CN210151752U CN201920461330.9U CN201920461330U CN210151752U CN 210151752 U CN210151752 U CN 210151752U CN 201920461330 U CN201920461330 U CN 201920461330U CN 210151752 U CN210151752 U CN 210151752U
Authority
CN
China
Prior art keywords
steel
purlin
foundation pit
holes
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920461330.9U
Other languages
Chinese (zh)
Inventor
刘宇晨
高亿群
史红福
熊勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Original Assignee
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Engineering Design & Research Institute Co Ltd filed Critical Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority to CN201920461330.9U priority Critical patent/CN210151752U/en
Application granted granted Critical
Publication of CN210151752U publication Critical patent/CN210151752U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a foundation ditch steel shore, it encloses the purlin including supporting steel pipe, fixing bolt and two steels, all installs the bracket on envelope's the double-phase offside, and two steels enclose the purlin and install respectively on the bracket of both sides, the steel encloses and is equipped with a plurality of location screws on the purlin, fixing bolt runs through the location screw and inserts and fix in the envelope, the both ends of supporting the steel pipe enclose the purlin with two steels respectively and meet. The utility model discloses a enclose the purlin with the steel and place on the bracket to enclose purlin and envelope with the fixing bolt connection steel, make the steel enclose the purlin not only can bear the pressure that comes from envelope, can also bear the pulling force, holistic steel bearing structure is more stable. Use the utility model discloses can the reduction of erection time, and because steel member reuse, therefore reduce construction cost.

Description

一种基坑钢顶撑A kind of foundation pit steel roof support

技术领域technical field

本实用新型涉及基坑工程领域中的一种钢顶撑,特别是一种基坑钢顶撑。The utility model relates to a steel roof brace in the field of foundation pit engineering, in particular to a foundation pit steel roof brace.

背景技术Background technique

基坑支撑系统包括钢筋混凝土支撑和钢结构支撑两种。目前在深基坑工程的施工中,为防止基坑发生踢脚破坏等失稳现象,深基坑工程中的顶撑通常采用既能承担压力,又能承担拉力的钢筋混凝土撑。然而,钢筋混凝土撑的施工工期较长,拆除较困难,材料不能重复利用,成本较高。钢结构支撑与钢筋混凝土撑相比,有安装和拆除方便、施工速度快、可以重复利用等的优点,但现有的钢结构支撑只能承担压力,不能承担拉力,因此现在需要一种能同时承担压力与拉力的钢结构支撑。The foundation pit support system includes reinforced concrete support and steel structure support. At present, in the construction of deep foundation pit engineering, in order to prevent the instability of foundation pit such as kicking damage, the top support in deep foundation pit engineering usually adopts reinforced concrete support that can bear both pressure and tension. However, the construction period of reinforced concrete braces is long, the dismantling is difficult, the materials cannot be reused, and the cost is high. Compared with reinforced concrete bracing, steel structure support has the advantages of convenient installation and dismantling, fast construction speed, and can be reused. However, the existing steel structure support can only bear the pressure and cannot bear the tension. Therefore, there is a need for a system that can simultaneously Steel structural support for compressive and tensile forces.

实用新型内容Utility model content

本实用新型的目的,在于提供一种基坑钢顶撑,其既能承受压力也能承受拉力。The purpose of the utility model is to provide a foundation pit steel top support, which can bear both pressure and tension.

本实用新型解决其技术问题的解决方案是:一种基坑钢顶撑,其包括支撑钢管、固定螺栓和两根钢围檩,围护结构的两相对侧上均安装有牛腿,两根钢围檩分别安装在两侧的牛腿上,所述钢围檩上设有多个定位螺孔,所述固定螺栓贯穿定位螺孔并插入围护结构中固定,所述支撑钢管的两端分别与两钢围檩相接。The solution of the utility model to solve the technical problem is as follows: a steel top support for a foundation pit, which comprises a supporting steel pipe, a fixing bolt and two steel purlins. Corbels are installed on two opposite sides of the surrounding structure, and two steel purlins are installed. The steel enclosure purlins are respectively installed on the corbels on both sides. The steel enclosure purlins are provided with a plurality of positioning screw holes. The fixing bolts penetrate the positioning screw holes and are inserted into the enclosure structure to be fixed. The two ends of the supporting steel pipe They are connected with two steel purlins respectively.

作为上述技术方案的进一步改进,围护结构包括钢板桩,所述钢板桩上设有多个第一通孔,所述钢板桩的外侧设有定位槽钢,所述定位槽钢上设有多个第二通孔,所述固定螺栓依次贯穿定位螺孔、第一通孔及第二通孔,所述固定螺栓的末端固接有螺母。As a further improvement of the above technical solution, the enclosure structure includes steel sheet piles, the steel sheet piles are provided with a plurality of first through holes, the outer sides of the steel sheet piles are provided with positioning channels, and the positioning channels are provided with multiple a second through hole, the fixing bolt penetrates the positioning screw hole, the first through hole and the second through hole in sequence, and a nut is fixedly connected to the end of the fixing bolt.

作为上述技术方案的进一步改进,多个所述定位螺孔均分为两排布置,两排定位螺孔分别位于钢围檩的上部和下部。As a further improvement of the above technical solution, a plurality of the positioning screw holes are evenly arranged in two rows, and the two rows of positioning screw holes are respectively located at the upper and lower parts of the steel purlin.

作为上述技术方案的进一步改进,所述钢板桩的外侧与定位槽钢之间设有混凝土块。As a further improvement of the above technical solution, a concrete block is provided between the outer side of the steel sheet pile and the positioning channel steel.

作为上述技术方案的进一步改进,所述支撑钢管的一端通过固定端头与钢围檩连接,所述支撑钢管的另一端通过活络端头与钢围檩连接,所述活络端头通过限位连接件与钢围檩相接。As a further improvement of the above technical solution, one end of the supporting steel pipe is connected to the steel purlin through a fixed end, and the other end of the supporting steel pipe is connected to the steel purlin through a flexible end, and the movable end is connected by a limit connection The piece is connected to the steel purlin.

作为上述技术方案的进一步改进,所述限位连接件包括两个插销、设置在活络端头端面上的外管和两个均设置在钢围檩内侧的内管,两个内管均插入外管中,两个内管的侧壁上均设有第一销孔,所述外管的侧壁上设有两个第二销孔,所述插销贯穿第一销孔及第二销孔。As a further improvement of the above technical solution, the limit connector includes two pins, an outer tube arranged on the end face of the flexible end, and two inner tubes both arranged on the inner side of the steel purlin, and the two inner tubes are inserted into the outer In the pipe, the side walls of the two inner pipes are provided with first pin holes, the side walls of the outer pipes are provided with two second pin holes, and the pins pass through the first pin holes and the second pin holes.

作为上述技术方案的进一步改进,还包括位于两个内管之间的千斤顶,所述千斤顶的底部固定在钢围檩的内侧,所述千斤顶的顶部与活络端头的端面相接。As a further improvement of the above technical solution, it also includes a jack located between the two inner tubes, the bottom of the jack is fixed on the inner side of the steel purlin, and the top of the jack is connected to the end face of the flexible end.

作为上述技术方案的进一步改进,还包括两个插销保护件,所述插销保护件的一端固定在钢围檩上,所述插销保护件的另一端与外管的外壁相抵,所述插销保护件均垂直于插销的轴向。As a further improvement of the above technical solution, it also includes two bolt protectors, one end of the bolt protector is fixed on the steel purlin, the other end of the bolt protector is in contact with the outer wall of the outer tube, and the bolt protector are perpendicular to the axial direction of the pin.

作为上述技术方案的进一步改进,还包括吊筋,所述吊筋的一端固定在围护结构上,所述吊筋的另一端与钢围檩的上部连接。As a further improvement of the above technical solution, it also includes a hanging bar, one end of the hanging bar is fixed on the enclosure structure, and the other end of the hanging bar is connected with the upper part of the steel purlin.

本实用新型的有益效果是:本实用新型通过将钢围檩放置在牛腿上,并用固定螺栓连接钢围檩与围护结构,使钢围檩不仅可以承受来自围护结构的压力,还能承受拉力,整体的钢支撑结构更稳定。使用本实用新型能缩短工期,且由于钢构件可重复利用,因而降低了建造成本。The beneficial effects of the utility model are: the utility model places the steel purlin on the corbel and connects the steel purlin and the enclosure structure with fixing bolts, so that the steel purlin can not only bear the pressure from the enclosure structure, but also can Bearing tensile force, the overall steel support structure is more stable. The use of the utility model can shorten the construction period, and because the steel components can be reused, the construction cost is reduced.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单说明。显然,所描述的附图只是本实用新型的一部分实施例,而不是全部实施例,本领域的技术人员在不付出创造性劳动的前提下,还可以根据这些附图获得其他设计方案和附图。In order to illustrate the technical solutions in the embodiments of the present invention more clearly, the following briefly describes the accompanying drawings that are used in the description of the embodiments. Obviously, the described drawings are only a part of the embodiments of the present invention, but not all of the embodiments, and those skilled in the art can also obtain other design solutions and drawings according to these drawings without creative work.

图1是本实用新型中一种实施方式的正视图;1 is a front view of an embodiment of the present utility model;

图2是本实用新型中另一种实施方式的正视图;2 is a front view of another embodiment of the present invention;

图3是本实用新型中另一种实施方式的俯视图。FIG. 3 is a top view of another embodiment of the present invention.

具体实施方式Detailed ways

以下将结合实施例和附图对本实用新型的构思、具体结构及产生的技术效果进行清楚、完整地描述,以充分地理解本实用新型的目的、特征和效果。显然,所描述的实施例只是本实用新型的一部分实施例,而不是全部实施例,基于本实用新型的实施例,本领域的技术人员在不付出创造性劳动的前提下所获得的其他实施例,均属于本实用新型保护的范围。另外,文中所提到的所有联接/连接关系,并非单指构件直接相接,而是指可根据具体实施情况,通过添加或减少联接辅件,来组成更优的联接结构。The concept, specific structure and technical effects of the present invention will be clearly and completely described below in conjunction with the embodiments and accompanying drawings, so as to fully understand the purpose, features and effects of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, those skilled in the art can obtain other embodiments without creative work, All belong to the scope of protection of the present invention. In addition, all the coupling/connection relationships mentioned in the text do not mean that the components are directly connected, but refer to a better coupling structure by adding or reducing coupling accessories according to specific implementation conditions.

参照图1,一种基坑钢顶撑,其包括支撑钢管1、固定螺栓2和两根钢围檩3,围护结构的两相对侧上均安装有牛腿4,两根钢围檩3分别安装在两侧的牛腿4上,所述钢围檩3上设有多个定位螺孔,所述固定螺栓2贯穿定位螺孔并插入围护结构中固定,所述支撑钢管1的两端分别与两钢围檩3相接。当围护结构为工法桩时,牛腿4直接焊接或通过膨胀螺栓安装在工法桩的内侧。钢围檩3放置在牛腿4上,并使钢围檩3紧贴工法桩的内侧,定位螺栓孔分为两排排列,两排定位螺孔分别位于钢围檩3的上部及下部,一排中的各定位螺孔等距分布。固定螺栓2穿入到定位螺孔,并插入到工法桩进行固定,使钢围檩3与围护结构紧密连接。优选地,固定螺栓2的插入长度大于工法桩的半径。Referring to Figure 1, a foundation pit steel top support, which includes a supporting steel pipe 1, a fixing bolt 2 and two steel purlins 3, two opposite sides of the enclosure structure are installed with corbels 4, two steel purlins 3 They are respectively installed on the corbels 4 on both sides. The steel purlin 3 is provided with a plurality of positioning screw holes. The ends are respectively connected with the two steel purlins 3. When the enclosure structure is a construction method pile, the corbel 4 is directly welded or installed on the inner side of the construction method pile through expansion bolts. The steel purlin 3 is placed on the corbel 4, and the steel purlin 3 is close to the inner side of the construction method pile. The positioning bolt holes are arranged in two rows. The positioning screw holes in the row are equally spaced. The fixing bolts 2 are inserted into the positioning screw holes and inserted into the construction method piles for fixing, so that the steel purlins 3 are tightly connected with the enclosure structure. Preferably, the insertion length of the fixing bolt 2 is greater than the radius of the construction method pile.

作为另一个实施例,参照图2~3,围护结构包括钢板桩6,所述钢板桩6上设有多个第一通孔,所述钢板桩6的外侧设有定位槽钢5,所述定位槽钢5上设有多个第二通孔,所述固定螺栓2依次贯穿定位螺孔、第一通孔及第二通孔,所述固定螺栓2的末端固接有螺母。所述钢板桩6的外侧与定位槽钢5之间设有混凝土块7。当围护结构为钢板桩结构时,固定螺栓2将钢围檩3固定到钢板桩6上,固定螺栓2的螺杆被固定在定位槽钢5和钢围檩3之间。优选地,定位槽钢5的水平方向上的中心线应与钢围檩3的水平方向上的中心线重合。同时,为提高固定螺栓2的稳固性和抗拉性能,在安装好固定螺栓2后,在钢板桩6与定位钢槽5之间填充快硬细石混凝土,以对固定螺栓2进行进一步的固定。另外,为紧固钢板桩6与钢围檩3之间的连接,钢板桩6与钢围檩3之间也可填充快硬细石混凝土。As another embodiment, referring to FIGS. 2 to 3 , the enclosure structure includes a steel sheet pile 6 . The steel sheet pile 6 is provided with a plurality of first through holes, and the outer side of the steel sheet pile 6 is provided with a positioning channel steel 5 . The positioning channel steel 5 is provided with a plurality of second through holes, the fixing bolts 2 pass through the positioning screw holes, the first through holes and the second through holes in sequence, and the ends of the fixing bolts 2 are fixed with nuts. A concrete block 7 is provided between the outer side of the steel sheet pile 6 and the positioning channel steel 5 . When the enclosure structure is a steel sheet pile structure, the steel enclosure purlin 3 is fixed to the steel sheet pile 6 by the fixing bolts 2 , and the screw rod of the fixing bolt 2 is fixed between the positioning channel steel 5 and the steel enclosure purlin 3 . Preferably, the center line of the positioning channel steel 5 in the horizontal direction should coincide with the center line of the steel purlin 3 in the horizontal direction. At the same time, in order to improve the stability and tensile performance of the fixing bolts 2, after the fixing bolts 2 are installed, fast-hardening fine stone concrete is filled between the steel sheet pile 6 and the positioning steel groove 5 to further fix the fixing bolts 2. . In addition, in order to fasten the connection between the steel sheet piles 6 and the steel purlins 3 , fast-hardening fine stone concrete can also be filled between the steel sheet piles 6 and the steel purlins 3 .

进一步作为优选的实施方式,多个所述定位螺孔均分为两排布置,两排定位螺孔分别位于钢围檩3的上部和下部。同一排中的多个定位螺孔等间距排列,钢板桩6上可安装有两个定位槽钢5,以分别对应位于钢围檩3上部的定位螺孔及位于钢围檩3下部的定位螺孔。As a further preferred embodiment, a plurality of the positioning screw holes are arranged in two rows, and the two rows of positioning screw holes are located at the upper and lower parts of the steel purlin 3 respectively. Multiple positioning screw holes in the same row are arranged at equal intervals, and two positioning channel steels 5 can be installed on the steel sheet pile 6 to correspond to the positioning screw holes located at the upper part of the steel purlin 3 and the positioning screw located at the lower part of the steel purlin 3 respectively. hole.

进一步作为优选的实施方式,所述支撑钢管1的一端通过固定端头与钢围檩3连接,所述支撑钢管1的另一端通过活络端头与钢围檩3连接,所述活络端头通过限位连接件与钢围檩3相接。所述限位连接件包括两个插销8、设置在活络端头端面上的外管和两个均设置在钢围檩3内侧的内管,两个内管均插入外管中,两个内管的侧壁上均设有第一销孔,所述外管的侧壁上设有两个第二销孔,所述插销8贯穿第一销孔及第二销孔。将插销8插入到第一销孔及第二销孔后,为保证钢围檩3与活络端头的连接强度,另外使用钢条插入到第一销孔和第二销孔中钢条将插销8的周围填塞密实。Further as a preferred embodiment, one end of the supporting steel pipe 1 is connected to the steel purlin 3 through a fixed end, and the other end of the supporting steel pipe 1 is connected to the steel purlin 3 through a flexible end, and the flexible end is The limit connector is connected with the steel purlin 3. The limiting connector includes two pins 8, an outer tube arranged on the end face of the active end, and two inner tubes both arranged on the inner side of the steel purlin 3. The two inner tubes are inserted into the outer tube, and the two inner tubes are inserted into the outer tube. The side walls of the tube are provided with first pin holes, the side walls of the outer tube are provided with two second pin holes, and the pins 8 pass through the first pin holes and the second pin holes. After inserting the pin 8 into the first pin hole and the second pin hole, in order to ensure the connection strength between the steel purlin 3 and the flexible end, a steel bar is used to insert the first pin hole and the second pin hole. Pack tightly around.

进一步作为优选的实施方式,还包括位于两个内管之间的千斤顶9,所述千斤顶9的底部固定在钢围檩3的内侧,所述千斤顶9的顶部与活络端头的端面相接。在支撑钢管1安装好后,千斤顶9用于施加预应力,以使形成一个整体稳定的围护支撑系统。预应力施加到位后,固定活络端头,并烧焊牢固。Further as a preferred embodiment, it also includes a jack 9 located between the two inner tubes, the bottom of the jack 9 is fixed on the inner side of the steel purlin 3, and the top of the jack 9 is in contact with the end face of the flexible end. After the supporting steel pipe 1 is installed, the jack 9 is used to apply prestressing force, so as to form an overall stable enclosure support system. After the prestress is in place, fix the flexible end and weld it firmly.

进一步作为优选的实施方式,还包括两个插销保护件10,所述插销保护件10的一端固定在钢围檩3上,所述插销保护件10的另一端与外管的外壁相抵,所述插销保护件10均垂直于插销8的轴向。Further as a preferred embodiment, it also includes two bolt protectors 10, one end of the bolt protector 10 is fixed on the steel purlin 3, the other end of the bolt protector 10 is in contact with the outer wall of the outer tube, the The plug protectors 10 are all perpendicular to the axial direction of the plug 8 .

进一步作为优选的实施方式,还包括吊筋11,所述吊筋11的一端固定在围护结构上,所述吊筋11的另一端与钢围檩3的上部连接。吊筋11对钢围檩3施加拉力,从而减少了牛腿4受到的压力,钢围檩3的更稳固可靠。As a further preferred embodiment, it also includes a hanging bar 11 , one end of the hanging bar 11 is fixed on the enclosure structure, and the other end of the hanging bar 11 is connected to the upper part of the steel purlin 3 . The hanging bars 11 exert tensile force on the steel purlin 3, thereby reducing the pressure on the corbel 4, and the steel purlin 3 is more stable and reliable.

以围护结构为钢板桩6结构为例,说明本实用新型的安装步骤:Taking the enclosure structure as the steel sheet pile 6 structure as an example, the installation steps of the present utility model are described:

(1)在基坑外侧开挖沟槽并安装钢板桩6,安装定位槽钢5到钢板桩6的外侧;(1) Excavate a trench on the outside of the foundation pit and install the steel sheet pile 6, and install the positioning channel steel 5 to the outside of the steel sheet pile 6;

(2)安装牛腿4、钢围檩3和吊筋11;(2) Install corbel 4, steel purlin 3 and hanging bar 11;

(3)安装固定螺栓2,并在定位槽钢5和钢板桩6之间紧密填充快硬细石混凝土;(3) Install the fixing bolts 2, and tightly fill the fast-hardening fine stone concrete between the positioning channel steel 5 and the steel sheet pile 6;

(4)临时固定钢支撑,通过千斤顶9施加预应力;(4) Temporarily fix the steel support, and apply prestress through the jack 9;

(5)安装插销8及插销保护件10。(5) Install the latch 8 and the latch protector 10 .

以上是对本实用新型的较佳实施方式进行了具体说明,但本发明创造并不限于所述实施例,熟悉本领域的技术人员在不违背本实用新型精神的前提下还可作出种种的等同变型或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。The preferred embodiments of the present utility model have been described above in detail, but the invention is not limited to the embodiments, and those skilled in the art can also make various equivalent modifications without departing from the spirit of the present utility model. Or alternatives, these equivalent modifications or alternatives are included within the scope defined by the claims of the present application.

Claims (9)

1.一种基坑钢顶撑,其特征在于:包括支撑钢管(1)、固定螺栓(2)和两根钢围檩(3),围护结构的两相对侧上均安装有牛腿(4),两根钢围檩(3)分别安装在两侧的牛腿(4)上,所述钢围檩(3)上设有多个定位螺孔,所述固定螺栓(2)贯穿定位螺孔并插入围护结构中固定,所述支撑钢管(1)的两端分别与两钢围檩(3)相接。1. a foundation pit steel top brace, is characterized in that: comprise supporting steel pipe (1), fixing bolt (2) and two steel purlins (3), on both opposite sides of the enclosure structure, corbels ( 4), two steel purlins (3) are respectively installed on the corbels (4) on both sides, the steel purlins (3) are provided with a plurality of positioning screw holes, and the fixing bolts (2) pass through the positioning The two ends of the supporting steel pipe (1) are respectively connected with the two steel purlins (3). 2.根据权利要求1所述的基坑钢顶撑,其特征在于:围护结构包括钢板桩(6),所述钢板桩(6)上设有多个第一通孔,所述钢板桩(6)的外侧设有定位槽钢(5),所述定位槽钢(5)上设有多个第二通孔,所述固定螺栓(2)依次贯穿定位螺孔、第一通孔及第二通孔,所述固定螺栓(2)的末端固接有螺母。2 . The foundation pit steel roof support according to claim 1 , wherein the enclosure structure comprises a steel sheet pile ( 6 ), the steel sheet pile ( 6 ) is provided with a plurality of first through holes, and the steel sheet pile ( 6 ) is provided with a plurality of first through holes. The outer side of (6) is provided with a positioning channel steel (5), the positioning channel steel (5) is provided with a plurality of second through holes, and the fixing bolts (2) sequentially pass through the positioning screw holes, the first through holes and the In the second through hole, a nut is fixedly connected to the end of the fixing bolt (2). 3.根据权利要求2所述的基坑钢顶撑,其特征在于:多个所述定位螺孔均分为两排布置,两排定位螺孔分别位于钢围檩(3)的上部和下部。3. The steel top support for foundation pit according to claim 2, characterized in that: a plurality of said positioning screw holes are equally divided into two rows and arranged, and the two rows of positioning screw holes are respectively located at the upper and lower parts of the steel purlin (3) . 4.根据权利要求2所述的基坑钢顶撑,其特征在于:所述钢板桩(6)的外侧与定位槽钢之间设有混凝土块(7)。4. The foundation pit steel top support according to claim 2, characterized in that: a concrete block (7) is arranged between the outer side of the steel sheet pile (6) and the positioning channel steel. 5.根据权利要求1所述的基坑钢顶撑,其特征在于:所述支撑钢管(1)的一端通过固定端头与钢围檩(3)连接,所述支撑钢管(1)的另一端通过活络端头与钢围檩(3)连接,所述活络端头通过限位连接件与钢围檩(3)相接。5. The foundation pit steel top support according to claim 1, characterized in that: one end of the supporting steel pipe (1) is connected to the steel purlin (3) through a fixed end, and the other end of the supporting steel pipe (1) is connected to the steel purlin (3). One end is connected with the steel purlin (3) through a flexible end, and the movable end is connected with the steel purlin (3) through a limit connecting piece. 6.根据权利要求5所述的基坑钢顶撑,其特征在于:所述限位连接件包括两个插销(8)、设置在活络端头端面上的外管和两个均设置在钢围檩(3)内侧的内管,两个内管均插入外管中,两个内管的侧壁上均设有第一销孔,所述外管的侧壁上设有两个第二销孔,所述插销(8)贯穿第一销孔及第二销孔。6. The foundation pit steel top support according to claim 5, characterized in that: the limit connecting piece comprises two pins (8), an outer pipe arranged on the end face of the movable end, and two bolts both arranged on the steel The inner pipe on the inner side of the purlin (3), the two inner pipes are inserted into the outer pipe, the side walls of the two inner pipes are provided with first pin holes, and the side walls of the outer pipe are provided with two second pin holes. A pin hole, the plug (8) penetrates the first pin hole and the second pin hole. 7.根据权利要求6所述的基坑钢顶撑,其特征在于:还包括位于两个内管之间的千斤顶(9),所述千斤顶(9)的底部固定在钢围檩(3)的内侧,所述千斤顶(9)的顶部与活络端头的端面相接。7. The foundation pit steel top support according to claim 6, characterized in that: it also comprises a jack (9) positioned between two inner pipes, and the bottom of the jack (9) is fixed on the steel purlin (3) Inside, the top of the jack (9) is in contact with the end face of the flexible end. 8.根据权利要求6所述的基坑钢顶撑,其特征在于:还包括两个插销保护件(10),所述插销保护件(10)的一端固定在钢围檩(3)上,所述插销保护件(10)的另一端与外管的外壁相抵,所述插销保护件(10)均垂直于插销(8)的轴向。8. The foundation pit steel top support according to claim 6, characterized in that: further comprising two bolt protectors (10), one end of the bolt protectors (10) being fixed on the steel purlin (3), The other end of the plug protector (10) abuts against the outer wall of the outer tube, and the plug protectors (10) are all perpendicular to the axial direction of the plug (8). 9.根据权利要求1所述的基坑钢顶撑,其特征在于:还包括吊筋(11),所述吊筋(11)的一端固定在围护结构上,所述吊筋(11)的另一端与钢围檩(3)的上部连接。9. The foundation pit steel roof support according to claim 1, characterized in that: it further comprises a hanging bar (11), one end of the hanging bar (11) is fixed on the enclosure structure, and the hanging bar (11) The other end is connected with the upper part of the steel purlin (3).
CN201920461330.9U 2019-04-04 2019-04-04 A kind of foundation pit steel roof support Active CN210151752U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920461330.9U CN210151752U (en) 2019-04-04 2019-04-04 A kind of foundation pit steel roof support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920461330.9U CN210151752U (en) 2019-04-04 2019-04-04 A kind of foundation pit steel roof support

Publications (1)

Publication Number Publication Date
CN210151752U true CN210151752U (en) 2020-03-17

Family

ID=69756519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920461330.9U Active CN210151752U (en) 2019-04-04 2019-04-04 A kind of foundation pit steel roof support

Country Status (1)

Country Link
CN (1) CN210151752U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576437A (en) * 2020-05-07 2020-08-25 中国一冶集团有限公司 Foundation pit assembled type section steel supporting and protecting method
CN111779000A (en) * 2020-07-30 2020-10-16 中铁十局集团第四工程有限公司 A kind of quick disassembly foundation pit support structure and construction method
CN112030987A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Node structure of concrete-filled steel tube support and crown beam, construction method and support system
CN112030989A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Connection node of concrete-filled steel tubular support and crown beam, construction method and support system
CN112030988A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Assembled hollow steel tube concrete support system and construction method thereof
CN112030986A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Combined steel pipe concrete waist beam structure, prefabricated member, connecting joint and construction method
CN112302035A (en) * 2020-11-24 2021-02-02 中铁第四勘察设计院集团有限公司 Prefabricated hollow steel pipe concrete supporting member, inner supporting system and construction method
CN112302034A (en) * 2020-11-24 2021-02-02 中铁第四勘察设计院集团有限公司 Prefabricated hollow concrete supporting member, inner supporting system and construction method
CN112502160A (en) * 2020-11-24 2021-03-16 中铁第四勘察设计院集团有限公司 Post-tensioning precast concrete supporting member, inner supporting system and construction method
CN114016516A (en) * 2021-11-08 2022-02-08 贵州建工集团第一建筑工程有限责任公司 Concrete-steel structure mixed angle brace construction method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576437A (en) * 2020-05-07 2020-08-25 中国一冶集团有限公司 Foundation pit assembled type section steel supporting and protecting method
CN111779000A (en) * 2020-07-30 2020-10-16 中铁十局集团第四工程有限公司 A kind of quick disassembly foundation pit support structure and construction method
CN112030987A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Node structure of concrete-filled steel tube support and crown beam, construction method and support system
CN112030989A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Connection node of concrete-filled steel tubular support and crown beam, construction method and support system
CN112030988A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Assembled hollow steel tube concrete support system and construction method thereof
CN112030986A (en) * 2020-07-31 2020-12-04 中铁第四勘察设计院集团有限公司 Combined steel pipe concrete waist beam structure, prefabricated member, connecting joint and construction method
CN112302035A (en) * 2020-11-24 2021-02-02 中铁第四勘察设计院集团有限公司 Prefabricated hollow steel pipe concrete supporting member, inner supporting system and construction method
CN112302034A (en) * 2020-11-24 2021-02-02 中铁第四勘察设计院集团有限公司 Prefabricated hollow concrete supporting member, inner supporting system and construction method
CN112502160A (en) * 2020-11-24 2021-03-16 中铁第四勘察设计院集团有限公司 Post-tensioning precast concrete supporting member, inner supporting system and construction method
CN114016516A (en) * 2021-11-08 2022-02-08 贵州建工集团第一建筑工程有限责任公司 Concrete-steel structure mixed angle brace construction method

Similar Documents

Publication Publication Date Title
CN210151752U (en) A kind of foundation pit steel roof support
CN106884651A (en) A kind of slopes wall concrete bottom board prestress loading device
CN104763161A (en) Beam-adding reinforced structure of a reinforced concrete floor with an opening and construction method
CN210798276U (en) Open caisson pouring template convenient to disassemble and assemble
CN109322483B (en) Reinforcing and supporting structure of shear wall external formwork
CN217028931U (en) Steel pipe concrete support assembly
CN218521808U (en) Foundation pit supporting structure
CN110676791A (en) Assembled cable trench and construction method
CN217679165U (en) A assemble board-like strutting arrangement for municipal administration slot excavation
CN206538769U (en) Combined support system for foundation pit support structure
CN113136874B (en) A detachable concrete-filled steel tube foundation pit support system
CN209923940U (en) Foundation excavation collapse prevention supporting structure is built in room
CN212611998U (en) Strutting arrangement is used in municipal administration bridge construction
CN219671361U (en) Deep foundation pit supporting combined structure
CN221857802U (en) A pipeline rack device for tunnel construction
CN221221676U (en) Anti-backward device for pipe jacking construction
CN221480825U (en) Deep foundation pit supporting device convenient to assemble
CN216664107U (en) Combined pile for building foundation engineering
CN222207252U (en) Beam side template shaping and reinforcing device
CN114151092B (en) Tunnel expanding and excavating connecting device and tunnel expanding and excavating method
CN222949017U (en) River bed pipeline slot supporting construction
CN221920958U (en) Rectangular steel sleeve for rectangular pipe jacking construction
CN221941324U (en) A kind of soft soil foundation inflatable anchor
CN208268160U (en) A kind of external hanging type attachment device
CN217537000U (en) Anchor rope drilling bored concrete pile combination retaining structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant