U CN202321483716U CN219931660U CN 219931660 U CN219931660 U CN 219931660U CN 202321483716 U CN202321483716 U CN 202321483716U CN 219931660 U CN219931660 U CN 219931660U
Authority
CN
China
Prior art keywords
wallboard
support
supporting
support frame
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321483716.2U
Other languages
Chinese (zh)
Inventor
秦绍清
王稳权
孙锋波
范倩琨
张树荣
赵永林
周鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co ltd Of China National Chemical Engineering
Original Assignee
Fourth Construction Co ltd Of China National Chemical Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co ltd Of China National Chemical Engineering filed Critical Fourth Construction Co ltd Of China National Chemical Engineering
Priority to CN202321483716.2U priority Critical patent/CN219931660U/en
Application granted granted Critical
Publication of CN219931660U publication Critical patent/CN219931660U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides steel structure wallboard installation auxiliary equipment, which comprises a support frame for bearing wallboards, wherein the support frame is of a truss structure, a climbing passage for workers to enter and exit is formed in the middle of the support frame, and a support side surface for fixing the wallboards is formed on the side surface of the support frame; the support frame is provided with a lower end part for supporting the ground, and the support frame is in an upright state when the lower end part is supported on the ground; the other side surface of the support frame, which is opposite to the support side surface, is a support side surface, and when the support side surface is supported on the ground, the support frame is in a horizontal lying state. The utility model adopts the supporting frame to fix and move the wallboard, so that the wallboard is stably supported by the supporting frame in the hoisting process, the wallboard is prevented from deforming and damaging, the hoisting length of the wallboard is prolonged, the cost is saved, and the wallboard mounting joint is reduced.

Description

Steel construction wallboard installation auxiliary assembly
Technical Field
The utility model belongs to the technical field of steel structure buildings, and particularly relates to auxiliary equipment for installing a steel structure wallboard.
Background
At present, the application of the steel structure building is gradually increased due to the advantages of factory production, convenient and simple installation, short construction period and the like, and is gradually applied to the fields of factory buildings, workshops, even infrastructure and the like; the enclosure structure of the steel structure building basically adopts sandwich composite wallboards and profiled single-layer steel plates, in the traditional wallboard installation process, short wallboards are generally adopted to be installed on the wall surface of the steel structure main body frame, and then the short wallboards are spliced to meet the length requirement of the whole wallboard; the wallboard of the steel structure building is thinner, and the rigidity of the larger wallboard often cannot meet the conditions of hoisting and even transportation; when workers install the wallboards, the wallboards are required to be pulled upwards from the ground to be in place by adopting ropes, and the safety cannot be effectively ensured because the peripheries of the workers are not protected.
For example, the chinese patent application No. CN202211312938.8 discloses a steel structure assembled building external wall panel installation device and its implementation method, which adopts the main technical means that an independent installation auxiliary support platform is provided, and the connection of a hoisting machine is controlled to control the position lifting movement of a supporting plate and a wall panel, so that the installation is troublesome.
Therefore, how to prevent the damage of the wallboard during the installation and hoisting, and to increase the hoisting length of the wallboard, become the technical problem to be solved in the industry.
Disclosure of Invention
The utility model aims to solve the problems in the prior art, and provides the steel structure wallboard installation auxiliary equipment which can prevent the damage of wallboards during installation and hoisting, increase the hoisting length of wallboards and solve the problems of up-and-down channels and working environments of workers.
The aim of the utility model can be achieved by the following technical scheme:
the steel structure wallboard installation auxiliary equipment comprises a support frame for bearing wallboards, wherein the support frame is of a truss structure, a climbing passage for workers to enter and exit is formed in the middle of the support frame, and a support side surface for fixing the wallboards is formed on the side surface of the support frame; the support frame is provided with a lower end part for supporting the ground, and the support frame is in an upright state when the lower end part is supported on the ground; the other side surface of the support frame, which is opposite to the support side surface, is a support side surface, and when the support side surface is supported on the ground, the support frame is in a horizontal lying state.
In some embodiments, a lifting ring is provided on the upper end of the support frame opposite the lower end.
In some embodiments, a baffle is provided on the support side to support the lower end of the wall panel.
In certain embodiments, the height of the baffles is less than the thickness of the wallboard.
In some embodiments, the wall panel comprises a plurality of binding ropes for binding the wall panel to the supporting side surface, and binding holes for the binding ropes to pass through are arranged on the two sides of the wall panel on the supporting frame.
In some embodiments, the support sides are provided with cushioning pads that support the wallboard.
In some embodiments, the support frame is a rectangular frame body, and the support frame comprises support columns positioned at four corners, and adjacent support columns are connected through connecting rods.
In some embodiments, the central space enclosed by the support column and the connecting rod is a climbing channel.
In some embodiments, links arranged up and down the support column form a climbing ladder for the climbing channel.
Compared with the prior art, the steel structure wallboard installation auxiliary equipment has the following advantages:
the utility model adopts the supporting frame to fix and move the wallboard, so that the wallboard is stably supported by the supporting frame in the hoisting process, the wallboard is prevented from deforming and damaging, the hoisting length of the wallboard is prolonged, the cost is saved, and the wallboard mounting joint is reduced. The support frame is internally provided with a channel for workers to climb, so that the periphery of the workers is provided with a surrounding area, the safety is effectively guaranteed, the safety risk is reduced, and the problems of the upper and lower channels and the working environment of the workers are solved.
Drawings
In the drawings (which are not necessarily drawn to scale), like numerals may describe similar components in different views. Like reference numerals having different letter suffixes may represent different instances of similar components. The drawings illustrate generally, by way of example and not by way of limitation, various embodiments discussed herein.
FIG. 1 is a schematic top view of a support frame;
FIG. 2 is a schematic side view of a support frame with wallboard placed;
FIG. 3 is an end-on schematic view of the support bracket;
FIG. 4 is a schematic view of the installation of wallboard using a support stand;
in the figure, 1, wallboard; 2. a support column; 3. a connecting rod; 4. a support side; 5. a lower end portion; 6. climbing a channel; 7. a hanging ring; 8. a baffle; 9. tying the rope; 10. binding hole sites; 11. a buffer sleeve; 12. a building; 13. and (5) a worker.
Detailed Description
The following are specific examples of the present utility model and the technical solutions of the present utility model will be further described with reference to the accompanying drawings, but the present utility model is not limited to these examples, and the following embodiments do not limit the utility models according to the claims. Furthermore, all combinations of features described in the embodiments are not necessarily essential to the inventive solution.
It will be appreciated by those of ordinary skill in the art that all directional references (e.g., above, below, upward, downward, top, bottom, left, right, vertical, horizontal, etc.) are descriptive of the drawings to aid the reader in understanding, and do not represent (e.g., positional, azimuthal, use, etc.) limitations on the scope of the utility model defined by the appended claims. In addition, the term "substantially" may refer to slight imprecision or slight deviation in terms of conditions, amounts, values, or dimensions, some of which are within manufacturing tolerances or tolerances.
Examples:
as shown in fig. 1, 2 and 3, an auxiliary device for installing a steel structure wallboard 1 comprises a support frame for bearing the wallboard 1, wherein the support frame is of a truss structure, namely, the support frame is a rectangular frame body formed by welding steel profiles, the support frame comprises support columns 2 which are positioned at four corners and serve as main body supports, the support columns 2 of the embodiment are angle steel profiles, and adjacent support columns 2 are connected together through connecting rods 3, so that a rectangular frame structure body is formed.
The rectangular frame structure body is provided with four side surfaces and an upper end surface and a lower end surface, one side surface is used as a supporting side surface 4 for fixing the wallboard 1, the other side surface opposite to the supporting side surface 4 on the supporting frame is the supporting side surface 4, and when the supporting side surface 4 is supported on the ground, the supporting frame is in a horizontal lying state, namely the supporting side surface 4 faces upwards, and at the moment, the wallboard 1 is conveniently fixed on the supporting side surface 4.
One end face is a lower end part 5 for supporting the ground, when the lower end part 5 is supported on the ground, the support frame is in an upright state, and the wallboard 1 can be in an upright state at the moment;
the middle space that support column 2 and connecting rod 3 enclose is climbing passageway 6, promptly four sides of rectangular frame structure body enclose into the climbing passageway 6 that supplies workman 13 business turn over, workman 13 can be in climbing passageway 6 right wallboard 1 installs the operation, and the connecting rod 3 of arranging from top to bottom along support column 2 constitutes climbing ladder of climbing passageway 6 to workman 13 removes in climbing passageway 6.
And a hanging ring 7 is arranged on the upper end part of the support frame opposite to the lower end part 5, so that the support frame can be lifted and moved by a crane.
The support side 4 is provided with a baffle 8 for supporting the lower end 5 of the wallboard 1 so as to drag the lower end of the wallboard 1, and the height of the baffle 8 is smaller than the thickness of the wallboard 1 so as to contact the wallboard 1 with the surface of a building 12.
The wall plate 1 is fixed on the support frame through the binding ropes 9, and binding holes 10 for the binding ropes 9 to pass through are formed in the support frame and are positioned on two sides of the wall plate 1, and the wall plate 1 is bound on the support frame through the binding ropes 9.
The cushion pad that supports wallboard 1 is provided with on the support side 4, avoids the support frame to cause the damage to wallboard 1 surface, and this embodiment adopts be in support column 2 spaced cover has a plurality of cushion collar 11.
As shown in fig. 4, the wallboard installation process is as follows:
1) When the supporting side face is supported on the ground, the supporting frame is in a horizontal lying state, a worker manually lifts the wallboard plate onto the supporting side face, the inner side of the wallboard faces upwards, and the outer side of the wallboard faces the supporting side face;
2) Binding the wallboard on the supporting frame by workers through ropes;
3) The supporting frame is hoisted by a crane, so that the supporting frame is in an upright state, phi 16 round steel bent lifting lugs are welded in the short side direction of the top of the supporting frame for convenient hoisting and installation of the wallboard, a boom beam is welded by double splicing, and a U-shaped clamping ring is connected with a steel wire rope during hoisting;
4) The wallboard is hoisted to the installation position along with the support frame, workers climb to the installation working position from the climbing channel of the support frame, and during climbing, the safety belt of the workers is tied and hung on the falling protector put down from the crane hook;
5) After the worker makes the wallboard correspond to the installation position, the fixing rope is released, the wallboard is fixed on the surface of the building through the peg at the corresponding position by the worker, after the worker finishes working, the worker descends to the ground from the support frame channel, and then the crane hangs the support frame to the ground, so that the support frame is in a horizontal lying state, and the next wallboard is placed on the support side face conveniently;
6) And repeating the steps to install the wallboard again.
Although some terms are used more herein, the possibility of using other terms is not excluded. These terms are used merely for convenience in describing and explaining the nature of the utility model; they are to be interpreted as any additional limitation that is not inconsistent with the spirit of the present utility model. The order of execution of the operations, steps, and the like in the apparatuses and methods shown in the specification and the drawings may be any order as long as the order is not particularly limited, and the output of the preceding process is not used in the following process. The use of the description of "first", "next", etc. for convenience of description does not imply that the operations must be performed in such order.
The specific embodiments described herein are offered by way of example only to illustrate the spirit of the utility model. Those skilled in the art may make various modifications or additions to the described embodiments or substitutions thereof without departing from the spirit of the utility model or exceeding the scope of the utility model as defined in the accompanying claims.

Claims (10)

1. The utility model provides a steel construction wallboard installation auxiliary assembly which characterized in that: the wall board climbing device comprises a supporting frame for bearing the wall board, wherein the supporting frame is of a truss structure, a climbing passage for workers to enter and exit is formed in the middle of the supporting frame, and a supporting side surface for fixing the wall board is formed on the side surface of the supporting frame; the support frame is provided with a lower end part for supporting the ground, and the support frame is in an upright state when the lower end part is supported on the ground; the other side surface of the support frame, which is opposite to the support side surface, is a support side surface, and when the support side surface is supported on the ground, the support frame is in a horizontal lying state.
2. The steel structure wallboard installation auxiliary device according to claim 1, wherein an upper end portion of the supporting frame opposite to the lower end portion is provided with a hanging ring.
3. The steel structure wallboard installation aid of claim 1, wherein the support side is provided with a baffle supporting a lower end of the wallboard.
4. A steel structure wallboard installation aid according to claim 3, wherein the height of the baffles is less than the thickness of the wallboard.
5. The steel structure wallboard installation aid of claim 1, further comprising a strapping line for strapping the wallboard to the support side, wherein the support frame is provided with strapping holes for the strapping line to pass through to be located on both sides of the wallboard.
6. The steel structure wallboard installation aid of claim 1, wherein the support side is provided with a cushion pad supporting the wallboard.
7. The steel structure wallboard installation auxiliary device according to claim 6, wherein the supporting frame is a rectangular frame body, the supporting frame comprises supporting columns positioned at four corners, and adjacent supporting columns are connected through connecting rods.
8. The steel structure wallboard installation aid of claim 7, wherein the cushioning pad is a cushioning sleeve that fits over the support column.
9. The steel structure wallboard installation auxiliary device according to claim 7, wherein a middle space surrounded by the support column and the connecting rod is a climbing channel.
10. The steel structure wallboard installation aid of claim 9, wherein the links arranged up and down the support column form a climbing ladder of the climbing channel.
CN202321483716.2U 2023-06-12 2023-06-12 Steel construction wallboard installation auxiliary assembly Active CN219931660U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321483716.2U CN219931660U (en) 2023-06-12 2023-06-12 Steel construction wallboard installation auxiliary assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321483716.2U CN219931660U (en) 2023-06-12 2023-06-12 Steel construction wallboard installation auxiliary assembly

Publications (1)

Publication Number Publication Date
CN219931660U true CN219931660U (en) 2023-10-31

Family

ID=88503758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321483716.2U Active CN219931660U (en) 2023-06-12 2023-06-12 Steel construction wallboard installation auxiliary assembly

Country Status (1)

Country Link
CN (1) CN219931660U (en)

Similar Documents

Publication Publication Date Title
JP6893188B2 (en) Demolition system and demolition method of existing structures
JP6508958B2 (en) Demolition system and demolition method
KR100978170B1 (en) Integrated support for elevator machines, pulleys, and terminations
JP2018070362A (en) Elevator installation method
JP5300311B2 (en) Vertical pipe construction method and vertical pipe unit
JP2909413B2 (en) Suspension device for building exterior walls
JP2009121108A (en) Reinforcing bar assembly method and reinforcing bar assembly jig for reinforcing structure of high structure
CN219931660U (en) Steel construction wallboard installation auxiliary assembly
JP5421143B2 (en) Overhead crane installation equipment
JP6391134B2 (en) Dismantling method and dismantling system
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
CN112031370A (en) Ceiling installation equipment and construction method thereof
JPH09268778A (en) Dismantling method of water-containing gas holder and members used for the method
JP5245104B2 (en) Boiler scaffold and its construction method
CN212583152U (en) Suspended ceiling mounting equipment
JP6646220B2 (en) Construction method of suspended steel frame for suspended ceiling
JP3822084B2 (en) Construction lifting system for high-rise buildings
JP6508959B2 (en) Demolition system and demolition method
JP6084936B2 (en) Elevator installation apparatus and method of assembling the installation apparatus
JP5761595B2 (en) Module structure, module construction method
JP2023087141A (en) Curing system for building demolition and curing method for building demolition
JP2022101717A (en) Curing system in demolishing building, and demolition method of building to be demolished
JP3301923B2 (en) Elevator work scaffolding equipment
CN220888323U (en) Liftable formula steel bar binding platform for high mound of rectangle is applicable to
CN219219743U (en) Portable lifting attached scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant