[go: up one dir, main page]

CN216289884U - Liftable and rotatable fixing support for cable laying - Google Patents

Liftable and rotatable fixing support for cable laying Download PDF

Info

Publication number
CN216289884U
CN216289884U CN202122986937.9U CN202122986937U CN216289884U CN 216289884 U CN216289884 U CN 216289884U CN 202122986937 U CN202122986937 U CN 202122986937U CN 216289884 U CN216289884 U CN 216289884U
Authority
CN
China
Prior art keywords
steel pipe
cable
clamp
support
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122986937.9U
Other languages
Chinese (zh)
Inventor
李佳雄
林鑫
汪成东
郭应辉
张仁武
钟方方
马耀原
李飞耀
苟发荣
郑浩南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Engineering Group Co Ltd
Original Assignee
China Railway Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Engineering Group Co Ltd filed Critical China Railway Construction Engineering Group Co Ltd
Priority to CN202122986937.9U priority Critical patent/CN216289884U/en
Application granted granted Critical
Publication of CN216289884U publication Critical patent/CN216289884U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model belongs to the field of support equipment, and particularly relates to a liftable and turnable fixing support for cable laying, which comprises a transverse support, a vertical support and a fixing cable clamp, wherein the transverse support is arranged at the upper end of the vertical support in a fixed connection mode, the vertical support comprises at least two vertically connected second steel pipes, the second steel pipe positioned above can axially move along the second steel pipe positioned below and then be fixed, the fixing cable clamp is detachably connected to a third steel pipe of the transverse support, and the third steel pipe extends along the transverse direction, and the fixing cable clamp comprises a U-shaped fixing clamp, a steel pipe fixing clamp and a cable fixing clamp; the plurality of second steel pipes are connected to realize height adjustment of the vertical support; the U-shaped fixing clamp and the steel pipe fixing clamp are matched to realize relative rotation with the third steel pipe, the position of the fixed cable clamp on the third steel pipe is changed, and different requirements of a construction site are met; the overhead laid cable is clamped and pressed by the cable fixing clamp to support and limit the overhead laid cable.

Description

Liftable and rotatable fixing support for cable laying
Technical Field
The utility model belongs to the field of support equipment, and particularly relates to a liftable and rotatable fixing support for cable laying.
Background
At present, the cable laying mode of the electric trunk line on the domestic construction site is required to be buried or overhead, and the electric cable of the temporary line on the construction site is required to change at any time along with the change of the construction area; the position of the aerial laid power cable is not easy to change, the power cable on the construction site is mostly buried, laid with a floor or laid along a steel bar, the power cable on the buried and laid with the floor is not protected by any external package, is easy to be damaged by other machines on the construction site, and is easy to be damaged by earthwork construction or long construction operation on the construction site, so that the power cable cannot be used; the power cable laid along the reinforcing steel bar is easy to damage, so that safety accidents are caused.
Chinese utility model patent publication number is CN213937367U, and the public day is 20210810, discloses a job site removes with laying overhead support, include: dead lever, tripod, base, worm drive mechanism, protective case and cross horizontal pole, the tripod comprises connecting plate, landing leg, fixed block and dead lever, the marginal welding of connecting plate lower surface has the landing leg, the welding of landing leg lower extreme outside has the fixed block, threaded hole is seted up to the fixed block upper surface, fixed block upper surface movable mounting has the dead lever. When the power cable moves, the whole device needs to be detached, and the relocation, installation and movement are carried out, so that the changing and adjusting process is complicated.
SUMMERY OF THE UTILITY MODEL
The utility model provides a liftable and rotatable fixing support for cable laying, which realizes height adjustment of a vertical support through interconnection of a plurality of second steel pipes; realize the relative rotation between U type fixing clip and steel pipe fixation clamp and the third steel pipe through first bolt to change the position of fixed cable clamp on the third steel pipe, with the different needs that adapt to the job site, make the used of electricity cable used repeatedly simultaneously.
The utility model provides a liftable, can have enough to meet need formula fixed bolster for cable laying, includes horizontal support, vertical support and fixed cable clamp, horizontal support sets up in the vertical support upper end with fixed connection's mode, vertical support includes the second steel pipe that two at least can vertically splice, is located the top the second steel pipe can be fixed again after the second steel pipe axial displacement that is located the below, fixed cable clamp detachably connects on the third steel pipe of horizontal support along horizontal extension, fixed cable clamp includes:
the inner diameter of the arc-shaped part of the U-shaped fixing clamp is not smaller than the outer diameter of the third steel pipe, so that the third steel pipe of the transverse bracket can penetrate through the U-shaped fixing clamp;
the steel pipe fixing clamps penetrate through the two vertical ends of the U-shaped fixing clamp, move along the two vertical ends of the U-shaped fixing clamp, clamp and press the third steel pipe, and are fixed by first bolts;
and the cable fixing clamp is connected at the two vertical ends of the U-shaped fixing clamp in a penetrating manner, is fixed on the U-shaped fixing clamp by a second bolt, and clamps and presses the overhead laid cable.
The height adjustment of the vertical support is realized through the interconnection of the second steel pipes, and the power cable is in a high position and is not easy to damage due to the fact that the power cable is laid on the overhead construction site; meanwhile, the U-shaped fixing clamp, the steel pipe fixing clamp and the third steel pipe are rotated relatively through the first bolt, so that the position of the fixed cable clamp on the third steel pipe of the transverse support is changed, different requirements of a construction site are met, and the power cable is reused; the overhead laid cable is clamped and pressed by the cable fixing clamp to support and limit the overhead laid cable.
As a further improvement of the liftable and rotatable fixing support for cable laying, the lower end of the second steel pipe positioned above can be nested with the upper end of the second steel pipe positioned below.
Through setting up not unidimensional second steel pipe, stretch into the bottom of the second steel pipe of top with the second steel pipe top of below, assemble a plurality of second steel pipes of connection through size block independent assortment, realize the extension of vertical support height to satisfy the demand of the different built on stilts height of job site.
As a further improvement of the lifting and turnover type fixing support for cable laying, sleeves are arranged at the positions where the lower end of the second steel pipe positioned above is connected with the upper end of the second steel pipe positioned below to realize splicing, and the splicing mode is threaded connection or a connecting rod penetrating through the second steel pipe and the sleeves is inserted in a perforation manner.
Through inserting through connection with sleeve screw-thread fit, perhaps punch between two adjacent second steel pipes, realize the extension of vertical support height to satisfy the demand of the different built on stilts height of job site.
As a further improvement of the liftable and revolvable fixing bracket for cable laying of the present invention, the steel pipe fixing clip has an arc-shaped portion attached to the third steel pipe.
The steel pipe fixing clamp is provided with an arc-shaped part attached to the third steel pipe, is matched with the U-shaped fixing clamp and can clamp and press the third steel pipe of the transverse bracket, and the U-shaped fixing clamp, the steel pipe fixing clamp and the third steel pipe are connected in a clamping and pressing mode; meanwhile, the cable clamp can rotate around the third steel pipe, so that the position and angle of the fixed cable clamp can be adjusted, and different requirements of a construction site can be met.
As a further improvement of the liftable and rotatable fixing support for cable laying, the steel pipe fixing clamp is of a flat plate type.
The steel pipe fixing clamp is arranged to be a flat plate type and is matched with the U-shaped fixing clamp to clamp and press the third steel pipe of the transverse support, so that the U-shaped fixing clamp, the steel pipe fixing clamp and the third steel pipe are clamped and clamped; meanwhile, the cable clamp can rotate around the third steel pipe, so that the position and angle of the fixed cable clamp can be adjusted, and different requirements of a construction site can be met.
As a further improvement of the liftable and revolvable fixing bracket for cable laying of the present invention, the cable fixing clamp comprises two semi-annular clamps arranged oppositely for clamping the cable.
The two semi-annular clamps which are oppositely arranged are connected to the U-shaped fixing clamp and used for fixing and containing the power cables and integrating the power cables, so that the power cables are prevented from being disordered and used in a staggered mode; the power cable is protected, the service life is prolonged, and the power cable can be repeatedly used for many times.
As a further improvement of the liftable and rotatable fixing support for cable laying, the bottom of the vertical support is connected with a support body foundation, the support body foundation comprises a concrete column and a first steel pipe, the bottom end of the first steel pipe is embedded into the concrete column, and the upper end of the first steel pipe is nested with the lower end of the second steel pipe.
The vertical support is fixed through a frame body foundation at the bottom, and the stability of the vertical support is enhanced by the concrete column poured by the residual concrete; and a first steel pipe embedded into the concrete column is arranged on the concrete column and is used for being connected with a second steel pipe of the vertical support in a nested manner.
As a further improvement of the liftable and rotatable fixing support for cable laying, the transverse support further comprises a fourth steel pipe, and the fourth steel pipe is vertically connected to the bottom of the third steel pipe.
And the transverse support and the vertical support are connected through a fourth steel pipe.
As a further improvement of the liftable and rotatable fixing support for cable laying, the vertical supports are disk buckle type scaffold steel pipes and comprise connecting disks, and two adjacent vertical supports are connected through fastening joints for fastening the connecting disks.
The connecting discs on the steel pipes of the buckling scaffold are buckled through the buckling heads so as to realize the mutual connection among the vertical supports.
The utility model has the beneficial effects that:
according to the utility model, the height adjustment of the vertical support is realized by the interconnection of the plurality of second steel pipes, and the power cable is in a high position and is not easy to damage due to the fact that the power cable is exposed on the overhead construction site, so that the power cable can be lifted and turned over; meanwhile, the U-shaped fixing clamp, the steel pipe fixing clamp and the third steel pipe are rotated relatively through the first bolt, so that the position of the fixed cable clamp on the third steel pipe of the transverse support is changed, different requirements of a construction site are met, and the power cable is reused; clamping and pressing the aerial laid cable by using a cable fixing clamp, and supporting and limiting the aerial laid cable; simultaneously through each steel pipe nested connection, perhaps between each steel pipe with sleeve screw-thread fit connection, can realize the independent assortment concatenation between a plurality of steel pipes, and then realize the extension in the not unidimensional degree for the altitude mixture control of vertical support and the length adjustment of horizontal support, and realize being connected between vertical support and support body basis, the horizontal support.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of a stationary cable clamp;
FIG. 3 is a schematic structural view of a frame foundation;
FIG. 4 is a schematic view of the vertical support;
fig. 5 is a schematic structural view of the transverse bracket.
Reference numerals:
2. a fixed cable clamp; 21. a U-shaped fixing clip; 22. a steel pipe fixing clamp; 23. a cable retaining clip; 24. a first bolt; 25. a second bolt;
3. a frame foundation; 31. a concrete column; 32. a first steel pipe;
4. a vertical support; 41. a second steel pipe; 42. a connecting disc;
5. a transverse support; 51. a third steel pipe; 52. and a fourth steel pipe.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it should be understood that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art. In addition, the technical features involved in the different embodiments of the present invention described below may be combined with each other as long as they do not conflict with each other.
Example 1
What figure 1 ~ 5 show is a liftable, can have enough to meet need formula fixed bolster for cable laying, its characterized in that: including horizontal support 5, vertical support 4 and fixed cable clamp 2, horizontal support 5 sets up in vertical support 4 upper ends with fixed connection's mode, vertical support 4 includes the second steel pipe 41 of two at least vertical concatenations, is located the top second steel pipe 41 can be fixed again after the 41 axial displacement of second steel pipe along the below of being located, fixed cable clamp 2 detachably connects on horizontal support 5 along the third steel pipe 51 of horizontal extension, fixed cable clamp 2 includes:
a U-shaped fixing clip 21 having an inner diameter of an arc portion not smaller than an outer diameter of the third steel pipe 51 so that the third steel pipe 51 of the lateral bracket 5 can pass through the U-shaped fixing clip 21;
a steel pipe fixing clip 22, which is threaded on the two vertical ends of the U-shaped fixing clip 21, moves along the two vertical ends of the U-shaped fixing clip 21, is clamped on the third steel pipe 51, and is fixed by the first bolt 24;
and the cable fixing clamps 23 are connected to the two vertical ends of the U-shaped fixing clamp 21 in a penetrating mode, are fixed on the U-shaped fixing clamp 21 through second bolts 25 and clamp and press cables for aerial laying.
The height adjustment of the vertical support 4 is realized through the interconnection of the second steel pipes 41, and the power cable is in a high position and is not easy to damage due to the fact that the power cable is exposed on the overhead construction site; meanwhile, the U-shaped fixing clamp 21, the steel pipe fixing clamp 22 and the third steel pipe 51 are relatively rotated through the first bolt 24, so that the position of the fixed cable clamp 2 on the third steel pipe 51 of the transverse bracket 5 is changed to meet different requirements of a construction site, and meanwhile, the power cable is repeatedly used; the overhead laid cable is clamped and pressed by the cable fixing clamp 23 to support and limit the overhead laid cable.
In this embodiment, the lower end of the second steel pipe 41 positioned above can be nested in the upper end of the second steel pipe 41 positioned below.
Through setting up not unidimensional second steel pipe 41, stretch into the bottom of the second steel pipe 41 of top with the second steel pipe 41 top of below, assemble a plurality of second steel pipes 41 of connection through size block independent assortment, realize the extension of vertical support 4 height to satisfy the demand of the different built on stilts height of job site.
In this embodiment, a sleeve is disposed at a position where the lower end of the second steel pipe 41 located above is connected to the upper end of the second steel pipe 41 located below, so as to achieve splicing, and the splicing mode is a threaded connection or a connection rod inserted through the second steel pipe 41 and the sleeve by drilling.
Through inserting through connection with sleeve screw-thread fit, perhaps punch between two adjacent second steel pipes 41, realize the extension of vertical support 4 height to satisfy the demand of the different built on stilts height of job site.
In this embodiment, the steel pipe fixing clip 22 has an arc-shaped portion attached to the third steel pipe 51.
The third steel pipe 51 of the transverse bracket 5 can be clamped and pressed through the arc part attached to the third steel pipe 51 and matched with the U-shaped fixing clamp 21, so that the U-shaped fixing clamp 21, the steel pipe fixing clamp 22 and the third steel pipe 51 are connected in a clamping and pressing mode; meanwhile, the fixed cable clamp 2 can rotate around the third steel pipe 51, so that the position and angle of the fixed cable clamp 2 can be adjusted, and different requirements of a construction site can be met.
In the present embodiment, the steel pipe fixing clip 22 is a flat plate type.
The steel pipe fixing clamp 22 is arranged to be flat, and is matched with the U-shaped fixing clamp 21 to clamp and press the third steel pipe 51 of the transverse support 5, so that the U-shaped fixing clamp 21, the steel pipe fixing clamp 22 and the third steel pipe 51 are clamped and clamped; meanwhile, the fixed cable clamp 2 can rotate around the third steel pipe 51, so that the position and angle of the fixed cable clamp 2 can be adjusted, and different requirements of a construction site can be met.
In this embodiment, the cable retaining clip 23 comprises two oppositely disposed semi-annular clamps for clamping the cable.
The two semi-annular clamps which are oppositely arranged are connected to the U-shaped fixing clamp 21 and used for fixing and containing the power cables and integrating the power cables, so that the power cables are prevented from being disordered and used; the power cable is protected, the service life is prolonged, and the power cable can be repeatedly used for many times.
In this embodiment, as shown in fig. 3, the bottom of the vertical support 4 is connected to the frame foundation 3, the frame foundation 3 includes a concrete column 31 and a first steel tube 32, the bottom end of the first steel tube 32 is embedded in the concrete column 31, and the upper end of the first steel tube 32 is nested with the lower end of the second steel tube 41.
The vertical support 4 is fixed through the frame foundation 3 at the bottom, and the concrete column 31 poured by the residual concrete enhances the stability of the vertical support 4; the concrete column 31 is provided with a first steel tube 32 embedded inside the concrete column 31 for connecting with a second steel tube 41 of the vertical bracket 4.
In this embodiment, the transverse bracket 5 further comprises a fourth steel pipe 52, and the fourth steel pipe 52 is vertically connected to the bottom position of the third steel pipe 51.
The transverse bracket 5 and the vertical bracket 4 are connected by a fourth steel pipe 52.
In this embodiment, as shown in fig. 4, the vertical supports 4 are scaffold steel pipes, two adjacent vertical supports 4 include connecting discs 42, and the vertical supports 4 are connected to each other by fastening the connecting discs 42 through fasteners.
The connecting discs 42 on the steel pipes of the scaffold are buckled through the buckling heads so as to realize the mutual connection among the vertical supports 4.
The using method of the utility model comprises the following steps:
when the scaffold is used, the scaffold base 3 is moved to a proper position, the second steel pipe 41 is connected with the first steel pipe 32, so that the first steel pipe 32 extends into the second steel pipe 41 or the first steel pipe 32 and the second steel pipe 41 are inserted into a penetrating connection through a sleeve and a perforation; the plurality of second steel pipes 41 are connected to the vertical support 4 through nesting connection or through sleeves and perforations to reach a preset height, and the top end of the second steel pipe 41 at the top is connected with the bottom end of the fourth steel pipe 52 of the transverse support 5, so that the second steel pipe 41 extends into the fourth steel pipe 52 or the second steel pipe 41 is connected with the fourth steel pipe 52 through sleeves and perforations; a plurality of fixed cable clamps 2 are uniformly arranged on the third steel pipe 51 of the transverse bracket 5 to support the electric cables.
When adjusting fixed cable clamp 2 position and angle, adjust the first bolt 24 of connecting U type fixing clip 21 and steel pipe fixation clamp 22, make it can remove along third steel pipe 51, and the duplex winding third steel pipe 51 rotates, until adjusting suitable position and angle, screws up first bolt 24, accomplishes the regulation of fixed cable clamp 2.
When the vertical supports 4 are connected and supported, the connecting discs 42 on the second steel pipes 41 are buckled through the buckling joints, so that the vertical supports 4 are connected with each other.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes, which are made by using the contents of the present specification and the accompanying drawings, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (9)

1. The utility model provides a liftable, can have enough to meet need formula fixed bolster for cable laying which characterized in that: including horizontal support (5), vertical support (4) and fixed cable clamp (2), horizontal support (5) set up in vertical support (4) upper end with fixed connection's mode, vertical support (4) include second steel pipe (41) of two at least vertical concatenations, are located the top second steel pipe (41) can be fixed again after second steel pipe (41) axial displacement along being located the below, fixed cable clamp (2) detachably connects on horizontal support (5) along transversely extending third steel pipe (51), fixed cable clamp (2) include:
a U-shaped fixing clip (21), the inner diameter of the arc part of which is not less than the outer diameter of the third steel pipe (51), so that the third steel pipe (51) of the transverse bracket (5) can pass through the U-shaped fixing clip (21);
the steel pipe fixing clamps (22) are connected to the two vertical ends of the U-shaped fixing clamp (21) in a penetrating mode, move along the two vertical ends of the U-shaped fixing clamp (21), clamp and press the third steel pipe (51), and are fixed through first bolts (24);
and the cable fixing clamp (23) is connected to the two vertical ends of the U-shaped fixing clamp (21) in a penetrating mode, is fixed on the U-shaped fixing clamp (21) through a second bolt (25), and clamps and presses the overhead laid cable.
2. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the lower end of the second steel pipe (41) positioned above can be nested in the upper end of the second steel pipe (41) positioned below.
3. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the lower end of the second steel pipe (41) positioned above and the upper end of the second steel pipe (41) positioned below are connected, and sleeves are arranged at positions to realize splicing, and the splicing mode is threaded connection or a connecting rod penetrating through the second steel pipe (41) and the sleeves is inserted in a perforation manner.
4. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the steel pipe fixing clamp (22) is provided with an arc-shaped part attached to the third steel pipe (51).
5. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the steel tube fixing clamp (22) is of a flat plate type.
6. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the cable fixing clamp (23) comprises two semi-annular clamps which are oppositely arranged and used for clamping the cable.
7. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the bottom of vertical support (4) is connected support body basis (3), support body basis (3) include concrete column (31) and first steel pipe (32), embedding in first steel pipe (32) bottom in concrete column (31), first steel pipe (32) upper end with second steel pipe (41) lower extreme is nested.
8. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: the transverse support (5) further comprises a fourth steel pipe (52), and the fourth steel pipe (52) is vertically connected to the bottom of the third steel pipe (51).
9. A liftable and revolvable fixing bracket for cable laying according to claim 1, characterized in that: vertical support (4) are the dish knot formula scaffold steel pipe, vertical support (4) include connection pad (42), adjacent two through the joint lock joint between vertical support (4) connection pad (42) are connected.
CN202122986937.9U 2021-12-01 2021-12-01 Liftable and rotatable fixing support for cable laying Active CN216289884U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122986937.9U CN216289884U (en) 2021-12-01 2021-12-01 Liftable and rotatable fixing support for cable laying

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122986937.9U CN216289884U (en) 2021-12-01 2021-12-01 Liftable and rotatable fixing support for cable laying

Publications (1)

Publication Number Publication Date
CN216289884U true CN216289884U (en) 2022-04-12

Family

ID=81041083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122986937.9U Active CN216289884U (en) 2021-12-01 2021-12-01 Liftable and rotatable fixing support for cable laying

Country Status (1)

Country Link
CN (1) CN216289884U (en)

Similar Documents

Publication Publication Date Title
CN101280560A (en) Lattice pillar component and mounting method thereof
CN216289884U (en) Liftable and rotatable fixing support for cable laying
CN214658956U (en) Prefabricated post hoist and mount are transferred positioner
CN112726824A (en) Mounting and hoisting method for assembled steel structure building steel column node
JP5680367B2 (en) Lifting equipment
CN214740048U (en) Verticality adjusting device
CN116717132A (en) Prefabricated guardrail and construction method thereof
JP2020089192A (en) Temporary support pole, telephone pole rebuilding support device, and telephone pole rebuilding method
CN213774549U (en) Steel bar positioning frame erecting device
KR100829062B1 (en) Concrete pressure pipe support and construction method of cable stayed bridge using the same
CN114481838B (en) Fish bellied suspension cable combined bracket and construction method thereof
CN219825581U (en) Beam-column connection node structure
KR20210078119A (en) Supporter for installating horizontal member of supporting system
CN219286970U (en) A mounting structure that is used for building carrier plate to install interim block terminal
CN112803337B (en) Electrical system of lifting machine for urban construction
KR102577469B1 (en) Jack support installation device
CN221001917U (en) Novel overhanging I-steel
CN216763967U (en) Track base of construction elevator
CN112252201B (en) Prestressed anchorage utensil is used in bridge construction
CN217381932U (en) Concrete pump pipe vertical section reinforcing apparatus
CN216428804U (en) Auxiliary device for positioning prestressed tendons
CN217811167U (en) Fixed support bracket capable of adjusting elevation of embedded support leg of tower crane
CN219315818U (en) Positioning device for embedded sleeve of cast-in-situ cover plate of cable shaft
CN112252722B (en) Residential formwork installation method for building engineering construction
CN220057633U (en) Movable steel anchor box for pre-buried steel pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant