[go: up one dir, main page]

CN209798057U - Hot galvanizing flue gas absorption device - Google Patents

Hot galvanizing flue gas absorption device Download PDF

Info

Publication number
CN209798057U
CN209798057U CN201822262148.9U CN201822262148U CN209798057U CN 209798057 U CN209798057 U CN 209798057U CN 201822262148 U CN201822262148 U CN 201822262148U CN 209798057 U CN209798057 U CN 209798057U
Authority
CN
China
Prior art keywords
cover
zinc
hot
hood
smoking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822262148.9U
Other languages
Chinese (zh)
Inventor
葛满全
丁志平
葛国全
葛知名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinghua Huacheng Galvanized Pipe Fittings Co Ltd
Original Assignee
Xinghua Huacheng Galvanized Pipe Fittings Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinghua Huacheng Galvanized Pipe Fittings Co Ltd filed Critical Xinghua Huacheng Galvanized Pipe Fittings Co Ltd
Priority to CN201822262148.9U priority Critical patent/CN209798057U/en
Application granted granted Critical
Publication of CN209798057U publication Critical patent/CN209798057U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Coating With Molten Metal (AREA)

Abstract

本实用新型提供一种热镀锌烟气吸收装置,包括支撑架、收集罩、操作窗、吸烟通道以及风机。支撑架安装在所述锌锅的周边,与锌锅之间为密闭连接;收集罩密闭地安装在支撑架上,收集罩为灯泡状,操作窗和吸烟通道均设置在收集罩上;风机的数量和吸烟通道的数量相同,风机一一对应地安装在吸烟通道上。采取锌烟收集罩,避免锌液飞溅,起到防护作用。收集罩为灯泡状,较窄的罩壁有利于锌烟被集中升至罩顶,较大的穹顶状罩顶有利于锌烟的聚集,方便顶部的吸烟通道集中吸收,并且将吸烟通道中的冷风较大程度的集中在罩顶处,减轻风机对锌锅中锌液温度的降低。

The utility model provides a hot-dip galvanized flue gas absorption device, which comprises a support frame, a collection cover, an operation window, a smoking channel and a fan. The support frame is installed on the periphery of the zinc pot, and is airtightly connected with the zinc pot; the collection cover is installed on the support frame in a sealed manner, and the collection cover is in the shape of a light bulb, and the operation window and the smoking channel are all arranged on the collection cover; The number is the same as the number of smoking passages, and the fans are installed on the smoking passages in a one-to-one correspondence. A zinc fume collection cover is used to avoid splashing of zinc liquid and play a protective role. The collection hood is in the shape of a light bulb. The narrower hood wall is conducive to the concentration of zinc fume to the top of the hood, and the larger dome-shaped hood is conducive to the accumulation of zinc fume, which is convenient for the concentrated absorption of the smoking channel on the top, and the smoke in the smoking channel The cold air is concentrated on the top of the hood to a large extent, which reduces the temperature reduction of the zinc liquid in the zinc pot by the fan.

Description

一种热镀锌烟气吸收装置A hot-dip galvanized smoke absorption device

技术领域technical field

本实用新型涉及热镀锌生产中产生的锌烟治理技术领域,尤其涉及一种热度子女烟气吸收装置。The utility model relates to the technical field of zinc fume treatment produced in hot-dip galvanizing production, in particular to a hot child smoke absorption device.

背景技术Background technique

热镀锌也称热浸镀锌,是钢铁构件浸入熔融的锌液中获得金属覆盖层的一种方法。近年来随高压输电、交通、通讯事业迅速发展,对钢铁件防护要求越来越高,热镀锌产品需求量也不断增加。锌锅正常运行时由于表面很快形成氧化层,烟气产生量较少。当工件浸入和提出锌锅的瞬间,由于搅动和工件上的助镀剂挥发,导致烟气大量增加。锌锅内工件进行热镀锌时产生大量烟雾,产生的原理说明如下:工件经过酸洗去锈后,工件再经溶剂氯化铵处理,再经过烘干之后,外表完全被氯化铵所包住。工件在进入镀锌锅的瞬间,由于高温作用,导致氯化铵迅速分解产生氯化铁、氯化锌、氧化锌、氯化铵等盐类及金属氧化物烟尘,其中以氯化铵为主,这些烟尘的粒径极为细小,在0.0l~1μm范围内。Hot-dip galvanizing, also known as hot-dip galvanizing, is a method in which steel components are immersed in molten zinc to obtain a metal coating. In recent years, with the rapid development of high-voltage power transmission, transportation, and communication, the protection requirements for steel parts are getting higher and higher, and the demand for hot-dip galvanized products is also increasing. When the zinc pot is in normal operation, due to the rapid formation of an oxide layer on the surface, the amount of smoke generated is less. When the workpiece is immersed in and lifted out of the zinc pot, due to the agitation and the volatilization of the flux on the workpiece, the smoke will increase significantly. A lot of smoke is produced when the workpiece in the zinc pot is hot-dip galvanized. The principle of the generation is as follows: After the workpiece is pickled to remove rust, the workpiece is treated with the solvent ammonium chloride, and after drying, the appearance is completely covered by ammonium chloride. live. When the workpiece enters the galvanizing pot, due to the high temperature, the ammonium chloride is rapidly decomposed to produce ferric chloride, zinc chloride, zinc oxide, ammonium chloride and other salts and metal oxide fumes, of which ammonium chloride is the main one. , the particle size of these soot is extremely fine, in the range of 0.0l ~ 1μm.

目前的热镀锌生产过程中产生的锌烟治理方式,主要是在锌锅上沿边侧安装吸风口(以下简称侧吸),将锌烟通过管道吸到除尘器进行除尘处理,达标排放。它主要存在以下缺点:The current treatment method for zinc fume produced in the hot-dip galvanizing production process is mainly to install a suction port on the side of the zinc pot (hereinafter referred to as side suction), and suck the zinc fume through the pipeline to the dust collector for dust removal treatment, and discharge up to the standard. It mainly has the following disadvantages:

1、侧吸方式对在锌锅边沿产生的锌烟有较强的吸收效果,经过除尘器除尘后可以做到达标排放,但对于锌锅中间产生的锌烟难以做到有效的吸收,特别是目前热镀锌行业追求产量,锌锅宽度在不断加宽的情况下,锌锅中间锌烟难以吸收,无组织排放严重,环保难以达标。1. The side suction method has a strong absorption effect on the zinc fume generated at the edge of the zinc pot. After dust removal by the dust collector, it can reach the standard discharge, but it is difficult to effectively absorb the zinc fume generated in the middle of the zinc pot, especially At present, the hot-dip galvanizing industry is pursuing output. When the width of the zinc pot is continuously widening, it is difficult to absorb the zinc fume in the middle of the zinc pot, the unorganized emission is serious, and it is difficult to meet the environmental protection standards.

2、侧吸方式在锌锅两边都安装吸风口,为保证吸收效果,一套侧吸需要配备两台大功率风机同时工作,做成了场地,用电的浪费。2. The side suction method installs suction ports on both sides of the zinc pot. In order to ensure the absorption effect, a set of side suction needs to be equipped with two high-power fans to work at the same time, which makes the site and wastes electricity.

3、侧吸方式在锌锅上沿边侧安装吸风口,距离锌液表面太近,一方面吸风加速锌液表面氧化,生成大量氧化锌,造成原料浪费,另一方面吸风的同时带走大量锌锅热量,造成热量流失,加大能源成本。3. The side suction method is to install the suction port along the side of the zinc pot, which is too close to the surface of the zinc liquid. On the one hand, the suction speeds up the surface oxidation of the zinc liquid, and a large amount of zinc oxide is generated, resulting in waste of raw materials. On the other hand, the air is sucked away at the same time. A large amount of zinc pot heat causes heat loss and increases energy costs.

实用新型内容Utility model content

本实用新型的目的是为了解决现有技术中存在的缺点,而提出的一种热镀锌烟气吸收装置。The purpose of the utility model is to solve the shortcomings in the prior art, and propose a hot-dip galvanizing smoke absorption device.

为实现上述目的,本实用新型采用了如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:

一种热镀锌烟气吸收装置,所述烟气吸收装置用以吸收锌锅加热时产生的锌烟,所述烟气吸收装置包括支撑架、收集罩、操作窗、吸烟通道以及风机;A hot-dip galvanizing smoke absorption device, the smoke absorption device is used to absorb zinc fume generated when the zinc pot is heated, and the smoke absorption device includes a support frame, a collection cover, an operation window, a smoking channel and a fan;

所述支撑架为可拆卸的组装式结构,所述支撑架安装在所述锌锅的周边并且与所述锌锅的顶面高度平齐,所述支撑架与所述锌锅之间为密闭连接;所述收集罩密闭地安装在所述支撑架上,所述收集罩为灯泡状,所述收集罩包括罩顶和罩壁,所述罩顶连接在所述罩壁的上方,所述罩顶的水平截面直径大于所述罩壁的水平截面直径;所述操作窗上下滑动或者左右滑动地安装在所述罩壁上,当所述操作窗关闭时,所述操作窗与所述收集罩之间密闭连接;所述吸烟通道的数量为至少2个且分布在所述罩顶上;所述风机的数量和所述吸烟通道的数量相同,所述风机一一对应地安装在所述吸烟通道上。The support frame is a detachable assembled structure, the support frame is installed on the periphery of the zinc pot and is at the same height as the top surface of the zinc pot, and the space between the support frame and the zinc pot is airtight connection; the collection cover is airtightly installed on the support frame, the collection cover is bulb-shaped, the collection cover includes a cover top and a cover wall, the cover top is connected above the cover wall, the The horizontal section diameter of the cover top is larger than the horizontal section diameter of the cover wall; the operation window is installed on the cover wall by sliding up and down or left and right, and when the operation window is closed, the operation window and the collecting The hoods are airtightly connected; the number of the smoking passages is at least 2 and distributed on the top of the hood; the number of the fans is the same as the number of the smoking passages, and the fans are installed one by one on the On the smoking aisle.

优选地,所述收集罩为一体成型结构。Preferably, the collection cover is an integrally formed structure.

优选地,所述罩顶和所述罩壁为可拆卸结构,所述罩顶和所述罩壁之间通过卡槽与卡固件相楔合,所述罩顶和所述罩壁的连接处涂有密封胶或者是安装有密封圈进行密封。Preferably, the hood top and the hood wall are detachable structures, the hood top and the hood wall are wedged with the fastener through a slot, and the connection between the hood top and the hood wall Coated with sealant or installed with a sealing ring for sealing.

优选地,所述操作窗为电控式操作窗。Preferably, the operation window is an electronically controlled operation window.

优选地,所述操作窗的高度范围为1.65-1.75米。Preferably, the height range of the operation window is 1.65-1.75 meters.

优选地,所述操作窗的底部与所述支撑架之间的距离不超过15厘米。Preferably, the distance between the bottom of the operation window and the support frame is no more than 15 cm.

优选地,所述吸烟通道为与所述罩顶密闭相连的软管。Preferably, the smoking channel is a flexible pipe airtightly connected to the hood.

优选地,所述吸烟通道可拆卸地安装在所述罩顶的外部。Preferably, the smoking channel is detachably installed on the outside of the hood.

优选地,所述风机为风速可调的变频风机。Preferably, the fan is a variable frequency fan with adjustable wind speed.

与现有技术相比,本实用新型的有益效果为:Compared with the prior art, the beneficial effects of the utility model are:

摒弃传统的露天侧吸方式,采取锌烟收集罩,降低了镀锌过程中产生的锌液飞溅造成的人身伤害和锌的浪费,起到防护作用。锌烟收集罩是全封闭在锌锅上的,在生产过程中产生的锌烟迅速上升,被收集罩顶上多个吸烟通道吸收,烟尘吸收效率效果大幅提升。此外,收集罩为灯泡状,较窄的罩壁有利于锌烟被集中升至罩顶,较大的穹顶状罩顶有利于锌烟的聚集,方便顶部的吸烟通道集中吸收,并且将吸烟通道中的冷风较大程度的集中在罩顶处,减轻风机对锌锅中锌液温度的降低。Abandoning the traditional open-air side suction method, adopting a zinc fume collection cover, which reduces the personal injury and zinc waste caused by the splash of zinc liquid generated during the galvanizing process, and plays a protective role. The zinc fume collection hood is fully enclosed on the zinc pot. The zinc fume generated during the production process rises rapidly and is absorbed by multiple smoking channels on the top of the collection hood, greatly improving the smoke absorption efficiency. In addition, the collection hood is bulb-shaped, and the narrower hood wall is conducive to the concentration of zinc fumes to the top of the hood. The larger dome-shaped hood is conducive to the accumulation of zinc fumes, which is convenient for the concentrated absorption of the smoking channel at the top, and the smoking channel The cold air in the tank is concentrated on the top of the hood to a large extent, which reduces the temperature reduction of the zinc liquid in the zinc pot by the fan.

附图说明Description of drawings

图1为一种热镀锌烟气吸收装置的示意图。Figure 1 is a schematic diagram of a hot-dip galvanizing smoke absorption device.

其中,1-支撑架,2-收集罩,21-罩顶,22-罩壁,3-操作窗,4-吸烟通道,5-风机。Among them, 1-support frame, 2-collecting hood, 21-hood top, 22-hood wall, 3-operation window, 4-smoking channel, 5-fan.

具体实施方式Detailed ways

为使对本实用新型的目的、构造、特征、及其功能有进一步的了解,兹配合实施例详细说明如下。In order to have a further understanding of the purpose, structure, features, and functions of the present utility model, the detailed description is as follows in conjunction with the embodiments.

请结合参照图1,本实用新型提供了一种热镀锌烟气吸收装置,烟气吸收装置用以吸收锌锅加热时产生的锌烟,烟气吸收装置包括支撑架1、收集罩2、操作窗3、吸烟通道4以及风机5。Please refer to Fig. 1, the utility model provides a hot-dip galvanizing flue gas absorption device, the flue gas absorption device is used to absorb the zinc fumes produced when the zinc pot is heated, the flue gas absorption device includes a support frame 1, a collection cover 2, Operation window 3, smoking channel 4 and blower fan 5.

支撑架1为可拆卸的组装式结构,支撑架1安装在锌锅的周边并且与锌锅的顶面高度平齐,支撑架1与锌锅之间为密闭连接;锌锅一般是固定在混凝土台中或是半地下坑中,支撑架1的高度可以根据实际情况调节,支撑架1将锌锅围起来,收集罩2密闭地安装在支撑架1上,收集罩2就可以将锌锅笼罩在内部,以防止镀锌过程中产生的锌液飞溅造成的人身伤害和锌的浪费,起到防护作用。收集罩2为灯泡状,收集罩2包括罩顶21和罩壁22,罩顶21连接在罩壁22的上方,罩顶21的水平截面直径大于罩壁22的水平截面直径;在使用时,锌锅内的锌液被加热,产生锌气向上挥发,较窄的罩壁22可以将锌气约束在一定范围内较为集中地被送至罩顶21处,罩顶21为穹顶状,并且体积较罩壁22更为开阔,便于缓存锌气,并且可以将风机5的冷风都局限在罩顶21中,不会对下方的温度产生较大的影响,一方面不会吸风加速锌液表面氧化,生成大量氧化锌,造成原料浪费,另一方面不会吸风的同时带走大量锌锅热量,造成热量流失,加大能源成本。操作窗3上下滑动或者左右滑动地安装在罩壁22上,当吸收锌气时,操作窗3关闭;当吸收锌气结束后,操作窗3打开,便于工人操作。当操作窗3关闭时,操作窗3与收集罩2之间密闭连接,防止吸收锌气时锌气从操作窗3处泄漏。吸烟通道4的数量为至少2个且分布在罩顶21上;风机5的数量和吸烟通道4的数量相同,风机5一一对应地安装在吸烟通道4上,从顶部抽取锌气,可以完全吸收所有的锌气,避免传统侧吸式因为锌锅面积过大而无法吸收中间锌气的尴尬。The support frame 1 is a detachable assembled structure. The support frame 1 is installed around the zinc pot and is at the same height as the top surface of the zinc pot. The support frame 1 and the zinc pot are airtightly connected; the zinc pot is generally fixed on the concrete In Taichung or semi-underground pits, the height of the support frame 1 can be adjusted according to the actual situation. The support frame 1 surrounds the zinc pot, and the collection cover 2 is installed on the support frame 1 airtightly. Inside, it plays a protective role to prevent personal injury and zinc waste caused by the splash of zinc liquid generated during the galvanizing process. Collection cover 2 is bulb-shaped, and collection cover 2 comprises cover top 21 and cover wall 22, and cover top 21 is connected on the top of cover wall 22, and the horizontal section diameter of cover top 21 is greater than the horizontal section diameter of cover wall 22; When in use, The zinc liquid in the zinc pot is heated to produce zinc gas that volatilizes upwards. The narrower cover wall 22 can confine the zinc gas within a certain range and send it to the cover top 21 in a concentrated manner. The cover top 21 is dome-shaped and has a volume It is more open than the cover wall 22, which is convenient for buffering zinc gas, and can confine the cold air of the fan 5 to the cover top 21, which will not have a great impact on the temperature below. Oxidation generates a large amount of zinc oxide, which causes waste of raw materials. On the other hand, it does not absorb a large amount of heat from the zinc pot at the same time, causing heat loss and increasing energy costs. The operation window 3 is installed on the cover wall 22 by sliding up and down or left and right. When the zinc gas is absorbed, the operation window 3 is closed; when the zinc gas absorption is finished, the operation window 3 is opened, which is convenient for workers to operate. When the operation window 3 is closed, the airtight connection between the operation window 3 and the collection cover 2 prevents zinc gas from leaking from the operation window 3 when zinc gas is absorbed. The quantity of smoking channel 4 is at least 2 and is distributed on the cover top 21; Absorb all the zinc gas, avoiding the embarrassment that the traditional side suction type cannot absorb the middle zinc gas because of the large area of the zinc pot.

在一实施例中,收集罩2为一体成型结构,密封效果好。在另一实施例中,罩顶21和罩壁22为可拆卸结构,罩顶21和罩壁22之间通过卡槽与卡固件相楔合,罩顶21和罩壁22的连接处涂有密封胶或者是安装有密封圈进行密封;这样在安装时可以分为两步安装,更加方便,并且清洗时也可以分成两部分清洗,由于收集罩2为灯泡状,罩顶21和罩壁22分开清洗更加方便。In one embodiment, the collecting cover 2 is integrally formed, and the sealing effect is good. In another embodiment, the cover top 21 and the cover wall 22 are detachable structures, and the slot between the cover top 21 and the cover wall 22 is wedged with the fastener, and the connection between the cover top 21 and the cover wall 22 is painted with Sealant or sealing ring is installed for sealing; it can be divided into two steps during installation, which is more convenient, and it can also be divided into two parts for cleaning during cleaning. Since the collection cover 2 is bulb-shaped, the cover top 21 and the cover wall 22 It is more convenient to wash separately.

优选地,操作窗3为电控式操作窗3,操作窗3可以由气缸或者是液压缸或者是电机提供动力,通过电路或是无线信号与控制端相连,可以更好地达到密封的效果。Preferably, the operation window 3 is an electronically controlled operation window 3, and the operation window 3 can be powered by a cylinder, a hydraulic cylinder, or a motor, and is connected to the control terminal through a circuit or a wireless signal, so as to achieve a better sealing effect.

优选地,操作窗3的高度范围为1.65-1.75米,便于工人操作。Preferably, the height range of the operation window 3 is 1.65-1.75 meters, which is convenient for workers to operate.

优选地,操作窗3的底部与支撑架1之间的距离不超过15厘米,既能够让操作窗3与支撑架1之间保留一定的距离,防止操作窗3开关出现问题,又不会影响工人进出操作。Preferably, the distance between the bottom of the operation window 3 and the support frame 1 is no more than 15 centimeters, which can keep a certain distance between the operation window 3 and the support frame 1 to prevent problems with the switch of the operation window 3 without affecting Workers enter and exit operations.

优选地,吸烟通道4为与罩顶21密闭相连的软管,即吸烟通道4的方向可以随意变化,即可以随时调整吸烟通道4中的风向。Preferably, the smoking channel 4 is a hose airtightly connected to the hood 21, that is, the direction of the smoking channel 4 can be changed at will, that is, the wind direction in the smoking channel 4 can be adjusted at any time.

优选地,吸烟通道4可拆卸地安装在罩顶21的外部,不伸入到收集罩2内部,不会对锌气的吸收产生妨碍。Preferably, the smoking channel 4 is detachably mounted on the outside of the hood top 21, and does not protrude into the collection hood 2, so as not to hinder the absorption of zinc gas.

优选地,风机5为风速可调的变频风机5,可以改变用于抽取锌气的风速大小。Preferably, the fan 5 is a variable frequency fan 5 with adjustable wind speed, which can change the wind speed for extracting zinc gas.

由上所述,本实用新型摒弃传统的露天侧吸方式,采取锌烟收集罩,降低了镀锌过程中产生的锌液飞溅造成的人身伤害和锌的浪费,起到防护作用。锌烟收集罩是全封闭在锌锅上的,在生产过程中产生的锌烟迅速上升,被收集罩顶多个吸烟通道吸收,烟尘吸收效率效果大幅提升。此外,收集罩为灯泡状,较窄的罩壁有利于锌烟被集中升至罩顶,较大的穹顶状罩顶有利于锌烟的聚集,方便顶部的吸烟通道集中吸收,并且将吸烟通道中的冷风较大程度的集中在罩顶处,减轻风机对锌锅中锌液温度的降低。From the above, the utility model abandons the traditional open-air side suction method and adopts a zinc fume collection cover, which reduces the personal injury and zinc waste caused by the splash of zinc liquid generated during the galvanizing process, and plays a protective role. The zinc fume collection hood is fully enclosed on the zinc pot. The zinc fume generated during the production process rises rapidly and is absorbed by multiple smoking channels on the top of the collection hood, greatly improving the smoke absorption efficiency. In addition, the collection hood is bulb-shaped, and the narrower hood wall is conducive to the concentration of zinc fumes to the top of the hood. The larger dome-shaped hood is conducive to the accumulation of zinc fumes, which is convenient for the concentrated absorption of the smoking channel at the top, and the smoking channel The cold air in the tank is concentrated on the top of the hood to a large extent, which reduces the temperature reduction of the zinc liquid in the zinc pot by the fan.

本实用新型已由上述相关实施例加以描述,然而上述实施例仅为实施本实用新型的范例。必需指出的是,已揭露的实施例并未限制本实用新型的范围。相反地,在不脱离本实用新型的精神和范围内所作的更动与润饰,均属本实用新型的专利保护范围。The utility model has been described by the above-mentioned relevant embodiments, but the above-mentioned embodiments are only examples for implementing the utility model. It must be pointed out that the disclosed embodiments do not limit the scope of the present invention. On the contrary, changes and modifications made without departing from the spirit and scope of the utility model all belong to the patent protection scope of the utility model.

Claims (9)

1.一种热镀锌烟气吸收装置,所述烟气吸收装置用以吸收锌锅加热时产生的锌烟,其特征在于:所述烟气吸收装置包括支撑架、收集罩、操作窗、吸烟通道以及风机;1. A hot-dip galvanizing flue gas absorbing device, said flue gas absorbing device is used to absorb the zinc smoke produced when the zinc pot is heated, it is characterized in that: said flue gas absorbing device comprises support frame, collection cover, operating window, Smoking channels and fans; 所述支撑架为可拆卸的组装式结构,所述支撑架安装在所述锌锅的周边并且与所述锌锅的顶面高度平齐,所述支撑架与所述锌锅之间为密闭连接;所述收集罩密闭地安装在所述支撑架上,所述收集罩为灯泡状,所述收集罩包括罩顶和罩壁,所述罩顶连接在所述罩壁的上方,所述罩顶的水平截面直径大于所述罩壁的水平截面直径;所述操作窗上下滑动或者左右滑动地安装在所述罩壁上,当所述操作窗关闭时,所述操作窗与所述收集罩之间密闭连接;所述吸烟通道的数量为至少2个且分布在所述罩顶上;所述风机的数量和所述吸烟通道的数量相同,所述风机一一对应地安装在所述吸烟通道上。The support frame is a detachable assembled structure, the support frame is installed on the periphery of the zinc pot and is at the same height as the top surface of the zinc pot, and the space between the support frame and the zinc pot is airtight connection; the collection cover is airtightly installed on the support frame, the collection cover is bulb-shaped, the collection cover includes a cover top and a cover wall, the cover top is connected above the cover wall, the The horizontal section diameter of the cover top is larger than the horizontal section diameter of the cover wall; the operation window is installed on the cover wall by sliding up and down or left and right, and when the operation window is closed, the operation window and the collecting The hoods are airtightly connected; the number of the smoking passages is at least 2 and distributed on the top of the hood; the number of the fans is the same as the number of the smoking passages, and the fans are installed one by one on the On the smoking aisle. 2.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述收集罩为一体成型结构。2. The hot-dip galvanized fume absorption device according to claim 1, characterized in that: the collection cover is integrally formed. 3.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述罩顶和所述罩壁为可拆卸结构,所述罩顶和所述罩壁之间通过卡槽与卡固件相楔合,所述罩顶和所述罩壁的连接处涂有密封胶或者是安装有密封圈进行密封。3. The hot-dip galvanized fume absorbing device according to claim 1, characterized in that: the cover top and the cover wall are detachable structures, and the cover top and the cover wall are connected with each other through a card slot. The clips are wedged together, and the joint between the cover top and the cover wall is coated with sealant or installed with a sealing ring for sealing. 4.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述操作窗为电控式操作窗。4. The hot-dip galvanizing fume absorption device according to claim 1, characterized in that: the operation window is an electronically controlled operation window. 5.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述操作窗的高度范围为1.65-1.75米。5. The hot-dip galvanizing fume absorption device according to claim 1, characterized in that: the height range of the operation window is 1.65-1.75 meters. 6.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述操作窗的底部与所述支撑架之间的距离不超过15厘米。6. The hot-dip galvanizing fume absorption device according to claim 1, characterized in that: the distance between the bottom of the operation window and the support frame is no more than 15 cm. 7.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述吸烟通道为与所述罩顶密闭相连的软管。7. The hot-dip galvanizing fume absorbing device according to claim 1, characterized in that: the smoking channel is a hose that is airtightly connected to the hood. 8.如权利要求7所述的热镀锌烟气吸收装置,其特征在于:所述吸烟通道可拆卸地安装在所述罩顶的外部。8. The hot-dip galvanizing fume absorbing device according to claim 7, characterized in that: the smoking channel is detachably installed on the outside of the hood. 9.如权利要求1所述的热镀锌烟气吸收装置,其特征在于:所述风机为风速可调的变频风机。9. The hot-dip galvanizing fume absorption device according to claim 1, characterized in that: the fan is a variable frequency fan with adjustable wind speed.
CN201822262148.9U 2018-12-30 2018-12-30 Hot galvanizing flue gas absorption device Expired - Fee Related CN209798057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822262148.9U CN209798057U (en) 2018-12-30 2018-12-30 Hot galvanizing flue gas absorption device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822262148.9U CN209798057U (en) 2018-12-30 2018-12-30 Hot galvanizing flue gas absorption device

Publications (1)

Publication Number Publication Date
CN209798057U true CN209798057U (en) 2019-12-17

Family

ID=68819186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822262148.9U Expired - Fee Related CN209798057U (en) 2018-12-30 2018-12-30 Hot galvanizing flue gas absorption device

Country Status (1)

Country Link
CN (1) CN209798057U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114918217A (en) * 2022-05-25 2022-08-19 烟台市福源金属表面工程有限公司 Hot-galvanize air curtain side-draft zinc smoke environment-friendly device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114918217A (en) * 2022-05-25 2022-08-19 烟台市福源金属表面工程有限公司 Hot-galvanize air curtain side-draft zinc smoke environment-friendly device

Similar Documents

Publication Publication Date Title
WO2022022418A1 (en) Integrated factory building air purification device having telescopic air suction and supply structures
CN110819758A (en) Combined converter tertiary dust collection device and converter steelmaking system
CN202316213U (en) Mobile passing-type polishing and painting device
CN209798057U (en) Hot galvanizing flue gas absorption device
CN203215787U (en) Integrated cooking stove
CN214572181U (en) Water-saving galvanizing pool
CN208219376U (en) A kind of energy saving and environment friendly construction of the highway concrete power saw
CN211367623U (en) Combined converter tertiary dust collecting device and converter steelmaking system
CN206229113U (en) A kind of water curtain dust pelletizing system
CN204503726U (en) The galvanizing device for eliminating smoke and dust that a kind of pressure-vaccum combines
CN203657516U (en) Integrated smoke flow guiding and gathering equipment of smelting furnace
CN201686735U (en) Double-suction exhaust gas collection device on batch hot-dip galvanizing pool
CN202030779U (en) Fume colleting shield for tilting trough of shaft furnace
CN104550177A (en) Blowing and suction combined hot galvanizing smoke prevention and dust removal device
CN210394480U (en) Intermediate frequency furnace smelting production line with dust removal function
CN209798056U (en) Mobile hot-dip galvanized fume absorption hood
CN204195113U (en) A kind of smoke removing device for weld job
CN208536087U (en) A kind of smoke withdrawing cover for kitchen use that wind-force layout is adjusted
CN208082775U (en) A kind of movable type paint spray booth
CN103981325A (en) Novel sucking-and-blowing type secondary flue gas gathering apparatus for converter
CN220061882U (en) A solar wall heating device
CN210937576U (en) Metallization film capacitor brazing movable local exhaust device
CN217383056U (en) A high-efficiency trapping device for oil fume heat plume based on the shielding effect of high-speed jet
CN205425864U (en) A jar flue gas collecting cover is rolled over to portable molten iron
CN222205286U (en) A new type of environmentally friendly hot-splashing treatment device for converter slag

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191217