[go: up one dir, main page]

CN217759930U - Wind-proof vibration-proof hanging basket - Google Patents

Wind-proof vibration-proof hanging basket Download PDF

Info

Publication number
CN217759930U
CN217759930U CN202221467238.1U CN202221467238U CN217759930U CN 217759930 U CN217759930 U CN 217759930U CN 202221467238 U CN202221467238 U CN 202221467238U CN 217759930 U CN217759930 U CN 217759930U
Authority
CN
China
Prior art keywords
hanging basket
basket body
connecting plate
building
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221467238.1U
Other languages
Chinese (zh)
Inventor
龙进松
陈涛
唐勇超
王家杰
陈果
王蛟
毛卫东
吴耀勇
夏锦
曹垠
谭政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Original Assignee
Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd filed Critical Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Priority to CN202221467238.1U priority Critical patent/CN217759930U/en
Application granted granted Critical
Publication of CN217759930U publication Critical patent/CN217759930U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a building engineering high altitude construction equipment technical field, especially a prevent wind hanging flower basket that shakes. Contain hanging flower basket body, hoist cable and stop device, stop device connect in the building of hanging flower basket body side, stop device follows the axial interval distribution of hoist cable, stop device is used for the restriction the hoist cable horizontal direction rocks, stop device can retrieve in the building of hanging flower basket body side. When the hanging basket is constructed, one end of a sling is connected with the hanging basket body, and the other end of the sling is connected with a hanging point and hung on a building on the side of the hanging basket body; limiting devices are distributed between the hoisting point and the hanging basket body at intervals along the axial direction of the sling, so that the sling is limited to shake in the horizontal direction of the point; the swayable length of the whole sling is shortened, the hanging basket body is prevented from swaying violently when the wind load is large, the stability of the hanging basket body is improved, and the construction efficiency and the construction safety are guaranteed; when the hanging basket body needs to be lifted, the limiting device which influences the lifting of the hanging basket body is retracted into the building.

Description

Wind-proof hanging basket
Technical Field
The utility model relates to a building engineering high altitude construction equipment technical field, especially a prevent wind hanging flower basket that shakes.
Background
The hanging basket is high-altitude operation equipment which can replace a traditional scaffold, reduce labor intensity, improve working efficiency and be reused. At present, the use of the construction hanging basket gradually becomes a trend, and the construction hanging basket is widely accepted in high-altitude operations such as outer wall construction of high-rise buildings, curtain wall installation, heat insulation construction, maintenance and cleaning of outer walls and the like. Use the construction hanging flower basket, can exempt from to take the scaffold frame, make construction cost greatly reduced, the operating expenses is only 28% of traditional scaffold frame, and work efficiency improves by a wide margin moreover.
However, in practical use, particularly in high-rise building construction, since the hanging point of the hanging basket is usually arranged on the roof and suspended in the air by the sling, when the hanging basket meets strong wind weather, the hanging basket can seriously shake in the high air due to the long shaking distance between the hanging basket and the hanging point. This not only can influence constructor's work efficiency, still can threaten constructor's personal safety.
SUMMERY OF THE UTILITY MODEL
The invention of the utility model aims to: the wind-proof hanging basket aims at the problems that when the hanging basket is constructed in a high-rise building, due to the fact that a sling can shake for a long distance, the hanging basket is prone to being blown by wind to shake in the high altitude, construction operation efficiency is affected, and potential safety hazards exist.
In order to realize the purpose, the utility model discloses a technical scheme be:
the utility model provides a prevent wind hanging flower basket that shakes, contain the hanging flower basket body and connect in the hoist cable of hanging flower basket body both sides still contains stop device, stop device connect in the building of hanging flower basket body side, stop device follows the axial interval distribution of hoist cable, stop device is used for the restriction the hoist cable horizontal direction rocks, stop device can retrieve in corresponding building.
The limiting device is connected to a building on the side edge of the hanging basket body, and optionally, the limiting device can be directly connected or indirectly connected with the hanging basket body;
the limiting devices are distributed at intervals along the axial direction of the sling and are connected at different heights/different layers of the building; the specific spacing distance is adjusted according to the wind load intensity of the actual use scene, and is not particularly limited;
the limiting device is used for limiting the horizontal shaking of the sling, and conventionally, the requirement of shaking prevention far away from the building vertical surface is low mainly aiming at the transverse shaking of the sling along the side building vertical surface and the shaking close to the building vertical surface; in particular, some use scenarios, for example: when the wind load is large, the limiting device is limited in all horizontal directions as much as possible. To sum up, it is different according to the in-service use scene, choose for use different stop device, for example: a groove, a movable buckle and the like.
Stop device can retrieve in the building of hanging flower basket body side, and stop device need contact hoist cable when being used for spacingly, when the hanging flower basket body has the demand of vertical reciprocating, in order to avoid taking place to interfere, needs stop device can retrieve to the building of hanging flower basket body side. There are various implementations here, for example: the whole translation retraction, the rotation retraction or the telescopic retraction and the like.
When the hanging basket is constructed, one end of a sling is connected with the hanging basket body, and the other end of the sling is connected with a hanging point and hung on a building on the side of the hanging basket body; the limiting devices distributed at intervals between the lifting point and the hanging basket body along the axial direction of the sling can limit the horizontal swinging of the sling at the point; the swayable length of the whole sling is shortened, the hanging basket body is prevented from swaying violently when the wind load is large, the stability of the hanging basket body is improved, and the construction efficiency and the construction safety are guaranteed; when needs promote the hanging flower basket body, will influence in its stop device who lifts withdraws the building, stop device can not block the rebound of hanging flower basket body to when guaranteeing to rock spacingly to the hoist cable, do not influence the normal use of hanging flower basket body.
As the utility model discloses an optimal scheme still contains connecting plate, support, stop device passes through leg joint the connecting plate can and then connect on corresponding building, the connection can be dismantled on corresponding building interior floor to the connecting plate, the support with stop device can retrieve in the building that corresponds.
Considering the requirement that the limiting device is retracted into a building, the limiting device is preferably indirectly connected to a floor slab in the building through a connecting plate, and the limiting device is connected to a support and can be integrally designed; compared with the limit device which is directly connected to the building, the limit device is more convenient to withdraw;
the connecting plates are detachably connected in the corresponding buildings and can be detached after construction, and subsequent use of the buildings is not influenced; the connecting plate is connected in a building, so that the connecting plate can be more safely installed and disassembled by constructors;
the support and the limiting device can be retracted into the corresponding building, the support and the limiting device can be translated on the connecting plate as a whole to be retracted into the building, or the support can rotate relative to the connecting plate, so that the limiting device is driven to be retracted into the building as a whole, or the end of the support connected with the limiting device is telescopic, and the retraction drives the limiting device to be retracted into the building.
On the basis, the shape of the connecting plate is not required, and the connecting plate can be fixed on a building and connected with the building and the bracket; similarly, no special requirements are made on the shape of the bracket; preferably, stop device connects in support one end, makes things convenient for the support to withdraw when removing, and the support does not take place to interfere with the hoist cable, and the support stretches out building length this moment and is confirmed by hoist cable apart from building distance.
As the utility model discloses a preferred scheme, the support pass through slewing mechanism connect in the connecting plate, be connected with on the connecting plate and be used for the restriction pivoted mounting when the support uses.
Because the connecting plate is connected on the high-rise building floor, the conventional hanging basket body is also large in size, and the length of the support extending out of the floor is long. For example, the support needs to extend out of a floor slab by 80cm, which is determined by the distance between a sling and a building in specific implementation, and the support is retractable and integrally moved and detached, so that the structure is complex and the operation consumes a long time. Therefore, the preferred support moving mode is selected to be rotatable, the connecting plate comprises a rotating mechanism, and the support rotates through the rotating mechanism. Constructors can withdraw the support only by rotating the support in the building.
The fixing piece is additionally arranged, so that the limiting device is prevented from rotating when the sling is limited to swing. For example: the bracket can horizontally rotate, the two horizontal sides of the position where the bracket is located when the limiting device is used for limiting are respectively provided with a detachable upright post as a fixing piece, and the two upright posts limit the bracket to horizontally rotate when in use; the support can vertical rotation, can be in the position detachable of above-mentioned two stands bit in the support top couple together, takes place vertical rotation when restricting the support use.
As the preferred scheme of the utility model, the support can vertical rotation.
Considering from conventional horizontal rotation and vertical rotation, if horizontal rotation is selected, the horizontal rotation has higher requirement on the horizontal size of the building due to the longer length of the bracket; and stop device will be spacing to hoist cable level, and support horizontal rotation is higher to stop device structural requirement, for example: when the slipknot is used as a limiting device, the opening and closing angle of the slipknot is required to be larger in order to horizontally rotate.
And choose the vertical rotation of support for use, the building floor height can satisfy the rotatory demand of support, requires lower to stop device moreover to foretell slipknot example, only need open less angle, the support can rotate.
As the preferred proposal of the utility model, the bracket can rotate 0 to 180 degrees.
The support can rotate 180, compare in other angles, and the support can directly rotate inside the building this moment to paste connecting plate or floor. The stress concentration of the support rotation connecting point is avoided, the support is retracted to the tight connecting plate, and constructors are not easy to touch and are safer.
As the preferred scheme of the utility model, the connecting plate marginal distance corresponds the outer facade of building at least 20cm.
The distance between the edges of the connecting plates and the corresponding building outer vertical surfaces is at least 20cm, so that constructors are far away from the edges of the building when mounting and dismounting the connecting plates, and the building is safer.
As the preferred scheme of the utility model, each the connecting plate is connected at least one the support.
For example: when the hanging basket body uses two slings, two limiting devices are correspondingly arranged, two supports are correspondingly arranged, a connecting plate is correspondingly arranged, the two supports are connected to the connecting plate, and the distance between the two supports is determined according to the distance between the two slings. Can be used as a whole, is more convenient to move, disassemble, connect and position, and is suitable for the use scene of the specification determination of the hanging basket body. Obviously, if a single connecting plate corresponds to a single bracket, the advantage of flexibly adjusting the distance according to different basket specifications is achieved. Can be specifically adjusted according to the use scene. It should be apparent that the above examples are only for explaining the case that the connecting plate connects a plurality of brackets, and are not used for limiting the number of the slings and the limiting devices to be in one-to-one correspondence, nor limiting the number of the limiting devices and the brackets to be in one-to-one correspondence.
As the preferred scheme of the utility model, the support is shaped steel, the connecting plate is galvanized steel sheet.
The bracket and the connecting plate are made of common materials, are convenient to process and manufacture and have good mechanical properties.
As the preferred scheme of the utility model, stop device is the slipknot, the slipknot contains locking device.
Here, the slipknot means an opening and closing gripper; when the limiting device is a slipknot, preferably, the shape of the slipknot is matched with that of the sling, and the slipknot can limit the sling in all horizontal directions and can complete fixed-point limiting of the sling; preferably, the slipknot contains locking device, and when fixed hoist cable, the locking slipknot prevents that under the wind-force effect, the hoist cable takes off from the slipknot outward, causes spacing inefficacy.
As the preferred scheme of the utility model, the limiting device is arranged at every 2-3 layers corresponding to the building.
The limiting device is arranged on the corresponding building every 2-3 layers, so that the limiting device can limit the swinging of a sling when the limiting device is used, and each layer of the hanging basket needs to be retracted by constructors when the hanging basket is lifted.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that: when the construction hanging basket is used, the position of the sling is limited by using the device, so that the swayable length of the sling is shortened, the hanging basket is prevented from swaying greatly under wind load, the stability of the hanging basket in implementation is improved, and the construction efficiency and the construction safety are guaranteed; furthermore, the support can be moved back, upward lifting of the hanging basket in use is not influenced, and the applicability is stronger; the paint can be disassembled after use, and subsequent construction is not affected; simple structure, easy to assemble and remove.
Drawings
Fig. 1 is a schematic structural diagram of a wind vibration prevention hanging basket according to embodiment 1 of the present invention.
Fig. 2 is a schematic partial structural diagram a of a wind vibration prevention hanging basket according to embodiment 1 of the present invention.
Fig. 3 is a schematic structural diagram of a wind vibration prevention hanging basket according to embodiment 2 of the present invention.
Fig. 4 is a schematic partial structural diagram b of a wind vibration prevention hanging basket according to embodiment 2 of the present invention.
Fig. 5 is a schematic partial structural diagram c of a wind vibration prevention hanging basket according to embodiment 2 of the present invention.
The mark in the figure is: 1-hanging basket body, 2-sling, 3-support, 4-connecting plate, 5-limiting device, 6-common bolt, 7-fixing piece, 8-rotating mechanism, 9-fixing device and 31-telescopic node.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Example 1
As shown in fig. 1 and 2, the wind vibration prevention hanging basket comprises a hanging basket body 1, a sling 2, a support 3, a connecting plate 4, a limiting device 5, a fixing device 9 and a telescopic node 31.
The connecting plate 4 is a galvanized steel plate, the fixing device 9 is an expansion bolt, and as shown in fig. 1, the connecting plate 4 is fixedly connected to the floor slab through the fixing device 9. It is obvious that the common material of the connecting plate 4 and the fixing means 9 are only shown by way of example and are not particularly limited.
In the embodiment, on the building of the side edge of the hanging basket body 1, every 3 layers are provided with connecting plates 4, and the limiting devices 5 correspondingly realize multipoint control on the axial direction of the sling 2; here, only by way of example, a conventional building has a height of about 3m, and thus, in this embodiment, a space of 9m can satisfy a conventional use scenario. If aiming at the condition that the floor height is higher and/or the wind load is larger, more limiting devices 5 are arranged, and the actual requirements can be flexibly set.
The shape of the connecting plate 4 in this embodiment is rectangular, and is not particularly limited, and may alternatively be circular, trapezoidal, etc., as long as it can be fixed to a building and connected to the bracket 3; each connecting plate 4 is correspondingly provided with four expansion bolts, so that the expansion bolts can be uniformly, stably and detachably fixed on a building; the fixed position is on the floor in the building, apart from building outward flange 30cm, and constructor can install in the building, fixed connection board 4 and adjust telescopic bracket 3, and this numerical value is the realization show of this embodiment only, does not do specific restriction.
Support 3 is connected on connecting plate 4, and in this embodiment, support 3 contains flexible node 31, and support 3 is scalable, realizes through the shrink of support 3 that hanging flower basket body 1 does not take place to interfere when lifting upward, hanging flower basket body 1 and support 3.
It is obvious that in this embodiment, the contact portions of the bracket 3 and the connecting plate 4 can be fixedly connected.
The top of the movable end of the bracket 3 comprises a limiting device 5, as shown in the partial schematic view a of fig. 2, in this embodiment, the limiting device 5 is a groove. The width of the groove is 5mm larger than the diameter of the sling 2, so that the horizontal swinging of the sling 2 can be limited, and the sling 2 can move up and down in the groove when the hanging basket body 1 moves up and down. This value is only an exemplary demonstration that the groove depth can effectively limit the sway of the sling 2 and the up-and-down movement of the sling 2 in the groove, and is not a specific limitation. Can be determined according to the diameter of the sling 2 in actual use and the anti-shaking requirement.
In some embodiments, the recess is fixed with the bracket 3; alternatively, the recess is integral with the bracket 3.
In some embodiments, the stop device 5 may also be a snap or other structure. For example: the limiting devices 5 are two vertical plates which can move along the end parts of the supports 3, the two plates and the supports 3 jointly form a groove for limiting the sling 2, and the distance between the two plates is adjusted for limiting the slings 2 with different specifications; furthermore, the two plates can be fixed, and the sling 2 is prevented from moving when being limited.
As another embodiment, the position-limiting device 5, the bracket 3 and the connecting plate 4 are integrally arranged, that is, the position-limiting device 5 is directly connected to the building, and at this time, the retraction of the position-limiting device 5 can also be completed by integrally disassembling the position-limiting device.
The floor that place building is placed to connecting plate 4 and support 3, stop device 5, is higher than hanging flower basket body 1, nevertheless chooses for use the floor that is close to hanging flower basket body 1 to make 2 of hoist cable can rock the length and shorten, the effectual influence that reduces wind load to hanging flower basket body 1.
Along 2 axial directions of hoist cable, from bottom to top interval sets up a plurality of stop device 5. Prevent wind the effect of shaking better, in addition withdrawing the building as the stop device 5 of lower floor, stop device 5 on upper strata plays prevents rocking the effect in addition.
In some embodiments, the limiting device 5 can also be a slipknot or other structure capable of limiting the sling 2.
In some embodiments, the bracket 3 can be integrally movable, and when the sling 2 needs to be limited, the bracket 3 is partially moved out of the floor, so that the limiting device 5 is matched with the sling 2; when the hanging basket body 1 is lifted upwards, the bracket 3 is moved to integrally move into a building.
Obviously, the connecting plate 4 can be connected with a plurality of brackets by adjusting the size of the connecting plate 4, for example, in the embodiment, one connecting plate 4 corresponds to two brackets 3 as long as the corresponding limiting device 5 can be limited to two slings 2 respectively.
The utility model discloses a use as follows:
when using hanging flower basket body 1, preferentially arrange the device on the high level that is close to hanging flower basket body 1, also can be according to the use scene, from the top down every 3 layers arrange connecting plate 4, support 3 and stop device 5 to the realization is to the spacing that 2 rocks of hoist cable, makes the mobile length of 2 of hoist cable shorten, reduces rocking of hanging flower basket body 1 that wind load brought.
In specific implementation, the connecting plate 4 is fixedly connected to the floor slab through the fixing device 9. Obviously, two connecting plates 4 are fixed correspondingly to the two slings 2 of the basket body 1. The telescopic joint of the bracket 3 is pulled out, so that the limiting device 5 on the bracket 3 can limit the swing of the sling 2. According to the implementation, the swinging of the sling 2 under wind load can be effectively limited.
When the basket body 1 needs to be lifted upwards, the supports 3 are retracted into the telescopic nodes 31, and the basket body 1 and the slings 2 cannot interfere with the supports 3 when lifted upwards.
When the construction is finished, the connecting plate 4 is detached from the floor slab, the whole device is stored, and the whole device can be installed again in the follow-up process when in need.
Example 2
As shown in fig. 3-5, embodiment 2 provides a wind vibration prevention hanging basket, which comprises a basket body 1, a sling 2, a bracket 3, a connecting plate 4, a limiting device 5, a common bolt 6, a fixing member 7, a rotating mechanism 8 and a fixing device 9.
The connecting plate 4 is a galvanized steel plate, the fixing device 9 is an expansion bolt, and as shown in fig. 3, the connecting plate 4 is fixedly connected to the floor slab through the fixing device 9. It is obvious that the common material of the connecting plate 4 and the fixing means 9 are only shown by way of example and are not particularly limited.
In this embodiment, as can be seen from fig. 3, the limiting device 5 is arranged on the adjacent layer, and the anti-shaking effect is better compared with the limiting device 5 arranged on the interlayer in embodiment 1. The hanging basket is more suitable for the time that wind load is big and/or hanging basket body 1 position is high, and the construction is safer.
The connecting plate 4 comprises a rotating mechanism 8, and the bracket 3 is rotatably connected to the connecting plate 4 through the rotating mechanism 8. As shown in fig. 5, a partial schematic view c, in this embodiment, the support 3 is rotatable in a vertical plane.
In this embodiment the bracket 3 is able to rotate through 180 °, i.e. when the bracket 3 is retracted, the bracket 3 can rotate to the attachment plate 4 within the building. So implement, avoid the tie point atress of support 3 and connecting plate 4 too big, also can avoid support 3 to support in the slant, touch constructor.
In some embodiments, the support 3 can also rotate on a horizontal plane, and when the hanging basket body 1 is lifted, the support 3 only needs to be avoided into a building.
The fixed end of the bracket 3 is hinged with a connecting plate 4, and the movable end of the bracket 3 is connected with a limiting device 5. A limiting device 5 is welded at the top of the movable end of the bracket 3, as shown in a partial schematic view b in fig. 4, in this embodiment, the limiting device 5 is a circular slipknot. The inner diameter of the circular slipknot is matched with the diameter of the sling 2, namely the inner diameter of the circular slipknot is 1cm larger than the diameter of the sling 2. Is used for realizing the fixed point locking of the sling 2 when the hanging basket body 1 works. Thereby make the portable length of hoist cable 2 shorten, reduce the influence that wind load brought, and the internal diameter of circular slipknot slightly is greater than the diameter of hoist cable 2, under the prerequisite that stop device 5 and support 3 do not take place to interfere with hanging flower basket body 1, do not influence the reciprocating of hanging flower basket body 1. The numerical values are only used for showing that the numerical values are slightly larger than the diameter of the sling 2, and the size of the limiting device 5 in specific implementation is comprehensively determined according to the diameter of the sling 2 and the anti-shaking requirement.
In some embodiments, the limiting device 5 is not limited to a circular buckle, and other conventional shapes such as a square shape can be used, as long as the sling 2 can be limited under the limitation, and no large shaking occurs.
Furthermore, stop device 5 is last to have a locking device, and the constructor on the hanging flower basket body 1 can lock it during the use, prevents that wind load is too big, and hoist cable 2 slippage is outside stop device 5.
The connecting plate 4 is fixedly connected with a fixing member 7, as shown in detail in fig. 5, the fixing member 7 is a part with a hole. Also a conventional bolt 6 is included. During the use, support 3 rotates to the position that restriction hoist cable 2 rocked, realizes spacing to support 3 jointly through ordinary bolt 6 and mounting 7.
It is obvious that the fixing 7 is here preferably a holed part and that a common bolt 6 is used to assist the limiting. The common bolt 6 can be replaced by other common connection forms; the fixing member 7 and the common bolt 6 may be integrated, so long as they can be moved or detached, and the bracket 3 can be retracted into the building.
In some embodiments, where the support frame 3 is selected to be horizontally rotatable, the fixing member 7 is preferably detachably connected to the connecting plate 4. For example: corresponding threaded holes are formed in the connecting plate 4, and the fixing piece 7 is structurally connected in an adaptive mode.
The utility model discloses a use as follows:
when using hanging flower basket body 1, from the lower multilayer arrangement of building top the utility model provides a prevent wind device that shakes to the realization makes 2 mobile length of hoist cable shorten to the fixed point control of 2 different positions of hoist cable, reduces the influence that wind load brought.
In concrete implementation, the connecting plate 4 is fixedly connected to the floor slab through the fixing device 9. Obviously, two connecting plates 4 are fixed correspondingly to the two slings 2 of the basket body 1. The common bolt 6 is disassembled, the bracket 3 is rotated, the limiting device 5 on the bracket 3 can limit the swinging of the sling 2, the limiting device 5 is locked, and the common bolt 6 is installed. According to the implementation, the length of the sling 2 which can be swayed can be effectively limited and shortened, and the hanging basket body 1 is further stable.
When the hanging basket body 1 needs to be lifted upwards, the common bolts 6 are disassembled, the limiting devices 5 are loosened, the support 3 is rotated to the position above the floor, and the hanging basket body 1 and the sling 2 cannot interfere with the support 3 when lifted upwards.
In the implementation process, the locking and the loosening of the slipknots are operated by constructors on the hanging basket body 1, and the rotation of the bracket 3 is operated by constructors in the building.
When the construction is finished, the connecting plate 4 is detached from the floor slab, the whole device is stored, and the device can be installed again in the follow-up process.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. The utility model provides a prevent wind hanging flower basket that shakes contains hanging flower basket body (1) and connects in hoist cable (2) of hanging flower basket body (1) both sides, its characterized in that: still contain stop device (5), stop device (5) connect in the building of hanging flower basket body (1) side, stop device (5) are followed the axial interval distribution of hoist cable (2), stop device (5) are used for the restriction hoist cable (2) horizontal direction rocks, stop device (5) can be retrieved in corresponding building.
2. The wind vibration prevention hanging basket according to claim 1, characterized in that: still contain connecting plate (4) and support (3), stop device (5) pass through support (3) are connected connecting plate (4) and then connect on corresponding building, connecting plate (4) can be dismantled and connect on corresponding building interior floor, support (3) with stop device (5) can be retrieved in corresponding building.
3. The wind vibration prevention hanging basket according to claim 2, characterized in that: the support (3) is rotatably connected with the connecting plate (4) through a rotating mechanism (8), and a fixing piece (7) used for limiting the support (3) to rotate when in use is connected onto the connecting plate (4).
4. The wind vibration prevention hanging basket according to claim 3, wherein: the support (3) can vertically rotate.
5. The wind vibration prevention hanging basket according to claim 4, wherein: the rotating range of the bracket (3) is 0-180 degrees.
6. The wind vibration prevention hanging basket according to claim 2, characterized in that: the distance between the edge of the connecting plate (4) and the corresponding building outer vertical surface is at least 20cm.
7. The wind vibration prevention hanging basket according to claim 2, characterized in that: each connecting plate (4) is connected with at least one bracket (3).
8. The wind vibration prevention hanging basket according to claim 2, characterized in that: the support (3) is made of profile steel, and the connecting plate (4) is made of galvanized steel sheets.
9. The wind vibration prevention hanging basket according to any one of claims 1 to 8, characterized in that: the limiting device (5) is a movable buckle, and the movable buckle comprises a locking device.
10. The wind vibration prevention hanging basket according to any one of claims 1 to 8, characterized in that: the limiting devices (5) are arranged at intervals of 2-3 layers corresponding to buildings.
CN202221467238.1U 2022-06-13 2022-06-13 Wind-proof vibration-proof hanging basket Active CN217759930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221467238.1U CN217759930U (en) 2022-06-13 2022-06-13 Wind-proof vibration-proof hanging basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221467238.1U CN217759930U (en) 2022-06-13 2022-06-13 Wind-proof vibration-proof hanging basket

Publications (1)

Publication Number Publication Date
CN217759930U true CN217759930U (en) 2022-11-08

Family

ID=83892211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221467238.1U Active CN217759930U (en) 2022-06-13 2022-06-13 Wind-proof vibration-proof hanging basket

Country Status (1)

Country Link
CN (1) CN217759930U (en)

Similar Documents

Publication Publication Date Title
CN207608238U (en) A kind of boom hoisting of building panel
CN201376850Y (en) Unitary curtain wall field lifting device
CN108455449A (en) A kind of interior rail type mobile curtain wall Lift-on/Lift-off System
CN217759930U (en) Wind-proof vibration-proof hanging basket
CN210460017U (en) Adjustable prefabricated wall mounting bracket
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN113882648A (en) All-steel attached lifting scaffold equipment and construction method thereof
CN105520681B (en) Flexion-extension formula folding arm window cleaning equipment
CN220790180U (en) Externally hung wallboard connecting node
CN219507489U (en) ACC plate hoisting auxiliary device
CN111155438A (en) Construction equipment applied to steel tower column and construction process thereof
CN214653190U (en) Adjustable portable lifting device
CN115893221A (en) Electric hanging basket for complex curtain wall and construction method thereof
CN212222218U (en) Single-point hoisting pile erecting system
CN210105347U (en) High-rise partition plate installation equipment with good stability
CN117166812B (en) Construction method for reforming protective structure of building curtain wall during tower crane limitation
CN210561720U (en) Pier stud maintenance repair operation platform
CN215666734U (en) Simple hanging bracket for wind power installation platform union pile-flushing hose
CN219690329U (en) Hanging basket for bridge high-altitude operation
CN221567619U (en) Telescopic shed roof for steel bar processing shed
CN220725708U (en) Simple movable hanging cage
CN217759925U (en) BIM-based steel operating platform for light production well
CN221399734U (en) Lifting scaffold
CN219771536U (en) A multifunctional combined reversible lifting mechanism
CN220978760U (en) Elevator derrick construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant