CN217425585U - A high-voltage cable withstand voltage test tool - Google Patents
A high-voltage cable withstand voltage test tool Download PDFInfo
- Publication number
- CN217425585U CN217425585U CN202222118250.8U CN202222118250U CN217425585U CN 217425585 U CN217425585 U CN 217425585U CN 202222118250 U CN202222118250 U CN 202222118250U CN 217425585 U CN217425585 U CN 217425585U
- Authority
- CN
- China
- Prior art keywords
- voltage
- cable
- sleeve
- box body
- sealing box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Cable Accessories (AREA)
Abstract
本实用新型涉及一种高压电缆耐压试验工装,包括密封箱体以及用于连接电缆插拔头的高压套管;密封箱体外接充气设备,高压套管密封连接于密封箱体上;高压套管上端设有供电缆插拔头的消弧插入棒安装的安装孔,本实用新型的有益效果是:将高压电缆的插拔头直接连到工装的高压套管上,解决了高压电缆的插拔头连接时封堵和接线的问题,简单快速、可靠地完成耐压试验,对人身、设备安全给予极大保障;取代了操作人员直接对带插拔头的高压电缆进行试验,利用该试验工装直接模拟实际设备工况进行施工作业。
The utility model relates to a high-voltage cable withstand voltage test tool, which comprises a sealing box body and a high-voltage sleeve for connecting a cable plug-in head; the sealing box is externally connected to an inflation device, and the high-voltage sleeve is sealed and connected to the sealing box; the high-voltage sleeve The upper end of the pipe is provided with an installation hole for the installation of the arc-extinguishing rod of the cable plug-in head. The beneficial effect of the utility model is that the plug-in head of the high-voltage cable is directly connected to the high-voltage sleeve of the tooling, which solves the problem of plugging the high-voltage cable. The problem of plugging and wiring when the head is connected, the withstand voltage test can be completed simply, quickly and reliably, which greatly guarantees the safety of people and equipment; it replaces the operator to directly test the high-voltage cable with the plug and use the test. The tooling directly simulates the actual equipment conditions for construction operations.
Description
技术领域technical field
本实用新型涉及电力设备技术领域,具体涉及一种高压电缆耐压试验工装。The utility model relates to the technical field of electric equipment, in particular to a high-voltage cable withstand voltage test tool.
背景技术Background technique
在输配电系统线路中,高压电缆铺设是至关重要的一环。高压电缆铺设完成后需对电缆及电缆终端进行耐压试验,试验目的主要是检测铺设过程中有无对绝缘造成损伤、电缆终端制作是否合格,对出厂试验的合格性进行验证。在配电系统中带插拔电缆头的高压电缆应用十分广泛,其中SF6(六氟化硫)环网柜、箱式变电站、高压电缆分支箱等都在使用。由于高压电缆的插拔头为腔式结构,在制作和安装过程中一定不能有划伤和杂质,绝缘间隙如果没有保证好,试验和使用过程中易发生爬电,甚至绝缘层被击穿。在耐压试验过程中,直接进行试验时,高压电缆的插拔头不易封堵和不易接线的情况,对人身、设备安全均有较大影响。In the transmission and distribution system, the laying of high-voltage cables is a crucial part. After the high-voltage cable is laid, it is necessary to carry out a withstand voltage test on the cable and the cable terminal. The main purpose of the test is to detect whether there is any damage to the insulation during the laying process, whether the cable terminal is qualified, and to verify the eligibility of the factory test. High-voltage cables with pluggable cable heads are widely used in power distribution systems, including SF 6 (sulfur hexafluoride) ring network cabinets, box-type substations, and high-voltage cable branch boxes. Because the plug head of the high-voltage cable is a cavity structure, there must be no scratches and impurities during the production and installation process. If the insulation gap is not guaranteed, creepage is likely to occur during the test and use, and even the insulation layer is broken down. In the process of withstand voltage test, when the test is performed directly, the plug and unplug of the high-voltage cable are not easy to be blocked and difficult to connect, which has a great impact on the safety of people and equipment.
实用新型内容Utility model content
本实用新型所要解决的技术问题是提供一种高压电缆耐压试验工装,以克服上述现有技术中的不足。The technical problem to be solved by the utility model is to provide a high-voltage cable withstand voltage test tool to overcome the above-mentioned deficiencies in the prior art.
本实用新型解决上述技术问题的技术方案如下:一种高压电缆耐压试验工装,包括密封箱体以及用于连接电缆插拔头的高压套管;密封箱体外接充气设备,高压套管密封连接于密封箱体上;高压套管上端设有供电缆插拔头的消弧插入棒安装的安装孔。The technical solution of the utility model to solve the above-mentioned technical problems is as follows: a high-voltage cable withstand voltage test tool, including a sealed box body and a high-voltage sleeve for connecting the cable plug-in head; the sealed box is connected to an external inflation device, and the high-voltage sleeve is sealed and connected On the sealed box body; the upper end of the high-voltage bushing is provided with a mounting hole for the installation of the arc-extinguishing insert rod of the cable plug-in head.
本实用新型的有益效果是:将高压电缆的插拔头直接连到工装的高压套管上,解决了高压电缆的插拔头连接时封堵和接线的问题,简单快速、可靠地完成耐压试验,对人身、设备安全给予极大保障;取代了操作人员直接对带插拔头的高压电缆进行试验,利用该试验工装直接模拟实际设备工况进行施工作业。The beneficial effect of the utility model is that the plug-in head of the high-voltage cable is directly connected to the high-voltage sleeve of the tooling, which solves the problems of blocking and wiring when the plug-in head of the high-voltage cable is connected, and the pressure resistance is completed simply, quickly and reliably. The test provides great protection for personal and equipment safety; instead of the operator directly testing the high-voltage cable with plug-in head, the test tool is used to directly simulate the actual equipment working conditions for construction operations.
在上述技术方案的基础上,本实用新型还可以做如下改进。On the basis of the above technical solutions, the utility model can also be improved as follows.
进一步,还包括套管压板,套管压板套设于高压套管上,并与密封箱体可拆卸连接。Further, it also includes a casing pressure plate, the casing pressure plate is sleeved on the high-voltage casing, and is detachably connected with the sealing box.
进一步,高压套管中部向外延伸设置有裙边,裙边设置于密封箱体上方,且裙边的下端面与密封箱体的上端面相抵,套管压板套设于裙边上方;套管压板通过螺栓与密封箱体可拆卸连接。Further, the middle part of the high-voltage casing is provided with a skirt extending outward, the skirt is arranged above the sealing box, and the lower end face of the skirt is in contact with the upper end face of the sealing box, and the casing pressure plate is sleeved above the skirt; the casing; The pressing plate is detachably connected with the sealing box through bolts.
进一步,密封箱体上设有充气阀,充气阀与外接充气设备可拆卸连接。Further, an inflation valve is provided on the sealing box, and the inflation valve is detachably connected to an external inflation device.
进一步,高压套管至少设置有两个。Further, at least two high-voltage bushings are provided.
进一步,密封箱体为不锈钢材质。Further, the sealed box is made of stainless steel.
附图说明Description of drawings
图1为本实用新型的结构示意图一;Fig. 1 is the structural representation one of the utility model;
图2为本实用新型的结构示意图二;Fig. 2 is the structural representation two of the utility model;
图3为本实用新型的结构示意图三;Fig. 3 is the structural representation three of the utility model;
图4为本实用新型的剖面结构示意图;Fig. 4 is the sectional structure schematic diagram of the utility model;
图5为本实用新型的使用状态结构示意图。FIG. 5 is a schematic diagram of the structure of the utility model in use state.
附图中,各标号所代表的部件列表如下:In the accompanying drawings, the list of components represented by each number is as follows:
1、密封箱体,11、充气阀,2、高压套管,21、裙边,22、安装孔,3、套管压板,4、插拔头。1. Sealed box, 11. Inflatable valve, 2. High-pressure casing, 21. Skirt, 22. Mounting hole, 3. Casing pressure plate, 4. Plug and pull head.
具体实施方式Detailed ways
以下结合附图对本实用新型的原理和特征进行描述,所举实例只用于解释本实用新型,并非用于限定本实用新型的范围。The principles and features of the present invention will be described below with reference to the accompanying drawings, and the examples are only used to explain the present invention, and are not intended to limit the scope of the present invention.
实施例1,如图1~图5所示,一种高压电缆耐压试验工装,包括密封箱体1以及用于连接插拔电缆头的高压套管2;密封箱体1外接充气设备,高压套管2密封连接于密封箱体1上;高压套管2上端设有供电缆插拔头的消弧插入棒安装的安装孔22。
将高压电缆的插拔头4直接连到工装的高压套管2上,解决了高压电缆的插拔头4连接时封堵和接线的问题,简单快速、可靠地完成耐压试验,对人身、设备安全给予极大保障;取代了操作人员直接对带插拔头4的高压电缆进行试验,利用该试验工装直接模拟实际设备工况进行施工作业;具体实施过程中,利用SF充气设备对密封箱体1内进行灌充SF气体,使其内部SF气体压力达到1.2bar-1.4bar,灌充SF气体的目的是为了增强其外绝缘强度。The
实施例2,如图1~图5所示,本实施例为在实施例1的基础上所进行的进一步改进,其具体如下:
还包括套管压板3,套管压板3套设于高压套管2上,并与密封箱体1可拆卸连接,套管压板3对高压套管2起到固定作用,避免高压套管2松动、泄漏。It also includes a
实施例3,如图1~图5所示,本实施例为在实施例2的基础上所进行的进一步改进,其具体如下:
高压套管2中部向外延伸设置有裙边21,裙边21设置于密封箱体1上方,且裙边21的下端面与密封箱体1的上端面相抵,套管压板3套设于裙边21上方;套管压板3通过螺栓与密封箱体1可拆卸连接。A
通过套管压板3压住裙边21,从而对高压套管2进行固定,固定效果更好。The
实施例4,如图1~图5所示,本实施例为在实施例1的基础上所进行的进一步改进,其具体如下:
密封箱体1上设有充气阀11,充气阀11与外接充气设备可拆卸连接,以便于携带和拆装;具体实施过程中,充气阀11可外接气压表,对内部气体压力进行监测,当密封箱体1内气体压力不足时,及时进行补气。The
实施例5,如图1~图5所示,本实施例为在实施例1的基础上所进行的进一步改进,其具体如下:Embodiment 5, as shown in FIGS. 1 to 5 , this embodiment is a further improvement on the basis of
高压套管2至少设置有两个,以便于同时对多个高压电缆进行耐压实验。There are at least two high-
实施例6,如图1~图5所示,本实施例为在实施例1至5任一实施例的基础上所进行的进一步改进,其具体如下:Embodiment 6, as shown in FIGS. 1 to 5 , this embodiment is a further improvement on the basis of any of
密封箱体1为不锈钢材质,不会生锈,更加耐高压,使用寿命更久。The sealed
尽管上面已经示出和描述了本实用新型的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本实用新型的限制,本领域的普通技术人员在本实用新型的范围内可以对上述实施例进行变化、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it should be understood that the above embodiments are exemplary and should not be construed as limitations of the present invention, and those of ordinary skill in the art are within the scope of the present invention Variations, modifications, substitutions and variations can be made to the above-described embodiments.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222118250.8U CN217425585U (en) | 2022-08-12 | 2022-08-12 | A high-voltage cable withstand voltage test tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222118250.8U CN217425585U (en) | 2022-08-12 | 2022-08-12 | A high-voltage cable withstand voltage test tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217425585U true CN217425585U (en) | 2022-09-13 |
Family
ID=83173045
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222118250.8U Active CN217425585U (en) | 2022-08-12 | 2022-08-12 | A high-voltage cable withstand voltage test tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217425585U (en) |
-
2022
- 2022-08-12 CN CN202222118250.8U patent/CN217425585U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108152693B (en) | GIL equipment three-pillar insulator fault simulation test platform and simulation test method | |
CN102916362B (en) | A kind of Intelligent inflatable high-voltage vacuum switch cabinet for metros | |
CN105606850A (en) | High-voltage DC support insulator test apparatus, test system and system method | |
CN109768509B (en) | Elbow type joint special for electrified repair of power cable, repair device and method | |
CN207992375U (en) | Three support insulator fault simulating test platform of GIL equipment | |
CN217425585U (en) | A high-voltage cable withstand voltage test tool | |
CN115047376A (en) | Device and method for detecting electric leakage of rural power circuit | |
CN206431110U (en) | SF6 measurement multifunction conjunctions | |
CN211669312U (en) | Three-station grounding device for cable voltage withstand test | |
CN105552770A (en) | Connection body between high-voltage sleeve pipe of transformer and gas insulated switchgear (GIS) device | |
CN204967217U (en) | A connection structure that is used for between oil filled cable and dry -type crosslinked cable | |
CN205543941U (en) | Connector of transformer high -tension bushing and GIS equipment room | |
CN209282121U (en) | A kind of seepage-proof oil SF6Gas density relay | |
CN103050905B (en) | Switch cubicle ac voltage withstanding insulation annex | |
CN218996645U (en) | Quick docking device for vertical circuit breaker and isolating switch | |
CN205786928U (en) | It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator | |
CN201877773U (en) | Branch joint for high voltage power cable | |
CN204118546U (en) | A kind of cable interim reconfiguration transition case | |
CN204008708U (en) | 10kV ring main unit high-potting mask | |
CN207896462U (en) | Entrance bushing | |
CN211649416U (en) | Universal SF6 inflation test joint | |
CN206349684U (en) | 10kVSF6 gas-insulated metal enclosed switchgear cabinet Rapid Combination making-up air devices | |
CN215981264U (en) | Universal SF6 inflatable test joint | |
CN104020325A (en) | High-voltage test shielding cover for 10kV ring main unit | |
CN106019022B (en) | Cover plate test device for connecting gas chamber between oil-gas type transformer and GIS and operation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A high-voltage cable withstand voltage test fixture Effective date of registration: 20230920 Granted publication date: 20220913 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HOLIC ELECTRICAL TECHNOLOGY CO.,LTD. Registration number: Y2023980057571 |
|
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PC01 | Cancellation of the registration of the contract for pledge of patent right |
Granted publication date: 20220913 Pledgee: Guanggu Branch of Wuhan Rural Commercial Bank Co.,Ltd. Pledgor: HOLIC ELECTRICAL TECHNOLOGY CO.,LTD. Registration number: Y2023980057571 |
|
PC01 | Cancellation of the registration of the contract for pledge of patent right |