CN212154195U - Blanking platform for super high-rise building construction - Google Patents
Blanking platform for super high-rise building construction Download PDFInfo
- Publication number
- CN212154195U CN212154195U CN202020440125.7U CN202020440125U CN212154195U CN 212154195 U CN212154195 U CN 212154195U CN 202020440125 U CN202020440125 U CN 202020440125U CN 212154195 U CN212154195 U CN 212154195U
- Authority
- CN
- China
- Prior art keywords
- plate
- fixedly connected
- spring
- clamping
- building construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to the technical field of building construction, in particular to a blanking platform for super high-rise building construction, which comprises a bottom plate and a first spring, wherein the top end of the bottom plate is fixedly connected with the first spring, the other end of the first spring is fixedly connected with a top plate, the top end of the bottom plate is fixedly connected with a limiting rod, the top end of the top plate is fixedly connected with a side plate, the top end of the side plate is fixedly connected with a baffle plate, a clamping plate is embedded in the inner side of the top plate, the left side and the right side of the clamping plate are fixedly connected with a second spring, the other end of the second spring is fixedly connected with a clamping block, the other end of the clamping block is fixedly connected with a connecting rod, the position of the clamping plate embedded in the top plate is determined through the wheel track of a material conveying trolley, the position of a wheel clamping sleeve on the, therefore, the material conveying trolleys of different specifications can be fixed on the material conveying platform, and the production safety is improved.
Description
Technical Field
The utility model relates to a construction technical field specifically is a blanking platform for super high-rise building construction.
Background
Along with the development of society and the improvement of economic level, high-rise buildings get into people's field of vision more and more, in the work progress of super high-rise building, the workman often can utilize the loop wheel machine to hoist building material through blanking platform, lifts by crane to suitable height and conveniently workman transports building material, reduces workman's work load, therefore it can be seen that blanking platform plays the effect of the heaviness to super high-rise building construction, the importance of safety in the building construction is not clear, the emergence of building accident can often be reduced by a wide margin to the blanking platform of security, improves workman's production safety greatly.
People are only simple sheet layer and purse seine with blanking platform in the super high-rise building work progress mostly, carry out safety fixing to the fortune material dolly on the blanking platform, often can cause the dolly slope lifting by crane the in-process, cause the emergence of building accident even, blanking platform top does not shelter from the setting in addition, often can cause the cement pollution in the fortune material dolly, the engineering quality of super high-rise building construction can not be guaranteed, in lifting rope sudden fracture's building accident, blanking platform in the usual production does not have the shock attenuation effect, often can cause huge noise, building tool and material receive huge impact force simultaneously, cause the loss to company's property, therefore, propose a blanking platform for super high-rise building construction to above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a blanking platform is used in super high-rise building construction to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a super high-rise building construction is with blanking platform, includes bottom plate and first spring, the first spring of top fixedly connected with of bottom plate, the other end fixedly connected with roof of first spring, the top fixedly connected with gag lever post of bottom plate, the top fixedly connected with curb plate of roof, the top fixedly connected with baffle of curb plate, the cardboard has been inlayed to the inboard of roof, the left and right sides fixedly connected with second spring of cardboard, the other end fixedly connected with fixture block of second spring, the other end fixedly connected with connecting rod of fixture block, the top fixedly connected with push rod of connecting rod, the wheel cutting ferrule has been inlayed to the inboard of roof, the inboard sliding connection of wheel cutting ferrule has the bolt, and bolt and cardboard sliding connection, the outside screwed connection of bolt has the nut.
Preferably, the number of the limiting rods is 4, and the cross sections of the limiting rods are square and are connected with the top plate in a sliding mode.
Preferably, the number of the push rods is 4, and the push rods are connected with the top plate in a sliding mode.
Preferably, the inner side of the clamping plate is provided with round holes at equal intervals.
Preferably, the number of the wheel cutting sleeves is 4, and the wheel cutting sleeves are symmetrically distributed on two sides of the clamping plate.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses in, roof through setting up, the cardboard, the bolt, the nut, the wheel cutting ferrule, the second spring, the fixture block, connecting rod and push rod, can be in the work progress fixed fortune material dolly position on the blanking platform, confirm the position of cardboard embedding on the roof according to the wheel track of fortune material dolly in the use, confirm the position of wheel cutting ferrule at the cardboard through the size of fortune material dolly wheel, fix the wheel cutting ferrule on the cardboard through bolt and nut, thereby can be with the fortune material dolly fixed position of different specifications on fortune material platform, improve the production security.
2. The utility model discloses in, through the baffle and the roof that set up, can avoid lifting by crane the in-process, in workman's clearance rubbish or other debris fall into the cement of fortune material dolly, guarantee that the workman utilizes effectual cement to be under construction to guarantee the construction quality of high building.
3. The utility model discloses in, through the first spring and the gag lever post that set up, can avoid fortune material dolly and building material to reduce the impact force in accident and the ordinary production of weighing down suddenly, reduce the noise that produces in the work progress, improve the construction environment.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a side view of the present invention of fig. 1;
fig. 3 is a top view of the present invention shown in fig. 1;
FIG. 4 is a schematic view of the structure at A of FIG. 1 according to the present invention;
fig. 5 is a schematic structural diagram of the point B in fig. 1 according to the present invention.
In the figure: 1-bottom plate, 2-first spring, 3-top plate, 4-limiting rod, 5-clamping plate, 6-wheel clamping sleeve, 7-bolt, 8-nut, 9-second spring, 10-clamping block, 11-connecting rod, 12-push rod, 13-side plate and 14-baffle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution:
the utility model provides a super high-rise building construction is with blanking platform, including bottom plate 1 and first spring 2, the first spring 2 of top fixedly connected with of bottom plate 1, the other end fixedly connected with roof 3 of first spring 2, the top fixedly connected with gag lever post 4 of bottom plate 1, the top fixedly connected with curb plate 13 of roof 3, the top fixedly connected with baffle 14 of curb plate 13, cardboard 5 has been inlayed to the inboard of roof 3, the left and right sides fixedly connected with second spring 9 of cardboard 5, the other end fixedly connected with fixture block 10 of second spring 9, the other end fixedly connected with connecting rod 11 of fixture block 10, the top fixedly connected with push rod 12 of connecting rod 11, wheel cutting ferrule 6 has been inlayed to the inboard of roof 3, the inboard sliding connection of wheel cutting ferrule 6 has bolt 7, and bolt 7 and 5 sliding connection of cardboard, the outside screwed connection of bolt 7 has nut.
The number of the limiting rods 4 is 4, the cross sections of the limiting rods 4 are square and are in sliding connection with the top plate 3, and the cross sections of the limiting rods 4 are square in the using process, so that the blanking platform can be horizontally lifted or lowered under the condition that the impact force of the first spring 2 is reduced in sudden falling accidents and ordinary production; the number of the push rods 12 is 4, the push rods 12 are connected with the top plate 3 in a sliding mode, and the push rods 12 push the clamping blocks 10 in the using process, so that the clamping plates 5 can be smoothly embedded into the top plate 3; round holes are formed in the inner side of the clamping plate 5 at equal intervals, bolts 7 can penetrate into the round holes formed in the inner side of the clamping plate 5 and the wheel clamping sleeves 6 according to the size of wheels of the material conveying trolley in the using process, and the material conveying trolley is fixed by nuts 8, so that the material conveying trolleys with different wheel sizes are fixed on the blanking platform; the number of the wheel clamp sleeves 6 is 4, the wheel clamp sleeves are symmetrically distributed on two sides of the clamping plate 5, and wheels can be clamped in the using process, so that the material conveying trolley is fixed on the blanking platform, and the production safety is improved.
The working process is as follows: in the utility model, according to the wheel track of the material conveying trolley, the clamping plate 5 is embedded into different positions of the top plate 3, the push rod 12 is pushed towards the direction close to the clamping plate 5, the push rod 12 can push the clamping block 10 to compress the second spring 9 through the connecting rod 11, so that the second spring 9 is compressed, after the clamping block 10 exits from the clamping hole arranged on the clamping plate 5, the clamping plate 5 is upwards pulled out, the position of the clamping plate 5 clamped on the top plate 3 is determined according to the wheel track of the material conveying trolley, the push rod 12 is pushed towards the direction close to the clamping plate 5, the position of the exiting is pushed, the clamping plate 5 is aligned with the position embedded in the top plate 3, the push rod 12 is aligned with the small hole exiting from the push rod 12, when the clamping plate 5 is placed at the bottom of the small hole, the push rod 12 is loosened, the second spring 9 extends, so that the second spring 9 pushes the clamping block 10 to be clamped into, take off bolt 7, thereby confirm the position that wheel cutting ferrule 6 is fixed on cardboard 5 according to the size of fortune material dolly wheel, slip and cardboard 5 sliding connection's wheel cutting ferrule 6 to suitable position, penetrate cardboard 5 and wheel cutting ferrule 6 with bolt 7, it is fixed with wheel cutting ferrule 6 promptly to spin up nut 8, with 3 sliding connection's of roof gag lever post 4 under the circumstances of the first spring 2 reduction impact force in sudden drop accident and the usual production, guarantee blanking platform level rise or descend, and can shelter from debris with curb plate 13 fixed connection's baffle 14.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a super high-rise building construction is with blanking platform, includes bottom plate (1) and first spring (2), its characterized in that: the wheel clamping mechanism is characterized in that a first spring (2) is fixedly connected to the top end of the bottom plate (1), a top plate (3) is fixedly connected to the other end of the first spring (2), a limiting rod (4) is fixedly connected to the top end of the bottom plate (1), a side plate (13) is fixedly connected to the top end of the top plate (3), a baffle plate (14) is fixedly connected to the top end of the side plate (13), a clamping plate (5) is embedded in the inner side of the top plate (3), second springs (9) are fixedly connected to the left side and the right side of the clamping plate (5), a clamping block (10) is fixedly connected to the other end of the second spring (9), a connecting rod (11) is fixedly connected to the other end of the clamping block (10), a push rod (12) is fixedly connected to the top end of the connecting rod (11), a wheel clamping sleeve (6), and the bolt (7) is connected with the clamping plate (5) in a sliding way, and the outer side of the bolt (7) is spirally connected with a nut (8).
2. The blanking platform for super high-rise building construction of claim 1, wherein: the number of gag lever post (4) has 4, and the cross section of gag lever post (4) is the square, and all with roof (3) sliding connection.
3. The blanking platform for super high-rise building construction of claim 1, wherein: the number of the push rods (12) is 4, and the push rods (12) are connected with the top plate (3) in a sliding mode.
4. The blanking platform for super high-rise building construction of claim 1, wherein: round holes are arranged on the inner side of the clamping plate (5) at equal intervals.
5. The blanking platform for super high-rise building construction of claim 1, wherein: the number of the wheel clamping sleeves (6) is 4, and the wheel clamping sleeves are symmetrically distributed on two sides of the clamping plate (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020440125.7U CN212154195U (en) | 2020-03-30 | 2020-03-30 | Blanking platform for super high-rise building construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020440125.7U CN212154195U (en) | 2020-03-30 | 2020-03-30 | Blanking platform for super high-rise building construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212154195U true CN212154195U (en) | 2020-12-15 |
Family
ID=73725968
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020440125.7U Active CN212154195U (en) | 2020-03-30 | 2020-03-30 | Blanking platform for super high-rise building construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212154195U (en) |
-
2020
- 2020-03-30 CN CN202020440125.7U patent/CN212154195U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212154195U (en) | Blanking platform for super high-rise building construction | |
CN201614227U (en) | Hoisting rigging device | |
CN2235961Y (en) | Lifter | |
CN212101636U (en) | Automatic tubular pile hoist | |
CN205857026U (en) | A kind of movable type bridge anticollision barrier construction operation chassis | |
CN203593574U (en) | Movable cable cover plate jacklift of transformer substation | |
CN201647851U (en) | Multifunctional building crane | |
CN202063655U (en) | Anti-tilting safe device of tower type crane | |
CN101717034A (en) | Hoisting rigging device | |
CN209835410U (en) | Device for quick aerial tripping in steel structure hoisting | |
CN204778565U (en) | Well lid handling device | |
CN204727473U (en) | A kind of crane hanger antiswing device | |
CN211229187U (en) | Prefabricated T roof beam hoist and mount angle bead device | |
CN216105440U (en) | Lifting machine for building engineering | |
CN211646007U (en) | Bridge pier hanging surrounding basket construction platform | |
CN203568734U (en) | Novel safe lifting gear of tower crane | |
CN217414421U (en) | Railway precast beam prestressing force stretch-draw protection frame | |
CN108862002B (en) | Hoisting device and hoisting method for ultrathin steel plate shear wall in tower crane blind area | |
CN218467178U (en) | Safety tool for hoisting concrete precast column | |
CN211396549U (en) | Telescopic folding elevator shaft construction operation platform | |
CN210288131U (en) | Movable lifting type prestress tensioning device | |
CN217756530U (en) | Lifting device for floor without back jacking | |
CN215854704U (en) | Tower crane jacking climbing position monitoring device | |
CN219622241U (en) | Wall-attached support of attached lifting scaffold | |
CN220376095U (en) | Hoisting device for main cable saddle grid of suspension bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |