CN211393650U - Hoisting equipment for live construction of pole-mounted electric equipment - Google Patents
Hoisting equipment for live construction of pole-mounted electric equipment Download PDFInfo
- Publication number
- CN211393650U CN211393650U CN201921873806.6U CN201921873806U CN211393650U CN 211393650 U CN211393650 U CN 211393650U CN 201921873806 U CN201921873806 U CN 201921873806U CN 211393650 U CN211393650 U CN 211393650U
- Authority
- CN
- China
- Prior art keywords
- insulating
- pole
- main column
- locking
- connecting piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Electric Cable Installation (AREA)
Abstract
本实用新型公开了一种杆上用电设备带电施工吊装设备,包括位于直角三角形三条边上的绝缘主柱、绝缘横梁和绝缘支撑杆,其中,绝缘主柱位于第一条直边上且平行于电杆设置,绝缘横梁位于第二条直边上且与绝缘主柱垂直,绝缘支撑杆位于斜边上,所述绝缘主柱与绝缘横梁之间通过绝缘调节支架连接,所述绝缘主柱沿高度方向设有至少一个线杆抱箍,所述线杆抱箍抱紧固定于电杆,所述绝缘横梁的中部连接有连接件,所述绝缘支撑杆的一端与连接件连接,另一端与线杆抱箍连接或通过连接件与绝缘主柱连接,所述绝缘横梁远离绝缘主柱一端连接有滑车挂点或者滑轮。本实用新型能够及时处理缺陷修复,保障线路的正常运行,减少和避免停电工作而造成的重大经济损失。
The utility model discloses a live construction and hoisting equipment for electrical equipment on a pole, which comprises an insulating main column, an insulating cross beam and an insulating support rod located on three sides of a right-angled triangle, wherein the insulating main column is located on the first straight side and is parallel to the Set on the pole, the insulating beam is located on the second straight side and is perpendicular to the insulating main column, the insulating support rod is located on the hypotenuse, the insulating main column and the insulating beam are connected by an insulating adjusting bracket, and the insulating main column is connected. At least one line pole hoop is arranged along the height direction, the line pole hoop is tightly fixed to the electric pole, the middle part of the insulating beam is connected with a connecting piece, one end of the insulating support rod is connected with the connecting piece, and the other end is connected with the connecting piece. It is connected with the line pole hoop or connected with the insulating main column through the connecting piece, and one end of the insulating beam away from the insulating main column is connected with a pulley hanging point or a pulley. The utility model can deal with defect repair in time, guarantee the normal operation of the line, and reduce and avoid the heavy economic loss caused by the power failure.
Description
技术领域technical field
本实用新型涉及电力施工工具,具体涉及杆上用电设备带电施工吊装设备。The utility model relates to electric power construction tools, in particular to live construction hoisting equipment for electric equipment on a pole.
背景技术Background technique
在偏远山区,地形复杂,更换柱上开关或其他杆上用电设备采用大型起吊设备不太现实。因此研究适用于偏远山区复杂地形,可以在不影响正常供电的情况下带电安装、更换柱上开关或其他杆上用电设备的全绝缘吊装架,对于提高柱上开关或其他杆上用电设备更换效率显得非常重要。In remote mountainous areas with complex terrain, it is not practical to use large lifting equipment to replace switches on the pole or other electrical equipment on the pole. Therefore, the research is suitable for the complex terrain in remote mountainous areas, and the fully insulated hoisting frame that can be installed and replaced on the pole or other electrical equipment on the pole can be installed and replaced without affecting the normal power supply. Replacement efficiency is very important.
实用新型内容Utility model content
本实用新型所要解决的技术问题就是提供一种杆上用电设备带电施工吊装设备,可以在不影响正常供电的情况下实现快速带电安装、更换柱上开关或其他杆上用电设备。The technical problem to be solved by the utility model is to provide a live construction hoisting equipment for electric equipment on a pole, which can realize rapid live installation, replacement of switches on the pole or other electric equipment on the pole without affecting the normal power supply.
为解决上述技术问题,本实用新型采用如下技术方案:杆上用电设备带电施工吊装设备,包括位于直角三角形三条边上的绝缘主柱、绝缘横梁和绝缘支撑杆,其中,绝缘主柱位于第一条直边上且平行于电杆设置,绝缘横梁位于第二条直边上且与绝缘主柱垂直,绝缘支撑杆位于斜边上,所述绝缘主柱与绝缘横梁之间通过绝缘调节支架连接,所述绝缘主柱沿高度方向设有至少一个线杆抱箍,所述线杆抱箍抱紧固定于电杆,所述绝缘横梁的中部连接有连接件,所述绝缘支撑杆的一端与连接件连接,另一端与线杆抱箍连接或通过连接件与绝缘主柱连接,所述绝缘横梁远离绝缘主柱一端连接有滑车挂点或者滑轮。In order to solve the above-mentioned technical problems, the utility model adopts the following technical scheme: the electric equipment on the pole is charged for construction and hoisting equipment, including an insulating main column, an insulating cross beam and an insulating support rod located on the three sides of the right triangle, wherein the insulating main column is located on the third side. One straight side is arranged parallel to the pole, the insulating beam is located on the second straight side and is perpendicular to the insulating main column, the insulating support rod is located on the oblique side, and an insulating adjusting bracket is passed between the insulating main column and the insulating beam. connection, the insulating main column is provided with at least one line pole hoop along the height direction, the line pole hoop is tightly fixed to the electric pole, the middle part of the insulating beam is connected with a connector, and one end of the insulating support rod is It is connected with the connecting piece, and the other end is connected with the line pole hoop or with the insulating main column through the connecting piece, and one end of the insulating beam away from the insulating main column is connected with a pulley hanging point or a pulley.
可选的,所述绝缘调节支架设有向下延伸的竖向连接部,所述绝缘主柱采用螺栓与竖向连接部固定。Optionally, the insulating adjustment bracket is provided with a vertical connecting portion extending downward, and the insulating main column is fixed to the vertical connecting portion by bolts.
可选的,所述绝缘调节支架设有扇形连接部,所述扇形连接部的中心设有中心连接孔,所述扇形连接部沿扇形弧向分布有若干调节连接孔,所述绝缘横梁采用螺栓与中心连接孔及其中一个调节连接孔连接固定。Optionally, the insulation adjustment bracket is provided with a fan-shaped connection part, the center of the fan-shaped connection part is provided with a central connection hole, the fan-shaped connection part is distributed with a number of adjustment connection holes along the fan-shaped arc, and the insulation beam adopts bolts. It is connected and fixed with the central connecting hole and one of the adjustment connecting holes.
可选的,所述线杆抱箍与绝缘主柱转动连接,所述绝缘主柱设有凸出的锁定块,所述锁定块上设有锁定孔,所述线杆抱箍对应锁定块设有扇形的调节块,所述调节块沿弧向设有若干调节孔,所述锁定孔与其中一个调节孔之间通过锁定螺栓连接。Optionally, the line pole hoop is rotatably connected to the insulating main column, the insulating main column is provided with a protruding locking block, the locking block is provided with a locking hole, and the line pole hoop is provided corresponding to the locking block. There is a fan-shaped adjusting block, the adjusting block is provided with a plurality of adjusting holes along the arc direction, and the locking hole is connected with one of the adjusting holes by a locking bolt.
可选的,所述滑车挂点或者滑轮组连接有过载传感器,所述过载传感器连接有无线通讯模块。Optionally, an overload sensor is connected to the pulley attachment point or the pulley block, and a wireless communication module is connected to the overload sensor.
本实用新型采用上述技术方案,具有如下有益效果:The utility model adopts the above-mentioned technical scheme, and has the following beneficial effects:
1、是适用于多类型杆上快速安装并满足起重要求的组合式小型绝缘吊装架,比传统安装、更换杆上用电设备节省时间,节约资金,提高效率。1. It is a combined small insulating hoisting frame suitable for quick installation on multiple types of poles and meeting lifting requirements. Compared with traditional installation and replacement of electrical equipment on poles, it saves time, saves money and improves efficiency.
2、绝缘横梁可以调节高度和角度,适用于复杂环境,采用螺栓与中心连接孔及其中一个调节连接孔连接固定调节后位置,保证调节后固定可靠。2. The height and angle of the insulating beam can be adjusted, which is suitable for complex environments. Bolts are used to connect the central connection hole and one of the adjustment connection holes to fix the adjusted position to ensure reliable fixation after adjustment.
3、线杆抱箍与绝缘主柱转动连接,因而可以转动角度,方便在合适的角度吊装,锁定孔与其中一个调节孔之间通过锁定螺栓连接,可以保证转动角度后位置锁定,保证吊装安全。3. The pole hoop is connected with the main insulation column in rotation, so the angle can be rotated, which is convenient for hoisting at a suitable angle. The locking hole is connected with one of the adjustment holes by a locking bolt, which can ensure that the position is locked after the rotation angle and ensure the safety of hoisting. .
4、根据过载传感器通过无线通讯模块的反馈信息,操作人员可以远离电杆获得起吊的柱上开关或其他杆上用电设备是否过载,消除安全隐患,保证吊装安全。4. According to the feedback information of the overload sensor through the wireless communication module, the operator can get away from the pole to obtain whether the hoisted pole switch or other electrical equipment on the pole is overloaded, so as to eliminate potential safety hazards and ensure the safety of hoisting.
5、能够及时处理缺陷修复,保障线路的正常运行,减少和避免停电工作而造成的重大经济损失,有效提升了带电应用比例,提高了供电可靠率,实现降本降耗。5. It can deal with defect repair in time, ensure the normal operation of the line, reduce and avoid major economic losses caused by power outages, effectively increase the proportion of live applications, improve the reliability of power supply, and achieve cost reduction and consumption reduction.
本实用新型的具体技术方案及其有益效果将会在下面的具体实施方式中结合附图进行详细的说明。The specific technical solutions of the present invention and its beneficial effects will be described in detail in the following specific embodiments in conjunction with the accompanying drawings.
附图说明Description of drawings
下面结合附图和具体实施方式对本实用新型作进一步描述:Below in conjunction with accompanying drawing and specific embodiment, the utility model is further described:
图1为本实用新型的结构示意图。Figure 1 is a schematic structural diagram of the utility model.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本实用新型及其应用或使用的任何限制。基于本实用新型中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the invention, its application or uses in any way. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.
本领域技术人员可以理解的是,在不冲突的情况下,下述的实施例及实施方式中的特征可以相互组合。It can be understood by those skilled in the art that the features in the following embodiments and implementations can be combined with each other without conflict.
在本实用新型使用的术语是仅仅出于描述特定实施例的目的,而非旨在限制本实用新型。例如下述的“上”、“下”等指示方位或位置关系的词语仅基于附图所示的方位或位置关系,仅为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置/元件必须具有特定的方位或以特定的方位构造和操作,因此不能理解为对本实用新型的限制。The terms used in the present invention are for the purpose of describing particular embodiments only, and are not intended to limit the present invention. For example, the following words such as "upper" and "lower" indicating orientation or positional relationship are only based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the indicated Devices/elements must have a specific orientation or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention.
实施例一Example 1
如图1所示,杆上用电设备带电施工吊装设备,包括位于直角三角形三条边上的绝缘主柱2、绝缘横梁5和绝缘支撑杆4,其中,绝缘主柱位于第一条直边上且平行于电杆设置,绝缘横梁位于第二条直边上且与绝缘主柱垂直,绝缘支撑杆位于斜边上,所述绝缘主柱与绝缘横梁之间通过绝缘调节支架3连接,所述绝缘主柱沿高度方向设有至少一个线杆抱箍1,所述线杆抱箍抱紧固定于电杆,所述绝缘横梁的中部连接有连接件,所述绝缘支撑杆的一端与连接件连接,另一端与线杆抱箍连接或通过连接件与绝缘主柱连接,所述绝缘横梁远离绝缘主柱一端连接有滑车挂点6。As shown in Figure 1, the live construction and hoisting equipment for the electrical equipment on the pole includes an insulating
当然,本领域技术人员可以理解的是,上述的滑车挂点6也可以用滑轮进行替换。Of course, those skilled in the art can understand that the above-mentioned
具体的,所述绝缘调节支架设有向下延伸的竖向连接部,所述绝缘主柱采用螺栓与竖向连接部固定。Specifically, the insulating adjusting bracket is provided with a vertical connecting portion extending downward, and the insulating main column is fixed to the vertical connecting portion by bolts.
进一步的,为了适用于复杂环境,实现绝缘横梁的高度角度调节,所述绝缘调节支架设有扇形连接部,所述扇形连接部的中心设有中心连接孔,所述扇形连接部沿扇形弧向分布有若干调节连接孔,所述绝缘横梁采用螺栓与中心连接孔及其中一个调节连接孔连接固定。根据需要调节角度后通过螺栓固定,可以保证在吊装过程中位置不发生变化。Further, in order to be suitable for complex environments and realize the height angle adjustment of the insulating beam, the insulating adjusting bracket is provided with a fan-shaped connecting part, and the center of the fan-shaped connecting part is provided with a central connecting hole, and the fan-shaped connecting part is arranged along the fan-shaped arc direction. A number of adjustment connection holes are distributed, and the insulating beam is connected and fixed with the central connection hole and one of the adjustment connection holes by bolts. Adjust the angle as needed and fix it with bolts to ensure that the position does not change during the hoisting process.
实施例二
在实施例一的基础上,本实施例中,所述线杆抱箍与绝缘主柱转动连接,所述绝缘主柱设有水平凸出的锁定块,所述锁定块上设有一个锁定孔,所述线杆抱箍对应锁定块设有扇形的调节块,所述调节块沿弧向设有若干调节孔,所述锁定孔与其中一个调节孔之间通过锁定螺栓连接,线杆抱箍抱紧固定在电杆上后,可以转动绝缘主柱调节整个设备相对电杆的角度,角度确定后,通过锁定螺栓连接固定,保证转动角度后位置锁定,保证吊装安全。On the basis of the first embodiment, in this embodiment, the line pole hoop is rotatably connected to the insulating main column, the insulating main column is provided with a horizontally protruding locking block, and the locking block is provided with a locking hole , the line rod hoop is provided with a fan-shaped adjustment block corresponding to the locking block, the adjustment block is provided with a number of adjustment holes along the arc direction, the locking hole and one of the adjustment holes are connected by a locking bolt, and the line rod hoop is provided with a fan-shaped adjustment block. After it is firmly fixed on the pole, the main insulating column can be rotated to adjust the angle of the entire equipment relative to the pole. After the angle is determined, it is fixed by locking bolts to ensure that the position is locked after the rotation angle and ensure the safety of hoisting.
在上述实施例中,所述滑车挂点或者滑轮组连接有过载传感器,所述过载传感器连接有无线通讯模块,通过无线通迅模块与远程终端通讯,操作人员可以远离电杆获得起吊的柱上开关或其他杆上用电设备是否过载,消除安全隐患,保证吊装安全。In the above embodiment, an overload sensor is connected to the pulley hanging point or the pulley block, and the overload sensor is connected to a wireless communication module. Through the wireless communication module to communicate with the remote terminal, the operator can obtain the lifting switch from the pole away from the pole. Whether the electrical equipment on the pole or other poles is overloaded, eliminate potential safety hazards and ensure the safety of hoisting.
以上所述,仅为本实用新型的具体实施方式,但本实用新型的保护范围并不局限于此,熟悉该本领域的技术人员应该明白本实用新型包括但不限于上面具体实施方式中描述的内容。任何不偏离本实用新型的功能和结构原理的修改都将包括在权利要求书的范围中。The above are only specific embodiments of the present utility model, but the protection scope of the present utility model is not limited thereto. Those skilled in the art should understand that the present utility model includes but is not limited to those described in the above specific embodiments. content. Any modifications that do not depart from the functional and structural principles of the present invention are intended to be included in the scope of the claims.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921873806.6U CN211393650U (en) | 2019-11-01 | 2019-11-01 | Hoisting equipment for live construction of pole-mounted electric equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921873806.6U CN211393650U (en) | 2019-11-01 | 2019-11-01 | Hoisting equipment for live construction of pole-mounted electric equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211393650U true CN211393650U (en) | 2020-09-01 |
Family
ID=72225065
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921873806.6U Active CN211393650U (en) | 2019-11-01 | 2019-11-01 | Hoisting equipment for live construction of pole-mounted electric equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211393650U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111017744A (en) * | 2019-11-01 | 2020-04-17 | 国网浙江嵊州市供电有限公司 | Small-size insulating hoist and mount frame of combination formula on pole |
-
2019
- 2019-11-01 CN CN201921873806.6U patent/CN211393650U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111017744A (en) * | 2019-11-01 | 2020-04-17 | 国网浙江嵊州市供电有限公司 | Small-size insulating hoist and mount frame of combination formula on pole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208939464U (en) | A kind of distribution network live line work electrification assembly and disassembly parallel groove clamp specific purpose tool | |
CN203932813U (en) | Power equipment maintaining cable insulation support device | |
CN211393650U (en) | Hoisting equipment for live construction of pole-mounted electric equipment | |
CN206148848U (en) | A lifting device for large tonnage live conductors | |
CN205791238U (en) | A kind of 10kV distribution line charged lifter of straightway three-phase conducting wire | |
CN201438617U (en) | Electric lifting tool for linear insulator string on ZM tower | |
CN103035368A (en) | 10kV transformer frame | |
CN217642650U (en) | Arrester fixing device | |
CN111017744A (en) | Small-size insulating hoist and mount frame of combination formula on pole | |
CN214255641U (en) | a cross-arm structure | |
CN210838851U (en) | Bus duct convenient to adjust and connect end plate | |
CN201999641U (en) | Support structure of sliding contact line of traveling crane | |
CN210007228U (en) | insulating operating rod for transformer maintenance | |
CN210508615U (en) | Power transformation framework | |
CN203891559U (en) | Combined type double-pole cross arm structure | |
CN207691378U (en) | Ground wire carrying out safety backup overhanging golden tool string | |
CN207651992U (en) | A kind of 110 kv cable outdoor terminal platforms | |
KR20170115359A (en) | Cross Arm Descending Device And Method For The none power cut construction In The power distribution lines | |
CN105449612A (en) | A conductive wire insulation support plate apparatus | |
CN218299685U (en) | Disconnecting link structure and tower with same | |
CN205172139U (en) | Supplementary pole tumbler bearing of embracing of transmission line head of mast | |
CN205116881U (en) | Movable pole switch hoisting support | |
CN222138509U (en) | Bridge machine wiping line fixing device | |
CN205845747U (en) | A kind of chopper upending frame | |
CN219349919U (en) | Single-rod small-capacity three-phase upper transformer rack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |