[go: up one dir, main page]

CN216240788U - Pre-control top retaining wall protection type mechanized upward high-layering filling system - Google Patents

Pre-control top retaining wall protection type mechanized upward high-layering filling system Download PDF

Info

Publication number
CN216240788U
CN216240788U CN202122923784.3U CN202122923784U CN216240788U CN 216240788 U CN216240788 U CN 216240788U CN 202122923784 U CN202122923784 U CN 202122923784U CN 216240788 U CN216240788 U CN 216240788U
Authority
CN
China
Prior art keywords
ore
mining
filling
stope
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122923784.3U
Other languages
Chinese (zh)
Inventor
刘伟军
陈敏
龚永超
万孝衡
欧任泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Institute of Mining Research Co Ltd
Original Assignee
Changsha Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Institute of Mining Research Co Ltd filed Critical Changsha Institute of Mining Research Co Ltd
Priority to CN202122923784.3U priority Critical patent/CN216240788U/en
Application granted granted Critical
Publication of CN216240788U publication Critical patent/CN216240788U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a pre-control top-retaining wall type mechanized upward high-layering filling system, which divides a stope into a plurality of ore sections from bottom to top, divides any one ore section into a plurality of ore layers from bottom to top, adopts high-layering and layer-by-layer stoping from bottom to top, fills the ore layers after the stoping of the ore layers is finished, and adopts a long anchor rope as a support for the top ore layer plate of the uppermost layer which finishes the stoping after 3 to 4 ore layers are continuously stoped. Through the mode, the utility model combines the traditional upward layered filling method and the segmented filling method to change the height of the single layer into the height layer (the height of the double layer), thereby reducing the whole supporting cost and the engineering quantity, improving the production capacity of the stope, accelerating the production efficiency and shortening the operation cycle time of the stope.

Description

预控顶留护壁式的机械化上向高分层充填系统Pre-controlled top-retaining wall-type mechanized upward-to-high layered filling system

技术领域technical field

本实用新型涉及地下矿山采矿技术领域,特别是涉及一种预控顶留护壁式的机械化上向高分层充填系统。The utility model relates to the technical field of underground mine mining, in particular to a mechanized upward-to-high layered filling system of a pre-control jacking and retaining wall type.

背景技术Background technique

在采矿领域中,特别是对于二步骤间柱采场这种开采条件复杂的矿体。二步骤采场回采时两侧为充填体,同时,二步骤采场受一步骤采场内充填体泌水、充填体强度不足等影响。一步骤采场的充填体强度不足以支撑整个二步骤采场的稳定性,导致二步骤采场回采安全条件极差。即由于一步骤采场充填体质量不达标,出现充填体垮塌现象,导致一步骤充填体无法满足二步骤的回采要求。目前传统的采矿方法较难适应这种矿体开采。In the field of mining, especially for the ore body with complex mining conditions, such as the two-step inter-pillar stope. When the two-step stope is mined, there are backfills on both sides. At the same time, the two-step stope is affected by the bleeding of the backfill and the insufficient strength of the backfill in the one-step stope. The strength of the backfill in the one-step stope is not enough to support the stability of the entire two-step stope, resulting in extremely poor mining safety conditions in the two-step stope. That is to say, because the quality of the backfill body in the one-step stope does not meet the standard, the backfill body collapses, resulting in the failure of the one-step backfill body to meet the mining requirements of the two-step process. The current traditional mining methods are difficult to adapt to this kind of ore body mining.

现有技术提供了一种破碎矿体夹层的分层分段组合开采方法,该采矿方法沿破碎矿体夹层走向依次划分盘区、盘区间柱,在每个盘区内垂直走向依次划分一步骤矿房采场、二步骤矿柱采场。一步骤矿房采场水平方向由两个并行进路构成,竖直方向的进路数量由分段高度决定,采完即充,形成胶结充填体置换条柱。盘区内一步骤矿房采场采充完毕之后,转为二步骤矿柱采场回采,二步骤采场两侧为一步骤胶结充填体,二步骤矿柱采场采用长锚索预加固的下向平行深孔分段空场嗣后充填的高效采矿方法。这种方法虽然对二步骤矿柱采场采用长锚索预加固,并对其采用分段采矿充填的方法,在一定程度上提高了二步骤矿柱采场开采时的效率以及安全性,但是这种回采及充填的方式仍然采用传统的方式,其开采效率并没有得到本质上的提高,且充填体强度较差,给作业人员带来一定的安全隐患。The prior art provides a layered and segmented combined mining method for broken ore body interlayers. The mining method sequentially divides panels and inter-panel columns along the direction of the broken ore body interlayers, and sequentially divides a step in the vertical direction of each panel area. Mine stope, two-step pillar stope. The horizontal direction of the stope of the one-step mine is composed of two parallel paths, and the number of paths in the vertical direction is determined by the height of the section. After the mining and filling of the one-step stope of the mine house in the panel is completed, it is transferred to the two-step pillar stope mining. The two sides of the two-step stope are the one-step cemented filling bodies, and the second-step pillar stope is pre-reinforced with long anchor cables. Efficient mining method for subsequent filling of segmented open fields in downward parallel deep holes. Although this method uses long anchor cables to pre-reinforce the two-step pillar stope, and adopts the method of segmented mining and filling, which improves the efficiency and safety of the two-step pillar stope mining to a certain extent, but This method of mining and filling still adopts the traditional method, and its mining efficiency has not been substantially improved, and the strength of the filling body is poor, which brings certain safety hazards to the operators.

因此,设计一种结构简单、安全性较强、回采效率高、生产能力强的二步骤机械化上向高分层充填采矿系统就很有必要。Therefore, it is necessary to design a two-step mechanized up-filling mining system with simple structure, strong safety, high recovery efficiency and strong production capacity.

实用新型内容Utility model content

为了克服上述问题,本实用新型提供了一种预控顶留护壁式的机械化上向高分层充填系统,该系统将采场自下而上分成若干个矿段,并将任意一个矿段自下而上分成若干个矿层,采用自下而上的高分层逐层回采,并在矿层回采完成后对矿层进行充填,当连续回采3至4层矿层后,对完成回采的最上层的矿层顶板采用长锚索作为支护。从而结合传统的上向分层充填法和分段充填法,将“单分层”高度变成“高分层(双分层高度)”,减少了整体的支护费用和工程量,提高采场的生产能力,并加快生产效率,缩短采场的作业循环时间。In order to overcome the above problems, the present utility model provides a pre-control top-retaining wall-type mechanized upward-to-high layered filling system, which divides the stope into several ore sections from bottom to top, and separates any ore section from the bottom to the top. It is divided into several ore layers from bottom to top, and the bottom-up high-layer mining is adopted layer by layer, and the ore layer is filled after the mining of the ore layer is completed. The roof is supported by long anchor cables. Therefore, combined with the traditional upward layered filling method and sub-layered filling method, the height of "single layer" is changed to "high layer (double layer height)", which reduces the overall support cost and engineering quantity, and improves the mining efficiency. The production capacity of the stope is improved, and the production efficiency is accelerated, and the operation cycle time of the stope is shortened.

为实现上述的目的,本实用新型采用的技术方案是:For realizing the above-mentioned purpose, the technical scheme that the utility model adopts is:

一种预控顶留护壁式的机械化上向高分层充填系统,采用所述的预控顶留护壁式的二步骤机械化上向高分层充填采矿方法,包括并列设置的若干采场、设置于所述采场外周壁的矿壁、设置于所述采场顶端的顶板、以及设置于所述顶板顶端的长锚索预控顶支护;A pre-control top-retaining wall-type mechanized upward high-layered filling system adopts the two-step mechanized upward-to-high layered filling mining method of the pre-control top-retaining wall type, comprising a plurality of stopes arranged in parallel, setting The mine wall on the outer peripheral wall of the stope, the roof set on the top of the stope, and the long anchor cable pre-controlled roof support set on the top of the roof;

任意一个所述采场包括自下而上分段设置的若干矿段,任意一个所述矿段包括自下而上分层设置的若干矿层,自下而上依次排列的三个相邻所述矿段构成一个采矿阶层。Any one of the stopes includes a number of ore sections arranged in sections from bottom to top, any one of the ore sections includes a number of ore layers arranged in layers from bottom to top, and three adjacent ore layers arranged in sequence from bottom to top. Sections form a mining hierarchy.

进一步的,任意一个所述矿层包括下部充填区域、以及设置于所述下部充填区域的顶端的上部充填区域;所述下部充填区域用于充填低强度配比的胶结充填体,所述上部充填区域用于充填高强度配比的胶结充填体。Further, any one of the ore layers includes a lower filling area and an upper filling area arranged at the top of the lower filling area; the lower filling area is used for filling a cemented filling body with a low strength ratio, and the upper filling area is It is used to fill cemented fillings with high strength ratios.

进一步的,位于最下方的所述采矿阶层的三个所述矿段的底端沿水平方向设置有下盘沿脉运输巷,所述下盘沿脉运输巷通过沿倾斜方向设置的采区斜坡道连通;位于最下方的三组所述下盘沿脉运输巷的远离矿区的一端通过沿竖直方向设置的溜井连通。Further, the bottom ends of the three mining sections of the lowermost mining strata are provided with a lower wall along the vein transportation road along the horizontal direction, and the lower wall along the vein transportation road passes through the mining area slope arranged in the inclined direction. One end of the three groups of the lowermost group of the lower wall conveying lanes along the veins, which is far away from the mining area, is communicated through the chute arranged in the vertical direction.

进一步的,位于所述采矿阶层的上下两端的所述下盘沿脉运输巷与所述采区斜坡道的连接位置处设置有中段运输巷,所述中段运输巷与所述下盘沿脉运输巷位于同一平面内,并彼此呈垂直状态设置;位于所述采矿阶层的中间位置处的所述下盘沿脉运输巷与所述采区斜坡道的连接位置处设置有分段运输巷,所述分段运输巷与所述下盘沿脉运输巷连通;所述矿层与所述中段运输巷以及所述分段运输巷之间设置有分层联络道。Further, a middle section transport roadway is provided at the connection position of the lower wall along the vein transportation road at the upper and lower ends of the mining stratum and the mining area ramp, and the middle section transportation roadway and the lower wall are transported along the vein. The lanes are located in the same plane and are arranged in a vertical state with each other; at the connection position of the lower wall along the vein transport lane and the mining area ramp at the middle position of the mining stratum, there is a segmented transport lane. The sectional transportation roadway is communicated with the lower wall along the vein transportation roadway; a layered communication road is arranged between the ore seam, the middle-section transportation roadway and the sectional transportation roadway.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:

1.本实用新型的预控顶留护壁式的机械化上向高分层充填系统,通过将采场自下而上分成若干个矿段,并将任意一个矿段自下而上分成若干个矿层,采用自下而上的高分层逐层回采,并在矿层回采完成后对矿层进行充填,当连续回采3至4层矿层后,对完成回采的最上层的矿层顶板采用长锚索作为支护。从而结合传统的上向分层充填法和分段充填法,将“单分层”高度变成“高分层 (双分层高度)”,减少了整体的支护费用和工程量,提高采场的生产能力,并加快生产效率,缩短采场的作业循环时间。1. The pre-controlled top-retaining wall-type mechanized up-to-high layered filling system of the present invention divides the stope into several ore sections from bottom to top, and divides any ore section into several ore layers from bottom to top , adopt bottom-up high-layered mining layer by layer, and fill the ore layer after the mining layer is completed. When 3 to 4 layers of ore layers are continuously recovered, the top plate of the uppermost layer of the ore layer after mining is completed. Long anchor cable is used as a support protect. Therefore, combined with the traditional upward layered filling method and sub-layered filling method, the height of "single layer" is changed to "high layer (double layer height)", which reduces the overall support cost and engineering quantity, and improves the mining efficiency. The production capacity of the stope is improved, and the production efficiency is accelerated, and the operation cycle time of the stope is shortened.

2.本实用新型的预控顶留护壁式的机械化上向高分层充填系统,通过对采场留设相应厚度的矿壁来回采二步骤采场,从而维持二步骤采场的整体稳定性,同时减少一步骤采场充填体强度不足等影响。2. The pre-control top-retaining wall-type mechanized up-to-high layered filling system of the present invention is used to mine the two-step stope back and forth by setting the mine wall of the corresponding thickness in the stope, thereby maintaining the overall stability of the two-step stope. , while reducing the impact of insufficient strength of the one-step stope filling.

3.本实用新型的预控顶留护壁式的机械化上向高分层充填系统,通过采用长锚索作为预控顶的支护方式来加固顶板,以实现顶板的预控重构,构建高分层采场安全作业的顶板环境。3. The pre-controlled top-retaining wall-type mechanized up-to-high layered filling system of the present invention reinforces the roof by using long anchor cables as the supporting method of the pre-controlled roof, so as to realize the pre-controlled reconstruction of the roof and construct a high-rise building. Roof environment for safe operation in layered stopes.

4.本实用新型的预控顶留护壁式的机械化上向高分层充填系统,通过将同一矿层采用不同的充填体进行充填,降低充填成本,矿层的底部可采用低强度配比的充填体进行充填,矿层的上部采用高强度胶结充填体浇面作为铲运机工作的平台,构筑上向水平高分层充填的作业条件。4. The pre-control top-retaining wall-type mechanized up-to-high layered filling system of the present invention reduces the filling cost by using different filling bodies for filling the same ore layer, and the bottom of the ore layer can use a filling body with a low strength ratio For filling, the upper part of the ore seam adopts the high-strength cemented filling body pouring surface as the working platform of the scraper to construct the working conditions of upward horizontal high-layer filling.

附图说明Description of drawings

图1是本实用新型的预控顶留护壁式的机械化上向高分层充填系统的结构示意图;Fig. 1 is the structure schematic diagram of the pre-control top retaining wall type mechanized upward high layered filling system of the present invention;

图2是本实用新型的预控顶留护壁式的机械化上向高分层充填系统的预控顶长锚索支护的布置示意图;Figure 2 is a schematic diagram of the arrangement of the pre-controlled top long anchor cable support of the pre-controlled top retaining wall-type mechanized upward high layered filling system of the present invention;

图3是图1中沿Ⅱ-Ⅱ方向的剖视示意图;Fig. 3 is the sectional schematic diagram along II-II direction in Fig. 1;

图4是图1中沿Ⅲ-Ⅲ方向的剖视示意图;Fig. 4 is the sectional schematic diagram along III-III direction in Fig. 1;

图5是本实用新型的预控顶留护壁式的机械化上向高分层充填方法的流程示意图;5 is a schematic flow chart of the pre-controlled top retaining wall-type mechanized upward-to-high layered filling method of the present invention;

附图中各部件的标记如下:11、底柱;12、间柱;13、滤水井;14、水平炮孔;15、充填回风井;16、长锚索;17、充填体;18、矿体;20、矿段;21、矿层;22、矿壁;23、中段运输巷;24、溜井;25、采区斜坡道;26、下盘沿脉运输巷;27、分段运输巷;28、分层联络道;29、采场联络道。The marks of the parts in the drawings are as follows: 11, bottom column; 12, inter-column; 13, water filtering well; 14, horizontal blasthole; 15, filling and return air well; 16, long anchor cable; 17, filling body; 18, ore body; 20, ore section; 21, ore seam; 22, mine wall; 23, transport road in the middle section; 24, chute; 28. Layered contact road; 29. Stope contact road.

具体实施方式Detailed ways

下面结合附图对本实用新型的较佳实施例进行详细阐述,以使本实用新型的优点和特征能更易于被本领域技术人员理解,从而对本实用新型的保护范围做出更为清楚明确的界定。显然,所描述的实施例仅仅是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所得到的所有其它实施例,都属于本实用新型所保护的范围。The preferred embodiments of the present utility model will be described in detail below in conjunction with the accompanying drawings, so that the advantages and features of the present utility model can be more easily understood by those skilled in the art, so that the protection scope of the present utility model can be more clearly defined. . Obviously, the described embodiments are only some of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

实施例1Example 1

如图1至3所示,一种预控顶留护壁式的机械化上向高分层充填系统100,包括并列设置的若干采场、设置于采场外周壁的矿壁22、设置于采场顶端的顶板、以及设置于顶板顶端的长锚索16预控顶支护。矿壁22的厚度设置为2~3m,从而维持二步骤采场的整体稳定性,同时减少一步骤采场充填体17强度不足等影响。长锚索16预控顶支护能够加固顶板,以实现顶板的预控重构,构建高分层采场安全作业的顶板环境。特别的,长锚索16预控顶支护的高度为3~4个矿层21的高度,并将长锚索16预控顶支护的网度设置为3.0×2.5m。即锚索排距为3.0m,间距为2.5m,在确认采场支护的安全后方可进行下一矿层21的回采作业。As shown in Figures 1 to 3, a pre-controlled top retaining wall type mechanized upward high layered filling system 100 includes several stopes arranged in parallel, a mine wall 22 arranged on the outer peripheral wall of the stope, and a stope arranged in the stope. The roof at the top and the long anchor cable 16 arranged at the top of the roof pre-control the roof support. The thickness of the mine wall 22 is set to be 2-3 m, so as to maintain the overall stability of the two-step stope, and at the same time reduce the influence of insufficient strength of the one-step stope filling body 17 . The long anchor cable 16 pre-controlled roof support can strengthen the roof to realize the pre-controlled reconstruction of the roof and build a roof environment for safe operation in high-layer stopes. In particular, the height of the pre-controlled top support of the long anchor cable 16 is the height of 3 to 4 mine layers 21, and the mesh size of the pre-controlled top support of the long anchor cable 16 is set to 3.0×2.5m. That is, the row spacing of the anchor cables is 3.0m, and the spacing is 2.5m, and the mining operation of the next layer 21 can be carried out after confirming the safety of the stope support.

如图3至4所示,在一些实施例中,任意一个采场包括自下而上分段设置的若干矿段20,任意一个矿段20包括自下而上分层设置的若干矿层21。特别的,矿段20的高度为20m,矿层21的高度为4~6m。分层控顶高度为6~8m,最下层的矿层21的采高为6~8m。As shown in FIGS. 3 to 4 , in some embodiments, any stope includes several ore sections 20 arranged in sections from bottom to top, and any ore section 20 includes several ore layers 21 arranged in layers from bottom to top. In particular, the height of the ore section 20 is 20m, and the height of the ore layer 21 is 4-6m. The height of the layered control roof is 6-8m, and the mining height of the bottom layer 21 is 6-8m.

矿层21的分层充填高度为2~3m,每次上分层回采结束后,再进行胶结充填。任意一个矿层21包括下部充填区域、以及设置于下部充填区域的顶端的上部充填区域。下部充填区域用于充填低强度配比的胶结充填体17,上部充填区域用于充填高强度配比的胶结充填体17。对同一矿层21采用不同的充填体17 充填,能够降低充填成本。矿层21的底部可采用低强度配比的充填体17进行充填,矿层21的上部采用高强度胶结充填体17浇面作为铲运机工作的平台,构筑上向水平高分层充填的作业条件。The layered filling height of the ore bed 21 is 2-3m, and cemented filling is performed after each upper layer mining is completed. Any one of the mineral layers 21 includes a lower backfill area and an upper backfill area provided at the top of the lower backfill area. The lower filling area is used for filling the cemented filling body 17 with a low strength ratio, and the upper filling area is used for filling the cemented filling body 17 with a high strength ratio. Using different filling bodies 17 to fill the same ore layer 21 can reduce the filling cost. The bottom of the ore layer 21 can be filled with a filling body 17 with a low strength ratio, and the upper part of the ore layer 21 can be filled with a high-strength cemented filling body 17 pouring surface as the working platform of the scraper to construct the working conditions of upward horizontal and high layered filling.

如图3至4所示,在一些实施例中,位于最下方的相邻三个矿段20构成下盘的采矿阶层,位于同一采矿阶层的三个矿段20的底端沿水平方向设置有下盘沿脉运输巷26,下盘沿脉运输巷26通过沿倾斜方向设置的采区斜坡道25连通,以实现各个矿段20的连通。位于最下方的三组下盘沿脉运输巷26的远离矿区的一端通过沿竖直方向设置的溜井24连通。溜井24是在脉外每隔100~150m 布置一条。As shown in FIGS. 3 to 4 , in some embodiments, the three adjacent ore sections 20 located at the bottom constitute the mining level of the lower wall, and the bottom ends of the three ore sections 20 located in the same mining level are provided along the horizontal direction with The lower wall along the vein transportation road 26, the lower wall along the vein transportation road 26 is connected by the mining area ramp 25 set along the inclined direction, so as to realize the communication of each mining section 20. The ends of the lowermost three groups of lower-wall along-vein transport lanes 26 that are far away from the mining area are communicated through a chute 24 arranged in the vertical direction. The chute 24 is arranged every 100-150m outside the vein.

位于采矿阶层的上下两端的下盘沿脉运输巷26与采区斜坡道25的连接位置处设置有中段运输巷23,中段运输巷23与下盘沿脉运输巷26连通,以将不同的采场连通。位于采矿阶层的中间位置处的下盘沿脉运输巷26与采区斜坡道 25的连接位置处设置有分段运输巷27,分段运输巷27与下盘沿脉运输巷连通。矿层21与中段运输巷23以及分段运输巷27之间设置有分层联络道28,以将采场与分段运输巷27连通。各个采场均通过采场联络道29与下盘沿脉运输巷26 连通。A middle section transport road 23 is provided at the connection position of the lower wall along the vein transport road 26 at the upper and lower ends of the mining stratum and the mining area slope 25, and the middle section transport road 23 is communicated with the lower wall along the vein transport road 26, so as to connect different mining areas. Field connectivity. At the connection position of the lower wall along-vein transport road 26 at the middle position of the mining level and the mining area slope 25, a sub-section transport road 27 is provided, and the sub-section transport road 27 communicates with the lower wall along the vein transport road. A layered communication road 28 is provided between the mine seam 21 , the middle section transportation road 23 and the subsection transportation roadway 27 , so as to connect the stope with the subsection transportation roadway 27 . Each stope is connected with the transportation lane 26 along the vein of the lower wall through the stope connection road 29 .

如图3至4所示,并参阅图1,在一些实施例中,矿体18的顶端沿竖直方向设置有充填回风井15。采场的左侧两端设置有滤水井13。新鲜的空气从滤水井13的底端进入采场,对工作面进行清洗。同时,污风从充填回风井15回到上中段回风巷内。采场内可由局扇辅助通风,确保良好的作业环境。As shown in FIGS. 3 to 4 , and referring to FIG. 1 , in some embodiments, the top end of the ore body 18 is provided with a filling and return air shaft 15 along the vertical direction. The left ends of the stope are provided with water filtering wells 13 . Fresh air enters the stope from the bottom end of the water filtering well 13 to clean the working face. At the same time, the dirty air is returned to the upper and middle return air lanes from the filling return air shaft 15 . Local fans can be used to assist ventilation in the stope to ensure a good working environment.

如图5所示,一种采用上述预控顶留护壁式的机械化上向高分层充填系统的预控顶留护壁式的二步骤机械化上向高分层充填采矿方法,包括以下步骤:As shown in FIG. 5 , a two-step mechanized upward high-layered filling mining method using the above-mentioned pre-controlled jacking and retaining wall-type mechanized up-to-high-layered filling system, comprising the following steps:

S1、将二步骤间柱12划分为若干个采场,并在相邻两个采场之间设置矿壁 22。S1. The second-step inter-column 12 is divided into several stopes, and a mine wall 22 is set between two adjacent stopes.

在本步骤中,留设间柱12的宽度设置为4~6m,采场沿矿体18走向布置,并将采场的长度设置为40m,其宽度设置为12m,矿壁22的厚度为2~3m。In this step, the width of the retaining column 12 is set to 4-6m, the stope is arranged along the trend of the ore body 18, the length of the stope is set to 40m, its width is set to 12m, and the thickness of the mine wall 22 is 2 ~3m.

S2、将任意一个采场自下而上划分为若干个矿段20,并将任意一个矿段20 自下而上划分为若干个矿层21。S2. Divide any stope into several ore sections 20 from bottom to top, and divide any ore section 20 into several ore layers 21 from bottom to top.

在本步骤中,将采场由上至下分为上中下三段采矿阶层,单个采矿阶层的高度为40~60m。每个采矿阶层包括多个矿段20。矿段20的高度为20m,矿层 21的高度为4~6m。当采场回采超过2~3个矿层21后,方可回采相邻采场。采场的底端设置有底柱11,底柱11的高度设置为6m,并不设顶柱。In this step, the stope is divided into upper, middle and lower mining strata from top to bottom, and the height of a single mining stratum is 40-60m. Each mining tier includes a plurality of blocks 20 . The height of the ore section 20 is 20m, and the height of the ore layer 21 is 4-6m. When the stope mining exceeds 2 to 3 ore layers 21, the adjacent stope can be mined. The bottom end of the stope is provided with a bottom column 11, the height of the bottom column 11 is set to 6m, and no top column is provided.

S3、对采场进行切割,并在采场的上向高分层顶板处设置预控顶支护。S3. Cut the stope, and set up pre-control roof support at the upper and higher layered roof of the stope.

在本步骤中,预控顶支护为长锚索16预控顶支护,长锚索16预控顶支护的高度为3~4个矿层21的高度,并将长锚索16预控顶支护的网度设置为3.0 ×2.5m。即锚索排距为3.0m,间距为2.5m,在确认采场支护的安全后方可进行下一矿层21的回采作业。In this step, the pre-control top support is the long anchor cable 16 pre-control top support, the height of the long anchor cable 16 pre-control top support is the height of 3 to 4 mine layers 21, and the long anchor cable 16 is pre-controlled The mesh size of the top support is set to 3.0 × 2.5m. That is, the row spacing of the anchor cables is 3.0m, and the spacing is 2.5m, and the mining operation of the next layer 21 can be carried out after confirming the safety of the stope support.

S4、对位于最下层的矿层21进行回采。S4, mining the ore layer 21 located in the lowest layer.

S5、对上一次回采完后的矿层21进行充填,并在充填完成后对位于矿层21 上一层的矿层21进行回采。S5 , backfill the ore seam 21 after the last mining, and after the filling is completed, carry out the mining of the ore seam 21 located one layer above the ore seam 21 .

在本步骤中,回采采用沿矿体18走向内全面回采的方式,并进行自下而上的高分层逐层回采,分层控顶高度为6~8m,最下层的矿层21的采高为6~8m。In this step, the mining adopts the method of comprehensive mining along the direction of the ore body 18, and carries out high-layer-by-layer mining from bottom to top. 6 to 8m.

回采过程包括凿岩与爆破两个阶段。具体来讲,采用Boomer281全液压凿岩台车机械化且智能化地钻凿水平炮孔14,以提高凿岩效率。压顶采用亚光面控制爆破,保证顶板平整与稳定。凿岩结束后,清洁炮孔,采用人工装药,炸药采用2#岩石炸药,起爆器击发导爆管雷管,导爆管雷管再引爆导爆索,由导爆索起爆每个炮孔中敷设的导爆管雷管,引爆炸药。The mining process includes two stages: rock drilling and blasting. Specifically, the Boomer 281 full hydraulic rock drilling rig is used to mechanically and intelligently drill the horizontal blasthole 14 to improve the rock drilling efficiency. The top pressing adopts a matte surface to control blasting to ensure the flatness and stability of the top plate. After the rock drilling is completed, clean the blasthole, use artificial charge, and use 2# rock explosive as the explosive. The detonator fires the detonating tube detonator, and the detonating tube detonator detonates the detonating cord, which is detonated by the detonating cord and laid in each blasthole. The detonator detonator, detonates the explosive.

回采是由铲运机运输矿石,铲运机由分段运输巷27经分层联络道28进入采场装矿,铲取矿石后直接卸往脉外溜井24,经电机车运至主溜井24。当采场顺路溜井24暴露出来后,则由脉内顺路溜井24出矿。In mining, the ore is transported by the scraper. The scraper enters the stope from the sectional transport lane 27 through the layered communication road 28 to load the ore. . When the stope runner 24 is exposed, the ore is extracted from the runner 24 in the vein.

在本步骤中,对每个矿层21采用分级充填的方式,其充填高度为2~3m,以对其下一矿层21预留2~3m的回采空间。矿层21的底部采用低强度配比的胶结充填体17进行充填;矿层21的顶部采用高强度配比的胶结充填体17进行充填,其充填高度为0.5~1m。矿层21的上部采用高强度胶结充填体17浇面作为铲运机工作的平台,构筑上向水平高分层充填的作业条件。In this step, a graded filling method is adopted for each ore layer 21, and the filling height is 2-3m, so as to reserve 2-3m of recovery space for the next ore layer 21. The bottom of the ore layer 21 is filled with cemented filling body 17 with low strength ratio; the top of the ore layer 21 is filled with cemented filling body 17 with high strength ratio, and the filling height is 0.5-1 m. The upper part of the ore bed 21 adopts the pouring surface of the high-strength cemented filling body 17 as the working platform of the scraper, and constructs the working conditions of upward-level and high-layered filling.

充填是在每个矿层21的矿石清理完毕后,根据充填的要求,进行充填准备及充填作业。在分层联络巷内砌筑充填挡墙,充填管道从每个采场的充填回风井15进入采场进行充填,并预留2~3m的作业空间。井下掘进的废石可就近充填于采空区,采场中的废石留在采场充填。Filling is to carry out filling preparation and filling operation according to filling requirements after the ore of each ore layer 21 is cleaned up. The backfill retaining wall is built in the layered contact roadway, and the backfill pipeline enters the stope from the backfill air well 15 of each stope for backfilling, and a working space of 2-3m is reserved. The waste rock excavated underground can be filled in the goaf nearby, and the waste rock in the stope can be filled in the stope.

S6、重复步骤S5,直至连续对3~4个矿层21完成回采。S6. Step S5 is repeated until the mining of 3 to 4 mineral layers 21 is completed continuously.

S7、在完成回采后的最上层矿层21的顶板处设置预控顶支护。S7. Pre-control roof support is arranged on the roof of the uppermost ore layer 21 after the mining is completed.

在本步骤中,预控顶支护采用长锚索16的支护方式,并在3~4个矿层21 完成回采后,安装长锚索16预控顶支护,能够保证回采充填过程的安全性。In this step, the long anchor cable 16 is used for the pre-control top support, and after the mining of 3 to 4 layers 21 is completed, the long anchor cable 16 is installed for the pre-control top support, which can ensure the safety of the mining and filling process. sex.

S8、依次重复步骤S5、S6、以及S7,直至回采至采场的顶板。S8. Repeat steps S5, S6, and S7 in sequence until mining reaches the roof of the stope.

以上所述仅用以说明本实用新型的技术方案,而非对其进行限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;凡是利用本实用新型说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本实用新型的专利保护范围内。The above is only used to illustrate the technical solution of the present invention, rather than to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still be used for the foregoing implementation. The technical solutions described in the examples are modified, or some or all of the technical features thereof are equivalently replaced; any equivalent structure or equivalent process transformation made by using the contents of the description and drawings of the present utility model, or directly or indirectly used in other related The technical field of the present invention is similarly included in the scope of patent protection of the present invention.

Claims (4)

1.一种预控顶留护壁式的机械化上向高分层充填系统,其特征在于,包括并列设置的若干采场、设置于所述采场外周壁的矿壁(22)、设置于所述采场顶端的顶板、以及设置于所述顶板顶端的长锚索(16)预控顶支护;1. a pre-control top retaining wall-type mechanized upward high layered filling system is characterized in that, comprising several stopes arranged in parallel, a mine wall (22) arranged on the outer peripheral wall of the stope, The roof at the top of the stope, and the long anchor cable (16) pre-controlled roof support arranged at the top of the roof; 任意一个所述采场包括自下而上分段设置的若干矿段(20),任意一个所述矿段(20)包括自下而上分层设置的若干矿层(21),自下而上依次排列的三个相邻所述矿段(20)构成一个采矿阶层。Any one of the stopes includes a number of ore sections (20) arranged in sections from bottom to top, and any one of the ore sections (20) includes a number of ore layers (21) arranged from bottom to top in layers, from bottom to top Three adjacent said ore sections (20) arranged in sequence constitute a mining stratum. 2.根据权利要求1所述的预控顶留护壁式的机械化上向高分层充填系统,其特征在于,任意一个所述矿层(21)包括下部充填区域、以及设置于所述下部充填区域的顶端的上部充填区域;所述下部充填区域用于充填低强度配比的胶结充填体(17),所述上部充填区域用于充填高强度配比的胶结充填体(17)。2. The pre-control top retaining wall-type mechanized upward high-layered filling system according to claim 1, wherein any one of the ore layers (21) comprises a lower filling area, and is arranged in the lower filling area The upper filling area at the top of the upper filling area; the lower filling area is used for filling the cemented filling body (17) with low strength ratio, and the upper filling area is used for filling the cement filling body (17) with high strength ratio. 3.根据权利要求2所述的预控顶留护壁式的机械化上向高分层充填系统,其特征在于,位于最下方的所述采矿阶层的三个所述矿段(20)的底端沿水平方向设置有下盘沿脉运输巷(26),所述下盘沿脉运输巷(26)通过沿倾斜方向设置的采区斜坡道(25)连通;位于最下方的三组所述下盘沿脉运输巷(26)的远离矿区的一端通过沿竖直方向设置的溜井(24)连通。3. The pre-controlled top-retaining wall-type mechanized up-to-high layered filling system according to claim 2, characterized in that, the bottom ends of the three mining sections (20) of the lowest mining layer are located at the bottom The lower wall along the vein transportation lane (26) is arranged along the horizontal direction, and the lower wall along the vein transportation lane (26) is connected by the mining area ramp (25) arranged along the inclined direction; One end of the disk along the vein transport road (26) away from the mining area is communicated through a chute (24) arranged in the vertical direction. 4.根据权利要求3所述的预控顶留护壁式的机械化上向高分层充填系统,其特征在于,位于所述采矿阶层的上下两端的所述下盘沿脉运输巷(26)与所述采区斜坡道(25)的连接位置处设置有中段运输巷(23),所述中段运输巷(23)与所述下盘沿脉运输巷(26)位于同一平面内,并彼此呈垂直状态设置;位于所述采矿阶层的中间位置处的所述下盘沿脉运输巷(26)与所述采区斜坡道(25)的连接位置处设置有分段运输巷(27),所述分段运输巷(27)与所述下盘沿脉运输巷(26)连通;所述矿层(21)与所述中段运输巷(23)以及所述分段运输巷(27)之间设置有分层联络道(28)。4. The pre-controlled top-retaining wall-type mechanized upward high layered filling system according to claim 3, characterized in that, the lower wall along the vein transportation roadway (26) located at the upper and lower ends of the mining layer and the A middle section transportation road (23) is provided at the connection position of the slope road (25) in the mining area. The vertical state is arranged; a sectioned transportation road (27) is provided at the connection position of the lower wall along the vein transportation road (26) and the mining area ramp (25) at the middle position of the mining stratum. The sectional transportation roadway (27) is communicated with the lower wall along the vein transportation roadway (26); the ore seam (21) is arranged between the middle section transportation roadway (23) and the sectional transportation roadway (27). There are tiered contact channels (28).
CN202122923784.3U 2021-11-25 2021-11-25 Pre-control top retaining wall protection type mechanized upward high-layering filling system Active CN216240788U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122923784.3U CN216240788U (en) 2021-11-25 2021-11-25 Pre-control top retaining wall protection type mechanized upward high-layering filling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122923784.3U CN216240788U (en) 2021-11-25 2021-11-25 Pre-control top retaining wall protection type mechanized upward high-layering filling system

Publications (1)

Publication Number Publication Date
CN216240788U true CN216240788U (en) 2022-04-08

Family

ID=80955960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122923784.3U Active CN216240788U (en) 2021-11-25 2021-11-25 Pre-control top retaining wall protection type mechanized upward high-layering filling system

Country Status (1)

Country Link
CN (1) CN216240788U (en)

Similar Documents

Publication Publication Date Title
CN103557002B (en) A kind of mechanized concentrates drop shaft filling-up method
CN109236295B (en) A three-step mining method suitable for deep thick and large deposits
CN101105129B (en) Mining Environment Reconstruction Continuous Mining Followed by Fill Mining
CN106223958B (en) The slant middle thick orebody subregion rock drilling stage falls ore deposit afterwards filling collaboration mining codes
CN101858217B (en) House pillar changeable panel upward demix filling mining method
CN1260461C (en) Continuous mining method of stepped sectional extruding and ore caving followed by filling
CN101818643B (en) Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN112796758B (en) Open stoping subsequent filling mining method at deep hole stage in high-section no-cutting raise pull groove
CN107869349A (en) A kind of mechanized mining method of gently inclined medium thick orebody
CN101871347A (en) Reconstruction of mining environment Layered and striped middle and deep hole drop mining method
CN103306720A (en) Inclined layered solid filling coal mining method for ultra-thick coal seam
CN102606159A (en) Medium thick heavy-pitch crushed ore body frame type artificial top downward segmenting cemented filling method
CN102619513A (en) Room and pillar type medium-length hole filling mining method using bottom ore withdrawal structures simultaneously arranged in original rock
CN102678121A (en) Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN109577979B (en) High-ground-stress large ore body downward segmented filling mining method
CN103615250A (en) Subsection-studding all-open-stoping backfilling collaborative mining method
CN109209490B (en) Working face withdrawing method for gangue filling auxiliary end mining stage
CN112682041A (en) Filling mining method for upper-wall-breaking gentle-inclination thick and large ore body
CN114592867A (en) Temporary top pillar induced caving and sill pillar-free sublevel caving combined mining method
CN116877081A (en) High-efficiency deep hole mining method for deep broken rock mass large span based on lithology improvement
CN116291444A (en) Safe, efficient and low-lean mining method
CN109931063B (en) Upward step-by-step staggered filling mining method
CN113187482B (en) Upward mining quasi-downward drift filling mining method
CN111894667B (en) Upward double-layered approach filling mining method for broken ore body with recoverable supports
CN216240788U (en) Pre-control top retaining wall protection type mechanized upward high-layering filling system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant