CN213144093U - Wind-resistant construction enclosure - Google Patents

Wind-resistant construction enclosure Download PDF

Info

Publication number
CN213144093U
CN213144093U CN202021093697.9U CN202021093697U CN213144093U CN 213144093 U CN213144093 U CN 213144093U CN 202021093697 U CN202021093697 U CN 202021093697U CN 213144093 U CN213144093 U CN 213144093U
Authority
CN
China
Prior art keywords
enclosure
wind
push
baffle
resistant construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021093697.9U
Other languages
Chinese (zh)
Inventor
蔡阳
李林
路毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to CN202021093697.9U priority Critical patent/CN213144093U/en
Application granted granted Critical
Publication of CN213144093U publication Critical patent/CN213144093U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本实用新型公开了一种抗风施工围挡,包括围挡板和支撑组件,所述支撑组件包括立柱,斜撑杆,所述围挡板底端嵌入在混凝土基座上,所述围挡板由上至下间隔设有矩形通孔,所述矩形通孔上各交错设置推拉板,所述推拉板依靠滑轮移动,所述立柱螺栓连接在混凝土基座上,且两两立柱之间固定连接有围挡板,所述斜撑杆上侧焊接在围挡板上,所述斜撑杆的下端焊接在固定基座上。本实用新型中,通过设有推拉板,遇到大风天气时,可移动推拉板,使得矩形通孔进行透风。本实用新型的有益效果在于:所述围挡抗风性能好,可靠性高,便于安装与拆卸等特点。

Figure 202021093697

The utility model discloses a wind-resistant construction enclosure, comprising an enclosure baffle and a support assembly. The support assembly includes a vertical column and a diagonal strut. The bottom end of the enclosure baffle is embedded on a concrete base. The plate is provided with rectangular through holes at intervals from top to bottom, and push-pull plates are staggered on each of the rectangular through holes. The push-pull plates move by means of pulleys. The column bolts are connected to the concrete base, and the two columns are fixed between the two columns. An enclosure plate is connected, the upper side of the diagonal strut is welded on the enclosure plate, and the lower end of the oblique brace is welded on the fixed base. In the utility model, by being provided with a push-pull plate, the push-pull plate can be moved when the windy weather is encountered, so that the rectangular through holes can be ventilated. The beneficial effects of the utility model are as follows: the enclosure has the characteristics of good wind resistance, high reliability, and easy installation and disassembly.

Figure 202021093697

Description

Wind-resistant construction enclosure
Technical Field
The utility model relates to a construction facility technical field, concretely relates to anti-wind is executed and is enclosed fender.
Background
The building construction enclosure is a measure taken for isolating a construction site from the external environment and enabling the construction site to become a relatively closed space, and comprises the step of constructing the enclosure by adopting a traditional brick-laying and color steel plate structure. The building construction encloses the fender and should be neat firm, and the position of settling should also not hinder road traffic and pedestrian and pass through. The enclosure on the construction site of the construction project is an important component of safe and civilized construction, and can provide reliable guarantee for the safety and closed management of the construction site.
The existing building construction enclosure is focused on the sealing property, the enclosure has the defects of unreliable fixation between the enclosure and the ground and easy overturning, the structural safety is low, and once an emergency occurs, constructors or passing vehicles and pedestrians can be injured. Above all, the stability of anti-wind is relatively poor, meets with under the strong wind weather, encloses the fender and topples over the damage easily, and mostly is once using, is difficult to the use of once having enough to meet the need, and reuse rate is low.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction that the piece together is convenient, intensity is high, anti-wind-force is strong encloses the fender, solves the on-the-spot original wind resistance and the stability of enclosing structure of construction not good enough, can not used repeatedly the scheduling problem.
In order to achieve the purpose, the utility model adopts the following technical proposal: the wind-resistant construction enclosure comprises an enclosure plate and a support assembly, wherein the support assembly comprises stand columns and inclined support rods, the bottom end of the enclosure plate is embedded in a concrete base, rectangular through holes are formed in the enclosure plate from top to bottom at intervals, push-pull plates are arranged on the rectangular through holes in a staggered mode, and the push-pull plates move by means of pulleys; the upright posts are connected to the concrete base through bolts, an enclosure baffle is fixedly connected between every two upright posts, the sections of the upright posts are H-shaped, the left end and the right end of each upright post are respectively provided with a concave slot, and the two ends of the enclosure baffle are embedded into the concave slots; the upper side of the inclined stay bar is welded on the enclosure baffle, and the lower end of the inclined stay bar is welded on the fixed base.
Preferably, a through hole frame is arranged on the rectangular through hole, blocking pieces are arranged on the upper side and the lower side of the through hole frame respectively, spaced sliding rails are arranged on the through hole frame, the at least two rectangular push-pull plates are installed in the through hole frame in a staggered mode, and pulleys are arranged at the bottom ends of the rectangular push-pull plates.
Preferably, the blocking piece is in a strip shape, the sliding rail is composed of the blocking piece and a blocking piece, and a handle is arranged on the surface of the inner side of the push-pull plate.
Preferably, the lower end of the fixed base is welded with a conical piercing nail.
Preferably, the conical piercing spike is provided with a spiral groove.
Preferably, the U-shaped steel frame is welded on the inner side of the enclosure plate, and the two ends of the outer side of the bottom of the enclosure plate are provided with triangular steel.
Preferably, a groove is formed in the middle of the top of the concrete base.
Preferably, at least three rectangular through holes are distributed on the baffle plate and are distributed on the baffle plate at equal intervals.
Preferably, both sides of the top of the upright post are provided with bolt holes.
The utility model has the advantages that: at first, the utility model discloses a be equipped with the push-and-pull board, when meetting strong wind weather, can be through removing the push-and-pull board to make the rectangle through-hole ventilate, prevent to lead to this construction to enclose because wind-force is too big to keep off askew to topple over to one side, thereby enclose to keep off to protect this construction. Secondly, through set up the notch on stand and concrete foundation, both retrained the activity of enclosing the baffle, be convenient for again the construction encloses the installation and the dismantlement of fender, and is swift convenient, and the while encloses the baffle and can also the secondary turnover use. Moreover, through the secondary reinforcement of the triangular steel frame and the piercing nails, the capability of resisting strong wind of the construction enclosure is further improved.
Drawings
The accompanying drawings, which form a part hereof, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the invention without undue limitation. In the drawings:
FIG. 1 is a front view of an embodiment of the present invention
FIG. 2 is a side view of an embodiment of the present invention
FIG. 3 is a top view of an embodiment of the present invention
FIG. 4 is a side view of the rectangular through hole in the embodiment of the present invention
FIG. 5 is a front view of the push-pull plate according to an embodiment of the present invention
Description of reference numerals: 1-concrete base, 2-upright post, 3-enclosure plate, 4-push-pull plate, 41-handle, 5-diagonal brace rod, 6-U-shaped steel frame, 7-fixed base, 71-piercing nail, 8-rectangular through hole, 9-through hole frame, 91-slide rail, 911-blocking sheet, 912-blocking sheet, 92-pulley, 10-concave slot, 11-triangular steel, 12-bolt hole
Detailed Description
It should be noted that, in the present invention, the embodiments and features of the embodiments may be combined with each other without conflict.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "back", "top", "bottom", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
As shown in fig. 1 to 3, the wind-resistant construction enclosure comprises an enclosure plate 3 and a support assembly, wherein the support assembly comprises a vertical column 2 and a diagonal brace 5. The bottom end of the enclosure baffle 3 is embedded in the concrete base 1, rectangular through holes 8 are formed in the enclosure baffle 3 from top to bottom at intervals, push-pull plates 4 are arranged on the rectangular through holes 8 in a staggered mode, and the push-pull plates 4 move by means of pulleys 92; the upright posts 2 are connected to the concrete base 1 through bolts, the enclosure baffle plates 3 are fixedly connected between every two upright posts 2, the sections of the upright posts 2 are H-shaped, the left and right sides of each upright post are respectively provided with a concave slot 10, a groove is formed in the middle of the top of the concrete base 1, and the enclosure baffle plates 3 are embedded into the grooves of the concrete base 1 from top to bottom along the concave slots 10 on the upright posts 2, so that the displacement of the enclosure baffle plates is effectively restrained; at least three rectangular through holes 8 are distributed on the baffle 3 and are distributed on the baffle 3 at equal intervals.
As shown in fig. 4 and 5, a hollow through-hole frame 9 is disposed on the rectangular through-hole 8, blocking pieces 911 are disposed on the upper and lower sides of the through-hole frame 9, and the blocking pieces 911 are strip-shaped, so that the pulley 92 is effectively prevented from moving in a staggered manner, and the moving range of the push-pull plate 4 is limited. The slide rail 91 comprises hindering piece 911 and separation blade 912, and the through-hole frame 9 is equipped with spaced slide rail 91, and two piece at least rectangle push-and-pull boards 4 are crisscross to be installed in rectangle through-hole frame 9, and push-and-pull board 4 inboard surface mounting has handle 41, and rectangle push-and-pull board 4 bottom all is equipped with pulley 92 for the frictional force between push-and-pull board 4 and slide rail 91 reduces, has effectively saved the manpower.
As shown in fig. 2, the upper side of the diagonal brace 5 is welded to the apron 3, and the lower end of the diagonal brace 5 is welded to the fixed base 7. The welding of fixed baseplate 7 lower extreme has toper puncture nail 71, is equipped with the helicla flute on the toper puncture nail 71, and the in-process that the puncture nail pricked soil has injectd the degree of freedom of all directions in the soil embedding helicla flute, has further improved fixed baseplate 7's ability of grabbing ground and steadiness. Enclose 3 inboard welding of baffle plate has U shaped steel frame 6, both can consolidate and enclose the fender, can reserve space again and place relevant construction pipelines such as water pipe and cable, enclose 3 bottom outside both ends of baffle plate bolted connection triangle steel 11 respectively, further strengthen the construction and enclose the stability of keeping off.
The working principle is as follows: this construction encloses when keeping off and use, at first pours out concrete base 1 through concrete around the construction site, then through 2 bolted connection on concrete base 1 of stand, and fixedly connected with fender 3 between two liang of stands 2, and during 3 concave slots 10 along stand 2 of fender follow from last to imbedding concrete base 1 recess down, 5 upper sides of diagonal brace weld on fender 3, and the lower extreme welding of diagonal brace 5 is on fixed baseplate 7. And finally, connecting the two ends of the outer side of the bottom of the enclosing baffle 3 with triangular steel 11 through bolts, and further fixing the construction enclosing baffle, so that the installation of the building construction enclosing baffle is finished.
As the further improvement to the technical scheme, the steel sheets can be fixedly connected with the bolt holes 12 on the two sides of the top of the upright post 2, the vertical displacement of the enclosure plate is further restrained, and therefore the stability of the enclosure plate is improved.
As a further improvement to the above technical solution, the concrete foundation 1 may also be prefabricated, further reducing the construction time.
Finally, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the present invention can be modified or replaced by other means without departing from the spirit and scope of the present invention, which should be construed as limited only by the appended claims.

Claims (9)

1.一种抗风施工围挡,包括围挡板(3)和支撑组件,所述支撑组件包括立柱(2),斜撑杆(5),其特征在于:所述围挡板(3)底端嵌入在混凝土基座(1)上,所述围挡板(3)由上至下间隔设有矩形通孔(8),所述矩形通孔(8)上各交错设置推拉板(4),所述推拉板(4)依靠滑轮(92)移动,所述立柱(2)螺栓连接在混凝土基座(1)上,且两两立柱(2)之间固定连接有围挡板(3),所述立柱(2)截面为H型,左右两端各设有凹形插槽(10),所述围挡板(3)两端嵌入凹形插槽(10),所述斜撑杆(5)上侧焊接在围挡板(3)上,所述斜撑杆(5)的下端焊接在固定基座(7)上。1. A wind-resistant construction enclosure, comprising an enclosure baffle (3) and a support assembly, the support assembly comprising a column (2), a diagonal strut (5), characterized in that: the enclosure baffle (3) The bottom end is embedded on the concrete base (1), the enclosure plate (3) is provided with rectangular through holes (8) at intervals from top to bottom, and push-pull plates (4) are staggered on the rectangular through holes (8). ), the push-pull plate (4) moves by means of the pulley (92), the column (2) is bolted on the concrete base (1), and the two columns (2) are fixedly connected with a surrounding baffle plate (3). ), the cross section of the column (2) is H-shaped, the left and right ends are provided with concave slots (10), the two ends of the enclosure baffle (3) are embedded in the concave slots (10), the diagonal braces The upper side of the rod (5) is welded on the enclosure plate (3), and the lower end of the diagonal strut (5) is welded on the fixed base (7). 2.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述矩形通孔(8)上设置通孔框架(9),所述通孔框架(9)上下两侧各设置阻碍片(911),所述通孔框架(9)设有间隔的滑轨(91),所述至少两块矩形推拉板(4)交错安装在通孔框架(9)内,所述矩形推拉板(4)底端均设有滑轮(92)。2. A wind-resistant construction enclosure according to claim 1, characterized in that: a through-hole frame (9) is arranged on the rectangular through-hole (8), and the upper and lower sides of the through-hole frame (9) are respectively A blocking piece (911) is provided, the through-hole frame (9) is provided with spaced slide rails (91), and the at least two rectangular push-pull plates (4) are staggeredly installed in the through-hole frame (9). The bottom ends of the push-pull plates (4) are provided with pulleys (92). 3.根据权利要求2所述的一种抗风施工围挡,其特征在于:所述阻碍片(911)为条形状,所述滑轨(91)由阻碍片(911)和挡片(912)组成,所述推拉板(4)内侧表面安装有把手(41)。3 . The wind-resistant construction enclosure according to claim 2 , wherein the blocking piece ( 911 ) is in the shape of a bar, and the slide rail ( 91 ) is composed of a blocking piece ( 911 ) and a blocking piece ( 912 ). 4 . ), a handle (41) is installed on the inner surface of the push-pull plate (4). 4.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述固定基座(7)下端焊接有锥形穿刺钉(71)。4. The wind-resistant construction enclosure according to claim 1, wherein a conical piercing nail (71) is welded to the lower end of the fixing base (7). 5.根据权利要求4所述的一种抗风施工围挡,其特征在于:所述锥形穿刺钉(71)上设有螺旋槽。5 . The wind-resistant construction enclosure according to claim 4 , wherein a spiral groove is provided on the conical puncture nail ( 71 ). 6 . 6.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述围挡板(3)内侧焊接有U型钢架(6),所述围挡板(3)底部外侧两端设有三角钢(11)。6. A wind-resistant construction enclosure according to claim 1, characterized in that: a U-shaped steel frame (6) is welded on the inner side of the enclosure baffle (3), and a bottom outer side of the enclosure baffle (3) is welded. Both ends are provided with triangular steel (11). 7.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述混凝土基座(1)顶部中间设有凹槽。7 . The wind-resistant construction enclosure according to claim 1 , wherein a groove is provided in the middle of the top of the concrete base ( 1 ). 8 . 8.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述围挡板(3)上分布至少三个矩形通孔(8),等间距分布在所述围挡板(3)上。8. A wind-resistant construction enclosure according to claim 1, characterized in that: at least three rectangular through holes (8) are distributed on the enclosure baffle (3), and are equally spaced on the enclosure baffle (3) on. 9.根据权利要求1所述的一种抗风施工围挡,其特征在于:所述立柱(2)顶部两侧均有螺栓孔(12)。9 . The wind-resistant construction enclosure according to claim 1 , wherein bolt holes ( 12 ) are provided on both sides of the top of the column ( 2 ). 10 .
CN202021093697.9U 2020-06-10 2020-06-10 Wind-resistant construction enclosure Expired - Fee Related CN213144093U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021093697.9U CN213144093U (en) 2020-06-10 2020-06-10 Wind-resistant construction enclosure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021093697.9U CN213144093U (en) 2020-06-10 2020-06-10 Wind-resistant construction enclosure

Publications (1)

Publication Number Publication Date
CN213144093U true CN213144093U (en) 2021-05-07

Family

ID=75726087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021093697.9U Expired - Fee Related CN213144093U (en) 2020-06-10 2020-06-10 Wind-resistant construction enclosure

Country Status (1)

Country Link
CN (1) CN213144093U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113738183A (en) * 2021-09-29 2021-12-03 嘉兴市天坤营造工程设计有限公司 Safety dust-proof enclosure for engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113738183A (en) * 2021-09-29 2021-12-03 嘉兴市天坤营造工程设计有限公司 Safety dust-proof enclosure for engineering

Similar Documents

Publication Publication Date Title
CN213144093U (en) Wind-resistant construction enclosure
CN212406336U (en) Bridge construction guardrail device
CN209760968U (en) Integrated louver-shaped fence
CN217949823U (en) Protective shed frame device for crossing existing railway on expressway
CN211923601U (en) Protective system for existing road striding under box girder
CN218759194U (en) Face limit protection fence suitable for infrastructure field
CN113481872A (en) Structure and construction method for safety guardrail on bent cap
CN218841526U (en) Upper and lower ladder cage structure of lattice type tower crane foundation for deep foundation pit
CN201649003U (en) Active powder concrete column and steel pipe combination rail structure
CN216108576U (en) Be applied to platform set up structure on precipitation well
CN217269109U (en) Reinforcing bar processing canopy
CN220908259U (en) Prefabricated reinforced concrete guardrail
CN219344269U (en) Guardrail for building
CN216428010U (en) Cast-in-place beam support of ramp bridge
CN217781788U (en) Steel construction station outer protector
CN218715699U (en) Construction that can have enough to meet need encloses fender structure
CN220245381U (en) Can have enough to meet need tower crane operation platform
CN220955008U (en) Assembled highway bridge construction site guard rail
CN217000486U (en) T-shaped assembled latticed column
CN221220007U (en) Quick assembly disassembly's modularization encloses fender
CN213014081U (en) Impact-resistant protective shed
CN213173733U (en) Assembled protective railing for basement deep foundation pit
CN214170003U (en) Edge protection structure combined with aluminum film in double-unit staggered-layer construction
CN214062567U (en) Telescopic assembled guardrail
CN221320764U (en) Upstream end of wave beam steel guardrail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210507