CN216075270U - Anti installation coupling assembling that floats of newly-built basement - Google Patents
Anti installation coupling assembling that floats of newly-built basement Download PDFInfo
- Publication number
- CN216075270U CN216075270U CN202121880135.3U CN202121880135U CN216075270U CN 216075270 U CN216075270 U CN 216075270U CN 202121880135 U CN202121880135 U CN 202121880135U CN 216075270 U CN216075270 U CN 216075270U
- Authority
- CN
- China
- Prior art keywords
- basement
- anchoring
- steel strand
- newly
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims description 19
- 230000008878 coupling Effects 0.000 title claims description 3
- 238000010168 coupling process Methods 0.000 title claims description 3
- 238000005859 coupling reaction Methods 0.000 title claims description 3
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 92
- 239000010959 steel Substances 0.000 claims abstract description 92
- 238000004873 anchoring Methods 0.000 claims abstract description 43
- 238000007667 floating Methods 0.000 claims abstract description 33
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 21
- 238000013461 design Methods 0.000 claims description 12
- 238000004804 winding Methods 0.000 claims description 3
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 230000002787 reinforcement Effects 0.000 description 28
- 238000010276 construction Methods 0.000 description 15
- 239000004567 concrete Substances 0.000 description 13
- 238000011065 in-situ storage Methods 0.000 description 11
- 239000004576 sand Substances 0.000 description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 9
- 238000000034 method Methods 0.000 description 7
- 239000002689 soil Substances 0.000 description 7
- 230000008569 process Effects 0.000 description 6
- 239000004575 stone Substances 0.000 description 5
- 238000004140 cleaning Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 239000004568 cement Substances 0.000 description 3
- 201000010099 disease Diseases 0.000 description 3
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 3
- 238000005553 drilling Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 239000004035 construction material Substances 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000013507 mapping Methods 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 230000001502 supplementing effect Effects 0.000 description 2
- 230000008719 thickening Effects 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 241001391944 Commicarpus scandens Species 0.000 description 1
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008602 contraction Effects 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical group C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000013049 sediment Substances 0.000 description 1
Images
Landscapes
- Foundations (AREA)
Abstract
The utility model relates to a newly-built basement anti-floating mounting and connecting assembly, which comprises a basement foundation, a pile foundation and a reinforcing mesh, wherein the basement foundation comprises a cross-center area and a support area which are integrally formed and connected with each other, the reinforcing mesh is arranged in the foundation, and the newly-built basement anti-floating mounting and connecting assembly further comprises: the anchoring part is provided with a plurality of anchoring holes and threaded holes, the anchoring part is arranged in the support area and is positioned near the support area, the anchoring holes are formed in the anchoring part, bolts sequentially penetrate through the threaded holes of the anchoring part and the reinforcing mesh and are in threaded connection with nuts, the steel strand comprises a horizontal section and an inclined section, an included angle between the horizontal section and the inclined section is an obtuse angle, the horizontal section is positioned above the inclined section, the free end of the inclined section is anchored in the anchoring holes, a fixing part is fixedly arranged in the cross-center area and is fixedly connected to the free end of the horizontal section of the steel strand, and a prestress tensioning part provides tensioning prestress for the steel strand.
Description
Technical Field
The utility model relates to the technical field of construction of newly-built basements, in particular to an anti-floating mounting and connecting assembly for a newly-built basement.
Background
With the rapid development of social economy, new technologies and new materials are widely applied to building engineering projects, the more deep the basement of a newly built building is built, the more deep the basement is built, the deep excavated basement cannot be influenced by underground water level, and particularly, the basement bottom plate is easy to deform, crack, seep water and other diseases under the direct action of high-pressure underground water, so that the safety and normal use of the structure are influenced. For the above-mentioned diseases, the conventional methods of thickening the bottom plate, pressing weight to resist floating, supplementing an anti-floating anchor rod behind a waterproof plate to resist floating, draining and reducing pressure are generally adopted, but the conventional method is adopted to solve the above-mentioned basement bottom plate anti-floating diseases and can also produce the following problems: 1. thickening the bottom plate and resisting floating by weight: the increased thickness of the bottom plate can reduce the clear height of the basement, so that the use is influenced; 2. and (3) supplementing an anti-floating anchor rod behind the waterproof plate for anti-floating: the existing basement structure is formed, pressure underground water can gush out when the bottom plate is perforated, silt below the foundation can be brought out accordingly, the bottom of the foundation can be hollowed out seriously, the bearing capacity of the existing structural foundation is influenced, the structural potential safety hazard is generated, and the existing waterproof plate can be prevented from being damaged by anchor rod drilling and cannot be recovered. 3. Draining and reducing pressure: the anti-floating problem cannot be fundamentally solved, the drainage ditch and the drainage facility need to be regularly enclosed, the operation cost is high, and the method is suitable for the soil layer with the upper layer of stagnant water and lower water permeability, wherein the underground water is the soil layer;
in order to solve the problems, Chinese patent CN201310483570.6 appears later, which discloses a high-seepage-proofing anti-floating pile raft structure, which is characterized in that a prestressed hollow pipe section is arranged at the upper part of a cast-in-situ bored pile, the prestressed hollow pipe section is concentric with the cast-in-situ bored pile, and a reinforcement cage of the cast-in-situ bored pile penetrates through the prestressed hollow pipe pile section and extends into a raft foundation to be connected with a reinforcement in the raft; the inner side of the prestressed hollow pipe section is provided with an internal connecting rib; laying a sand cushion layer and a broken stone blind ditch on the upper part of the foundation soil; the raft foundation is sequentially provided with a horizontal water-resisting layer, a cement soil plate and a reinforced concrete raft from bottom to top; and a reinforced material is fixedly connected between the foundation pit fender post and the wall body of the side wall of the basement. The utility model not only can enhance the integrity and the strength of the upper structure, but also can reduce the uplift pressure of underground water and fully utilize the waste slurry of the cast-in-situ bored pile to realize waste utilization; the prestressed hollow pipe section is arranged at the top of the pile body, so that a pile cutting process of the cast-in-situ bored pile can be omitted, and the construction efficiency is improved. The utility model also discloses a construction method of the high-seepage-proofing anti-floating pile raft structure;
however, in the actual operation process, the utility model still has certain problems: according to the technical scheme disclosed by the patent, when the patent is implemented, before concrete is poured into a reinforcement cage, a hollow pipe needs to be fixedly connected to the reinforcement cage, then the concrete is poured, the fixation of the hollow pipe and the reinforcement cage is further realized, then anchor cables are driven into the hollow pipe by adopting expansion bolts and are fixed with the concrete, and finally, a steel strand is adopted between the two anchor cables for prestress tensioning;
in the process, firstly, the hollow pipe and the reinforcement cage need to be fixed, and the inclined arrangement of the anchor rod can be ensured only when the hollow pipe needs to be inclined, therefore, when the hollow pipe and the reinforcement cage are primarily fixed, a specific connecting piece is required to be adopted for fixed connection, secondly, the fixed connection of the anchor cable and the steel strand is important, because the pre-tightening tension of the steel strand directly determines the anti-floating effect of the basement, the pre-tightening tension of the steel strand is determined by the anchor cable, the pre-tightening tension of the steel strand between the two anchor cables can be adjusted by adjusting the extension and contraction of the anchor cable in the hollow pipe, and the connecting piece between the anchor cable and the steel strand can be realized by special parts, the special part not only plays a role in connection, but also plays a role in conveniently adjusting the pre-tightening tension of the steel strand, and in conclusion, the construction process and the materials for providing the pre-tightening tension for the steel strand are complex;
for this reason, there is an urgent need to solve the existing problems.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problems, the utility model aims to provide a newly-built basement anti-floating mounting and connecting assembly to solve the technical problem that the construction process and materials for providing pre-tightening tension for steel strands are complex.
In order to achieve the above object, in one aspect, the present invention provides a newly-built basement anti-floating installation connection assembly, including a basement foundation and a reinforcing mesh, where the basement foundation includes a span region and a support region that are integrally formed and connected to each other, and the reinforcing mesh is disposed in the foundation, further including:
the anchoring piece is fixedly connected with the reinforcing mesh and arranged near the support area, and an anchoring connection hole is formed in the anchoring piece;
the steel strand comprises a horizontal section and an inclined section, an included angle between the horizontal section and the inclined section is an obtuse angle, the horizontal section is positioned above the inclined section, and the free end of the inclined section is anchored in the anchoring hole;
the fixing piece is fixedly arranged on the middle spanning area and is fixedly connected to the free end of the horizontal section of the steel strand;
and the prestress tensioning piece provides tensioning prestress for the steel strand.
Still further preferably, the anchor comprises:
the base is provided with a threaded hole;
the anchorage device is integrally formed on the base, and the anchorage hole is arranged on the base and the anchorage device in a penetrating manner;
and the bolt sequentially passes through the threaded hole of the anchoring piece and the reinforcing mesh and is in threaded connection with the nut.
Further preferably, each strand of steel strand is formed by three steel wires intertwined with each other.
Preferably, the fixing part comprises a permanent anchor and two finished anchorage devices, and the permanent anchor and the finished anchorage devices are provided with anchor holes for the steel strand to pass through;
the steel strand anchor is characterized by further comprising a movable seat and a fixed seat, wherein grooves for the steel strand to pass through are formed in the movable seat and the fixed seat, and the movable seat and the fixed seat are arranged between the finished anchor and the permanent anchor and fixedly connected with the finished anchor.
Preferably, the prestress tension member is two jacks, and the two jacks are arranged between the movable seat and the fixed seat and drive the movable seat to move.
It is further preferred that said anchor openings are of a tapered design, and that part of said anchor openings of said permanent anchors are oriented oppositely to the remaining anchor openings.
Still further preferably, the underground basement foundation further comprises a leveling layer, wherein the leveling layer is arranged on the surface of the basement foundation and submerges the prestress tension piece, the fixing piece and the horizontal section of the steel strand.
Further preferably, the anti-floating support is applied to basement anti-floating, four adjacent support areas of a basement foundation are selected, and a prestress tension member, a fixing member and a plurality of steel strands are arranged between the adjacent support areas and the opposite support areas respectively.
In order to achieve the above object, another aspect of the present invention provides an anti-floating construction method for a newly-built basement, comprising the following steps:
s1: preparation before construction: cleaning a construction site according to a design drawing, mapping the position of a pile body, and organizing construction materials, machinery and personnel to be in place;
s2: excavation of a foundation pit: digging a foundation pit fender pile at a designed position, according to the calculated discharge amount of cement soil formed by curing slurry generated during construction of a cast-in-situ bored pile in a foundation pile, overetching to a proper depth, and finishing;
s3: laying a sand cushion and a broken stone blind ditch: uniformly paving a sand cushion layer with the thickness of 300-700 mm on the upper part of the foundation soil, and uniformly arranging drainage broken stone blind ditches at intervals in the vertical direction and the horizontal direction in the sand cushion layer;
s4: forming a hole by using the cast-in-situ bored pile: special hole forming equipment is adopted for hole forming according to design requirements, the vertical precision of the hole forming of the pile body is ensured, and the pile length, the pile position deviation and the hole forming depth meet the design requirements;
s5: sinking a steel reinforcement cage: after the hole cleaning of the cast-in-situ bored pile is finished, sinking the reinforcement cage into the hole by adopting hoisting equipment, and controlling the top elevation and the hoisting quality of the reinforcement cage;
s6: paving a reinforcing mesh, paving the reinforcing mesh on the sand cushion layer, and mutually binding the reinforcing mesh and the reinforcement cage;
s7: installing an anchoring piece, wherein the anchoring piece is installed on the steel bar net close to the steel bar cage through bolts and nuts;
s8: installing steel strands, installing a plurality of steel strands on each anchoring part, wherein each steel strand is provided with an inclined section and a horizontal section, an included angle between the inclined section and the horizontal section is an obtuse angle, and the horizontal section is positioned above the inclined section;
s9: pouring concrete: drilling a bored pile hole until a part of the inclined section of the steel strand is submerged to form the foundation, and properly vibrating and compacting concrete in the pouring process;
s10: applying a steel strand tensioning prestress, fixedly mounting one fixed seat on the surface of a mid-span area of a foundation through an anchor rod, enabling the steel strand on one anchor piece on an adjacent steel reinforcement cage to pass through one fixed seat and be anchored on the permanent anchor, enabling the steel strand on the other anchor piece on the adjacent steel reinforcement cage to pass through one movable seat and be anchored on the permanent anchor, fixing the fixed end of a jack on the fixed seat, fixing the movable end of the jack with the movable seat, driving the jack to enable the movable seat to move, applying the tensioning prestress on the horizontal section of the steel strand, anchoring the movable seat on concrete through the anchor rod, and taking out the jack;
s11: applying tension prestress of all steel strands in the underground chamber, forming a rectangular reinforcement cage group by taking four reinforcement cages as vertexes according to the positions of the reinforcement cages, connecting every two of the four vertexes of the reinforcement cage group to form an installation connecting line, and implementing the step S10 on the installation connecting line to realize the tension prestress application of all the steel strands in the underground chamber;
s12: leveling, concrete is laid on the foundation, so that the movable seat and the fixed seat are submerged by the concrete.
Compared with the prior art, the utility model has the beneficial effects that:
(I): one end of the steel strand is anchored on the support area by arranging the anchoring part, the other end of the steel strand is anchored on the fixing part of the midspan area, and the prestress tensioning part provides tensioning prestress for the steel strand, so that the buoyancy of the midspan area is finally transferred into the support area;
(II): because tensioning prestress needs to be applied to the steel strands, the value of the tensioning prestress is large, and the base is connected to the steel bar net by bolts, so that the connection between the base and the steel bar net cannot be influenced even if the value of the tensioning prestress of the steel strands is large according to the principle of the jack, and the strength of the anchoring piece is enhanced by adopting an integrated forming design between the base and the anchorage device, so that the anchoring piece is prevented from being broken by the steel strands due to the large value of the tensioning prestress;
(III): the steel strand is through adopting three copper wires intertwine thereby can promote its tensile strength, and when prestressing force tensioning member provided the stretch-draw prestressing force for the steel strand, the steel strand was difficult for the rupture.
(IV): permanent anchor plays through adopting the toper design to make steel strand wires when the anchor, and the anchor that can be comparatively stable is on permanent anchor, and when jack drive sliding seat removed, at this moment, the steel strand wires obtained stretch-draw prestressing force, because the anchor eye orientation of permanent anchor is opposite, consequently, after removing the jack, because permanent anchor both sides atress is balanced, the phenomenon of kick-backing can not appear in permanent anchor.
Drawings
FIG. 1 is a construction layout of an anti-floating installation and connection assembly for a newly-built basement according to the present invention;
fig. 2 is a cross-sectional view at a in fig. 1 of a newly-built basement anti-floating installation and connection assembly of the utility model;
fig. 3 is a schematic connecting diagram of the anchoring member of fig. 2 of the anti-floating installation and connection assembly for the newly-built basement;
fig. 4 is a schematic view of the connection between the fixing member and the prestressed tension member of fig. 2 of the anti-floating installation and connection assembly for a newly-built basement.
In the figure: 1. basement foundation; 11. a mid-span area; 12. a pedestal region; 3. a reinforcing mesh; 4. an anchoring member; 41. a base; 411. a threaded hole; 42. an anchorage device; 421. an anchoring hole; 5. steel strand wires; 6. a fixing member; 61. a permanent anchor; 62. finishing the anchorage device; 621. an anchor eye; 63. a movable seat; 64. a fixed seat; 7. a pre-stressed tension member.
Detailed Description
To explain the technical content, structural features, attained objects and effects of the present invention in detail, embodiments are described below in detail with reference to the accompanying drawings.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate orientations or positional relationships based on those shown in the drawings, and are used merely for convenience in describing the present invention and for simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be taken as limiting the scope of the present invention.
The support area 12 of the basement foundation 1 is provided with the pile foundation below, so that the compressive strength of the support area is high, sediment and underground water below the support area 12 cannot influence the support area 12, and the midspan area 11 is not supported by the pile foundation below the midspan area 11, so that the basement foundation 1 at the midspan area 11 is poor in stability and the technical problem described by the background art is easy to occur;
the permanent anchor 61 is used for locking the tensioning prestress obtained by the steel strand 5 and comprises an anchorage device 42 and a base 41, wherein six anchor holes 621 which are arranged in an equal circumferential array are formed in the permanent anchor 61, the six anchor holes 621 adopt a conical design, the directions of the three anchor holes 621 are towards the left, the directions of the rest three anchor holes 621 are towards the right, and the anchor holes 621 of the permanent anchor 61 face to the opposite directions, so that after the jack is removed, the permanent anchor 61 cannot rebound due to the fact that the two sides of the permanent anchor 61 are stressed in a balanced manner;
the anchoring member 4 is used for fixedly connecting one end of the steel strand 5 with the steel mesh 3, as shown in fig. 3, and comprises a base 41 and an anchoring device 42, wherein the base 41 and the anchoring device 42 are integrally formed, so that the strength of the anchoring member 4 can be ensured, the steel strand 5 cannot be broken when being tensioned and prestressed, and six threaded holes 411 are formed in the base 41; the base 41 and the anchorage device 42 are provided with a through anchorage hole 421;
the fixing piece 6 is fixedly arranged on the middle span area 11 through an anchor rod and is used for being connected with the steel strand 5, as shown in fig. 4, the fixing piece comprises a permanent anchor 61, a movable seat 63, a fixed seat 64 and two finished product anchors 62, wherein anchor holes 621 for the steel strand 5 to pass through are formed in the permanent anchor 61 and the finished product anchors 62, grooves for the steel strand 5 to pass through are formed in the movable seat 63 and the fixed seat 64, and the finished product anchors 62 are fixedly connected with the fixed seat 64 or the movable seat 63 through bolts;
the steel strand 5 is used for transferring buoyancy of the middle crossing area 11 into the support area 12 and is formed by winding three steel wires, the steel strand 5 can improve tensile strength by winding the three steel wires, when the prestress tension piece 7 provides tension prestress for the steel strand 5, the steel strand 5 is not easy to break and comprises a horizontal section and an inclined section, an included angle between the horizontal section and the inclined section is an obtuse angle, and the horizontal section is positioned above the inclined section;
the jack does not make excessive statements on the prior art, provides tensioning prestress for the steel strand 5, adopts the jack to provide power due to the large value of the tensioning prestress of the steel strand 5, saves labor, can steplessly adjust the movement amount of the movable seat 63, meets construction requirements, and does not make excessive statements on the jack body for the prior art;
in order to achieve the aim, the utility model provides an anti-floating construction method for a newly-built basement, which comprises the following steps:
s1: preparation before construction: cleaning a construction site according to a design drawing, mapping the position of a pile body, and organizing construction materials, machinery and personnel to be in place;
s2: excavation of a foundation pit: digging a foundation pit fender pile at a designed position, according to the calculated discharge amount of cement soil formed by curing slurry generated during construction of a cast-in-situ bored pile in a foundation pile, overetching to a proper depth, and finishing;
s3: laying a sand cushion and a broken stone blind ditch: uniformly paving sand cushion layers with the thickness of 300-700 mm on the upper part of the basement foundation 1, and uniformly arranging drainage broken stone blind ditches at intervals in the vertical direction and the horizontal direction in the sand cushion layers;
s4: forming a hole by using the cast-in-situ bored pile: special hole forming equipment is adopted for hole forming according to design requirements, the vertical precision of the hole forming of the pile body is ensured, and the pile length, the pile position deviation and the hole forming depth meet the design requirements;
s5: sinking a steel reinforcement cage: after the hole cleaning of the cast-in-situ bored pile is finished, sinking the reinforcement cage into the hole by adopting hoisting equipment, and controlling the top elevation and the hoisting quality of the reinforcement cage;
s6: paving a reinforcing mesh 3, paving the reinforcing mesh 3 on the sand cushion layer, and mutually binding the reinforcing mesh 3 and a reinforcement cage;
s7: installing an anchoring piece 4, and installing the anchoring piece 4 on the reinforcing mesh 3 close to the reinforcement cage through bolts and nuts (because tensioning prestress needs to be applied to the steel strands 5, the value of the tensioning prestress is large, and the base 41 is connected to the reinforcing mesh 3 through bolts, so that according to the principle of a jack, even if the value of the tensioning prestress of the steel strands 5 is large, the connection between the base 41 and the reinforcing mesh 3 cannot be influenced, and the strength of the anchoring piece 4 is enhanced by adopting an integrated forming design between the base 41 and the anchorage device 42, so that the anchoring piece 4 is prevented from being broken by the steel strands 5 due to the large value of the tensioning prestress;
s8: installing steel strands 5, installing a plurality of steel strands 5 on the anchoring piece 4, wherein each steel strand 5 is provided with an inclined section and a horizontal section, an included angle between the inclined section and the horizontal section is an obtuse angle, and the horizontal section is positioned above the inclined section;
s9: pouring concrete: drilling a bored pile hole until the inclined section of a part of the steel strand 5 is submerged to form a basement foundation 1, and properly vibrating and compacting concrete in the pouring process;
s10: applying a tensioning prestress to the steel strand 5, referring to fig. 2, fixedly mounting a fixed seat 64 on the surface of the midspan region 11 of the basement foundation 1 through an anchor rod, enabling the steel strand 5 on one anchoring part 4 on an adjacent steel reinforcement cage to pass through the fixed seat 64 and be anchored on a permanent anchor 61, enabling the steel strand 5 on the other anchoring part 4 on the adjacent steel reinforcement cage to pass through a movable seat 63 and be anchored on the permanent anchor 61, fixing the fixed end of a jack on the fixed seat 64, fixing the movable end with the movable seat 63, driving the jack to enable the movable seat 63 to move, applying the tensioning prestress to the horizontal section of the steel strand 5, anchoring the movable seat 63 on concrete through the anchor rod, and taking out the jack;
s11: applying tension prestress to all steel strands 5 in the underground chamber, as shown in fig. 1, forming a rectangular reinforcement cage group by taking four reinforcement cages as vertexes according to the positions of the reinforcement cages, connecting the four vertexes of the reinforcement cage group pairwise to form an installation connecting line, and implementing step S10 on the installation connecting line to realize the tension prestress application of all the steel strands 5 in the underground chamber;
s12: leveling, namely paving concrete on the basement foundation 1 to enable the concrete to submerge the movable seat 63 and the fixed seat 64.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the utility model. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.
Claims (8)
1. The utility model provides an anti installation coupling assembling that floats of newly-built basement, includes basement ground (1) and reinforcing bar net (3), and basement ground (1) is including the cross-middle district (11) and the support district (12) of integrated into one piece and interconnect, reinforcing bar net (3) set up in basement ground (1), its characterized in that still includes:
the anchoring piece (4) is fixedly connected with the reinforcing mesh (3) and arranged near the support area (12), and an anchoring connection hole (421) is formed in the anchoring piece (4);
the steel strand (5) comprises a horizontal section and an inclined section, an included angle between the horizontal section and the inclined section is an obtuse angle, the horizontal section is positioned above the inclined section, and the free end of the inclined section is anchored in the anchoring hole (421);
the fixing piece (6) is fixedly arranged on the middle spanning area (11) and is fixedly connected to the free end of the horizontal section of the steel strand (5);
and the prestress tension piece (7) is used for providing tension prestress for the steel strand (5).
2. The new basement anti-floating installation and connection assembly according to claim 1, wherein the anchoring member (4) comprises:
a base (41) provided with a threaded hole (411);
the anchorage device (42) is integrally formed on the base (41), and the anchorage hole (421) is arranged on the base (41) and the anchorage device (42) in a penetrating manner;
the bolt sequentially passes through the threaded hole (411) of the anchoring piece (4) and the reinforcing mesh (3) and is in threaded connection with the nut.
3. The anti-floating installation and connection assembly for the newly-built basement according to claim 1, wherein: each strand of steel strand (5) is formed by mutually winding three steel wires.
4. The anti-floating installation and connection assembly for the newly-built basement according to claim 1, wherein: the fixing piece (6) comprises a permanent anchor (61) and two finished product anchors (62), wherein anchor holes (621) for steel strands to pass through are formed in the permanent anchor (61) and the finished product anchors (62);
the steel strand anchor is characterized by further comprising a movable seat (63) and a fixed seat (64), grooves for the steel strand (5) to penetrate through are formed in the movable seat (63) and the fixed seat (64), and the movable seat (63) and the fixed seat (64) are arranged between the finished product anchor (62) and the permanent anchor (61) and fixedly connected with the finished product anchor (62).
5. The anti-floating installation and connection assembly for the newly-built basement according to claim 4, wherein: the prestress tension member (7) is composed of two jacks which are arranged between the movable seat (63) and the fixed seat (64) and drive the movable seat (63) to move.
6. The anti-floating installation and connection assembly for the newly-built basement according to claim 5, wherein: the anchoring openings (621) are of a conical design, and part of the anchoring openings (621) of the permanent anchors (61) are oriented opposite to the rest of the anchoring openings (621).
7. The anti-floating installation and connection assembly for the newly-built basement according to claim 1, wherein: the leveling layer is arranged on the surface of the basement foundation and submerges the horizontal sections of the prestress tension pieces (7), the fixing pieces (6) and the steel strands (5).
8. The anti-floating installation and connection assembly for the newly-built basement according to claim 1, wherein: the anti-floating support is applied to basement anti-floating, four adjacent support areas (12) of a basement foundation (1) are selected, and a prestress tension member (7), a fixing member (6) and a plurality of steel strands (5) are arranged between the adjacent and opposite support areas (12) respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121880135.3U CN216075270U (en) | 2021-08-12 | 2021-08-12 | Anti installation coupling assembling that floats of newly-built basement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121880135.3U CN216075270U (en) | 2021-08-12 | 2021-08-12 | Anti installation coupling assembling that floats of newly-built basement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216075270U true CN216075270U (en) | 2022-03-18 |
Family
ID=80669325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121880135.3U Active CN216075270U (en) | 2021-08-12 | 2021-08-12 | Anti installation coupling assembling that floats of newly-built basement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216075270U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116220422A (en) * | 2023-02-28 | 2023-06-06 | 杭州圣基建筑特种工程有限公司 | Static pressure pile sinking construction method for anchor rod of existing underground garage |
-
2021
- 2021-08-12 CN CN202121880135.3U patent/CN216075270U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116220422A (en) * | 2023-02-28 | 2023-06-06 | 杭州圣基建筑特种工程有限公司 | Static pressure pile sinking construction method for anchor rod of existing underground garage |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111236260A (en) | Variable-rigidity combined type prefabricated double-row pile supporting structure and construction method thereof | |
CN1112484C (en) | Prestressed underground continuous Wall | |
CN112726692A (en) | Multi-defense line vibration control method for ancient building | |
CN107326898B (en) | I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof | |
CN216075270U (en) | Anti installation coupling assembling that floats of newly-built basement | |
CN113605465B (en) | Prestress tensioning structure and method for anti-floating construction | |
CN113605464B (en) | Self-locking technology-based foundation anti-floating first-aid repair structure and method | |
CN113565146B (en) | Prestress tensioning system for basement anti-floating construction | |
CN214363508U (en) | Foundation pit supporting structure | |
CN220725134U (en) | Assembled UHPC truss anchor plate slope protection structure | |
CN215562841U (en) | Newly-built basement is anti to float with installation connecting elements | |
JP3075179B2 (en) | Bridge pier foundation structure and its construction method | |
CN218597130U (en) | Side expands resistance to plucking rubble pile foundation structure that slip casting combines | |
CN116856932A (en) | Large-diameter prestress assembly vertical shaft structure containing glass fiber rib part and construction method | |
CN213897237U (en) | Prestressed anti-floating anchor cable for tree root pile | |
CN215105479U (en) | Foundation rock anchor pile plate type foundation of tower crane | |
CN116971413A (en) | Retaining wall emergency joint reinforcement construction method and reinforcement system structure | |
CN210122735U (en) | Underground structure anti-floating system based on outward-protruding wing foot plate | |
CN111719576B (en) | Sinking guiding system suitable for underground shaft group construction and underground shaft group construction method | |
CN210066763U (en) | Foundation pit side wall structure reinforcing and supporting device | |
CN211228521U (en) | Frame bridge supporting construction | |
KR200293048Y1 (en) | shoring structure using prestressed retaining wall | |
CN221523601U (en) | Hydraulic and hydroelectric engineering high side slope assembled supporting structure | |
CN222730569U (en) | Urban river steel dam deep foundation pit supporting system approaching existing gas pipeline | |
CN219568637U (en) | Buried drainage box culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |