CN218147843U - Construction system suitable for trestle - Google Patents
Construction system suitable for trestle Download PDFInfo
- Publication number
- CN218147843U CN218147843U CN202222476329.8U CN202222476329U CN218147843U CN 218147843 U CN218147843 U CN 218147843U CN 202222476329 U CN202222476329 U CN 202222476329U CN 218147843 U CN218147843 U CN 218147843U
- Authority
- CN
- China
- Prior art keywords
- truss
- pile
- construction
- tubular pile
- tubular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 80
- 238000007667 floating Methods 0.000 claims abstract description 44
- 238000005553 drilling Methods 0.000 claims abstract description 17
- 239000011435 rock Substances 0.000 claims abstract description 16
- 238000004873 anchoring Methods 0.000 claims description 14
- 238000000034 method Methods 0.000 description 22
- 229910000831 Steel Inorganic materials 0.000 description 15
- 239000010959 steel Substances 0.000 description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 14
- 230000008569 process Effects 0.000 description 9
- 238000009826 distribution Methods 0.000 description 8
- 238000005266 casting Methods 0.000 description 4
- 230000009471 action Effects 0.000 description 3
- 238000010009 beating Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 230000007246 mechanism Effects 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000010008 shearing Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000005188 flotation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 125000003003 spiro group Chemical group 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model relates to a construction system suitable for landing stage, it includes: floating equipment; the construction platform is supported on the floating transportation equipment and comprises a truss, and the truss is provided with a plurality of guide sleeves; the pile driving equipment is arranged on the construction platform, and when the tubular pile is inserted into the corresponding guide sleeve, the tubular pile is driven into a rock stratum by the pile driving equipment; the drilling device is arranged on the construction platform and is used for drilling the tubular pile to form a pouring channel; and the pouring device is arranged on the construction platform and is used for pouring concrete into the pouring channel to form an anchor pile buried in a rock stratum. The efficiency of positioning the tubular piles can be improved and the relative position accuracy between the tubular piles can be improved.
Description
Technical Field
The utility model relates to an interim mound construction field, in particular to construction system suitable for landing stage.
Background
At present, the trestle mainly comprises steel pipe columns, connecting beams, distribution beams and longitudinal beam panels. The steel pipe pile needs to be buried in a covering layer at the bottom of a water, a hole needs to be drilled in the steel pipe pile for the steel pipe pile without the covering layer area or the shallow covering layer area, and a concrete anchor pile is constructed to guarantee that the bearing capacity of a foundation meets the requirement.
In the related art, in order to accurately position the buried position of the steel pipe pile, a guide device is manufactured, the steel pipe pile is driven to a preset depth by a fishing method, and the steel pipe pile is drilled to construct an anchor pile after the connection system, the longitudinal beam and the distribution beam of the trestle are erected.
However, the "fishing method" requires hole-by-hole construction, requires separate positioning each time, and is complicated in positioning and low in positioning accuracy.
SUMMERY OF THE UTILITY MODEL
The embodiment of the utility model provides a construction system suitable for landing stage to need fix a position alone every steel-pipe pile in solving the correlation technique, fix a position the problem that complicated and positioning accuracy is low.
In a first aspect, a construction system suitable for a trestle is provided, which includes: floating equipment;
the construction platform is supported on the floating transportation equipment and comprises a truss, and the truss is provided with a plurality of guide sleeves;
the pile driving equipment is arranged on the construction platform, and when the tubular pile is inserted into the corresponding guide sleeve, the tubular pile is driven into a rock stratum by the pile driving equipment;
the drilling device is arranged on the construction platform and is used for drilling the tubular pile to form a pouring channel;
and the pouring device is arranged on the construction platform and is used for pouring concrete into the pouring channel to form an anchor pile buried in a rock stratum.
In some embodiments, the construction system further comprises:
and the lifting device is arranged on the tubular pile at the top of the anchor pile after the anchor pile is poured and formed, and is used for lifting the truss to a preset height to be fixedly connected with the tubular pile.
In some embodiments, each guide sleeve of the truss is correspondingly provided with a positioning clamping plate;
when the truss is lifted to the design height, the positioning clamping plates are arranged on the truss, and the truss and the tubular pile are locked by the positioning clamping plates.
In some embodiments, the construction platform includes a support plate mounted on the truss, and the support plate is removably mounted above the truss.
In some embodiments, the truss includes a transverse truss section extending in a transverse bridge direction, and the guide sleeve is provided at each of two ends of the transverse truss section.
In some embodiments, the truss further comprises longitudinal truss sheets extending along the longitudinal bridge direction, the longitudinal truss sheets and the transverse truss sheets are perpendicular to each other, the longitudinal truss sheets and the transverse truss sheets are alternately arranged to form a rectangular frame structure, and a guide sleeve is arranged at each of four top points of the rectangular frame structure.
In some embodiments, the transverse webs are shorter than the longitudinal webs.
In some embodiments, the rectangular frame structure has a connecting system therein, the connecting system being connected to both the transverse webs and the longitudinal webs.
In some embodiments, the floatation device is provided with an anchoring arrangement.
In some embodiments, the guide sleeve comprises a first sleeve and a second sleeve which are spaced up and down and are coaxially arranged.
In a second aspect, a construction method suitable for a trestle is provided, which includes the following steps: placing a truss on floating equipment, and floating and stopping the floating equipment to an erection area, wherein the truss is provided with a plurality of guide sleeves; the pipe pile penetrates through the guide sleeve and is buried in water in an erection area; the pile driving equipment drives the pipe pile into the rock stratum; the drilling device drills holes in the tubular pile to form a pouring channel; and pouring concrete into the pouring channel by using the pouring device to form an anchor pile buried in the rock stratum.
In some embodiments, said floating facility to an erection area comprises the steps of: setting a temporary fixing point on the floating transportation equipment, and installing the truss at the temporary fixing point; floating the floating equipment to the erection area, and adjusting the position of the floating equipment according to the designed pile position and the position of the guide sleeve; until the axis of the guide sleeve is coaxial with the designed pile position, the anchoring structure is anchored, and the floating equipment is anchored.
In some embodiments, after the casting device forms the anchor pile buried in the rock formation to the casting channel, the method further comprises the following steps: mounting a lifting device on the top of the tubular pile; the lifting device lifts the truss to the design height, positioning clamping plates are arranged at each guide sleeve of the truss, and the truss and the tubular pile are locked through the positioning clamping plates.
The utility model provides a beneficial effect that technical scheme brought includes:
the embodiment of the utility model provides a construction system suitable for landing stage, because, the truss has a plurality of guide sleeve pipes, can lead to a plurality of tubular piles simultaneously, and can guarantee the precision of the relative position between each tubular pile, only need can accomplish to the truss location at every turn and fix a position a plurality of tubular piles simultaneously, improved the efficiency of location, and improved the relative position precision between the tubular pile. Therefore, the position accuracy of the tubular pile can be improved, and the efficiency of tubular pile positioning is improved.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a top view of a construction system suitable for a trestle according to an embodiment of the present invention;
fig. 2 is a front view of a construction system suitable for a trestle according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of a floating construction platform of floating equipment according to an embodiment of the present invention;
fig. 4 is a schematic structural view of a construction system when the pipe pile is lifted by the lifting device provided by the embodiment of the utility model;
fig. 5 is a schematic structural view of a construction system when a drilling device provided by the embodiment of the present invention drills a tubular pile;
fig. 6 is a schematic structural diagram of a construction system for forming an anchor pile by pouring concrete according to an embodiment of the present invention;
fig. 7 is a schematic structural diagram of a construction system when a lifting device provided by an embodiment of the present invention lifts a truss;
fig. 8 is a schematic structural view of a construction system when a longitudinal beam is hoisted to the upper side of a tubular pile according to an embodiment of the present invention;
fig. 9 is a schematic top view of a truss provided in an embodiment of the present invention;
fig. 10 is a schematic front view of a truss provided in an embodiment of the present invention;
fig. 11 is a flowchart of a construction method according to an embodiment of the present invention;
FIG. 12 is a flowchart of step S1 in FIG. 11;
fig. 13 is a flowchart of another construction method according to an embodiment of the present invention.
In the figure:
1. a truss; 11. a guide sleeve; 111. a first sleeve; 112. a second sleeve; 12. a frame body; 121. a transverse truss panel; 122. a longitudinal truss web; 123. a connecting system;
2. floating equipment; 21. an anchoring structure;
3. a hoisting device;
4. a tubular pile;
5. a drilling device;
6. anchoring piles;
7. a support plate;
8. a lifting device;
9. positioning a clamping plate;
a. a stringer; b. a transverse distribution beam.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
The embodiment of the utility model provides a construction system suitable for landing stage, it can solve and need fix a position alone every steel-pipe pile among the correlation technique, fixes a position the problem that complicated and positioning accuracy is low.
Referring to fig. 1 to 10, for a construction system suitable for trestle that the embodiment of the present invention provides, it includes: a floating transport device 2; the construction platform is supported on the floating equipment 2 and comprises a truss 1, and the truss 1 is provided with a plurality of guide sleeves 11; the pile driving equipment is arranged on the construction platform, and after the tubular pile 4 is inserted into the corresponding guide sleeve 11, the tubular pile 4 is driven into a rock stratum by the pile driving equipment; the drilling device is arranged on the construction platform and is used for drilling the tubular pile 4 to form a pouring channel; and the pouring device is arranged on the construction platform and is used for pouring concrete into the pouring channel to form an anchor pile 6 buried in the rock stratum. That is to say, can realize the construction on water through setting up construction platform on floating equipment 2, set up a plurality of guide sleeve 11 through truss 1 of construction platform, can once satisfy the location installation of a plurality of tubular piles 4 through fixing a position truss 1. In this embodiment, the truss 1 is provided with four guide sleeves 11, and the positioning of the four-time tubular pile 4 can be satisfied by positioning the one-time truss 1. Meanwhile, as the tubular piles 4 penetrate through the guide sleeves 11, the truss 1 can ensure the precision of the relative positions of the four guide sleeves 11 connected with the truss, namely the position precision between the tubular piles 4 penetrating through the four guide sleeves 11 is ensured, and the overlarge relative position error between the tubular piles 4 caused by repeated positioning is avoided. Compared with the method of ensuring the relative position precision between the tubular piles 4 by positioning for many times in water, the truss 1 can be manufactured on land, so that the relative position precision between the guide sleeves 11 can be better ensured. That is, the number of times of positioning is reduced and the efficiency of construction is improved by the truss 1. And meanwhile, the relative position precision between the tubular piles 4 can be improved. After each tubular pile 4 is positioned, the tubular piles 4 are driven into the rock strata through pile driving equipment arranged on the construction platform, wherein the adjacent tubular piles 4 can be connected into a whole by utilizing the truss 1 due to the fact that the truss 1 is provided with the plurality of guide sleeves 11. Tubular pile 4 only leads through guide structure among the correlation technique, and each tubular pile 4 is independent with other tubular piles 4, can receive rivers lateral force when tubular pile 4 is inserting and beating the in-process, still can lead to tubular pile 4 to take place to deflect because the lateral force of rivers when serious, and the rework seriously drags the construction progress slowly. In this embodiment, the tubular piles 4 passing through different guide sleeves 11 on the same truss 1 can form a whole, so that the single tubular pile 4 is prevented from toppling due to the lateral force of water flow. The inserting and beating precision of the tubular pile 4 is improved. After the tubular pile 4 is inserted and beaten, a hole is drilled in the tubular pile 4 through a drilling device arranged on the construction platform to form a pouring channel, and then concrete is poured into the pouring channel by using the pouring device arranged on the construction platform to form an anchor pile 6 buried in a rock stratum. The positioning and anchoring of the tubular pile 4 are realized. Wherein truss 1 not only can play the location of supplementary tubular pile 4, connects adjacent tubular pile 4 and forms the effect of a whole resistance rivers lateral force. The truss 1 can also support a pile driving device, a drilling device and a pouring device above the truss to be constructed on water in the construction process. In the embodiment, the truss 1 is formed by assembling and welding profile steels, so that the cost is low.
Referring to fig. 7 and 8, in some alternative embodiments, the construction system further includes: and the lifting device 8 is arranged on the tubular pile 4 at the top of the anchor pile 6 after the anchor pile 6 is poured and formed, and the lifting device 8 is used for lifting the truss 1 to a preset height to be fixedly connected with the tubular pile 4. That is to say, truss 1 not only is used for leading tubular pile 4, can play the effect of contacting adjacent tubular pile 4 with tubular pile 4 fixed connection after tubular pile 4 construction is accomplished simultaneously, improves the stability of landing stage. In this embodiment, to the guide structure of tubular pile 4 and the strengthening mechanism between tubular pile 4 combine together, reduced construction cost, and improved the efficiency of construction, need not demolish guide structure after guide structure uses the completion, will connect the roof beam floating again to tubular pile 4 department construction. The truss 1 can be directly lifted and fixedly connected with the tubular pile 4, so that the step of removing a guide mechanism is omitted, and the step of transporting and positioning the connecting beam is simplified. In this embodiment, hoisting device 8 comprises crossbeam, steel strand wires and hydraulic jack, and during the construction, the crossbeam is arranged in the top of tubular pile 4, and hydraulic jack sets up in the top of crossbeam, and the anchor point on truss 1 is passed to one end of the steel strand wires, and the anchor point of hydraulic jack is passed to another end of the steel strand wires. The truss 1 is lifted by continuously retracting the steel strands through a hydraulic jack, and as shown in the figure, at least two anchoring points are arranged on the truss 1 so as to prevent the truss 1 from deflecting in the lifting process. In this embodiment, because truss 1 is the rectangle structure, respectively be equipped with an anchor point at four apex points of truss 1, guarantee the steady of lift process.
Referring to fig. 5 to 10, in some alternative embodiments, a positioning clamping plate 9 is correspondingly arranged at each guide sleeve 11 of the truss 1; when the truss 1 is lifted to the design height, the positioning clamping plates 9 are arranged on the truss 1, and the truss 1 and the tubular pile 4 are locked by the positioning clamping plates 9. That is, the truss 1 is locked on the pipe pile 4 through the positioning clamping plate 9. In this embodiment, the positioning clamping plate is a square plate cut from a steel plate. Comparing fig. 5 with fig. 6, can insert at tubular pile 4 and beat the back, to fixed positioning cardboard 9 on tubular pile 4 again, can enclose into a spacing space through upper and lower spaced positioning cardboard 9, make truss 1 support on positioning cardboard 9, can not limit truss 1 in positioning cardboard 9 fixed connection this moment, only through the position of positioning cardboard 9's holding power restriction truss 1. Comparing fig. 7 and fig. 8, when the truss 1 needs to be lifted, the positioning clamping plate 9 on the tubular pile 4 is removed, the positioning clamping plate 9 is installed on the tubular pile 4 after the truss 1 is lifted to a preset height, the positioning clamping plate 9 is fixedly connected with the truss 1, the truss 1 and the tubular pile 4 connected with the truss 1 form a whole, the truss 1 can transmit horizontal force between the tubular piles 4, and the stability of the trestle is improved. In this embodiment, truss 1 and tubular pile 4 all link to each other with location cardboard 9 through the welding, in other embodiments, also can be connected truss 1, tubular pile 4 and location cardboard 9 through the mode of spiro union.
In this embodiment, every tubular pile 4 all is connected with four layers of location cardboard 9, and four layers of location cardboard 9 enclose mutually and form two spacing spaces, and the spacing space on upper strata is used for restricting first sleeve 111, and the spacing space on lower floor is used for restricting second sleeve 112. The positioning clamping plates 9 of each layer are fixedly connected with the tubular piles 4 at even intervals along the circumferential direction of the tubular piles 4. More secure than a single point fixation.
Referring to fig. 3 to 7, in some alternative embodiments, the construction platform includes a support plate 7 mounted on the girder 1, and the support plate 7 is detachably mounted above the girder 1. That is to say, realize the installation to pile equipment, drilling equipment and pouring device through the backup pad 7 that sets up on truss 1, through the detachable connected mode, can dismantle after the use is accomplished in order to the switching of construction next time, reduced the cost of construction. In this embodiment, the truss 1 is a frame structure, and the supporting plate 7 is disposed on the truss 1, so that the related device can be better supported on the construction platform, and the related device is prevented from sinking into the hole of the truss 1. In this embodiment, the supporting plate 7 is a plate-shaped structure composed of a section steel, a steel plate, and a bailey beam, and a temporary locking mechanism is provided between the supporting plate 7 and the truss 1 to improve the stability of the supporting plate 7.
Referring to fig. 9, in some alternative embodiments, the truss 1 includes a transverse truss blade 121 extending along the transverse bridge direction, and both ends of the transverse truss blade 121 are provided with one of the guide sleeves 11.
That is to say, be equipped with two guide sleeve 11 along horizontal direction of the bridge arrangement on truss 1, it can realize that tubular pile 4 along horizontal direction of the bridge arrangement, tubular pile 4 at horizontal direction of the bridge interval arrangement can satisfy the installation of horizontal distribution roof beam b. In the erection process, the transverse distribution beam b can be supported above the two tubular piles 4, so that the risk of toppling over of the transverse distribution beam b is reduced. The stability of the bridge is improved. The longitudinal beam a is supported by the transverse distribution beam b, the distance between the centers of the two guide sleeves 11 connected by the transverse truss sheets 121 in the embodiment is larger than the width of the longitudinal beam a, and the transverse distribution beam b can extend out of two sides of the longitudinal beam a in the transverse bridge direction in the erection process, so that better support is provided for the longitudinal beam a.
Referring to fig. 9, in some alternative embodiments, the truss 1 further includes a longitudinal truss piece 122 extending along the longitudinal bridge direction, the longitudinal truss piece 122 and the transverse truss piece 121 are perpendicular to each other, the longitudinal truss piece 122 and the transverse truss piece 121 are alternately arranged to form a rectangular frame structure, and a guide sleeve 11 is disposed at each of four vertices of the rectangular frame structure. When a truss 1 is positioned, the positioning of four tubular piles 4 can be simultaneously met, and lateral forces in the longitudinal bridge direction and the transverse bridge direction can be transmitted between the tubular piles 4. The performance of resisting the lateral force of the water flow of the tubular pile 4 is improved.
Referring to fig. 9 and 10, the transverse webs 121 are shorter than the longitudinal webs 122. That is, the longitudinal girder pieces 122 are longer than the transverse girder pieces 121, so that the interval between the tubular piles 4 in the longitudinal direction can be made larger than the interval between the tubular piles 4 in the transverse direction. The tubular piles 4 which can be connected to the same truss 1 are spaced longer at the pivot points in the longitudinal bridge direction, so that better support is provided for the longitudinal beams a.
Referring to fig. 9, in some alternative embodiments, the rectangular frame structure is provided with connecting links 123, and the connecting links 123 are connected to both the transverse webs 121 and the longitudinal webs 122. That is, the rectangular frame structure is reinforced by the connection system 123. The load-bearing capacity of the truss 1 is improved. In this embodiment, the connection system 123 is connected with the rectangular frame structure to form a plurality of triangular structures, so as to reduce the deformation risk of the truss 1 under stress.
Referring to figure 3, in some alternative embodiments, the flotation device 2 is provided with an anchoring structure 21. In this embodiment, a barge is used as the floating equipment 2, the truss 1 is floated to the erection area by the floating equipment 2, the anchoring structure 21 is thrown into the water after the guide sleeve 11 is accurately positioned, and the floating equipment 2 is prevented from drifting away in the erection process by the anchoring structure 21. In this embodiment, a temporary support fixing point is provided on the floating device 2 to prevent the truss 1 from moving relative to the floating device 2.
Referring to fig. 9 and 10, in some alternative embodiments, the guide sleeve 11 includes a first sleeve 111 and a second sleeve 112 spaced apart from each other and coaxially disposed. That is, the first sleeve 111 and the second sleeve 112 are used to position the same tubular pile 4 twice, so that the positioning accuracy of the tubular pile 4 is improved.
Referring to fig. 1 to 11, an embodiment of the present invention further provides a construction method, which includes the following steps:
s1, placing a truss 1 on floating equipment 2, and floating and stopping the floating equipment 2 to an erection area, wherein the truss 1 is provided with a plurality of guide sleeves 11;
s2, the tubular pile 4 penetrates through the guide sleeve 11 and is buried in water in an erection area;
s3, driving the pipe pile 4 into the rock stratum by using pile driving equipment;
s4, drilling holes in the tubular pile 4 by using a drilling device to form a pouring channel;
and S5, pouring concrete into the pouring channel by using the pouring device to form an anchor pile 6 buried in the rock stratum.
Through a plurality of guide sleeve 11 that set up on truss 1, can satisfy the location of a plurality of tubular piles 4 simultaneously when fixing a position truss 1, compare and fix a position 4 alone to tubular pile, improved the efficiency of fixing a position 4 to tubular pile. And construction platform can provide the support for pile equipment, drilling equipment and pouring device, compares the degree of difficulty that has reduced the construction on water. In this embodiment, the truss 1 can be manufactured in a factory, and compared with the independent positioning on water, the relative position accuracy between the pipe piles 4 can be better ensured. In this embodiment, the tubular pile 4 is hoisted by the hoisting device 3 to pass through the guide sleeve 11. Adjacent tube piles 4 may be connected to form a whole by using the truss 1. Tubular pile 4 only leads through guide structure among the correlation technique, and each tubular pile 4 is independent with other tubular piles 4, can receive rivers lateral force when tubular pile 4 is inserting and is beaten the in-process, still can lead to tubular pile 4 to take place to deflect because the lateral force of rivers when serious, and the rework is serious drags the construction progress slowly. In this embodiment, the tubular piles 4 passing through different guide sleeves 11 on the same truss 1 can form a whole, so that the single tubular pile 4 is prevented from toppling due to the lateral force of water flow. The inserting and beating precision of the tubular pile 4 is improved.
Referring to fig. 12, preferably, the step S1 of floating the floating facility 2 to the erection space includes the steps of:
s101, arranging a temporary fixing point on floating equipment 2, and installing the truss 1 at the temporary fixing point;
s102, floating the floating equipment 2 to the erection area, and adjusting the position of the floating equipment 2 according to the designed pile position and the position of the guide sleeve 11;
and S103, anchoring the anchoring structure 21 until the axis of the guide sleeve 11 is coaxial with the designed pile position, and anchoring the floating equipment 2. That is, the girder 1 and the floating facility 2 are temporarily fixed to prevent the girder 1 from being deflected after being positioned. When the floating equipment 2 is transported to the erection area in a floating mode, the position of the floating equipment 2 is adjusted according to the designed pile position and the position of the guide sleeve 11, and after the position is adjusted, the floating equipment 2 is anchored by the anchoring structure 21.
Referring to fig. 13, in some alternative embodiments, after the step S5, that is, after the casting device forms the anchor pile 6 buried in the rock formation to the casting channel, the following steps are further included:
mounting a lifting device on the top of the tubular pile 4;
the lifting device 8 lifts the truss 1 to the designed height, a positioning clamping plate 9 is arranged at each guide sleeve 11 of the truss 1, and the truss 1 and the tubular pile 4 are locked through the positioning clamping plates 9. That is, after the pipe piles 4 are positioned and grouted to form the anchor piles 6, the girder 1 is not removed. The truss 1 can be lifted to a preset height to be fixedly connected with the tubular piles 4, force transmission between the tubular piles 4 can be achieved through the truss 1, and stability between the tubular piles 4 is improved. Also can set up location cardboard 9 before promoting truss 1 on tubular pile 4, form spacing space support truss 1 through location cardboard 9, avoid truss 1 to remove 4 relative tubular piles, promote preceding truss 1 can only support on location cardboard 9 and not weld with location cardboard 9. When the truss 1 needs to be lifted, the positioning clamping plates 9 are firstly detached from the tubular piles 4. After the truss 1 is lifted, one side of the positioning clamping plate 9 is welded on the tubular pile 4, and the other side of the positioning clamping plate is welded on the guide sleeve 11. Truss 1 not only receives the holding power of location cardboard 9, when tubular pile 4 received the yawing force, truss 1 can receive the shearing force under the effect of location cardboard 9 to the shearing force can be transmitted to other tubular piles 4 that link to each other with same truss through truss 1 on, improves holistic anti yawing force ability through the pre-buried power of other tubular piles 4.
The embodiment of the utility model provides a principle of construction system suitable for landing stage does:
set up a plurality of guide sleeve 11 through truss 1, after fixing a position truss 1, can guarantee that the location of a plurality of guide sleeve 11 is accurate, reduced the number of times of location on water, improved the efficiency of construction, reduced the degree of difficulty of location on water. And the truss 1 is connected with a plurality of guide sleeves 11, so that the relative position precision between the tubular piles 4 connected with the same truss 1 can be ensured. And the truss 1 is supported on the floating transportation equipment 2, so that an overwater construction platform can be provided for related construction equipment while positioning is provided, and the construction difficulty is reduced.
In the description of the present invention, it should be noted that the terms "upper", "lower", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention. Unless expressly stated or limited otherwise, the terms "mounted," "connected," and "coupled" are to be construed broadly and encompass, for example, both fixed and removable coupling as well as integral coupling; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
It is noted that, in the present invention, relational terms such as "first" and "second", and the like, may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrases "comprising a," "8230," "8230," or "comprising" does not exclude the presence of additional like elements in a process, method, article, or apparatus that comprises the element.
The above description is merely illustrative of the invention and is provided to enable any person skilled in the art to make or use the invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims (10)
1. The utility model provides a construction system suitable for landing stage which characterized in that, it includes:
a floating device (2);
the construction platform is supported on the floating transportation equipment (2), and comprises a truss (1), and the truss (1) is provided with a plurality of guide sleeves (11);
the pile driving equipment is arranged on the construction platform, and when the tubular pile (4) is inserted into the corresponding guide sleeve (11), the tubular pile (4) is driven into a rock stratum by the pile driving equipment;
the drilling device is arranged on the construction platform and is used for drilling the tubular pile (4) to form a pouring channel;
and the pouring device is arranged on the construction platform and is used for pouring concrete into the pouring channel to form an anchor pile (6) buried in the rock stratum.
2. The construction system according to claim 1, wherein:
the construction system further includes:
lifting device (8), work as anchor pile (6) are pour and are formed the back, lifting device (8) install in anchor pile (6) top on tubular pile (4), lifting device (8) be used for with truss (1) promote to predetermine the height with tubular pile (4) fixed connection.
3. The construction system according to claim 2, wherein:
each guide sleeve (11) of the truss (1) is correspondingly provided with a positioning clamping plate (9);
when the truss (1) is lifted to the design height, the positioning clamping plates (9) are arranged on the truss (1), and the truss (1) and the tubular pile (4) are locked by the positioning clamping plates (9).
4. The construction system according to claim 1, wherein:
the construction platform comprises a supporting plate (7) installed on the truss (1), and the supporting plate (7) is detachably installed above the truss (1).
5. The construction system of claim 1, wherein:
the truss (1) comprises a transverse truss sheet (121) extending along the transverse bridge direction, and two ends of the transverse truss sheet (121) are provided with the guide sleeves (11).
6. The construction system of claim 5, wherein:
the truss (1) further comprises longitudinal truss sheets (122) extending along the longitudinal bridge direction, the longitudinal truss sheets (122) and the transverse truss sheets (121) are vertical to each other, the longitudinal truss sheets (122) and the transverse truss sheets (121) are alternately arranged to form a rectangular frame structure, and one guide sleeve (11) is arranged at each of four top points of the rectangular frame structure.
7. The construction system of claim 6, wherein:
the transverse webs (121) are shorter than the longitudinal webs (122).
8. The construction system of claim 6, wherein:
a connecting system (123) is arranged in the rectangular frame structure, and the connecting system (123) is connected with the transverse truss sheets (121) and the longitudinal truss sheets (122) at the same time.
9. The construction system according to claim 1, wherein:
the floating transportation equipment (2) is provided with an anchoring structure (21).
10. The construction system of claim 1, wherein:
the guide sleeve (11) comprises a first sleeve (111) and a second sleeve (112) which are arranged at intervals up and down and coaxially.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222476329.8U CN218147843U (en) | 2022-09-19 | 2022-09-19 | Construction system suitable for trestle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222476329.8U CN218147843U (en) | 2022-09-19 | 2022-09-19 | Construction system suitable for trestle |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218147843U true CN218147843U (en) | 2022-12-27 |
Family
ID=84563430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222476329.8U Active CN218147843U (en) | 2022-09-19 | 2022-09-19 | Construction system suitable for trestle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218147843U (en) |
-
2022
- 2022-09-19 CN CN202222476329.8U patent/CN218147843U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111305066A (en) | Hybrid combination beam steel-concrete combination section and mounting method thereof | |
CN113403965A (en) | Positioning guide frame for steel trestle steel pipe pile construction and construction method | |
CN109653101B (en) | Method for erecting trestle for bridge construction | |
CN115491986A (en) | Construction system suitable for trestle and construction method thereof | |
CN112195779A (en) | Multifunctional trestle construction method suitable for thick pebble layer | |
CN114000459B (en) | Method for erecting platform for high-pile wharf cast-in-place pile construction | |
CN215715233U (en) | Set up steel-pipe pile landing stage of concrete anchor pile | |
JP2004285735A (en) | Method of constructing temporary landing bridge by using truss frame | |
CN218147843U (en) | Construction system suitable for trestle | |
CN212426749U (en) | Hybrid reinforced concrete joint section | |
CN117779763A (en) | Construction platform and construction method for supporting piles of large-span trestle | |
CN110924312A (en) | Construction method of steel trestle | |
CN211340426U (en) | Main bridge water mound construction platform structure | |
CN215051970U (en) | Steel trestle structure of deep water bare rock stratum river channel | |
CN213507989U (en) | Deepwater steel trestle capable of being constructed quickly | |
CN115387207A (en) | Shallow covering layer steel-concrete composite pile pier structure and construction method | |
CN210134451U (en) | Steel-pipe pile basis of aquatic tower crane | |
CN115354579A (en) | Prefabricated pile foundation construction platform and pile foundation construction method | |
CN218712227U (en) | Girder steel landing stage that slides | |
CN218027576U (en) | Drilling platform for deep-water shallow-covering-layer riverbed | |
CN113969540B (en) | Construction temporary trestle and construction method thereof | |
CN219010981U (en) | Cast-in-situ beam bearing support device | |
CN115506324A (en) | Drilling platform for deep-water shallow-covering-layer riverbed and construction method thereof | |
CN221798120U (en) | Bridge body of pilot hole lifting trestle and pilot hole lifting trestle | |
CN222275228U (en) | Overwater trestle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |